You are on page 1of 216

Marine Equipment & Operation

David N. EDELSON Senior Project Installation Manager TPUSA


Universidad de los Andes 28 June 2013

Agenda

1. Introductions

0830 to 0845

2. Subsea Pipelines Systems Installation Overview

0845 to 1000

3. Break

1000 to 1030

4. S-Lay & R-Lay Pipeline Installation Method

1030 to 1230

5. Lunch

1230 to 1400

6. Subsea Construction

1400 to 1530

7. Break

1530 to 1600

8. Structures Transport and Installation

1600 to 1730

9. Wrap-up and Final Questions

1730 to 1800

Copyright Technip and others.

About the Instructor


Title: Senior Project Installation Manager
Marine Operations Engineering
Company: Technip USA Inc.
Region: North America
Business Segment: Offshore
Education: BSc. Naval Architecture / Marine
Engineering

David N.
EDELSON

Experience: Over 28 years experience in


marine/offshore oil & gas industries involving
floating (drillship, FPSO, semi-submersible,
spar) and fixed (jackup, jacket, gravity base
structure) production and drilling facility design,
fabrication, upgrade, installation (including
topside floatover) and repair.
Contact:

dedelson@technip.com
+1 281-249-7923

Copyright Technip and others.

TERMINOLOGY

Transportation & Installation

Copyright Technip and others.

Shallow Water Field Development Systems


Fixed Steel Platform (Jacket)
Topside carrying processing
equipment and
accommodation
Rigid Subsea Pipeline
Rigid Riser installed on Jacket
Rigid Subsea Tie-in Spool
Trunk Line

Copyright Technip and others.

Deepwater Field Development Systems


Floating Platform
(Spar, TLP, SemiSubmersible, FPSO)
Subsea Equipment
(Subsea / Wet Tree,
Manifold, Jumper, etc)
In-field Flowline with
PLET / PLEM / ILS
Riser (SCR, Flexible
Riser)

Copyright Technip and others.

Deepwater Field Development Systems


MC
MC 503/547
503/547 3000
3000 fsw
fsw (914m)
(914m)

LLOG
LLOG Who
Who Dat
Dat Project
Project
Gulf
of
Mexico
Gulf of Mexico

Flexible
Flexible Risers
Risers
Gas Export Line

87,800 10 Gas Pipeline


to existing pipeline
94,700 14 Oil Pipeline

PLET

Dual 15,000 6 insulated flowlines


Dual 11,500 6 insulated flowlines

3 Jumpers

PLET
6 Jumpers

2 PLETS
4 Slot Subsea Manifold

Location A

2 PLETS
(2) Slot Subsea
Manifolds

Location E

Subsea Control Equipment (Umbilical, UTA, SDU, Flying Lead)


Export Lines to subsea T, platform or shore

Copyright Technip and others.

Different Types of Rigid Subsea Pipelines


Deepwater In-Field Pipelines
Production, Water/Gas Injection and Gas Lift.
Small Diameters 6 to 10 (152mm 254mm)
Insulated
5LPP Five Layer Polypropylene
GSPU Glass Syntactic Polyurethane

Corrosion Coated
FBE Fusion Bonded Epoxy
3LPP Three Layer Polypropylene
3LPE Three Layer Polyethylene

Typically no concrete coatings


Short distances (Typically weight 5 to 20 km)
Shallow Water In-Field Pipelines
Same as above but concrete coated for stability and / or
trenched

Copyright Technip and others.

Different Types of Rigid Subsea Pipelines


Export and Trunk Lines
Oil and Gas Exporting
Large Diameters 12 to 48 (305mm 1,219mm)
Corrosion Coated
FBE Fusion Bonded Epoxy
3LPP Three Layer Polypropylene
3LPE Three Layer Polyethylene

Typically concrete coated for stability reasons


Long distances (typically 25 to 100 km to existing subsea
export networks or to the beach)

Copyright Technip and others.

Different Types of Rigid Subsea Pipelines


In-Field Pipe-in-Pipe
Typically for Production flowlines
Diameters 6 (152mm) in 10 (254mm) or
8 (203mm) in 10 (254mm)
Insulation coating on inner pipe
Aerogel
Polyurethane Foam

Corrosion coating on outer pipe (3LPP, etc)


Short distances
In-Field Pipeline Bundles
Pipeline bundle product integrates the required
flowlines, water injection, gas lift, chemical
injection and control systems necessary for
any subsea development and assembles them
within a large diameter steel carrier pipe.
Towhead structures incorporating equipment
and valves, designed specifically to the
requirements of the field, are attached at each
end of the bundle
10

Copyright Technip and others.

Subsea Structures Installed with the Pipelines


PLET (Pipeline End Termination)
Single hub structures at the end of the
pipeline for connecting the pipeline to
the subsea Manifolds via jumpers
PLEM (Pipeline End Manifold)
Larger multiple hub (dual or triple)
structures at the end of the pipelines for
connecting the pipelines directly to the
X-mas trees via jumpers
ILS (In-line Sled / Structure)
Single or dual hub subsea structures in
the middle of the pipeline section to
connect the pipelines to existing or
future wells via Jumpers

11

Copyright Technip and others.

Risers Connecting Pipelines to Platforms


Rigid Deep Water Steel Catenary Riser (SCR)
Typically used in deep and ultra deep waters
Flexible Riser
Typically used in medium to deep water
Rigid Shallow Water Riser
Fixed to the jacket structures via clamps

12

Copyright Technip and others.

Power & Control from Platforms


Umbilicals
Conduit for electrical power and
communications, fiber optic
communications and hydraulic and
chemical services.
Umbilical Termination Assembly (UTA)
Terminates umbilical and provides single
or multiple outlet connections for electrical
power and communications, fiber optic
communications and hydraulic and
chemical services.
Subsea Distribution Unit (SDU)
Receives electrical power and
communications, fiber optic
communications and hydraulic and
chemical services from the UTA and
distributes to multiple users such as trees,
manifolds, pumping and boosting stations
and infield tie-ins.
13

Copyright Technip and others.

PIPELINE INSTALLATION

Transportation & Installation

Copyright Technip and others.

Rigid Pipeline Systems Installation Methods


S-Lay
J-Lay
Reel Lay
Towing

15

Copyright Technip and others.

What is S-Lay?

Bollard Pull

Water Depth

Top Tension

Bottom Tension

16

Copyright Technip and others.

What is J-Lay?

