Professional Documents
Culture Documents
Project Procurement
Management
Project Participants
Architect
Structural engineer
Service engineers
(Mechanical, electrical,
hydraulics, fire
protection)
Interior designer
Environmental designer
etc.
Designer
Client
Owner (developer)
Financier
Land supplier
etc.
Main contractor
Subcontractors
Suppliers
etc.
Project
Organization
Builder
Client Requirements
Ideal goals:
Low cost
High quality
Rapid completion
IS IT POSSIBLE???
Traditional
Construction Management
Project Management
Design and Construct (Build)
Novations
Public Private Partnership (PPP)
Project Alliance
Functional Arrangements (
Traditional System
Client
Architect
Negotiated Fees
Builder
Consultants
Q.S.
subcontractors
Suppliers
Traditional System
Architect:
Appointed by the client with a contract;
Carry out the conceptual and detailed designs;
Organize design team including structural engineer,
service engineer (mechanical, electrical, fire safety,
hydraulic engineer), landscape designer, interior designer,
quantity surveyor, etc;
Have contractual links with these specialist consultants
and engineers;
Work as a project manager for the client, and oversee the
whole project design and construction;
Arrange documentation and administer the tender process
and help the client appoint a builder (most likely based on
lowest price).
Builder (Contractor):
Risk sharing:
Client has a low risk profile;
Architect works as the agent of the client. A claim
cannot be made against the agent for acts performed as
agent of the client but must be made against the client;
Contactor is responsible for the construction quality and
time, and take the risk of subcontracts.
The contract price paid to the contractor may be in the
form of a lump sum, a schedule of prices, or a mixture
of both, or even cost-plus.
Advantages
Disadvantages
Construction cannot start until the project is fully designed
and documented, which extends the period of the whole
project and increase the financial risk and burden of the
client;
The builder tends to be in an adversarial situation with the
architect/client (high potential of conflict);
The variations of design after the award of contract are
costly;
The lack of the builders technological and management
expertise and input into those aspects of the design will
weaken the constructability;
If the builder goes bankrupt, payments made to the
builder not passed onto the sub-contractor may have to be
paid again.
Contract Strategies
Construction Management
Construction Management is an example of
managed delivery method, which is
characterised by a more active role for the
client as an active member of the project
team.
It attempts to unite a three-party team of client,
architect and construction manager into a
non-adversarial, cohesive contractual
relationship, all with a common goal to serve
the project objectives and the clients needs
in the best possible way.
Client
Fee + Reimbursable
Fees
Architect
Construction manager
Q.S.
Tendered
Amounts
Consultants
Subcontractors
Suppliers
Client
Fees
Architect
Construction manager
Q.S.
Tendered
Amounts
Consultants
Subcontractors
Suppliers
10
Construction
Management (cont.)
Client:
Acquire land and arrange finance;
Appoint an architect to prepare and coordinate the
design and documentation (together with the
construction manager);
Appoint an construction manager to organize the
construction and seek his advice on the design as
well;
Select and appoint subcontractors based on the
recommendation of construction manager;
Work in the project team actively and is involved
in the projects day-to-day affairs.
Construction
Management (cont.)
Architect:
Appointed by the client with a contract;
Carry out the conceptual and detail design with the
knowledge input from the construction manager;
Organize design team including structural engineer,
service engineer (mechanical, electrical, fire safety,
hydraulic engineer), landscape designer, interior
designer, quantity surveyor, etc;
Have contractual links with these specialist
consultants and engineers;
Help construction manager arrange documentation
and administer the tender process.
11
Construction
Management (cont.)
Construction Manager:
Appointed by the client in two optional ways (agency CM or nonagency CM);
Under the agency CM,
Construction
Management (cont.)
Construction Manager:
Under the non-agency CM (not typical)
12
Construction
Management (cont.)
