VALUATION FOR WORKS AT NAMUGONGO FOYER SITE

Original Boq

ITEM

DESCRIPTION

UNIT QTY

BILL NO. 2
PRELIMINARIES
Sufficiency of Tender
The Contractor shall be deemed to have satisfied himself
before tendering as to the correctness and sufficiency of his
Tender for the Works and of the rates and prices stated in
the priced Bills of Quantities which rates and prices shall
cover all his obligations under the contract and all matters
and things necessary for the proper completion and
maintenance of the works.
Definition of terms and abbreviations
The Terms and Abbreviations and used in this Bills of
quantities shall be interpreted as follows:"BS"
Shall mean The current British Standard of
Specification published by the British standards Institution,
Park Street, London, W.l England
"NO"
Shall mean Number
"LM"
Shall mean Linear metres
"M"
Shall mean Linear meters
"SM"
Shall mean Square meters
"CM"
Shall mean Cubic Meters
"DITTO"
Shall mean The whole of the preceding
description except as qualified in the section in which it
occurs. Where it occurs in brackets, it shall mean the whole
of the preceding description which is contained within the
appropriate
""MS"
Shall mean Measured separately.
Carried to Summary USHS
1

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

Bill No.2 (ctd)


Definition of terms and abbreviation (ctd)
"B.S.M"
Shall mean Both sides measured.
"P.C"
Shall mean Prime Cost
""75mm to 150mm" Shall mean Exceeding 75mm but not
exceeding 150mm in girth, and all items described in this
manner shall be similarly construed .
"A small pipe" Shall mean Any pipe not exceeding 55mm
internal diameter.
"Alarge pipe" Shall mean Any pipe not exceeding 55mm and
not exceeding 110mm internal diameter.
"An extra large pipe Shall mean Any pipe exceeding 110mm
internal diameter.
Access to site and temporary roads.
Means of access to the Site shall be agreed with the Architect
prior to tne commencement of the Works and the Contractor
must allow for building any temporary access road s for the
transport of materials, plant and workmen as may be
required for the complete execution of the Works. including
the provision of temporary culverts, crossings, bridges means
of gaining access.
Upon the completion of the Works, the Contractor shall
remove such temporary roads, culverts, bridges, etc. and
make good and reinstate all works disturbed to the
satisfaction of the architect.

Carried to Summary USHS


2

5,000,000

3,000,000

5,000,000

3,000,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
UNIT QTY
Area to be occupied by the Contractor
The area of the site which may be occupied by the Contractor
for. use as storage and for the purpose of erecting
workshops, etc. shall be defined on the site by the Architect.

Bill No.2 (ctd)


Setting Out
The Contactor shall set out the Works in accordance with the
dimension" and levels "shown "on the Drawings and shall be
responsible for the correctness of all dimensions and levels
so set out by him and will be required to amend all errors
arising from inaccurate setting out at his own cost and
expense. In the event of any error or discrepancy in the
dimensions or levels marked on the Drawings being
discovered, such errors or discrepancies shall be reported by
the Contactor to the Architect for his immediate attention.

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

700,000

700,000

700,000

700,000

No Work shall be commenced by the Contractor until he has


received written instruction from the Architect to adjust such
cliscrepancies which may be proved. Upon receipt of such
instructions, the Contactor shall thereupon be responsible
for accurate setting out of the Works, giving effect to the
adjustments necessary to comply with such instructions,and
no claim for extra expense or relief from the provision of
Clause 5 of the Conditions of Contract based on any
discrepancy or error in the dimensions or levels shown on the
Drawings may be made thereafter.
Carried to Summary USHS
3

