CHAMC, Inc.

315 Wilkins Dr.


Des Plaines, IL 60016
Tel: 847 390 6020
www.CHAMCO.net

Proposal
For

The Government of
City of
Biomass or Municipal Solid Waste Conversion to Briquette
(300 T/D MSW)
Gasification - 8.8 MW Power Plant
&
Biogas & Solar Power

Introduction:
This is a 8.8 MW Power Plant Project, which includes turning any biomass into
Electricity plus Solar Power Plant.
The proposal describes primarily multiples of 4.4 MW electricity from Municipal Solid
Waste (MSW). However other biomass such as animal wastes, used waste tier or wood, if
available are used.
Solar farm could be added to the project, which the same turnkey prices will be applies.
The Grand Project could be for any multiple of 4.4 MW power project, if you decide
to expand the project by adding multiple units of 4.4 MW to this plant.
For example, if a community produces approximately 600 Tons of MSW per day. This
amount of MSW will be enough to produce 17.6 Mega Watts electricity.
To achieve 17.6 MW or 35.2 MW, four units or eight units of 4.4 MW will be installed
together.
In case of future expansion, 4.4 MW units could be added to the existing plants.
In this proposal, MSW will go through three stages to generate electricity:
First, MSW will be sorted. The constructional waste, ferrous & nonferrous wastes, glass
pieces & other noncombustible ingredients will be separated. Sorting machine with
atomized conveyor & magnetic separators will be installed before subjecting the biomass
to RDF Briquetting machines.
Second, gasification unite, thermal cracking of fuel (briquettes) at a high temperature of
1050deg. C to 1100deg. C in the minimal presence of Oxygen to produce Synthesis Gas
or Syn-Gas
Third, Electric Generation, which injecting SynGas directly into gas engine generator,
which has been modified exclusively by us to work with syngas to produce Electricity.
The unit is coupled with 4x3.6 MW generator requires approximately 200 T/D briquette,
which is derived from approximately 300 Tons of MSW.
If there will be any excess briquettes, with caloric value of 3,000 Calories per Kg. could
be sold in the market or increasing the power plants capacity in the future.
We do recommend adding 10% coal or wood to the MSW Briquettes for better operation
of the gasification.

Scope of Work:
Upon award of the contract, CHAMCO. will furnish a turnkey job for the MSW
processing units, Gasification and Power Plants and solar farm.

Project Cost:
The total cost of the Sorting and Briquette making facilities, Gasification and Power
Plants including; survey, feasibility study and planning, engineering, procurement,
contracting, test, commission and training is approximately $4,000,000 (four million
USD) per Mega Watt.
Therefore, cost of this 8.8 MW pilot plant project will be:
$35,200,000 (thirty five million and two hundred thousand US Dollars).

Note:
For this 8.8 MW project, the total generators rating will be 14.4 MW, but the output is
around 8.8 MW.
This is due to the fact that synthetic gas (SynGas) has less caloric value of the natural gas,
and even less than BioGas. Therefore a natural gas engine, which is rated 3.6 MW, after
modification for syngas will generate 2.2 MW.
This is our unique Know-how that we modify natural gas engines to run with syngas.

Project Timeline:
Following land acquisition, obtaining all permits, contacting with all local authorities,
and award of contract, the following timeline is to be expected:

Site assessment and engineering 3-4 months (according to the specific conditions
encountered)

Procurement 5-8 months (according to the specific units required)

Installation of the units 6-9 months (according to conditions on the ground)

Commissioning 3-5 months (according to the type of units specified)


After synchronization in the commissioning phase, there will be a 3-month operational
phase with CHAMCO. technicians on location to handle training and operational details
that may arise. Total time from award of contract to completed system is 17-26 months
depending upon conditions encountered on the ground.

Facility Process Overview:

MSW will arrive at the MSW processing facility location around the city. This
facility can be located either at the generation facility or another location remote
from the generation facility.

Garbage will be sorted and dried. Recycling can be done at this stage.

Garbage will be sized and processed into RDF.

The RDF will be used at Gasification units to produce Syngas.

