Professional Documents
Culture Documents
Project Planning
Planning in General : SWOT analysis
S: Strengths
W: Weaknesses
O: Opportunities
T: Threats
Emad Elbeltagi
Project Planning
Characteristics of a good plan
Simple
Flexible
Easy to control
13/01/2002
Emad Elbeltagi
Project Planning
Planning Inputs and Outputs
INPUTS
OUTPUTS
Activities
Contract information
Drawings
Method statement
Specifications
Available resources
Bills of quantities
Responsibility
PLANNING
Site reports
Activities duration
Organizational data
Activities cost
Construction methods
13/01/2002
Reporting levels
Emad Elbeltagi
Project Planning
Planning Major steps
13/01/2002
Emad Elbeltagi
Project Planning
Work Breakdown Structure (WBS)
The WBS is a hierarchical structure which is designed to
logically sub-divide all the work-elements of the project into
smaller elements.
House
Civil
Foundations
13/01/2002
Plumping
Walls/
Roof
Pipin
g
H/C
Water
Emad Elbeltagi
Electrical
Wiring
Finishing
Project Planning
Work Breakdown Structure (Why)
Identifying Activities
Scheduling
13/01/2002
Emad Elbeltagi
Project Planning
WBS & Organizational Breakdown Structure (OBS)
WBS (Work elements)
Project
Area 1
Beams
Subcontr
actor B
Electrical
superinte
ndent
Formwork
Area 2
Columns
Reinforcement
Area 3
Slabs
Concreting
Concrete
foreman
OBS
(Responsibility Project
& reporting) manager
General
contractor
Subcontr
actor A
13/01/2002
Civil
superinte
ndent
Formwork
foreman
Control account
Rebar
foreman
Mechanic
al
superinte
ndent
Emad Elbeltagi
Project Planning
WBS Coding
13/01/2002
Emad Elbeltagi
Project Planning
Project Activities
13/01/2002
Emad Elbeltagi
Project Planning
Project Activities
Types of construction activities:
13/01/2002
Emad Elbeltagi
Project Planning
Project Activities
Example (Double Span Bridge):
Hand rail
13/01/2002
Precast
beams
Emad Elbeltagi
Code
Description
10
Set-up site
14
Procure RFT
16
20
30
40
50
60
70
80
90
100
110
120
140
150
155
160
170
180
Road surface
190
Bridge railing
200
Clear site
Project Planning
Activities Relationships
13/01/2002
Emad Elbeltagi
Project Planning
Predecessors
Successors
Predecessor
to Act. B
13/01/2002
Successor to
Act. B
Emad Elbeltagi
Code
Description
10
Set-up site
Predecessors
---
14
Procure RFT
---
16
---
20
10
30
10
40
50
14, 20
60
14, 30
70
14, 40
80
50
90
60
100
70
110
120
140
150
155
160
170
180
Road surface
190
Bridge railing
200
Clear site
10
80
90
110, 120
140
150
155, 160, 170
155
180, 190
Project Planning
Type of Activities Relationships
Four Types:
Finish to Start (FS)
Start to Start (SS)
FS
FF
SS
SF
13/01/2002
Emad Elbeltagi
Project Planning
Type of Activities Relationships
Finish-Start
When A finishes, then B can start
Default Relationship
13/01/2002
First Activity
Second Activity
Emad Elbeltagi
Project Planning
Type of Activities Relationships
Start-Start
When A starts, then B can start
A
First Activity
B
Second Activity
13/01/2002
Emad Elbeltagi
Project Planning
Type of Activities Relationships
Finish-Finish
When A finishes, then B can finish
A
First Activity
B
Second Activity
13/01/2002
Emad Elbeltagi
Project Planning
Type of Activities Relationships
Start-Finish
When A starts, then B can finish
A
First Activity
B
Second Activity
13/01/2002
Emad Elbeltagi
Project Planning
Overlaps
how much a particular activity must be completed
before a succeeding activity may start
13/01/2002
Emad Elbeltagi
Project Planning
Overlaps
Example
Consider the construction of the following sequential activities of
a bridge consists of 19 bays
13/01/2002
Emad Elbeltagi
Project Planning
Relationships Considering Resource Constraints
Activity description
Predecessors
(unconstrained
resources)
Predecessors
(constrained
resources)
A1
B1
C1
Excavate unit 1
Concreting unit 1
Brickwork unit 1
A1
B1
A1
B1
A2
B2
C2
Excavate unit 2
Concreting unit 2
Brickwork unit 2
A2
B2
A1
B1, A2
C1, B2
A3
B3
C3
Excavate unit 3
Concreting unit 3
Brickwork unit 3
A3
B3
A2
B2, A3
C2, B3
13/01/2002
Emad Elbeltagi
Project Planning
Project networks: AOA
Two Types:
Activity-On-Arrow; AOA (Arrow Networks).