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Existing Services
Before any Work is commenced by the Sub-Contractors or
Specialized Firms, dimensions must be checked on the Site
and / or buildings and agreed with the Contactor,
irrespective of the comparative dimensions shown on the.
Drawings. The Contractor shall be responsible for the
accuracy of such dimensions.
Prior to the commencement of any Work, the Contractor is
to
ascertain from the relevant Authorities the exact position,
depth and levels of all existing electric cables, water pipes or
other services in the area and he shall make whatever
provisions may be required by the Authorities concerned for
the support and protection of such services. Any damage or
disturbance caused to any service shall be reported
immediately to the Architect and the relevant Authority and
shall be made good to their satisfaction at the Contactors
expense.
Transport to and from the Site
The Contractor shall include in his prices for the transport of
materials workmen, etc., to and from the Site of the
proposed Works,
at such hours and such routes as are permitted by the
Authorities

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

Public and private roads, pavements etc.


The Contractor will be required to make good, at his own
expense,
any damage 'he may cause to the present 'road surfaces and
pavements during the period of the Works. In particular all
the
existing lawns, gardens, storm water channels, hedges,
fences etc.,
which may be destroyed or damaged during the progress of
the
Works are to be made good by the Contractor to the
approval of the
Architect.
Security of the Works
The Contractor shall be entirely responsible for the security
of all the Works, stores, materials, plant, personnel, etc.,
both of his own and Sub-Contractors', and shall provide all
necessary watching, lighting and other precautions as
necessary as to ensure the security and the
protection of the public.

Carried to Summary USHS


5

3,000,000

1,000,000

3,000,000

1,000,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Water for the Works


The. Contractor shall allow for providing all temporary water
supplies
;required for the works, including Sub-Contract Works,
together with "all necessary storage tanks and distribution
systems for the same 'and must allow for bearing all
expenses incurred and paying for .all water consumed
without charge to any Sub-Contractor. Expenses in
connection with Nominated Sub-Contractors should be
allowed for in the attendance items under the relevant P.c.
Sums.
No guarantee or warranty is given as to the availability or
suitability
of water at the site.

Carried to Summary USHS


6

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

1,000,000

1,000,000

1,000,000

800,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
Electric Light and Power
The Contractor shall allow for providing all temporary
lighting and
power supplies required for the works, including SubContract
works, together with all.necessary distribution systems for
the same
and must allow for bearing all expenses incurred and paying
for all
current consumed without charge to any Sub-Contractor.
Expenses
in connection with Nominated Sub-Contractors should be
allowed for
in the attendance items under the relevant P.c. Sums.
No guarantee or warranty is given as to the availability or
suitability
of power at the site.

UNIT QTY

Carried to Summary USHS


7

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

1,000,000

1,000,000

1,000,000

1,000,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

Telephone
The Contractor shall arrange for, provide and maintain a
telephone
on the Site from the commencement to the completion of
the
Contract and shall pay all charges in connection therewith.
Temporary Buildings for use by the Contractor
The Contractor shall at his own cost, supply and erect all
temporary
buildings, sheds, mess rooms and stores with floors at least
l50mm
above ground level. No office, stores or other temporary
buildings
shall be erected on Site without first obtaining the consent
from the
Architect as to the type of temporary building to be supplied
and the
position in which they are to be erected.
Sheds for Storage of Materials
The Contractor shall provide and maintain on the Site, ample
weatherproof sheds for storage of cement and other
perishable
materials and shall clear the same away on completion and
make
good any disturbed surfaces.

Carried to Summary USHS


8

500,000

500,000

7,000,000

7,000,000

7,500,000

7,500,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
UNIT QTY
Offices for the Consultants
(i) The Contractor shall provide, erect and maintain where
directed on Site approved weatherproof lockup office for the
sole use of the Consultants with a floor area not less than 14
square metres. The office shall be constructed with concrete
or wooded floor and the walls and ceiling internally are to be
lined with fibreboard. Glazed windows shall be provided of
not less than 1 metre square area and the door shall have a
strong lock or fastening. The office shall be provided with
artificial lighting and electric power. The office is to be
furnished with a table of sufficient size to carry the drawings,
complete with drawers, and also stools and chairs. The table
should be adequate to sit at least 8 (Eight) people. The
contractor shall allow for regular cleaning of the office..
(ii) The Contractor shall keep on the Site and maintain in
good condition, one dumpy or quickset level and leveling
staff and one 30 metres steel/linen tape for the use of the
Consultants. The Contractor shall also provide stationery for
use by the consultants.

