You are on page 1of 262

DEVIATION

NAME OF THE WORK: SUPPLY AND ERECTION OF GANTRY CRANE TO OPERATE


STOP LOG STATEMENT
GATES OF BHUPATHIPALEM RESERVOIR SCHEME, RAMPACH
Unit
S.
No

As per Sanctioned Estimate As per Execution

Item of Work
Qty.

Rate /
Unit

Amount
in Rs.

Qty

Rate/
Unit

Probables
Amount
in Rs.

1 Manufacture, supply and erection, testing and


commissioning of Gantry Crane adequate capacity
along with counter weight of adequate capacity
moving gantry crane consisting of rail mounted gantry
frame, of platform with hand railing long bar cross
travel arrangements, rope drums, gear systems,
electric motors, electro-magnetic brake system, cabin,
control panel, wire rope, ladder, motorised cable
reeling drum, lifting beam etc. with all accessories for
operating spillway stop log gate elements including
cost and conveyance of all materials, machinery and
labour, cutting,bending, aligning, anchoring, welding,
finishing etc. including rail track, lifting beam as per
specifications with all leads, lifts and other general and
incidental charges are completed for finished item of
work as directed by the engineer-in-charge

As per statement enclosed


MT
2 cleaning gantry crane components to expose fresh
metal surface for painting by sand blasting method as
per specifications including cost of all materials,
labour, machinery, scaffolding etc., complete with
initial lead for sand up to 1km and all lifts
Area at the rate of 18 sqm/MT
Total Area = 58.003x18 = 1044.054 sqm

SQ.M

52.37 146243

1050

307

7658746

322350

57.500

1035.00

146243

8408956

307

317744

Qty

Rate/
Unit

3 Painting structurals on sand blasted surfaces with two


coats of zinc phosphate primer (airless spray preferred
40 microns/coat and one coat 65 +/- 5 of alkalyd
based micaceous iron oxide paint followed by two
coats of synthetic enamel paint 25 microns/coat cost
of materials, labour, scaffolding etc., complete with all
leads and all lifts
SQ.M

1050

204

214200

1035.00

204

211140

21.59

6371.00

137552

4 RCC M- 25Nominal mix (Cement:fine aggregate:


coarse aggregate) corresponding to Table 9 of IS 456
using 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges,
sales & other taxes on all materials including all
operational, incidental and labour charges such as
machine mixing, laying concrete, curing etc.,complete
but excluding cost of steel and its fabrication charges
for finished item of work, but excluding centering,
shuttering. (Page No.664) BLD CSTN-3-13 S.No.30.

Pedestals over pier & abutment &Dogging beams


Cum

5 PCC M- 25 Nominal mix (Cement:fine aggregate:


coarse aggregate) corresponding to Table 9 of IS 456
using 20mm size graded machine crushed hard
granite metal (coarse aggregate) from approved
quarry including cost and conveyance of all materials
like cement, fine aggregate (sand) coarse aggregate,
water etc., to site and including Seigniorage charges,
sales & other taxes on all materials including all
operational, incidental and labour charges such as
machine mixing, laying concrete, curing
etc.,complete , but excluding centering, shuttering.

spillway bridge rail concrete


Cum
6 Supplying, fitting and placing HYSD bar reinforcement
(Fe 415) in substructure complete as per drawings and
technical specification Clauses 1002, 1005, 1010 &
1202 MORD / Sections 1600 & 2200 MORTH for Bars
below 36 mm dia including over laps and wastage,
where they are not welded.

pedestals under rail girder


7 Supplying, fitting and placing with MS bar
reinforcement in substructure complete as per
drawings and technical specification Clauses 1002,
1005, 1010 & 1202 MORD / Sections 1600 & 2200
MORTH for Bars below 36 mm dia including over laps
and wastage, where they are not welded.

pedestals under rail girder


Total
Provision for Design charges @ 2% on 9187270

2.07

6272.00

12955

MT

0.3696

54479

20133

MT

0.011719

52490

615

8195296

9109096
182182

LS.PROVISIONS
9 Provision
10 Provision
11 Provision
Provision
12 Provision

for
for
for
for
for

VAt @ 4% on 8195296
Revised VAt @ 5% on 9187270
Labour cess @ 1% 8195296
Labour cess @ 1% 9187270
tender publication charge

Grand Total

327812
455455
81953
27939

91091
27939

8633000

9865762

RAMPACHODAVARAM (M), E.G.Dist

obables
Amount
in Rs

Excess Less Remarks

14.2797

NAME OF THE WORK: SUPPLY AND ERECTION OF GANTRY CRANE TO OPERATE STOP LOG GATES OF BHUPATHIPALEM RESERVOIR SCHEME, RAMPAC

S.No Item of work

unit

As per Approved
drawing

Qty

S.No Item of work

Weight

U/S GANTRY GIRDER

U/S GANTRY GIRDER

Drawing No.211/1

Drawing No.211/1

Abutment pier/vent

Abutment pier/vent

ISMC 300X90 - 13875 LG

639.60

1A ISMC 300X90 - 13875 LG


3 Plate 730x10 - 13875 LG

1
2

639.60
1272.20

ISMC 300X90 - 13830 LG (box grider one side channel)

1A ISMC 300X90 - 13830 LG (box grider other side channel)


3 Plate 730x10 - 13830 LG(box grider both sides plates )

As p

Qty

Weight

495.11

1
2

495.11
1585.06

617.45

164 pairs

229.60

45 Kg/m RAIL - 13575 LG

610.70

45 Kg/m RAIL - 13830 LG(Rail on the box grider )

5a

Plate 100x25 - 150 LG

52

153.00

5a

Plate 100x25 - 150 LG (Rail cleats)(Total Rail)

Plate 200x8 - 300 LG

20

67.60

Plate 200x8 - 300 LG (Inside the box grider web support end )

20

75.36

Plate 300x8 - 715 LG

13

134.70

Plate 300x8 - 715 LG(Inside the box grider middle end support )

13

175.12

Plate 100x8 - 300 LG

22.60

Plate 100x8 - 300 LG(Base plate vertical support)

12.06

10

Plate 360x20 - 520 LG

88.10

10

Plate 350x20 - 520 LG (Base plate)

57.15

11

Plate 380x20 - 540 LG

96.60

11

Plate 380x20 - 540 LG (Base plate)

64.43

12

Plate 100x10 - 100 LG


ROD 32 - 750- LG with M30 2 Nut
& 2 Washer

12

15.70

12

Plate 100x10 - 100 LG (Base plate)

12

9.42

20

90.00

13

ROD 32 - 750- LG with M30 2 Nut & 2 Washer

20

90.00

13

14

L75x75x8 - 150 LG

11.90

14

L75x75x8 - 150 LG (Fixing angle box grider and channel under


the foot bridge corner angle )

15

M16x58LG HEX BOLT WITH NUT


& WASHER

36

5.00

15

M16x58LG HEX BOLT WITH NUT & WASHER

16

ISMC 150X75 - 680 LG

102.70

16

ISMC 150X75 - 680 LG (Support for the foot bridge over the
checked plate )

100.37

17

CHQD PL 520X6 - 13875 LG

340.00

17

CHQD PL 520X6 - 13830 LG ( over the foot bridge along the u/s
Grider )

338.72

19

L 65X65X6 - 13875 LG

80.30

19

80.21

21

L 65X65X6 - 1250 LG

65.20

21

L 65X65X6 - 13830 LG(over the foot bridge along with checked


plate )
L 65X65X6 - 1250 LG (vertical post for railing)

65.25

22

FL 50X8 - 13125 LG

41.00

22

FL 50X8 - 13830 LG (Railing support flat)

43.42

24

32 NB PIPE(L) - 14725 LG

48.40

24

32 NB PIPE(L) - 13830 LG (Railing support pipe )

42.87

26

PL 100X20 - 540 LG

8.40

26

PL 100X20 - 540 LG (Top base plate)

8.48

27

PL 270X20 - 560 LG

23.70

27

PL 270X20 - 560 LG (Base plate in concrete)

23.74

30

ISMB 300X140 - 600 LG

27.60

30

ISMB 300X140 - 600 LG(Rail end support)

26.52

9
REMOVED

4584.60
TOTAL WT IN KGS 4875.5 X 2

12.02

4647.47

9750.00

TOTAL WT IN KGS X 2
1
1
2

456.09
456.09
1168.11

568.78

2
2a
4

Intermediate pier/vent
ISMC 300X90 - 12740 LG
ISMC 300X90 - 12740 LG
Plate 730x8 - 12740 LG

1
1
2

462.40
462.40
1168.10

2
2a
4

Intermediate pier/vent
ISMC 300X90 - 12740 LG
ISMC 300X90 - 12740 LG
Plate 730x8 - 12740 LG

45 Kg/m RAIL - 12750 LG

573.60

45 Kg/m RAIL - 12740 LG

6a

PL 100X25 - 150LG

50

147.10

PL 200X8 - 300LG

16

60.10

Plate 100x25 - 150 LG (Rail cleats)

PL 200X8 - 300LG (INSIDE THE BOX GRIDER -STIFFNERS)

9294.94

Included in
abutment
16

60.29

PL 300X8 - 715LG

80.80

PL 300X8 - 715LG(INSIDE THE BOX GRIDER -STIFFNERS)

107.76

PL 100X8 - 300LG

15.00

PL 100X8 - 300LG (BASE PLATE SIDE STIFFNERS)

15.07

10

PL 360X20 - 520 LG

58.70

10

PL 350X20 - 520 LG (TOP BASE PLATE )

57.15

11

PL 380X20 - 540 LG

64.40

11

PL 380X20 - 540 LG (BASE PLATE IN CONCRETE)

64.43

12

PL 100X10 - 100 LG
ROD 32 - 750- LG with M30 2 Nut
& 2 Washer

16

12.50

12

PL 100X10 - 100 LG (Anchor bolt base plate )

16

12.56

16

72.00

13

ROD 32 - 750- LG with M30 2 Nut & 2 Washer (Anchor bolts )

16

72.00

14

L75X75X8 - 150LG

10.60

14

L75X75X8 - 150LG (Corner angle b/t box grider and channel)

10.68

15

M16X58 LG HEX BOLT WITH


NUT & WASHER

32

4.10

15

M16X58 LG HEX BOLT WITH NUT & WASHER

16

ISMC 150X75 - 680LG

91.30

16

ISMC 150X75 - 680LG(Support for the foot bridge over the


checked plate )

89.22

18

CHQDPL520X6 - 12740 LG

312.00

18

CHQDPL520X6 - 12740 LG( over the foot bridge along the u/s
Grider )

312.03

20

L 65X65X6 - 12750 LG

73.80

20

73.89

21

L 65X65X6 - 12750 LG

58.00

21

L 65X65X6 - 12740 LG(over the foot bridge along with checked


plate )
L 65X65X6 - 1250 LG(vertical post for railing)

58.00

23

FLAT 50X8 - 12750 LG

40.00

23

FLAT 50X8 - 12740 LG(Railing support flat)

40.00

25

32NB PIPE(L) - 12750 LG

40.00

25

32NB PIPE(L) - 12740 LG(Railing support pipe)

39.49

26

PL 100X20 - 540 LG

16.90

26

PL 100X20 - 540 LG (BASE PLATE )

16.96

27

PL 270X20 - 560 LG

47.40

27

PL 270X20 - 560 LG (Base plate under the concrete)

47.48

28

PL 200X10 - 200LG

6.20

28

PL 200X10 - 200LG (grider boxes joint plates )

6.28

29

M16X58 LG HEX BOLT WITH


NUT & WASHER

1.20

29

M16X58 LG HEX BOLT WITH NUT & WASHER boxes joint


plate bolts )

1.20

31

PL 200X10 - 200LG

6.20

31

PL 200X10 - 200LG

32

ISA 100X100X10 - 1426 LG

32

ISA 100X100X10 - 675 LG

13

Removed

Removed
9

90.52

33

ISMC 100X75 - 1440 LG

33

ISMC 100X75 - 1500 LG

3884.80

96.60
3920.68

TOTAL WT IN KGS 4X4172.6

15539.20

TOTAL WT IN KGS 4X4172.6

15682.71

TOTAL WT OF DRG 211/1

25289.20

TOTAL WT OF DRG 211/1

24977.64

TRACK ASSEMBLY ON T-BEAM

TRACK ASSEMBLY ON T-BEAM

Drawing No.211/2

Drawing No.211/2

45 Kg/m RAIL yard- 75450 LG

3395.30

45 Kg/m RAIL yard- 75850 LG (Rail length on bridge )

3386.35

PL 180X16 - 300 LG

151

640.00

PL 180X16 - 300 LG (Rail support bottom plate )

153

994.50

16 ROD WITH M20 NUTS - 2Nos


+ 2 WASHER - 500 LG

302

302.00

16 ROD WITH M20 NUTS - 2Nos + 2 WASHER - 500 LG

PL 100X16

302

237.00

PL 100X16 (Rail cleates )

PL 50X25 - 85 LG C/S

326

271.90

PL 50X25 - 85 LG C/S

Removed

PL 350X20 - 350 LG

38.50

PL 350X20 - 350 LG

Removed

25 DIA ANCHOR ROD 750L WITH


NUTS & WAHSERS

12

30.90

25 DIA ANCHOR ROD 750L WITH NUTS & WAHSERS

Removed

PL 100X16 - 100 LG

12

15.10

PL 100X16 - 100 LG

Removed

PL 300X10 - 250 LG

39.30

PL 300X10 - 250 LG(Rail end support base plate)

11.78

10
11

ISMB 300X140 - 600 LG


PL 120X10 - 300 LG

2
8

56.10
37.40

10
11

ISMB 300X140 - 600 LG(Rail end support)


PL 120X10 - 300 LG(Rail end support stiffner)

2
4

53.04
11.30

12

PL 170X10 - 350 LG

9.40

12

PL 170X10 - 350 LG

Removed
153 pairs

Removed

214.20

13

HEX BOLT M16X150 LG WITH


N&W( FOR FIXING WOODEN
STOPPER BUFFER)

0.90

13

HEX BOLT M16X150 LG WITH N&W (wooden stopper buffer


fixing bolts)

0.90

14
15

WOOD 200X200X100
PL 300X16 - 300 LG

2
6

13.00
42.40
5129.20
5129.20

14
15

WOOD 200X200X100
PL 300X16 - 300 LG

2
2

13.00
22.61
4707.68
4707.68

2
2
2
2

344.71
202.40
376.05
376.05

158.26

104

30.27

4
4
7
6
16
2
18 pairs

52.75
60.29
80.89
37.68
14.47
390.65
25.20

TOTAL WT IN KGS

TOTAL WT IN KGS

1
2
3
3a

DETAILS OF RAIL GIRDER & TIE


BEAM
Drawing No.212
RAIL GIRDER
PL 440x10 - LG 4986
PL 440x10 - LG 2930
PL 480x10 - LG 4986 (c/s)
PL 480x10 - LG 4986

2
2
2
2

344.30
202.40
375.60
372.80

1
2
3
3a

Drawing No.212
RAIL GIRDER
PL 440x10 - LG 4990 (Top plate)
PL 440x10 - LG 2930 (Bottem plate )
PL 480x10 - LG 4990 (c/s) (side plate)
PL 480x10 - LG 4990 (side plate)

PL 700X12 - LG 600 LG

158.30

PL 700X12 - LG 600 LG (Leg joint plate )

M20X70 LG HEX FIT BOLTS IS


3640 WITH NUT & WASHER

112

32.60

M20X70 LG HEX FIT BOLTS IS 3640 WITH NUT & WASHER

6
7
7a
7b
8
9
10

PL 400X8 - LG 420
PL 400X8 - LG 480
PL 400X8 - LG 460
PL 250X8 - LG 400
PL 90X8 - LG 160
45 Kg/m RAIL - 3870 LG
PL 100X25 - 150 LG (c/s)

4
4
8
8
16
2
26

42.20
48.20
92.40
50.20
14.50
347.90
76.50

6
7
7a
7b
8
9
10

PL 400X10 - LG 420 (Box inside stiffners)


PL 400X10 - LG 480 (Box inside stiffners)
PL 400X8 - LG 460
PL 250X8 - LG 400
PL 90X8 - LG 160 (Joint support stiffners)
45 Kg/m RAIL - 4375 LG
PL 100X25 - 150 LG (c/s)

11

ISMB 300X140 - 350 LG (c/s)

65.50

11

ISMB 300X140 - 350 LG (c/s) (Rail end support)

61.88

12
13

ISMC 150X75 - 700 LG


ISA 75X75X8 - 150 LG

14
14

191.00
13.30

12
13

ISMC 150X75 - 700 LG (plot form support )


ISA 75X75X8 - 150 LG(corner joint angle)

14
14

160.72
18.69

14

M16X60 LG HEX BOLT WITH


NUT & WASHER

56

6.20

14

M16X60 LG HEX BOLT WITH NUT & WASHER

DETAILS OF RAIL GIRDER & TIE BEAM

Removed

15

ISA 50X50X6 - 1250 LG

14

56.20

15

ISA 50X50X6 - 1250 LG ( vertical post)Hand rail

26

146.25

16

FL 50X8 - 4000 LG

25.10

16

FL 50X8 - 5000 LG(Hand Rail support flat)

94.19

17

32 DIA NB PIPE (L) - 6300 LG

39.60

17

32 DIA NB PIPE (L) - 5000 LG(hand rail support pipe)

31.40

18

ISA 65X65X6 - 4486 LG

52.30

18

ISA 65X65X6 - 4486 LG

19

CHQD PL 670X6 - 4886 LG

319.70

19

CHQD PL 570X6 - 5000 LG(plotform)

268.47

CHQD PL 600X6 -4500 LG (plotform extension

127.17

Removed

2926.80

21

3058.42

TOTAL WEIGHT IN KGS

TOTAL WEIGHT IN KGS

U/S AND D/S TIE GIRDER

U/S AND D/S TIE GIRDER

PL 440X8 - 292 LG

16.10

21

21a PL 440X8 - 276 LG

15.30

22

PL 292X8 - 400 LG

23

PL 400X8 - 700 LG

24

PL 440X8 - 290 LG

16.03

21a PL 440X8 - 275 LG (Tie grider extension plate top)

30.40

36.60

22

PL 290X8 - 400 LG(Tie grider extension plate side)

58.28

70.30

23

PL 400X8 - 700 LG (Tie grider extension plate bottom)

70.34

PL 400X8 - 4000 LG

442.10

24

PL 440X8 - 4000 LG (grider top and bottom plates)

442.11

25

PL 400X8 - 4000 LG

401.20

25

PL 400X8 - 4000 LG (grider both side plates)

401.92

26

PL 400X8 - 380 LG

10

95.40

26

PL 400X8 - 380 LG (Grider box inside stiffners )

10

95.46

27

PL 300X8 - 380 LG

57.20

27

PL 300X8 - 380 LG (side joint plate )

57.27

28

PL 300X8 - 440 LG

66.30

28

PL 300X8 -440 LG (Top joint plate )

66.32

29

PL 250X10 - 300 LG (C/S)

23.50

29

PL 250X10 - 300 LG (C/S) (Dummy plate )

23.55

30

ISA 65X65X8 - 3500 LG

20.30

30

ISA 65X65X8 - 5000 LG

38.50

31

ISA 75X75X6 - 200 LG

6.80

31

ISA 75X75X6 - 200 LG

Removed

32

ISA 50X50X6 - 1250 LG

28.10

32

ISA 50X50X6 - 1250 LG

Removed

33

FL 50X8 - 4400 LG

13.80

33

FL 50X8 - 4400 LG

Removed

34

32 DIA NB PILE(L) - 6700 LG (B/S)

21.10

34

32 DIA NB PILE(L) - 6700 LG (B/S) Railing pipe)

35

M16X50 LG HEX BOLTS WITH


NUT & WASHER

10

1.30

35

M16X50 LG HEX BOLTS WITH NUT & WASHER

Removed

36

M16X60 LG HEX BOLTS WITH


NUT & WASHER

350

54.00

36

M16X60 LG HEX BOLTS WITH NUT & WASHER

Removed

37

M16X50 LG HEX BOLTS WITH


NUT & WASHER

24

3.30

37

M16X50 LG HEX BOLTS WITH NUT & WASHER

Removed

TOTAL WEIGHT IN KGS

1372.70

TOTAL WEIGHT IN KGS

COLUMN DETAILS

COLUMN DETAILS OF RAIL GIRDER & TIE BEAM

Drawing No.213

Drawing No.213

21.04

1321.20

PL 400X8 - 6799 LG (C/S)

341.60

PL 400X8 - 6799 LG (C/S) [6680] (Colum box side plates )

341.58

PL 540/325X8 - 6721 (C/S)

456.00

PL 540/325X8 - 6721 (C/S) [6680](Colum box side plates )

365.10

PL 485X12 - 600LG

27.40

PL 485X12 - 600LG Leg base plate )

27.41

ISA 50X50X6 - 400 LG (C/S)

14.40

ISA 50X50X6 - 400 LG (C/S) (Leg inside strengthinh stiffners)

14.40

ISA 50X50X6 - 500 LG (C/S)

18.00

ISA 50X50X6 - 500 LG (C/S)(Leg inside strengthinh stiffners)

18.00

ISA 50X50X6 - 400 LG (C/S)

16

28.80

ISA 50X50X6 - 400 LG (C/S)(Leg inside strengthinh stiffners)

16

28.80

PL 80X8 - 250 LG (C/S)

16

20.00

PL 80X8 - 250 LG (C/S) (Top & Bottom Leg stiffners )

16

20.10

M16X60 LG FIT BOLTS AS PER


IS:3640

22

4.60

M16X60 LG FIT BOLTS AS PER IS:3640 (Leg fixing bolts )

22

4.60

Scrap Each leg 1 tonn

1000.00

TOTAL WEIGHT

1478.41

TOTAL WT IN KGS X 4
GANTRY TRAVEL
ARRANGEMENT
Drawing No.214

5913.63

GANTRY TRAVEL ARRANGEMENT


Drawing No.214

WORM REDUCER '0' TYPE 5"

204.00

WORM REDUCER '0' TYPE 5"

203.20

150 A.C.EM - BRAKE

36.00

150 A.C.EM - BRAKE

27.80

150 BRAKE DRUM COUPLING

13.00

150 BRAKE DRUM COUPLING

32.60

3 HP MOTOR

150.00

100.20

PLUMMER BLOCK SNA 512 TC

19.20

3 HP/2.2 kw MOTORs
PLUMMER BLOCKs SNA 512 with bearingis 22211 and
sleeaves 312-SNA 512 TC

24.90

130X130X10 - 275 LG

13.30

130X130X10 - 275 LG (120x110x10 required cutting)

21.67

8
9
10

PL 80X8 - 120 LG
PL 495X10 - 1200 LG
PL 280X30 - 330 LG

4
2
2

2.40
39.40

8
9
10

PL 80X8 - 100 LG
PL 550X10 - 1200 LG
PL 280X30 - 360 LG

4
2
2

2.01
103.62
47.48

11

SHIM PL - 280X5.9 - 300 LG

7.60

11

SHIM PL - 280X5.9 - 300 LG

Removed

12

PL 160X10 - 445 LG

22.20

12

PL 160X10 - 445 LG

Removed

13

PL 148X10 - 445 LG

10.20

13

PL 148X10 - 445 LG

Removed

14

PL 148X10 - 75 LG

3.40

14

PL 148X10 - 75 LG

Removed

15

PL 240X10 - 365 LG

27.40

15

PL 240X10 - 365 LG

Removed

16

PL 167X10 - 365 LG

8.80

16

PL 167X10 - 365 LG

Removed

17

PL 95X10 - 157 LG

4.60

17

PL 95X10 - 157 LG

Removed

18

PL 130X16 - 350 LG
PL 110X10 - 130 LG
PL 300X8 - 540 LG

4
2
6

22.86
2.25
61.04

M20X100 LG HEX BOLT NUT & WASHER(worm reducer base


plate fixing bolts)

0.50

18

PL 300X8 - 535 LG

19

M20X100 LG HEX BOLT NUT &


WASHER

0.50

19

21
22
23
24

M10X65 LG HEX BOLT NUT &


WASHER
ISMC 300X90 - 9300 LG
PL 445X8 - 6900 LG
CHQD PL 445X6X6900
PL 300X8 - 285 LG

25

ISA 65X65X6 - 300 LG

13.00

25

ISA 65X65X6 - 300 LG (Bogii end corner ancle)

