Professional Documents
Culture Documents
1.0
1.1
1.2
Reliability
1.3
Maintainability
1.4
Project Evaluation
CHAPTER SIX
2.0
Testing
2.1
CHAPTER SEVEN
CONCLUSION
REFERENCES
CHAPTER ONE
1.0
INTRODUCTION
As the quest for change over on public power supply and stand by generation
increase. Engineering have researches deep into the different methods of
achieving to both manual and automatic types.
It may not be taken seriously in some places where power supply is up to
90 constant or where intermittent outage causes no great damage. However,
place where they have business centers, industrial centers and even cold rooms
need to almost 100% supply. So in this case there is need to provide a standby
power supply in the event of power outage. The most important task is just to
provide a standby power supply by great attention is paid to the reliability of
the system. That is immediately and change over without fluctuations.
The first type of change over switch were purely manual operated. They
usually have three switch able position, main, off and generator. An arm is
provided from where the operator can have access to the switching. Here, the
effectiveness of the switching (i.e how fast it is effected each time power needs
to be changed) largely depends on the operator. The change over system will be
ineffective when the operator is not around.
ii
The second generation of change over switches were made semiautomatic in which the mains power supply directly powers the contactors.
This arrangement is wired is such a way that if the mains power supply fails,
the contractors will all drop leaving the supply to the generator position. The
effectiveness of the system will now depend on the operator top start up the
generator on time.
The main problem suffered by the above mentioned two versions of the
change over switch is that the operator must have to be continuously on duty
for it to be very effective. They lent use full closed loop system to operate.
The present day technology has made it possible for the change over
switch to come in a number of designs switch using the closed loop system at
feed back control. Some of them use comparators, logic circuits and electronic
timers to achieve the task. Some even used simple micro processor chips to
function.
The design of this project is such that a combination of comparators
digitals switches (logic IC), electronics timers and electromagnetic switches are
used to achieve a very fast and effective change over in this case. This project
was entirely constructed and the thesis written by Nwalua Chukwukereze under
iii
at the non-inverting input. Hence, the output of the comparators will be below
(zero volts).
If there is low voltage (below 190v) in one or more of the phase voltages, the voltage at the inverting input will be less than
reference voltage at the non-inverting input this will produce a high output (+9v) from the comparator. One or more of this art the input of
the OR gate will cause the output of the OR gate to be high and after a delay time of about 30 seconds this voltage appears at the inputs of
the AND gate.
Now the inputs of the AND gate will depend on the position of the
enable switch. If it is switched off, the information from the comparators will
not pass the AND gate. But if it is switched on (i.e both inputs will now be
high) the information will be reflected at the output of the AND gate and it will
be used to achieve the 3 switches generator on/off and then change over switch.
Also if there is complete power failure in one or more phase, the
operation of the system will be the same as described above for low voltage.
For the switching actions, the information at the output of the AND gate
operates the 3 switches at the same time. It supplies voltage to the coil of
contactor A leaving the contacts on the normally close (NC) position ready
for generator supply. Also the generator starter and turn off receive
information, the turn off will switch on d.c supply to the high voltage coil
while the starter supplies starting pulses (through the multivibrator) to the kick
vi
starter. When the generator starts running, a signal is sent to the starter to
disable it.
Also the generator sends signals to the delay circuit and after some delay
time. It will switch on contactor B and the generator will start supplying. But
if the power is restored and the comparators okay the supply (i.e if it is above
190v) the OR gate output goes low and time delay, the C/O will be effected
again and the generator will be turned off by cutting off d.c supply to the high
voltage coil. The aim of the delay is to stoop any fluctuation in power which is
less than 15 seconds from reaching the control relays the power supply uses a
9v back.up battery with a 9v regulator. It is interesting to note that when supply
is restored, the system automatically returns the consumers to his original
power supply as the case may be.
1.2
The block diagram representation of the automatic change over switch is the
one shown in figure 2.1 below, though for the previous years the details of the
Automatic C/O switch have never been shown in block form. Therefore, there
vii
******************************
TERMS OF USE
This Material is for Academic Research Purposes only. On no
account should you copy this material word for word. Copying
this material Word for Word is against our Terms of Use.
That you ordered this material shows you have agreed Our
Terms of Use.
viii
******************************
Better is not good enough, the best is yet to come!
Endeavour to be the best!!
ix