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Bill No.2 (ctd)


Office for the Consultants (ctd)
(iii)He .shall provide, erect and maintain a lockup pedestal
type water or bucket closet for the sole use of the
Consultants including making temporary connection to drain
where applicable to the satisfaction of the Government and
Medical officers of Health and shall provide the services of a
cleaner and pay all conservancy charges and keep both office
and closet clean and in sanitary condition from the
commencement to the completion of the Works and
dismantle and make good disturbed surfaces to the
satisfaction of the Architect on completion of the Works.
(iv)The office and the closet shall be completed before the
Contractor is permitted to commence the Works.
permitted to commence the Works.

10

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
UNIT QTY
Office for the Clerk of Works
The Contractor shall provide, erect and maintain where
directed on site an approved weatherproof office for the sole
use of the Clerk of Works. The office shall be not less than 10
square meters and shall be of construction similar to the
office of the consultants. The office shall be furnished with 1
No. desk with lockable drawers, 1 No. AO Size drawing chest
with four drawers, 1 No. lockable metal filing cabinet. The
office shall also have all power and lighting points as
necessary. The contractor shall allow for regular cleaning of
the
office.

11

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Signboard
The, contractor shall provide and erect where directed and
maintain during the whole period of building operations and
remove at completion, an approved temporary signboards to
the Architect's standard design and giving the title of the
Works and showing the names of the Employer, Architect,
Quantity Surveyor, Engineers and the Contractor with
sufficient space to add the names of the
Nominated Sub Contractors and suppliers. The lettering
concerning the Architect, Quantity Surveyor and the
Engineer is not to be more than 75mm high

RATE

Measured Quantities

AMOUNT

800,000

QTY

AMOUNT

Sanitation of the Works


Sanitation of the Works shall be arranged and maintained by
the Contractor to the satisfaction of the Government and
local authorities, labour department and the architect.

Carried to Summary USHS


12

1,500,000

400,000

2,300,000

400,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

Bill No.2 (ctd)


Materials, Tools, Plant and Scaffolding
All materials and workmanship used in the execution of the
Works shall be of the best quality and description unless
otherwise described. Any materials for the Works
condemned by the Architect shall immediately be removed
from the Site at the Contractor's expense .
The Contractor shall be responsible for the provision of all
materials, scaffolding, tools, plants, transport and workmen
required for the Works except insofar as may be stated
otherwise herein and he shall allow for the provision of the
foregoing except for such items specifically and only required
for the use of the Nominated Sub- Contractors as described
herein.
No timber used for scaffolding, form work or similar purpose
shall be used afterwards in the permanent Works.
All such plant, tools and scaffolding shall comply with all
regulations whether general or local in force throughout the
period of the Contract and shall be altered or adapted during
the Contract as may be necessary to comply with any
amendments in / or additions to
such regulations.

Carried to Summary USHS


13

8,000,000

6,000,000

8,000,000

6,000,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
Supervision and Working Hours
The said Works shall be executed under the direction and to
the
entire satisfaction of the Architect ,who shall at all times
during normal working hours have access to the works and
the yards and the workshops of the contractor and subcontractor or other places where work is being prepared for
the Contract
The working hours shall be those generally worked by good
employers in the Building and Civil Engineering Trade in
Uganda. No
work shall be carried out at night or on gazetted holidays
unless the
Architect shall so direct
No work shall be covered up nor shall any concreting be
carried out
in the absence of the Clerk of Works without the prior
approval of the
Architect in writing .