26

PL 65X8 - 283 LG

9.30

26

PL 65X8 - 283 LG

20

28

M10X35 LG HEX BOLT NUT &


WASHER
PL - 300X10 - 455 LG

29

16

1.20

20

M8X65 LG HEX BOLT NUT & WASHER

16

1.00

4
2
2
12

1350.40
385.60
163.50

21
22
23
24

ISMC 300X90 - 9330 LG


PL 445X8 - 6900 LG
CHQD PL 445X6X6900
PL 300X8 - 285 LG (Bogiee inside stiffner )

4
2
2
12

1336.06
385.65
289.24
64.43

13.92

42.80

28

M10X35 LG HEX BOLT NUT & WASHER (end cover fixing


bolts )
PL - 300X10 - 460 LG (bogiee end cover )

200X50 - 200 LG (RUBBER)

57.60

29

30

M12X60 LG SCREWS

16

13.50

31

PL - 220X10 - 220 LG

32

PL - 60X10 - 180 LG

16

33

M16X36LG HEX SCREW WITH


SPRING WASHER

34

27

24

27

Removed

24
4

43.33

200X50 - 200 LG (RUBBER)

8.80

30

M12X60 LG SCREWS (Buffer stopper screws)

16

31

PL - 220X10 - 220 LG (Roller pin locking plate ) bogiee

30.40

13.50

32

PL - 60X10 -180 LG Roller lock plate )

16

13.56

32

1.80

33

M16X36LG HEX SCREW WITH SPRING WASHER (Lock


plate fixing bolts )

32

1.80

100 - 365 LG ROUND

89.00

34

100 - 370 LG ROUND ( long travel pins )

85.00

35

SPACER OD=200;ID=131; 8 THK

10.00

35

SPACER OD=200;ID=131; 8 THK

4.51

36

SPACER OD=200;ID=131; 93 THK

31.30

36

SPACER OD=200;ID=100; 95 THK

33.60

37

6 GREASE NIPPLE
M16X65 LG HEX BOLT NUT &
WASHER

37

38

6 GREASE NIPPLE
M16X65 LG HEX BOLT NUT & WASHER (Plumber block
fixing bolts )

PL 80X10 - 485 LG

16

38

39

39
2744.50

PL 80X10 - 485 LG

Removed
2961.43

GANTRY TRAVEL WHEEL


ASSEMBLY
Drawing No.215

GANTRY TRAVEL WHEEL ASSEMBLY


Drawing No.215

GEARED WHEEL (DRIVE END)

330.00

GEARED WHEEL (DRIVE END) with Bronze bush

349.70

PLAIN WHEEL (NON DRIVE


END)

300.00

PLAIN WHEEL (NON DRIVE END) with Bronze bush

341.30

BUSH OD-120 , ID-100 ,--180

38.00

BUSH OD-120 , ID-100 ,--180

GRUB SCREW M8 X 20 LG

24

1.00

GRUB SCREW M8 X 20 LG

24

1.00

GEAR WHEEL
M20X 80 LG FIT BOLT AND
SPRING WASHER
PINION (AS NOTED)
80 X 850LG

104.00

GEAR WHEEL

114.10

1.20

M20X 80 LG FIT BOLT AND SPRING WASHER

1.20

2
2

19.20
24.40
817.80

7
8

PINION
80 X 850LG (Gear to warm reducer shaft )

2
2

29.40
32.90
869.60

6
7
8

DETAILS OF CT WHEEL
ASSEMBLY
Drawing No.216

Already
included

DETAILS OF CT WHEEL ASSEMBLY


Drawing No.216

DRIVE END ASSEMBLY

DRIVE END ASSEMBLY

CRANE WHEEL (GEAR SIDE)

146.00

CRANE WHEEL (GEAR SIDE) with bronze bush

144.60

GEAR WHEEL (AS NOTED)

36.00

GEAR WHEEL

32.80

HEX BOLT M65 X 65 LG FIT


BOLT & SPRING WASHER

1.50

HEX BOLT M65 X 65 LG FIT BOLT & SPRING WASHER


(Fixing gear wheel to penion)

1.50

GRUB SCREW M8 X 15 LG

16

GRUB SCREW M8 X 15 LG

16

BUSH OD-120 , ID-90 ,LG-140

11.00

Bronze BUSH OD-120 , ID-90 ,LG-140

Already
included

OD-130, ID-91, TH-70

6.50

OD-130, ID-91, TH-70 (Speacers )

6.85

7
8
9
10

ROUND 60 X 515 LG
KEY 14X9-70LG
PINION (AS NOTED)
KEY 12X8-60LG

2
2
2
2

22.80

ROUND 60 X 515 LG
KEY 14X9-70LG
PINION
KEY 12X8-60LG

2
2
2
8

18.70

19.40
-

7
8
9
10

11

SNA 511 TC PLUMMER BLOCK


WITH 2211 K BEARING H-311
SLEEVE

17.40

11

SNA 511 TC PLUMMER BLOCK WITH 2211 K BEARING


H-311 SLEEVE

37.35

12

PL 70X10-220LG

4.80

12

PL 80X10-260LG (plumber block housing plate )

9.80

14
15

90 X309 LG ROUND
6 GREASE NIPPLE

2
2

30.00
-

14
15

90 X309 LG ROUND
6 GREASE NIPPLE

2
6

29.00

16

OD-130, ID-91, TH-13

1.60

16

OD-130, ID-91, TH-13


Plumber blocks fixed bolts

DRIVE END ASSEMBLY WT.


IN.KGS

DRIVE END ASSEMBLY WT. IN.KGS

NON-DRIVE END ASSEMBLY

NON-DRIVE END ASSEMBLY

6.90

Removed
12
287.50

GRUB SCREW M 8 X 15

16

GRUB SCREW M 8 X 15

14
15
16

90 ROUND - 309 LG
6 GREASE NIPPLE
OD-130, ID-91, TH-13

2
2
2

30.00
1.60

14
15
16

90 ROUND - 309 LG
6 GREASE NIPPLE
OD-130, ID-91, TH-13

17

BUSH OD-120 , ID-90 ,LG-130

11.00

17

BUSH OD-120 , ID-90 ,LG-130

18

CRANE WHEEL PLAIN

120.00

18

CRANE WHEEL PLAIN with bronze

135.30

19

OD-130, ID-91, TH-13

7.40

19

OD-130, ID-91, TH-70

6.85

NON-DRIVE END ASSEMBLY WT.


IN KGS

NON-DRIVE END ASSEMBLY WT. IN KGS

Removed
2
2
2

29.00
1.38

Below
included

165.68

DETAILS OF CRAB FRAME &


CROSS TRAVEL ARRANGEMENT

DETAILS OF CRAB FRAME & CROSS TRAVEL


ARRANGEMENT

Drawing No.218

Drawing No.218

ISMB 600 X 210 - 4712 LG

1146.80

ISMB 600 X 210 - 4720 LG

1157.34

2
3
4

ISMC 200 X 80 - 4712 LG


ISMC 250 X 82 - 2000 LG
PL 290X12-370 LG

2
4
4

208.00
244.70
40.50

2
3
4

ISMC 200 X 80 - 4712 LG


ISMC 250 X 82 - 2000 LG
PL 250X12-390 LG

2
4
4

208.62
243.20
36.74

ISA 75X75X6 - 250LG

13.60

ISA 75X75X6 - 250LG (Inside end corner angle )

13.60

PL 75X8-210 LG

15.00

PL 75X8-210 LG

M12 X 70 LG HEX BOLT , NUT &


WASHER

16

1.50

M12 X 70 LG HEX BOLT , NUT & WASHER (Rubber fixing


bolts)

16

1.50

RUBBER-200 X 50 - 200LG

RUBBER-200 X 50 - 200LG

8.80

M16 X 50 LG HEX BOLT , NUT &


WASHER

24

3.30

M16 X 50 LG HEX BOLT , NUT & WASHER(End bogiee cover


fixing plates )

24

3.30

10

CHQDPL 210X6-1200 LG

26.70

10

CHQDPL 210X6-1200 LG

11
12
12a
13
13A
14

PL 210X10-250LG
ISMC 400X100-1088LG
ISMC 300X90-1088 LG
ISMC 250 X 80 - 430 LG
ISMC 250 X 80 - 470 LG
PL 500X20-1582 LG

6
2
2
4
5
2

25.70
109.20
93.00
63.60
71.10
248.30

11
12
12a
13
13A
14

PL 210X10-250LG (Bogiee stiffners)


ISMC 400X100-1080LG
ISMC 300X90-1080 LG
ISMC 250 X 80 - 430 LG (stiffners )
ISMC 250 X 80 - 470 LG
PL 500X20-1580 LG

6
2
2
7
5
2

25.91
106.27
77.33
91.50
71.44
248.06

15

90X300 LG PIN (AS NOTED )

37.00

15

90X300 LG PIN (for bottom block)

42.00

16
17

PL 200X10-200 LG
PL 50X10-170 LG

6
12

22.00
9.50

16
17

PL 200X10-200 LG (pully support plate )


PL 50X10-170 LG (pully lock plates )

6
12

18.84
8.01

18

M16 X 45 LG HEX SCREW WITH


SPRING WASHER

45

5.20

18

M16 X 45 LG HEX SCREW WITH SPRING WASHER

Removed

19

ISA 75X75X8 - 150LG

10

13.40

19

ISA 75X75X8 - 150LG

Removed

Removed

Already incuded

20

ISA 50X50X6-1250 LG

10

56.20

20

ISA 50X50X6-1250 LG

Removed

21

32 DIA NB PIPE(L) - 6500 LG

33.50

21

32 DIA NB PIPE(L) - 6500 LG

Removed

22

FL 50X5 - 4650 LG

18.20

22

FL 50X5 - 4650 LG

Removed

23

ISA 65X65X6-4650 LG

54.00

23

ISA 65X65X6-4650 LG

Removed

24

M16 X 50 LG HEX BOLT , NUT &


WASHER

20

1.40

24

M16 X 50 LG HEX BOLT , NUT & WASHER

Removed

25

CHQDPL 400X6-1625 LG

70.20

25

CHQDPL 400X6-1625 LG

Removed

26

CHQDPL 470X6-5070 LG

126.60

26

CHQDPL 470X6-5070 LG

Removed

26a CHQDPL 470X6-1050 LG

53.20

26a CHQDPL 470X6-1050 LG

Removed

27
28
29

OD-200, ID-91, 8 TH
ID=92,OD=110 - 118 LG
6 GREASE NIPPLES

3
3
3

5.90
24.10
-

27
28
29

OD-200, ID-91, 8 TH (spacers)


ID=90,OD=110 - 120 LG (pulley spacers )
6 GREASE NIPPLES

3
3
3

30

SHAFT 50 - 2394 LG

37.50

30

SHAFT 50 - 2400 LG (C.T. Motar line shaft )

4.69
7.80

59.70
31

SHAFT 50 - 1494 LG

23.60

31

SHAFT 50 - 1494 LG (C.T. Motar line shaft )

32

WORM REDUCER 'O' TYPE 4"

65.00

32

WORM REDUCER 'O' TYPE 4" (cross travel )

70.90

33

150 BRAKE DRUM COUPLING

6.60

33

150 BRAKE DRUM COUPLING

16.40

34

150 EM BRAKE (AS NOTED )

18.00

34

150 EM BRAKE

13.80

35

1.5HP MOTOR (AS NOTED)

34.00

35

1.5 KW / 2 HP MOTOR

16.70

36

FLEXI COUPLING TO SUIT 50

20.00

36

FLEXI COUPLING TO SUIT 50 Shaft

42.50

37

SNA 511 TC PLUMMER BLOCK


WITH 2211K BEARING H - 311

214.50

37

SNA 511 TC PLUMMER BLOCK WITH 2211K BEARING H


- 311

10.25

38

ISMC 150X75 - 460LG

15.40

38

ISMC 150X75 - 460LG

15.09

39

PL 270X12 - 320LG

8.10

39

PL 270X12 - 320LG

Removed

40

PL 125X41 - 400 LG

18.00

40

PL 125X41 - 400 LG

Removed

41

PL 200X10-210 LG

3.30

41

PL 200X10-210 LG

Removed

42

PL 82X8 - 86 LG

0.80

42

PL 82X8 - 86 LG

Removed

43

PL 62X8 - 210 LG

1.00

43

PL 62X8 - 210 LG

Removed

44

PL 225X10 - 230LG

4.06

44

PL 225X10 - 230LG

Removed

45

PL 190X8 - 275 LG

3.20

45

PL 190X8 - 275 LG

Removed

46

M10X50 LG HEX BOLT NUT &


WASHER

0.80

46

M10X50 LG HEX BOLT NUT & WASHER

0.80

47

M20X40 LG HEX BOLT NUT &


WASHER

1.60

47

M20X40 LG HEX BOLT NUT & WASHER

1.60

TOTAL WEIGHT IN KGS

TOTAL WEIGHT IN KGS

DETAILS DRIVE UNIT


ASSEMBLY(HOIST)
Drawing No.219

2622.69

DETAILS DRIVE UNIT ASSEMBLY(HOIST)


Drawing No.219

WORM REDUCER (AS NOTED)


10"

236.00

WORM REDUCER (AS NOTED) 10"

353.10

250 EM BRAKE (AS NOTED )

30.00

250 EM BRAKE (AS NOTED )

35.40

250 BRAKE DRUM COUPLING

13.20

250 BRAKE DRUM COUPLING

37.50

14 HP MOTOR

125.00

14 HP MOTOR

137.20

5
6

ISMC 150X75-1480 LG
ISMC 150X75-700 LG

1
1

2
2

44.60
21.80

5
6

ISMC 150X75-1470 LG
ISMC 150X75-700 LG

2
2

48.22
22.96

SHIM 625X3.5-480 LG

7.90

SHIM 625X3.5-480 LG

PL 625X20 - 480 LG

28.80

PL 620X20 -480 LG(Reducer base plate )

Removed
1

46.72

PL 70X10X70 LG (C/S)

1.60

PL 70X10X70 LG (C/S)

Removed

10

PL 70X10 - 352LG (C/S)

3.00

10

PL 70X10 - 352LG (C/S)

Removed

11

ISA 75X75X8 - 550 LG

8.90

11

ISA 75X75X8 - 550 LG (Reducer base plate support )

12

PL 200X12 - 530 LG

9.40

12

PL 200X12 - 530 LG

Removed

13

ISA 75X75X8 - 470 LG

8.40

13

ISA 75X75X8 - 470 LG

Removed

14

PL 150X18 - 230 LG (C/S)

1.50

14

PL 150X18 - 230 LG (C/S)

Removed

15

ISA 75X75X8 - 550 LG

8.90

15

ISA 75X75X8 - 550 LG (Motar base plate support )

16

PL 70X10 -137 LG

1.90

16

PL 70X10 -137 LG

17

PL 400X12 -350 LG (C/S)


HEX BOLT M30 - 85 LG NUT &
WASHER

13.20

17

13.19

1.50

18

PL 400X12 -350 LG (C/S) (Motar base plate )


HEX BOLT M25 - 150 LG NUT & WASHER ( Reducer base
plate fixing bolts)

0.50

19

FLANGE COUPLING 75

84.00

19

FLANGE COUPLING 75

12.10

20

HEX BOLT M-14

20
21

HEX BOLT M-14


PL 180X20 -550 LG (EM Brake base plate )
HEX BOLT M10 - 75 LG NUT & WASHER ( EM Brake base
plate fixing bolts)
TOTAL WEIGHT

4
1

0.45
15.54

18

22
TOTAL WEIGHT
DETAIL OF GEAR BOX
ASSEMBLY
Drawing No.220

9.79

9.79

Removed

4
742.46

DETAIL OF GEAR BOX ASSEMBLY


Drawing No.220

ISMC 400X100 - 1350 LG

67.60

ISMC 400X100 - 1350 LG (Rope drum frame one side )

66.69

ISMC 400X100 - 1150 LG

55.10

ISMC 400X100 - 1100 LG ((Rope drum frame other side )

54.34

3
4
5

ISMC 400X100 - 950 LG


ISMC 400X100 - 940 LG
ISMC 400X100 - 160 LG

1
1
1

47.50
47.00
8.00

3
4
5

ISMC 400X100 - 950 LG


ISMC 400X100 - 940 LG
ISMC 400X100 - 160 LG

1
1
1

46.44
46.93
7.90

6
7
8

ISMC 400X100 - 500 LG


PL 90X10 - 500 LG
PL 90X10 - 1350 LG

1
1
1

25.10
3.50
9.50

6
7
8

ISMC 400X100 - 500 LG


PL 90X10 - 400 LG
PL 90X10 - 1350 LG

1
1
1

24.70
2.83
9.54

PL 190X8 - 390 LG (C/S)

23.30

PL 190X8 -390 LG(C/S) ISMC Stiffners )

23.27

10

PL 90X8 - 390 LG (C/S)

6.60

10

PL 90X8 - 390 LG (C/S)ISMC Stiffners )

6.61

11

PL 350X20 - 640 LG (C/S)

70.30

11

PL 350X20 - 640 LG (C/S)(Rope drum pin )

70.34

12

PL 100X10 - 280 LG

4.40

12

PL 100X10 -280 LG(Rope drum lock pin )

4.40

13

M16 X 40 LG HEX SCREW WITH


SPRING WASHER

16

3.00

13

M16 X 40 LG HEX SCREW WITH SPRING WASHER (Lock


plate fixing bolts )

16

3.00

14

PL 95X10 - 75LG

1.20

14

PL 95X10 - 75LG (Rope drum shaft stiffners )

1.12

15

PL-OD=200,ID=82 , 8MM THICK

3.00

15

PL-OD=200,ID=82 , 8MM THICK

Removed

16

SHIM 90X5 - 315 LG

2.00

16

SHIM 90X5 - 315 LG

Removed

17

PL 100X25 - 350 LG

13.70

17

18

PLUMMER BLOCK SNA 516

18.00

18

PL 100X25 - 350 LG (Moter support )


PLUMMER BLOCK SNA 516 with bearing No 22216 and
sleeave No 316

19

HEX BOLT M20 & WASHER

4.00

19

HEX BOLT M20 -75 LG


block fixing bolts )

20

HEX BOLT M20 X 85 LG NUT &


WASHER

13

5.50

20

HEX BOLT M20 X 85 LG NUT & WASHER

21

WIRE ROPE 20 - SUFFICIENT

10

270.40

21

WIRE ROPE 20 - SUFFICIENT (6/36)

89.95

22

80 ROUND - 1150 LG

45.30

22

80 ROUND - 1150 LG

41.85

23

80 ROUND - 708.5 LG

29.50

23

80 ROUND - 708.5 LG

22.30

24
25

KEY - 22X14 - 110 LG


KEY - 20X12 - 130 LG

1
1

0.10
0.20

24
25

KEY - 22X14 - 110 LG


KEY - 20X12 - 130 LG
TOTAL WEIGHT

1
1

LG HEX NUT

LG HEX NUT & WASHER (Plumber

13.74

22.95

1.20

Removed

560.08

TOTAL WEIGHT IN KGS X 2


DETAILS OF ROPE DRUM

DETAILS OF ROPE DRUM

Drawing No.221

Drawing No.221

1120.16

ROPE DRUM (AS NOTED) LH

280.00

ROPE DRUM WITH BRONZEES

240.55

ROPE CLAMP - 70X20 - 120 LG

2.60

ROPE CLAMP - 70X20 - 120 LG

2.25

M10 - 80 LG HEX SCREW WITH


SPRING WASHER

1.60

M10 - 80 LG HEX SCREW WITH SPRING WASHER

1.60

M16 FIT BOLTS IS:3640 WITH


SPRING WASHER - 65 LG

0.90

M16 FIT BOLTS IS:3640 WITH SPRING WASHER - 65 LG

Removed

BUSH OD=100,ID=80 - 60 LG

1.50

BUSH OD=100,ID=80 - 60 LG

Already
included

TOTAL WEIGHT
TOTAL WEIGHT IN KGS X 2
DETAIL OF WHEEL W1 & PINION
P1
Drawing No.222

244.40
488.80

DETAIL OF WHEEL W1 & PINION P1


Drawing No.222

WHEEL W1 (AS NOTED)

185.00

WHEEL W1 with Bronze bushes

PL 40X16 - 100 LG

3.80

PL 40X16 - 100 LG

Removed

BUSH OD=100,ID=80 - 100LG

2.50

BUSH OD=100,ID=80 - 100LG

Already
Included

M6 - 20LG C.S.K SCREW

12

M6 - 20LG C.S.K SCREW

12

210.75

PINION P1 (AS NOTED)

25.00

PINION P1 (Rope drume )

TOTAL WEIGHT
TOTAL WEIGHT IN KGS X 2
DETAILS OF BOTTOM BLOCK

DETAILS OF BOTTOM BLOCK

Drawing No.223

Drawing No.223

B.O.Q OF BOTTOM BLOCK

B.O.Q OF BOTTOM BLOCK

15.85
226.60
453.20

1
2

PL 750X16 - 1720 LG
PL 220X10 - 220 LG

2
4

324.00
22.80

1
2

PL 750X16 - 1720 LG (Bottom block )


PL 220X10 - 220 LG (Locking pin base plate )

2
4

324.05
15.20

LOCK PLATE 50X10 - 140LG

16

43.10

LOCK PLATE 50X10 - 140LG

16

8.79

PL-222X8 - 525 LG

14.70

PL-225X8 - 560 LG (side bottom block plates )

15.83

PL-180X8 - 210 LG

2.40

PL-180X8 - 210 LG Hook support plate )

4.75

6
7

PL-210X8 - 750 LG
PL - 210X3.15 - 760 LG

1
2

4.60
19.00

6
7

PL-210X8 - 560 LG
PL - 210X3.15 - 760 LG

1
2

7.39
7.89

90 - 310 LG ROUND

29.60

90 - 310 LG ROUND (Bottom block pulley pins )

28.90

10

ROUND 100 - 290 LG (AS


NOTED)

14.50

10

ROUND 100 - 290 LG (Bottom block pulley pins )

33.70

11

SPACER ID=100,OD=220, 8THK

16.50

11

SPACER ID=100,OD=220, 8THK

7.58

12

6 GREASING NIPPLE

12

6 GREASING NIPPLE

13

M16 - 40 LG HEX SCREW WITH


WASHER

40

2.50

13

M16 - 40 LG HEX SCREW WITH WASHER (Lock plate fixing


bolts )

32

2.00

14

PULLEY - 400 PCD (C/S)

167.50

14

PULLEY - 400 PCD (C/S) ( with Bronze Bushs)

310.70

15

PL 220X32 - 220 LG

24.00

15

PL 220X32 - 220 LG

48.63

TOTAL WT IN KGS

685.20

TOTAL WT IN KGS

PULLEY
1a

PULLEY

39.07

1a

815.40

PULLEY

Already
Included

PULLEY

Already
Included

2a

BUSH OD = 115, ID = 90 ; 90 LG

2.79

2a

BUSH OD = 115, ID = 90 ; 90 LG

3a

GRUB SCREW M6X20


TOTAL WT IN KGS

0.03

3a

GRUB SCREW M6X20

DETAILS OF LIFTING BEAM

DETAILS OF LIFTING BEAM

Drawing No.224

Drawing No.224

Already
Included

ISMC 300X90 - 10114 LG

730.60

ISMC 300X90 - 10110 LG (Main frame channel )

723.88

PL 170X12 - 300LG

10

48.00

PL 170X12 - 300LG (joint plates )

10

48.04

PL 100X12 - 250LG

20

47.00

PL 100X12 - 350LG (Channel flange support plate )

20

65.94

ISA 75X75X8 - 350 LG

6.30

PL 50X25 - 350 LG (plate instead of


75 x75 x 8 angle )

6.87

PL 370X10 - 1500 LG

87.20

PL 370X10 - 1500 LG (End roller support plate )

87.14

PL 200X10 - 700 LG

22.00

PL 200X10 - 900 LG (End roller support plate )

28.26

PL 150X10 - 1500 LG

70.70

PL 150X10 - 1500 LG (End roller support inside plate )

13.56

8
9
10

PL 300X12 - 240 LG
PL 150 - 576 LG
PL 200 x 12 THK

2
2
2

13.60
24.40
6.00

8
9
10

PL 300X12 - 240 LG (Hook pin support plate )


150 - 576 LG
PL 200 x 12 THK

2
2
2

56.52
25.70
5.92

11

PL 375X40 - 1000 LG

219.80

11

PL 375X40 - 1000 LG

12

PL 80X80 - 150 LG

16.50

12

PL 80X30 - 150 LG (main hook base plate)

5.65

13

PL OD=180,ID=120, 44 THK

19.50

13

PL OD=180,ID=120, 44 THK (hook support spacer)

19.53

14

BUSH OD=120,ID=80, 128 LG

4.66

14

BUSH OD=120,ID=80, 128 LG (hook support)

12.63

15
16
17
18

PL 50X10 - 120 LG
M6 GREASE NIPPLE
80 - 240 LG ROUND
PL 350X16 - 720 LG

16
3
2
2

7.50

PL 50X10 - 120 LG (hook lock plate)


M6 GREASE NIPPLE
80 - 240 LG ROUND (hook roller pin)
PL 350X16 - 720 LG (equal plates)

16
3
2
2

7.54

22.64
63.30

15
16
17
18

16.50
63.30

19

PL OD=250,ID=60, 32 THK

11.70

19

PL OD=250,ID=60, 32 THK (spacer between equal plates)

11.62

Removed

20

PL OD=150,ID=31, 16THK

12.90

20

PL OD=150,ID=31, 16THK (spacer)

12.75

21

60 - 240 LG ROUND

5.40

21

60 - 240 LG ROUND (release pin)

3.60

22

LT BUSH OD=60,ID=50, 64 THK

0.50

22

LT BUSH OD=60,ID=50, 64 THK (bronze bush)

23

M6 GREASE NIPPLE

23

M6 GREASE NIPPLE

24

PL OD=170,ID=52, 10THK

1.60

24

PL OD=170,ID=52, 10THK

25

SPLIT PIN M6

1.60

25

SPLIT PIN M6

26
27
28

PIN 30 - 160 LG
PL 80X12 - 90 LG
PL 150X16 - 750 LG
M30 - 200 LG WITH NUT &
WASHER

1
2
2

0.90
1.40
28.30

26
27
28

1
2
2

0.39
1.36
28.26

1.20

29

PIN 20 - 160 LG
PL 80X12 - 90 LG (supporting plate)
PL 150X16 - 750 LG (counter weight plates)
M30 - 200 LG WITH NUT & WASHER (counter weight fixing
bolt)

1.20

30

PL OD=200,ID=31, 20 THK

24.70

30

PL OD=200,ID=31, 20 THK (counter plates)

24.07

31

PL 98X16 - 2675 LG

65.85

31

PL 98X16 - 2800 LG (web plates)

68.93

32

PL OD=240,ID=102, 40 THK

45.30

32

PL OD=240,ID=102, 40 THK (inclined grader fixing roller)

46.56

33

PL 250X16 - 3095 LG

388.70

33

PL 250X16 - 3095 LG (equal inclined plates)

388.73

34

PL OD=240,ID=102, 16 THK

18.00

34

PL OD=240,ID=102, 16 THK (fixing plate)

18.62

35

PL 80X10 - 98 LG

2.50

35

PL 80X10 - 98 LG (extension plate)

2.46

36

PL 70X10 - 98 LG

4.30

36

PL 70X10 - 98 LG

37
38
39
40

PL 500X10 - 130 LG
PIN 100 - 240 LG
PL 250X10 - 350 LG
PL 280X16 - 625 LG
SEAMLESS TUBE 60 (MIN
8.7THK) - 2987 LG
PL 80X20 - 110 LG

16
2
4
4

8.20
46.20
49.00
88.00

37
38
39
40

PL 50X10 - 130 LG (lock plates)


PIN 100 - 240 LG (inclined fixing plate)
PL 250X10 - 350 LG (roller block)
PL 280X16 - 625 LG (roller block lock plate)

16
2
4
4

8.16
27.70
27.48
87.92

66.70

41

SEAMLESS TUBE 60 (MIN 8.7THK) - 2987 LG

46.00

5.60

42

PL 80X20 - 110 LG (tube support plate)

5.53

LH2
RH2

4.00

43

HEX BOLT M30 X 200 LG WITH LOCK NUT

LH2 RH2

4.00

29

41
42
43

HEX BOLT M30 X 200 LG WITH


LOCK NUT

already
included

3.23

Removed

Removed

44

PL 80X40 - 110 LG

LH2
RH2

11.00

44

PL 80X40 - 110 LG

LH2 RH2

11.05

45

PL 80X10 - 130 LG

LH2
RH2

11.00

45

PL 80X10 - 130 LG

LH2 RH2

6.53

46

HEX BOLT M28 - 120 LG WITH


NUT & WASHER

3.50

46

HEX BOLT M28 - 120 LG WITH NUT & WASHER

4.00

47

HEX SCREW M16 - 30 LG WITH


WASHER

56

1.60

47

HEX SCREW M16 - 30 LG WITH WASHER

TOTAL WT IN KGS

2319.35

Removed

TOTAL WT IN KGS

DETAILS OF SPRING GUIDE


ROLLER

DETAILS OF SPRING GUIDE ROLLER

Drawing No.225

Drawing No.225

2027.12

200DIA ROLLER

12.00

200DIA ROLLER

12.93

BUSH OD=70,ID=50 ; 80 THK

1.30

BUSH OD=70,ID=50 ; 80 THK

already
included

70DIA X 147LG

4.40

70DIA X 147LG

removed

PL 200X16 - 235 LG

8.90

PL 200X16 - 235 LG (roller plate)

11.81

PL 80X10 - 85 LG

1.00

PL 80X10 - 85 LG (stiffeners)

1.07

M12 X 30 LG HEX SCREW WITH


WASHER

M12 X 30 LG HEX SCREW WITH WASHER

PL 50X10 - 120 LG

0.60

PL 50X10 - 120 LG

PL 200X16 - 400 LG

15.00

PL 200X36 - 300 LG (roller break base plate)

16.96

80 DIA 16 THK

5.00

70 DIA 14 THK

0.42

10

SPRING

4.60

10

SPRING

3.15

11

PL 60X10 - 80 LG

0.60

11

PL 60X10 - 80 LG

removed

removed

12

M16 X 180 LG HEX BOLT WITH


NUT & WASHER

TOTAL WT IN KGS

1.00

12

54.40

M16 X 180 LG HEX BOLT WITH NUT & WASHER

removed

TOTAL WT IN KGS

DETAILS OF CABIN

DETAILS OF CABIN

Drawing No.226

Drawing No.226

20.53

ISA 35X35X5 - 543 LG

4.20

ISA 75X75X8 - 1300 LG

46.28

SH - 650X3 - 975 LG

14.90

ISA 75X75X8 - 2150 LG

38.27

ISA 35X35X5 - 788 LG

2.00

ISA 75X75X8 - 2000 LG

53.40

ISA 75X75X6 - 2550 LG

45.40

40 DIA PIPE 1200 LG

3.90

ISA 35X35X5 - 1985 LG

10.30

ISA 35X35X4 - 1300 LG

5.46

ISA 35X35X5 - 1288 LG

6.70

ISA 35X35X4 - 2000 LG

4.20

GL - 350X5 - 810 LG

ISA 35X35X4 - 1300 LG

16.80

10DIA - 150LG

ISA 35X35X4 - 1350 LG

5.67

ISA 75X75X6 - 2550 LG

13.20

ISA 35X35X4 - 1800 LG

7.56

10

PIPE 100DIA - 1850 LG

4.30

10

ISA 25X25X3 - 800 LG

7.04

11

ISA 35X35X5 - 335 LG

1.70

11

CHQD 350X1150X6

18.96

12

20DIA - 200 LG

1.90

12

CHQD 1250X1260X6

74.18

14

ISA 75X75X6 - 2000 LG

17.80

14

SH - 1300X3.15 - 2025 LG

65.10

15

SH - 340X3 - 1280 LG

10.20

15

SH - 425X3.15 - 2170 LG

45.61

17

ISA 35X35X5 - 1310 LG

6.80

SH - 300X3.15 - 1150 LG

8.53

18

SH - 1350X3 - 1700 LG

54.00

GL - 280X5 - 800 LG

2.80

19

SH - 490X3 - 1580 LG

GL - 540X5 - 800 LG

5.40

20

SH - 140X3 - 700 LG

21

ISA 35X35X5 - 1285 LG

22

GL - 350X5 - 810 LG

23

ISA 35X35X5 - 1548 LG

36.50

17

ISA 35X35X5 - 1310 LG

Removed

24

CHQD 380X5 - 1300 LG

4.60

18

SH - 1350X3 - 1700 LG

Removed

25

ISMC 100X50 - 1300 LG

13.30

19

SH - 490X3 - 1580 LG

Removed

26

SH - 970X3 - 1280 LG

20

SH - 140X3 - 700 LG

Removed

27

ISMC 100X50 - 1290 LG

8.00

21

ISA 35X35X5 - 1285 LG

Removed

28

GL - 210X5 - 810 LG

22.70

22

GL - 350X5 - 810 LG

Removed

29

GL - 530X5 - 810 LG

24.80

23

ISA 35X35X5 - 1548 LG

Removed

30

RUBBER BEAD AS NOTED TO


FIX GLASS 12000LG

58.50

24

CHQD 380X5 - 1300 LG

Removed

24.60

25

ISMC 100X50 - 1300 LG

Removed

26

SH - 970X3 - 1280 LG

Removed

27

ISMC 100X50 - 1290 LG

Removed

28

GL - 210X5 - 810 LG

Removed

29

GL - 530X5 - 810 LG

Removed

30

RUBBER BEAD AS NOTED TO FIX GLASS 12000LG

Removed

31

ISA 35X35X5 - 800 LG

Removed

32

SH - 300X3 - 1300 LG

Removed

33

ALUMINIUM BEAD AS DETAILS

12.00

35

ISA 35X35X5 - 2150 LG

11.10

33

ALUMINIUM BEAD AS DETAILS

Removed

37

ISA 35X35X5 - 1290 LG

3.30

35

ISA 35X35X5 - 2150 LG

Removed

38

ISA 35X35X5 - 361 LG

1.80

36

CHQD 1250X5 - 1250 LG

Removed

39

ISA 35X35X5 - 700 LG

1.80

37

ISA 35X35X5 - 1290 LG

Removed

41

SH - 410X3 - 700 LG

13.50

38

ISA 35X35X5 - 361 LG

Removed

42

SH - 180X3 - 700 LG

3.00

39

ISA 35X35X5 - 700 LG

Removed

45

12 GAUGE WIRE MESH 250 DIA

41

SH - 410X3 - 700 LG

Removed

46
47
46
47

SH - 50X3 - 470 LG
SH - 950X3 - 2200 LG
SH - 50X3 - 470 LG
SH - 950X3 - 2200 LG

1
1
1
1

42
45
46
47

SH - 180X3 - 700 LG
12 GAUGE WIRE MESH 250 DIA
SH - 50X3 - 470 LG
SH - 950X3 - 2200 LG

Removed
Removed
Removed
Removed

0.50
49.10
0.50
49.10

TOTAL WT IN KGS

612.40

TOTAL WT IN KGS

DETAILS OF PARKING BRAKE

DETAILS OF PARKING BRAKE

Drawing No.227

Drawing No.227

409.16

PL 290X12 - 680 LG

18.60

PL 290X12 - 680 LG

Removed

ISMC 250X80 - 326 LONG


PLUMMER BLOCK SNA-507 TC
BEARING NO.2207K WITH
ADOPTER SLEEVE H 307
M10 - 65 LG HEX BOLT NUT &
TAPER WASHER

22.30

ISMC 250X80 - 326 LONG

Removed

4.00

PLUMMER BLOCK SNA-507 TC BEARING NO.2207K WITH


Removed
ADOPTER SLEEVE H 307

M10 - 65 LG HEX BOLT NUT & TAPER WASHER

Removed

M16 HEX NUT IS:1363 (P3)

0.03

M16 HEX NUT IS:1363 (P3)

Removed

6
7
8
9
10
11
12

1
1
1
4
4
2
2

0.10
1.80
22.40
58.30
36.90
3.20

6
7
8
9
10
11
12

PL OD=35,ID=18; 6 THK
ROUND 20DIA - 780 LG
PL 350X12 - 680LG
SPLIT PIN 6DIA - 75LG
PL 140X16 - 800LG
PL 350X16 - 420 LG
PL 70X12 - 240 LG

Removed
Removed
Removed
Removed
Removed
Removed
Removed

12.40

13

BLOCK 90X50 - 175 LG (LH TH1 & RH TH1)

Removed

14
15
16
17
18
19
20
21
22
23

PL OD=35,ID=18; 6 THK
ROUND 20DIA - 780 LG
PL 350X12 - 680LG
SPLIT PIN 6DIA - 75LG
PL 140X16 - 800LG
PL 350X16 - 420 LG
PL 70X12 - 240 LG
BLOCK 90X50 - 175 LG (LH TH1
& RH TH1)
ROUND 40DIA - 710 LG
SHIM 52X1 - 185 LG
PL OD=60,ID=32, 6 THK
ROUND 30DIA - 215 LG
SPLIT PIN 6DIA - 75LG
PL 70X20 - 220 LG
ROUND 20DIA - 215 LG
PL OD=40,ID=22; 6 THK
PL 60X16 - 65 LG
ROD 20DIA X 90 LG

1
10
8
2
4
2
2
4
4
3

7.00
0.80
1.10
2.40
4.80
1.20
0.20
2.00
0.70

14
15
16
17
18
19
20
21
22
23

ROUND 40DIA - 710 LG


SHIM 52X1 - 185 LG
PL OD=60,ID=32, 6 THK
ROUND 30DIA - 215 LG
SPLIT PIN 6DIA - 75LG
PL 70X20 - 220 LG
ROUND 20DIA - 215 LG
PL OD=40,ID=22; 6 THK
PL 60X16 - 65 LG
ROD 20DIA X 90 LG

Removed
Removed
Removed
Removed
Removed
Removed
Removed
Removed
Removed
Removed

24

OD= 50 (AS NOTED) 50 THK

0.80

24

OD= 50 (AS NOTED) 50 THK

Removed

25
26

PL 90X12 - 100 LG
PL 82X12 - 420 LG

5
2

2.20
6.50

25
26

PL 90X12 - 100 LG
PL 82X12 - 420 LG

Removed
Removed

3
4

13

209.73

1
2
3
4
5
6
7
8
9

PL OD=167,ID=103, 25 THK (Square plate )


PL 100X25 - 280 LG
PL 97X25 - 165 LG
PL 100X25 - 200 LG
PL 100X25 - 230 LG
ROD 32DIA X 290 LG
ISMC 300X90 - 470 LONG
PL 250X25 - 465 LG
ROD25DIA X 900 LG (Handle Rod )

1
2
2
2
2
1
2
1
1

Total Weight
DETAILS OF DOGGING BEAM

3.39
10.99
6.28
7.85
9.03
1.42
33.65
22.81
3.47
98.89

DETAILS OF DOGGING BEAM

1
2
3a
3b
3
4

PL 500X12 - 500 LG
ROD 20DIA- 450 LG
PL150X12 - 1850 LG
PL150X10 - 1850 LG
PL 250X10 - 1850 LG
PL 59X12 - 225 LG

4
16
2
2
2
12

94.20
17.70
52.20
43.50
72.60
15.00

1
2
3a
3b
3
4

PL 500X12 - 500 LG
ROD 20DIA- 550 LG (Anchor Rods piers)
PL150X12 - 1880 LG
PL150X10 - 1880 LG
PL 250X10 - 1880 LG
PL 60X12 - 250 LG

PL 120X12 - 240 LG

10.80

PL 120X12 - 240 LG

Removed

ROD 16 DIA-305 LG

1.90

ROD 16 DIA-305 LG

Removed

HAND CHAIN-200 LG

10.00

HAND CHAIN-200 LG

Removed

ISA 75X75X8-272 lg

19.40

ISA 75X75X8-280 lg

9.97

ROD 20DIA-300 LG (Anchor Rods Abutments)

2.96

PL 100X12 - 100 LG (Anchor Rods plates Abutments)

3.14

80/6

10.47

PL 100X12 - 100 LG (Anchor Rods plates Piers))


Total Weight
Total Weight x 6
Electrical Items
Resistance box Weight

4
80/6
2
2
2
12

94.20
18.11
53.13
44.27
73.79
16.96

327.00
1962.00

21.90

1
2
3
4
5
6
7
8
9
10

Panel box Weight


Electrical cable Weight
Cable reeling drum
Cable reeling drum supports
With out drawing
Big Ladder
ISA 75X75X8 - 4300 LG
ISA 65X65X6 - 470 LG
1.5'' (38 mm )- 3650 pipe
ISA 65X65X6 - 250 LG
Total Weight
Small Ladder
ISA 75X75X8 - 3000 LG
ISA 50X50X6 - 420 LG
1.5'' (38 mm )- 1900 pipe
ISA 65X65X6 - 250 LG
Total Weight
Motor box covers
CT Motor & Gear box cover
LT Wheel box cover
LT Motor & Gear box cover on bridge
LT Motor & Gear box cover o npier
LT Gear wheel cover on bridge
LT Gear wheel cover on pier
Lifting Motor & Gear box cover
Rope drum Motor & Gear box cover-1
Rope drum Motor & Gear box cover-2
CT Wheel cover
Total Weight
Grand Total

133.00
33.20
115.00
59.55

2
14
2
6

76.54
38.16
23.73
8.70
147.13

2
9
2
4

53.40
17.01
12.35
5.80
88.56

1
1
1
1
1
1
1
1
1
1

32.00
23.90
44.90
41.00
20.90
19.40
83.50
83.30
84.20
16.10
449.20

LOG GATES OF BHUPATHIPALEM RESERVOIR SCHEME, RAMPACHODAVARAM (M), E.G.Dist

As per execution

Member
s

Total wt

Unit weight

990.23

35.8 kg/m

2
2

990.23
3170.11

35.8 kg/m

1234.89

229.60

150.72

350.24

24.12

114.30

128.87

18.84

180.00

1 pair wt.=1.4 kg

24.03

8.9 kg/m

200.74

16.4 kg/m

677.45

160.43

5.8 kg/m

130.50

5.8 kg/m

86.84

=30.8/9.81 kg/m

85.75

3.1 kg/m

16.96

47.48

53.04

44.2 kg/m

4
4
4

1824.37
1824.37
4672.42

35.8 kg/m
35.8 kg/m

2275.13

241.15

431.06

60.29

228.59

257.73

50.24

288.00

42.72

8.9 kg/m

356.86

16.4 kg/m

1248.11

295.57

5.8 kg/m

232.00

5.8 kg/m

160.00

=30.8/9.81 kg/m

157.98

3.1 kg/m

67.82

189.91

25.12

4.80

362.07

14.9 kg/m

386.40

9.2 kg/m

3386.35

994.50

Each plate 6.5 kg

214.20

1.4kg /pair

11.78

1
1

53.04
11.30

44.2 kg/m

0.90

1
1

13.00
22.61

1
1
1
1

344.71
202.40
376.05
376.05

158.26

30.27

1
1
1
1
1
1
1

52.75
60.29
80.89
37.68
14.47
390.65
25.20

1.4kg /pair

61.88

44.2 kg/m

1
1

160.72
18.69

16.4 kg/m
8.9 kg/m

146.25

4.5 kg/m

94.19

=30.8/9.81 kg/m

31.40

3.14 kg/m

268.47

127.17

16.03

30.40

58.28

70.34

442.11

401.92

95.46

57.27

66.32

23.55

38.50

Removed

7.7 kg/m

21.04

3.14 kg/m

1366.33

1460.39

109.65

57.60

4.5 kg/m

72.00

4.5 kg/m

115.20

4.5 kg/m

80.38

18.40

4000.00

each leg / 1 tonne

203.20

203.2/2 nos

27.80

27.8/2 nos

32.60

32.6/2nos

100.20

100/2 nos

24.90

24.9/4 nos

21.67

19.7 kg/m

1
1
1

2.01
103.62
47.48

1
1
1

22.86
2.25
61.04

0.50

1.00

1
1
1
1

1336.06
385.65
289.24
64.43

35.8 kg/m

13.92

5.8 kg/m

1
1

43.33

8.80

1
1

30.40

13.56

1.80

85.00

4.51

33.60

1
1

85kg/4 nos

=67.2/2 per 2 nos

349.70

349.7 kg/2 nos

341.30

341.3kgs/ 2 nos

1.00

114.10

1.20

1
1

29.40
32.90

29.4/2nos
32.9/ 2 nos

144.60

144.6 kgs/ 2 nos

32.80

32.8 kgs/ 2 nos

1.50

114.1/ 2 nos

6.85

13.7kgs/4 nos

18.70

18.7 / 2 nos

6.90

6.9/2 nos

37.35

24.9kgs/4 nos

9.80

29.00

58kgs/4 nos

29.00

58kgs/4 nos

1.38

135.30

135.3kgs/2 nos

6.85

13.7kgs/4 nos

1157.34

122.6kg/m

1
1
1

208.62
243.20
36.74

22.1kg/m
30.4kg/m

13.60

6.8kg/m

1.50

8.80

3.30

1
1
1
1
1
1

25.91
106.27
77.33
91.50
71.44
248.06

49.4 kg/m
35.8 kg/m
30.4 kg/m
30.4 kg/m

42.00

42 kg/3 nos

1
1

18.84
8.01

Removed

Already incuded

1
1

4.69
7.80

7.8 kg/3 nos

59.70

59.7 kg / both
2400 mm line
shaft & 1500 mm
line shaft

70.90

70.9 kg / 1 no

16.40

16.4 kg / 1 no

13.80

13.8 kg / 1 no

16.70

16.7 kg / 1 no

42.50

42.5 kg / 8 nos

10.25

20.5 kg / 4 nos

15.09

16.4 kg/m

0.80

1.60

353.10

353.1 kg / 1 no

35.40

35.4 kg / 1 no

37.50

37.5 kg / 1 no

137.20

137.2 kg / 1 no

1
1

48.22
22.96

16.4 kg / m
16.4 kg / m

46.72

9.79

8.9 kg / m

9.79

8.9 kg / m

13.19

0.50

12.10

1
1

0.45
15.54

133.38

49.4 kg / m

108.68

49.4 kg / m

2
2
2

92.87
93.86
15.81

49.4 kg / m
49.4 kg / m
49.4 kg / m

12.1 kg/2 nos

2
2
2

49.40
5.65
19.08

49.4 kg / m

46.53

13.23

140.67

8.79

6.00

2.24

27.48

45.90

2.40

179.90

Total wire rope Wt


=179.90

83.70

83.7 kgs /2 nos

44.60

44.6 kgs /2 nos

45.9 kg/4 nos

481.10

=(254+227.1)/2 ,
LH Rope
drum=254, RH
Rope drum=227.1

4.50

4.5 kgs / 4 nos

3.20

421.50

=(209.4+212.1)/2 ,
Gear wheel1=209.4, Gear
wheel-2=212.1

31.70

31.7kKgs / 2 Nos

1
1

324.05
15.20

8.79

15.83

4.75

1
1

7.39
7.89

28.90

28.9 kg/ 2 nos

33.70

33.7 kg/ 2 nos

7.58

1
1

2.00

310.70

48.63

310.7 Kgs/7 nos

723.88

48.04

65.94

6.87

87.14

28.26

13.56

1
1
1

56.52
25.70
5.92

5.65

19.53

12.63

1
1
1
1

7.54
0.00
16.50
63.30

11.62

35.8 kg/m

25.7kg/2nos

16.5kg/2 nos

12.75

3.60

0.00

3.23

1
1
1

0.39
1.36
28.26

1.20

24.07

68.93

46.56

388.73

18.62

2.46

1
1
1
1

8.16
27.70
27.48
87.92

46.00

5.53

4.00

3.6kg/1no

27.7kg/2 nos

46/2 no

11.05

6.53

4.00

51.70

47.23

4.27

51.7kgs/4nos

67.82

1.69

12.60

12.6kgs/16 nos

46.28

8.9 kg/m

38.27

8.9 kg/m

53.40

8.9 kg/m

3.90

3.25 kg/m

5.46

2.1 kg/m

4.20

2.1 kg/m

16.80

2.1 kg/m

5.67

2.1 kg/m

7.56

2.1 kg/m

7.04

1.1 kg/m

18.96

74.18

65.10

45.61

8.53

2.80

5.40

5 mm glass sheet
12.5 kg /sq.m

1
1
1
1
1
1
1
1
1

3.39
10.99
6.28
7.85
9.03
1.42
33.65
22.81
3.47

6
6
6
6
6
6

565.20
108.68
318.77
265.64
442.74
101.74

59.81

8.9 kg/ m

11.86

2.47 kg/ m

12.56

62.80

Total 80 nos

21.90

2.9 kg/1no

4.9 kg/m
35.8 kg/m
3.85 kg/m

2.47 kg/ m

2
1
1
1

266.00
33.20
115.00
59.55

133 kg/1no
33.2kgs
115 kg/1no
59.55 kg/1set

1
1
1
1

76.54
38.16
23.73
8.70

8.9 kg/m
5.8 kg/m
3.25 kg/m
5.8 kg/m

1
1
1
1

53.40
17.01
12.35
5.80

8.9 kg/m
4.5 kg/m
3.25 kg/m
5.8 kg/m

1
1
1
1
1
1
1
1
1
1

32.00
23.90
44.90
41.00
20.90
19.40
83.50
83.30
84.20
16.10

57499.89
or say

57.50

Sl.No

Description

SUPPLEMENTARY ITEMS
Unit L

RCC M- 25Nominal mix (Cement:fine aggregate: coarse aggregate)


corresponding to Table 9 of IS 456 using 20mm size graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as machine mixing, laying concrete,
curing etc.,complete but excluding cost of steel and its fabrication charges
for finished item of work, but excluding centering, shuttering. (Page
No.664) BLD CSTN-3-13 S.No.30.

1
a) Pedestals over pier & abutment
abutment 1
Pier1
pier2
pier3
pier4
pier5
abutment2
b) Pedestals under dogging beams
abutment 1
Pier1
pier2
pier3
pier4
pier5

abutment2

Total

Cum

2.5
2.69
2.75
2.73
2.74
2.74
2.46

0.83
0.8
0.82
0.7
0.7
0.83
0.78

1.29
1.28
2.72
2.75
2.78
2.75
2.76
2.77
2.8
2.74
0.89
0.9
0.98
0.93
1.28
1.29

0.61
0.6
0.6
0.62
0.6
0.6
0.61
0.6
0.6
0.6
0.6
0.61
0.59
0.62
0.57
0.63

PCC M- 25 Nominal mix (Cement:fine aggregate: coarse aggregate)


corresponding to Table 9 of IS 456 using 20mm size graded machine
crushed hard granite metal (coarse aggregate) from approved quarry
including cost and conveyance of all materials like cement, fine aggregate
(sand) coarse aggregate, water etc., to site and including Seigniorage
charges, sales & other taxes on all materials including all operational,
incidental and labour charges such as machine mixing, laying concrete,
curing etc.,complete , but excluding centering, shuttering.

2
c) spillway bridge rail concrete

Total

Cum

76.5

0.45

Cum

Supplying, fitting and placing HYSD bar reinforcement (Fe


415) in substructure complete as per drawings and
technical specification Clauses 1002, 1005, 1010 & 1202
MORD / Sections 1600 & 2200 MORTH for Bars below 36
mm dia including over laps and wastage, where they are
not welded.
3
Steel Fe-415
pedestals under rail girder
20mm dia rods - 7 pedestals each 20 nos
8mm dia rods - 7 pedestals each 3 nos
Total Steel Fe-415
Total
Supplying, fitting and placing with MS bar reinforcement in
substructure complete as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 MORD /
Sections 1600 & 2200 MORTH for Bars below 36 mm dia
4
including over laps and wastage, where they are not
MS
Rods
welded.
pedestals under dogging beams
6mm reinforcement
6mm stirrups
Total MS Rods
Total

MT

7x20
7x3

0.9
7.1

24x3
24x1

0.55
0.55

MT

MT

MT

Qty

0.62
0.86
0.9
0.86
0.96
0.86
0.62

1.29
1.85
2.03
1.64
1.84
1.96
1.19

0.33
0.29
0.56
0.55
0.63
0.6
0.55
0.57
0.58
0.56
0.54
0.53
0.54
0.54
0.29
0.29

0.26
0.22
0.91
0.94
1.05
0.99
0.93
0.95
0.97
0.92
0.29
0.29
0.31
0.31
0.21
0.24

21.59

0.06

2.07

2.07

310.73
58.83
369.56

0.3696

8.79
2.93
11.72

0.011719

DATA
NAME OF WORK:- Manufacturing, supply and errection of Radial gates of size 10.00 x 7.50M size of 6 vents and
highest bridge and Hoish equipment for spill way regulator of Bhupathipalem Reservoir project.
- Est. Rs. 5.15 Crores CR.No.18/07-08.
Name of sub-work:- Construction of lascar, electrician and watchman quarters at Bhupatipalem Reservoir site
S.No

Qty

Description of Item

PCC M- 25 Nominal mix (Cement:fine aggregate: coarse aggregate)


corresponding to Table 9 of IS 456 using 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as machine mixing, laying concrete, curing etc.,complete , but excluding
centering, shuttering.

PCC Grade M25 (Design Mix) (MORTH):


(i) For height upto 5 m
Case I : Using Concrete mixer :
Rate per Cum
1.000

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4 (D) Case I
excluding formwork.

PCC Grade M25 using 40 mm Graded Metal (Design Mix) (MORTH 12.8 D)
CASE I : Using Concrete Mixer
Unit = cum
Taking output = cum
a)

Material

0.40

Cement

0.45

Coarse sand

0.36

40 mm Aggregate

0.36

20 mm Aggregate

0.18

10 mm Aggregate
Total material cost
b)

Labour

Mate

0.1

Mason

1.39

Mazdoor (Unskilled)

25%

Add 25% agency allowence on Labour =(35+389.20)*25%

Total cost for Labour


c)

Machinery

0.40

Concrete mixer (cap. 0.40/0.28 cum)

0.40

Generator 33 KVA
Total cost for Machinery
Add on cost of material, labour and machinery (a+b+c)
d) formwork

10.00%

Add on cost of material, labour and machinery (a+b+c) for Formwork

14.00%

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

RCC M- 25Nominal mix (Cement:fine aggregate: coarse aggregate)


corresponding to Table 9 of IS 456 using 20mm size graded machine crushed
hard granite metal (coarse aggregate) from approved quarry including cost and
conveyance of all materials like cement, fine aggregate (sand) coarse
aggregate, water etc., to site and including Seigniorage charges, sales & other
taxes on all materials including all operational, incidental and labour charges
such as machine mixing, laying concrete, curing etc.,complete but excluding
cost of steel and its fabrication charges for finished item of work, but excluding
centering, shuttering. (Page No.664) BLD CSTN-3-13 S.No.30.

R.C.C. grade M 25 (Design Mix)


Unit = cum
Height upto 5m
Case I : Using concrete Mixer
0.403

(a) Material
Cement

0.450

Coarse sand

0.540

20 mm aggregate

0.360

10 mm aggregate
Total material cost
(b) Labour

Mate

0.10

Mason (1st Class)

1.39

Mazdoor (Unskilled)

25%

Add 25% agency allowence on Labour =(35+389.20)*25%


Total cost for Labour
(c) Machinery

0.40

Concrete mixer 0.4/0.28 cum capacity

0.40

Generator 33 KVA

0.100

Vibrator
Total cost for Machinery
Add on cost of material, labour and machinery (a+b+c)

11.00%
14.00%

(d) Formwork @ 10% on (a+b+c)


e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in substructure
complete as per drawings and technical specification Clauses 1002, 1005, 1010 &
1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia including
over laps and wastage, where they are not welded.

Unit = t
(a) Material
1.050

HYSD bars including 5 per cent overlaps and wastage

6.000

Binding wire
Total material cost
(b) Labour for cutting, bending, shifting to site, tying, and placing in position

6.840

Mate
Blacksmith
Mazdoor (Unskilled)

25%

Add 25% agency allowence on Labour =(700+1915.20)*25%

2.000

14%

Total cost for Labour


Add on cost of material and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
Supplying, fitting and placing with MS bar reinforcement in substructure complete as per
drawings and technical specification Clauses 1002, 1005, 1010 & 1202 MORD / Sections 1600
& 2200 MORTH for Bars below 36 mm dia including over laps and wastage, where they are
not welded.

1.050
6.000

1.500

Unit = t
(a) Material
MS bars including 5 per cent overlaps and wastage
Binding wire
Total material cost
(b) Labour for cutting, bending, shifting to site, tying, and placing in position
Mate
Blacksmith

5.780

Mazdoor (Unskilled)

25%

Add 25% agency allowence on Labour =(525+1618.40)*25%

14%

Total cost for Labour


Add on cost of material and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

0 x 7.50M size of 6 vents and stop log gates elements


ir project.

patipalem Reservoir site


Rate

per

Amount

0.00
cum

0.00
0.00

5800.00

tonne
cum

1040.94
1809.05
1809.05
1809.05

cum
cum
cum

2320.00
468.42
651.26
651.26
325.63
4416.57

day

350.00
280.00
424.20

day
day

35.00
389.20
106.05

530.25

174.20
104.50

hr / cum
hour

69.68
41.80
111.48
5058.30
505.83
708.16
6272.29

Say

5800.00

1040.94
1809.05
1809.05

t
cum
cum
cum

6272.00

2337.40
468.42
976.89
651.26
4433.97

day

350.00
280.00

day
day

35.00
389.20

424.20

106.05
530.25

174.20

hour

69.68

104.50

hour

41.80

209.00

hour

20.90
132.38
5096.60

Say

42000.00
70.00

560.63
713.52
6370.75
6371.00

44100.00
420.00
44520.00

t
kg

day

350.00
280.00

700.00
1915.20

day
day

2615.20

653.80

Say

40900.00
70.00

t
kg

3269.00
47789.00
6690.46
54479.46
54479.00

42945.00
420.00
43365.00

day

350.00

day

525.00

280.00

1618.40

day

2143.40

535.85

Say

2679.25
46044.25
6446.20
52490.45
52490.00

LEAD STATEMENT
Name of work:- Gantry Crane
Sl.
Description of Materials
No.

Unit

Source quarry Lead in KM

CT
1 Cement
2 Steel (MS)
2 Steel (Fe-415)
3 Sand for mortar
8 20mm-10mm HBG metal

1 MT
1 MT
1MT
1 CUM
1 CUM

site of work
site of work
site of work
Vangalapudi
-do -

-_
2x1.1=2.2
3x1.1= 3.30

Total
lead
KM

ST
_
-

MR
58
57
54

Initial
cost

58
60
58

5800
40900
42000
385
1150

CERTIFICATES
1) Certified that the leads are correct to the best of my knowledge.
2) Certified that the seignorage charges are adequate & as per G.O.Ms.No.industries and commerce dt.
3) Certified that the estimate is prepared based on the current SSR 2013-14

conveyance
charge

634
615

Loading & unloading 25% tribal


charges
allowance
on
unloading
charges
-

13.50+6.75=20.25
27.10+13.55=40.65

1.69
3.4

Cost of
material
at site of
work

5800
40900
42000
1040.94
1809.05

RBR_FNDN
Andhra Pradesh Standard Data
I. Roads and Bridges

Chapter - 11
FOUNDATION
Index-code

RBR-FNDN-1

S. No

Description

Excavation for Structures


Earthwork in excavation for structures as per drawing and technical
specifications Clause 305.1 including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and backfilling in trenches with
excavated suitable material as per Technical Specification 305 MORD / 304
MORTH

Note : Classifications of Earth Work Specification are as per 302.2.1(a) of


MORD and 301.2.1 of MORT&H
(I) Ordinary soil
(A) Manual Means
(i)

Upto 3 m depth
Unit = cum
Taking output = 10 cum
a)Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10

Note : 1. Cost of dewatering may be added, where required, up to 5 per cent of labour cost. Assessmen
as per site conditions.
2. The cost of shoring and shuttering, where needed, may be added on cost of excavation for open found

3. The excavated earth if found suitable, can be used partly for backfilling in trenches & partly for road
has not been added except for marshy soil. This note is common to all cases of item 11.1 excluding 11.1
(B) Mechanical Means
i

Upto 3 m depth
Unit = cum
Taking output = 240 cum
a)Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 240 cum = a+b+c+d
Rate per cum = (a+b+c+d)/240

Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10 per cent of
dewatering shall be made as per site conditions.

3 m to 6 m depth
Unit = cum
(A) Manual Means
a)Labour
Mate / Supervisor
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
ii

Note : 1. Cost of dewatering may be added, when needed, up to 5 per cent of labour cost.

484

RBR_FNDN
2. Cost of shoring and shuttering, where needed, may be taken @ 10 per cent on cost of excavation for

485

RBR_FNDN
B

Mechanical Means
Unit = cum
Taking output = 210 cum
a)

Labour

Mate
Mazdoor (Unskilled)
b)

Machinery

Hydraulic excavator 1.0 cum bucket capacity


c&d) Overheads & Contractors Profit
Cost for 210 cum = a+b+c+d
Rate per cum = (a+b+c+d)/210

Note : Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessment for de
site conditions.
iii

Depth above 6 m

(A) Manual Means

Unit = cum
Taking output = 10 cum
a)

Labour

Mate/Supervisor
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : 1. Cost of dewatering may be added where required upto 5 per cent of labour cost.

shall be made as per site conditions..


B

Mechanical Means
Unit = cum
Taking output = 180 cum
a)

Labour

Mate
Mazdoor (Unskilled)
b)

Machinery

Hydraulic excavator 1.0 cum bucket capacity


c&d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180

Note : 1. Cost of dewatering upto 5 per cent of (a+b) may be added, where required. Assessm

made as per site conditions..

2. Labour provided for excavation by mechanical means includes that required for trimming of
(II) Ordinary rock (not requiring blasting)

(A) Manual Means


Upto 3 m depth
Unit = cum
Taking output = 10 cum
a)Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = (a+b+c)/10
Note : Cost of dewatering upto 5 per cent of labour cost may be added, where required as pe

486

RBR_FNDN
(B) Mechanical Means
Upto 3 m depth
Unit = cum
Taking output = 180 cum
a)Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Hydraulic Excavator 1 cum bucket capacity
c&d) Overheads & Contractors Profit
Cost for 180 cum = a+b+c+d
Rate per cum = (a+b+c+d)/180
Note : 1. Cost of dewatering upto 5% of a+b may be added, where required, up to 10
per cent of labour cost. Assessment for dewatering shall be made as per site conditions.

2. in case of rock foundation beyond 3 m is not dug and hence not


included.
(III) Hard rock (requiring blasting)

Upto 3 m depth including 1.5 m depth in hard rock


Unit = cum
Taking output = 10 cum
a)Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hammers for drilling at 15 cum
per hour
c) Material
Gelatin 80%
Detonator electric
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note : 1. Cost of dewatering @ 5 per cent of (a+b) may be added, where
required as per site condition.
2. No limitation of depth in MORTH
(IV) Hard rock (blasting prohibited)

Upto 3 m depth including 1.5 m depth in hard rock


Unit = cum
Taking output = 10 cum
a)Labour
Mate
Mazdoor (Unskilled)
b) Machinery
Air compressor 210 cfm / 250 cfm with 2 jack hammers of pneumatic breaker
at 1 cum per hour
c&d) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d
Rate per cum = a+b+c+d)/10
Note : Cost of dewatering up to 5 per cent of (a+b) may be added, where required as
per site conditions.
2. in case of rock foundation beyond 3 m is not dug and hence not included.
(MORTH)

487

RBR_FNDN
(V) Marshy soil

Unit = cum
Taking output = 10 cum
a)Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 10 cum = a+b+c
Rate per cum = a+b+c)/10
Note : Cost of dewatering @ 5 per cent of (a) may be added.
Shoring and shuttering @ 15 per cent of (a) may be added where required.

Since marshy soil cannot be used in filling in trenches, it shall be removed and replaced by approved q
includes labour input for disposal of marshy soil from excavated pit with a lead upto 50 m lead.

Marshy soil is generally available upto 3 m depth. The rate has, therefore, been done upto 3 m dep
excavation refer analysis in item (i) to (iv) of ordinary soil.
(a) Marshy soil

Including Refilling with selected earth conveyed from 1000 M lead


through Tractor Trally.
Unit = cum
Taking output = 10 cum
(A) Manual Means (upto 3 m depth)
a)Labour
Mate / Supervisor
Mazdoor (Unskilled)
b) Machinery
Tractor - Trally
c) Material
Selected earth for refilling with conveyance from 1000m
d&e) Overheads & Contractors Profit
Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10

Note : 1. Cost of dewatering @ 5 per cent of (a) may be added. Assessment for dewatering
conditions.
2. Shoring and shuttering @ 15 per cent of (a) may be added where required.
3. It is assumed, that Marshy soil will be available upto 3 m depth only. For deeper excava
analysis in item (i) to (iv) for ordinary soil.
(B) Mechanical Means
a)Labour
Mate
Mazdoor for dressing sides, bottom and back filling (Unskilled)
b) Machinery
Hydraulic Excavator 1 cum bucket capacity @ 60 cum / hour
Tipper 5.5 cum capacity, 4 trips per hour
c) Material
Selected earth for refilling

d&e) Overheads & Contractors Profit


Cost for 10 cum = a+b+c+d+e
Rate per cum = a+b+c+d+e)/10
Note :1. Cost of dewatering @ 5 per cent of (a+b) may be added where required. Assessment for de
site conditions.

2. Shoring and shuttering @ 10 per cent of (a+b) may be added where required.
3. It is assumed, that Marshy soil will be available upto 3 m depth only. For deeper excava
analysis in item (i) to (iv) for ordinary soil.

488

RBR_FNDN
VI

Back Filling in Marshy Foundation Pits


Unit : Cum
Taking Output : 6 cum
a)

RBR-FNDN-2

Labour

Mate
Mazdoor (Unskilled) for dressing sides, bottom and backfilling
b)
Machinery
Tractor-trolley for transportation
c&d) Overheads & Contractors Profit
Cost for 6 cum = a+b+c+d
Rate per cum = (a+b+c+d)/6
Filling in foundation trenches as per drawing and technical specification
Clause 305.3.9 MORD & 304 MORTH

II

Sand filling
Unit = cum
a)Labour
Mate
Mazdoor (Unskilled)
b) Material
Sand
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Earth filling (For marshy soil)
Unit = cum
Taking output = 6 cum
a)Labour
Mate
Mazdoor (Unskilled)
b&c) Overheads & Contractors Profit
Cost for 6 cum = a+b+c
Rate per cum = (a+b+c)/6
Note : Cost of transportation of good quality earth has not been included. Only labour for carrying cart
the foundation pits has been taken in the rate. The cost of carted earth may be worked out separately if
the adjoining area.

Backfilling of foundation trenches shall normally be done with excavated earth. The cost of t
item 11.1. Only in case the excavated earth is not of suitable quality, sand filling or backfillin
resort to.

RBR-FNDN-3

Filling annular space around footing in rock as per technical specification


Clause 1203.4.3. MORD
Unit = cum
P.C.C grade M 15
Nominal mix 1:2.5:5 (Hand mixing)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e

489

RBR_FNDN
(a) Filling Annular Space Around Footing in Rock with CC 1:3:6 nominal mix using
40mm nominal size stone aggregate as pre Tech. Specification 304 & 2100 MORTH

Unit = cum
Taking out put = 1 cum
Lean cement concrete 1:3:6 nominal mix. Rate may be taken as per item 11.4.
4

Providing concrete for plain/reinforced concrete in open foundations using 40 mm


nominal size Graded hard stone aggregate, mechanically mixed, placed in
foundation and compacted by vibration including curing for 14 days complete as
per drawings and technical specifications Clause 802, 803, 1202 & 1203 MORD and
1500, 1700 & 2100 MORTH.

RBR-FNDN-4

I
(i)

P.C.C grade M 10
Nominal mix 1:3:6
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
Water
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Mechanical concrete mixer 0.4/0.28 cum capacity fitted with water measuring device and
preferably also with load cell.

Water tanker 6 kl capacity


(d) Formwork @ 4% on cost of material, labour and machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:3:6 (Hand mixing) (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork@4% on cost of material (a) and labour (b)

II
iii

d&e) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e
P.C.C grade M 15 (MORD)
Nominal mix (1:2.5:5) (Mechanical Mixer)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)

490

RBR_FNDN
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
d) Formwork @ 4% on cost of material, labour and machinery (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

Note : Needle Vibrator is an item of minor T & P which is already included in overhead charges. Hence
cement concrete works.

Nominal mix 1:2.5:5 (Hand mixing) (MORD)


Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
V P.C.C. grade M 20 (MORD)
(i) Nominal mix (1:2:4) (Mechanical Mixer)
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
(ii) Nominal mix 1:2:4 (Hand mixed) (MORD)
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 4% out of material and labour (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
iv

491

RBR_FNDN
i P.C.C grade M 15 (Design Mix) MORTH 12.8 A using 40 mm Graded Metal

Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
d) Formwork @ 4% on cost of material, labour and machinery (a+b+c)

ii

e&f) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e+f
P.C.C. grade M 20 (Design Mix) MORTH 12.8 B using 40 mm Graded Metal

Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
C i R.C.C grade M 20 using Concrete mixer (Nominal Mix) using 20 mm
Graded Metal (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

492

RBR_FNDN
ii

R.C.C grade M 20 (Design Mix) using 20 mm Graded Metal (MORTH)


CASE I : Using Concrete Mixer
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 4% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case II : With Batching Plant, Transit Mixer and Concrete Pump (RCC
M20) (Design Mix) (MORTH 12.8 C)
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/ hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 km, L-lead in km
Concrete Pump
d)
Formwork @ 4 per cent on cost of concrete i.e. cost of material, labour
and machinery
e&f) Overheads & Contractors Profit
Cost for 120 cum = a+b+c+d+e+f
Rate per cum = ( a+b+c+d+e+f )/120

PCC Grade M25 using 40 mm Graded Metal (Design Mix) (MORTH 12.8 D)
CASE I : Using Concrete Mixer
Unit = cum
Taking output = cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)

493

RBR_FNDN
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d)
Formwork @ 3.75 per cent of (a+b+c)
e&f) Overheads & Contractors Profit
Rate for cum = a+b+c+d+e+f
CASE II : With Batching Plant, Transit Mixer and Concrete Pump (M 25)
(MORTH 12.8 D)
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
d)
Formwork @ 3.75 per cent of cost of concrete i.e. cost of material, labour and
machinery

e&f) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
E

R.C.C. grade M 25 (Design Mix) using 20 mm Graded Metal (MORD & MORTH 12.8
E)

Case 1 : Using Concrete Mixer


Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
Bhisti
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 3.75% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete Pump (RCC M 25)
(MORTH 12.8 E)

Unit: cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate

494

RBR_FNDN
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
d)
Formwork @ 3.75 per cent on cost of concrete i.e. cost of material,
labour and machinery

e&f) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120
PCC Grade M 30 (MORTH 12.8 F) Design Mix using 40 mm Graded Metal
CASE I : Using Concrete Mixer
Unit = cum
Taking output = cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d)
Formwork @ 3.5 per cent of (a+b+c)
e&f) Overheads & Contractors Profit
Rate for 1 cum = a+b+c+d+e+f
CASE II : With Batching Plant, Transit Mixer and Concrete Pump (PCC M
30) Design Mix
Unit : cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

495

RBR_FNDN
d)
Formwork @ 3.5 per cent of cost of concrete i.e. cost of material, labour
and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
G

R.C.C. grade M 30 Design Mix, using 20 mm Graded Metal (MORTH 12.8


G)
Case 1 : Using Concrete Mixer
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 3.5% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete Pump (RCC M
30) Design Mix
Unit: cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
d)
Formwork @ 3.5 per cent on cost of concrete i.e. cost of material,
labour and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120

R.C.C. grade M 35 Design Mix using 20 mm Graded Metal (MORTH 12.8.H)


Case 1 : Using Concrete Mixer
Unit = cum
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate

496

RBR_FNDN
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 3% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case 2 : With Batching Plant, Transit Mixer and Concrete Pump (RCC
M35) Design Mix
Unit: cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity 1 cum
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity lead beyond 1 Km, L - lead in Kilometer

Concrete Pump
Vibrator
d)
Formwork @ 3 per cent on cost of concrete i.e. cost of material, labour
and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum (a+b+c+d+e+f )/120

Note : Where ever concrete is carried out using batching plant, transit mixer, concrete pump, Admixture
cement may be added for achieving desired slump of concrete.

NOTE : Concrete used in any component or structure shall be specified by designation along with presc
i.e., "Design Mix" or "Nominal Mix". For all items of concrete, only "Design Mix" shall be used, except wh
permitted as per drawing or by the Engineer. "Nominal Mix" may be permitted only for minor bridges a
construction where strength requirements are upto M 20 only. "Nominal Mix" may also be permitted for
screed below open foundations.

Note : Water : A provision for cost of water may be added at 1.2 kl / 1 cum (including curing

conditions

Coarse Aggregate : Single grade nominal size can also be used instead of graded metal, ke

view
5

Brick masonry work in cement mortar in foundation complete excluding pointing


and plastering as per drawing and technical specifications Clauses 600, 1202 &
1203 MORD / 1300 MORTH with Second Class Bricks & Moulded Bricks

RBR-FNDN-5

Unit = cum
Brick masonry in 1:3 cement mortar
(a) Material
Bricks
Cement mortar 1:3 (Rate as per Sub-analysis)
(b) Labour
Mate
Mason (1st Class)

497

RBR_FNDN

II

III

Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:3 (1 cement : 3 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
Brick masonry in 1:4 cement mortar
Unit = cum
(a) Material
Bricks
Cement mortar 1:4
Rates as per sub-analysis
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:4 (1 cement : 4 sand)
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
Brick masonry in cement-lime-mortar (1:0.5:4.5)
Unit = cum
(a) Material
Bricks
Cement lime mortar rates as per sub-analysis
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement-lime-mortar 1:0.5:4.5 (1 cement: 0.5 lime putty : 4.5 sand)

Unit = cum
(a) Material
Cement
Lime putty
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
Note : i. To provide 512 Nos Bricks Traditional size 23 x 11 x 7 cms and 520 Nos Modular Bric
ii. Compressive strength of individual Brick shall not be less than 70 kg / cm 2

498

RBR_FNDN
6

Stone masonry work in cement mortar in foundation complete as per drawing and
technical specifications Clauses 702, 704, 1202 & 1203 MORD and 1405 MORTH.

RBR-FNDN-6

Unit = cum
Coursed rubble masonry (1st sort)
(i) CRS 1st Sort in 1:3 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
I

Cement mortar (1:3) (Rate as in item 11.5 I)


(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(ii) CRS 1st Sort in 1:4 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar 1:4 (Rate as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iii) CRS First Sort in cement-lime-sand mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for C.R. masonry 1st sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : Quantity of required chips has not been provided for separately as it is assumed
that the same will be available from dressing of stones.
II
(i)

Coursed rubble masonry (2nd sort)


In 1:3 cement mortar
Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 I.)
Water
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

499

RBR_FNDN
(ii) CRS 2nd Sort in 1:4 cement mortar

Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (Rate as in item 11.5 II)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iii) CRS 2nd Sort in cement-lime-mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for C.R. masonry 2nd sort
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)

cement-lime-mortar (1:0.5:4.5) (Rate as in item 11.5 III)


(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III Random Rubble Masonry
(i) In 1:3 cement mortar
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:3) (Rate as in item 11.5 I)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(ii) RR Masonry in cement mortar 1:4
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:4) (Rate as in item 11.5 II)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d

500

RBR_FNDN
(iii) RR Masonry in cement mortar 1:6

Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement mortar (1:6) (Rate as in Sub Analysis)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub Analysis :
Cement Mortar 1:6
Unit = cum
(a) Material
Cement
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)
(iv) RR Masonry in cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
CR Stone
Stone for R.R. masonry
Through bond stone (7 nos 0.24 x 0.24 x 0.39 = 0.16 cum)
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : Quantity of required chips has not been provided for separately as it is assumed
that the same will be available from dressing of stones
7

RBR-FNDN-7

Supplying, fitting and placing HYSD bar reinforcement in foundation


complete as per drawings and technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars below 36 mm dia including
over laps and wastage, where they are not welded.
Unit = t
(a) Material
HYSD bars including 5 per cent for overlaps and wastage

Binding wire
(b) Labour for cutting, bending, shifting to site, tying and placing in
position
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

501

RBR_FNDN
A

Supplying, fitting and placing HYSD bar reinforcement in foundation


complete including wastage, as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for
Bars 36 mm dia and above, where welding required to be done
compulsorily.
Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and placing in
position
Welder
Blacksmith
Mazdoor (Unskilled)
(c) Overheads on (a+b)
(d) Contractors profit on (a+b+c)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
Supplying, fitting and placing TMT bar reinforcement in foundation
complete as per drawings and technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars below 36 mm dia including
over laps and wastage, where they are not welded.

RBR-FNDN-8

Unit = t
(a) Material
TMT bars including 5 per cent for overlaps and wastage
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and placing in
position

Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
Supplying, fitting and placing TMT bar reinforcement in foundation
complete including wastage, as per drawings and technical
specifications Clauses 1000 and 1202 MORD & 1100, 1600 MORTH for
Bars 36 mm dia and above, where welding required to be done
compulsorily.
Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and placing in
position
Welder
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

502

RBR_FNDN
Supplying, fitting and placing MS bar reinforcement in foundation
complete as per drawings and technical specifications Clauses 1000 and
1202 MORD & 1100, 1600 MORTH for Bars below 36 mm dia including
over laps and wastage, where they are not welded.

RBR-FNDN-9

Unit = t
(a) Material
MS bars including 5 per cent for overlaps and wastage
Binding wire
(b) Labour for cutting, bending, shifting to site, tying and placing in
position
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
WELL FOUNDATION
Providing and Constructing Temporary Island 16 m diameter for
Construction of Well Foundation for 8m dia. Well as per Tech.
Specification 1203 MORTH.

10

RBR-FNDN-10
A

Assuming depth of water 1.0 m and height of island to be 1.25 m.

Unit = 1 No
Taking output = 1 No.
a) Material
Earth (compacted)
Sand bags
b)
Labour
Mate
Mazdoor for filling sand bags, stitching and placing
c)
Machinery
Crane with grab 1 cum capacity
Consumables @ 2.5 per cent of (c) above
d&e) Overheads & Contractors Profit
Rate per No. (a+b+c+d+e)
Note : It is assumed that earth will be available within the working space of crane with grab bu
B

Assuming depth of water 4.0 m and height of island 4.5 m.

Unit = 1No
Taking output = 1 No
a) Material
Earth (compacted)
Sand bags
Wooden ballies 8" Dia and 9 m long
Wooden ballies 2" Dia for bracing
b)
Labour
Mate
Mazdoor for piling 8" dia ballies for piling 8" dia ballies
Mazdoor for bracing with 2" dia ballies
Mazdoor for filling sand bags, stitching and placing
c)
Machinery
Crane with grab 1 cum capacity
Consumables and other arrangements for piling ballies @ 2.5 per cent of
(a+b+c).
d&e) Overheads & Contractors Profit
Rate per No. (a+b+c+d+e)
Note : For other well diameters rate can be worked out on the basis of cross-sectional area
island shall be in the conformity with clause 1203.2 of MoRTH specifications.

503

RBR_FNDN
C

Providing and constructing one span service road to reach island


location from one pier location to another pier location as per Tech.
Specification 1203 MORTH.
Assuming span length 30 m, width of service road 10m and depth of water 1m
Unit = 1 meter
Taking output = 30 metre
a) Material
Earth
Sand bags
b)
Labour
Mate
Mazdoor (Unskilled) for filling sand bags, stitching and placing

c)
Machinery
Front end Loader 1 cum capacity
Tipper 5.5 cum capacity
d&e) Overheads & Contractors Profit
Cost for 30 m = (a+b+c+d+e)
Rate per m = (a+b+c+d+e)/30
11

Providing and Laying Cutting Edge of Mild Steel weighing 40 kg per metre for Well
Foundation complete as per Drawing and Technical Specification 1204, 1900
MORTH.

RBR-FNDN-11

Unit = 1 MT
Taking output = 1 MT
a) Material
Structural steel in plates, angles, etc including 5 per cent wastage

Nuts & bolts


b)
Labour
(for cutting, bending, making holes, joining, welding and erecting in position)

Mate
Fitter
Blacksmith
Welder
Mazdoor (Unskilled)
Electrodes, cutting gas and other consumables @ 10 per cent of cost of (a) above

Handling loading and unloading on (a)


Hire charges of Welding machine on (a)
c&d) Overheads & Contractors Profit
Rate per MT (a+b+c+d)
Plain/Reinforced Cement Concrete, in Well Foundation complete as per
Drawing and Technical Specification 1200, 1500 & 1700 MORTH.

12

RBR-FNDN-12

Unit = 1 cum
Taking output = 1 cum
A

Well Curb

(i)

RCC M20 Grade


Same as per 4.C.(ii) Case I, except for formwork which shall be@ 20 per cent of the
cost of concrete instead of 4 per cent.

Case 1 : Using Concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 20 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate per m (a+b+c+d+e+f)

504

RBR_FNDN
Case II : With Batching Plant, Transit Mixer and Concrete Pump as per
4.C.(ii) Case II
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(ii) RCC M25 Grade

Same as per 4.E except for formwork which shall be@ 20 per cent of the cost
of concrete instead of 3.75 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4.E

d) formwork @ 20 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) RCC M35 Grade
Same as for 4(H) except for formwork which shall be@ 20 per cent of the cost
of concrete instead of 3.0 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d) formwork @ 20 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4H

d) formwork @ 20 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Note : If curb concrete is carried out within steel liner, cost of formwork shall be
excluded.
(B)
I

II

Well staining
PCC M15 Grade (Design Mix) using 40 mm Graded Metal
Same as per 4 B(i) except for formwork which shall be @ 10 per cent of the
cost of concrete instead of 4 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate per m (a+b+c+d+e+f)
PCC M20 Grade (Design Mix) using 40 mm Graded Metal
Same as per 4 B(ii) except for formwork which shall be @ 10 per cent of the
cost of concrete instead of 4 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate per m (a+b+c+d+e+f)

505

RBR_FNDN
III

RCC M20 Grade (Design Mix) using 20 mm Graded Metal


Same as per 4C (ii) except for formwork which shall be @ 10 per cent of the
cost of concrete instead of 4 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d) formwork @ 10 per cent of the cost of concrete
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as per 4C (ii)

d) formwork @ 10 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
IV PCC M25 Grade Design Mix
Same as per 4D except for formwork which shall be @ 10 per cent of the cost
of concrete instead of 3.75%
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
RCC M25 Grade Design Mix
Same as per 4 E except for formwork which shall be @ 10 per cent of the cost
of concrete instead of 3.75 %
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4 E
d) formwork @ 10 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VI PCC M30 Grade Design Mix
Same as for 4 (F) except for formwork which shall be @ 10 per cent of the
cost of concrete instead of 3.5 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

506

RBR_FNDN
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4 F
d) formwork @ 10 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VII RCC M30 Grade Design Mix
Same as for 4(G) except for formwork which shall be @ 10 per cent of the cost
of concrete instead of 3.5 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4G


d) formwork @ 10 per cent of the cost of concrete
e)
Overhead charges @ input on (a+b+c+d)
f)
Contractor's profit @ input on (a+b+c+d+e)
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
VIII RCC M35 Grade
Same as for 4 (H) except for formwork which shall be @ 10 per cent of the
cost of concrete instead of 3 per cent.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d) formwork @ 10 per cent of the cost of concrete


Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) as in 4 H
d) formwork @ 10 per cent of the cost of concrete
Water
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
IX RCC M40 Grade (Design Mix) using 20 mm Graded Metal
Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Meson
Mazdoor (Unskilled)
c)
Machinery
Batching Plant
Generator 100 KVA

507

RBR_FNDN
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity for lead beyond 1 km.
Concrete Pump
d)
Formwork @ 10 per cent on cost of concrete i.e. cost of material, labour
and machinery
e&f) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e+f
Rate per cum = (a+b+c+d+e+f)/120
(C) Bottom Plug
Concrete to be placed using tremie pipe
Note : 10% extra cement to be added where under water concreting is involved
(i)

PCC Grade M20 Design Mix


Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane 3 tonnes capacity for handling tremie pipe
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
(PCC M20)
Unit ; cum
Taking Output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.

508

RBR_FNDN
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Add 5 per cent of cost of material and labour towards cost of forming sump,
protective bunds, chiselling and making arrangements for under water
concreting with tremie pipe.
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(ii) PCC Grade M25 Design Mix
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
(PCC M25)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

509

RBR_FNDN
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(iii) PCC Grade M30 Design Mix
Case I : Using Concrete Mixer
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
(PCC M30)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer

Concrete Pump
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

510

RBR_FNDN
(iv) PCC Grade M35 Design Mix

Case 1 : Using Concrete Mixer


Unit = 1 cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Light Crane of 3 tonnes capacity for handling tremie pipe
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
(PCC M35)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity, lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Add 5 per cent of cost of material and labour towards cost of forming sump, protective
bunds, chiselling and making arrangements for under water concreting with tremie pipe.

d&e) Overheads & Contractors Profit


cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

511

RBR_FNDN
(D)
(i)

Intermediate plug
Grade M20 PCC Design Mix
Same as in bottom plug concrete, excluding cost of forming sump, protective
bunds, chiseling etc.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(ii) Grade M25 PCC Design Mix
Same as in bottom plug concrete, excluding cost of forming sump, protective
bunds, chiseling etc.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)
d&e) Overheads & Contractors Profit
Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(iii) Grade M30 PCC Design Mix
Same as in bottom plug concrete, excluding cost of forming sump, protective
bunds, chiseling etc.
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(E) Top plug
(i) Grade M15 PCC Design Mix
Same as Item 4.B(i) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(ii) Grade M20 PCC Design Mix
Same as Item 4.B(ii) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(iii) Grade M25 PCC Design Mix
Same as Item 4(D) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)

512

RBR_FNDN
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(iv) Grade M30 PCC Design Mix
Same as Item 4(F) excluding formwork
Case 1 : Using Concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
Case II : Using Batching Plant, Transit Mixer and Crane/concrete pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c)

d&e) Overheads & Contractors Profit


Rate per cum = (a+b+c+d+e)
(F) Well cap
(i) RCC Grade M20 (Design Mix)
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Form Work @ 4 per cent of a+b+c
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Concrete Pump (RCC M 20)

Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump

513

RBR_FNDN
Formwork @ 4 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(ii) RCC Grade M25 (Design Mix)
Case I : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Form Work of a+b+c
Centering Charges
Water
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Concrete Pump (RCC M
25)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3.75 per cent of ( a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120

514

RBR_FNDN
(iii) RCC Grade M30 (Design Mix)

Case 1 : Using Concrete Mixer


Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Formwork @ 3.5 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Concrete Pump (RCC M
30)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 3.5 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
(iv) RCC Grade M35 (Design Mix)
Case 1 : Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm Aggregate
20 mm Aggregate
b)
Labour
Mate
Mason

515

RBR_FNDN
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
Formwork @ 3 per cent of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 15 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/15
Case II : Using Batching Plant, Transit Mixer and Concrete Pump (RCC M
35)
Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m ) :
Transit Mixer 4 cum capacity for lead upto 1 km.
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork of (a+b+c)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
Note : Where ever concrete is carried out using batching plant, transit mixer,
concrete pump, Admixtures @ 0.4 per cent of weight of cement may be added
for achieving desired slump of concrete.
(v) RCC M40 Grade (Design Mix)

Using Batching Plant, Transit Mixer and Concrete Pump


Unit = cum
Taking output = 120 cum
a) Material
Cement
Coarse Sand
20 mm Aggregate
10 mm Aggregate
Admixture
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Batching Plant
Generator 100 KVA
Loader 1 cum capacity
Transit Mixer 4 cum capacity for lead upto 1 km.
Transit Mixer 4 cum capacity for lead beyond 1 km.

516

RBR_FNDN
Concrete Pump
Formwork on cost of concrete i.e. cost of material, labour and machinery
d)
Overhead charges @ input on (a+b+c)
e)
Contractor's profit @ input on (a+b+c+d)
d&e) Overheads & Contractors Profit
cost of 120 cum = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/120
13

RBR-FNDN-13

Sinking of 6 m external diameter well (other than pneumatic method of


sinking) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

Note : To arrive proportionate quantities keeping the cross sectional area


& depth (22/7xd2xh) for lesser diametre wells than 6m
Unit = Running Meter.
Taking output = 1 m
Diameter of well - 6 m.
(A) Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.50 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking = 0.33 m per hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10m upto 20m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.

517

RBR_FNDN
(B) Clayey Soil ( 6m dia. Well )

Unit = Running Meter.


Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.33 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m

Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
Add 5 per cent of cost for dewatering of the cost, if required

Add 25 per cent of cost for Kentledge including supports, loading arrangement
and Labour ).
(v) Beyond 30m upto 40 m

Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
Add 5 per cent of cost for dewatering, if required
Add 20 per cent of cost for Kentledge including supports, loading arrangement
and Labour).
(C)

Soft Rock (6m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in Soft rock strata up to 3m
Rate of sinking = 0.25 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver

518

RBR_FNDN
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(D) Hard Rock (6m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer
for drilling.

14

RBR-FNDN-14

Dewatering @ 5 per cent of cost of (b+c), if required.


Consumables in sinking @ 10 per cent of cost of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
Sinking of 7 m external diameter well (other than pneumatic method of
sinking) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 7 m.
(A) Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.30 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

519

RBR_FNDN
(ii) Beyond 3m upto 10m depth

Rate of sinking = 0.22 m per hour.


a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10m upto 20m
a. Add 5 per cent for every additional meter depth of sinking over the rate of sinking for
the previous meter
(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking
for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading arrangement and
Labour).
(v) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of sinking over the rate of sinking for
the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading arrangement, and
Labour etc.
(B) Clayey Soil ( 7m dia. Well )

Unit = Running Meter.


Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking = 0.22 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @ 10 per cent of (b)
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking = 0.17 m per hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.

520

RBR_FNDN
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
(C)

Soft Rock ( 7m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking = 0.22 m per hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.

Air compressor with pneumatic breakers


Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
c)
Overhead charges @ input on (a+b)
d)
Contractor's profit @ input on (a+b+c)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(D) Hard Rock ( 7m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in Hard rock strata up to 3 m
Rate of sinking = 0.17 m per hour.
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
Diver
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer
for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of cost of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)

521

RBR_FNDN
Sinking of 8 m external diameter well (other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

15

RBR-FNDN-15

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 8 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.20 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
Clayey Soil ( 8m dia. Well )
Unit = Running Meter.
Taking output = 1 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
B

522

RBR_FNDN
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
C

Soft Rock ( 8m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.20 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

523

RBR_FNDN
D

Hard Rock ( 8m dia well )


Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.17 m/hour
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer
for drilling.

16

RBR-FNDN-16

Dewatering @ 5 per cent of cost of (b+c), if required.


Consumables in sinking @ 10 per cent of cost of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
Sinking of 9 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

Unit = Running Meter.


Taking output = 1 m
Diameter of well - 9 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.25 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.18 m/hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

524

RBR_FNDN
(iii) Beyond 10m upto 20m

a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
Clayey Soil ( 9m dia. Well )
Unit = Running Meter.
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.17 m / hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
B

Consumables in sinking @ 10 per cent of (b)


c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking 0.15 m / hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).

525

RBR_FNDN
C

Soft Rock ( 9m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata up to 3m
Rate of sinking 0.15 m / hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ of 5 per cent of (a+b), if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Hard Rock ( 9m dia well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.15 m / hour
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
Diver
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer
for drilling.
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of cost of (c).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)

17

RBR-FNDN-17

Sinking of 10 m external diameter well (other than pneumatic method of sinking)


through all types of strata namely sandy soil, clayey soil and rock as shown
against each case, complete as per drawing and technical specifications 1207
MORTH. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 1 m
Diameter of well - 10 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.20 m / hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )

526

RBR_FNDN
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking 0.17 m / hour
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
Clayey Soil (10m dia. Well )
Unit = Running Meter
Taking output = 1 cum
(i) Depth below bed level upto 3.0 M
Rate of sinking 0.18m/hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
B

Consumables in sinking @ 10 per cent of (b)


c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking 0.15m/hour.
a) Labour
Mate
Sinker
Sinking helper ( semi-skilled )
b)
Machinery
a. Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
b. Air compressor with pneumatic chisel attachment for cutting hard clay

c. Consumables in sinking @ 10 per cent of (b)


c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)

527

RBR_FNDN
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of sinking for
the previous meter

b. Add for dewatering @ 5 per cent of cost, if required.


(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of sinking over the rate of sinking
for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading arrangement and
Labour ).
(iv) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of sinking over the rate of sinking for
the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading arrangement and
Labour).
C

Soft Rock (10m dia well )


Unit = Running Meter.
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking 0.14m/hour.
a) Labour
Mate
Sinker ( skilled )
Sinking helper ( semi-skilled )
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ 5 per cent of cost, if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Hard Rock (10m dia well )
Unit = Running Meter.
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking 0.12 m/ hour.
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer or
drill
Dewatering @ 5 per cent of cost (c), if required.
Consumables in sinking @ 10 per cent of cost of (c).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)

528

RBR_FNDN
Sinking of 11 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

18

RBR-FNDN-18

Unit = Running Meter


Taking output = 0.50 m
Diameter of well - 11 m.
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.15 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
d&e) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.13 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
(iii) Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
Clayey Soil (11 m dia. Well )
Unit = Running Meter
Taking output = 0.50 meter
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.10 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
B

529

RBR_FNDN
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.08 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
C

Soft Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.06 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic breakers
Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ 5 per cent of cost, if required
c&d) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50

530

RBR_FNDN
D

Hard Rock (11m dia well )


Unit = Running Meter.
Taking output = 0.50 m
Depth in hard rock upto 3 m
Rate of sinking @ 0.05 m/hour
a) Material
Gelatine 80 per cent
Electric Detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer or
drill

19

RBR-FNDN-19

Dewatering @ 5 per cent of cost (c), if required.


Consumables in sinking @ 10 per cent of cost of (c).
d&e) Overheads & Contractors Profit
Cost for 0.5m = a+b+c+d
Rate per metre = (a+b+c+d)/0.50
Sinking of 12 m external diameter well ( other than pneumatic method of
sinking ) through all types of strata namely sandy soil, clayey soil and
rock as shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

Unit = Running Meter


Taking output = 0.25 m
Diameter of well - 12 m.
A Sandy Soil
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.05 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.038 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Consumables in sinking @10 per cent of (b)


c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25

531

RBR_FNDN
(iii) Beyond 10m upto 20m

a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
Clayey Soil (12 m dia. Well )
Unit = Running Meter.
Taking output = 0.25 meter.
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.04 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
B

Consumables in sinking @ 10 per cent of (b)


c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.03 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).

532

RBR_FNDN
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering, if required
c. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour).
C

Soft Rock (12m dia well )


Unit = Running Meter
Taking output = 0.25 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.025 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.

Consumables in sinking @ 10 per cent of (b)


Add for dewatering @ 5 per cent, if required
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d
Rate per metre = (a+b+c+d)/0.25
Hard Rock (12m dia well )
Unit = Running Meter
Taking output = 0.25 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.020 m/hour
a) Material
Gelatine80 per cent
Electric detonator
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker / Jack hammer
or drill
Dewatering @ 5 per cent, if required.
Consumables in sinking @ 10 per cent of (c).
c&d) Overheads & Contractors Profit
Cost for 0.25m = a+b+c+d+e
Rate per metre = (a+b+c+d+e)/0.25

533

RBR_FNDN
Sinking of Twin D Type well (other than pneumatic method of sinking)
through all types of strata namely sandy soil, clayey soil and rock as
shown against each case, complete as per drawing and technical
specifications 1207 MORTH. Depth of sinking is reckoned from bed level.

