Professional Documents
Culture Documents
STANDARDISED
EEPCO
SPECIFICATIONS
Spec No
TS-CO-01
TS-CO-02
TS-CO-03
TS-CO-04
TS-CO-05
TS-CO-06
TS-GN-01
TS-GN-02
TS-GN-03
TS-GN-05
TS-GN-06
TS-IN-01
TS-IN-02
TS-IN-03
TS-MA-02
TS-ME-01
TS-ME-02
TS-ME-03
TS-SG-01
TS-SG-02
TS-SG-03
TS-SG-04
TS-SG-06
TS-SG-07
TS-SG-09
TS-SG-12
TS-SG-13
TS-SG-14
TS-TR-01
TS-TR-02
TS-TR-06
TS-UV-01
Spec Title
Overhead Conductors and Accessories
LV AB Cables and Accessories
MV UG cables and Accessories
LV - XLPE Power Cables
MV and LV Insulators
Spun concrete poles and Accessories
EEPCO System and Environmental Data
General Contractual Obligations
General management Requirements
Street Light Materials
Mini SCADA System
Installation of 15kV lines
Installation of ABC
Installation of Underground Cables
Earthing Materials
kWh Meters
Meter Boxes and meter CTs
Consumer Connection Cables
Pole mounted MV Drop out Fuses
MV Surge Arrestors
Pole mounted Distribution Box
LV Pole mounted Fuse Switch & Cut out
15kV Pole Mounted Load Break Switch
15kV Pole mounted Air Break Switch
Pole Mounted Autorecloser
15kV Ring Main Units
Pole Mounted 15kV Switched Capacitors
Pole Mounted 15kV Sectionalisers
3 Phase Distribution Transformers
Compact Substations
15kV Voltage Boosters
Utility Vehicles
1.
INTRODUCTION
The 8 Regional Town Distribution Rehabilitation is a subproject of the World
Bank Energy Access Project Additional Financing Project. The two main
components comprise the Transmission Rehabilitation and the Distribution
Rehabilitation which in turn includes the Rural and the Urban (7 towns + Addis
Ababa rehabilitation)
London Power Associates Ltd. in association with Global Energy Consulting
Engineers Pvt Ltd. from India and the local firm Hagbes Ltd. have been awarded a
contract to undertake the Design, Procurement and Supervision Implementation for
the distribution component including the Rural and Urban components.
Part of the consultancy services was to review and modify/upgrade the
specifications for equipment and materials associated with the project.
The consultant has undertaken extensive review of the current EEPCo specifications
and based on his experience has produced updated specifications.
This section of the report addresses the issues of standardised specification and their
adoption by EEPCo company wide and the creation of a department that will handle
the management of these specifications.
It should be noted that ALL orderly run utilities have produced their standardised
specifications and the larger utilities have even more detailed specifications for
equipment types. The bigger and more well run the utility is the larger number of
specifications they have to ensure good management.
2.
STANDARDISED SPECIFICATIONS
In order to improve the management efficiency of the utility and make it easy to
produce tenders for goods and works it is of paramount importance to set up
standardised specifications for equipment and installation works. These documents
should be set up to reflect all hard earned experience of the utility in order to build
on the past and avoid mistakes.
These specifications shall become the standard of equipment and works throughout
the utility and country in order to ensure system uniformity & integration and lead to
cost effectiveness, minimisation of spares and maintenance, improve in Health &
Safety, better environmental management etc. Industry shall also follow the same
standard specifications in order to ensure that the electrical system follows the same
rules and policies across the country.
3.
DEPARTMENTAL STRUCTURE
A department within EEPCo shall be established charged with the production,
update, control, maintenance and circulation of these specifications.
These specifications shall be supplied to any consultant who undertakes system
development or design leading to procurement.
The consultants shall either use them as they are, or be requested to review them
with the view of improving adding details, modify / upgrade them under the
approval of EEPCo.
Any deficiencies or improvements to the specifications shall be undertaken in a
controlled manner and shall not be introduced without the express approval of the
specifications department.
Additional specifications shall be produced following the same style, format and
philosophy of the specifications.
EEPCo standards department shall be responsible for the orderly development of
these specifications and for their circulation, dissemination and adherence.
4.
Specification document
This shall contain the scope, international standard bodies compliance, testing
requirements, technical details etc. and shall be in text format.
b)
Technical schedule
This shall be the list of the technical requirements associated with the specification.
They have been produced in a spread sheet form as it would be easy to compare the
returned data from bids. It is also easy to carry out check on the numbers. These
spread sheets can be given to the Bidders in electronic form to facilitate ease of
assessment.
Once the system has been operating for a few years the specifications can be in a
single text document for ease of management.
The decision to group several equipment at this stage comes in for convenience. As
the utility expands and the management of the specifications improves it will break
down these current specifications into further modules to suit its operational
5.
6.
PUBLICATION OF SPECIFICATIONS
The specifications once establishes shall become public domain and should be
available in the web for the industry to have easy access. The latest specification shall
be published. In this way it would not even be necessary to include the specifications
in the bidding document, but simply quote them. This is the mechanism of also
referring to the international standards by just quoting the standard number.
The specifications department shall be responsible for the maintenance of the
specifications on the web site, or through the web management department.
7.
APPROVED MANUFACTURERS
The issue of quality of equipment is of major concern to ALL utilities around the
world and especially to the developing world. Utilities in the developed countries as
a rule have very tight regulations on the equipment that comes into the country and
in this way there are many safeguards in an attempt to ensure good quality of
equipment.
In developing countries as the specifications are not generally of good standard and
the international community through aid programs require that bidding is open to
international bidders the ground is open to abuse. Many utilities end-up with low
quality goods which in the long term cost more than buying good products in the
first place.
The solution is not simple and there is no simple remedy. If the specifications are
made too tight they may be seen as favouring only certain manufacturers or
describing a particular product. In contracts for equipment such as the World Bank
it is also not possible to request the submission of samples and carry out an
examination of the quality and reject goods which look of poor quality even if they
satisfy the specification as this will be against the rules which specify that the criteria
must be included in the tender and only those can be used to decide on compliance
and not subjective comparisons of equipment offered.
Several utilities however in the developed world have what is called an approved list
of manufacturers and products. The utility has carried extensive research of sample
products submitted or collected by the utility and approved the equipment, and
subsequently have established the list of equipment that are suitable and accepted to
be used within the utility.
This can be seen as a prequalification process but the range of manufacturers must
be wide enough to encourage competition, otherwise it may be seen as market fixing
and preferential treatment of manufacturers.
This approach can certainly be used if the utility uses own funds or government
funds provided that the government has accepted the approved manufacturers list.
8.
SPECIFICATIONS PRODUCED
At this stage LPA who has been assigned to carry out the 8 towns design has
produced the specifications required for the project following this format.
The specifications produced are as shown on the contents table.
EEPCo will have to adopt this POLICY and develop all the specifications required
for the operation of the company in due course. This may be achieved either by
undertaking the development in house or through the consultants with every project
that is being implemented. This would be easy but it can harbour pitfalls with the
consultants as EEPCo would have to have a tight control, and departments other
than the project management will have to be involved with the consultants.
EEPCO
SPECIFICATION
TS-CO-01
Overhead Conductors and Accessories
SECTION 1- SCOPE
SPECIFICATION TS-CO-01
EEPCO
Date
Brief Description
Rev 1
Dec 2012
First Issue
Rev 2
Feb 2013
Rev 3
23 March 2013
Rev 4
8 April 2013
Page: i , 11-Apr-13
SECTION 1- SCOPE
SPECIFICATION TS-CO-01
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
OVERHEAD CONDUCTORS & ACCESSORIES
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
TYPE TESTS
ROUTINE TESTS AND ACCEPTANCE TESTS
2
2
5.
5.1
5.2
5.3
5.4
5.5
5.6
5.7
GENERAL
CONDUCTOR REQUIREMENT
STRANDING
JOINTS IN WIRES
TOLERANCES
SURFACE CONDITIONS
GREASING OF CONDUCTORS
3
3
3
3
4
4
4
6.
7.
8.
9.
10.
5
5
5
6
6
10.1
10.2
10.3
10.4
10.5
10.6
6
7
7
8
8
8
11.
11.1
11.2
11.3
11.4
GENERAL
PARALLEL GROOVE CLAMPS
CABLE LUG
PARALLEL GROOVE CLAMPS FOR ALUMINUM TO COPPER
CONNECTION
INSULATED MID SPAN JOINTS
COMPRESSIBLE MID-SPAN JOINT
STRAIN CLAMP
SOCKET
BALL EYE
EARTHING ROD WITH CLAMP
SPLICING SLEEVE
11.5
11.6
11.7
11.8
11.9
11.10
11.11
Page: ii , 11-Apr-13
9
9
10
11
12
12
13
13
14
15
15
SPECIFICATION TS-CO-01
EEPCO
SECTION 1- SCOPE
11.12
11.13
11.14
11.15
11.16
11.17
15
16
16
17
17
17
12.
13.
17
18
13.1
13.2
13.3
18
19
20
SECTION 1- SCOPE
SPECIFICATION TS-CO-01
EEPCO
SCOPE
This specification covers the Design, Manufacture, Testing and delivery of
Overhead both bare and XLPE insulated All Aluminium Alloy Conductors
(AAAC).
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
AS 3675
IEC 60028
IEC 60060
IEC 60104
IEC 60229
IEC 60287
IEC 60811
IEC 60889
IEC 61089
BS 3242
ASTM D2303
ASTMB399
AAAC conductors
CONFLICT:
See spec TS-GN-02 General Contractual obligations.
4.
Page: 1 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
4.1
TYPE TESTS
Test results shall be provided according to IEC requirements, not later as
specified in the technical schedules or elsewhere, and they will comprise of the
following:
a)
b)
Resistance tests.
c)
d)
Abrasion test
e)
Electrical test
4.2
b)
Diameter Measurement
Page: 2 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
5.
5.1
GENERAL
All Aluminium Alloy Conductors (AAAC) bare conductor shall have the
following characteristics.
All details shall be according to IEC standard and IEC 61089.
5.2
CONDUCTOR REQUIREMENT
The required characteristics of the All Aluminium Alloy conductors are as
follows:
Number
of strands
Diameter
of strands,
mm
Nominal
Al. area,
mm2
Calculated
Al. area
mm2
AAAC 25 mm2
2.3
25
29
AAAC 50 mm2
3.3
50
59.87
19
2.82
100
118.7
19
3.48
150
180.7
AAAC 200 mm
37
2.87
200
239.4
Type
5.3
STRANDING
In all constructions, successive layers shall have opposite directions of lay, the
outermost layer being right-handed. Right-handed lay and left- handed lay shall
be as defined in the latest edition of IEC 61089 .
The wires in each layer shall be evenly and closely stranded.
The lay ratios of different layers shall comply with BS 7884 (aluminium
conductors), as applicable.
In conductors having multiple layers, the lay ratio of a layer shall not be larger
than the lay ratio of the layer directly below it.
5.4
JOINTS IN WIRES
Joints in wires shall comply with the requirements of BS 7884 (aluminium
conductors),
Page: 3 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
5.5
TOLERANCES
Wire diameter shall not depart from the normal value by more than +/-1%.
No diameter of a wire shall differ from the standard diameter by more than plus
or minus 2%.
The mean diameter of a wire shall not differ from the standard diameter by more
than plus or minus 1%.Standard length 5%.
Measurements of resistance shall be carried out to an accuracy of at least 0.1%
5.6
SURFACE CONDITIONS
All wires making up the conductor shall be free from points, sharp edges,
abrasions or other imperfections that would tend to increase radio inference and
corona loss. The conductors shall also be free from metal particles and dirt.
The making and lying of the conductor strands shall be such as to produce a
conductor free from a tendency to untwist or spring apart when cut. The
stranding shall be such that when subjected to 50% of ultimate strength there
shall be no high wires but a cylindrical form shall be maintained.
5.7
GREASING OF CONDUCTORS
(i)
The inner layers of all aluminium conductors shall be covered with approved
anti-corrosive grease having a high melting point. The grease shall completely fill
the interstices between the strands. There shall be no excess grease remaining on
the outer surface which might cause adherence of grit and other material during
pulling out and erection. The minimum drop point (IP 31) of the grease shall be
110oC, and it shall not migrate towards the bottom of the conductor when the
conductor is maintained continuously at a temperature of 95o.
(ii)
(iii)
(iv)
(v)
The grease shall protect the conductor from corrosion in service which may
include operation in atmospheres containing salt spray or industrial pollution.
(vi)
(vii)
The grease shall be compatible with any wire drawings lubricant present on the
wires.
(viii)
The grease shall not flow within, nor exude from the conductor, at temperatures
up to and including 110oC.
(ix)
The grease shall retain its properties including pseudo plasticity, thixotrophy,
syneresis, resistance to oxidation and chemical stability at all operating
temperatures between -10oC and +100oC.
(x)
The grease must not present a health hazard and shall meet all relevant current
health safety requirements.
Page: 4 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
6.
(xi)
All conductors shall be fully greased and wiped in such a way that all wires in the
conductor are covered with grease except the outer surface of those in the out
layer, all the inner interstices filled with grease and the outer interstices have a
small quantity of grease remaining along the lines of contact of the wires
(xii)
The Supplier shall give details of the proposed greasing system and name the
grease to be used in the Technical Data Schedules. He shall also give details of
the proposed wiping system.
(xiii)
The Supplier shall specify the minimum weight of grease (kg/km) in each of the
conductors offered in the attached technical Data Schedules.
(xiv)
(xv)
The Supplier shall give details of the control supervision and testing measures
taken to ensure that there are no discontinuities in greasing.
max.0.5
7.
8.
Page: 5 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
9.
10.