UNIT QTY

14

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Fair Wages
The Contractor shall pay rates of wages and observe hours
and
conditions of labour not less favourable than the minimum
ratesof
remuneration and minimum conditions of employment
applicable in
the district in which the works is carried out. The relevant
notice
must be posted up and kept posted upon the Site where it
can
conveniently be read by the employees concerned
Training Levy
The Contractor's attention is called to the requirement for
payment
by the Contractor of a training Levy and the Contractor
should allow
in the Preliminaries of this Contract for all costs arising or
resulting
there from.

15

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Labour
No labour with the exception of the watchman, may be
housed on the
Site and the Contractor shall allow for all transport and other
charges in moving labour to and from the Site at such hours
and
such routes as are permitted by the Authorities. The
Contractor is to
provide, erect and maintain satisfactory housing for the
watchmen
and shall remove the same on completion of the Works
Existing Property
The Contractor shall take every precaution to avoid damage
to all existing property including roads, cables, drains and
other services and he will be held responsible for all damage
thereto, arising from , the execution of this Contract, and he
shall make good such damages when directed at his own
expense.
Protection of the Works.
The Contractor shall cover up and protect all finished works
liable to damage including provision of temporary roofs,
gutters, drains, etc. until the completion of the Works.

16

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
In the event of any damage occurring to the Works,
materials,
sewers, drains, gullies, paths or other Works on the Site
temporarily in the possession of the Contractor, for the
purpose of this Contract, either from the weather, want of
proper protection, defects or insufficiency of the Works, the
Contractor
alone shall be responsible and shall without extra charges,
make good all damages arid pay' all costs which may be
levied

UNIT QTY

Standard Measurements
All dimensions and measurements, etc., shown on the
Drawings and given in this Bills of Quantities shall be metric.
Bills of quantities
The Method of Measurements herein used must be accepted
and will be strictly adhered to for the adjustments of
variations or for remeasurements as necessary. The whole of
the quantities in these Bills, unless expressly otherwise
stated, have been arrived at by taking the net measurements
of various items of completed Works from the Drawings
All the works in this Contract that is liable to adjustment has
been measured as "Provisional" ill these Bills of Quantities,
and no excavation or foundation work or other works so
described shall be filled in or covered up until all
measurement needed for the Adjustments of Variations
under clause 11 of the Conditions of Contract have been
made by the Quantity Surveyor.

17

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
UNIT QTY
The rates set out by the Contractor against each item shall,
unless otherwise expressly provided to the contrary, or
unless there is a separate item for extra labour, cutting or
waste, be held to include for waste on materials, carriage
and cartage, carrying in and return of, : empties, ~J.vis-u.ng,
setting.Titting and fixing in position, making good and all
other labours and everything else necessary for the
completion of each item and for establishment charges and
profit
Throughout the Bills of Quantities generally, no mention
is.rnade of heights for hoisting and. all prices must include
for hoisting and fixing at any level within the limit shown on
the Drawings or included in the general description unless a
specific level is stated.
The Contractor shall be deemed to have made allowance in
his rates
generally to cover items of Preliminaries expenses in
conriection With
P.C Sums or other items if these have not been priced against
the
respective items.
These Bills of Quantities have been prepared in the
elemental form
and each element contains work in various trades. For the
purpose of pricing, the Bills of Quantities may be taken apart
and each trade collected together but when the Tender is
submitted the Bills of Quantities must be re-assembled in the
correct order

18

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Copyright
The copyright of these Bills of Quantities is vested in the
Quantity
Surveyor and they may not be reproduced in whole or in part
without
the Quantity Surveyor's written permission
Prime Cost (P.C)Items
(i)The words "Prime Cost" (or the initials "P.C")wherever
appearing in
these. Bills of Quantities, shall mean net cost exclusive of any
trade, cash or other discounts whatsoever but inclusive of
the
cost of packing, carriage and delivery. Such costs shall be the
sums due to the Sub-Contractor or suppliers after
adjustment
where applicable in respect of measurements or rates.