Bollard Pull

Top Tension

Bottom Tension

17

Copyright Technip and others.

What is Reel Lay?


Lay Distance
Bollard Pull

Lay Angle

Water Depth

Top Tension

Min Bend Radius


Bottom Tension

Touchdown Point
18

Copyright Technip and others.

What is Towing?

Leading
Tug

TrailingTug

19

Copyright Technip and others.

Comparison between the different methods


S-Lay

J-Lay

Reel Lay

Waterdepth

Very Shallow to Medium

Deep & Ultra Deep

Shallow to Deep

Pipeline Type

Export & Trunk

Export

In-Field

Outside Diameter

4 60 in (102 1524 mm)

Up to 24 in (610 mm)

Up to 18 in (457 mm)

Length

Short to Very Long

Short to Long

Short to Medium

Fabrication

On Vessel

On Vessel

On Shore (Spool Base)

Lay Speed

1 4 miles / day (1.6 6.4 km)

Slower than S-Lay

500 m/hr

Coatings

All Types

Corrosion

Corrosion & Insulation


(no concrete)

20

Copyright Technip and others.

S-LAY PIPELINE INSTALLATION

Transportation & Installation

Copyright Technip and others.

S-Lay Using G1200 Vessel

22

Copyright Technip and others.

G1200 Principle Dimensions


Length

162.3m

Breadth

37.8m

Depth (freeboard deck)

9.1m

Depth (main deck)

16.1m

Operating draft

5.8m 6.6m

23

Copyright Technip and others.

G1200 Vessel Marine Systems


Class: Derrick and Pipe Laying Vessel, DPS-2, Self Propelled.
Power: 6 main engine/generator sets delivers a total output power of 25 MW
Thrusters:
Propulsion and DP: 2 ea. 4,500 kW azimuth thrusters
DP: 5 ea. 2,400 kW azimuth thrusters & 1 ea. 880 kW tunnel thruster
Mooring System:
8 each 110 ton electric mooring winches
915m x 64mm wire rope capacity
12 ton Flipper Delta anchors
Accommodation: 264
Transit Speed: up to 15 Knots

24

Copyright Technip and others.

G1200 Vessel Capabilities


Variable deck load 4,000mt (5mt/m2)
Main Deck Pipe Storage Capacity
16
Bare
Pipe

16
Conc.
Coated

24 OD
Bare
Pipe

24 OD
Conc.
Coated

No. of
Joints

873

688

390

295

Length
(km)

10.6

8.4

4.8

3.6

Fuel 2,200mt
Fresh water 1,400mt
Endurance (days) 45 transit / 35 pipelay
Helideck Octagonal, 23m diameter,
suitable for Super Puma and Sikorsky
S61-N
25

Copyright Technip and others.

G1200 Vessel Profile

26

Copyright Technip and others.

Main Deck Layout


Piperack
Pipe Elevators

Pipe End Prep


27

Copyright Technip and others.

Freeboard Deck Layout


Field Joint Coating
(FJC) Stations

Tensioners

A&R Winch
Pipe Elevator

NDE/Repair Stations
Welding Stations

28

Copyright Technip and others.

Free Board Deck Pipe Transfer Equipment


NDE / Repair

Weld Station

Tensioner

FJC Station

29

Copyright Technip and others.

Pipe Joints Route On the Main Deck

30

Copyright Technip and others.

Pipe Joints Route On the Main Deck

31

Copyright Technip and others.

Pipe Joints Route On the Main Deck

32

Copyright Technip and others.

Pipe Joints Route On the Main Deck

33

Copyright Technip and others.

Pipe Joints Route On the Freeboard Deck

34

Copyright Technip and others.

Pipe Joints Route On the Freeboard Deck

35

Copyright Technip and others.

Pipe Joints Route On the Freeboard Deck

36

Copyright Technip and others.

Pipe Joints Route On the Freeboard Deck

37

Copyright Technip and others.

Pipeline Welding Techniques


Manual Welding
Standard up to +/- 20 years ago
Typically 300 bevel
Electrode Consumables

Semi-Automated Welding
Currently standard practice
U shaped bevel
Wire Consumables

38

Copyright Technip and others.

Internal Line-Up Clamp (ILUC)


Internal alignment of two pipe joints
Copper backing shoe allows full
penetration weld from outside without
backing bars
Moves from connection to
connection

39

Copyright Technip and others.

Non Destructive Examination (NDE)


Radiography (X-ray or Gamma ray)
X-ray source on pipe crawler inside pipeline to
shoot X-ray film of weld
Automatic Ultrasonic Testing (AUT)
Sound waves move through the inspected material.
Normally they follow a straight line, but when they hit
upon a defect, the sound waves are reflected. As a
result of the reflection of sound beams it is possible to
trace defects in the materials, even at a long distance
away from the surface of the material.

40

Copyright Technip and others.

Field Joint Coatings


Line pipe supplied in average lengths of 40 (12.2m)
joints with coating except for ends (coating cut-back)
Pipe must be coated between joints to provide anticorrosion insulation protection and/or weight
Field joint coatings must withstand fabrication and
installation conditions:
Bending & Straightening (Flexibility,
Stiffness mismatch)
Interaction with rollers on barge and stinger
Environmental conditions during storage, installation and service
(Brittleness, Softening, UV Degradation)
Application process effects on the steel pipe (Cool down time, etc.)

41

Copyright Technip and others.

Different Types of FJCs


Fusion Bonded Epoxy (FBE)
Works well with all types of corrosion parent
coatings (FBE, 3LPP, 3LPEetc)
Heat Shrink Sleeves (HSS)
Works well with all types of corrosion and
parent coatings. Very widely used in the Slay industry.
Injection Moulded Polyurethane (IMPU)
Works with PU based insulation parent
coatings (GSPU).
Injection Moulded Polypropylene (IMPP)
Works with PP based insulation parent
coatings (5LPP).

42

Copyright Technip and others.

Heat Shrink Sleeve (HSS) Field Joint Coating

43

Copyright Technip and others.

G1200 in Action

44

Copyright Technip and others.

G1200 Main Pipelay Equipment


Tensioners:
4 @125mt Remacut, 500mT total during lay
4 @ 160mt, 640mT total on breaks in case of accidental flooding
A/R Winch: 400mT pull, 3000m x 108mm or 64mm low-rotation wire
Davits: 6 @ 50mT each
Deepwater stinger: 91m long, 900 departure at 84m radius (typical)
Maximum radius 366m
Shallow water stinger: 37m long with 152m 366m radius

45

Copyright Technip and others.

