DV3-H1

Installation & General Inspection


Date
Huawei Representative
TNL Representative
Site ID-GIS Code
Site Type (Shelter (Indoor/ Outdoor,Nano),
Civil, Mobility Shared)
Site Type (AC/Non-AC)
Site on SDH,CEN
(ALU,Cisco,Hauwei,ZTE),MW,SDH L2 POI

Details
09/9/2016
Zaid
Rakesh
DV3
SHELTER
AC
CEN
H1
Huawei MA5600T
0/9/0 & 0/10/0

Node Name
Vendor & Model
MSAN Uplink Port Details
MSAN Uplink Connectivity Type (Ethernet/
Fiber)
Software
Source A in VDc
Source B in VDc
Earthing Value in Ohm
Amps Rating of MCB's

MA5600V800R016C00
-53.7
-53.6
1.05
63A

Sr No

Item

Slot

Serial Numbers

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18

H801CITD
H80DCCPE
H80DCCPE
H80DCCPE
H80DCCPE
H80DCCPE
H80DCCPE
H808ASPB
H806VPGA
H802SCUN
H802SCUN
H806VPGA
H808ASPB
H80DCCPE
H80DCCPE
H80DCCPE
H80DCCPE
H80DCCPE
H80DCCPE

0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18

020LKLD0FA000235
023ANU10FC002067
023ANU10FC002230
023ANU10FC002020
023ANU10FC002224
023ANU10FC001941
023ANU10FC002228
020STCDMFA600955
022PRY10FA001067
021VDEDMFB600253
021VDEDMFB600123
022PRY10FA001275
020STCDMFA600405
023ANU10FC002123
023ANU10FC002065
023ANU10FC001860
023ANU10FC001860
023ANU10FC002211
023ANU10FC001861

Description

Status

Remarks

19

Proper Installation/Mounting of Rack

OK

Applicable for NEW RACk


only

20

Proper Installation/Mounting of
MSAN Shelf

OK

21

Sufficient Space for Air Circulation

OK

Fiber

Criteria
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W
H/W

installed shall be verified from NOC thru EMS


installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS
installed shall be verified from NOC thru EMS

Pass/Fail
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass
Pass

Physical Verification

22
23
24
25
26
27

No Physical Damage to MSAN


Shelf/Cards
No Physical Damage to MSAN
Cards
Proper laying of Power Cables
Terminating of power cables to Dual
Power Supply
Earth Cable is properly Grounded
Proper Laying of Fiber/ Ethernet
Cables

Pass/Fail
exiting rack

Pass
Pass

Applicable for New Rack


only and if Space avialbale

Air-flow from bottom to TOP for MA5600T and from


Left to right for MA5603T

Pass

OK

Pass

OK

Pass

OK

Pass

OK

Cabinet to DCDB only

Pass

OK

Pass

OK

Pass

28

Proper Laying of Subscribers Cables

OK

Pass

29

All Cards are screw tight


Check the Labelling of Shelf, Power
Cables, Grounding Cables & Uplink
Connectivity Cables
All Alarms LEDs/ Lamps are in
healthy condition.
Unused Slots are close with Blank
pannel

OK

Pass

OK

Pass

30
31
32

33
34

OK

Should be Green

OK

Pass
Pass

Optical Power Level of Uplinking


Fiber Patch Cord

Uplink Port

Tx (db)

Rx(db)

Limit (db)

Pass/Fail

0/9/0

1/5/6

-6.110112

-6.187043

should be greater than -19

Pass

1/6/5

-5.800442

-5.412111

should be greater than -19

Pass

0/10/0

Mohd Zaid
Huawei Representative Signature

Rakesh
TNL Field Representative Signature