(ii) Any increases or decreases in these Prime Cost Sums


resulting from the adjustments and properly paid by the
Contractor, shall be added to or deducted from the Contract
Sum in the final account. In subetanriation, the Contractor is
required to produce to the Quantity , Surveyor, all
quotations, invoices and receipted accounts as shall be
necessary to show the details of the sums actually paid.

19

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
UNIT QTY
(ill)Any sums added by the Contractor in these Bills of
Quantities in respect of profit upon any Prime Cost Sums will
be deducted in the final settlement of accounts and a sum
will be added, the amount of which will bear the same the
proportion to the sum added as the net
amount properly expended bears to the original P.C. Sum.

RATE

Measured Quantities

AMOUNT

Samples
The 'Contractor shall furnish at the earliest possible
opportunity
before work commences at his own cost, any samples of
materials of
workmanship that may be called for by the Architect for his
approval
or rejection and any further samples in the case of rejection
until
such samples are approved by the Architect and such
samples when
approved shall be the minimum standard for the work to
which they
apply.

700,000

Carried to Summary USHS

700,000
20

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

Proprietary articles
Where proprietary articles are specified herein, the
Contractor may propose the use of materials of' equal quality
but from other manufacturers with the approval of the
Architect, but the decision of the Architect-will be [mal

Protection
Cover up and protect from damage, including damage from
inclement
weather, all finished work and unfixed materials including
that of the Sub-Contractor, etc., to' the satisfaction of the
Architect until the completion of the Contract and make
good any damage which occurs. Carefully preserve all trees
or bushes on or near the site.

Removal of Plant. Rubbish. Etc


The Contractor shall, upon completion of the Works, remove
and clear away temporary buildings, plant, rubbish and
unused material shall leave the whole of the Site of the
Works in a dean and tidy state to the satisfaction of the
Architect. He shall also remove all rubbish and dirt from the
Site at weekly intervals or as directed by the Architect
1,500,000
Particular care shall be taken in leaving windows dean and
removal
of all paint and cement stains there from

1,500,000

Carried to Main Summary USHS


21

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Prevention of Nuisance
The Works and such sections of the Site necessary therefore
shall be
under the entire care and control of the Contractor during
the whole
period of the Contract and he shall take all possible
precautions to
prevent any nuisance,(ct
Inconvenience or injury to the holders or occupiers of the
existing or
surrounding properties and to the public generally, and shall
at all
times .keep all the paths and roads affected by the Works in
a safe
and dear state and shall use properprecautions to ensure the
safety
of all wheeled traffic and pedestrians.
Visitors to the Site
The Contractor is required to control all Visitors to the Site
and to
keep out unauthorized visitors and to provide a visitors book
and
ensure that all the unauthorized visitors sign therein.

22

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

Firm Price Contract


The fluctuation Clause 32, (3),(A),(B)is deleted from the
Contract.
- This is a firm price Contract and the Contractor must allow
in
his rates for any increase in the prices of labour and/ or
'materials which may occur after submission of the Tender.

Programme & progress.


If required by the Architect, this chart shall be generated and
updated
by an approved computer program.
Approval by the Architect of the programme shall not relieve
the Contractor of any of his' obligations under this Contract
The Contractor shall not without the Architect's consent
make any material alteration to the approved programme.
If the Architect decides that progress does not match the
programme,
he may order the Contractor to revise the programme. The
Contractor shall thereafter revise the programme to show
the
modifications necessary.