Syngas directly will be used in to generate electricity.


Cost Benefit Analysis:
We provide a system to convert solid waste to electric energy.
The main considerations are:
1.
2.
3.
4.

Effective use of the landfill for real estate values


Environmentally sound disposal of the waste
Employment of local population
Production of electricity

Eliminating landfill sites, which produce harmful gases that pollute the air and most
importantly, eliminating the danger of leakage into the underground water tables, and a
potential setting for breeding diseases of all types.
Note:
The Power Plant will be located where the transmission line and substations are. This
location might be different from the MSW dumpsite, where briquettes are produced. In
that case transporting briquettes to the power plant is the others responsibility.
Project Income:
A Power Purchase Agreement (PPA) for electricity, which the national grid pays to
the owner of the plant. For calculation purposes we will use 10 cents per kilowatt hour
(KWH).
Assume that the PPA for 8.8 MW of electrical power generation at a fixed price is $0.10
per KWH.
Sale of electricity =
8.8 MW(net power generation) x 1000 x 24 (hours) x 365 (days) x $0.10 x
0.85(Efficiency Factor) = $7,800,000 gross income from power generation annually.
B - Tipping Fee: Municipalities pay the plant operators/owners a tipping fee for each Ton
that they receive and handle per day. The average tipping fee is around $40 per Ton in the
US. We will assume a tipping fee of $30 per Ton:
Tipping Fee = 300 (T/D) x $30 (per Ton) x 365 Days = $3,285,000 Annually.

Project Costs:
A - Plant Turnkey Cost includes Engineering, Procurement Contracting, Insurance,
Marketing and Commission etc.
Cost of the Project: $35,200,000
For example, a plant in South China, which converts 1000 Tons per day and generates 20
MW, has cost the Chinese more than $86m (Documented from the web). But the last cost
estimate at 2005 was $120m. That is around $4.5 Million per MW
Therefore the most conservative cost estimate of a 8.8 MW power project would be
$39.600,000. CHAMCO quotes: $35,200,000.
B Adding coal to the Fuel. Adding 10 to 15% coal to the MSW Briquettes if the price
of coal is low, could increase efficiency of the gasification units. This option should be
considered in the future.
C - Operation & Labor Cost. For this project of 5 MW power plants and RDF plant, a
work force of about 6 technical and 14 non-technical workers are estimated.
Assuming $80,000 per technical and $40,000 per non-technical works, the approximate
labor costs will be: 6 x $80,000 + 14 x $40,000 = $1,040,000
CHAMCO proposes to build a facility to process 300 Tons of garbage per day and
generate 8.8 MW by using RDF. The total estimated cost is $35,200,000.

Summary:

Assume 5 years Return On Investment (ROI)

Cost of facilities
$35,200,000

Income from PPA


$7,800,000

Income from tipping fee $3,285,000

Labor costs
$1,040,000

Maintenance costs
$140,000

ROI =35,200,000/(7,800,000+3,285,0001,040,000140,000) ~ 4

years

Note:
This offer is for a direct sale.
In case of BOT or BOOT the financing could be arranged
and investment costs will be added to this offered price.

Municipal Solid Waste Conversion to RDF

CHAMCO, Inc.
The Municipal Solid Wastes (MSW) should be sorted first into recyclable and
combustible components.
This is a typical sorting facility and Briquette making plant. The Bioreactor is used if
composting.

Depending to the conditions of the MSW, if the moisture is high, it should be dried.
The combustible component of the MSW is turned into RDF (Refused Derived Fuel)
pellet by shredding, crushing, electromagnetic separations.