Tensioners and Stern Rollers

46

Copyright Technip and others.

Deep Water Stinger

47

Copyright Technip and others.

Shallow Water Stinger

1 SECTIONS 38.5M
48

Copyright Technip and others.

A&R Winch and Wire Routing

49

Copyright Technip and others.

A&R Winch

50

Copyright Technip and others.

Davits

51

Copyright Technip and others.

Installation Analysis
WHY do we need to perform installation analysis?

To ensure we are within equipment capacity


To ensure product integrity is not compromised
To maximize weather window
To maximize installation efficiency
To develop innovative installation techniques

52

Copyright Technip and others.

Installation Analysis Stages


WHEN Do We Need to Perform Analysis?

TENDER

Preliminary
calculations
Feasibility check
Vessel selection
Method
statement

PROJECT
EXECUTION

Detailed
engineering
phase
Deliverables

OFFSHORE
PHASE

Provide real-time
assistance to
critical steps
Provide help for
unplanned events

53

Copyright Technip and others.

Static Analysis Acceptance Criteria


Stress Based Design (Mexico, Middle East.etc.)
Overbend Stress < 85 90% Section Modulus Yield Stress (SMYS)
Sagbend Stress < 72% SMYS
Strain Based Design
Overbend Strain Det Norske Veritas (DNV) Criteria

Sagbend Strain < 0.15%

54

Copyright Technip and others.

Dynamic Analysis Acceptance Criteria


DNV Simplified Criterion
Overbend

Sagbend stress < 87% SMYS


DNV Local Buckling Check
Overbend is considered Displacement Control up to the last roller in
contact with the pipe
Sagbend region is considered Load Control and it starts at the last
roller on the stinger tip section
55

Copyright Technip and others.

Key Software
Pipelines Analysis
Offpipe, Orcaflex and Pipelay Rigid pipelines (S-lay configurations)
Orcaflex Flexibles, umbilicals
Structural Analysis
SACS General structural engineering
ANSYS Finite Element Analysis (FEA)
Naval Architecture
MOSES Mooring analysis
SESEAM Response Amplitude Operator (RAO) generation
Drafting
Autocad Drafting and Design
Inventor Animation and Design
56

Copyright Technip and others.

Normal Lay and Dead Band Range

57

Copyright Technip and others.

Vessel Rollers Set-up

58

Copyright Technip and others.

Stinger Rollers Set-up

59

Copyright Technip and others.

Stinger Rollers Set-up (Contd)

60

Copyright Technip and others.

S-Lay Installation Activities


Start-up / Initiation
Normal Lay & Dead Band Range
Abandonment and Recovery
Laydown
Wet Buckle Recovery
Davit pick-up and Sweeping / Lateral Move
Shallow Water Risers / Spools Installation
Shallow Water Beach Pull
Above Water Tie-in
PLETs Installation (1st End / 2nd End)
SCR Installation (1st End and 2nd End)
Flooding, Gauging & Hydrotesting
61

Copyright Technip and others.

Start-up / Initiation

62

Copyright Technip and others.

A&R and Lay Down

63

Copyright Technip and others.

Wet Buckle Recovery

64

Copyright Technip and others.

Davit Pick-up & Sweeping In Shallow Water

65

Copyright Technip and others.

Shallow Water Beach Pull

66

Copyright Technip and others.

Shallow Water Risers/Spools Installation

67

Copyright Technip and others.

Above Water Tie-In (AWTI)

68

Copyright Technip and others.

1st End PLET Installation

69

Copyright Technip and others.

2nd End PLET Handling System

70

Copyright Technip and others.

2nd End PLET Installation

71

Copyright Technip and others.

2nd End PLET Deployment

72

Copyright Technip and others.

Firing Line / Stinger Clearances for ILS


Installation

73

Copyright Technip and others.

SCR 1st End Installation (Lay Away)

74

Copyright Technip and others.

SCR 2nd End Installation (Lay Towards)

75

Copyright Technip and others.

Flooding, Gauging and Hydrotesting


Flooding and Cleaning
Done through Start-up/A&R heads
using Pig Launchers and Receivers and
foam / wire brush pigs
Gauging
Done to confirm no buckles in the
pipeline using a gauging pig with a
calibrated disc (Typ. 95% of the
smallest ID of the system)
Hydrotesting
The whole system is pressurized to
1.25 times the design pressure and
pressure is held for a minimum of 8 hrs
to confirm welds integrity and no
leakage.
76

Copyright Technip and others.

Typical S-Lay Challenges


Stress Intensification at field Joints due to concrete coating on
main pipe
Restrictions on dimensions/weights during ILS installation
Weather limitations during pipe transfer from barges or pipe
carriers at <3m Hsig (significant wave height)
Pipe logistics can impact lay rates
High bottom tensions in shallow water
Offshore break downs / repairs / production delays are all on
critical path (more costly compared to onshore production at the
spool base)

77

Copyright Technip and others.

WELDING PROCESSES

78

Transportation & Installation

Copyright Technip and others.

Welding Familiarization
Terminology
Welding Generic term referring to arc welding
Electrode Filler metal that supports the arc and fills the weld
joint (SMAW, FCAW, GMAW and SAW) or tungsten electrode
that supports the arc (GTAW). Filler metal is added
independently on GTAW.
Filler Metal Metal that becomes the welded connection
Weld Joint Design of the end of the parts that are going to be
welded, commonly a V or J groove design.
Base metal or parent material rolled, cast, forged metal part of
the pipe that remains unaffected by the welding process.
Heat Affected Zone (HAZ) The base metal next to the weld
that has metallurgically changed.

79

Spoolbase / Welding

Copyright Technip and others.

Welding Familiarization

Parent Material (PM)


Heat Affected Zone (HAZ)
Fusion Line (FL)
Weld Metal (WM)

80

Spoolbase / Welding

Copyright Technip and others.

Welding Processes & Positions

Different types of Welding exist. The quality of the welds, the level
of productivity required and the Client specifications will, amongst
other requirements, drive the choice.
Main techniques used on production sites:

81

SMAW
FCAW-G
GTAW
SAW
GMAW

Shield Metal Arc Welding (flux coated rod)


Flux Core Arc Welding Gas shielded
Gas Tungsten Arc Welding
Submerged Arc Welding
Gas Metal Arc Welding

Spoolbase / Welding

Copyright Technip and others.