10.1
a)
b)
c)
Construction
Drum flanges shall be 2-layer construction with minimum 60 mm thickness. Each
layer shall be nailed and fixed with grip nails at approximately 90 degrees. Nails
shall be driven from the inside face of the flange, punched and then clenched on
the outer face. There shall not be less than 2 nails per board in each circle.
Page: 6 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
d)
Spindle holes
Reels shall be constructed so that they must be supported either on an axle
through the reel flange. A round spindle hole of minimum diameter 120mm is
required at the centre of the wooden drums. Spindle hole/supports shall be
reinforced with a suitable steel flange.
e)
Conductor ends
The inner as well as outer end of conductor shall be brought out on the drum
flange and shall be clamped in such a manner to make the conductor length
marking easily visible.
Each end of conductor shall be crimped to prevent unwinding and causing
danger.
f)
g)
Lugging
The conductors shall be lagged or covered with suitable material to provide
physical protection during transit and during storage and handling operations.
Preferable mode of lugging shall be by wooden lagging on the circumference with
a thickness of at least 40 mm.
10.2
DRUM SIZES
The drums shall have the following dimensions:
Max. Diameter:
2280 mm;
Max. Width:
1140 mm;
Page: 7 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
reserves the right to place orders for the above lengths on the same terms and
conditions appliconductor for the standard lengths during the validity of the
Contract.
10.4
a)
DRUM MARKING
Direction of drum rolling
The direction for rolling as indicated by an arrow together with the words "Roll
this way" shall be marked on each flange.
Each drum shall be marked to indicate weather proofing.
b)
Drum Labels/Marking
The drum shall have metallic or plastic plates /labels or shall have the data
indelibly branded on the conductor drum for shipping purpose. In any case all
branding shall be indelibly marked to indicate the following:
1) Name of Purchaser EEPCO
2) Contract Number,
3) Manufacturers name,
4) Trade mark/model if any,
5) Conductor type, name and specification
6) Conductor size and stranding,
7) Exact length of conductor (in meters) contained in the drum,
8) Gross weight (kgs) of the loaded drum,
9) Net weight (kgs) of the conductor,
10) Drum Serial Number,
Each case/consignment shall contain a fully detailed packing list covering the
above details in a sealed waterproof envelope.
Three copies of each packing list shall be sent to the Employer prior to dispatch.
10.5
DRUM WARRANTEES
The bidder/contractor would implicitly guarantee the soundness of the conductor
drums for three (3) years.
Should the drums fail within this period, due to poor quality of materials and
workmanship, the contractor shall be responsible for re-drumming the
conductor/conductor to new drums provided free of charge by the contractor.
Damage due to careless handling and storage by the client shall not be covered
under this guarantee.
Damage due to careless handling and storage by the contractor or his agents shall
be fully covered under this guarantee.
10.6
SHIPMENT
The Contractor shall be responsible for CIF / CIP (or as specified in the tender)
delivery of all goods to the point of delivery specified in the tender inquiry.
Page: 8 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
11.
11.1
GENERAL
Conductor connectors are required for aluminium alloy non-tension and tension
joints, and for connecting aluminium alloy conductor to terminals of outdoor and
indoor electrical equipment. These shall be complete with any special tools, bolts
and washers appropriate to the application for which they are to be used.
The edges of the connector barrels shall be rounded to assist stress relief when
the connectors are used with covered (partially insulated) conductors. All
connectors shall be supplied pre-filled with high quality oxide inhibiting
compound and shall be protectively capped to prevent spillage or spoilage of this
compound. All connectors shall be clearly and permanently marked with the
correct size and category.
In addition all connectors shall comply with the following:
The current must be uniformly distributed among the strands of the conductors
The connector must have at least the same conductance as the conductor and
carry the full continuous current rating of the conductor size they are designed for
The original quality of contacts shall be maintained throughout the connectors
service life
Glow discharges and radio interferences must be reduced to a minimum.
All compression connectors shall be suitable for installation using either manual
or hydraulic compression tools. Details of dies and tools required for the
compression connectors offered shall be submitted with the Bidder. Complete
instructions for the installation of each type of connector shall be provided by the
contractor.
Preformed ties shall be supplied for conductor dead ends, guy dead ends and
conductor ties. Bolted parallel groove clamps shall be used for jumpers spur takeoffs and connections to Fuse cut outs.
The Preformed ties for bare conductor and stay wire shall be adequate strength,
must not slip whilst in service and compatible with the AAAC and AAC
conductors, and galvanized steel guy wires specified. The Contractor shall ensure
that all preformed ties are compatible for installation with the insulators and
thimbles specified or as required for correct construction
11.2
11.2.1
Design
The clamp shall be suitable for one or more of the aluminium standard
conductors according to DIN 48201. DIN 48215for overhead power lines.
The size of the clamps shall be suitable for the conductors of sizes mentioned in
clause.5.2 above.
Page: 9 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
11.2.2
Material
The clamps shall be manufactured from materials, which withstand the
mechanical loads and service conditions.
All materials of clamps shall be corrosion resistant and shall not deteriorate in
service. The tensile strength of the body shall be at least 300 N/mm2.The clamp
shall be greased during manufacture.
11.2.3
Markings
The clamp shall be marked with the name or trademark of the manufacturer and
the type or catalogue number of the clamp.
11.2.4
Quotation
The quotation shall be accompanied at least by the following information in three
copies.
(i)
(ii)
(iii)
all materials and coatings specified according to ISO, IEC, BS or DIN standards.
(iv)
(v)
technical characteristics
(vi)
(vii)
markings
(viii)
11.3
CABLE LUG
11.3.1
Design
Straight and angle cable lugs shall be made of tinned brass. Both the tube and eye
shall be suitable for copper and aluminium conductors and be delivered with all
necessary bolts, nuts and washers.
11.3.2
Materials
The cable lugs shall be manufactured from materials which withstand the
mechanical loads and services conditions. All materials of the cable lugs shall
resist corrosion and shall not deteriorate in service.
11.3.3
Marking
Each cable lug shall be marked with name or trade mark of the manufacturer and
the specified cross-section of the conductor.
Page: 10 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
11.4
11.4.1
Design
The parallel groove clamps for A1-Cu-connection Clamps will be used for nontension connecting of aluminium and copper conductors complying withthe
following standards.
DIN 48215
DIN 48201
BS 6485
BS 6360
The clamp shall be suitable for the Aluminium-alloy conductors and for the
copper conductors according to BS 6485 or BS 6360 .
Cu 2.5 mm2
Cu 16 mm2
Cu 4 mm2
Cu 25 mm2
Cu 6 mm2
Cu 35 mm2
Cu 10 mm2
11.4.2
Material
The parts of the clamps shall be manufactured from materials, which withstand
the mechanical loads and environmental circumstances. All ferrous parts shall be
hot-dip galvanized.
The tensile strength of the body shall be at least 300 N/mm2.
The clamp shall be greased during manufacture.
Each clamp shall be marked with the name or trademark of the manufacturer.
The markings shall be legible and durable.
11.4.3
Quotation
The quotation shall be accompanied at least by the following information in three
copies:
(i)
(ii)
(iii)
All materials and coatings specified according to ISO, IEC, BS or DIN standards.
(iv)
(v)
Technical characteristics
(vi)
Page: 11 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
(vii)
Markings
(viii)
11.5
11.6
11.6.1
Design
The mid span compressible joints shall be suitable for all aluminium conductors
to DIN 48207. The tensile strength of the body of the joints shall be at least 300
N/mm2 and shall be able to achieve at least 85% of the corresponding breaking
load of the conductor.
The conductor joint shall be suitable for the following all aluminium conductors
according to DIN 48201.
Mid span Compressible joints for AAAC offered shall be suitable for the
conductors mentioned at clause 5.2 above.
11.6.2
Material
The parts of the joints shall be manufactured from materials, which withstand the
mechanical loads and the prevailing service conditions. Material of the conductor
joints shall be corrosion resistant and shall not deteriorate in service.
11.6.3
Markings
The joints shall be marked at least with the conductor size it is meant for, the
name or trademark of the manufacturer and the catalogue number of the joint.
11.6.4
Quotation
The quotation shall be accompanied at least by the following information.
(i)
(ii)
Dimensional drawings
(iii)
(iv)
Technical characteristics
(v)
Markings
(vi)
Page: 12 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
If the manufacturer cannot comply with any requirement of this specification, the
exception shall be clearly stated in the quotation; otherwise it is taken for granted
that the items quoted meet the requirements.
11.7
STRAIN CLAMP
Bolted dead-end strain clamps, clevis type, minimum breaking load 40 kN, all
ferrous parts to be hot-dip galvanized. Nominal size of coupling shall be 16mm
according to IEC 120. Suitable for conductor diameter 6 - 18 mm.
11.8
SOCKET
11.8.1
Socket Eye
This Specification specifies the design, manufacture and testing requirements for
the Standards
IEC 60120 Dimensions of ball and socket couplings of disc insulator units.
IEC 60372 Locking devices for ball eye and socket eye couplings of disc insulator
units
11.8.2
Design
The socket eyes to be used together with string insulator units of cap and pin type
U40BL in accordance with IEC 305 with an electro-mechanical failing load of 45
kN to be used in the 33 kV distribution networks.
The socket eye shall be designed for a mechanical failing load of 45 kN.
The dimension and tolerances of the ball and socket coupling shall comply with
IEC 120. The sizes of the socket couplings to be used are the standard size
coupling 11 as specified in IEC 120. In addition to this the internal height of the
socket shall also meet the requirement of IEC 372.
The dimensions and tolerances of the split-pins shall meet the requirements of
IEC 372.
Cast fittings with socket shall be made of either malleable cast iron or approved
equal. Forged steel fittings with socket shall be made from steel of a suitable
grade.
Material of split-pins shall be a copper alloy or stainless steel complying with the
requirements of IEC 372.
All ferrous metal parts exposed to corrosion shall be protected by hot-dip
galvanizing.
11.8.3
Markings
The split-pins shall be installed into the locking position in sockets.
Each socket eye shall be marked with the name or trademark of the manufacturer,
type or catalogue number of fitting and the minimum failing load.
11.8.4
Testing
The sample and routine tests shall be carried in accordance with BS 3288: Part 1.
Test on split-pins shall be made according to IEC 372.
Page: 13 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
The dimensions of ball and socket couplings shall be checked on random samples
using gauges in accordance with IEC 120.
11.8.5
Quotation
The quotation shall be accompanied by the following information:
(i)
(ii)
dimensional drawings
(iii)
all materials and coatings specified according to ISO, IEC, BS or DIN standards.
(iv)
(v)
technical characteristics
(vi)
markings
(vii)
11.9
BALL EYE
11.9.1
Design
The ball eyes to be used together with string insulator units of cap and pin type
U70BL in accordance with IEC 305 for use in 33 kV overhead distribution lines.
The ball eye shall be designed for a mechanical failing load of 45 kN. The
dimension and tolerances of the ball and eye coupling shall comply with the
standard coupling size 11 of IEC 120 and IEC 372. In addition to this the
internal height (H2) of the ball shall also meet the requirement of IEC 372. The
ball eye dimension shall meet the requirements of BS 3288.
11.9.2
Materials
Ball eyes shall be made by forging from steel of suitable grade. All ferrous parts
exposed to corrosion shall be protected by hot-dip galvanizing.
11.9.3
Markings
Each ball eye shall be marked with the name or trademark of the manufacturer
and the type or catalogue number the coupling size and mechanical failing load.
The markings shall be legible and durable.
11.9.4
Testing
Testing shall be in accordance with standards referred by the manufacturer.
11.9.5
Quotation
The quotation shall be accompanied by the following information:
(i)
(ii)
dimensional drawings
(iii)
all materials and coatings specified according to ISO, IEC, BS or DIN standards.
Page: 14 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
(iv)
(v)
markings
(vi)
technical characteristics
(vii)
11.10
11.11
SPLICING SLEEVE
These shall be supplied for jointing the following bare MV conductors.
Nominal Size (mm)
200
150
100
50
25
Material to be Terminated
AAAC
AAAC
AAAC
AAAC
AAAC
The minimum failing load of splicing sleeve shall be greater than the breaking load
of the matching conductor. The splicing sleeve shall be suitable for jointing
AAAC .overhead conductor and shall provide conductivity that is equal or better
to the conductor.
11.12
Page: 15 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
a)
(i)
(ii)
Interlocking fingers,
(iii)
(iv)
Have a one, two, or three bolt pattern to suit conductor size and current rating,
(v)
(vi)
(vii)
b)
Types
Clamp shall be supplied for the following type of conductors:
Side A
Nominal Size
mm
200
150
100
50
25
11.13
Material to be
connected
AAAC
AAAC
AAAC
AAAC
AAAC
Side B
Nominal Size
Material to be
mm
connected
200
AAAC
150
AAAC
100
AAAC
50
AAAC
25
AAAC
MARKING
Each connector shall be legibly marked with the manufacturers catalogue number
and conductor diameter range for each grove, and each shall be supplied in a clear
plastic package.
Packaging
Each connector shall be supplied in an individual sealed clear plastic bag or
pocket. The bag shall be adequately durable to ensure no grease or oxide
inhibiting compound is lost or spoiled prior to the time of installation. The bag
shall be labelled with the makers name or trade mark, and the size range of the
fitting. Bags shall be further packaged in cardboard or similar containers in
quantities of approximately 100 fittings of the identical description.
11.14
Material to be terminated
AAAC
AAAC
AAAC
Page: 16 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
50
25
11.15
AAAC
AAAC
Material to be compressed
AAAC
AAAC
AAAC
AAAC
AAAC
All preformed ties shall be supplied with a neoprene pad for insertion over the
conductor where it rests in the insulator top or side groove.
11.16
TERMINAL LUGS
Terminal lugs shall be heavily tinned plated aluminium and of the compression
type pre-filled with compound and suitable for connection of conductor onto
copper terminals using suitable bolts. Terminal lugs with one 13 mm hole in palm
for AAAC
11.17
11.17.1
Packing
The accessories shall be packed in individual sealed clear plastic bags. The bags
shall be adequately durable and should not be spoiled prior to the time of use of
the accessories. The bags shall be further packaged in wooden or similarly strong
containers in quantities of approximately 100 fittings of identical description.