Pictures of few equipments are shown here:

Below is the schematic view of the RDF plant. Use of Solar Greenhouse and Rotary Kiln
should be decided later:

To see the animation of this picture visit www.CHAMCO.net

The final product is shown here. This has a caloric value of 3,000 Calories per Kg, which
is the fuel for Gasification unit:

Gasification

CHAMCO, Inc.
Gasification is a flexible, reliable, and clean energy technology that can turn a variety of
low-value feedstocks into high-value products and can provide a clean alternative source
of base load electricity.
Gasification has been reliably used on a commercial scale worldwide for more than 50
years in the refining, fertilizer, and chemical industries, and for more than 35 years in the
electric power industry.
GASIFIERS- (Pyrolyzers) are receiving backing & subsidies from various Governments
the world over. They utilize any type of biomass including MSW, coal, waste wood,
sawdust, furniture scraps, bagasse, rice husk, coconut shells, poultry litter, plastic, rubber,
tires, or any other combustible material.
Ultra clean gas is fed into the engines with the help of a microprocessor based, oil to gas
conversion system. When a load is activated the dual-fuel mode of operation of the
engine will start automatically at 85% gas and 15% furnace oil, for a short duration then
reverts back to 100% gas mode when the load becomes constant.
The exhaust emissions of the engine can be used for a Waste Heat Recovery Boiler.
800 Kg Steam at 7kg. Pressure per hr. can be obtained. This excess heat can be put to use
for other thermal applications.
In the updraft gasifier, moist biomass fuel is fed at the top and descends though gases
rising through the reactor. In the upper zone a drying process occurs, below which
pyrolysis is taking place. Following this, the material passes through a reduction zone
(gasification) and in the zone above the grate an oxidation process is carried out
(combustion).
In a coal gasification our coal gasifier consumes 418 Kg coal with 6000 Kcal/Kg caloric
value to produce 1 MWH. Therefore:
1 MW coal gasification power plant requires 10 Tons of coal / day.
Since the caloric value of MSW Briquettes is about 3000 Kcal/Kg, therefore:
5 MW MSW gasification power plant needs about 100 Tons of MSW Briquettes / day.
We assume this 100 Tons of briquettes will be derived from more than 100 Tons MSW in
the proposed site.

Gasification Operation:

To supply air for the combustion process and steam for the gasification process,
moist hot air is supplied at the bottom of the reactor. Combustible gas at a low
temperature (because of the evaporation of moisture in the drying zone) is
discharged at the top of the reactor, and inert ash from the heat-generating
combustion process is extracted from the reactor bottom through a water lock.

Breakdown of the price for a 4.4 MW Gasification power plant using MSW as Fuel

Part A:
Basic and Detailed Engineering
Shipping to the site
Storage at site
Mobilization
Civil Works
Mechanical Works (including structure & piping)
Electrical and Instrumentation
Tests
Commissioning
Training and operation for three months
Spare Parts
Note: Import Duties, Insurances and Taxes are not included.
Total Cost for Part A:

$3,500,000

Part B (Turning Garbage around 150 T/D into Briquettes):


4-man sorting system: 25' long x 36" wide picking table with four 16"x60" chutes with
52" clearance for gaylords or dumpsters. Walkway is 23' long x 33" wide with steps.
Powered by 1-hp three-phase electric motor. Equipped with 20' x 36" in feed conveyor.
Permanent Crossbelt Magnet
WWR CBS permanent crossbelt magnet powered by a 3/4-hp three-phase 220/480 volts
electric motor. Belt is made of heavy-duty rubber with cleats spaced according to
application. Maximum belt speed is 155 FPM.74" long x 18" belt surface, 44" long x 16"
wide magnet. Ideal for recycling operations and widely used in the sorting of co-mingle
(steel cans, bottle caps, etc).
18' Incline Conveyor
This covered conveyor is 18'-6" long and is powered by a 3-hp, 208-230-460 volt, threephase electric motor. It is equipped with a 25" belt, with 2" cleats on 24" centers. The
enclosure above the belt is 24" high x 28" wide.
Eidal Model 72 X 41 slow speed-high torque shredder,