Activity-On-Node; AON (Precedence Networks):
AOA
Activity represented as arrows with start and finish nodes called
Events
Activity A
13/01/2002
j>i
Emad Elbeltagi
Project Planning
Project networks: AOA
A
10
10
15
B depends on A
C depends on A and B
15
B
5
B
A
A
B
13/01/2002
10
15
15
15
C
10
B depends on A
C depends on A
C depends on A and B
D depends on A and B
15
Emad Elbeltagi
Project Planning
Project networks: AOA
Dummy activity
Activity with zero duration and no resources to adjust the network
C depends on A and B;
A
15
D depends on B only
20
D
25
10
5
10
15
30
15
B
Dummy
B
25
Dummy
D
15
20
10
Incorrect representation
13/01/2002
Correct representation
Emad Elbeltagi
Project Planning
Project networks: AON
AOA
Activity represented as nodes
10
A
13/01/2002
Activity number
Activity name
Emad Elbeltagi
Project Planning
Project networks: AON
10
A
20
B
10
A
30
C
B depends on A
40
D
20
B
C depends on A and B
D depends on C
30
C
10
A
20
B
40
D
13/01/2002
B depends on A
C depends on B
D depends on B
Emad Elbeltagi
Project Planning
Project networks: Example
13/01/2002
Activity
Predecessors
A
B
C
D
E
F
G
A, B
C
C
D
D, E
Emad Elbeltagi
Project Planning
Project networks: Example (AOA)
13/01/2002
Emad Elbeltagi
Project Planning
Project networks: Example (AON)
Calculate the Sequence step
Activity
Predecessor
Start
A
SS(Start) +1 = 2
A, B
E
F
G
Finish
C
D
D, E
F, G
13/01/2002
SS(C) +1 = 4
SS(C)+1 = 4
SS(D)+1 = 4
Highest of [SS(D), SS(E)] = 5
Highest of [SS(F), SS(G)] = 5
Emad Elbeltagi
Project Planning
Project networks: Example (AON)
Sequence step 1
13/01/2002
Emad Elbeltagi
Project Planning
Activity Duration & Direct Cost
13/01/2002
Emad Elbeltagi
Project Planning
Activity Duration & Direct Cost
Productivity can be estimated:
Productivity data
Daily production
Units/day
How many units can be done
in one time unit
13/01/2002
Man-hours/ unit
Mhrs/unit
Emad Elbeltagi
Project Planning
Activity Duration & Direct Cost
Example
What is the duration to install 6000 square feet of walls shuttering if:
13/01/2002
Emad Elbeltagi
Project Planning
Activity Duration & Direct Cost
Example (balanced mix of resources)
A wall involves 660 m3 concrete, 50 tone of steel, and 790 m2 of formwork.
- A 6 man concrete crew can place 16 m3 of concrete/day.
- A steel-fixer and assistant can fix 0.5 ton of reinforcement/day.
- A carpenter and assistant can fix and remove 16 m2 of shuttering/day
-
13/01/2002
Emad Elbeltagi
Project Planning
Activity Duration & Direct Cost
Activity direct cost:
13/01/2002
Emad Elbeltagi