23

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

PRELIMINARIES
SUMMARY
Page NO. 2
Page NO. 3
Page NO. 5
Page NO. 6
Page NO. 7
Page NO. 8
Page NO. 12
Page NO. 13
Page NO. 20
Page NO. 21

TOTAL AMOUNT FOR BILL NO.2


PRELIMINARIES
Carried to Main Summary USHS
24

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

5,000,000
700,000
3,000,000
1,000,000
1,000,000
7,500,000
2,300,000
8,000,000
700,000
1,500,000

3,000,000
700,000
1,000,000
800,000
1,000,000
7,500,000
400,000
6,000,000
-

30,700,000

20,400,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

SUBSTRUCTURE
ALL PROVISIONAL
Earthworks
Excavate to remove vegetable soil average150mm deep and
dispose

sm

1098

500

549,000

1890

945,000

cm

382

6,000

2,292,000

575

3,450,000

cm

134

7,000

938,000

224

1,568,000

Allow for keeping excavation free from water

item

50,000

50,000

50,000

Allow for supporting sides of excavations

item

100,000

100,000

100,000

Return, fill and ram selected excavated materials around


foundations

cm

274

5,000

1,370,000

641

3,205,000

Remove extra excavated material away from site

cm

242

6,500

1,573,000

Imported filling
Murram filling compacted around foundations

cm

716

15,000

10,740,000

Excavate foundation trench not exceeding 1.5metres deep

Ditto but pit for column bases starting from stripped level
not exceeding 1.5m deep

880

Hardcore
200mm Hardcore compacted and blinded to receive concrete
sm

716

70,000

50,120,000
67,732,000

Total Carried to Collection below

25

13,200,000
-

1095

76,650,000
99,168,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
Anti-termite treatment 'Dieldex' or other approved antrepellant applied as per Manufacturer's instructions
Treatment to bottoms and sides of excavation

UNIT QTY

sm

907

RATE

Measured Quantities

AMOUNT

QTY

2,000

1,814,000

AMOUNT

1517

3,034,000

354

4,071,000

Plain concrete Grade 10


50mm Blinding under wall foundations

sm

306

11,500

3,519,000

Ditto under column bases

sm

87

11,500

1,000,500

170

1,955,000

Reinforced concrete Grade 20


100mm Ground floor slab

sm

907

34,000

30,838,000

1095

37,230,000

Concrete apron 2250mm wide comporising


100mm thick hardcore bed on 100mm thick
murram bed'75 x 200mm concrete edge
upstand, fabric mesh and 25mm thick
screed

sm

110

50,000

5,500,000

12

4,800,000

Reinforced concrete Grade 25


Stub column

cm

400,000

1,200,000

column bases

cm

48

400,000

19,200,000

51

20,400,000

Strip foundation concrete

cm

61

400,000

24,400,000

148

59,200,000

Ground beam

cm

23

400,000

9,200,000

2,000,000

96,671,500

Total Carried to Collection below


26

132,690,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

Steel fabric reinforcement


142 steel fabric reinforcement laid with 200mm laps

sm

907

17,500

15,872,500

1095

19,162,500

Mild sfeel reinforcement bars to B.S.4449


8mm Bars

kg

8225

4,000

32,900,000

8225

32,900,000

12mm Bars

kg

1127

4,000

4,508,000

1127

4,508,000

16mm Ditto

kg

3719

4,000

14,876,000

3719

14,876,000

117

1,755,000

Formwork to:
Sides of stub column

sm

58

15,000

870,000

Sides of column bases

sm

159

15,000

2,385,000

304

4,560,000

Sides of Ground Beams

sm

179

15,000

2,685,000

40

600,000

Edge of Ground floor slab 100mm wide

lm

180

2,250

405,000

179

402,750

Solid concrete blockwork built in cement


: mortar (1:4), 230mm plinth walling

sm

508

50,000

25,400,000

930

46,500,000

99,901,500

Total Carried to Collection below


27

106,101,750

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
Surface drain channel :Damp proof membrane
1000 Gaugepolythene dampproof
membrane laid with 200 mm side and end
laps
Hessian based bituminous damp proof
course under:
230mm Ditto