Equipped with at KYB 525S hydraulic pack with Dennison pumps and a powered by
two (2) 75 hp, 230/460 V 3 phase electric motors. Throat opening is 72" wide X 41" deep
with a hopper opening of 92" X 76", 24 3 inch knives and controls.
Eidal Model 400 Vertical Grinder
This grinder is powered by two (2) 200-hp, 460 volts, three-phase electric motors and is
6' in diameter. Hopper opening is 82" tall x 70" wide. Can process 12-25 TPH of wet or
dry solid waste, wood & damage material, pallets, and electronics, scrap metal clips up to
3/16" thickness, tin cans, and non-ferrous metal. Reduction size can be varied to suit
material or end user without screens or grates through progressive grinding.
Surge Bins
Heavy 10 gauge steel construction, Sight Glasses, Drain Tube, and Hinged Top Access
Door, with openings for High and Low Level sensors, High Legs for Discharge, single
or tube outlets, slide gates, level sensors, safety ladders & top perimeter hand rails and
more.
Andritz Sprout Bauer Pellet mill
The pellet mill includes: Stainless steel pelleting chamber door 2 roll roller assembly
1 used pelleting die 400 HP Motor, Heavy duty pellet chamber on motorized frame for
easy access
Separate inlet screws achieving effective distribution of product to the press rolls, Safety
stop
Taper fit die Renewable wear rings
Note: All the equipments of Briquette Plant are assembled and made in USA.
Total Cost for Part B:

$4,000,000

Part C (Gasification Unit)


Air Blower with a 12.5 KW motor
Ash Pan with manual / automatic circular movement by hydraulic Pump with 3.5KW
motor
Gasified Reactor w. refractory w. an over pressure release valve
Refractory & a double wall for Water & steam Jacket, Steam safety release valve. Fresh
water circulation by a 3.5 KW mono-block pump set.
Hopper for charging of fuel at the top.
Motorized Conveyor Bucket with channels for upward & downward motion for charging
of fuel. 2.25KW motor.
Staircase with Platform for inspection.
Venturi type Cyclone Filters with 3.5 KW. Mono-block Pump set for water circulation

10

Four Pipe filters with showers for cooling of Gas & washing of Particulate impurities of
Producer Gas. With 3.5 KW mono-block Pump set for water circulation.
Four Stage Dust & Tar Separators- outlet pipe & a valve fitted in bottom for Tar removal.
Over pressure release valve fitted in each D & T separator
Water Tank- Common for all filters & Dust & Tar separators. Solid impurities removed
as sediments. Water is re-circulated in cooling tower
Cooling Tower fitted with 3.5 KW mono block Pump set for water circulation
De-moisturizer for Producer Gas with a 3.5 KW Pump set for water circulation over
condenser
Humidity Analyzer to check moisture content
Gas temperature meter
Gas flow meter with totalizer
Gas Controller
Note: The Gasification equipments are mainly from India and could be assembled in the
US if needed.
Total Cost for Part C:

$5,000,000

Part D (Generating Unit)


Engine, modified & converted for Producer Gas mode of operation with microprocessor
controlled actuator type Governors
Mounting frame for Alternator & Engine
On-line Gas Analyzer with sampling system
List of Auxiliaries with the Engine in power plant
S.n Part Name
Heat Exchanger tube type
Lube Oil Cooler- tube type
Lube Oil 4-way Motorized filter
Lube Oil Line Filter
Lube oil Magnet Filter
Lube oil Separator MAPX205 Clarifier, MAB-103 Centrifugal Purifier
Lube oil drain pump 2.5x2.5, 3HP gear type
Lube Oil Priming Pump 4x4 29 HO (Gear Type) 7.5 H.p.
Lube oil Main pump either inbuilt or separate.
Rocker lube oil tank with gauge glass- 100 Ltr. Capacity
Rocker Arm lube oil motorized, gear type pump 2.5x2.5, 5 H.P
Raw water Pumpset- 6x6(150KL/hr) with 10 H.P. motor
Jacket water pump set- 6x6(150 KL/hr) with 10 H.P. motor
Make-up Water filling pump- Drain to Main Tank: 2.5x2.5, 5 H.P.
Mono-block pump set
Cooling Tower- 150 KL capacity
Air Starting valve

Qty
1
1
1
1
1
1
1
1
1
1
1
1
1
1
1
2

11

Air Compressor-32kg/cm with 10H.P. motor


Air Bottle / tank with a capacity of 25 cu.mt.