11.17.2
Marking
The bags shall be labelled with the makers name or trade mark, the size, range of
the accessories etc.
Each connector shall be legibly marked with the manufacturers catalogue number
and conductor diameter range for each grove, and each shall be supplied in a clear
plastic package.
12.
Page: 17 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
13.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
13.1
Page: 18 , 11-Apr-13
SPECIFICATION TS-CO-01
EEPCO
13.2
SPECIFICATION TS-CO-01
EEPCO
13.3
LPA-GECE
EEPCo
No
Item
Unit
Requirement
Bid Offer
Requirement
Bid
Offer
Manufacturer
Manufacturer's Code N
Type
Standard
Conductor Material
- Aluminium Area
AAAC
AAAC
AAAC
AAAC
AAAC
mm2
25
50
100
150
200
N/mm
7/2.3
7/3.3
19/2.82
19/3.48
37/2.87
mm
6.9
9.9
14.1
17.4
20.09
10
ohm/km
1.1453
0.5498
0.2787
0.1831
0.1385
11
kN
9.44
16.78
33.32
50.64
67.09
12
- Weight
IEC
Ash
kg/km
79.5
164
326
497
659
13
14
Temperature Range
-5 to +45
-5 to +45
-5 to +45
-5 to +45
-5 to +45
15
Humidity
70
70
70
70
70
16
Drum:
2000
2000
2000
1000
1000
17
18
mm mm
19
- Gross weight
kg
Page 1
Date: 11/4/2013,
LPA-GECE
EEPCo
Item
Unit
Requirement
Bid Offer
Requirement
Requirement
Bid
Offer
Manufacturer
Manufacturer's Code N
Type
Standard
Conductor Material
IEC
AAAC
AAAC
AAAC
AAAC
AAAC
Ash
Conductor Characteristics
7.1
- Aluminium Area
mm2
25
50
100
150
200
7.2
N/mm
7/2.3
7/3.3
19/2.82
19/3.48
37/2.87
7.4
mm
6.9
9.9
14.1
17.4
20.09
7.5
ohm/km
1.1453
0.5498
0.2787
0.1831
0.1385
7.6
kN
9.44
16.78
33.27
50.64
67.09
7.7
- Weight
kg/km
79.5
164
XLPE
XLPE
XLPE
XLPE
XLPE
>=2.55
7.3
Insuslation
8.1
- Material
8.2
- Thicknes
mm
>=2.55
>=2.55
>=2.55
>=2.55
8.3
- Density
g/cm
>=0.93
>=0.93
>=0.93
>=0.93
>=0.93
8.4
- Colour
Black or gray
Black or gray
Black or gray
Black or gray
Black or gray
0.5
8.5
- Meltfolw Index
Max
0.5
0.5
0.5
0.5
10
Temperature Range
-5 to +45
-5 to +45
-5 to +45
-5 to +45
-5 to +45
11
Humidity
70
70
70
70
70
12
Drum:
2000
2000
2000
1000
1000
13
14
mm mm
15
- Gross weight
kg
Page 2
Date: 11/4/2013,
EEPCo
Item
1. Stranded Bare copper conductor
Unit
Requirement
Manufacturer
Country of Origin
Type designation
Standard
Overall diameter,
mm
7.5
Cross section,
mm
35
No of Strand
Diameter of strand,
mm
2.5
DC resistance at 200C,
ohm/km
0.5
10
11
Weight,
12
13
IEC 228
230
kg/km
310
Modules of elasticity,
kpa
11x10 7
kN
8.7
14
,/0C
16.6x10 -6
15
16
16.1
Diameter
16.2
Width
17
kg
18
kg
No
Bid Offer
Item
Unit
Requirement
Bid Offer
Unit
Requirement
Bid Offer
kN
> 4.5
N/mm2
>1
Manufacturer
2.2
Country of origin
2.3
Type designation
2.4
Standard
2.5
Diameter of wire
2.6
No of strands
2.7
Breaking load kN
40
2.8
Tensile Strength
1000
8
7 / 2.6mm
2.9
250g/m2
2.10
100 mt
2.11
No
Item
3. Aluminum Round Tie Wire for All
Aluminum Conductors
3.1
Manufacturer
3.2
Country of origin
3.3
Standard applied
3.4
Type designation
3.5
3.6
Breaking load
3.7
Tensile Strength
3.8
Diameter
mm
3.9
kg
30
25
No
Item
4. Parallel Groove Clamps Al/Al 25160
mm2
4.1
Manufacturer
4.2
Country of origin
4.3
Type Designation
4.4
4.5
EEPCo
Unit
Requirement
mm2
Al 25200mm2
mm2
Al 25200mm2
4.6
mm
4.7
mm
4.8
Aluminum alloy
Aluminum alloy
4.9
4.10
Material standard
4.11
4.12
4.13
4.14
4.15
4.16
4.17
No
Item
5. Cable Lugs 35, 75,120,185,300 mm2
diameter
5.1
Manufacturer
5.2
Country of origin
5.3
Type designation
5.4
Standard referred
5.5
Material
5.6
Material standard
5.7
35,75,120,185,300
5.8
35,75,120,185,300
5.9
5.10
5.11
5.12
No
Item
6.Parallel Groove Clamps Al 25200
mm2/Cu 10120 mm2
6.1
Manufacturer
6.2
Country of origin
6.3
Type Designation
6.4
mm2
Al 25200mm2
6.5
mm2
Cu 10120 mm2
6.6
mm
6.7
mm
6.8
6.9
6.10
Material standard
6.11
6.12
6.13
6.14
N/mm2
Bid Offer
300
M10
mm
85
g
pcs
Unit
Requirement
Bid Offer
DIN48215
Tinned Brass
DIN48215
300
>10 (thin quoting)
Unit
Requirement
Bid Offer
Aluminum Alloy
Copper
N/mm2
300
M10
No
Item
6.15
6.16
6.17
No
EEPCo
Unit
Requirement
mm
43
Bid Offer
g
Pcs.
Item
Unit
Requirement
mm2
Al 25100mm2
Bid Offer
Manufacturer
7.2
Country of origin
7.3
Type Designation
7.4
7.5
Aluminum Alloy
7.6
Material standard
7.7
N/mm2
300
7.8
KN
40
7.9
mm
7.10
Kg
7.11
Pcs.
0.178
Manufacturer
8.2
Country of origin
8.3
Type Designation
8.4
8.5
Al 2550mm2
8.6
Material standard
Aluminum Alloy
8.7
8.8
KN
25
8.9
mm
0.118
8.10
Kg
8.11
Pcs.
No
Item
N/mm2
300
Unit
Requirement
mm2
Al 25125mm2
Bid Offer
Manufacturer
9.2
Country of origin
9.3
Type Designation
9.4
9.5
9.6
Material standard
9.7
9.8
KN
9.9
mm
9.10
Kg
9.11
Pcs.
No
Item
Aluminum Alloy
N/mm2
Unit
0.118
Requirement
Bid Offer
Manufacturer
10.2
Country of origin
10.3
Type Designation
10.4
No
Item
EEPCo
Unit
Requirement
10.5
Al 25200mm2
10.6
Material standard
Aluminum Alloy
10.7
N/mm2
10.8
KN
10.9
mm
10.10
Kg
10.11
Pcs.
Bid Offer
0.118
Manufacturer
10.2
Country of origin
10.3
Type Designation
10.4
10.5
Al 25200mm2
10.6
Material standard
10.7
N/mm2
Aluminum Alloy
10.8
KN
10.9
mm
10.10
Kg
10.11
No
0.118
Pcs.
Item
Unit
Requirement
Bid Offer
Manufacturer
11.2
Country of origin
11.3
Type Designation
11.4
11.5
Material
11.6
Material standard
11.7
Size
11.8
11.9
11.10
N-m
11.11
mm
11.12
11.13
No
mm
BS 3288,IEC 120
120
KN
70
M12
85
g
pcs
Item
Unit
Requirement
Bid Offer
13 Socket Eye
12.1
Manufacturer
12.2
Country of origin
12.3
Type Designation
12.4
Material standard
12.5
12.6
kN
70
12.7
Diameter of eye
kN
40
12.8
mm
17.5
12.9
mm
85
12.10
kg
12.11
No
Forged steel
BS 3288
pcs
Item
Unit
Requirement
Bid Offer
No
Item
EEPCo
Unit
Requirement
13.1
Manufacturer
13.2
Country of origin
13.3
Type Designation
13.4
Material standard
13.5
kN
70
13.6
kN
40
13.7
Diameter of eye
mm
13.8
mm
16
13.9
mm
85
13.10
kg
13.11
No
Item
15. Earth Rod and Clamp
14.1
Manufacturer
14.2
Country of origin
14.3
Type Designation
14.4
Standard referred
14.5
14.6
Standard Reference
14.7
Material Standard
14.8
Section profile
14.9
14.10
Bid Offer
Forged steel
pcs
Unit
Requirement
Bid Offer
Galvanised steel
DIN 50975
DIN 50976
mm
50 x 50 x 3
EEPCO
SPECIFICATION
TS-CO-02
LV ABCables& Accessories
SPECIFICATION TS-CO-02
EEPCO
Date
Brief Description
Rev 0
Jan 2011
First Issue
Rev1
Dec2012
Rev2
Feb2013
Rev 3
20 April 2013
Rev 4
30 April 2013
Page: i , 1-May-13
SPECIFICATION TS-CO-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
LV AB CABLES& ACCESSORIES
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
2
2
3
5.
DESIGN
5.1
5.1
5.2
5.3
5.4
GENERAL
ABC CONFIGURATIONS - SIZES
CONSTRUCTION OF CONDUCTORS
MESSENGER (NEUTRAL CONDUCTOR ) :
INSULATION
4
5
5
5
6
6.
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6
7
7
8
9
9
10
10
7.
8.
9.
10.
LV AB CABLE ACCESSORIES
PACKING AND MARKING
QUALITY ASSURANCE PLAN
SCHEDULE FOR LV AB CABLES ANDACCESSORIES
10
16
16
17
10.1
10.2
17
18
Page: ii , 1-May-13
SECTION 1- SCOPE
SPECIFICATION TS-CO-02
EEPCO
LV AB CABLES& ACCESSORIES
1.
SCOPE
This specification covers the Design, Manufacture, Testing and delivery
requirements of Cross Linked Poly Ethylene insulated (XLPE) Aluminium Cables
twisted over a central bare Aluminium alloy messenger wire (along with associated
accessories) for use as LV overhead line.
ABC conductors shall be according to the French general standard NFC 33
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
IEC 60071
Insulation co-ordination
IEC 60228
IEC 60230
IEC 60885
IEC 60811
VDE 0276part
626
NFC 33-0411998
NFC 33-0211998
NFC-004-1998
NFC 330421998
Page: 1, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
3.1
NFC 332091998
ASTM D 1603
CONFLICT:
See spec TS-GN-02.
4.
4.1
TYPE TESTS
Type test includes all the items listed below and shall be performed on each rated
cross-sectional area per IEC. As long as design, material and manufacturing
methods are not changed so that the tested properties are unfavorably affected,
the test need not be renewed.
4.1.1
Tensile test.
(ii)
Wrapping test.
(iii)
Resistance Test
4.1.2
(ii)
(iii)
(iv)
Shrinkage Test
(v)
(vi)
(vii)
(viii)
4.1.3
b)
Elongation Test
c)
Resistance Test
4.2
ROUTINE TESTS
Sample test of a manufactured lot of cables is performed and includes all items as
follows:
4.2.1
Conductors Resistance
The resistance of the conductors is measured with DC voltage on a complete
cable. The value of resistance/length, converted into 20C with a correction
Page: 2, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
factor according to IEC 60228, must not exceed the values for Aluminium
conductors given in IEC 60228.
4.2.2
Check of Dimensions
The thickness of the conductor insulation is determined according to IEC
publication 60811. The prescribed thickness shall be kept within the tolerances
given in IEC publication 60502-1, clause 4.2 (c) and (d).
The diameter D of the core including insulation is measured and shall be within
the tolerance limits given.
4.2.3
Tensile Test
The test shall be performed according to IEC 60228.
4.2.4
Visual Inspection
A specimen of 0.5 m is selected and visually inspected. In all cores the conductor
insulation shall lie close to the conductor, but it shall be possible to remove it
without pieces of the insulation remaining on or between the strands of the
conductor.
4.2.5
Voltage test
The routine test includes voltage test (dry test) with AC voltage of 10 kV, 50 Hz,
which is applied between the earthen conductor in each cable core and an
electrode through which this core is passing. The electrode can consist of a closemeshed wire network, metal balls or a similar device which completely encloses
the core of ionized air. Each point of the surface of the core shall be in the
electric field at the electrode for at least 0,1s . Any break down shall not be
allowed.
4.3
ACCEPTANCE TESTS
All the tests indicated aboveshall be conducted.
4.3.1
AC Voltage Test
AC voltage test is performed as a wet test. Before the test, at least 10 m of cable
shall have been immersed for 24 h in water having a temperature of 20 C. The
Page: 3, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
SECTION 5- DESIGN
cable shall then withstand 4 kV, 50 Hz, for 4 h between the conductor and the
water.
4.3.3
4.3.4
(i)
(ii)
b)
4.3.5
5.
5.1
DESIGN
GENERAL
The first part of the designation refers to the number and size (nominal cross
sectional area) of the phase conductor and the last part to size of the messenger.
Page: 4, 1-May-13
SECTION 5- DESIGN
SPECIFICATION TS-CO-02
EEPCO
5.1
5.2
Phase conductor
(mm2)
Messenger
(mm2)
Street lighting
conductor (mm2)
3x95
70
16
3x95
70
3x50
35
3x50
35
3x35
25
3x25
25
3x120
95
16
16
CONSTRUCTION OF CONDUCTORS
All conductors shall be constructed to IEC 61089. The properties of the
Aluminium wires before stranding shall be as below.
Tensile strength not less than
90 N/mm2
0.02845 ohm/mm/m
The messenger, which is also the neutral conductor, takes all of the mechanical
stresses.
5.3
Page: 5, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
278 N/mm
0.0328 ohm/mm/m
Density at 20C
2.7 kg/m
No joints are allowed in the messenger except those made on the base rod or wire
before final drawing. The messenger shall be round, stranded and compacted to
have smooth round surface.
The messenger takes all the mechanical stress and also serves as a neutral
conductor.
The other parameters are mentioned in the technical schedule TS-CO-02 S.
In addition to the above the following specification shall apply:
5.4
INSULATION
The Insulating Material shall be of black weather resistant cross linked
thermosetting polyethylene (XLPE) conforming to NFC 32-020 and shall be
suitable for climatic conditions of the country.
The mechanical strength and other mechanical properties such as tensile strength,
minimum elongation at break and physical/chemical properties shall conform to
the relevant Clauses in NFC 32-020.
The minimum tensile strength shall not be less than 14.5 Mpa and the minimum
elongation at break shall be 200%.
Adherence of the insulating sheath to the strain bearing neutral conductor shall be
adequate enough to prevent the slipping of the insulating sheath. The required
adherence shall be achieved by the use of paper material or other technique.
The insulating sheath shall be fully pressure extruded on the bare conductors of
the phases / street lamp / neutral messenger.
6.
6.1
Page: 6, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
6.2
CABLE IDENTIFICATION
Cable identification shall include embossing of the outer over sheath with the
following details:a)
EEPCO
b)
Manufacturers name
c)
Cable size
d)
Rated Voltage
e)
Year of Manufacturer
The letters and figures shall be raised and shall consist of upright block characters.
There should be at least one such marking set at every 2m to suit manufacturing
process.
6.2.2
6.3
b)
Page: 7, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
The surface of the cable drum where cable is stored shall be free from sharp
objects such as nail tis or protruding heads, which might damage the conductor.
c)
Construction
Drum flanges shall be 2-layer construction with minimum 60 mm thickness. Each
layer shall be nailed and fixed with grip nails at approximately 90 degrees. Nails
shall be driven from the inside face of the flange, punched and then clenched on
the outer face. There shall not be less than 2 nails per board in each circle.
d)
Spindle holes
Reels shall be constructed so that they must be supported either on an axle
through the reel flange. A round spindle hole of minimum diameter 120mm is
required at the centre of the wooden drums. Spindle hole/supports shall be
reinforced with a suitable steel flange.
e)
Cable ends
The inner as well as outer end of cable shall be brought out on the drum flange
and shall be clamped in such a manner to make the cable length marking easily
visible.
Each end of cable shall be durably sealed at both ends with hot melted paste and
provided with shrinkable end caps to prevent ingress of moisture.
f)
g)
6.4
Lugging
DRUM SIZES
The drums shall have the following dimensions:
Max. Diameter:
2280mm;
Max. Width:
1140mm;
Page: 8, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
6.5
1000m
500m
The length of cable for drum shall be as specified in the technical schedules.
A variation of + 5% of the cable drum length may be acceptable.
All cable lengths cut and used for various tests shall be to contractor's account
and shall not be included in cable length to be supplied.
Bidder shall also indicate the maximum single length, over and above the standard
length, he can manufacture in the guaranteed technical particulars of offer. This
may be required for special stretches like river crossing etc. The Purchaser
reserves the right to place orders for the above lengths on the same terms and
conditions applicable for the standard lengths during the validity of the Contract.
6.6
DRUM MARKING
a)
b)
Drum Labels/Marking
The drum shall have metallic or plastic plates /labels or shall have the data
indelibly branded on the cable drum for shipping purpose. In any case all
branding shall be indelibly marked to indicate the following:
1) Name of Purchaser EEPCO
2) Contract Number,
3) Manufacturers name,
4) Trade mark/model if any,
5) Conductor type, name and specification
6) Conductor size and stranding,
7) Exact length of conductor (in meters) contained in the drum,
8) Gross weight (kgs) of the loaded drum,
9) Net weight (kgs) of the conductor,
10) Drum Serial Number,
Each case/consignment shall contain a fully detailed packing list covering the
above details in a sealed waterproof envelope.
Three copies of each packing list shall be sent to the Employer prior to dispatch.
Page: 9, 1-May-13
SPECIFICATION TS-CO-02
EEPCO
6.7
DRUM WARRANTEES
The bidder/contractor would implicitly guarantee the soundness of the cable
drums for three (3) years.
Should the drums fail within this period, due to poor quality of materials and
workmanship, the contractor shall be responsible for re-drumming the
cable/conductor to new drums provided free of charge by the contractor.
Damage due to careless handling and storage by the client shall not be covered
under this guarantee.
Damage due to careless handling and storage by the contractor or his agents shall
be fully covered under this guarantee.
6.8
SHIPMENT
The Contractor shall be responsible for CIF / CIP (or as specified in the tender)
delivery of all goods to the point of delivery specified in the tender inquiry.
7.
LV AB CABLE ACCESSORIES
7.1.1
General
The design, performance and test requirements shall confirm to this specification
and the following standards. However in case of any conflict, the requirements of
this specification shall prevail.
Specification/Standard Number
NFC33-020
NFC33-209
NFC20-540
NFC33-004
NFC33-040
NFC33-041
Title
Insulation Piercing Connectors
LV Aerial Bunched Cables
Environment Testing for Outdoor
Electrical Ageing Test
Suspension Equipments
Anchoring Devices
The devices shall also be compatible with the cables of sizes & dimensions as
defined in the Cable Specifications for the cables with which they are intended to
be used.
a)Since ABC accessories are to be used with insulated neutral-cum-messenger,
their design should incorporate specific features to prevent damage to the
insulation when meeting the required electrical, mechanical & thermal
requirements.
b)All mechanical, electrical & thermal ratings should meet or exceed90%ofthe
corresponding ratings of the cable, or the values specified here in, whichever are
more stringent.
c) The accessories should provide Double Insulation so that a single point
failure of insulation will not result in the system tripping.
The ABC Accessories shall consist of the following:
Insulation Piercing
Connectors(IPC)
SPECIFICATION TS-CO-02
EEPCO
Anchoring Assembly(AA)
SPECIFICATION TS-CO-02
EEPCO
The IPCs shall be water proof and the water tightness shall be ensured by
appropriate elastomer materials and not by grease or paste alone.
Design of IPC should be such as to not cause damage to t h e insulation of
adjacent conductors due to vibration and relative movement during service.
The connector shall have a rigid removable end cap which can be slide fitted on
the main connector body on either right or left by the installer(depending on site
requirement)for sealing the cut end of the branch cable. Once the connector is
fitted, it should not be possible to remove the cap without removing the
connector.
7.1.3
Suspension Clamps
Suspension clamps for supporting on straight lines of aerial bundles conductor
cables and on angles up to 90.The main body of the suspension clamp shall be
manufactured from metal or a composite insulating material. Where the body of
the clamp is metal, a secondary insulation shall be provided between the cable and
metal component of the fitting. The design of the suspension clamp shall be such
that during the installation of the cable, the cable can be loosely supported
without damage to the insulation of the cable. The suspension clamps shall be
preferably of a type which can be installed without the use of tools. Where tools
shall be used, they are to be of a type and range normally used for overhead line
construction.
7.1.4
7.1.5
SPECIFICATION TS-CO-02
EEPCO
7.1.6
Tension Bracket-AA
The tension bracket shall be made out of a single piece of Aluminium Alloy(AA)
Suitable for attachment to a pole either by 16mm galvanized steel bolt(s) or
two stainless Steel straps of 20x0.7mm.
The tension bracket should be designed to ensure the Flexible rope can not slip
out at any angle.
7.1.7
Flexible Rope of AA
The Anchoring assembly shall be supplied with a stainless steel flexible rope to
connect the Tension Clamp to the Tension Bracket. The rope should have
sufficient flexibility to ease the tensional movement of the ABC System.
The Rope should be pre-fitted with compression type end fittings to secure the
tension clamp.
A wear resistant moveable saddle should be un-loosably fitted on the Rope to
prevent abrasion at the point of fitting into the tension bracket.
The Rope should have sufficient mechanical strength to with stand the
mechanical test for the complete assembly tests in this specification.
Wedge Type Tension Clamp of AA
Wedge type clamps shall be used for clamping the messenger without damaging
the insulation.
The clamp shall be capable of clamping an uncut messenger so that it can
continue with out break to the connecting point or next span.
The clamp shall be fully insulating type of mechanical and weather resisting
thermoplastic.
No bolts or loose parts are allowed as part of the clamping system.
No tools shall be needed for fitting the messenger in to the clamp.
After fitting the insulated messenger in the clamp, load T start will be held for 1
minute & then load increased to T final at rate between 50007,500N/mtr. In
each case there shall be no breakdown of any part of clamp and slippage of
messenger in relation to the clamp.
7.1.8
SPECIFICATION TS-CO-02
EEPCO
The clamps and movable links should be made of weather and UV resistant glass
fibre reinforced polymer.
Clamps should be fixed with pole by eyehook/bracket..Bracket should be made
of corrosion resistant aluminium alloy.
Ultimate tensile strength of the clamp should not be less than 15KN for 50/70
sq.mm insulated messenger wire 4.3kN for 25/35 sq.mm insulated messenger
wire.
Maximum allowable load of the clamp should not be less than 20kN for 50/70
sq.mm insulated messenger wire/15kN for 25/30 sq.mm insulated messenger
wire.
Suspension Assembly is used for supporting an ABC by installation on the
messengeratanintermediatepointofsupportsuchasapole.Itcanaccommodate
smallanglesofdeviationupto30O.
Each Suspension Assembly shall consist of,
Suspension Bracket of SA
The Suspension Bracket shall be made from single piece aluminium alloy suitable
for attachment to a pole by either.
The Suspension Bracket shall be provided with an upper bulge to prevent the
clamp from turning over on the Bracket for more than 45O from the horizontal or
to within less than 60mm from the pole/fixing structure.
The Suspension Bracket should be so designed to ensure that the articulated link
can not slip out of it.
7.1.10
7.1.11
Suspension Clamp of SA
Suspension Clamps are used for locking the messenger of the ABC bundle
without damaging the insulation or allowing the messenger to become
dismounted from the fitting.
SPECIFICATION TS-CO-02
EEPCO
Service clamp
The clamps should be designed to anchor insulated service lines(armoured or unarmoured) with 2/4 conductors.
The clamps should be made of weather and UV resistant polymer.
No losable part in the process of clamping arrangement.
The clamp should conform to the standard NFC 33042 or equivalent standard , if
any. No losable Breaking Load of the clamp should not be less than 3KN.
7.1.13
Transformer connection
In the case where AB cables are connected directly to the transformers the
connection to the transformer should be made with Pre-Insulated lugs for phase
and street lighting conductors and with an Aluminium Lug for neutral Messenger
The Barrel of the lug normally insulated with an Anti-UV black thermoplastic
tube sealed with a flexible ring. Die reference, size and strip length are to be
indicated on the plastic.
Sizes covered 16-70 & up to 95mm2Aluminium XLPE insulated cable. Reference
standard NFC 33021or equivalent standard, if any.
7.1.14
Junction sleeves
The sleeves should be Pre-insulated for phases, neutral messengers and street
lighting conductors.
Sleeve should be made of Aluminium, insulated with an Anti-UV black thermo
plastic tube hermetically sealed two ends with 2 flexible rings.
Die reference, size and strip length are indicated on the sleeve itself.
Sizes needed: To suit all the sizes being procured.
Reference standard: NFC33021orequivalent standard, if any.
Design as per furnished drawing.
7.1.15
Eye hooks
Eye hooks should be designed as to hold suspension clamps and Dead end
clamps and to be installed with the pole clamp.
Eye hooks should be made of forged Galvanised steel.
The clamps corrosion resistance should conform to the standards.
SPECIFICATION TS-CO-02
EEPCO
Bolts and nuts should be made of hot dip Galvanised steel according to VDE
0210 and VDE 0212.
Ultimate Tensile strength (UTs)of the clamp should be 20KN.
7.1.16
Dead-end clamps
The design of the clamp shall provide additional insulation between the insulated
conductor and all metallic pats of the clamp. The clamp portion of the dead-end
clamp shall, when assembled onto the appropriate cable size, sustain at least 95%
of the breaking load of the cable. The dead end clamps shall be preferably
designed to allow the cable to enter the fitting with a minimum separation of the
cable cores.
8.
8.1.1
Packing
The accessories shall be packed in individual sealed clear plastic bags. The bags
shall be adequately durable and should not be spoiled prior to the time of use of
the accessories. The bags shall be further packaged in wood or other similarly
strong containers in quantities of approximately 100 fittings of identical
description.
8.1.2
Marking
The marking on the packing shall be
9.
a)
Manufacturers Name
b)
c)
d)
e)
Voltage Grade
f)
SPECIFICATION TS-CO-02
EEPCO
10.
10.1
SPECIFICATION TS-CO-02
EEPCO
10.2
LPA-GECE
No
EEPCo
Item
General Requirements
Bid Offer
Requirement
16mm
conductor
Bid Offer
Requirement
25mm
conductor
35mm
conductor
Manufacturer
Manufacturer's Code
Type
Standard
IEC
60502
60502
60502
kV
0.6 / 1
0.6 / 1
0.6 / 1
kV
0.44
0.44
0.44
kV
kV
20
20
20
Cross section
mm
16
25
35
10
11
/km
1.91
1.2
0.868
12
mm
4.4
5.8
6.8
13
Inductive reactance
/km
14
mm
1.2
1.2
1.4
15
mm
6.8
8.2
9.6
16
kN
17
km
18
kg
19
kg
Bid Offer
Page 1
Date: 30/04/2013,
LPA-GECE
No
EEPCo
Item
General Requirements
Bid Offer
Requirement
Requirement
95mm
conductor
120mm
conductor
50mm
conductor
Manufacturer
Manufacturer's Code
Type
Standard
IEC
60502
60502
60502
kV
0.6 / 1
0.6 / 1
0.6 / 1
kV
0.44
0.44
0.44
kV
kV
20
20
20
Cross section
mm
50
95
120
10
11
/km
0.641
0.32
0.253
12
mm
9.6
12.7
13
Inductive reactance
/km
14
mm
1.4
1.4
1.4
15
mm
10.8
12.4
15.5
16
kN
17
km
18
kg
19
kg
Bid Offer
1.4
Page 2
Date: 30/04/2013,
LPA-GECE
No
EEPCo
Item
General Requirements
Bid Offer
Requirement
25mm
messenger
Bid Offer
Requirement
35mm
messenger
Bid Offer
Requirement
70mm
messenger
95mm
messenger
Manufacturer
Manufacturer's Code
Type
Standard
IEC
60502
60502
60502
60502
kV
0.6 / 1
0.6 / 1
0.6 / 1
0.6 / 1
kV
0.44
0.44
0.44
0.44
kV
kV
20
20
20
20
Cross section
mm
25
35
70
95
10
11
/km
1.38
0.986
0.493
0.363
12
mm
5.8
6.8
9.6
11.5
13
Inductive reactance
/km
1.4
1.4
1.4
14
mm
1.2
1.4
1.4
1.4
15
mm
8.2
9.6
12.4
14.3
16
kN
7.4
10.3
20.6
27.9
17
km
18
kg
19
kg
Bid Offer
Page 3
Date: 30/04/2013,
LPA-GECE
EEPCo
No
Item
(I)Suspension Clamp,ABC
Unit
1
2
3
4
Manufacturer
Country of origin
Type designation
Standard referred
5
6
Material
Material standard
mm
mm
9
10
11
Tensile strength
Thickness of zinc coating
Net weight per piece
kN
mm
kg
Requirement
Bid Offer
Wedge type
IEC
Aluminum alloy
IEC60826,
IEC5041
25 - 95
7-14
15
140
Manufacturer
Country of origin
Type designation
Standard referred
5
6
Material
Material standard
8
9
10
11
mm
mm
kN
mm
kg
Manufacturer
Country of origin
Type designation
Material
5
6
Material standard
Range of conductor cross-section
7
8
9
10
mm2
mm
kN
m
Kg
Aluminum Alloy
and insulating
material
BS
1650/2535
5
85
Page 4
Date: 30/04/2013,
LPA-GECE
EEPCo
No
Item
Unit
Requirement
Bid Offer
Manufacturer
Country of origin
Type designation
Material
5
6
Material standard
Range of conductor cross-section
7
8
9
10
mm
mm
kN
m
kg
Aluminum Alloy
and insulating
material
BS
1650/1650
5
43
Manufacturer
Country of origin
3
4
5
7
8
9
10
VI
1
2
3
4
5
6
N/mm
mm
mm
mm
mm
mm
mm
g. Washer thickness
mm
h. Length of thread
i. Thread length
mm
Galvanization
Thickness of galvanization
Net weight per piece
Standard packing size, sacks per piece
mm
kg
346
16
16
14
As per BS
standard
As per BS
standard
2
50
Hot-dip
galvanized
85
N/mm
mm
mm
400
16
Page 5
Date: 30/04/2013,
LPA-GECE
No
Item
c.
d.
e.
f.
7
8
9
10
1
2
3
4
5
6
Rod diameter
Thread nominal diameter
Thread minor diameter
Washer outside and inside diameter
mm
h. Length of thread
i. Thread length
mm
Manufacturer
Country of origin
Manufacturing capacity per month
Standard applied
Yield strength of hook
Complete dimension of hook
a. Length
b. Width
c. Rod diameter
d. Thread nominal diameter
e. Thread minor diameter
f. Washer outside and inside diameter
Bid Offer
As per BS
standard
As per BS
standard
2
50
Hot-dip
galvanized
85
N/mm
mm
mm
mm
mm
mm
mm
g. Washer thickness
mm
h. Length of thread
i. Thread length
mm
Galvanization
8
9
10
Thickness of galvanization
Net weight per piece
Standard packing size, sacks per piece
1
2
3
mm
kg
Requirement
16
14
VIII
Unit
mm
mm
mm
mm
g. Washer thickness
Galvanization
Thickness of galvanization
Net weight per piece
Standard packing size, sacks per piece
VII
EEPCo
mm
kg
352
16
16
14
As per BS
standard
As per BS
standard
2
50
Hot-dip
galvanized
85
Page 6
Date: 30/04/2013,
LPA-GECE
No
4
5
6
Item
Standard applied
Yield strength of hook
Complete dimension of hook
a. Length
b. Width
c. Rod diameter
d. Thread nominal diameter
e. Thread minor diameter
f. Washer outside and inside diameter
Unit
mm
mm
mm
mm
mm
mm
mm
h. Length of thread
i. Thread length
mm
Galvanization
8
9
10
Thickness of galvanization
Net weight per piece
Standard packing size, sacks per piece
IX
Requirement
Bid Offer
N/mm
g. Washer thickness
1
2
3
4
5
6
7
EEPCo
mm
kg
400
16
16
14
As per BS
standard
As per BS
standard
2
50
Hot-dip
galvanized
85
Type designation
Material
Dimension ( thickness and length)
Tensile strength
No of dead end tube per packet
Net weight per packet , g
Conductor crossection in mm2
X
mm
N/mm
gms
mm
PVC
3 and 30
> 40
50
50
Nylon tie
No
Item
1
2
3
4
5
6
7
8
Manufacturer
Country of origin
Type designation
Material
Dimension ( thickness, width, length)
Tensile strength
No of tie wire per packet
Net weight per packet ,
Unit
mm
N/mm
Specification
Requirement
Bid Offer
Nylon
1.7,10,400
100
100
gms
Page 7
Date: 30/04/2013,
EEPCO
SPECIFICATION
TS-CO-03
MV UG Cables and Accessories
EEPCO
Date
Brief Description
Rev 0
12 Dec 2012
Rev1
Feb 2013
Rev 2
Mar 2013
Rev 3
April 2013
Page: i , 27-Jun-13
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
MV UG CABLES AND ACCESSORIES
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
4.4
GENERAL
TYPE TESTS
ROUTINE AND ACCEPTANCE TESTS
AFTER INSTALLATION CABLE TESTS
2
2
2
3
5.
GENERAL REQUIREMENTS
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
CONSTRUCTION DETAILS
CONDUCTORS
CONDUCTOR SCREEN
INSULATION
CORE IDENTIFICATION
INSULATION SCREEN
WATER PROOFING
OUTER SHEATH
LAYING UP
INSTALLATION DATA
3
3
3
3
3
4
4
4
4
4
6.
CABLE CHARACTERISTICS
6.1
6.2
6.3
VOLTAGE CHARACTERISTICS
SIZES OF UG CABLES REQUIRED
CURRENT CARRYING CAPACITYCONDITIONS
4
5
5
7.
7.1
7.2
7.3
7.4
7.5
7.6
7.7
CABLE IDENTIFICATION
CABLE DRUMS AND PACKING
DRUM SIZES
CABLE DRUM LENGTH
DRUM MARKING
DRUM WARRANTEES
SHIPMENT
5
6
7
7
7
8
8
8.
9.
8
9
9.1
9.2
9.3
9.4
GENERAL
TERMINATION AND JOINTING MATERIALS
MV TERMINATION KITS FOR OVERHEAD LINES
MV TERMINATION KITS TO GROUND MOUNTED SWITCHGEAR
Page: ii , 27-Jun-13
9
9
10
10
EEPCO
9.5
9.6
10
10
10.
11
10.1
10.2
PACKING
MARKING
11
11
11.
SCHEDULES
12
11.1
11.2
12
13
SECTION 1- SCOPE
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
SCOPE
This specification covers the design, manufacture, testing and delivery of medium
voltage (33 and 15kV) , three-core and single core XLPE insulated underground
cable having stranded Copper or Aluminium conductors, copper wire screen and
extruded PVC or PE over sheath and accessories.
The cable for the 15kV system shall be a standard 24kV cable with accessories( at
Mean Sea Level - MSL). This will cater for installations at altitudes up to 3000M.
The cable for the 33kV system shall be 36kV maximum equipment voltage. All
the accessories for the 33kV cable must be for an altitude of 3000M. This means
that all accessories such as terminations shall be effectively for a 45 kV system.
2.
3.
REFERENCE STANDARDS
The cables and accessories supplied under this Section of the Contract shall
conform to the latest edition of the appropriate IEC standards or other
recognized international standards. In particular:
IEC60060
IEC60071
BS 7870-4.10
IEC60228
IEC60229
IEC60230
IEC60502
IEC60811
IEC60885
ASTM D2303
DIN/VDE0273
DIN 46391
3.1
CONFLICT
See specification TS-GN-02 General Contractual obligations.
Page: 1, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
4.
4.1
GENERAL
Please see Spec. TS-GN-02 General Contractual obligations.
4.2
TYPE TESTS
The following type tests as per the relevant standard shall be conducted on cables
of identical design to prove that one cable of each class satisfies all the design
requirements set out in this specification.
4.2.1
For Cable
1) Partial discharge test,
2) Bending test, plus partial discharge test,
3) Dielectric power factor as function of voltage and capacitance measurement, and
as a function of temperature,
4) Heating cycle test plus partial discharge test,
5) Impulse withstand test, followed by power frequency voltage test,
6) High voltage ac test,
7) Non-electrical tests as stated in IEC
The following additional type tests shall be carried out.
8) Extruded Insulation Shielding Test per AEIC CS-5.
9) Insulation Shield Stripping Test per AEIC CS-5.
4.2.2
For Accessories
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
4.3
Non-tracking tests.
Page: 2, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
4.4
Check for compliance with specifications herein and with the scheduled
quantities.
High-voltage test
5.
GENERAL REQUIREMENTS
Three-core 24kV, 36kV, single core 24kV copper conductor, Three core 24kV
aluminium , cross-linked polyethylene (XLPE) insulated, screened, PVC sheathed
underground cable shall be supplied for use in 15kV and 33kV distribution
circuits.
5.1
CONSTRUCTION DETAILS
The cable shall comprise three core circular stranded copper conductors, each
with extruded semi-conducting shielding, cross-linked polyethylene insulation
semi-conductor shielding, hygroscopic powder waterproofing and copper tape
screen. The three cores shall be laid up to form a circular cross-section using PVC
fillers and bound overall with polyester tapes. The cables shall be bedded with
extruded PVC, and sheathed overall with black PVC.
5.2
CONDUCTORS
The conductor shall be a circular compacted conductor of stranded plain annealed
copper or aluminium of cross-section as required for cable class 2 conductors in
accordance with IEC 60228.
5.3
CONDUCTOR SCREEN
The conductor screening shall be proposed by the manufacturer. The screen may
consist of a layer of at least 0.5mm thick extruded semi-conductive compound
bonded to the XLPE insulation.
5.4
INSULATION
The insulation shall consist of high quality extruded cross-linked polyethylene
(XLPE) of suitable thickness for a voltage rating of 20/36 kV (Uo/U) for 33kV
system and 24kV for 15 kV system at 50 Hz.
5.5
CORE IDENTIFICATION
a)
The cores shall be identified by the number 1, 2 and 3 printed on the outer
extruded semi-conductor.
The insulation screen shall be a semi-conductive polymer layer. This layer is
covered by a bedding of conductive swelling tape to ensure longitudinal water
tightness.
Page: 3, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
b)
5.6
The earthing screen shall be copper wires with an open pattern counter wound
copper strip.
INSULATION SCREEN
The insulation screen shall be a semi conductive polymer layer.
5.7
WATER PROOFING
A layer shall be included to prevent longitudinal and transversal water
ingresstransversally and longitudinally watertight design. With this option, the space
between the earthing screen wires is filled with a semi-conductive rubber based
filling sheath. An aluminium foil and a PE sheath are sandwiched on top of the
filling sheath, with a copper wire for equi-potential bonding to prevent any
potential difference between copper screen and aluminium foil.
5.8
OUTER SHEATH
The over sheath shall consist of an extruded layer of black PVC or PE complying
with the requirements of compound ST2 type specified in IEC 502. The over
sheath shall be spark tested in accordance with IEC 229. The outer sheath shall be
3.5 mm thick black extruded PVC, containing a termite repellent additive.
5.9
LAYING UP
The screened conductors of the three cores shall be laid up together with PVC
fillers to form a circular cross-section and bound overall with two polyester tapes.
5.10
INSTALLATION DATA
Core screen will be earthed at both ends and cables will be directly buried
underground. Depth of laying is 0.9m for 15 kV cables and 1.1m for 33 kV cables
Short lengths will be installed in air, pipes and ducts.
In addition the Bidder shall advise rating/derating factors for variations in the
above conditions as well for multiple circuits.
6.
CABLE CHARACTERISTICS
6.1
VOLTAGE CHARACTERISTICS
The cable shall fulfil at least the following conditions:
33kV
15kV
33 kV
15 kV
36 kV
24 kV
250kV
125 kV
95kV
50kV
System frequency
50 Hz
50 Hz
Page: 4, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
6.2
33kV
15kV
6.3
7.
30 C
90 C
1.2 C m/W
0.8 m
45oC
-5oC
25 oC
10 oC
7.1
CABLE IDENTIFICATION
Cable identification shall include embossing of the PVC over sheath with the
following details:a)
EEPCO
b)
Manufacturers name
c)
Cable size
d)
Rated Voltage
e)
Year of Manufacture
The letters and figures shall be raised and shall consist of upright block characters.
There should be at least one such marking set at every 2m to suit manufacturing
process.
Page: 5, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
7.1.2
7.2
b)
c)
Construction
Drum flanges shall be 2-layer construction with minimum 60 mm thickness. Each
layer shall be nailed and fixed with grip nails at approximately 90 degrees. Nails
shall be driven from the inside face of the flange, punched and then clenched on
the outer face. There shall not be less than 2 nails per board in each circle.
d)
Spindle holes
Reels shall be constructed so that they must be supported either on an axle
through the reel flange. A round spindle hole of minimum diameter 120mm is
required at the centre of the wooden drums. Spindle hole/supports shall be
reinforced with a suitable steel flange.
e)
Cable ends
Page: 6, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
The inner as well as outer end of cable shall be brought out on the drum flange
and shall be clamped in such a manner to make the cable length marking easily
visible.
Each end of cable shall be durably sealed at both ends with hot melted paste and
provided with shrinkable end caps to prevent ingress of moisture.
f)
g)
Lugging
The cables shall be lagged or covered with suitable material to provide physical
protection during transit and during storage and handling operations.
Preferable mode of lugging shall be by wooden lagging on the circumference with
a thickness of at least 40 mm.
7.3
DRUM SIZES
The drums shall have the following dimensions:
Max. Diameter:
2280mm;
Max. Width:
1140mm;
7.4
7.5
DRUM MARKING
a)
Page: 7, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
The direction for rolling as indicated by an arrow together with the words "Roll
this way" shall be marked on each flange.
Each drum shall be marked to indicate weather proofing.
b)
Drum Labels/Marking
The drum shall have metallic or plastic plates /labels or shall have the data
indelibly branded on the cable drum for shipping purpose. In any case all
branding shall be indeliblymarked to indicate the following:
1) Name of Purchaser EEPCO
2) Contract Number,
3) Manufacturers name,
4) Trade mark/model if any,
5) Conductor type, name and specification
6) Conductor size and stranding,
7) Exact length of conductor (in meters) contained in the drum,
8) Gross weight (kgs) of the loaded drum,
9) Net weight (kgs) of the conductor,
10) Drum Serial Number,
Each case/consignment shall contain a fully detailed packing list covering the
above details in a sealed waterproof envelope.
Three copies of each packing list shall be sent to the Employer prior to dispatch.
7.6
DRUM WARRANTEES
The bidder/contractor would implicitly guarantee the soundness of the cable
drums for three (3) years.
Should the drums fail within this period, due to poor quality of materials and
workmanship, the contractor shall be responsible for re-drumming the
cable/conductor to new drums provided free of charge by the contractor.
Damage due to careless handling and storage by the client shall not be covered
under this guarantee.
Damage due to careless handling and storage by the contractor or his agents shall
be fully covered under this guarantee.
7.7
SHIPMENT
The Contractor shall be responsible for CIF / CIP (or as specified in the tender)
delivery of all goods to the point of delivery specified in the tender inquiry.
8.
Page: 8, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
The contractor shall follow the approved Quality Assurance Plan. If desired by
the purchaser, he shall give access to all the documents and materials to satisfy the
purchaser that the Quality Assurance Plan is being properly followed.
9.
9.1
GENERAL
All high voltage terminations and joints shall be cold-applied elastomeric type.
They shall be factory engineered kits containing all the necessary components to
reinstate the cable insulation, metallic shielding of each core, together with the
reinstatement of the sheath, equivalent to the cable being terminated.
The Bidder shall submit at bidding and supply for the contract complete
illustrated instructions describing the methods for terminating or jointing the
cable.
Each terminating or jointing kit shall be in a separate package and a list of
materials indicating quantities and weights in the kit, and an illustrated instruction
sheet shall be included in the package. The Kits shall contain sufficient cleaning
solvents and cleaning cloths for the proper making of the joint or termination.
Voltage stress relief shall be provided and this shall be inherent in the heat
recoverable polymeric material.
The termination or joint shall be capable of tolerating any variances in the
manufactured dimensions of the cable such as oval, out of round, sectored or
oversize cable cores. The termination shall be capable of immediate energisation
once all components have been installed. The terminating or jointing materials
shall not be subject to storage limitations such as controlled temperature or
humidity restrictions, nor have shelf life limitations.
9.2
Page: 9, 27-Jun-13
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
9.3
Compression lugs
b)
Sealant tape
c)
d)
e)
f)
g)
h)
i)
Jointing instructions
All other items necessary to complete the kit
9.4
9.5
9.6
TOOLS
The following tools of well-proven design and performance shall be supplied for
cable laying, terminating and jointing.
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
Foot operated hydraulic 12 tone compressor complete with dies to fit all
compression terminals and connectors as supplied with the terminating kits. One
tool shall be suitable for all die sizes, and shall be complete with:
a)
Recommended kit of spares, each kit to include at least three sets of all seals and
other items required during normal servicing.
b)
c)
d)
e)
f)
Strong metal box for protection of hydraulic compressor unit when not in use.
g)
h)
Shear type cable cutters for cutting maximum cable size provided.
i)
Pencilling tool for XLPE insulation for shaping all cables specified.
j)
Cable pulling sock -flexible steel wire woven, completed with swivel, for pulling
all cables specified.
k)
Cable rollers in-line suitable for cables with maximum diameter of 3x300 mm.
10.
10.1
PACKING
In addition to the clause on packing etc. given in the Spec. No. TS-GN-02, the
following shall be given special attention.
The cable termination kits and jointing kits shall be packed in individual sealed
clear plastic bags. The bags shall be adequately durable and should not be spoiled
prior to the time of use of the accessories. The bags shall be further packaged in
cardboard or similar containers in reasonable quantities.
10.2
MARKING
The marking on the packing shall be,
a)Manufacturers Name,
b)Trade Mark, if any,
c)ItemNumber or identification number,
d)Size of the item,
e)Voltage Grade,
f)Gross mass of the packing.
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
11.
SCHEDULES
Please see separate technical schedule, TS-CO-03 S for MV cables and
accessories.
11.1
SPECIFICATION MV UG
CABLES AND ACCESSORIES
EEPCO
11.2
LPA-GECE
EEPCo
No
Item
Unit
I. General
1
2
3
Manufacturer
Country of origin
Type designation
Standard
6
7
8
8.1
8.2
8.3
9
Number of cores
Normal cross sectional area of conductor,
Conductor details
material
design
overall diameter,
Conductor screen
9.1
Material
8.2
11
thickness, mm
Maximum dielectric stress at conductor
screen (assumed smooth)
Insulation
11.2
Material
10
11.2
12
12.1
12.2
Requireme
nt
3cx95mm
Bid Offer
Requireme
nt
3cx185mm
UG
IEC 60502/
BS662
UG
IEC 60502/
BS662
kV
36
mm
Bid Offer
Requireme
nt
3cx300mm
Bid Offer
Requireme
nt
1cx300mm
UG
UG
BS 7870
BS 7870
36
36
36
Three
95
Three
185
Three
300
One
300
Copper
Copper
Copper
Copper
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Copper wire
Copper wire
Copper wire
Copper wire
Bid Offer
mm
kV/cm
mm
mm
Page 1
Date: 06/05/2013,
LPA-GECE
No
Item
Unit
I. General
13
14
15
16
17
18
19
20
21
22
23
24
24.1
24.2
24.3
EEPCo
Requireme
nt
3cx95mm
Bid Offer
Requireme
nt
3cx185mm
Bid Offer
Requireme
nt
3cx300mm
Bid Offer
Requireme
nt
1cx300mm
ohm/m
193
99.1
60.1
60.1
ohm/m
248
128
80
80
13.3
26.6
43.8
43.8
Bid Offer
ohm/m
ohm/m
nF/km
mA/m
A
kA
kA
mm
m
m
m
Page 2
Date: 06/05/2013,
LPA-GECE
EEPCo
No
Item
I. General
1
2
3
4
Unit Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requiremen Bid Offer
t
three core
three core
three core
single core
three core
Manufacturer
Country of origin
Type designation
Standard
UG
IEC 60502/
BS662
Voltage between phases of three phase
24
Number of cores
Three
Normal cross sectional area of conductor, mm 95
UG
IEC 60502/
BS662
24
Three
185
UG
IEC 60502/
BS662
24
Three
300
UG
IEC 60502/
BS662
24
single core
300
UG
IEC 60502/
BS662
24
Three
240
8
8.1
Conductor details
material
Copper
Copper
Copper
Copper
Aluminium
8.2
8.3
9
9.1
design
overall diameter,
Conductor screen
material
IEC 228
IEC 228
IEC 228
IEC 228
IEC 228
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
Extruded
XLPE semi
conductive
9.2
10
thickness,
Maximum dielectric stress at conductor
screen (assumed smooth)
Insulation
material
kV/cm
kV/cm
kV/cm
kV/cm
kV/cm
Extruded
mm XLPE semi
Extruded
XLPE semi
Extruded
XLPE semi
Extruded
XLPE semi
Extruded
XLPE semi
Copper wire
mm
ohm/k 0.193
m
Copper wire
Copper wire
Copper wire
Copper wire
0.0991
0.0601
0.0601
0.125
ohm/k 0.247
m
0.128
0.08
0.08
0.16
5
6
7
11
11.1
11.2
12
12.1
12.2
13
14
15
16
mm
mm
ohm/k
ohm/k
LPA-GECE
No
17
18
19
20
Item
Maximum electric capacitance per core
of cable
Maximum charging current per
conductor of cable at nominal voltage,
24.4
24.5
in ducts
21
22
23
24
24.1
24.2
24.3
24.6
EEPCo
Unit Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requiremen Bid Offer
t
F
mA/k
m
A
kA
kA
No smaller
than 12 times
No smaller
than 12 times
No smaller
than 12 times
No smaller
than 12 times
No smaller
than 12 times
No smaller
than 12 time
of the outer
sheath
No smaller
No smaller
than 12 time
of the outer
sheath
No smaller
No smaller
than 12 time
of the outer
sheath
No smaller
No smaller
than 12 time
of the outer
sheath
No smaller
No smaller
than 12 time
of the outer
sheath
No smaller
than 12 time
of the outer
sheath
No smaller
than 12 time
of the outer
sheath
No smaller
than 12 time
of the outer
sheath
No smaller
than 12 time
of the outer
sheath
No smaller
than 12 time
of the outer
sheath
No smaller
than 12 time
of the outer
sheath
than 12 time
of the outer
sheath
than 12 time
of the outer
sheath
than 12 time
of the outer
sheath
than 12 time
of the outer
sheath
m
m
m
m
LPA-GECE
EEPCo
No
1
2
3
4
5
6
7
8
Item
Manufacturer
Country of origin
Type designation
Cross-section of cable,
Power impulse withstand voltage,
Lightning impulse withstand voltage
Material of the body
Net weight of termination kit,
TS-CO-03 S
Unit
Requirement
mm
kV
g
No
1
2
3
4
5
6
7
Bid Offer
TS-CO-03 S
Item
Manufacturer
Country of origin
Type designation
Power frequency withstand Voltage level,
Lightning impulse withstand Voltage level,
Materials of the body
Maximum voltage stress,
Unit
Requirement
Bid Offer
Requirement
Bid Offer
kV
kV
kV/mm
No
1
2
3
4
5
6
7
8
9
10
Item
Manufacturer
Country of origin
Type designation
Power frequency withstand voltage
Lightning impulse withstand voltage
Tail length, mm
Material of stress relief cone
Material of the body
Maximum voltage stress
Net weight of termination kit
Unit
kV
kV
kV/mm
kg
No
1
2
Item
TS-CO-03 S
Unit
Requirement
Bid Offer
Manufacturer
Country of origin
Page 5
Date: 06/05/2013,
LPA-GECE
EEPCo
3
4
5
6
7
8
Type designation
Power frequency withstand voltage
Lightning impulse withstand voltage
Tail length, mm
Material of stress relief cone
Material of the body
9
10
kV
kV
kV/mm
kg
No
1
2
3
4
5
6
Item
Manufacturer
Country of origin
Type designation
Voltage level,
Material standard
Length of Tape per reel,
TS-CO-03 S
Unit
Requirement
kV
m
No
1
2
3
4
5
6
7
8
Item
Manufacturer
Country of origin
Type designation
Cross-section of cable,
Power impulse withstand voltage,
Lightning impulse withstand voltage
Material of the body
Net weight of termination kit,
Bid Offer
TS-CO-03 S
Unit
Requirement
Bid Offer
mm2
kV
kV
g
Page 6
Date: 06/05/2013,
EEPCO
SPECIFICATION
TS-CO-04
Rev-2-April 2013
SPECIFICATION TS-CO-04
EEPCO
Date
Brief Description
Rev 0
25/1/2011
First Issue
Rev1
Dec2012
Rev2
April 2013
Rev-2-April 2013
Page: 1 , 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
SPECIFICATION CONTENTS
Description
Page No
SPECIFICATION CONTENTS
LV POWER CABLES (XLPE INSULATED)
1.
SCOPE
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
3.
REFERENCE STANDARDS
2
1
1
1
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
4.4
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
AFTER INSTALLATION CABLE TESTS
2
2
2
2
5.
DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
5.7
GENERAL
CONDUCTORS
RATING
INSULATION
ARMOURING
OVERSHEATH
CORE IDENTIFICATION
2
2
2
3
3
3
4
6.
6.1
6.2
6.3
5
5
6
7.
7.1
7.2
7.3
7.4
7.5
7.6
7.7
CABLE IDENTIFICATION
CABLE DRUMS AND PACKING
DRUM SIZES
CABLE DRUM LENGTH
DRUM MARKING
DRUM WARRANTEES
SHIPMENT
6
7
8
8
9
9
10
8.