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY
-

sm

907

3,000

2,721,000

lm

447

3,000

1,341,000
-

1095

sm

69

7,500

517,500

930

Prepare and apply two. coats bituminous paint to:


Rendered plinth walls

3,285,000

Cement and sand (J :4) in:


Rendering to plinth walls

AMOUNT

sm

69

7,000

483,000

6,975,000
-

930

6,510,000
-

5,062,500

Total Carried to Collection below


28

16,770,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

COLLECTION PAGE
Page No. 25
Page No. 26
Page No. 27
Page No. 28

RATE

Measured Quantities

AMOUNT
67,732,000
96,671,500
99,901,500
5,062,500

269,367,500

TOTAL SUBSTRUCTURE TO SUMMARY


29

QTY

AMOUNT
99,168,000
132,690,000
106,101,750
16,770,000
-

354,729,750

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION
SEPTIC TANK
EXCAVATION
Excavate for trench commencing at reduced level but not
exceeding 3.0m deep

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

CM

20

12,000

240,000

20

240,000

WALLING
Well Burnt Clay Bricks jointed and pointed in cement sand(1:3)
mortar: with and including hoop iron wall ties every alternate
course :in
200mm Thick walls
SM

34

50,000

1,700,000

34

1,700,000

SM

38

8,000

304,000

38

304,000

CM

400,000

400,000

400,000

VIBRATED REINFORCED CONCRETE CLASS 25 (20MM


AGGREGATE) IN:
200mm septic tank base
200mm Top Slab

CM
CM

4
4

550,000
550,000

2,200,000
2,200,000

4
4

2,200,000
2,200,000

STEEL REINFORMENT as described including cutting to


length, bending, hoisting and fixing and including all
necessary tying wire and spacing blocks
RIBBED BARS to BS 4461
12mm ditto

KG

160

5,000

800,000

160

800,000

INTERNAL WALL SCREED, FIRST TWO COATS OF


CEMENT AND WASHED SAND (1:3) RENDER,
second coat of stucco putty screed, trowelled smooth
19mm Thick three layer work to walls
CONCRETE WORK
PLAIN CONCRETE CLASS 15 (20MM AGGREGATE)
Blinding

Total to collection

7,844,000
30

7,844,000

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

Measured Quantities

AMOUNT

QTY

AMOUNT

FORMWORK
Edges of floor bed 150 - 225mm high

LM

16

8,500

136,000

16

136,000

Soffits of suspended slab

SM

12

28,000

336,000

12

336,000

Manhole 450 x 600mm noting exceeding 1500mm deep, in


solid concrete block walls, rendered smooth inside complete
with benching, bitumen coated cast iron manhole cover and allNo

550,000

1,100,000

1,100,000

Manhole 750 x 600mm covers

No

650,000

650,000

650,000

Water proof rendering in two 100mm layers each layer


brashed with marthseal 501

SM

38

28,000

1,064,000

38

1,064,000

Allow for all necessary pipes and fittings

ITEM

400,000

400,000

400,000

1,000,000

1,000,000

1,000,000

Soak Pit 2.0m Diameter x 1.5m deep including all excavation;


hardcore fill; 1000gauge polythene and backfilling
No
Total to collection

4,686,000

4,686,000

Page 30

7,844,000

7,844,000

Page 31

4,686,000

4,686,000

12,530,000

12,530,000

Collection

Total Septic tank


31

VALUATION FOR WORKS AT NAMUGONGO FOYER SITE


Original Boq

ITEM

DESCRIPTION

UNIT QTY

RATE

AMOUNT

Measured Quantities

QTY

AMOUNT

SUMMARY
PRELIMINARIES

30,700,000

20,400,000

SUBSTRUCTURE

269,367,500

354,729,750

12,530,000

12,530,000

312,597,500

387,659,750

56,267,550

69,778,755

368,865,050

457,438,505

SEPTIC TANK
SUB-TOTAL
VAT 18%

GRAND TOTAL