1
1

Electrical:
Engine Control Panel
Control Panel for Purifier & HFO heating
Control Panel for motorized auxiliaries of Engine
Electrical Control Panel with AVR System & output at VCB
Cable + Lugs, Control Panel Wire(Teflon Coated) etc
List of emergency Spares in General with the Power Plant
subject to increase or decrease. Specifically they would depend on the Engine available
S.no
Part Name
Qty.
a.
Turbo Charger
1
b.
Head Complete with Rocker Arm
2
c.
Piston
2
d.
Liner
2
e.
Ring Set
16
f.
Main Bearing
2
g.
C.R. Bearing
2
h.
Thrust Bearing
1
i.
Main Bearing Housing + Cap
2
k.
Fuel Pump
6
l.
Connecting Rod
1
m.
High Pressure Pipe
4
n.
Safety Valve
4
Consumables:- O Rings, Iron Packing, Iron Channels

Total Cost for Part D:

Total Cost of the equipments (B+C+D):

$5,000,000

$14,000,000

Grand Total Cost 4.4 MW Power Plant using garbage as fuel (Turnkey):
$17,500,000 (seventeen and half million US Dollars)

12

13

The Gasification Chamber:

Attachment Drawings:
14

Chamco Tribal Corp.

Chamco Tribal Corp.

Natural Gas
Generator Set

Tractors India Pvt Ltd


Plot 11, Site IV, Industrial Area
Sahibabad, Ghaziabad 201010
Ph:
91 - 120 - 2777945
Mail:
pss.tiplindia.com

Genset Model

kVA Continuous

kW - Continuous

RPM

G3508

638

510

1500

G3512

1000

800

1500

G3512

1250

1000

1500

G3512

1406

1125

1500

G3512

1500

1200

1500

G3516

1750

1400

1500

G3516

2000

1600

1500

G3520

2500

2000

1500

G3520

2528

2022

1500

G3608

2281

1825

1000

G3612

3213

2570

1000

G3612

3625

2900

1000

G3616

4563

3650

1000

G3616

4850

3880

1000

G16CM34

8150

6520

750

Continuous power available for unlimited time


Continuous power in accordance to ISO 8528
Natural gas ratings are at LHV of 35.6 mJ/M3 (905 Btu/Ft3)
Methane number of natural gas is at various levels as per supplies
Other ratings in natural gas are available on request
Bio-gas, Propane & other fuel ratings available on request
Specification are subject to revisions & improvements

1, Taratolla Road
Kolkata 700024, West Bengal
Ph: 91 - 33 - 2469 3732 - 36

PARTNERING YOUR BUSINESS

TEST REPORT

Report No. GR: GL: 2210010741


JOE No. : 1121803441

DATE : 30/04/2011

Report Control No.: 2215013098


SAMPLE DRAWN BY SGS INDIA PVT. LTD.

SAMPLE IDENTIFIED AS : STACK EMISSION MONITORING


CUSTOMER NAME

MR. RAJIB MOHAN

ADDRESS

271/B, DEVPURI, CITY

COUNTRY

INDIA

LOCATION

PRODUCER GAS AFTER CLEANING

FUEL USED

MUNICIPAL SOLID BRIQUETTE WITH 25%PLASTIC CONTENT

SAMPLING DATE

04.04.2011

SAMPLE RECD ON

06.04.2011

TEST START DATE

06.04.2011

TEST END DATE

30.04.2011

TESTS

PROTOCOL

DIOXIN & FURAN

USEPA 23A/8290A

MERRUT - 250002

RESULTS
Separate sheet attached
*****End of Report*****

Per pro SGS India Pvt. Ltd.