20

RBR-FNDN-20

Unit = Running Meter


Taking output = 1 m
Dimensions of well.
Overall length = 12 m
Overall width = 6 m
A Sandy Soil
(i) Depth from bed level upto 3.0 M
Rate of sinking @ 0.18 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(ii) Beyond 3m upto 10m depth
Rate of sinking @ 0.17 m/hour
a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Consumables in sinking @10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10m upto 20m
Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
(iv) Beyond 20m upto 30 m
a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement and Labour.
(v) Beyond 30m upto 40 m

a. Add 10 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 20 per cent of cost for Kentledge including supports, loading
arrangement, and Labour etc.
Clayey Soil (Twin D Type Well )
Unit = Running Meter
Taking output = 1 meter
(i) Depth below bed level upto 3.0 M
Rate of sinking @ 0.16 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
B

Consumables in sinking @ 10 per cent of (b)


c&d) Overheads & Contractors Profit

534

RBR_FNDN
Rate per metre = (a+b+c+d)

535

RBR_FNDN
(ii) Beyond 3m upto 10m depth

Rate of sinking @ 0.15 m/hour


a) Labour
Mate
Sinker
Sinking helper (semi-skilled)
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Air compressor with pneumatic chisel attachment for cutting hard clay.
Consumables in sinking @ 10 per cent of (b)
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
(iii) Beyond 10 m upto 20 m
a. Add 5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add for dewatering @ 5 per cent of cost, if required.
(iv) Beyond 20m upto 30 m

a. Add 7.5 per cent for every additional meter depth of sinking over the rate of
sinking for the previous meter
b. Add 5 per cent of cost for dewatering on the cost, if required
c. Add 25 per cent of cost for Kentledge including supports, loading
arrangement and Labour ).
(v) Beyond 30m upto 40 m
a. Add 10 per cent for every additional meter depth of sinking over the rate of sinking for
the previous meter

b. Add 5 per cent of cost for dewatering, if required


c. Add 20 per cent of cost for Kentledge including supports, loading arrangement and
Labour).
C

Soft Rock (Twin D Type Well )


Unit = Running Meter
Taking output = 1 m
Depth in soft rock strata upto 3m
Rate of sinking @ 0.12 m/hour
a) Labour
Mate
Sinker ( skilled )
Sinking helper (semi-skilled)
Diver
b)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

Air compressor with pneumatic breakers


Consumables in sinking @ 10 per cent of (b)
Add for dewatering @ 5 per cent, if required
c&d) Overheads & Contractors Profit
Rate per metre = (a+b+c+d)
Hard Rock (Twin D Type Well )
Unit = Running Meter
Taking output = 1 m
Depth in hard rock strata upto 3 m
Rate of sinking @ 0.10 m/hour
a) Material
Geletine80 per cent
Electric detonators
b)
Labour
Mate
Driller
Blaster
Mazdoor (Unskilled)
Mazdoor (Skilled)

536

RBR_FNDN
c)
Machinery
Hire & running charges of crane with grab bucket of 0.75 cum capacity and
accessories.
Hire & running charges of compressor with pneumatic breaker/Jack hammer or
drill
Dewatering @ 5 per cent of cost of (b+c), if required.
Consumables in sinking @ 10 per cent of (b).
d&e) Overheads & Contractors Profit
Rate per metre = (a+b+c+d+e)
21

RBR-FNDN-21

Pneumatic sinking of wells with equipment of approved design, drawing and


specifications worked by competent and trained personnel and comprising of
compression and decompression chambers, reducers, two air locks separately for
men and plant & materials, arrangement for supply of fresh air to working
chambers, check valves, exhaust valves, shafts made from steel plates of riveted
construction not less than 6 mm thick to withstand an air pressure of 0.50 MPa,
controlled blasting of hard rock where required, staircases and 1 m wide landing
platforms with railing, arrangement for compression and decompression, electric
lighting of 50 V maximum, proper rooms for rest and medical examinations and
compliance with safety precautions as per IS:4138, all as per clause1207.6 of
MoRTH Specifications.

Unit - 1 cum
Taking output = 5 cum
a) Material
M35 grade RCC corbel provided for supporting of equipment (Dimensions as
per ground conditions). Rate may be adopted vide Item 4 (H)
HYSD bar reinforcement in corbel
Blasting material
Gelatine 80 per cent
Electric detonators
b)
Labour
Medical Officer
Para medical personnel
Mate
Driller
Blaster
Mazdoor unskilled (for cutting, blasting, cleaning, removal of Material etc.)
Mazdoor (Skilled) (for fixation and removal of adopter for air lock, carrying out
mechanical and electrical operations and repairs and other skilled jobs.)

Diver
c)
Machinery
(i) Induction, denudation and erection of plant and equipment including
all components and accessories for pneumatic method of well sinking.
Induction and denudation
Erection at site and commissioning
Usage of plant and equipment for pneumatic method of well sinking
Air compressor 250 cfm, 2 nos.
Hire and running charges of crane of 15 tonne capacity
Motorised barge of 20 tonne capacity
Boat to carry at least 20 persons
Electric generating set 33 KVA
Tipper 10 tonne capacity
d&e) Overheads & Contractors Profit
Cost for 5 cum = a+b+c+d+e (see notes below)
Rate per cum = (a+b+c+d+e)/5

537

RBR_FNDN

Note : 1. The cost of induction, denudation and erection of equipment shall be divided by the total quan
the wells of a particular bridge to arrive at the per cum rate on account of this item.

2. Cost of pneumatic sinking per cum of individual wells will be added to the cost indicated at (1) abo
pneumatic sinking per cum.

3. The cost of induction and denudation will depend upon the distance involved for shifting of equipme
individual cases as per actual ground conditions at the time of making of cost estimates.
4. In case pneumatic sinking is involved on a dry bed, the provision of barge and boat may be omitted.
5. The necessity and dimensions of the corbel will be as per actual ground conditions.

6. Small equipments like welding sets, pumps, vibrators, pneumatic tools, portable lamps, fire extinguish
been included as the same are covered as items of minor T&P under overhead charges.

RBR-FNDN-22

22

7. Depth of sinking shall be restricted to 30 m.


Sand Filling in Wells complete as per Drawing and Technical Specifications 1207
MORTH.

Unit = 1 cum
Taking output = 1 cum
a) Material
Sand (assuming 20 per cent voids )
b)
Labour
Mate
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per cum (a+b+c+d)
23

RBR-FNDN-23

Providing Steel Liner 10 mm thick for Curbs and 6 mm thick for Staining of Wells
including Fabricating and Setting out as per Detailed Drawing as per Tech.
Specifications 1200 & 1900 MORTH.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage
b)
Labour
Mate
Fitter
Blacksmith
Welder
Mazdoor (Unskilled)
Electrodes, cutting gas and other consumables @ 5 per cent on cost a (a) above.

c&d) Overheads & Contractors Profit


Rate for per MT (a+b+c+d)
24

RBR-FNDN-24

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per
Drawing and Technical Specifications in Section 1100 & 1700 MORTH and removal
of excavated earth with all lifts and lead upto 1000 m.

Pile diameter-750 mm
Unit = meter
Taking output = 15 m
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power unit and complete
accessories including shifting from one bore location to another.

Hire and running charges of Bentonite pump


Hire and running charges of light crane for lowering reinforcement cage

Loader I cum bucket capacity.

538

RBR_FNDN
Tipper 5.5 cum capacity for disposal of muck from pile bore hole

539

RBR_FNDN
Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 15 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/15
25

RBR-FNDN-25

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per
Drawing and Technical Specifications in Section 1100, 1600 & 1700 MORTH and
removal of excavated earth with all lifts and lead upto 1000 m.

Pile diameter-1000 mm
Unit = meter
Taking output = 10 m
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12 ( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power unit and complete
accessories including shifting from one bore location to another.

Hire and running charges of Bentonite pump


Hire and running charges of light crane for lowering reinforcement cage
Loader I cum bucket capacity.
Tipper 5.5 cum capacity for disposal of muck from pile bore hole

Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 10 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/10
26

RBR-FNDN-26

Bored cast-in-situ M35 grade R.C.C. Pile excluding Reinforcement complete as per
Drawing and Technical Specifications in Section 1100 & 1700 MORTH and removal
of excavated earth with all lifts and lead upto 1000 m.

Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b)
Machinery( for boring and construction )
Hire and running charges of hydraulic piling rig with power unit and complete
accessories including shifting from one bore location to another.

Hire and running charges of Bentonite pump


Hire and running charges of light crane for lowering reinforcement cage
Loader I cum bucket capacity.
Tipper 5.5 cum capacity for disposal of muck from pile bore hole

Bentonite
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
d&e) Overheads & Contractors Profit
Cost for 9 m = a+b+c+d+d+e
Rate per metre (a+b+c+d+e)/9

540

RBR_FNDN
27

RBR-FNDN-27

Driven cast-in-place vertical M35 grade R.C.C. Pile excluding Reinforcement


complete as per Drawing and & Technical Specification in Section 1100 & 1700
MORTH

Pile diameter - 750 mm


Unit = Running meter
Taking output = 40 metre
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( C ) (IV)
b)
Materials Pile shoes
i) C.I. shoes for the pile
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
iii) Steel helmet and cushion block on top of casing head during driving
c)
Machinery
Hire and running charges of piling rig Including double acting pile driving
hammer complete with power unit and accessories.
Hiring and running charges for light crane 5 tonnes lifting capacity for lowering
reinforcement and handling steel casing.
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 40 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/40
Note : 1.The quantity of concrete required to be removed above the designed top level of concrete, if
rate analysis.

2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained,
the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an a
of cost of concrete may be provided to cover its usage.
28

RBR-FNDN-28

Driven cast-in-place vertical M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and & Technical Specification in
Section 1100 & 1700 MORTH
Pile diameter - 1000 mm
Unit = Running meter
Taking output = 30 metre
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12 ( C ) (IV)
b) Materials Pile shoes
i) C.I. shoes for the pile
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
iii) Steel helmet and cushion block on top of casing head during driving
c)
Machinery
Hire and running charges of piling rig Including double acting pile driving
hammer complete with power unit and accessories.
Hiring and running charges for light crane 5 tonnes lifting capacity for lowering
reinforcement and handling steel casing.

Hire and running charges for light crane for lowering reinforcement cage.
d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 30 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/30

541

RBR_FNDN

Note : 1.The quantity of concrete required to be removed above the designed top level of concrete, if
rate analysis.
2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained,
the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an a
of cost of concrete may be provided to cover its usage.
29

RBR-FNDN-29

Driven cast-in-place vertical M35 grade R.C.C. Pile excluding


Reinforcement complete as per Drawing and & Technical Specification in
Section 1100 & 1700 MORTH
Pile diameter - 1200 mm
Unit = Running meter
Taking output = 20 metre
a) Materials
PCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( C ) (IV)
b)
Materials Pile shoes
i) C.I. shoes for the pile
ii) M.S. clamps for shoe @ 35 Kg per pile of 15 m
iii) Steel helmet on top of casing head during driving
c)
Machinery
Hire and running charges of piling rig Including double acting pile driving hammer
complete with power unit and accessories.
Hiring and running charges for light crane 5 tonnes lifting capacity for lowering
reinforcement and handling steel casing.

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
e&f) Overheads & Contractors Profit
Cost for 20 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/20
Note : 1. The quantity of concrete required to be removed above the designed top level of concrete, if
rate analysis.

2. In case steel lining is included in the design for driven cast-in-situ pile and is planned to be retained,
the rate analysis. In case the temporary steel casing used during casting is planned to be removed, an a
of cost of concrete may be provided to cover its usage.
30

RBR-FNDN-30

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete
as per Drawing and & Technical Specification in Section 1100 & 1700 MORTH

Pile Diameter = 500 mm


Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( F ) (IV)
b ) Material Pile shoes
a) C.I Shoes
b) M.S. shoes
c) Steel helmet and cushion block on top of pile head during driving.

c)
Machinery
Crane20 t capacity
Vibrating Pile driving hammer complete with power unit and accessories.

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 1 per cent of (a+b+c)
for carriage of piles from casting yard to work site and
stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 60 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/60

542

RBR_FNDN

31

RBR-FNDN-31

Note : The quantity of concrete required to be removed above the designed top level of concrete, if any,
analysis.
Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete
as per Drawing and & Technical Specification in Section 1100 & 1700 MORTH

Pile Diameter = 750 mm


Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( F ) (IV)
b ) Material Pile shoes
a) C.I. shoes
b) M.S. shoes
c) Steel helmet and cushion block on top of pile head during driving.

c)
Machinery
Crane 40 T capacity
Vibrating Pile driving hammer complete with power unit and accessories.

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 1 per cent of (a+b+c)
for carriage of piles from casting yard to work site and
stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 50 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/50
Note : The quantity of concrete required to be removed above the designed top level of conc
for in the rate analysis.
32

RBR-FNDN-32

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete
as per Drawing and & Technical Specification in Section 1100 & 1700 MORTH

Pile Diameter = 1000 mm


Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M35
Rate for concrete may be adopted same as for bottom plug vide item no. 12( F ) (IV)

b ) Material Pile shoes


a) C.I. shoes for the pile
b) M.S. shoes @ 35 Kg per pile of 15 m
c) Steel helmet and cushion block on top of pile head during driving.

c)
Machinery
Crane 50 t capacity.
Vibrating Pile driving hammer complete with power unit and accessories.

d)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 1 per cent of (a+b+c)
for carriage of piles from casting yard to work site and
stacking, and other imponderables during installation.

e)
Overhead charges @ input on (b+c+d)
f)
Contractor's profit @ input on (b+c+d+e)
e&f) Overheads & Contractors Profit
Cost for 40 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/40
Note : The quantity of concrete required to be removed above the designed top level of conc
for in the rate analysis.

543

RBR_FNDN
33

RBR-FNDN-33

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete
as per Drawing and & Technical Specification in Section 1100 & 1700 MORTH

Size of pile - 300 mm x 300 mm


Unit = Running Meter
Taking output = 60 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( F ) (IV)
b ) Material Pile shoes
a) C I shoes
b) M. S shoes
c) Steel helmet and cushion block on top of pile head during driving.
c)
Machinery
Crane 10 tonne capacity
Vibrating Pile driving hammer complete with power unit and accessories.

d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 1 per cent of (a+b+c) for carriage of piles from casting yard to work site and
stacking, and other imponderables during installation.

e)
Overhead charges @ input on (b+c+d)
f)
Contractor's profit @ input on (b+c+d+e)
e&f) Overheads & Contractors Profit
Cost for 60 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/60
Note : The quantity of concrete required to be removed above the designed top level of conc
for in the rate analysis.
34

RBR-FNDN-34

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement complete
as per Drawing and & Technical Specification in Section 1100 & 1700 MORTH

Size of pile - 500 mm x 500 mm


Unit = Running Meter
Taking output = 50 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug vide item no. 12( F ) (IV)

b ) Material Pile shoes


a) C I shoes
b) M. S shoes
c) Steel helmet and cushion block on top of pile head during driving.
c)
Machinery
Crane 20 tonne capacity
Vibrating Pile driving hammer complete with power unit and accessories.

d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 1 per cent of (a+b+c)
for carriage of piles from casting yard to work site and
stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 50 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/50
Note : The quantity of concrete required to be removed above the designed top level of conc
for in the rate analysis.

544

RBR_FNDN
35

RBR-FNDN-35

Driven precast vertical M35 grade R.C.C. Piles excluding Reinforcement


complete as per Drawing and & Technical Specification in Section 1100 &
1700 MORTH
Size of pile - 750 mm x 750 mm
Unit = Running Meter
Taking output = 40 m
a) Materials
RCC Grade M-35
Rate for concrete may be adopted same as for bottom plug vide item no.
12( F ) (IV)
b ) Material
Pile shoes
a) C I shoes
b) M. S shoes
c) Steel helmet and cushion block on top of pile head during driving.
c)
Machinery
Crane 20 tonne capacity
Vibrating Pile driving hammer complete with power unit and accessories.
d ) Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 1 per cent of (a+b+c)
for carriage of piles from casting yard to work site
and stacking, and other imponderables during installation.

e&f) Overheads & Contractors Profit


Cost for 40 m = a+b+c+d+e+f
Rate per metre (a+b+c+d+e+f)/40
Note : The quantity of concrete required to be removed above the designed top level of conc
for in the rate analysis.

RBR-FNDN-36

36

Driven Vertical Steel Piles complete as per Drawing and & Technical
Specification in Section 1100 & 1900 MORTH
Section of the pile - H Section steel column 400 x 250 mm (ISHB Series)
Unit = Running Meter
Taking output = 70 m
a) Materials
Structural steel including 5 per cent wastage @ 82.20 kg/m
b)
Machinery
Crane 10 T capacity
Vibrating Pile driving hammer complete with power unit and other accessories.
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 0.5 per cent of (a+b+c)
for providing steel helmet on top of pile head
during driving, stacking of piles at site, providing anti-corrosion treatment and
other imponderables during installation.
d&e) Overheads & Contractors Profit
Cost for 70 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/70

545

RBR_FNDN
37

RBR-FNDN-37

Driven Vertical Steel Piles complete as per Drawing and & Technical
Specification 1108 & Section 1100 & 1900 MORTH
Section of the pile - H Section steel column 450 x 250 mm (ISHB Series)
Unit = Running Meter
Taking output = 60 m
a) Materials
Structural steel including 5 per cent wastage @92.50 kg/m
b)
Machinery
Crane 10 T capacity
Vibrating Pile driving hammer complete with power unit and accessories.
c)
Labour
Mate/Supervisor
Mazdoor (Unskilled)
Add 0.5 per cent of (a+b+c)
for providing steel helmet and cushion block on
top of pile head during driving, stacking of piles at site, providing anti-corrosive
treatment and other imponderables during installation.

38

RBR-FNDN-38

d&e) Overheads & Contractors Profit


Cost for 60 m = a+b+c+d+e
Rate per metre (a+b+c+d+e)/60
Pile Load Test on single Vertical Pile in accordance with IS:2911(Part-IV)
and as per Tech Specification 1113 MORTH

Unit = 1 MT
Taking output = 1 MT
a) Initial and routine load test
b) Lateral load test
Note : Although, this item is incidental to work and is not required to be included in BOQ
required to be added in the estimate to assess cost of work.
39

RBR-FNDN-39

Cement Concrete for Reinforced Concrete in Pile Cap complete as per


Drawing and Technical Specifications in Section 1100, 1500 & 1700
MORTH
A. RCC Grade M20 (Design Mix)
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
Labour
and c)
Machinery

a)

Material,

b)

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

546

RBR_FNDN
(ii) RCC M 20 Design Mix Using Batching Plant, Transit Mixer and Concrete

Pump
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
b)
Labour
and c)
Machinery

a)

Material,

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Note : The value of a, b and c may be taken as applicable i.e. either using concrete mixer or b
RCC Grade M25 Design Mix
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
B

c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
Labour
and
c)
Machinery

a)

Material,

b)

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

547

RBR_FNDN
(ii) RCC M 25 Design Mix Using Batching Plant, Transit Mixer and Concrete

Pump
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 125 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
b)
Labour
and
c)
Machinery

a)

Material,

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Note : The value of a, b and c may be taken as applicable i.e. either using concrete mixer or b
RCC Grade M30 Design Mix
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
C

c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
Labour and c)
Machinery

a)

Material,

b)

d)
Overhead charges @ input on (a+b+c)
e)
Contractor's profit @ input on (a+b+c+d)
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15

548

RBR_FNDN
(ii) RCC M 30 Design Mix Using Batching Plant, Transit Mixer and Concrete

Pump
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 100 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
Labour and c)
Machinery

a)

Material,

b)

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Note : The value of a, b and c may be taken as applicable i.e. either using concrete mixer or b
RCC Grade M35 Design Mix
Unit = cum
Taking output = 15 cum
(i) Using Concrete Mixer
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
D

c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator (capacity 33 KVA)
Formwork @ 4 per cent on cost of concrete i.e. cost of
Labour and c)
Machinery

a)

Material,

b)

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
(ii) RCC M 35 Design Mix Using Batching Plant, Transit Mixer and Concrete
Pump
a) Material
Cement
Coarse sand
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason

549

RBR_FNDN
Mazdoor (Unskilled) for concreting
Mazdoor (Unskilled) for breaking pile head, bending bars, cleaning etc.
c)
Machinery
Batching Plant @ 20 cum/hour
Generator 125 KVA
Loader (capacity 1 cum)
Transit Mixer ( capacity 4.0 cu.m )
Lead upto 1 Km
Lead beyond 1 Km, L - lead in Kilometer
Concrete Pump
Formwork @ 4 per cent on cost of concrete i.e. cost of
Labour and c)
Machinery

RBR-FNDN-40

40

a)

Material,

b)

d&e) Overheads & Contractors Profit


Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
Leveling Course for Pile cap
Providing and laying of PCC M15 (Design Mix) leveling course 100mm
thick below the pile cap.
Unit = cum
Taking output = 15 cum
a) Material
Cement
Coarse sand
40 mm aggregate
20 mm Aggregate
10 mm Aggregate
b)
Labour
Mate
Mason
Mazdoor (Unskilled)
c)
Machinery
Concrete mixer (cap. 0.40/0.28 cum)
Generator 33 KVA
d&e) Overheads & Contractors Profit
Cost for 15 cum = a+b+c+d+e
Rate per metre (a+b+c+d+e)/15
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

550

RBR_FNDN

sh Standard Data
and Bridges

pter - 11

NDATION
Unit

Quantity

Rate
Rs.

Amount Rs.

Remarks

day

day

3.64

5 per cent of labour cost. Assessment for dewatering shall be made

ed on cost of excavation for open foundation.

backfilling in trenches & partly for road work. Hence cost of disposal
to all cases of item 11.1 excluding 11.1 V

day

day

8.32

hour

6.00

where required, up to 10 per cent of labour cost. Assessment for

day

day

4.68

5 per cent of labour cost.

551

RBR_FNDN
10 per cent on cost of excavation for open foundation.

552

RBR_FNDN

day

day

8.32

hour

6.00

d, where required. Assessment for dewatering shall be made as per

day

day

6.24

d upto 5 per cent of labour cost. Assessment for dewatering

day

day

10.40

hour

6.00

be added, where required. Assessment for dewatering shall be

cludes that required for trimming of bottom and side slopes.

day

day

5.20

ay be added, where required as per site condition.

553

RBR_FNDN

day

day

6.24

hour

6.00

day

day

0.50

day

0.25

day

8.35

hour

kg

3.50

Nos.

14.00

day

day

5.20

hour

6.00

554

RBR_FNDN

day

day

15.60

required.

removed and replaced by approved quality of soil. The labour cost


it with a lead upto 50 m lead.

s, therefore, been done upto 3 m depth of excavation. For deeper

day

day

10.40

hour

2.67

cum

5.00

added. Assessment for dewatering shall be made as per site

ded where required.


m depth only. For deeper excavation below 3m depth, refer

day

day

2.08

hour

0.17

hour

0.45

cum

5.00

ed where required. Assessment for dewatering shall be made as per

added where required.


m depth only. For deeper excavation below 3m depth, refer

555

RBR_FNDN

day
day

3.12

hour

2.00

day

day

0.31

cum

1.00

day

day

3.12

ncluded. Only labour for carrying carted earth with a lead of 50 m to


earth may be worked out separately if the same is not available from

with excavated earth. The cost of this operation is included in


able quality, sand filling or backfilling with carted earth may be

t
cum

0.275
0.48

cum

0.54

cum

0.27

cum

0.09

day

day

0.10

day

2.36
4.00%

556

RBR_FNDN

0.22

cum

0.45

cum

0.9

kl

1.2

day
day
day

0.1
1.39

hour

0.40

hour

0.13
4.00%

t
cum

0.220
0.45

cum

0.570

cum

0.280

cum

0.050

day

day
day

0.10
2.36
4.00%

t
cum
cum

0.275
0.48
0.48

cum

0.24

cum

0.08

day
day

0.10

day

1.39

557

RBR_FNDN
hour

0.40
4.00%

y included in overhead charges. Hence not added in rate analysis of

0.275

cum

0.48

cum

0.54

cum
cum

0.27
0.09

day
day
day

0.10
2.36
4.00%

0.33

cum

0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

1.39

day
hour

0.4
4.00%

t
cum

0.33
0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

2.36
4.00%

558

RBR_FNDN

0.275

cum

0.45

cum

0.54

cum

0.27

cum

0.09

day

day

0.10

day

1.39

hour

0.40

hour

0.40
4.00%

0.343

cum

0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

1.39

hour

0.4

hour

0.4
4.00%

0.33

cum

0.45

cum

0.54

cum

0.36

day

day

0.1

day

1.39

hr /
cum

0.4
4.00%

559

RBR_FNDN

t
cum

0.347
0.45

cum

0.54

cum

0.36

day

day

0.1

day

1.39

hr /
cum
hour

0.4
0.4
4.00%

tonne

41.66

cum

54.00

cum
cum

64.80
43.20

day

0.84

day

3.00

day

18.00

hour

6.00

hour
hour

6.00
6.00

hour
t.km

15.00
300L

hour

6.00
4.00%

tonne
cum
cum
cum
cum

0.40
0.45
0.36
0.36
0.18

day
day
day

0.1
1.39

560

RBR_FNDN
hr /
cum
hour

0.40
0.40
4.00%

tonne
cum
cum
cum
cum

47.95
54.00
43.20
43.20
21.60

day
day
day

3.00
18.84

hour
hour
hour
hour
tonne.k
m
hour

6.00
6.00
6.00
15.00
300L
6.00
3.75%

0.403

cum

0.45

cum

0.54

cum

0.36

day

day

0.1

day

1.39

day
hr /
cum

0.4
3.75%

tonne
cum
cum

48.38
54.00
64.80

cum

43.20

561

RBR_FNDN
day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne.k
m

300L

hour

6.00
3.75%

tonne
cum

0.405
0.45

cum

0.36

cum

0.36

cum

0.18

day

day

0.1

day

1.39

hour

0.4

hour

0.4
3.50%

tonne
cum
cum

48.60
54.00
43.20

cum
cum

43.20
21.60

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne.k
m

300L

hour

6.00

562

RBR_FNDN
3.50%

t
cum

0.407
0.45

cum

0.54

cum

0.36

day

day

0.1

day

1.39

hour

0.40

hour

0.40
3.50%

tonne
cum

48.80
54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne.k
m

300L

hour

6.00
3.50%

0.422

cum

0.45

cum

0.54

cum

0.36

563

RBR_FNDN
day

day

0.1

day

1.39

hour

0.40

hour

0.40
3.00%

tonne
cum

50.64
54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km
hour

300L
6.00
3.00%

ansit mixer, concrete pump, Admixtures @ 0.4 per cent of weight of

ecified by designation along with prescribed method of design of mix


"Design Mix" shall be used, except where "Nominal Mix" concrete is
be permitted only for minor bridges and culverts or other incidental
ominal Mix" may also be permitted for non-structural concrete or for

at 1.2 kl / 1 cum (including curing purpose) keeping the site


used instead of graded metal, keeping the site conditions in

Nos.