Welding Processes & Positions


Plate 1G, 2G, 3G and 4G
Pipe 1G, 2G, 5G and 6G

82

Spoolbase / Welding

Copyright Technip and others.

Welding Processes: SMAW


Areas of use
All steel from 2mm upwards
Widespread use (pipeline, jacket,
fabrication shop)
Universal process

Positives
Simple, inexpensive, and highly

portable equipment
Electrode provides and regulates its
own flux
All positions
Less sensitive to wind or drafts

Negatives
Welder skills based

Limited welding speed


Slag removal

83

Spoolbase / Welding

Copyright Technip and others.

Welding Processes: FCAW-G


Areas of use
All steel from 2mm upwards
Widespread use (pipeline,
jacket, fabrication shop)
Universal process
Positives
All positions
High productivity
Semi automatic process
Reduced welder skill
required
Negatives
Wire cost
Slag removal
Mechanical properties

84

Spoolbase / Welding

Copyright Technip and others.

Welding Processes: GTAW


Areas of use
Thin sections

Non ferrous metals


High quality welding (SCR,
nuclear field)

Positives
Low thermal distortion

High quality welding


No slag, very clean process

Negatives
Low deposit rate, low productivity

Not practical for thick sections


Highly skilled welders required

85

Spoolbase / Welding

Copyright Technip and others.

Welding Processes: SAW


Areas of use
Thick sections

Double jointing
Jacket legs

Positives

High productivity
Welder friendly
Reliable and simple
May be fully automatic

Negatives
Flux recycling

Slag removal
Flux storage
Practical in only the flat (1G) position

86

Spoolbase / Welding

Copyright Technip and others.

Welding Processes: GMAW


Areas of use
All steel from 2mm upwards

Widespread use
Universal process

Positives
Easy automation

High productivity
Semi automatic process
Reduced welder skill required

Negatives
Sensitive to wind and draft

Weld quality (porosities, lack of


fusion)
Normally limited to flat (1G) and
horizontal (2G) positions

87

Spoolbase / Welding

Copyright Technip and others.

Welding Processes - Summary

SMAW

FCAW-G

GMAW (auto)

SAW

GTAW

Productivity

++

++

--

Areas of use

Repairs
Flanges
Tie-Ins

Repairs
Jackets

Main flow lines & SCR


Double Joints

Double Joints
Piles

Root &hot pass SCR


Stainless steel

All

All, <6 (152mm)

>6 (152mm)

>12 (305mm)

All, Small OD x WT

7 to 10

12

16

21

Repair rate

< 3%

< 3%

< 4%

< 3%

< 2%

Cost to Use

--

++

++

Pipe sizes
Travel Speed
Inch /min

88

Spoolbase / Welding

Copyright Technip and others.

AUTOMATIC WELDING

89

Transportation & Installation

Copyright Technip and others.

Automatic Welding (GMAW)


Advantages: High productivity, less welders skill dependent, reproducibility
Disadvantages: High cost, many equipments involved, not easy to deploy
Areas of use: Preferred process for spoolbases, S-Lay and J-Lay barges
Process: Single or Dual-torch downhill pulsed GMAW, all passes from
outside of the pipe

90

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)


Welding Position
5 G (horizontal pipe) - Spoolbase and SLay barge

91

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)


Welding Position
2 G (vertical pipe) JLay

92

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding Joint Design

93

Narrow Groove

Wide Groove

A = 3 to 5 Degrees

A = 25 to 30 Degrees

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)

Shielding Gas
Shields the weld puddle from the atmosphere
Ensures smooth transfer of molten droplets from the wire to the weld
pool
Substantial effect on the stability of the arc
Substantial effect on the behaviour of the weld pool, in particular, its
penetration
Typical gas mixture (Ar/CO2 50/50 or 80/20)

94

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)


Ancillary Equipment
Pipe Facing Machine (PFM)
Bevels the ends prior welding

95

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)

Ancillary Equipment
Pipe Facing Machine (PFM)
3 main parts:
o clamping assembly
o rotating assembly
o sliding tools holder

96

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)

Ancillary Equipment
Internal Line Up Clamp (ILUC)
Facilitates fitup of the two pipes
When fit with copper backing, it
allows the weld to be placed above,
but not fuse to it

97

Spoolbase / Welding

Copyright Technip and others.

Automatic Welding (GMAW)


Ancillary Equipment
Internal Line Up Clamp (ILUC)

98

Spoolbase / Welding

Copyright Technip and others.

Welding Procedures Qualifications


(WPQs)

99

Transportation & Installation

Copyright Technip and others.

Welding procedures Qualifications (WPQs)


Review Project
and Specifications

Production

Create Weld
Matrix

Create
pWPSs

Submit for Client


Approval
Submit for Client
Review

Start
Qualification
Program

Initial ECA Acceptance


Requirements

Create
WPSs

Welds are
NDE tested

Welds are
Reeled

Mechanically test
Welds

Final ECA Acceptance


Requirements

100

Spoolbase / Welding

Copyright Technip and others.

Welding Procedures Qualifications (WPQs)


Typical Welding Procedure Specification (WPS)

101

Spoolbase / Welding

Copyright Technip and others.

Technip GMAW Welding System


Technip in-house developed GMAW welding system

102

Copyright Technip and others.

REEL LAY

103

Transportation & Installation

Copyright Technip and others.

Deep Blue Reel Lay Equipment


Top module
Main aligner

Main Reels

RD Tensioners

104

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Process


Spooling at Theodore Spoolbase
Spooling lines
Spooling elbow and reel packing

105

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment


Main Aligner

Upper Straightener

Lower
Straightener
106

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment


Upper Tensioner
Max Capacity 275te

Lower Tensioner
Max Capacity 275te
107

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment


Middle Floor

MWP
Movable Working
Platform

MWP Control
Room

108

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment

HOM
(Hang Off Module)

MCR
(Master Control Room)

109

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment


150Te starboard sheave

Stern roller

110

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment


360Te capstan winch
360Te wire storage drum

360Te wire route up


port tower leg
111

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Equipment


Storage in Fwd Carrousel

112

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Flex Chute

Copyright Technip and others.

