You are on page 1of 4

Project: Brewery Plant

Location: Mouza-Aima & Somsara, J.L.No 51&35, West Bengal - 712149

22-Jul-16

Subject : Progress Status


Particulars

Sr No

Completion Date

Support Required

Status Dated 12/07/2016

Support Required

Civil work - BBT and UT

100% completed

Tiling work decission pending


Railing decission pending

100% completed

1) Grade slab

ready for installation

a. Floor Tiling decission awaiting from CBPL


b. Praj has asked to after equipment
installation
c. Wall/window/doors / Tiles wall and floor
details awaited

Work is in Progress.
Completed
This will be completed up to 20.07.2016

2)Drain

will be done after Praj / CBPL clearance

100% completed

Status Dated 10/06/2016

Tiling work decission pending


Railing decission pending

Cellar Area

Filteration section

Will be completed up to 20.07.2016

a. Decided to construct upto window base level


and balance will be done after getting the
drawings of window/doors etc
b. Brick work decission has to be given by CBPL - Will be completed up to 25.07.2016
Light weight block or clay bricks ??
c. Wall / Floor tiling decission awaited from

Completed

3) Brickwork

25-06-2016

Upto window base wall will be


constructed by 25/06/16

Layout not finalised yet from CBPL


Clearance awaited from CBPL

CBPL

4)Plaster

Will be done after brick work completion

5)Paint

Will be completed up to 30.07.2016


Clearance awaited from CBPL

CIP section

1) Grade slab

ready for installation

2)Drain

will be done after Praj / CBPL clearance

a. Floor Tiling decission awaiting from CBPL


b. Praj has asked to after equipment
installation
c. Wall/winriow/doors details awaited

100% completed
100% completed

S'

Dependent on Masonry Work

Project: Brewery Plant


22-Jul-16

Location: Mouza-Aima & Somsara, J.L.No 51&35, West Bengal - 712149


Subject : Progress Status
Particulars

Sr No

Completion Date

Upto window base wall will be


constructed by 25/06/16

3) Brickwork

a. Decided to construct upto window base level


and balance will be done after getting the
drawings of window/doors etc
b. Brick work decission has to be given by CBPL Will be completed up to 20.07.2016
Light weight block or clay bricks ??
c. Wall tiling decission awaited from CBPL
H Plnnr

tilpc: Hptaik

Layout not finalised yet from CBPL


Clearance awaited from CBPL

awaitArl

Will be completed up to 25.07.2016

Will be done after brick work completion

4)Plaster

Support Required

Status Dated 12/07/2016

Support Required

Status Dated 10/06/2016

Dependent on Masonry Work

Clearance awaited from CBPL

5)Paint

Yeast section

1) Grade slab

ready for installation

2)Drain

will be done after Praj / CBPL clearance

a. Floor Tiling decission awaiting from CBPL


b. Praj has asked to after equipment
installation
c. Wall/window/doors / Floor tiles/ wall tiles
details awaited

Upto window base wall will be


constructed by 25/06/16

3) Brick work

100% completed

a. Decided to construct upto window base level


and balance will be done after getting the
drawings of window/doors etc
100% completed
b. Brick work decission has to be given by CBPL Light weight block or clay bricks ??
r Wall tilinp riprissinn awaitpri from CRPI

Cellar area slab (+9.Sm)leval

Will be completed up to 20.07.2016


Clearance awaited from CBPL

5)Paint

Cellar area slab (+5.5m)leval

Will be done after brick work completion

4)Plaster

100% completed

Completed

10-07-2016

Decission awaited from CBPL about Plaster or


100% completed
Painting with Putty. SRD has given suggestion
for not to do plaster as surface finsihing is good

a. Columns completed, Slab shuttering in


a. Details awaited for Wall, window, tiling etc
progress
Elevation drawing awaited from
b.
b. 100% completion - 20/07/2016 with
CBPL/Sandeep
deshuttring

Will be completed up to 20.07.2016

Utility

Completed

Project: Brewery Plant

Location: Mouza-Aima & Somsara, J.L.No 51&35, West Bengal - 712149

22-Jul-16

Subject : Progress Status


Sr No

Particulars

Completion Date

Status Dated 10/06/2016

Support Required

Status Dated 12/07/2016

Drawing Has Revised Hence rework needs to


Done
Rework : 22.07.2016 to 27.07.2016
Reshuttering and Reinforcement 28.07.2016 to
06.08.2016
Checking 07.08.2016
Casting 08.08.2016
Pedestal Above slab casting 10.08.2016
c
Tank ready for installations 18.08.2016
Deshuttering 29.08.2016