Authorized Signatory

This document is issued by the Company subject to its General Conditions of Service printed overleaf or available upon request and accessible
at www.sgs.com/terms_and_conditions.htm. Attention is drawn to the limitations of liability, indemnification and jurisdictional issues defined
therein. Any holder of his document is advised that information contained here on reflect the company finding at the time of its intervention only
and with in the limit of client instructions, if any. The company sole responsibility is to its client and this document does not exonerate party to a
transaction from exercising all their rights and obligations under the transaction documents. Any unauthorized alteration, forgery or falsification of
the content or appearance of this document is unlawful and offenders may be prosecuted to the fullest extend of the law. Unless other wise
stated the results shown in this test report refer only to the sample(s) tested and such sample(s) are retained for 7 days (in case of perishable
items) and 30 days for all other samples. The sample from regulatory bodies are to be retained as specified. This document cannot be
reproduced, except in full, without prior written approval of the Company.
SGS India Pvt Ltd Laboratory Services, 250, Udyog Vihar, Phase IV, Gurgaon - 122015, Haryana (India) Phone : +91-124-60600747 , Fax : 2399765.
Regd & Corp. Off : SGS House, 4B, A.S. Marg, Vikhroli (West), Mumbai-400083. Tel : (022) 25798421 to 28 Fax : (022) 25798431 to 35 www.sgs.com

Member of the SGS Group (SGS SA)

DIOXIN & FURAN :

Oxygen content
Carbon Dioxide
Moisture
Stack pressure
Extracted volume

:
:
:
:
:

Congener

0.4 (vol-%)
13.6 (vol-%)
12.59 (vol-%)
309 (mmHg)
5.15 (Nm3) (Total)

amount
(ng)
<0.0081
0.0093
<0.0081
<0.0081
0.0085
<0.010
<0.010
<0.010
<0.010
<0.018
<0.018
<0.010
<0.041
<0.041
<0.041
<0.20
<0.20

2,3,7,8-TCDF
2,3,7,8-TCDD
1,2,3,7,8-PeCDF
2,3,4,7,8-PeCDF
1,2,3,7,8-PeCDD
1,2,3,4,7,8-HxCDF
1,2,3,6,7,8-HxCDF
2,3,4,6,7,8-HxCDF
1,2,3,7,8,9-HxCDF
1,2,3,4,7,8-HxCDD
1,2,3,6,7,8-HxCDD
1,2,3,7,8,9-HxCDD
1,2,3,4,6,7,8-HpCDF
1,2,3,4,7,8,9-HpCDF
1,2,3,4,6,7,8-HpCDD
OCDF
OCDD
TOTAL

I-TEF

I-TEQ
(ng)
<0.00081
0.0093
<0.00041
<0.0041
0.0043
<0.0010
<0.0010
<0.0010
<0.0010
<0.0018
<0.0018
<0.0010
<0.0041
<0.0041
<0.0041
<0.00020
<0.00020

0.1
1
0.05
0.5
0.5
0.1
0.1
0.1
0.1
0.1
0.1
0.1
0.01
0.01
0.01
0.001
0.001

0.014-0.029
3

TOTAL PCDD/PCDF (NGTEQ/Nm )


TOTAL PCDD/PCDF (NGTEQ/Nm3)

0.006
0.003

At 11% O2 Ref.

European Norms for Dioxins in emissions 0.1 NGTEQ/Nm3


Remark: - TEQ = Toxic Equivalent Quoteint, i-TEF = International Toxic Equivalency Factor, ng = Nano Gram

Per Pro SGS INDIA PVT. LTD.

Authorized Signatory

This document is issued by the Company subject to its General Conditions of Service printed overleaf or available upon request and accessible
at www.sgs.com/terms_and_conditions.htm. Attention is drawn to the limitations of liability, indemnification and jurisdictional issues defined
therein. Any holder of his document is advised that information contained here on reflect the company finding at the time of its intervention only
and with in the limit of client instructions, if any. The company sole responsibility is to its client and this document does not exonerate party to a
transaction from exercising all their rights and obligations under the transaction documents. Any unauthorized alteration, forgery or falsification of
the content or appearance of this document is unlawful and offenders may be prosecuted to the fullest extend of the law. Unless other wise
stated the results shown in this test report refer only to the sample(s) tested and such sample(s) are retained for 7 days (in case of perishable
items) and 30 days for all other samples. The sample from regulatory bodies are to be retained as specified. This document cannot be
reproduced, except in full, without prior written approval of the Company.
SGS India Pvt Ltd Laboratory Services, 250, Udyog Vihar, Phase IV, Gurgaon - 122015, Haryana (India) Phone : +91-124-60600747 , Fax : 2399765.
Regd & Corp. Off : SGS House, 4B, A.S. Marg, Vikhroli (West), Mumbai-400083. Tel : (022) 25798421 to 28 Fax : (022) 25798431 to 35 www.sgs.com