Deep Blue Reel Lay Equipment


Flex Aligner

113

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Pipelay Capabilities

114

Reel Lay (high productivity)


Lay rate 3280 ft / hr
Pipe sizes Single wall pipe 4 to 18
Pipe-in Pipe, max 8 x 12

J-Lay (large dia, ultra deepwater)


Lay rate: 160 upto 320ft /hr
Single pipe 2 quads/hour
Pipe-in-Pipe: 1 quad / hour
Pipe sizes single wall up to 30
Pipe-in-pipe 10 x 16

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Packing Analysis

115

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Reel Lay Process


Mobilization
On deck and outriggers
Equipment, Structures, Piles

116

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Deep Blue
Outriggers

Copyright Technip and others.

Deep Blue Reel Lay Process


Straightening Trials and Tensioner Settings

117

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Deep Blue Pipelaying

118

Copyright Technip and others.

Distinctions Between S-Lay and R-Lay


S-lay can lay concrete coated pipe
S-lay can lay in very shallow water (no pipe/moon-pool clashing
issues)
Pipe experiences less strains during S-lay installation (0.3%
overbend strain compared to 2% reeling strain)
Advantageous for SCRs Fatigue (Sour Service)
Can lay large diameter pipelines (>18 OD)
Less residual torque in the pipe during PLET/ILS installation
(Less propensity to rotate)
Pipe production offshore vs onshore

119

Copyright Technip and others.

Flexible & Umbilical Installations

120

Transportation & Installation

Copyright Technip and others.

Flexible & Umbilical Installations


The common methods available to install pipelines are:
Horizontal over gutter from reel winch
Horizontal over wheel from tensioners
Vertical through tensioners
Storage & Packing options
Reels
Carousels
Installation Process
Over-boarding requirements for intermediate connections and accessories
Deck space requirements for flexible/umbilical storage
Damage & Contingencies

121

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Horizontal over gutter from reel winch
Lay tension < 20 Te

122

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Horizontal over wheel from tensioners
Lay tension < 50 T

123

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Vertical through tensioners
Lay tension < 450 T, water depth >75m

124

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Storage


Standard Reels
Outer flange diameter 7.8m, 8.6m, 9.2m, 9.6m.
Standard hub width diameter 4.4m.
Capacity <180 t product
Usually small diameter, short length, typical infield
umbilical or riser in shallow water.

125

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Storage


Laying baskets (2000T)
Dimensions 17.8m O.D, Hub 6m, Height 7m.
Capacity 2000t product
Usually large diameter, long length, typical
deepwater fexible riser, long control umbilical.
Laying basket 900 T

126

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Storage

86 reel on an extended cradle

2000t carousel

86 Extended cradle (8.5m)

86 Standard installation cradle (7m)


127

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Reel Packing Analysis Portable Reel

LENGTH = 4600m
Umbilical properties
O.D. = 114mm
WEIGHT = 30Kg/m
128

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Reel Packing Analysis Quick Reference Graph

Based on 2.5m partition.


Weights shown are the maximum pipe weight to accomplish the volume restriction for each outside diameter.

129

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Tensioners
Bi-cat has 2 tracks or 1 track pair

130

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Tensioners
Tri-cat has 3 tracks

131

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Tensioners
Quad-cat has 4 tracks or 2 track pairs

132

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Vertical Lay System (VLS04)
2 Tensioner 4 tracks
270 t Dynamic Safe Working Load (SWL)
Quad mode
135 t Dyn SWL Twin mode
3.68m contact length
280 t Dyn SWL A&R winch
2,500m wire A&R winch
280 t Dyn SWL Hang Off Table (HOT)
6 t SWL Harbor top crane / 12m reach

Min Diameter (Quad Mode)

90mm (3.54)

Min Diameter (Twin Mode)

70mm (2.75)

Max Diameter

600mm (23.6)

Max Opening

1.4m (4.6ft)

133

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Portable Pipelay System (PPS01)
2 Tensioner 4 tracks
350 t Dyn SWL Quad mode
175 t Dyn SWL Twin mode
4.23m contact length
400 t Dyn SWL A&R winch
2,750m wire A&R winch
450 t Dyn SWL HOT
15 t SWL Harbor top crane / 15m reach

134

Min Diameter (Quad Mode)

100mm (3.9)

Min Diameter (Twin Mode)

50mm (1.9)

Max Diameter

600mm (23.6)

Max Opening

1.65m (5.41ft)

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Example Deck Layout:
Manifold (x2)
Umbilical
Flexible Riser
Manifold

Umbilical
Mudmat

Umbilical
Flexible Riser

2,000t Carousel
135

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Example Deck Layout:
Infield Umbilicals (x6)
Flying Leads (FL)
FL Spread
Infield Umbilicals (6 reels, 9.2m)

AHC Crane
136

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

PPS01

2,000t Carousel

Copyright Technip and others.

Flexible & Umbilical Installations

Installation Process
Step 1
Unpack the 1st end pull-in end and
route onto the deck

137

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Step 2
Route 1st end around horizontal and
vertical deflector

Step 3
Pass 1st end over gutter down
through tensioners

Copyright Technip and others.

Flexible & Umbilical Installations


Installation Process
Step 4
Once arrived at HOT, connect 1st
end to pull in wire complete initiation
and lay

138

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Step 5
Bring 2nd end over gutter using crane
and hold back winch

Step 6 C onnect 2nd end to A&R winch, open


tensioner and bring 2nd end to HOT

Copyright Technip and others.

Flexible & Umbilical Installations


Installation Process
Step 7
Mount bend restrictor & anodes
(flexibles only)

139

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Step 8
Secure 2nd end fitting in HOT

Step 9 Complete intermediate or Connector


connection and deploy

Copyright Technip and others.

Flexible & Umbilical Installations


Installation Process
Step 10
Connect A&R Winch, take up
tension, open HOT and deploy
through splash zone

140

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Flexible & Umbilical Installations


Example Deck Layout:
Infield umbilical packed on reel
Main umbilical trans-spooled in carousel

141

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Subsea Installations:
Pipelay/Flexibles/Umbili
cal/Lifting/Subsea
Construction

Subsea Construction & Lifting

142

Transportation & Installation

Copyright Technip and others.

Subsea Construction

143

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Lift Engineering
What is the purpose of a
lifting engineering
assessment?
To understand operational
limitations
Lift is performed in a safe
and efficient manner
Adhere to the Technip
Lifting Procedures
Protect the asset!

144

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Lifting

145

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Crane Curves
Why use crane curves?
Lifting analysis maximum dynamic line tension
Is the lift feasible? Check against allowable maximum dynamic tension
Vessel mounted cranes have normally three different types of crane curves
Harbour Lift Crane Curves
- Sheltered water lift in port Hs = 0 m
Supply Boat Lift Crane Curves - Vessel to Vessel
Offshore Lift Crane Curves
- Deck & Subsea
What information does a crane curve provide?
Maximum hook elevation
Hook speeds & slewing restrictions
SWL vs Radius
SWL allowable static hook load
Allowable dynamic hook load = SWL * DAF

146

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Simplified vs Engineered Rigging Design

147

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Technip Lifting Operations Procedure (OOSCRN-010)

148

Subsea Installations:
Pipelay/Flexibles/Umbilical/Lifting/Subsea Construction

Copyright Technip and others.

Subsea Installations:
Pipelay/Flexibles/Umbili
cal/Lifting/Subsea
Construction

PRE-COMMISSIONING

155

Transportation & Installation

Copyright Technip and others.

Pre-commissioning Scope of Work


FLOWLINE (API, DNV-OS-F101)

UMBILICAL (ISO 13628-5)

Flooding

Interim Test during Storage / Pre Load Out Test

Cleaning

Monitoring during load out/transpooling

Gauging or Caliper Pigging

Post load-out test

Pig Detection

Transit Monitoring

Hydrostatic Testing

Testing prior to deployment

Pipeline Strength Test

Lay Monitoring

Spool/Jumper Leak Test

Umbilical Post Installation Testing

Leak Detection

Hydraulic Pressure Testing & Flushing

Flushing

Electrical Testing

Dewatering

Fiber Optic Testing

Air drying, Vacuum drying or Chemical Conditioning

Flying Lead Testing

Nitrogen Inerting/Packing

156

Copyright Technip and others.

Umbilical Monitoring & Testing

Air Driven Hydrostatic Test Pumps


Pressure / Temperature
Digital Manometers

Dual Pen P/T Chart


Recorder
Fluid Cleanliness Analysis Kit

Insulation Resistance Tester

Continuity Resistance
Tester (Ohmmeter)

Time Domain Reflectometer

Fiber Optic Test Unit

157
157

Copyright Technip and others.

Topside Pipeline Pre-commissioning

Typical Dewatering Spread including Air Compressor, Booster, Nitrogen Membrane


Operation Performed from a Support Vessel alongside the Platform

158

Copyright Technip and others.

Subsea Pipeline Pre-commissioning

Typical Subsea Pigging/Testing Configuration

Subsea Pig Launcher / Receiver


Flooding / Testing Skid Deployment
159

159

Copyright Technip and others.

Pipeline Pre-commissioning

Bi-Di Cleaning and Gauging Pigs

Standalone Pressure / Temperature Subsea Datalogger

Caliper Pig

160

160

Copyright Technip and others.

Downline Spread (for subsea pigging / testing)

Flexible downline spread

Coil tubing deployment spread

161

Copyright Technip and others.

PLATFORM TRANSPORT AND


INSTALLATION

162

Transportation & Installation

Copyright Technip and others.

Platform Installation
Typical Platform Make-up
Vent/Flare Boom

Topside or Deck

Jacket
Risers
Conductors
Piles/
Foundation &
Mudmats
163

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Platform Installation - Definitions


Piles
Piles or driven piles serve as a foundation for an offshore platform. Its a steel
tubular member consisting of a driving head, the body & the driving shoe. Piles are
fabricated by welding together rolled steel plates, usually 1.5m in length. The
diameter & pile length depends upon the soil characteristics & magnitude of
loads to be supported.

Jacket
Jacket is a space frame structure made of tubular steel members. The jacket legs
and braces transmit environmental and topside loads into the piles & subsequently
into the seabed. Jackets typically have three, four, six or eight legs. Jackets with
three legs are known as tripods. Jackets with single caisson type leg also exist. The
base of the jacket has mud mats, which increase the bearing surface & thus
support the weight of the jacket in un piled condition.

Conductors
Conductors are tubular steel members housing the casing pipes for the well.
Conductors provides structural support for the internal well tubing and casing
strings. A conductor is installed through the guides of an existing jacket. Lateral
support is provided to the conductor by guides at the platform's horizontal
elevations
164

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Definitions
Riser
A riser is the vertical part of a subsea pipeline, which delivers hydrocarbons to &
from the platform facilities above sea. It is a pressurized pipe & runs along the face
of the jacket. Riser may be preinstalled on the jackets, installed offshore or any time
during the life span of a platform. Risers are secured to the jacket by mechanical
clamping.

Deck
The deck is the main visible portion of an offshore platform. A deck can have
multiple levels, each fabricated with a grid of steel beams supported by tubular
columns. Depending upon functions of a platform the deck size varies. A processing
platform has huge deck consisting of separator modules, injection modules,
processing modules, pumping modules, power generation units, controlling office &
accommodation modules as well. The well head platforms on the other hand have
relatively very small decks.

Others
There are some tertiary items that are important for the completion/working of an
offshore platform. These consist of flare booms, boat landings, riser guards, bridges
etc.
165

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Launch Barge (Typical)

166

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Load Out

167

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Load Out

JACKET

Skidding and
Launch Beam

168

Offshore Heavy Lift


Transportation & Installation

WINCHES

Copyright Technip and others.

Jacket Installation Load Out

TRAILERS

169

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Loadout

FABRICATION
GRILLAGE
FABRICATION
STANDS
HEAVY DUTY
TRAILER

170

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Load Out

171

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Seafastening

Based upon the size


of the jacket, loading
criterion, the sea
fastening is designed.
However a typical
looks like as shown.

Tie Down
Brace

Tie downs are subjected to both static & dynamic loading. Gravity & inertial
loads are calculated for all anticipated barge accelerations, angles of roll &
pitch during the design storm adopted for the tow to site. Wind Loads are
also consider for jackets with huge surface area. Computer programs are
used for stress analysis. Manual calculations are done in accordance with
AISC allowable stress criterion & marine warranty guidelines.
172

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Seafastening

173

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Seafastening

STOPPER

174

Offshore Heavy Lift


Transportation & Installation

DETAIL 2

Copyright Technip and others.

Jacket Installation Offshore Transportation

For transportation
purposes, a two
phase motion
analysis is carried
out.

Vessel motion response (six degrees of freedom) to regular waves for a


range of wave periods is derived in the form of vessel response amplitude
operators.(RAOs). Then the response to irregular waves is derived from
significant height and wave period. The results shall comply with Marine
warranty specifications, for intact & damaged cases.

175

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Options

A JACKET CAN BE LOWERED INTO WATER IN THE FOLLOWING WAYS

176

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Launch


Once at location the transportation
barge is ballasted / deballasted to
get the required trim for launch.
Seafastening would already be cut.
The jacket slides down into water as
it gains momentum.

177

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Launch

178

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Lift


A lift can be made on either
the stern or on the side of the
construction vessel. Capacity
of an offshore rated crane is
more on stern (considered
fixed) & lesser on the side
(considered rotating).
A lift chart represents the lift
capabilities of a crane. It
defines a capacity for a
specific lift radius & the relative
hook height. It is always
advisable to have reserve
hook height & capacity when
planning a lift.

179

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Horizontal Lift


A horizontal lift refers to the jacket
lifted horizontally off the
material/cargo barge. A horizontal
lift is always followed by upending.
There are always two different sets
of rigging for lifting & upending in
this case.

180

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Vertical Lift


A vertical lift refers to the jacket
lifted vertically off the
material/cargo barge. a vertical
lift doesnt require upending &
saves the need of another set of
rigging. Lift chart shall be
thoroughly checked when
planning vertical lifts.

181

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Lift Plan Example

182

Copyright Technip and others.

Jacket Installation - Upending

A Jacket can be Upended in the Following Ways

183

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Self-Upending

Large jackets have extensive


ballasting & control systems
installed to permit flooding &
venting.
The sequence of flooding
and venting is predetermined
for safe upending of the
jacket.
The jackets may require
external/detachable
buoyancy units to assist free
floating & keep the center of
buoyancy above the center of
gravity, to ease self
upending.
184

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Single Block Upending


After the jacket is lifted and
lowered into water, the
upending slings (preinstalled) are hooked to the
crane block.
The crane upends the
jacket as defined by the
procedure.

SLINGS BEING HOOKED

JACKET BEING UPENDED


185

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Single Block Upending

186

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Double Block Upending


For shorter, horizontally
loaded jackets, upending
can be done in air. This
can be done if the crane
has two independent travel
blocks & both rated for the
calculated loading.
The lift shall be planned
such that, both blocks &
rigging stay clear of each
other at all times.
Ideally both the blocks shall
fall straight to connect to
lift/upending slings.
187

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Double Block Upending

MAIN BLOCK AUXILIARY BLOCK

188

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Setting On Bottom


Once upended the jacket has
to be maneuvered to the
TO
proposed location on the
seabed. The jacket is brought OPERATE
closer to the proposed location
& lowered within the installation
tolerances.
Normally the jacket legs are
closed on both sides, having
positive pressure & have to be
flooded (using reach rod)before
setting it down.

REACH
ROD

Flooding can also be done


during upending through a
manifold installed on top of
jacket.
189

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Setting On Bottom

Connecting hoses to
flooding manifold,
before upending.

Removing flooding
manifold post
upending. Jacket set
on bottom.

190

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Piling


Once the jacket is set on
bottom, a temporary
connection/walkway is
established. The walkway is
called the gangway.
Normally the jacket legs on
top are closed & have to be
prepared/opened for piling.
This refers to removal of
closure plates.
There is no access around the
jacket legs in most of the
cases thus, temporary access
platforms have to be installed
or scaffolding erected.
191

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Piling


Generally the first section
of pile for any leg is
labeled as P1 for that
particular leg. The
following sections have
same denomination.
For smaller jacket P1 can
penetrate below seabed
to support itself, but for
longer jackets the weight
has to be supported by the
jacket itself.
Based upon the jacket on
bottom stability response,
piling sequence is
suggested and has to be
followed on site.
192

Offshore Heavy Lift


Transportation & Installation

ON BOTTOM STABILITY EXTRACT


MIN SAFETY
FACTOR IN ANY
OF THE CASE
SHALL BE

1.2

Copyright Technip and others.

Jacket Installation - Piling


Piles are transported on
the cargo barges. Piles
have to be upended from
the horizontal position &
then inserted in the jacket
legs.
The self weight of the pile
induces bending stresses
in the pile & shall not
exceed the allowable.
If the stresses are beyond
allowable, multiple lift
points are required during
upending of the pile.

193

Offshore Heavy Lift


Transportation & Installation

The pile is upended from one end


using an internal lifting tool (ILT).
The ILT has serrated reciprocating
gripping surfaces which engage to the
inside of the pile.

Copyright Technip and others.

Jacket Installation Pile Upending

INTERNAL
LIFTING TOOL

PILE

PILES ON
DECK

194

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Pile Stabbing


Generally the P1s are the
longest section in the entire pile
make. Pile makeup is detailing
of whole length of pile, number
of sections, drive shoe, drive
head, bom etc. The P1s are
lowered directly into the leg &
have the drive shoe at front.
The jacket legs at the bottom
have sealing diaphragms.
Sometimes the drive shoes
have small wedges to easily
pierce through the diaphrag.
Pile On Speed

195

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Piling


The subsequent pile sections
have preinstalled guides, which
eases stabbing as well as align
the latter pile to the former pile.
The suspended weight of the
pile induces a bending moment
(as shown).
The length of the pile sticking
up from the point of reference
is called the Stickup. It is
generally taken from the first
horizontal brace elevation.
Stabbing guides are designed
to withstand the bending
stresses.
196

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Piling


The stabbing guide serves no
purpose once the welding is
complete between two piles.

STICKUP

The pile itself shall also be


capable of withstanding the
bending stresses due to self
weight. The hammer weight
constitutes the maximum to the
bending moment as it is placed on
the pile top. Thus the bending
stresses at the point of reference
shall consider self weight moment
& moment due to weight of the
hammer & hoses etc.
The calculations are based upon
API RP 2A.
197

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Piling & Welding


The pile sections are welded
together & checked for any weld
flaws using ultrasonic testing.
A hydraulic hammer is used to
hammer the piles into the
seabed. The size & rating of the
hammer is based upon the
resistance to driving predicted
during the driving.
The principle behind pile driving
prediction & hammer selection
is the wave equation analysis.
GRL WEAP is the leading
software used to do the
drivability analysis.
198

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Piling


When all piles are stabbed
& sticking up, care shall
be taken that there is
enough space available
for the hammer to be set &
that the piles are not
clashing with each other.
This shall be done during
the engineering stage,
prior to fabrication of piles.

199

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Piling

PILING IN
PROGRESS
PILING COMPLETED
200

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Leveling


The jacket shall be installed
within the installation
tolerances.
The jacket levels are checked
after initial setup, during piling
& post piling.
If the jacket is out of tolerances
in level, the jacket has to be
leveled. The jacket side which
is high is either pushed down
or the lower side is pulled up
using hydraulic jacks.
another method is the direct
hookup method. The lower
side is picked up by crane.
201

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Leveling

Once the required levels


are achieved the jacket is
secured to the piles using
temporary dog plates or
tension bars.
Typically, for a four legged
jacket, to continue piling
any two diagonal legs shall
be dogged at all times,
post leveling.
The dog plates & t-bars
shall be engineered for the
anticipated loads.

202

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation - Piling


The pile drivability considers the actual location soil report to make accurate
driving predictions. As soil characteristics may vary over a short distance or
there could be localized rock formations, surprises are not uncommon.
The construction vessel shall be equipped with pile refusal remedial
equipment. Refusal is a criterion set forth by API RP 2A & it also depends
upon the usable energy of the hammer, within the allowable pile stresses.
Refusal occurs if there is unforeseen delay between subsequent pile driving
(leading to soil setup) or the pile encounters a rock layer ahead of the shoe.
For such cases a pile top drilling rig is used to remove the soil plug & drill to
the penetration depth.
Drilling is always followed by main pile grouting (re-forming the plug) or
insert piles + grouting, to attain the required foundation capacity. The
annulus between a driven pile & jacket leg is grouted to enhance rigidity &
composite characteristics. It is a two stage process. First, a certain length
is grouted & as grout settles, the remaining length is grouted until the jacket
top.
203

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Pile Top Drilling

204

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Leg Grouting

MECHANICAL/WIPER TYPE

INFLATABLE TYPE

TYPE OF GROUT SEALS

205

Offshore Heavy Lift


Transportation & Installation

GROUT PLUG FORMATION

Copyright Technip and others.

Jacket Installation Pile to Jacket Connection


The piles to jacket
connection is done using
either shim or crown plates.
piles are centralized using
temporary wedges before
the crowns are setup.

206

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Jacket Installation Pile Top Cut Off


During the course of the
installation a tide gauge is
deployed subsea or installed
on the jacket. The tide gauge
establishes the mean sea
level at that location & the
jacket top elevation is found.
The pile cut off elevation is
marked, relative to the
established jacket top
elevation.
field engineers verify the cutoff calculations & physical
measurements are done
before cut-off.
TIDE GAUGE
207

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation - Fabrication


THE DECK FABRICATION MOSTLY FOLLOWS THIS SEQUENCE

SIMULTANEOUS
OPERATIONS
ALLOCATED YARD
AREA
FABRICATION
STANDS & GRILLAGE +
CANS
APPROVED
DRAWINGS
MATERIALS

PREPARATION

PAINTING OF ALL THE DECKS &


TERTIARY STEEL
WELDING OF PIPE SUPPORTS,
ELECTRICAL &
INSTRUMENTION SUPPORTS
SUPPORTS
FABRICATION OF FRAMINGS,
LEG EXTENSIONS, BRACES &
COMPLETION OF PLATING
ASSEMBLY OF LEGS & BRACES

MOUNTING OF
EQUIPMENTS , PIPING
& ASSEMBLY OF DECKS
INSTALLING STAIRS,
INSTALLATION AIDS
RUNNING ELECTRICAL
CABLES
RUNNING HYDRAULLIC
& UTILITY LINES
SAFETY EQUIPMENTS &
FINAL PAINT/TOUCHUP

COMPLETION

208

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation - Fabrication

209

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation - Fabrication

210

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation - Loadout


As described earlier for the
jackets, the decks are loaded
out in a similar way.
Huge decks can be skid on to
the loadout barge using low
friction skid frames, whereas
trailers are more widely used.

211

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation Offshore Options


DECKS CAN BE INSTALLED IN THE FOLLOWING WAYS

SINGLE
LIFT

FLOAT
OVERS

MULTIPLE
LIFTS

DECK INSTALLATION

212

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation Float Over


Float over is a process
where the deck is lowered
on to the installed jacket
by ballasting/deballasting
the cargo barge/vessel.
Floatover jackets are
designed to receive the
carrying vessel between
the legs.

213

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation Float Over

214

Offshore Heavy Lift


Transportation & Installation

Copyright Technip and others.

Deck Installation Single Lift

Decks within the capacity of


the vessel cranes can be
installed in a single lift. The
lift can be made either on
the side or stern, depending
upon the size, weight & list
radius.

215

Copyright Technip and others.

Deck Installation Single Lift


Some construction barges
have two cranes working
simultaneously to lift heavy
decks. Though the lift is
single, it utilizes two blocks.
Two blocks from a same
crane can also be used for
lighter decks.
It can also be lifted &
installed in tandem, with
two different barges & two
different cranes lifting &
installing in a synchronized
manner.
216

Copyright Technip and others.

Deck Installation Multiple Modules

The decks can be installed


as modules as well if the
decks are too heavy and too
big.
For example, an eight-legged
deck can be installed as two
four-legged decks & then
joined offshore.

217

Copyright Technip and others.

Deck Installation - Lift Plan Example

Ventboom, helideck, compressor, equipment


removed from top deck
Access scaffolding installed
Riser pipes, stairs, etc removed and
secured
Rigging installed
Deck leg to Jacket leg weld removed by arc
gouging
Deck lifted and set into preinstalled grillage
on cargo barge
218

Copyright Technip and others.

Platform Installation - Completion


Once the deck is stabbed,
welding of the deck legs to
the piles is completed.
Boatlandings can be
installed before or after the
deck installation, based
upon planned schedule &
access under the deck
overhang.
Similarly, the riserguards
can be installed before or
after deck installation.

219

Copyright Technip and others.

Platform Installation - Completion

Vent/flare booms are installed after deck


installation & the piping spool to the flare
boom piping are installed.
Other completion activities include
painting of welded areas, riser hook-ups,
pipe supports, stairs to jacket, swing
ropes, navigation lights, padeye hatch
closing & sealing.

220

Copyright Technip and others.

Platform Installation - Complete

221

Copyright Technip and others.

Thank you for your Attention

www.technip.com

Copyright Technip and others.

You might also like