Risk sharing:
Client takes most of the risks (particularly under the
agency CM);
Under the non-agency CM, the CM takes the risk of
construction;
Architect takes the risk of design;
Agency CM is paid with a fee plus reimbursement +
Incentives (which indicates a risk sharing such as
guaranteed construction sum . For non-agency CM,
use guaranteed construction sum or Cost-Plus).
Construction
Management (cont.)
Advantages
Fast track;
Improved constructability;
Non-adversarial climate can improve work efficiency;
Since the client assumes more risk, the project is less reliant on
risk contingencies and the client has a better control over risk;
Greater flexibility to make design changes as the project
proceeds;
The CM method should attract more competitive prices from
separate contractors;
Information flow is greatly enhanced;
Teamwork reduces the incidence of contractual disputes;
Breaking up work into packages allows the client to control the
budget and to change, omit or postpone work where the
budget is likely to be exceeded.
13
Construction
Management (cont.)
Disadvantages
Total construction cost is unknown until the project is
completed;
The client carries more risk and is more exposed to the
adverse impact of risk (much of the financial risk is transferred
from the builder to the client);
The clients involvement and evolution of the design process
can have a detrimental effect on the cost;
Unless special provisions are made there may be no incentive
for the CM to contain costs;
Liquidated damages are almost impossible to enforce because
of the difficulty of proving who is to blame;
Non-agency CM could have a conflict interest with the client
when exposed to the possibility of a financial loss.
Construction
Management (cont.)
Contract Strategies
14
Project Management
Client
Fee
Fee
Project Manager
Fee
Architect
Consultants
Q.S.
Builder
subcontractors
Suppliers
15
Client
Fee
Fee
Project Manager
Fee
Architect
Consultants
Q.S.
Builder
subcontractors
Suppliers
Client:
Acquire land and arrange finance;
Appoint and empower a project manger to
represent the clients interest as the leader of a
project team in procuring the products;
Act as a member of the project team but fully
represented by the project manager in day-today decision;
Have only contractual relationship with architect
and builder.
16
Project Manager:
Have contract relationship with the client;
Represent the client to manage the project from the
inception to the completion on a day-to-day basis and is
required to act in the clients best interest;
Be responsible for the development of a strategic plan,
organization of the necessary resources both human and
physical, coordination and integration of activities at each
stage of the projects life cycle and control of the entire
process;
Make recommendations to the client on the selection of the
architect and builder;
Do not have contractual relationship with architect and
builder.
Architect:
Appointed by the client with a contract but overseen by the
project manager;
Carry out the conceptual and detailed designs;
Organize design team including structural engineer, service
engineer (mechanical, electrical, fire safety, hydraulic
engineer), landscape designer, interior designer, quantity
surveyor, etc;
Have contractual links with these specialist consultants and
engineers;
Have communication link with builder and report to project
manager.
17
Builder (Contractor):
Appointed by the client with a lump sum contract or fee +
reimbursable contract;
Appoint subcontractors and material suppliers with
contractual arrangements (usually with lump sum price);
Fulfil all the obligations under the contract, namely to build
the facility within the agreed cost and time budgets and to
the required quality standards;
Accept liability for construction performance and coordinate
the subcontractors;;
Have a communication link with the architects and report to
the project manager.
Risk sharing:
While the client empowers the project manager to lead the
team and be the main day-to-day decision-maker, the client
assumes the responsibility for contracts with other team
members;
In the absence of a guaranteed maximum price, the project
manager assumes the lowest level of risks; with a guaranteed
maximum price, the risk will naturally increase.
Architect needs to assume the risk associated with design
mistakes;
The contract price paid to the builder may be in the form of a
lump sum, a schedule of prices, or a mixture of both, or even
cost-plus.
18
Advantages
Disadvantages
The client is exposed to a high level of risk;
While the client carries a lot of risk, the client is not involved
in day-to-day decision making;
The project manager needs to be appointed at the early part
of the conceptual stage, which may not always be possible
or convenient;
The project manager must be given functional control over
resources including a fund for paying separate contractors.
19
Contract Strategies
The project manager is the clients agent based on a
contract (generally, fees) and appointed at the early part of
the conceptual design stage;
The architect and builder are appointed by the client with
the recommendation of the project manager;
The PM system is basically a fast-tracking in nature and the
contracts between the client and other parties are decided
based on the negotiation and the taking of risks.
20
Client
Tendered Lump Sum
or GMP
Builder
Negotiated Sum
Tendered Amounts
Architect
Subcontractors
Suppliers
Consultants
Client:
Acquire land and arrange finance;
Work a de facto project manager (may engage a specialist
consultant as a superintendent);
Appoint a D&C contractor (builder) and supervise the
contractor work;
Considering that D&C projects are expected to be fasttracked, direct involvement of the client in the project is
essential;
Experienced clients have no reason to engage independent
superintendents since they have the necessary expertise
in-house; inexperienced clients should consider using the
traditional method.
21
Builder:
Appointed by the client in a lump-sum contract;
is the single point responsibility for delivering the project,
managing design and construction including time, cost,
quality and safety;
Can be a company with capacity to design and construct or
contract the design and construction out;
Appoint design consultants (including architect) and
subcontractors with direct contractual relationship as well as
oversight relationship;
22
Risk sharing:
Brief is the most important document in appointing the D&C
builder; if the brief is not of sufficient details or unclear,
disputes may arise over the required standard or quality;
The client assumes the lowest risk provided that the brief is
clearly defined;
Whether a D&C contract is tendered or negotiated, it may be
difficult to estimate the contract price accurately due to a lack
of documentation; the builder would include a contingency
which could be either too high or too low;
The builder takes most of the risks (usually recognized as the
highest risky project delivery method for builder);
If the builder contracts the design and construction tasks out,
the designers and the subcontractors may have to take
corresponding risk.
Advantages
Time is saved because D&C is also fast tracked in nature;
The knowledge input of builder can improve constructability;
The client has only one party to deal with, improved direct
communication and management;
Variations will be minimised as the builder is in charge of the
design and construction;
The client knows the final cost right at the start if using lump
sum contract;
The builder has more flexibility to select the design and
construction methods which are the most suitable for him.
23
Disadvantages
Contract Strategies
Payment to the builder, covering both the design task
and the construction, is generally on a lump sum basis;
the contract sum is established by competitive tender
based on the clients brief, or negotiated based on
estimates prepared by the clients advisors (in this case,
could be Cost-Plus);
The design work would more often than not be
performed for the builder by an architectural firm with
sub-consultants, on a set fee basis negotiated with the
builder.
Subcontractors are engaged usually with lump sum
contracts based on competitive tendering.
24
Client
Client
Tendered Lump
Sum
Architect
Fee
Architect
Construction manager
Q.S.
Negotiated Fees
Tendered
Amounts
Builder
Consultants
Q.S.
Consultants
subcontractors
Subcontractors
Client
Client
Tendered Lump Sum
Fee
Fee
Project Manager
Fee
Architect
Suppliers
Suppliers
Q.S.
Builder
Tendered Amounts
Negotiated Sum
Builder
Architect
Subcontractors
Subcontractors
Consultants
Suppliers
Suppliers
Consultants
Novation
FINANCIERS
CONTRACTURAL
Functional
NOVATED
CONTRACT
LAND AQUISITION
Client
PRE NOVATION
POST NOVATION
COMPLIANCE ADVICE
HEAD CONTRACTOR
ARCHITECT
SUB CONTRACTORS
OTHER CONSULTANTS
25
GOVERNMENT
PROJECT
PERFORMANCE SPEC
ADVISORS
FINANCE
INVESTORS
OPERATOR
D&C TEAM
PROJECT MANAGER
ADVISORS
DESIGN TEAM
PROBITY
PROJECT MANAGER
Project Alliance
26