512

cum

0.2

day

day

0.89

564

RBR_FNDN
day

1.8

t
cum

0.48
1.05

day

day

0.2

Nos.

512

cum

0.2

day
day

0.89

day

1.8

0.36

cum

1.05

day

day

0.2

Nos.

512

cum

0.20

day

day

0.89

day

1.80

0.38

0.175

cum

1.05

day

day

3.05

x 7 cms and 520 Nos Modular Bricks 19 x 9 x 9 cms

s than 70 kg / cm2

565

RBR_FNDN

cum

0.94

Nos.

0.16

cum

0.28

day

day

2.5

day

2.32

cum

0.94

Nos.

0.16

cum

0.28

day

day

2.5

day

2.32

cum

0.94

Nos.

0.16

cum

0.28

day

day

2.5

day

2.32

cum

0.94

Nos.
cum

0.16
0.32

day

day

1.5

day

2.22

566

RBR_FNDN

cum

0.94

Nos.

0.16

cum

0.32

day

day

1.5

day

2.22

cum

0.94

Nos.

0.16

cum

0.32

day

day

1.50

day

2.22

cum

0.44

cum

0.5

Nos.

0.16

cum

0.33

day

day

1.2

day

cum

0.44

cum

0.5

Nos.

0.16

cum

0.33

day

day

1.2

day

567

RBR_FNDN

cum

0.44

cum

0.5

Nos.

0.16

cum

0.33

day

day

1.2

day

0.24

cum

1.05

day

day

0.2

cum

0.44

cum

0.5

Nos.

0.16

cum

0.33

day

day

1.20

day

2.00

r separately as it is assumed

1.05

kg

6.00

day

day

2.00

day

6.40

568

RBR_FNDN

1.025

each

70.000

Hr

10.00

kg

6.00

day

2.50

day

2.00

day

6.40

1.05

kg

6.00

day

day

2.00

day

6.40

1.025

each

70.000

Hr

10.00

kg

6.00

day

2.50

day

2.00

day

6.40

569

RBR_FNDN

1.05

kg

6.00

day

day

2.00

day

6.40

cum

251.20

each

750.00

day

day

15.40

hour

20.00

working space of crane with grab bucket.

cum

904.32

each

6000.00

each

95.00

190.00

day

day
day

23.60
12.00

day

110.00

hour

50.00

the basis of cross-sectional area of well. The diameter of the


TH specifications.

570

RBR_FNDN

cum

450.00

each

300.00

day

day

6.24

hour

27.00

hour

28.00

1.05

Kg

20.00

day

day

5.50

day

5.50

day

5.50

day

17.82

cum

1.00
20.00%

571

RBR_FNDN

cum

cum

1.00
20.00%

1.00
20.00%

cum

1.00
20.00%

cum

1.00
20.00%

cum

1.00
20.00%

cum

1.00
10.00%

cum

1.00
10.00%

572

RBR_FNDN

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

573

RBR_FNDN

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

cum

1.00
10.00%

tonne

51.60

cum

54.00

cum

64.80

cum

43.20

kg

206.00

day

day

3.00

day

18.84

hour

6.00

hour

6.00

574

RBR_FNDN
hour

6.00

hour

15.00

t.km

300xL

hour

6.00
10.00%

tonne
cum

5.55
6.75

cum

5.40

cum

5.40

cum

2.70

Kg

18.60

day

day

1.50

day

20.90

hour

6.00

hour

6.00

hour

6.00

tonne

44.40

cum

54.00

cum

64.80

cum

43.20

Kg

148.80

day

day

3.00

day

18.88

hour

6.00

hour

6.00

hour

6.00

hour

15.00

575

RBR_FNDN
t.km

300L

hour

6.00

tonne

5.99

cum

6.75

cum

5.40

cum

5.40

cum

2.70

Kg

21.60

day

day

1.50

day

20.90

hour

6.00

hour

6.00

hour

6.00

tonne
cum

47.88
54.00

cum

cum

64.80

cum

43.20

Kg

172.80

day

day

3.00

day

18.88

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne.k
m

300L

hour

6.00

576

RBR_FNDN

6.08

cum

6.75

cum

5.40

cum

5.40

cum

2.70

Kg

21.60

day

day

1.50

day

20.90

hour

6.00

hour

6.00

hour

6.00

48.64

cum

54.00

cum

64.80

cum

43.20

Kg

172.80

day

day

3.00

day

18.88

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne.k
m

300L

hour

6.00

577

RBR_FNDN

6.29

cum

6.75

cum

5.40

cum

5.40

cum

2.70

Kg

21.60

day

day

1.50

day

20.90

hour

6.00

hour
hour

6.00
6.00

50.28

cum

54.00

cum

64.80

cum

43.20

Kg

172.80

day
day

3.00

day

18.88

hour

6.00

hour

6.00

hour

6.00

hour

15.00

tonne.k
m

300L

hour

6.00

578

RBR_FNDN

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

cum

1.00

579

RBR_FNDN

cum

1.00

cum

1.00

cum

1.00

t
cum

5.12
6.75

cum

8.10

cum

5.40

day

day

1.50

day

20.86

hour

6.00

hour

6.00
4.00%

40.92

cum

54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300L

hour

6.00

580

RBR_FNDN
cum

4.00%

t
cum

6.05
6.75

cum

8.10

cum

5.40

day

day

1.50

day

20.86

hour/cu
m

6.00

hour

6.00
3.75%

cum

48.40

cum

54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300L

hour

6.00

cum

3.75%

581

RBR_FNDN

t
cum

6.10
6.75

cum

8.10

cum

5.40

day

day

1.50

day

20.86

hour

6.00

hour

6.00

cum

3.50%

t
cum

48.79
54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300L

hour

6.00

cum

3.50%

6.33

cum

6.75

cum

8.10

cum

5.40

day

day

1.50

582

RBR_FNDN
day

20.86

hour

6.00

hour

6.00

cum

3.00%

t
cum

50.64
54.00

cum

64.80

cum

43.20

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300L

hour

6.00

cum

3.00%

52.20

cum

54.00

cum

64.80

cum

43.20

kg

206.00

day

day

3.00

day

18.84

hour

6.00

hour

6.00

hour

6.00

hour

15.00

t.km

300.L

583

RBR_FNDN
hour

6.00

cum

3.00%

day

day

1.00

day

2.12

hour

2.00
10.00%

day

day

1.25

day

2.65

hour

3.00
10.00%

584

RBR_FNDN

day

day

1.50

day

2.40

hour

3.00
10.00%

day

day

3.00

day

4.80

hour

6.00

hour

2.00
10.00%

day

day

3.00

day

20.92

day

0.50

585

RBR_FNDN
hour
hour

4.00
3.50
10.00%

Kg

4.00

each

18.00

day

day

2.00

day

0.25

day

13.56

day

4.00

hour

6.00

hour

2.00

10.00%

day

day

1.25

day

2.65

hour

3.25
10.00%

586

RBR_FNDN

day

day

1.50

day

3.18

hour

4.50
10.00%

day

day

1.50

day

3.18

hour

4.50
10.00%

day

day

2.00

day

4.26

hour

6.00

hour

3.25
10.00%

587

RBR_FNDN

day

day

4.00

day

10.58

day

0.75

hour

4.50

hour

3.75
10.00%

Kg

7.00

each

30.00

day

day

2.00

day

0.25

day

19.60

day

4.00

day

0.50

hour

6.00

hour

2.00

10.00%

588

RBR_FNDN

day

day

1.50

day

3.18

hour

4.00
10.00%

day

day

1.75

day

3.75

hour

5.00
10.00%

day

day

2.00

hour

3.72

589

RBR_FNDN
hour

5.50
10.00%

day

day

2.50

day

4.82

hour

6.00

hour

3.50
10.00%

day

day

4.00

day

12.68

day

1.00

hour

5.00

hour

3.75
10.00%

590

RBR_FNDN

Kg

8.00

each

32.00

day

day

2.00

day

0.25

day

21.09

day

4.00

hour

6.00

hour

2.00

10.00%

day

day

1.50

day

3.44

hour

4.00
10.00%

day

day

1.75

day

4.27

hour

5.50
10.00%

591

RBR_FNDN

day

day

2.25

day

3.99

hour

5.75
10.00%

day

day

2.50

day

5.34

hour

6.50

hour

3.75
10.00%

592

RBR_FNDN

day

day

4.00

day

14.76

day

1.20

hour

6.50

hour

4.00
10.00%

Kg

10.00

each

40.00

day

day

2.00

day

0.25

day

23.17

day

4.00

day

1.00

hour

7.00

hour

2.50

10.00%

day

day

1.50

day

3.70

593

RBR_FNDN
hour

5.00
10.00%

day

day

2.00

day

4.56

hour

5.75
10.00%

day

day

2.50

day

5.75

hour

6.00
10.00%

day

day

3.00

day

5.90

hour

6.00

hour

4.00
10.00%

594

RBR_FNDN

day
day

4.00

day

16.86

day

1.40

hour

7.00

hour

4.25
10.00%

Kg

11.00

each

44.00

day

day

2.00

day

0.25

day

25.27

day

4.00

hour

8.50

hour

3.00

10.00%

595

RBR_FNDN

day

day

1.50

day

3.51

hour

6.00
10.00%

day

day

2.00

day

4.82

hour

4.00
10.00%

day

day

2.50

day

4.26

hour

5.00

596

RBR_FNDN
10.00%

day

day

3.50

day

6.18

hour

6.00

hour

4.25
10.00%

day

day

4.25

day

18.95

day

1.50

hour

8.00

hour

4.50
10.00%

597

RBR_FNDN

Kg

12.00

each

48.00

day

day

2.00

day

0.25

day

27.35

day

4.00

hour

10.00

hour

3.50

10.00%

day
day

1.75

day

4.22

hour

6.00
10.00%

day

day

2.50

day

5.12

hour

6.50
10.00%

598

RBR_FNDN

day

day

3.00

day

4.80

hour

6.25
10.00%

day

day

3.75

day

6.48

hour

8.33

hour

4.50
10.00%

599

RBR_FNDN

day

day

4.50

day

21.06

day

1.75

hour

10.00

hour

4.75
10.00%

Kg

14.00

each

56.00

day

day

2.00

day

0.25

day

29.44

day

4.50

hour

12.50

hour

4.00

10.00%

600

RBR_FNDN

day
day
day

1.25
3.95

hour

5.50
10.00%

day
day
day

1.50
4.30

hour

5.88
10.00%

day

day
day

2.50
4.26

hour

6.25
10.00%

601

RBR_FNDN

602

RBR_FNDN

day

day

3.25

day

6.45

hour

6.67

hour

4.50
10.00%

day

day

4.50

day

15.86

day

1.50

hour

8.33

hour

6.00
10.00%

Kg

10.00

each

40.00

day

day
day
day

2.00
0.25
26.34

day

4.25

603

RBR_FNDN
hour

10.00

hour

3.00

10.00%

Cum

8.00

0.48

Kg

1.50

each

6.00

day
day
day
day
day
day

0.50
1.00
1.00
0.50
31.86

day

10.00

day

4.00

hour

6.00

L.S
L.S
hour

6.00

hour

12.00

hour

6.00

hour

6.00

hour

6.00

hour

6.00

hour

6.00

604

RBR_FNDN

ment shall be divided by the total quantity of pneumatic sinking for all
ount of this item.

added to the cost indicated at (1) above to arrive at the final rate of

stance involved for shifting of equipment which may be assessed in


king of cost estimates.

n of barge and boat may be omitted.

l ground conditions.

tic tools, portable lamps, fire extinguishers, hose pipes etc., have not
der overhead charges.

cum

1.00

day
day

0.31

1.05

day

day

6.00

day

5.00

day

5.00

day

11.24

cum

6.62

hour

6.00

hour

6.00

hour

0.50

hour

0.30

605

RBR_FNDN
hour

0.30

606

RBR_FNDN
kg

300.00

day

day

3.64

cum

7.85

hour

6.00

hour

6.00

hour

0.50

hour

0.40

hour
kg

0.40
350.00

day

day

4.16

cum

10.17

hour

6.00

hour

6.00

hour

0.50

hour

0.50

hour

0.50

kg

385.00

day

day

4.68

607

RBR_FNDN

cum

17.66

Kg

160.00

Kg

70.00

Kg

50.00

hour

6.00

hour

0.50

day

day

3.12

the designed top level of concrete, if any, will be provided for in the

situ pile and is planned to be retained, the same may be included in


casting is planned to be removed, an additional cost @ 0.50 per cent

cum

23.55

Kg

160.00

Kg

70.00

Kg

50.00

hour

6.00

hour

0.50

hour

0.50

day

day

4.16

608

RBR_FNDN
the designed top level of concrete, if any, will be provided for in the

situ pile and is planned to be retained, the same may be included in


casting is planned to be removed, an additional cost @ 0.50 per cent

cum

22.61

Kg

160.00

Kg

70.00

Kg

50.00

hour

6.00

hour

0.50

day

day

4.68

the designed top level of concrete, if any, will be provided for in the

situ pile and is planned to be retained, the same may be included in


casting is planned to be removed, an additional cost @ 0.50 per cent

cum

11.78

Kg

240.00

Kg

105.00

Kg

30.00

hour

6.00

hour

6.00

day

day

3.12

609

RBR_FNDN

e designed top level of concrete, if any, will be provided for in the rate

cum

22.08

Kg

160.00

Kg

70.00

Kg

40.00

hour

6.00

hour

6.00

day

day

4.16

ove the designed top level of concrete, if any, will be provided

cum

31.40

Kg

160.00

Kg

70.00

Kg

50.00

hour

6.00

hour

6.00

day

day

5.20

ove the designed top level of concrete, if any, will be provided

610

RBR_FNDN

cum

5.40

kg

240.00

kg

105.00

Kg

30.00

hour

6.00

hour

6.00

day

day

3.12

ove the designed top level of concrete, if any, will be provided

cum

12.50

kg

160.00

kg

70.00

Kg

30.00

hour

6.00

hour

6.00

day

day

4.16

ove the designed top level of concrete, if any, will be provided

611

RBR_FNDN

cum

22.50

kg

160.00

kg

70.00

Kg

30.00

hour

6.00

hour

6.00

day

0.18

day

4.50
1.00%

ove the designed top level of concrete, if any, will be provided

6.04

hour

6.00

hour

6.00

day

day

3.12
0.50%

612

RBR_FNDN

tonnes

5.83

hour

6.00

hour

6.00

day

day

3.64
0.50%

1.00

1.00

ot required to be included in BOQ of contract, the same is


.

t
cum

5.12
6.75

cum

8.10

cum

5.40

day

day

1.50

day

20.90

day

1.00

hour

6.00

hour

6.00

cum

613

RBR_FNDN

5.12

cum

6.75

cum

8.10

cum

5.40

day

day

0.38

day

2.66

day

1.00

hour

0.75

hour

0.75

hour

0.75

hour

2.00

t.km

37.5L

hour

0.75

cum

4.00%

i.e. either using concrete mixer or batching plant.

5.99

cum

6.75

cum

8.10

cum

5.40

day

day

1.50

day

20.90

day

1.00

hour

6.00

hour

6.00

cum

4.00%

614

RBR_FNDN

5.99

cum

6.75

cum

8.10

cum

5.40

day

day

0.38

day

2.66

day

1.00

hour

0.75

hour

0.75

hour

0.75

hour

2.00

t.km

37.5L

hour

0.75

cum

4.00%

i.e. either using concrete mixer or batching plant.

6.10

cum

6.75

cum

8.10

cum

5.40

day

day

1.50

day

20.90

day

1.00

hour

6.00

hour

6.00

cum

4.00%

615

RBR_FNDN

6.10

cum

6.75

cum

8.10

cum

5.40

day

day

0.38

day

2.66

day

1.00

hour

0.75

hour

0.75

hour

0.75

hour

2.00

tonne.k
m
hour

37.5L

cum

4.00%

0.75

i.e. either using concrete mixer or batching plant.

t
cum

6.33
6.75

cum

8.10

cum

5.40

day

day

1.50

day

2.90

day

1.00

hour

6.00

hour

6.00

cum

4.00%

6.33

cum

6.75

cum

8.10

cum

5.40

day

day

0.38

616

RBR_FNDN
day

2.66

day

1.00

hour

0.75

hour

0.75

hour

0.75

hour

2.00

t.km

37.5L

hour

0.75

cum

4.00%

t
cum

4.13
6.75

cum

8.10

cum

4.05

cum

1.35

day

day

1.50

day

20.86

hour

6.00

hour

6.00

wards unskilled Mazdoor.

617

RBR-SBST
Andhra Pradesh Standard Data
I. Roads and Bridges

Chapter - 12
SUBSTRUCTURE
Index-code

S. No

Description

Brick masonry work in cement mortar in substructure complete


excepting pointing and plastering, as per drawing and technical
specification Clauses 602, 603, 604, 1202 & 1204 MORD and 1300 &
2200 MORTH

RBR-SBST-1

II

III

In 1:3 cement mortar


Unit = cum
(a) Material
Bricks 1st class traditional size 23 x 11 x 7 cm
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
In 1:4 Cement mortar
Unit = cum
(a) Material
Bricks 1st class traditional size 23 x 11 x 7 cm
Cement mortar (Rate as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
In 1:5 cement mortar
Unit = cum
(a) Material
Bricks 1st class traditional size 23 x 11 x 7 cm
Cement mortar
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Sub-analysis
Cement mortar 1:5 (1 cement, 5 sand)
(a) Material
Cement
Sand
(b) Labour

549

RBR-SBST
Mate
Mazdoor (Unskilled)
Total material and labour = (a+b)

550

RBR-SBST
IV

In cement lime mortar (1:0.5:4.5)


Unit = cum
(a) Material
Bricks 1st class traditional size 23 x 11 x 7 cm
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
In 1:5 cement mortar (with Modular Bricks)
Unit = cum
(a) Material
Bricks 1st class Modular size 19 x 9 x 9 cm
Cement mortar
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of materials and labour (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Note : 1. The compressive strength of any individual Brick shall not be less than 70 Kg/cm2

2. When Mortar mix is changed as CM 1:3 & 1:4 proportionate quantity of cement has to be substituted. N

Pointing with cement mortar (1:3) on brickwork as per drawing and


technical specification Clauses 613.3 and 1204 MORD and 1300 &
2200 MORTH

RBR-SBST-2

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1.3 (Rate as in item 11.5. I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : Scaffolding is already included in item 12.1
3

RBR-SBST-3

Plastering with cement mortar (1:4), 15 mm thick on brickwork in


substructure as per technical specification Clauses 613.4 & 1204 MORD

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:4 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
2. Though cement mortar of leaner mix has been included in item 12.1, for cement plaster mix of 1:4 ha
finishing

551

RBR-SBST

3. If cement plaster 12 mm or 18 mm thick is required elsewhere only the quantity of cement mortar m
basis without any change in the labour.

552

RBR-SBST
B

Plastering with cement mortar (1:3), on brickwork in substructure as per


technical specification Section 1300 & 2200 MORTH

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:3 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
C

Plastering with cement mortar (1:5), on brickwork in substructure as per


technical specification 1300 & 2200 MORTH

Unit = 10 sqm
Taking output = 10 sqm
(a) Material
Cement mortar 1:5 (Rate as in item 11.5 II )
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per 10 sqm = (a+b+c+d)
Note : 1. Scaffolding is already included in item 12.1
4

Stone masonry in cement mortar for substructure complete as per drawing &
technical specification Clauses 702, 704, 1202 & 1204 MORD and 1400 & 2200
MORTH

RBR-SBST-4
I
(i)

Coursed rubble masonry (1st sort)


In 1:3 cement mortar
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5. I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour (b) (a+b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d
(ii) In 1:4 cement mortar
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5.II)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour (b) 5% on (a+b)

c&d) Overheads & Contractors Profit

553

RBR-SBST
Rate per cum = a+b+c+d

554

RBR-SBST
(iii) In cement mortar (1:5)

Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls / blasted rubbles
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
As for scaffolding @ 5% on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iv) In cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for CR masonry 1st sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

II
(i)

Cement lime mortar (Rate as in item 11.5. III)


(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5% of (a) and (b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Coursed Rubble masonry (2nd sort)
In cement mortar (1:3)
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour (b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d
(ii) In 1:4 cement mortar
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate same as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour (b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d

555

RBR-SBST
(iii) In cement mortar (1:5)

Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement mortar (Rate same as in item 12.1 III)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
(iv) In cement lime mortar (1:0.5:4.5)
Unit = cum
(a) Material
Stone for CR masonry 2nd sort
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Spalls/blasted rubbles
Cement lime mortar (Rate as in item 11.5 III)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
III Random rubble masonry
(i) In cement mortar (1:3)
Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate as in item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour (b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d
(ii) In 1:4 cement mortar
Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)
Cement mortar (Rate same as in item 11.5 II)
(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of material (a) and labour (b) 5% on (a+b)

c&d) Overheads & Contractors Profit


Rate per cum = a+b+c+d

556

RBR-SBST
(iii) In cement mortar (1:5)

Unit = cum
(a) Material
Coursed Rubble Stone
Stone for RR masonry
Through and bond stone
(7 no x 0.24 x 0.24 m x 0.39 m = 0.16 cum)

IV

Cement mortar (Rate same as in item 12.1 III)


(b) Labour
Mate
Mason 1st Class
Mason 2nd Class
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent on (a+b)
c&d) Overheads & Contractors Profit
Rate per cum = a+b+c+d
Ashlar masonry ( first sort ) Tech. Specification 1405.5 MORTH
Plain ashlar
Unit = cum
Taking output = 1 cum
a) Material
Stone
Through and bond stone
(7no.x0.24mx0.24mx0.39m = 0.16 cu.m)
Cement mortar 1:3 (Rate as in Item 11.5 I)
b) Labour for masonry work
Mate
Mason
Mazdoor (Unskilled)
Add for scaffolding @ 5 per cent of cost of a)

Material and b)

Labour

c&d) Overheads & Contractors Profit


Rate per cum (a+b+c+d)

Note : The labour already considered in the cement mortar have been taken into account while providi
stone masonry works.
Plain/reinforced cement concrete in substructure complete as per drawings
and technical specification Clauses 802, 804, 805, 806, 807, 1202 and 1204
MORD and 1500, 1700 & 2200 MORTH

RBR-SBST-5

Note : Water for concrete : A provision for cost of water may be added at 1.2 kl / 1
cum (including curing purpose) keeping the site conditions
Coarse Aggregate : Single grade nominal size can also be used instead of graded
metal, keeping the site conditions in view

I
i

For height upto 5 m


Unit = cum
P.C.C grade M 15
Nominal mix (1:2.5:5) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
(d) Formwork @ 10% on cost of material, labour and machinery (a+b+c)

e&f) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e+f

557

RBR-SBST
(ii)

II
(i)

Nominal mix 1:2.5:5 (Hand mixing) (MORD)


Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 10% on (a+b)
d&e) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e
P.C.C. grade M 20 - Height upto 5m
Nominal mix (1:2:4) using CC Mixer (MORD)
Unit = cum
(a) Material
Cement
Coarse sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 63 KVA
Vibrator
(d) Formwork @ 10% on cost of material, labour and machinery (a+b+c)

e&f) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e+f
(a) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of above Item
(excluding Form Work)

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Nominal mix 1:2:4 (Hand mixed) (MORD)
(a) Height upto 5m
Unit = cum
(a) Material
Cement
Sand
40 mm aggregate
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Formwork @ 10% out of material and labour (a+b)

d&e) Overheads & Contractors Profit


Rate per cum = a+b+c+d+e

558

RBR-SBST
(b) Height 5m to 10m
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of item (a)
above (excluding Form Work)

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
III (C) PCC Grade M15 (Design Mix) (MORTH):
(i) For height upto 5 m

Case I : Using Concrete mixer :


Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.
4(B)(i) of Chapter 11, excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
III (C) PCC Grade M20 (Design Mix) (MORTH) :
(ii) For height upto 5 m
Case I : Using Concrete mixer :
Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(B)(ii) of Chapter 11, excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
III (C) PCC Grade M25 (Design Mix) (MORTH):
(iii) (i) For height upto 5 m
i Case I : Using Concrete mixer :
Rate per Cum
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(D) Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump

Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(D) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(D) Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork

559

RBR-SBST
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

560

RBR-SBST
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11. 4 (D) Case II excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11. 4(D) Case I excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item
4 (D) Case II excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
IV D PCC Grade M30 (Design Mix) (MORTH):
(i)

Height upto 5m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4 (F) Case I excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4 (F) Case II excluding formwork.
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

561

RBR-SBST
(ii)

Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(F) Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(F) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(F) Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11. 4
(F) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
V (A) R.C.C grade M 20 (Nominal Mix) (MORD):
Unit = cum
(i) Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 10% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f

562

RBR-SBST
(ii)

Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item V(A)(i)
above excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item V(A)(i)
above excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
V (B) R.C.C grade M 20 (Design Mix) (MORTH):
Unit = cum
(i) Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mason 2nd Class
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
(d) Formwork @ 10% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(c)(ii) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item V(B)(i)
Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

563

RBR-SBST
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(C) (ii) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item V (B) (i)
Case I excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(C) (ii) Case II excluding formwork.