Member of the SGS Group (SGS SA)

CHAMCO, Inc.
315 Wilkins Dr.
Des Plaines, IL 60016
Tel: 847 390 6020
www.CHAMCO.net
===============================================================
Biogas is a fuel gas made from biomass such as faeces, food waste, grass and straw etc.
during the anaerobic fermentation process.
Biogas contains about 55% - 70% methane (CH4), and some carbon dioxide, some water,
some hydrogen some carbon monoxide and some hydrogen sulfide (H2S).

The heat value of biogas is 5142 Kcal/m3


Conditions needed for biogas production are:
1- Strict absence of Oxygen.
2- Temperature between 8 65 Deg. C. Higher the temperature the more active methane
bacteria, and the higher biogas production.
3- Neutral or slightly Alkaline environment, a pH value between 6.8 and 7.5
For a 10 m3 biogas plant to keep a 5 m3/d biogas production, 150 kg cow dung or 110 kg
pig dung is needed daily.
The liquid from biogas plant can be recycled.
Biogas residue are good organic fertilizers.
Raw material needed to produce 1 cubic meter biogas:
Pig Manure
4 kg dry = 22.23 kg fresh
Cow Manure
5.26 kg dry = 30.96 kg fresh
Chicken Manure
4 kg dry = 13.34 kg fresh
Human Manure 3.33 kg dry = 16.67 kg fresh

Solar & Wind Power

CHAMCO, Inc.

1 MW Solar Power Farm or more:


Total Cost: $4,000,000 per MW.

The following is a proposal to install solar photovoltaic roof panel system on the residential properties
designed by the customer.
Description of Work:
Renewable Energy Alternatives (CHAMCO) will install 25 Homes on this property with 16 pcs. of 250watt Panels each manufactured by Lightway Solar Corp. or approved equal. The system will provide 4-kW
-Kilowatts DC STC. The panels will be installed on the roof of the building facing most efficient
orientation.
CHAMCO will furnish and install a roof mounted fastening system to support the panels installed. The
racking system will be fastened to the building structure with the appropriate flashing. CHAMCO will
work closely with the Customer and his or her representative for exact location, height and placement of
the solar panels and attachment to the building.
CHAMCO will furnish and install all certified photovoltaic panels and racking and fastener assembly labor,
electrical labor for all electrical work, inverters, combiner boxes, disconnects, circuit breakers and all
material necessary to connect the photovaltaic system with the existing building electric circuit panel
located on the interior of the existing structure. The inverter will be one 4000 watt, 240 volt, single-phase
type-- manufactured by Kaco-New Energy Inc. or equal. All warranty and guarantee paperwork will be
submitted to the customer at the project's completion. Each system will have internet monitoring capability
using the existing buildings internet connection, which is to be provided by others.
CHAMCO will provide the customer with an electrical wiring diagram and will furnish any documents
needed in order to install this project.
The customer will be responsible for providing access to the property and its utilities by CHAMCO in order
to facilitate the proper execution of the project and the related work.
All work will be performed in accordance with the applicable local building and electrical codes and
manufacturers specifications.

Cost:
25 Homes with 4 kW Solar Each

$400,000.00

Chamco, Inc
Tire Pyrolysis Plant Producing Tire Oil:

The semi-continuous pyrolysis system is to increase functions of shredding system,


automatic feeding, automatic slag on the basis of basic style pyrolysis oil system.
It can save the heating material and save the operation time for each batch.
Highly increased the batch pyrolysis efficiency.
Capacity 24Tons/day.
The pyrolysis method for recycling of used tires is an innovation technique that uses a
special mechanism to heat the used tires in a closed stove to melt down the tier into the
materials that they were made of.

Layout: