You are on page 1of 13

Parallel Operation of Transformers with Large Non-identical Taps for

Reactive Power Compensation


K Rajamani
Abhijit Mandal
Reliance Infrastructure Ltd
1.0 Introduction
A PV solar plant of 40MW capacity is established in Dhursar, Rajasthan, India. The
DC output from individual solar panels is converted to AC through inverters. Inverter
outputs are summed up and the consolidated output is stepped to 33kV with 380V /
33kV transformers. The transformers feed 33kV bus of switchyard through over
head lines. In the switchyard, 33kV voltage is further stepped up using two numbers
220/33 kV Step UP Transformers (SUTs). A 32KM overhead line, owned by Power
Plant Operator, connects Dhursar 220kV substation to Deechu substation of State
utility (Grid). The power evacuation scheme is shown in Fig 1. Circuit breaker
positions are omitted to simplify the network details. Details of CSP (Concentrated
Solar Plant), installed at the same location, are omitted as this is not directly
relevant to present analysis and discussions.

1 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

During night time, when the PV plant is down, small auxiliary power to the extent of
500KW is drawn over the Deechu Dhursar EHV line. In the vicinity of plant, MV or
LV lines are not present that could have supplied the auxiliary power. Tariff meter at
Deechu substation is used for billing purpose towards import of power from grid to
plant. The lightly loaded EHV line generates not so insignificant capacitive charging
MVAR. In the present case, assuming 0.14MVAR/KM for line charging, the 32KM
long line will generate about 4.5MVAR. Depending on the actual voltage at which
2

EHV line operates, charging VAR will vary (proportional to V ). Though the active
power drawn on the line is (maximum) 0.5MW, because of charging VAR of line, the
tariff meter at grid station registers maximum demand of about 5MVA. Assuming
demand charges of Rs 160/KVA/month, fixed charges work out Rs 8 lacs per
month.
It is desirable to reduce the contract demand to a minimum so that high fixed
charges are not paid for drawing just 500KW during night time. One straight forward
and well known solution is to install a shunt reactor of 4 to 5 MVAR at 33kV to nullify
the capacitive charging current from line. The reactor can be switched in during
night time and switched off during day time. This will directly reduce the demand
within 1 MVA.
Another (unconventional) alternative is to operate the two 220/33kV transformers in
parallel and deliberately keep the taps of transformers very different (say one at+5%
and the other at -5%). This results in circulating current between the two
transformers. The circulating current produces reactive loss and thus acts like a
shunt reactor. The reactive loss in transformer compensates the capacitive
generation from line. This results in reduced demand from grid station.
This article presents the results obtained from tests done at site operating the
transformer in parallel with non-identical taps.

2 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

2.0 Analysis prior to site testing


Before attempting this novel exercise at site, extensive analytical and simulation
studies were done for parallel operation with different taps to estimate the differential
voltage to be kept to reduce the demand at grid substation to less than 1 MVA.
Parameters of Step Up Transformer (SUT) are given below:
Rating: 50 / 60 / 75 MVA (ONAN / ONAF / OFAF)
Voltage: 220 / 33 kV
Tap Range: 10% in steps of 1.25%
Tap 1 242 / 33 kV
Tap 9(N) 220 / 33 kV
Tap 17 198 / 33 kV
Rated Impedance on 75 MVA: 11. 6% on Tap 9 (Nominal)
: 12.08% on Tap 1
: 11.70% on Tap 17
For simulation purposes, transformer impedance is considered as 11.8%.
Base current B = 75 / (1.732 x 33) = 1.312 kA
2.1 Permissible tap range to avoid overfluxing
During the testing, transformers should not be subjected to over fluxing condition [1].
The design flux density is 1.7T at all taps. Testing was planned after 7PM when the
PV plant shuts down. Based on recent records of 220kV grid voltage profile after
7PM, the maximum grid voltage expected during testing was 230kV. For applied
voltage of 230kV, the operating flux density at different taps is shown in Table 1.
Tap No

10

11

12

14

17

HV Vol kV

242

231

220

217.25

214.5

211.75

206.25

198

HV Vol %

+10

+5

-1.25

-2.5

-3.75

-6.25

-10

BOPE T

1.62

1.69

1.78

1.80

1.82

1.85

1.90

1.97

LV Vol kV

33
Table 1

For example:
Operating flux density at Tap 1 = (230/242) x 1.7 = 1.62T
Operating flux density at Tap 9(N) = (230/220) x 1.7 = 1.78T
Operating flux density at Tap 17 = (230/198) x 1.7 = 1.97T

3 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

The above gives a clue that initially keep the tap of one transformer at 9 and
progressively change the tap of other transformer towards 1 (positive maximum). In
this way, there is no danger of over fluxing. If the demand from Deechu to Dhursar
does not fall below 1MVA, even after keeping the tap at 1 on one transformer,
change the tap of other transformer towards 17 (negative maximum). But in this case
we must ensure that operating flux density does not exceed saturation flux density of
1.9T. As a measure of abundant caution, it was decided to restrict operating flux
density to below 1.85T. This corresponds to a tap 12. Hence the tap range available
is 1(+10%) for one transformer and 12(-3.75%) for other transformer. Studies were
done varying the taps within this permissible range.
2.2 Approximate differential voltage estimation
Assume reactive compensation requirement = Q = 5MVAR

Q = 5 / 75 = 0.0667pu
XT = 11.8% = 0.118pu
Let differential voltage when taps of the two transformers are non-identical = V
Refer Fig 2. When switch S is closed, circulating current flows. Refer Cl 6.2 [2].

Circulating current C = V / 2XT


2

Calculated Reactive Loss = C x 2XT = V / 2XT = Q

V = Sqrt(Q x 2XT) = 0.1255pu


4 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

The approximate voltage difference required is 12.55%. This will create circulating
current that will produce reactive loss of 5 MVAR.
This is verified by detailed load flow simulation described in next section.
2.3 Load flow studies
Refer Fig 3 for base case when both transformers are at nominal tap. The circulating
current is zero. The demand from grid is 5.041 MVA.

Next, tap of SUT1 is kept at 8 (+1.25%) while that of SUT2 is unchanged at 9. Refer
Table 2 and Fig 4. The circulating current between the transformers is 69A which
produces reactive loss. The demand from grid reduces to 4.993MVA.

5 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

Tap No (%)

CIR Amps

Differential

Reactive Compensation

Demand from Grid

MVAR

MVA

Voltage
SUT1

SUT2

(%)

Calculated

Measured

Calculated

Measured

Calculated

Measured

9 (0)

9 (0)

5.041

4.855

9 (0)

1.25

69.0

69.92

0.048

0.040

4.993

4.815

9 (0)

2.50

135.5

140.17

0.189

0.125

4.853

4.730

9 (0)

3.75

201.0

205.07

0.415

0.265

4.628

4.590

9 (0)

5.00

265.0

269.60

0.721

0.570

4.324

4.285

9 (0)

6.25

327.5

332.37

1.101

0.945

3.947

3.910

9 (0)

7.50

388.0

392.33

1.548

1.353

3.504

3.505

9 (0)

8.75

447.5

453.52

2.059

1.833

2.999

3.025

9 (0)

10.00

505.5

509.83

2.628

2.376

2.440

2.485

11.25

575.5

581.70

3.410

3.266

1.682

1.605

12.50

647.5

647.10

4.318

4.152

0.859

0.715

8
(+1.25)
7
(+2.50)
6
(+3.75)
5
(+5.00)
4
(+6.25)
3
(+7.50)
2
(+8.75)
1
(+10.0)
1

10

(+10.0)

(-1.25)

11

(+10.0)

(-2.50)

Table 2

6 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

In Fig 5, tap of SUT1 is at 1 (+10%) while that of SUT2 is at 9. The circulating current
is 505.5A. The demand from grid reduces to 2.44MVA.

In Fig 6, tap of SUT1 is at 1 (+10%) while that of SUT2 is at 11(-2.5%). The


circulating current is 647.5A. The demand from grid reduces to 0.859MVA. Thus with
a differential voltage of 12.5%, the demand from grid reduces below 1MVA which is
the desired objective.

7 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

3.0 Testing at site


The above theoretical analysis gave us confidence to go ahead with testing at site.
Before starting the test, all the existing switchyard protections and schemes were
checked and corrective actions where ever required were ensured to prevent
inadvertent tripping during testing. A template was made to note down the following
for each set of taps:

Tap numbers of SUT1 and SUT2

Grid Voltage

MVA and pf from grid as registered in tariff meter at Deechu

Currents on 33kV side of transformers

OTI and WTI readings

Operating current and restraining current as registered by differential


protection for each transformer.

Automatic control of OLTC was disabled. Tap changing was done locally. Since this
type of testing is one of a kind and rarely attempted before, engineers were
stationed locally near the transformers to notice any abnormal increase in vibration
or noise during testing.

8 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

3.1 Measurement of circulating current


On 33kV side, phase currents (magnitude) for both transformers are measured. The
circulating current is derived as follows:
1

Three phase currents from SUT1: R , Y , B


Three phase currents from SUT2: R , Y , B
1

Measured Circulating current C = (R + Y + B + R + Y + B ) / 6

3.2 Measurement of reactive compensation achieved


Reactive power on tariff meter at Deechu end is measured.
(i) With both transformers on nominal tap (Tap 9), Measured reactive power = Q0
(ii) With non-identical taps, measured reactive power = QK
Measured reactive compensation achieved = Q0 - QK
3.3 Measurement of MVA
The MVA demand is a direct measurement read from tariff meter at Deechu end.
3.4 Comparison between measured and calculated values
Refer Table 2.
(i) Testing started with taps of SUT1 and SUT2 kept at nominal values (Tap 9). The
measured values are:
Circulating current 0
Demand = 4.855MVA
Power factor = 0.043
MVAR = 4.8505
(ii) Tap of SUT1 is changed to 8(+1.25%) while tap of SUT2 tap is unchanged.at 9.
The measured values are:
Circulating current = 69.92A
Demand = 4.815MVA
Power factor = 0.044
MVAR = 4.8103
Reactive compensation realized = 4.8505 4.8103 = 0.0402MVAR

9 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

(iii) Tap of SUT1 is changed to 7(+2.5%) while tap of SUT2 is unchanged.at 9. The
measured values are:
Circulating current = 140.17A
Demand = 4.73MVA
Power factor = 0.043
MVAR = 4.7256
Reactive compensation realized = 4.8505 4.7256 = 0.1249MVAR
(iv) Similar measurements were taken till SUT1 tap is at 1(+10%) with tap of SUT2 is
unchanged at 9. The demand has come down to 2.485MVA (Refer Table 2). Next,
the tap of SUT2 was raised to 10 and then to 11 (-2.5%) with tap of SUT1 at 1. The
measured values are:
Circulating current = 647.1A (49% of RAT)
Demand = 0.715MVA
Power factor = 0.214
MVAR = 0.6984
Reactive compensation realized = 4.8505 0.6984 = 4.1521MVAR
(v) Measured reactive compensation for differential voltage of 1.25% is 0.0402
MVAR {Refer Cl(ii) above}. When differential voltage is increased ten times (12.5%),
{Refer Cl(iv) above} the measured reactive compensation increases by almost 100
times to 4.1521 MVAR. This exponential increase in reactive compensation
2

(proportional to C ) with increase in differential voltage can be seen from Fig 7.


(vi) Further increase in tap of SUT2 to Tap 12 will make the drawl from grid reactive
but the demand will be almost the same with tap of SUT2 at Tap 11. Hence the
testing was terminated with taps of SUT1 and SUT2 at Tap 1 and Tap 11
respectively.
(vii) With tap of SUT1 at 1 and tap of SUT2 at 11, the goal to get the demand at
Deechu below 1MVA is achieved. This corresponds to a differential voltage of 12.5%
and is in line with analytical predictions.

10 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

(viii) Comparisons between calculated values (from load flow studies) and values
obtained from test at site are shown in Fig 7, Fig 8 and Fig 9. The calculated and test
values are in close agreement.

11 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

Minor errors could be attributed to following:

Calculated

values

assume

constant

voltage

on

EHV

side.

During

measurement at site, grid voltage is not steady and varies when readings are
taken at different instances of time. Grid voltage varied between 225.6kV and
227.4 kV during the testing period.

Calculated values assume constant impedance at all taps. In practice, there


is a small variation in impedance at different taps.

Since the quantity measured is low (less than 5 MVA at 220kV), inherent
meter error cant be avoided.

(vii) During the entire testing duration transformers were operated under ONAN
conditions. WTI and OTI readings of both the transformers were monitored. The
maximum recorded values were 45C and 42C for WTI and OTI. These are much
below the alarm and trip settings which are in the range of 90C to 100C.
4.0 Acknowledgement
The authors acknowledge valuable inputs received from Sanjiv Srivastava on over
fluxing aspects.
The authors thank Sonu Karekar for conducting the load flow studies.
The authors acknowledge the contribution of the site team (K Sheshadri, Anil Jain,
Alpesh Prajapati, Amit Jain, Deepak Paswan and Shivdan) at Dhursar for helping to
conduct this unique test successfully and safely.
The authors are grateful to Tanvi Shrivastava. The technical support extended by her
greatly facilitated in getting the experiment through at site.

12 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

5.0 Conclusion
The conventional wisdom during parallel operation of transformers is to keep the
taps of both transformers identical. Specific master follower control schemes have
been developed for OLTC operation to achieve this golden rule. The main reason is
to avoid circulating current between transformers which only adds to heating of
transformer. In the present case, the golden rule has been deliberately broken. The
taps of both transformers are kept widely different to circulate substantial current
between the transformers. The circulating current produces reactive power loss and
the effect of shunt reactor is achieved without a physical reactor being present. The
reactive loss in transformer compensates capacitive VARs produced in EHV system.
This has been successfully demonstrated at site at 220kV level. In India, this may be
one of the few instances where parallel operation with such large deviation in taps at
EHV level has been attempted. The same idea could be extended by system control
operators for mitigating over voltage problems even at grid levels.

Another

interesting application could be for testing Differential / REF schemes passing


substantially large primary currents.
6.0 References
[1] Transformer engineering Design and practice, S V Kulkarni and S A Khaparde,
Marcel Dekker, 2004.
[2] Power transformers - Application guide, IEC 60076-8, 1997

13 of 13
June 2016, IEEMA Journal, Page No. 94 to 98

You might also like