Professional Documents
Culture Documents
Summer
08
16
previously created the mold and will only receive an order for parts.
The design engineer reviews the part and raw materials specifications
of the order. Once the order is accepted the raw materials order is
placed and production is scheduled, the materials can take up to one
week to arrive. Once the materials are received the dry and wet mixing
of the chemicals begins. Once the chemicals reach the desired
consistency it is transferred to the injection-molding area and
deposited into tanks. The mixing process takes one day to complete.
The molds are taken from the existing inventory or the clean and polish
area if it was a new mold order and the parts are manufactured. The
injection-molding department has the ability to produce 5,000 parts
per day, however orders are taking an average of one week in this
department. Once complete the parts will be sent for cutting and
trimming to remove leftover flashing. If the parts do not require
assembly they will be taken to shipping and sent to the customer. If
they do require assembly this can take an additional three days before
the order is shipped.
Through these processes we can track many of the issues
Custom Molds faces. First off, Custom Molds is misquoting customers,
because it takes three weeks simply to get the materials required to
make a mold. From here it's a rush to get into the mold fabrication
center, and this stress is split among the thirteen machinists the
company currently employs. At this point its a big rush to push out the
them long term. Another alternative that would best benefit the
company would be invest in research that can help the company
expand and grow. If the company is receiving high volume orders now,
they are going to keep growing. They need to take this into
consideration and see how they can stay on top of their competition.
The last long term alternative that Custom Molds could benefit from
would be to expand it's company. A successful business always need to
expand. This would mean that they would have to consider the cost
involved in order to do this, as well as the time it will take. If it is
profitable and they can afford it they will have to consider, the cost,
time frame they would need to expand, where they would look to put
another building, and many more detailed decisions. Essentially these
long term alternatives are just ideas that could help the company
improve in order to keep growing.
Some relevant facts include:
Master machinists cost the company much more than the mold
manufacturing parts
Tom Miller with more than 20 years experience in the connector
industry with Amp, Inc.
Mason Miller has Degrees in Chemistry and Chemical Engineering
from Arizona State University.
Currently the physical plant is more easily used for the
manufacturing of parts and not for creating molds.
1. What are the major issues facing Tom and Mason Miller?
The answer to this section can be found in the problems section
of the paper.
2. What are the competitive priorities of Custom Molds's processes
and the changing nature of the industry?
Competitive Priorities are:
A. Quality The molds should be top quality with no defects and
should also be consistent.
B. Lead-Time deliveries should be on time with the highest
development speed.
C. Low Cost They should have a low cost, ability to reduce costs
to at least the competitors cost, or if not lower to earn more of a
profit.
D. Flexibility customization of the mold.
Right now we believe that Custom Molds Inc. has competitive
priorities but is simply creating processes that don't nurture
them. The problems the Millers are facing are all failures to keep
up with their competitive priorities. For example, they are failing
at quality because many orders are being returned for defects.
They fail at lead time because many of the orders are being sent
out late and angering customers. They have achieved flexibility
in the customization of the mold but at a huge cost of time and
money. In terms of low cost, is seems they fail due to the results
of returned orders and the orders they have most likely lost. Not
to mention the astronomical cost of having thirteen highly
skilled, but expensive machinists. The changing nature of the
industry is there's starting to be less customization and more
Also
A new storage area can be created to reduce the 1 week wait for
materials
An expanded injection area to produce more parts
Possibility of hiring more injectors
Less wait for materials means more time for inspection
if the testing and inspection area were possibly moved to a more