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

VI
(i)

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
R.C.C. grade M 25 (Design Mix)
Unit = cum
Height upto 5m
Case I : Using concrete Mixer
(a) Material
Cement
Coarse sand
20 mm aggregate
10 mm aggregate
(b) Labour
Mate
Mason (1st Class)
Mazdoor (Unskilled)
(c) Machinery
Concrete mixer 0.4/0.28 cum capacity
Generator 33 KVA
Vibrator
(d) Formwork @ 10% on (a+b+c)
e&f) Overheads & Contractors Profit
Rate per cum = a+b+c+d+e+f
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(E) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

564

RBR-SBST
(ii)

Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item
VI (i) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4 (E) Case II excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

(iii) Height above 10m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Item
VI (i) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Note in MORD : 1. The cost of form work has been increased, for more height, to
account for cost of side support to form work.
2. Extra expenditure on structures which are more than 5m height is to cater for
cost involve for approaching the work spot by providing ramp for use by labour.
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4 (E) Case II excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to
cater for extra lift
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)

565

RBR-SBST
VII
(i)

RCC Grade M30 (Design Mix)


Height upto 5m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4(G) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(G) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(G) Case I excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(G) Case II

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter 11.4
(G) Case I excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(G) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

566

RBR-SBST
VIII RCC Grade M35
(i) Height upto 5m

Case I : Using concrete Mixer


Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4(H) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
e&f) Overheads & Contractors Profit
Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(H) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(ii) Height 5m to 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4(H) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(H) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
(iii) Height above 10m
Case I : Using concrete Mixer
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of
Chapter 11.4(H) Case I excluding of Formwork
d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)
Case II : With Batching Plant, Transit Mixer and Concrete Pump
Per Cum Basic Cost of Labour, Material & Machinery (a+b+c) of Chapter
11.4(H) Case II excluding of Formwork

d) formwork
Add on cost of material, labour and machinery (a+b+c) for Formwork
Add on cost of material, Labour and machinery excluding formwork to cater for
extra lift

e&f) Overheads & Contractors Profit


Rate perm (a+b+c+d+e+f)

567

RBR-SBST

Note in MORTH : The basic components of this analysis are the same as those of items 13.8 (A to H)
under:

a)
Ramps/Stairs: Extra expenditure on structures which are more than 5 m high @ 2 per cent of cost
per cent for heights above 10 m will be involved for approaching the work spot by providing higher ram
working parties.

b)
The above mentioned percentages have been suitably modified for different categories as cost for
whereas effort for access for same height will be similar. As the cost of richer concrete is comparatively m
added has been reduced to maintain the same cost for extra efforts.

Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in


substructure complete as per drawings and technical specification
Clauses 1002, 1005, 1010 & 1202 MORD / Sections 1600 & 2200
MORTH for Bars below 36 mm dia including over laps and wastage,
where they are not welded.

RBR-SBST-6

Unit = t
(a) Material
HYSD bars including 5 per cent overlaps and wastage

Binding wire
(b) Labour for cutting, bending, shifting to site, tying, and placing in
position
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
A

Supplying, fitting and placing HYSD bar reinforcement (Fe 415) in


substructure complete including wastage, as per drawings and technical
specification Clauses 1002, 1005, 1010 & 1202 MORD / Sections 1600 & 2200
MORTH for Bars 36 mm dia and above, where welding required to be done
compulsorily.

Unit = t
(a) Material
HYSD bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying, and placing in
position
Welder
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
7

RBR-SBST-7

Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructure
complete as per drawings and technical specification Clauses 1002, 1005,
1010 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia
including over laps and wastage, where they are not welded.

Unit = t
(a) Material
TMT bars including 5 per cent overlaps and wastage
Binding wire
(b) Labour for cutting, bending, shifting to site, tying, and placing in
position
Mate
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d

568

RBR-SBST
A

Supplying, fitting and placing TMT bar reinforcement (Fe 415) in substructure
complete including wastage, as per drawings and technical specification
Clauses 1002, 1005, 1010 & 1202 MORD / Sections 1600 & 2200 MORTH for
Bars 36 mm dia and above, where welding required to be done compulsorily.

Unit = t
(a) Material
TMT bars including 2.5 per cent for wastage
Welding Electrodes @ 5 per joint (14 joints / ton)
Welding Charges (Hire charges of Welding Machine)
Binding wire
(b) Labour for cutting, bending, shifting to site, tying, and placing in
position
Welder
Blacksmith/Bar Bender
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
8

RBR-SBST-8

Supplying, fitting and placing with MS bar reinforcement in substructure


complete as per drawings and technical specification Clauses 1002, 1005,
1010 & 1202 MORD / Sections 1600 & 2200 MORTH for Bars below 36 mm dia
including over laps and wastage, where they are not welded.

Unit = t
(a) Material
MS bars including 5 per cent overlaps and wastage
Binding wire
(b) Labour for cutting, bending, shifting to site, tying, and placing in
position
Mate
Blacksmith
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per t = a+b+c+d
9

RBR-SBST-9

Providing weep holes in brick masonry/stone masonry, plain/reinforced


concrete abutment, wing wall, return wall with 100 mm dia AC pipe extending
through the full width of the structures with slope of 1(V):20(H) towards
drawing face complete as per drawing and technical specification Clauses
614, 709, 1204.3.7 MORD / 2706 & 2200 MORTH.

Unit = Nos
Taking output = 30 Nos
(a) Material
AC pipe 100 mm dia including wastage @ 5 per cent. Average length of weep hole
is taken as one metre for the purpose of estimating

MS clamps
Collar for AC pipe (average taking 10% of above pipe rate)
Cement mortar 1:3 (For rate refer to item 11.5 I)
(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Cost for 30 Nos = (a+b+c+d)
Rate per No = (a+b+c+d)/30

Note in MORTH : 1. In case of stone masonry, the size of the weep hole shall be 150 mm x 80 mm
diameter.

2. For structure in stone masonry, the weep holes shall be deemed to be included in the item of stone m
be paid separately.

569

RBR-SBST
Backfilling behind abutment, wing wall and return wall complete as
per drawings & technical specification Clause 1204.3.8 MORD /
710.14 of IRC, 78 & 2200 MORTH

10

RBR-SBST-10

II

11

RBR-SBST-11

Unit = cum
Taking output = 10 cum
Granular material
(a) Material
Granular material
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Machinery
Plate compactor / power rammer
Water Tanker
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
Sandy material
Unit = cum
Taking output = 10 cum
(a) Material
Sand
(b) Labour
Mate
Mazdoor (Unskilled)
(c) Machinery
Plate compactor/power rammer
Water Tanker
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
Providing and laying filter media with granular crushed aggregates as per
specification to a thickness of not less than 600 mm with smaller size
towards the soil and bigger size towards the wall and providing over the
entire surface behind abutment, wing wall, return wall to the full height,
compacted to firm condition complete as per drawing and technical
specification Clause 1204.3.8 MORD / 710.14 of IRC, 78 & 2200 MORTH

Unit = cum
Taking output = 10 cum
(a) Material
Filter media as per specification
(b) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
c)
Machinery
Water Tanker of 6 KL capacity
d&e) Overheads & Contractors Profit
Cost for 10 cum of granular backfill = a+b+c+d+e
Rate per cum = (a+b+c+d+e)/10
Note : Suitable Grade of Filter media shall be proposed as per Specification in said
IRC.

570

RBR-SBST
12

Supplying, fitting and fixing in position true to line and level electrometric
bearing conforming to IRC:83 (Part-II) Section IX complete, including all
accessories as per drawings and technical specification Clause 1207.1
MORD

RBR-SBST-12

Unit = cubic centimeter


Considering an electrometric bearing of size 500 x 400 x 96 mm for this analysis,

Overall volume = 19200 cu.cm


Volume of 6 Nos 488x388x4 mm size reinforcing steel plates =
4545cu.cm.
Hence volume of elastomer = 14655 cu. cm.
a)Labour
Mate
Mazdoor (Unskilled)
Mazdoor Skilled
b) Material
Electrometric bearing assembly consisting of 7 internal layers of elastomer bonded
to 6 nos. internal reinforcing steel laminates by the process of vulcanisation,
complete with all components as per drawing and technical specification
Add for anchorage bolts if required and consumables @ 1 per cent on (a+b)

c&d) Overheads & Contractors Profit


Cost for 19200 cu.cm. of elastomeric bearing = a+b+c+d
Rate per cu.cm of elastomeric bearing = (a+b+c+d)/19200
Note : For such type of manufactured item, the overhead cost is taken as 30 per cent
instead of 20 per cent
i

Supplying, fitting and fixing in position true to line and level cast
steel rocker bearing conforming to IRC: 83(Pt.-1) section IX and
clause 2003 of MoRTH specifications complete including all
accessories as per drawing and Technical Specifications 2000, 1000
& 2200 MORTH.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis

a) Labour
Mate
Mazdoor (Skilled)
Mazdoor (Unskilled)
b)

Material

Cast steel rocker bearing assembly of 250 tonne design load capacity duly
painted complete with all its components as per drawing and
specifications
Add 1 per cent of cost of bearing assembly for foundation anchorage
bolts, lifting arrangements, grease and other consumables.

ii

c&d) Overheads & Contractors Profit


cost for 250 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/250
Supplying, fitting and fixing in position true to line and level forged
steel roller bearing conforming to IRC: 83(Pt.-1) section IX and
clause 2003 of MoRTH specifications complete including all
accessories as per drawing and Technical Specifications 2000, 1000
& 2200 MORTH.
Unit: one tonne capacity
Considering a 250 tonne capacity bearing for this analysis

a)

Labour

Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)

571

RBR-SBST
b)

Material

Forged steel roller bearing of 250 tonne design load capacity duly painted
complete with all its components as per drawing and specifications
Add 1 per cent of cost of bearing assembly for foundation anchorage
bolts, lifting arrangements, grease and other consumables.

iii

c&d) Overheads & Contractors Profit


cost for 250 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/250
Supplying, fitting and fixing in position true to line and level sliding
plate bearing with PTFE surface sliding on stainless steel complete
including all accessories as per drawing and Technical
Specifications and BS: 5400, section 9.1 & 9.2 (for PTFE) and clause
2004 of MoRTH Specifications & Sections 2000 & 2200 MORTH

Unit: one tonne capacity


Considering a 80 tonne capacity bearing for this analysis

a)

Labour

Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)

Material

PTFE sliding plate bearing assembly of 80 tonnes design load capacity duly
painted complete with all its components as per drawing and Technical
Specifications
Add 1% for foundation anchorage bolts and consumables.

c&d) Overheads & Contractors Profit


cost for 80 tonnes capacity bearing = a+b+c+d
iv

Rate per tonne capacity = (a+b+c+d)/80


Supplying, fitting and fixing in position true to line and level
elastomeric bearing conforming to IRC: 83 (Part-II) section IX and
clause 2005 of MoRTH specifications complete including all
accessories as per drawing and Technical Specifications 2000 &
2200 MORTH.
Unit: one cubic centimeter
Considering an elastomeric bearing of size 500 x 400 x 96 mm for this
analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel plates = 4545
cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
Elastomeric bearing assembly consisting of 7 layers of elastomer bonded to 6 nos.
internal reinforcing steel laminates by the process of vulcanisation, complete with
all components as per drawing and Technical Specifications.

Add 1 per cent of cost of bearing assembly for foundation anchorage


bolts and consumables.
c&d) Overheads & Contractors Profit
cost for 19200cc of elastomeric bearing = a+b+c+d
Rate per cc of elastomeric bearing = (a+b+c+d)/19200

572

RBR-SBST
v

Supplying, fitting and fixing in position true to line and level sliding plate
bearing with stainless steel plate sliding on stainless steel plate with mild
steel matrix complete including all accessories as per drawing and Technical
Specifications 2000, & 2200 MORTH.

Unit: one tonne capacity


Considering the sliding bearing of 80 tonnes design capacity for this analysis.

a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
Supply of sliding plate bearing of 80 tonne design capacity complete as per
drawings and Technical Specifications.
Add 1 per cent of cost of bearing assembly for foundation anchorage bolts and
consumables.

c&d) Overheads & Contractors Profit


cost for 80 tonnes of capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/80
vi

Supplying, fitting and fixing in position true to line and level POT-PTFE
bearing consisting of a metal piston supported by a disc or unreinforced
elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE
surface sliding against stainless steel mating surface, complete assembly to
be of cast steel/fabricated structural steel, metal and elastomer elements to
be as per IRC: 83 part-I & II respectively and other parts conforming to BS:
5400, section 9.1 & 9.2 and clause 2006 of MoRTH Specifications complete as
per drawing and approved Technical Specifications 2000, & 2200 MORTH.

Unit: one tonne capacity


Considering a Pot bearing assembly of 250 tonne capacity for this analysis.

a) Labour
Mate
Mazdoor (Unskilled)
Mazdoor (Skilled)
b)
Material
Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE
pads providing sliding surfaces against stainless steel mating together with cast
steel assemblies/fabricated structural steel assemblies duly painted with all
components as per clause 2006 and complete as per drawings and Technical
Specifications.

Add 1 per cent of cost of bearing assembly for foundation anchorage bolts and
consumables.

c&d) Overheads & Contractors Profit


cost for 250 tonnes capacity bearing = a+b+c+d
Rate per tonne capacity = (a+b+c+d)/250
13

RBR-SBST-13

Providing PCC M-20 architectural coping on the top of wing wall, return wall
etc. complete as per drawing and technical specification Clauses 615, 710
and 1204.3.11 MORD

Unit = Running m
Taking output = 1 m
Assume wall thickness = 345 mm
Projection of the coping will be 25 mm wide on both side of the wall = 345
+ 50 = 395 mm
Quantity = 1 x 0.395 x 0.150 = 0.059
PCC M-20 Grade (1:2:4) Nominal Mix
As per item No. 12.5 (II)(i) including Overheads & Contractor's Profit

Add 10% extra of cost of (a) being architectural coping


Cost of 1 m = a
Rate per m = a

573

RBR-SBST
14

RBR-SBST-14

Providing pressure relief pipes 100 mm dia in bottom slab of box cell on a
filter media base of 500 mm x 500 mm as per drawing and technical
specification Clause 1205.5.7 MORD

Unit = Nos
(a) Material
AC pipe 100 mm dia i/c wastage of 5 per cent 600 mm long upto the bottom of
leveling course
Filter media base with stone aggregate as per specifications 0.5 m x 0.5 m area 1
m deep

(b) Labour
Mate
Mason 1st Class
Mazdoor (Unskilled)
c&d) Overheads & Contractors Profit
Rate per No = (a+b+c+d)
General Note :
The provisions towards Mate is included in the provision towards unskilled Mazdoor.

574

RBR-SBST

radesh Standard Data


ads and Bridges

Chapter - 12

UBSTRUCTURE
Unit

Quantity

Rate
Rs.

Amount Rs.

Remarks

Nos.

512

cum

0.200

day
day
day

0.270
0.620

day

1.800

Nos.

512

cum

0.200

day
day
day
day

0.270
0.620
1.800

Nos.
cum

512
0.200

day
day
day
day

0.270
0.620
1.800

t
cum

0.288
1.050

575

RBR-SBST
day
day

0.200

576

RBR-SBST

Nos.
cum

512
0.200

day
day
day

0.620
1.800

Nos.
cum

520
0.200

day

day

0.270

day

0.620

day

1.800

hall not be less than 70 Kg/cm2

ate quantity of cement has to be substituted. No change in other data.

cum

0.030

day
day
day
day

0.500
0.740

cum

0.190

day
day
day

0.600
0.960

n item 12.1, for cement plaster mix of 1:4 has been proposed for better

577

RBR-SBST

ewhere only the quantity of cement mortar may be changed on prorata

578

RBR-SBST

cum

0.144

day

day

0.500

day

0.540

cum

0.144

day

day

0.500

day

0.540

cum
Nos.

0.940
0.160

cum

0.280

day
day
day
day

2.500
2.320

cum
Nos.

0.940
0.160

cum

0.280

day
day
day

2.500
2.320

579

RBR-SBST

580

RBR-SBST

cum
Nos.

0.940
0.160

cum
cum

0.280

day
day
day

2.500
2.320

cum
Nos.

0.940
0.160

cum

0.280

day
day
day

2.500
2.320

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day
day

1.500
2.220

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day
day

1.500
2.220

581

RBR-SBST

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day
day

1.500
2.220

cum
Nos.

0.940
0.160

cum
cum

0.320

day
day
day

1.500
2.220

cum
cum
Nos.

0.440
0.500
0.160

cum

0.330

day
day
day
day

1.200
2.000

cum
cum
Nos.

0.440
0.500
0.160

cum

0.330

day
day
day
day

1.200
2.000

582

RBR-SBST

cum
cum
Nos.

0.440
0.500
0.160

cum

0.330

day
day
day
day

1.200
2.000

cum

1.110

each

7.000

cum

0.280

day

day

2.500

day

2.700

r have been taken into account while providing these categories in the

0.275

cum

0.480

cum

0.480

cum

0.240

cum

0.080

day
day
day

0.100
1.390

hour

0.400
10.00%

583

RBR-SBST

t
cum

0.275
0.480

cum
cum

0.540
0.270

cum

0.090

day

day

0.100

day

2.360
10.00%

t
cum
cum
cum
cum

0.330
0.450
0.360
0.360
0.180

day
day
day
day

0.100
1.390

hour
hour

0.400
0.400
10.00%

cum

1.000

10.00%
2.00%

t
cum
cum
cum
cum

0.330
0.450
0.360
0.360
0.180

day
day
day

0.100
2.360
10.00%

584

RBR-SBST
cum

1.000

10.00%
2.00%

cum

1.000

10.00%

cum

1.000

10.00%

cum

1.000

10.00%

cum

1.000

10.00%

cum

1.000

12.00%

585

RBR-SBST
2.00%

586

RBR-SBST

cum

1.000

12.00%
2.00%

cum

1.000

15.00%
4.00%

cum

1.000

15.00%
4.00%

cum

1.00

10.00%

cum

1.00

10.00%

587

RBR-SBST

cum

1.00

12.00%
2.00%

cum

1.00

12.00%
2.00%

cum

1.00

15.00%
4.00%

cum

1.00

15.00%
4.00%

t
cum

0.330
0.450

cum
cum

0.540
0.360

day
day
day
day

0.100
1.390

hour
hour

0.400
0.400
10.00%

588

RBR-SBST

cum

1.00

12.00%
2.00%

cum

1.00

15.00%
4.00%

t
cum

0.347
0.45

cum
cum

0.54
0.36

day
day
day
day

0.06
0.10

hour
hour

0.40
0.40
10.00%

cum

1.00

1.33

10.00%

cum

1.00

12.00%
2.00%

589

RBR-SBST

cum

1.00

12.00%
2.00%

cum

1.00

15.00%
4.00%

cum

1.00

15.00%
4.00%

t
cum
cum
cum

0.403
0.450
0.540
0.360

day
day
day

0.10
1.39

hour
hour
hour

0.40
0.40
10.00%

cum

10.00%

590

RBR-SBST

cum

11.80%
1.80%

cum

11.80%
1.80%

cum

15.00%
4.00%

ncreased, for more height, to

han 5m height is to cater for


g ramp for use by labour.

cum

15.00%
4.00%

591

RBR-SBST

cum

10.00%

cum

10.00%

cum

11.50%
1.60%

cum

11.50%
1.60%

cum

14.00%
3.50%

cum

14.00%
3.50%

592

RBR-SBST

cum

10.00%

cum

1.000

10.00%

cum

11.00%
1.40%

cum

1.000

11.00%
1.40%

cum

13.00%
3.00%

cum

1.000

13.00%
3.00%

593

RBR-SBST

are the same as those of items 13.8 (A to H). The only changes are as

re more than 5 m high @ 2 per cent of cost for height upto 10 m and 4
aching the work spot by providing higher ramp/stair case for use by the

y modified for different categories as cost for various categories varies,


the cost of richer concrete is comparatively more, the percentage to be
efforts.

1.050

kg

6.000

day
day
day

2.000
6.840

t
each

1.025
70.000

Hr

10.00

kg

6.00

day

2.50

day
day

2.000
6.840

t
kg

1.050
6.000

day
day
day

2.000
6.840

594

RBR-SBST

1.025

each

70.000

Hr

10.00

kg

6.00

day

2.50

day
day

2.000
6.840

t
kg

1.050
6.000

day
day
day

1.500
5.780

31.500

Nos.

30.000
10.00%

cum

0.050

day
day
day

0.500
0.280

of the weep hole shall be 150 mm x 80 mm or circular with 150 mm

deemed to be included in the item of stone masonry work and shall not

595

RBR-SBST

cum

12.000

day
day

7.280

hour
hour

2.500
0.050

cum

12.000

day

day

7.280

hour
hour

2.500
0.060

cum

12.000

day
day
day

7.320
1.000

hour

0.060

ed as per Specification in said

596

RBR-SBST

day
day
day

1.060
0.500

Nos.

1.000

1.00%

d cost is taken as 30 per cent

day
day

0.500

day

1.060

each.

1.000

day
day

1.060

day

0.500

597

RBR-SBST
each.

1.000

day

day

1.060

day

0.500

each.

1.000

day
day
day

1.06
0.50

each.

1.00

598

RBR-SBST

day
day
day

0.790
0.350

each.

1.000

day
day
day

1.580
0.500

each.

1.000

cum

0.059

599

RBR-SBST

0.630

cum

0.250

day
day

0.016

day

0.831

on towards unskilled Mazdoor.

600

You might also like