NATIONAL REFINERY LIMITED

NRL ISBL UPGRADATION PROJECT


UNIT WISE PIPING WELDING PROGRESS
S. No.

UNIT

Total (DIN)

Completed (DIN)

Percentage of
Completion

000 (Interconnections)

1
305-FW

1548

1168

75.45%

306-FW

1752

1524

86.99%

307/308/309-FW

1476

970

65.72%

310/311/312-FW

2330

1614

69.27%

Cooling Water

10326

4102

39.73%

Process pipe

41881

4417

10.55%

Unit total

59313

13795

23.26%

305 (HPU)

2
Plumbing pipe

507

289

57.00%

Underground Process pipe

162

2.48%

Process pipe

21000

812

3.87%

21669

1105

5.10%

Unit total

306 (DHT)

3
Plumbing pipe

1200

1148

95.67%

Underground Process pipe

6082

724

11.90%

Process pipe

44650

4833

10.82%

51932

6705

12.91%

307/308/309 (Naphtha Block)

4
Plumbing pipe

400

0%

Underground Process pipe

4600

4005

87.07%

Process pipe

61630

8620

13.99%

66630

12625

18.95%

Unit total

310/311 (ATU)

5
Plumbing pipe

400

0%

Underground Process pipe

2068

1528

73.89%

Process pipe

30410

2009

6.61%

32878

3537

10.76%

Unit total

S. No.

UNIT

Total (DIN)

Completed (DIN)

Percentage of
Completion

310 x

6
Plumbing pipe

100

0.00%

Underground Process pipe

254

60

23.62%

Process pipe

1531

0%

1885

60

3.18%

Unit total

312 (SRU)

7
Plumbing pipe

200

0%

Process pipe

33117

0%

33317

0.00%

Unit total

312x

8
Plumbing pipe

100

0%

Process pipe

1210

0%

Unit total

1310

0.00%

Grand Total

268933

37827

14.07%