Professional Documents
Culture Documents
Question 1 (4 points)
List and briefly describe the ways projects may be terminated.
Question 2 (6 points)
What are the advantages of top-down budgeting and of bottom-up budgeting? What is the
most important task for top management to do in bottom-up budgeting?
Question 3 (5 points)
When might a firm choose to reduce a project? What factors must be considered in making this
decision?
Page 1 of 6
19
0
1
A
7
7
2
12 12
3
21 21
4
29 29
5
G
5
H
6
I
7
41 41
10
33 34
22 23
10
34 34
11
The contract do not contains any bonus-penalty clause. Fixed overhead costs are $ 500 (at the beginning
of the project). Variable overheads are $ 800 / day.
Table 1 shows for each activity, the normal and compressed durations and direct costs. Taking account of
these data:
Calculate the minimal duration of the project. (8 points)
Draw the "Direct Cost / Time" curve for this project. (3 points)
Draw the "Indirect Cost / Time" curve for this project. (4 points)
Taking into account the direct and the indirect costs, draw the "Total Cost / Time" curve. (3
points)
Determine the optimum duration to complete this project and the relative cost of this duration.
(2 points)
Table 1
Normal
Activity
Duration
A
B
C
D
E
F
G
H
I
TOTAL
7
5
9
19
10
8
5
11
7
Compressed
Cost
3 600$
5 500$
6 350$
4 700$
2 050$
1 200$
7 200$
9 450$
4 500$
44 550$
Duration
6
3
7
18
9
6
5
10
6
Cost
3 900$
6 500$
7 200$
4 900$
2 200$
1 700$
7 200$
10 000$
4 700$
Page 2 of 6
ACTIVITY
DURAT
ION
G
H
I
J
K
L
M
N
O
P
R
S
7
10
4
5
4
5
8
3
12
4
7
8
PREDECESSOR
None
G
G
G
H
H, I
J
I, M
K, L, N
L, N
L, N
R
Page 3 of 6
Quantity
Cost
70,00 m2
240,00 m2
160,00 m2
400,00 m2
45,00 $/ m2
50,00 $/ m2
65,00 $/ m2
55,00 $/ m2
1400,00 $/ t
0,6 tonne
1,6 tonne
1,1 tonne
7,8 tonnes
15,00 $/ t
20,00 $/ t
25,00 $/ t
20,00 $/ t
80,00 $/m3
15,00 m3
20,00 m3
10,00 m3
65,00 m3
10,00 $/ m3
15,00 $/ m3
20,00 $/ m3
15,00 $/ m3
700,00 m2
40,00 $/ m2
Page 4 of 6
Page 5 of 6
Determine the unit cost in 2005, using the method of floor area. (3 points)
What will be the probable cost of construction if the total area was 6500 m2? (4 points)
Determine the unit cost in 2005, using the method of the destination unit. (4 points)
Considering an annual inflation rate of 3%, calculate the probable cost of construction
for an 8-storey hotel with a capacity of 30 rooms per floor, which will be realized in
2015? (4 points)
Page 6 of 6