a.Water proofing from CBPLside is in


progress which will be colpeted by

a) Water treatment plant

30.06.2016

15/06/16

Support Required

Will be completed up to 25.07.2016

b. After handing over SRDPL required


15days time for slab casting

&

OS l (o

b) C02 andEelectrical area

Plinth beam

16-06-2016

100% completed

08 days required after getting the Bolt from


CBPL PEB vendor _

Boltfixing

20-06-2016

1) Soil backfilling up to plinth be

21-06-2016

Simultaneously SRD will start silver sand


levelling

Work is in Progress.
Completed
This will be completed up to 15.07.2016

Awaiting for Bolt from CBPL PEB vendor

100% completed

2)Silver sand backfilling

22-06-2016

Simultaneously start soling

15.07.2016

3)Soiling

24-06-2016

Simultaneously start pcc

20.07.2016

4)PCC

25-06-2016

Simultaneously further work will start

20.07.2016

Slab at 3.5m level -

22.07.2016

5)Gradeslab

will be done after clearance from CBPL

6)Grade slab foundation

Equipment Foundations will be done alongwith


gradeslab after clearance from CBPL for slab
25.07.2016

7)Drain

Completed

Simultaneously further work will start


_
with grade slab_

25.07.2016

25.07.2016

9)Plaster

a. After completion of PEB


b.Details awaited from CBPL/Consultant about
30.07.2016
wall, window etc
After completion of wall
30.07.2016

10)Paint

After completion of wall

8)Brick work above grade slab up to 1M

Soling, PCC, Grade slab, Drain in GS and


Foundations in Grade slab will be done along
with grade slab.
This will be completed after confirmation CBPL

c) Boiler House

Plinth beam

work in progress

a. Awaiting for the Bolt from CBPL/PEB vendor


b. 08 days required for SRD for Plinth Beam

Completed

construction
Boltfixing

Awaiting for the Bolt from CBPL/PEB vendor

Completed

1) Soil backfilling up to plinth beam top

CBPL scope

Completed

2)Silver sand backfilling

CBPL scope

Completed

3)Soling

Simultaneously start pcc

SRDPL required two days after handing over by


Completed
CBPL _

t I

Project: Brewery Plant

Location: Mouza-Aima & Somsara, J.L.No 51&35, West Bengal - 712149

22-Jul-16

Subject : Progress Status


Particulars

Sr No

Completion Date

Support Required

Status Dated 10/06/2016

4JPCC

two days after soling

Slab Boiler and operating


Platform)
Slab - Feed water Tank)

a. Drawing awaited from CBPL/Civil consultant

5)Grade slab

08 days required after clearance from CBPL

Status Dated 12/07/2016


Completed

b.SRDPL required 15 days for slab casting

Work is in Progress
will be completed up to 23.07.2016

6)Grade slab foundation

08 days required after clearance from CBPL

7)Drain

08 days required after clearance from CBPL

25.07.2016

8)Brlck work above grade slab up to 1M

Details awaited from CBPL/Consultant

30.07.2016

9)Plaster

Details awaited from CBPL/Consultant

30.07.2016

10)Paint

Details awaited from CBPL/Consultant

25.07.2016

100%Completed, ready for installation

Completed

a. work in progress, all plinth beams will


be completed by 25/06/16

Completed

Slab at 2.5 m level has completed


Balance work targeted to complete up to
27.07.2016

Soling, PCC, Grade slab, Drain in GS and


Foundations in Grade slab will be done along
with grade slab.
This will be completed after confirmation CBPL

25.07.2016

i) Chimney

Support Required

Bottling hall

Plinth beam

25-06-2016

Boltfixing

31/06/2016

Work is in Progress
will be completed up to 15.07.2016

1) Soil backfilling up to plinth beam top

CBPL scope

16.07.2016

2)Silversand backfilling

CBPL scope

18.07.2016

3)Soling

CBPL scope

23.07.2016

a. SRDPL required 08 days for PCC


b. Final drawing awaited for PCC/Packaging
equipment Foundations/Drains/Walls _
SRDPL required eight days which will be done

25.07.2016

4)PCC

5)Grade slab
6)Grade slab foundation
7)Drain

alongwith PCC

Foundation drawings awaited

30.07.2016

Drainage drawings awaited

30.07.2016

9)Plaster
10)Paint

for Plastering

Civil Work - ETP

after handovering to SRDPL(client scope)

Civil Work - Brew House Building

bolts received

Soling, PCC, Grade slab, Drain in GS and


Foundations in Grade slab will be done along
with grade slab.
This will be completed after confirmation CBPL

30.07.2016

a. After completion of PEB


30.07.2016
b. Window, wall, tiling details awaitedc. Fifteen 30.07.2016
days requiredfor Brickwall and around ten days

8)Brick work above grade slab up to 1M

a. All columns will be completed by 31/06


and ready for PEB erection

Awaiting for 24 mm bolts ,


Casting will be done at the same day when

Work is in Progr

For all section up to 0.00 level 1508.2016


(Refilling and Compaction will be done CBPL )

tc ' CZ /&

You might also like