SCHEDULES
10
8.1
8.2
8.3
10
10
11
Rev-2-April 2013
Page: 2 , 11-Apr-13
SECTION 1- SCOPE
SPECIFICATION TS-CO-04
EEPCO
SCOPE
(i)
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
IEC60028
IEC60071
Insulation co-ordination
IEC 60502
IEC60228
IEC60229
IEC60230
IEC60304
IEC60446
IEC60507
IEC60724
IEC60811
IEC60885
DIN/VDE0273
CONFLICT:
See spec TS-GN-02
4.
Rev-2-April 2013
Page: 1, 11-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-CO-04
EEPCO
4.1
TYPE TESTS
When such tests are specified Shield Stripping Test per IEC or AEIC CS-5.
4.2
ROUTINE TESTS
The routine and acceptance tests shall be performed at the manufacturer's works
in accordance with the relevant IEC/ISO standards supplemented by the specific
requirements indicated below and shall be free of charge to the Purchaser..
a)
The tests will be divided into the following categories and conducted as per the
relevant standard.
b)
Check for compliance with specifications herein and with the schedule
c)
d)
High-voltage test
e)
Conductor examination
f)
Check of dimensions
4.3
4.4
ACCEPTANCE TESTS
a)
Annealing test
b)
Conductor resistance
c)
d)
e)
f)
5.
DESIGN
5.1
GENERAL
The cable shall be constructed in accordance with IEC 60227 and IEC 60228.
The outer sheath shall be ultra violet stable black PVC. Cable shall be suitable for
direct burial in soil of temperature 25oC and soil thermal resistivity of 1.5
Km/W.LV cables will be buried at a depth of 600mm.
The cable design offered shall meet the following requirements.
5.2
CONDUCTORS
The copper conductors shall conform to IEC 60228.
5.3
RATING
Rev-2-April 2013
Page: 2, 11-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-CO-04
EEPCO
5.4
Size of
Cable
Cont
.
Curr
ent
ratin
g(A)
Curre
nt
rating
in
emerg
ency
use(A)
S.C.
Rating
(kA)
3x35/
16
180
195
3x50/
25
215
245
3x70/
35
265
300
10
3x95/
50
315
350
16
3x120
/70
365
450
20
3x185
/95
405
530
25
3x240
/120
465
540
40
3x300
/150
610
645
50
INSULATION
The insulation shall be in accordance with IEC standards and shall be
thermosetting cross linked extra-clean polyethylene compound or an approved
equivalent which is rated for 90oC continuous operation and which is applied
directly over and in intimate contact with the conductor shield.
5.5
ARMOURING
Armouring, where specified, shall be applied helically forming a layer of
galvanised steel wire over an inner covering and shall comply with the
requirements of IEC 60502.
5.6
OVERSHEATH
PVC over sheaths shall be of a heat, moisture, and sunlight resistant material that
is fire retardant and low acid emitting when subjected to the temperature limits of
the underlying insulation. Solutions to which the over sheath is resistant shall
include petrol, oil, acids and alkalis. The over sheath shall contain a termite, insect
and rodent repellent of a permanent nature.
Rev-2-April 2013
Page: 3, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
The over sheath shall be of a single extrusion of polyvinyl chloride (PVC) applied
over the armour wire and shall be in accordance with IEC 60502-1. In addition
the PVC over sheath shall be coloured black. The outer PVC sheath shall be
termite resistant.
5.7
CORE IDENTIFICATION
Individual cores shall be colour coded as per Table 1
5.7.1
Cable Construction
LV cables shall be constructed and delivered as summarised in Table 1.
No. of
cores
6.
Material/Shape
Insulation
colour
Armour
Conductor
size mm
3x35/16
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3x50/25
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3x70/35
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3x95/50
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3x120/70
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3x185/95
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3x240/120
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
3 x300/150
Copper / Stranded
Circular or shaped
Black, Blue,
Red & Yellow
Steel
Wire
Rev-2-April 2013
Page: 4, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
6.1
6.2
MATERIAL
6.2.1
CONDUCTOR
The conductor shall be composed of plain annealed copper wires made out of
high conductivity copper rods. The rated voltage shall be 1kV. The other
parameters to be specified are mentioned in the technical schedule.
6.2.2
FORM:
The conductors shall be circular and stranded. They shall be clean, reasonably
uniform in size and shape, smooth and free from all harmful defects.
6.2.3
JOINTS
Joints shall be permitted in the individual wires of which the conductor is formed
but no joint shall be within 300mm of any other joint within the same layer. The
joints shall be made by resistance butt welding, fusion welding, cold pressure
welding, electric welding, gas welding, brazing or silver soldering.
6.2.4
Classification
Class-2 for stranded circular non-compacted cables used for fixed installation.
6.2.5
6.2.6
INSULATION
The insulation shall be in accordance with IEC or AEIC Section C. In addition
the insulation shall be an extrusion of Union Carbide HFDA 4202 thermo setting
cross-linked extra-clean polyethylene compound or an approved equivalent which
is rated for 90oC continuous operation and which is applied directly over and in
intimate contact with the conductor shield.
6.2.7
APPLICATION
The insulation shall be so applied that it fits closely on the conductor and it shall
be possible to remove it without damage to the conductor.
6.2.8
CORE IDENTIFICATION
See Clause 5.7, above.
6.2.9
ARRANGEMENT OF MARKING
See Clause 5.8, above.
6.2.10
LAYING UP OF CORES
In the twin and multi-core cables, the cores shall be laid up together with a
suitable lay; the outermost layer shall have right hand lay and the successive layers
Rev-2-April 2013
Page: 5, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
shall be laid with opposite lay, where necessary. The interstices shall be filled with
non-hygroscopic material.
The following lay-up of core shall be applicable,
No. of cores
Lay-up
6.3
OUTER SHEATH
6.3.1
MATERIALS
For cables with general purpose insulation, the outer sheath shall be of Type ST-1
PVC compound as recommended for general purpose sheaths intended for use in
cables operating at a maximum rated conductor temperature 70 C. Composition
of the outer sheath shall be as above.
6.3.2
CONSTRUCTION
This outer sheath shall be applied by extrusion over the inner sheath as applicable
for un-armoured twin and multi-core cables. It shall be so applied that it fits
closely over inner sheath and it shall also be possible to remove it without
damaging the inner sheath. The colour of the outer sheath shall be black.
6.3.3
THICKNESS
The average and minimum thickness of the PVC outer sheath shall be not less
than the values specified hereunder:
Calculated diameter under the Thickness of outer sheath for unouter sheath
armoured cables.
Over (mm)
7.
Minimum (mm)
---
15
1.8
1.24
15
25
2.0
1.40
7.1
CABLE IDENTIFICATION
Cable identification shall includes embossing of the PVC over sheath with the
following details:a)
EEPCO
b)
Manufacturers name
c)
Cable size
d)
Rated Voltage
e)
Year of Manufacturer
Rev-2-April 2013
Page: 6, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
The letters and figures shall be raised and shall consist of upright block characters.
There should be at least one such marking set at every 2m to suit manufacturing
process.
7.1.2
7.2
b)
c)
Construction
Drum flanges shall be 2-layer construction with minimum 60 mm thickness. Each
layer shall be nailed and fixed with grip nails at approximately 90 degrees. Nails
shall be driven from the inside face of the flange, punched and then clenched on
the outer face. There shall not be less than 2 nails per board in each circle.
d)
Spindle holes
Reels shall be constructed so that they must be supported either on an axle
through the reel flange. A round spindle hole of minimum diameter 120mm is
Rev-2-April 2013
Page: 7, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
Cable ends
The inner as well as outer end of cable shall be brought out on the drum flange
and shall be clamped in such a manner to make the cable length marking easily
visible.
Each end of cable shall be durably sealed at both ends with hot melted paste and
provided with shrinkable end caps to prevent ingress of moisture.
f)
g)
7.3
Lugging
DRUM SIZES
The drums shall have the following dimensions:
Max.
Diameter:
Max.
Width:
2280
mm;
1140
mm;
Rev-2-April 2013
Page: 8, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
Bidder shall also indicate the maximum single length, over and above the standard
length, he can manufacture in the guaranteed technical particulars of offer. This
may be required for special stretches like river crossing etc. The Purchaser
reserves the right to place orders for the above lengths on the same terms and
conditions applicable for the standard lengths during the validity of the Contract.
7.5
DRUM MARKING
a)
b)
Drum Labels/Marking
The drum shall have metallic or plastic plates /labels or shall have the data
indelibly branded on the cable drum for shipping purpose. In any case all
branding shall be indelibly marked to indicate the following:
1) Name of Purchaser EEPCO
2) Contract Number,
3) Manufacturers name,
4) Trade mark/model if any,
5) Conductor type, name and specification
6) Conductor size and stranding,
7) Exact length of conductor (in meters) contained in the drum,
8) Gross weight (kgs) of the loaded drum,
9) Net weight (kgs) of the conductor,
10) Drum Serial Number,
Each case/consignment shall contain a fully detailed packing list covering the
above details in a sealed waterproof envelope.
Three copies of each packing list shall be sent to the Employer prior to dispatch.
7.6
DRUM WARRANTEES
The bidder/contractor would implicitly guarantee the soundness of the cable
drums for three (3) years.
Should the drums fail within this period, due to poor quality of materials and
workmanship, the contractor shall be responsible for re-drumming the
cable/conductor to new drums provided free of charge by the contractor.
Damage due to careless handling and storage by the client shall not be covered
under this guarantee.
Damage due to careless handling and storage by the contractor or his agents shall
be fully covered under this guarantee.
Rev-2-April 2013
Page: 9, 11-Apr-13
SPECIFICATION TS-CO-04
EEPCO
7.7
SHIPMENT
The Contractor shall be responsible for CIF / CIP (or as specified in the tender)
delivery of all goods to the point of delivery specified in the tender inquiry.
8.
9.
SCHEDULES
9.1
9.2
Rev-2-April 2013
SECTION 9- SCHEDULES
SPECIFICATION TS-CO-04
EEPCO
9.3
Rev-2-April 2013
LPA-GECE
EEPCo
No
Item
Unit
Requiremen
t
Bid Offer
Requiremen
t
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard
5 Cross-section of conductor
IEC 60502
mm2
3x35/16
3x50/25
Copper
Copper
0.6/1
4
XLPE
PVC
90
0.6/1
4
XLPE
PVC
90
12 Permissible conductor
temperature rise of insulation for
laying in the earth 20
70
70
13 Permissible conductor
temperature rise of insulation for
laying in the air,30
60
60
14 Maximum resistance of
conductor at 20C
15 Inductive reactance at 50HZ for
4 core
ohm/kM
0.524
0.387
ohm/kM
0.081
0.076
180
215
195
245
kA
6 Material of conductor
7
8
9
10
11
kV
m
kg
kg
m
Page 1
Date: 11/4/2013,
LPA-GECE
EEPCo
No
Item
Unit
Requiremen
t
Bid Offer
Requiremen
t
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard IEC60502
Yes
Yes
3x70/35
3x95/50
Copper
Copper
0.6/1
4
XLPE
PVC
90
0.6/1
4
XLPE
PVC
90
12 Permissible conductor
temperature rise of insulation for
laying in the earth,20
70
70
13 Permissible conductor
temperature rise of insulation for
laying in the air,30
60
60
14 Maximum resistance of
conductor at 20 C
15 Inductive reactance, ohm/kM at
50HZ for 4 core
Ohm/kM
0.268
0.193
0.075
0.073
265
315
300
350
kA
10
16
5 Cross-section of conductor
mm2
6 Material of conductor
7
8
9
10
11
kV
Ohm/kM
m
kg
kg
m
Page 2
Date: 11/4/2013,
LPA-GECE
EEPCo
No
Item
Unit
Requiremen
t
Bid Offer
Requiremen
t
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard
5 Cross-section of conductor
IEC 60502
mm2
3x120/70
3x185/95
Copper
Copper
0.6/1
4
XLPE
PVC
90
0.6/1
4
XLPE
PVC
90
70
70
60
60
0.153
0.124
0.073
0.072
6 Material of conductor
7
8
9
10
11
12 Permissible conductor
temperature rise of insulation for
laying in the earth,20 o
13 Permissible conductor
temperature rise of insulation for
laying in the air,30 o
14 Maximum resistance of
conductor at 20C
15 Inductive reactance, ohm/Km at
50HZ for 4 core
kV
Ohm/kM
Ohm/kM
365
405
450
530
kA
20
25
kg
m
Page 3
Date: 11/4/2013,
LPA-GECE
EEPCo
No
Item
Unit
Requiremen
t
Bid Offer
Requiremen
t
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard
5 Cross-section of conductor
IEC 60502
IEC 60502
3x240/120
3x300/150
Copper
Copper
0.6/1
4
XLPE
PVC
90
0.6/1
4
XLPE
PVC
90
70
70
60
60
0.0991
0.0601
0.072
0.072
mm2
6 Material of conductor
7
8
9
10
11
12 Permissible conductor
temperature rise of insulation for
laying in the earth,20 o
13 Permissible conductor
temperature rise of insulation for
laying in the air,30 oC
14 Maximum resistance of
conductor at 200C
15 Inductive reactance, ohm/Km at
50HZ for 4 core
kV
Ohm/kM
Ohm/kM
465
540
610
645
kA
40
50
m
kg
kg
m
Page 4
Date: 11/4/2013,
LPA-GECE
EEPCo
Technical Schedule for LV Cables(XLPE control cable), 2x2,.5mm, 2x4mm and 2x6mm2
No
Item
Unit
Requiremen
t
2x2.5
Bid Offer
Requireme
nt
2x4
Bid Offer
Requireme
nt
2x6
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard
5 Cross-section of conductor
6
7
8
9
10
Material of conductor
Rated voltage Uo/U
Number of cores
Insulation material of conductor
Sheath material
mm2
kV
IEC 60502
IEC 60502
IEC 60502
2x2.5
2x4
2x6
Copper
0.6/1
2
XLPE
PVC
Copper
0.6/1
2
XLPE
PVC
Copper
0.6/1
2
XLPE
PVC
11 Maximum temperature of
conductor in continuous use
90
90
90
12 Permissible conductor
temperature rise of insulation for
laying in the earth,20
70
70
70
60
60
60
7.4
4.61
3.08
13 Permissible conductor
30 C
temperature rise of insulation for
laying in the
air,30 Cof
14 Maximum
resistance
ohm/kM
conductor at 20 C
15 Inductive reactance at 50HZ for
4 core
ohm/kM
37
50
63
37
50
63
kA
0.36
0.57
0.86
mm
10.1
10.9
11.9
2000
2000
2000
kg
m
Page 5
Date: 11/4/2013,
LPA-GECE
EEPCo
No
Item
Unit
Requirem
ent
2x10
Bid Offer
Requireme
nt
4 x2.5
Bid Offer
Requireme
nt
4x4
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard
IEC 60502
IEC 60502
IEC 60502
2x10
Copper
0.6/1
2
XLPE
4 x2.5
Copper
0.6/1
4
XLPE
4x4
Copper
0.6/1
4
XLPE
oC
PVC
90
PVC
90
PVC
90
70
70
70
60
60
60
1.83
7.41
4.61
ohm/K
m
A
82
35
45
82
35
45
kA
1.43
0.36
0.57
19 Outer diameter mm
20 Standard delivery length per
drum, m (+/-5m)
mm
m
13.9
2000
11.9
2000
13.1
2000
kg
5
6
7
8
9
Cross-section of conductor
Material of conductor
Rated voltage Uo/U, kV
Number of cores
Insulation material of conductor
10 Sheath material
11 Maximum temperature of
conductor in continuous use
12 Permissible conductor
temperature rise of insulation for
laying in the earth,20
13 Permissible conductor
temperature rise of insulation for
laying in the air,30
14 Maximum resistance of
conductor at 20C
15 Inductive reactance, ohm/Km at
50HZ for 4 core
16 Continuous current rating in soil
in given service condition
17 Current rating in emergency use
in given service conditions
18 Short circuit rating in given
service condition
mm2
kV
ohm/k
m
Page 6
Date: 11/4/2013,
LPA-GECE
EEPCo
No
Item
Unit
c
Requirem
ent
4x6
Bid Offer
Requireme
nt
4x10
Bid Offer
Requireme
nt
4x16
Bid Offer
1 Manufacturer
2 Country of Origin
3 Type designation
4 Standard
IEC 60502
IEC 60502
IEC 60502
4x6
Copper
0.6/1
4
XLPE
4x10
Copper
0.6/1
4
XLPE
4x16
Copper
0.6/1
4
XLPE
PVC
90
PVC
90
PVC
90
20C
70
70
70
30C
60
60
60
3.08
1.83
1.15
ohm/K
m
A
57
75
97
57
75
97
kA
0.86
1.43
2.23
19 Outer diameter mm
20 Standard delivery length per
drum, m (+/-5m)
mm
m
14.6
2000
16
2000
18.5
2000
kg
5
6
7
8
9
Cross-section of conductor,
Material of conductor
Rated voltage Uo/U,
Number of cores
Insulation material of conductor
10 Sheath material
11 Maximum temperature of
conductor in continuous use,
12 Permissible conductor
temperature rise of insulation for
laying in the earth
13 Permissible conductor
temperature rise of insulation for
laying in the air,
14 Maximum resistance of
conductor at 20C,
15 Inductive reactance, ohm/Km at
50HZ for 4 core
16 Continuous current rating in soil
in given service condition
17 Current rating in emergency use
in given service conditions
18 Short circuit rating in given
service condition
mm2
kV
ohm/K
m
Page 7
Date: 11/4/2013,
EEPCO
SPECIFICATION
TS-CO-05
MV and LV Insulators
SPECIFICATION TS-CO-05
EEPCO
Date
Brief Description
Rev 0
25/1/2011
First Issue
Rev 1
Feb 2013
Rev 2
5 March 2013
Page: 1 , 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
MV AND LV INSULATORS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
2
2
2
5.
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
USE
TYPE
GENERAL
MEASUREMENTS
MATERIAL
ELECTRICAL AND MECHANICAL REQUIREMENTS
MARKING
PACKING
3
3
3
3
3
3
4
4
6.
PIN INSULATORS
6.1
6.2
6.3
6.4
6.5
6.6
USE
PERFORMANCE
MATERIAL
DESIGN AND CONSTRUCTION
SPINDLE DESIGN
MARKING
4
4
4
5
5
5
7.
7.1
7.2
7.3
7.4
7.5
7.6
USE
PERFORMANCE
NUMBER OF INSULATORS ON A STRING
MATERIAL
DESIGN AND CONSTRUCTION
MARKING
5
5
6
6
6
6
8.
8.1
8.2
8.3
8.4
USE
GENERAL
MATERIAL
PACKING
7
7
7
7
9.
STAY INSULATORS
Page: 2 , 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
9.1
9.2
9.3
9.4
PERFORMANCE
MATERIAL
DIMENSIONS
MARKING
7
8
8
8
10.
10.1
10.2
10.3
10.4
PERFORMANCE
MATERIAL
DIMENSIONS:
MARKING:
8
8
8
8
11.
12.
13.
ASSOCIATED HARDWARE
PACKING
SCHEDULES
9
9
10
13.1
13.2
13.3
10
10
11
Page: 3 , 3-Apr-13
SECTION 1- SCOPE
SPECIFICATION TS-CO-05
EEPCO
MV AND LV INSULATORS
1.
SCOPE
This specification covers the Design, Manufacture, Testing and delivery of
Medium Voltage Insulators.
2.
3.
REFERENCE STANDARDS
The insulators supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. The following IEC
publications or other national or international standards, which ensure equal or
higher quality, shall be applicable:
BS 3288-2
IEC 60060
IEC 60071 -1
IEC 60168
IEC 60273
IEC 60383
IEC 60383-1
IEC 60383-1
IEC 60437
Page: 1, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
3.1
IEC 60471
IEC 60720
IEC 61109
CONFLICT
See spec TS-GN-02
4.
4.1
TYPE TESTS
The following type tests as per the relevant standard shall be conducted on the
Insulators of identical design to prove that the offered insulator satisfies all the
design requirements set out in this specification.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
4.2
ROUTINE TESTS
The manufacturer shall carry out, at his own expense, the routine tests; specified
in IEC 60383. The routine tensile load shall be 50% of the electromechanical
failing load.
(i)
(ii)
(iii)
4.3
ACCEPTANCE TESTS
(i)
(ii)
(iii)
(iv)
(v)
Porosity test
Page: 2, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
5.
5.1
USE
The Insulators shall be used with the 15kVand 33kV system
5.2
TYPE
The Line Post Insulator according to IEC 60720 shall be of the type
IEC C10-125 for the 15kV system and
C10-250 for the 33kV system.
5.3
GENERAL
Line post insulators shall be tie top pattern (Class A). The neck and groove
dimensions shall be Standard Head as in IEC 60720 for horizontal or vertical
fitting.
The side and top grooves shall have a semi-conducting glaze to reduce radio
interference.
5.4
MEASUREMENTS
The line post insulator shall have dimensions according to IEC 60720, and
generally as in the figure shown herewith.
5.5
MATERIAL
The insulating part shall be made of porcelain, glaze colour brown or grey as
specified in technical schedules.
All ferrous parts shall be of hot-dip galvanized. The materials shall be free from
folds, cracks and other exterior and interior defects, which can affect its strength,
ductility, durability or ability to function.
All material shall be inspected and tasted in full to prove compliance with the
requirements of the specifications. The free surface of insulating parts shall be
cleaned from cement and other impurities.
5.6
22kV
Insulators
45kV
Insulators
Page: 3, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
5.7
Test
22kV
Insulators
45kV
Insulators
BS 60305
BS 60305
50kV
95kV
125kV
250kV
480mm
1040mm
10kN
10kN
MARKING
The insulating part shall be clearly and permanently marked with the name of the
manufacturer or trade mark, year of manufacture and lightning impulse voltage
according to the table above.
5.8
PACKING
Line post insulator units shall be packed in crates containing 6 insulator units and
fittings. The crates shall be packed on a pallet. The packing shall afford adequate
protection for the insulators during international transportation and rough
handling during delivery to site
6.
PIN INSULATORS
6.1
USE
The Pin Insulators shall be used with the 15kVand 33kV system
6.2
PERFORMANCE
The following performance figures shall be met
6.3
Test
22kV
Insulators
45kV
Insulators
BS 60305
BS 60305
50kV
95kV
125kV
250kV
480mm
1040mm
10kN
10kN
MATERIAL
The insulator shall preferably be of porcelain glazed colour brown or gray
specified in the technical schedules, but toughened glass insulators may also be
offered.
Page: 4, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
All ferrous parts shall be of hot-dip galvanized. The materials shall be free from
folds, cracks and other exterior and interior defects, which can affect its strength,
ductility, durability or ability to function.
All material shall be inspected and tasted in full to prove compliance with the
requirements of the specifications. The free surface of insulating parts shall be
cleaned from cement and other impurities.
6.4
6.5
SPINDLE DESIGN
The insulator spindle shall be in accordance with BS 3288 Part 2 Ref. 29 or
equivalent.
6.6
MARKING
All insulators shall have clearly and permanently marked on them: Name or
Trademark of the maker and year of manufacture.
7.
7.1
USE
The Insulators shall be used with the 15kVand 33kV system
7.2
PERFORMANCE
The Cap and Pin or disk Strain insulators shall be standard IEC sea level specified
insulators. The requirement for the Altitude will be accommodated by the use of
additional discs. The following performance figures, for the OVERALL STRING
of insulators, shall be met. The preferred type of Insulators shall be U70BL
according to IEC 60305.
Table 7.1.1 Requirements for the Overall String
Unit
22kV
Insulator
string
45kV
Insulator
strings
kVrms
50
95
Impulse withstand
kVpeak
125
250
Requirement
Page: 5, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
Unit
22kV
Insulator
string
45kV
Insulator
strings
mm
480
1040
kN
70
70
BS 60383
BS 60383
Requirement
7.3
7.4
MATERIAL
The insulator shall be of glazed porcelain, glass or polymer.
Each insulator shall be supplied with clevis and tongue end fittings to enable the
strain insulator to be attached to an eye nut on the cross-arm.
7.5
7.6
MARKING
All insulators shall have clearly and permanently marked on them: Name or
trademark of the maker and year of manufacture.
Page: 6, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
8.
8.1
USE
The Insulators shall be used with the 15kVand 33kV system
8.2
GENERAL
Composite strain insulators to IEC 61109 and IEC 60471 complete with fittings
shall be supplied. The fittings supplied with each insulator shall consist of one (1)
galvanized steel bow shackle, one (1) 16 mm galvanized steel pins complete with
stainless steel cotter pins and one (1) clevis thimble to suit the particular
conductor for which it is to be used.
The following minimum characteristics shall apply to the Complete Insulator:
System Voltage
8.3
24kV
Insulators
36kV
Insulators
kN
70
70
mm
480
1040
kV
50
95
kVp
125
250
MATERIAL
The insulators shall be in accordance with IEC 61109. Each insulator unit shall be
marked with the name or trade mark of the manufacturer and the year of
manufacture in accordance with IEC 61109 and means to ensure a system of
traceability for each of the component parts. In addition, each insulator unit shall
be marked with the specified mechanical failing load in conformity with lEC
61109.
The insulators shall be constructed on a fibre glass core rod with a one-piece
EPDMor silicone rubber sheath/weather shield. The end fillings shall be
compression crimped to the core and sheath to ensure a weatherproof seal. Hot
dip galvanized ferrous end fillings shall be supplied. A full description of the
materials and construction shall be provided with the bid.
8.4
PACKING
Insulator units shall be packed in crates and each crate shall contain 3 or 6
insulator units and fittings. The crates shall be packed on a pallet. The packing
shall afford adequate protection for the insulators during handling and shipping.
9.
STAY INSULATORS
9.1
PERFORMANCE
The following performance figures, per individual insulators, shall be met.
Page: 7, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
9.2
Voltage application
LV System
15kV System
33kV System
Frequency
50 Hz.
50 Hz.
50 Hz.
24kV Min.
24kV
(2
nos
series)
44kN
88kN
88kN
18kN
18kN
36kN
65mm
105mm
105mm
in
MATERIAL
The insulators shall be of glazed porcelain or toughened glass.
9.3
DIMENSIONS
Each stay-wire hole shall have a minimum diameter of 22mm, and shall be such
that a straight stay wire can be passed through it.
9.4
MARKING
All insulators shall have clearly and permanently marked on them the name or
trademark of the manufacturer.
10.
10.1
PERFORMANCE
10.2
1500 kgs
600 kgs
MATERIAL
The insulators shall be of porcelain and glazed brown. The surface of the
insulators should be perfectly smooth and free from all defects and cracks.
10.3
DIMENSIONS:
Principal required overall dimensions are height -78mm (max.), diameter -90mm,
axial hole dia. -21mm, (flared at ends) groove radius -12.5mm.
10.4
MARKING:
All insulators shall have clearly and permanently marked on them the name and
trademark of the manufacturer.
Page: 8, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
11.
ASSOCIATED HARDWARE
Hooks, conductor clamps and other associated hardware shall be in accordance
with associated Specification for "Insulator and Conductor Fittings for Overhead
Lines"
12.
PACKING
The insulators shall be packed securely. See spec. No.TS-GN-02.
Page: 9, 3-Apr-13
SPECIFICATION TS-CO-05
EEPCO
13.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
13.1
13.2
SPECIFICATION TS-CO-05
EEPCO
13.3
LPA - EEPCo
PIN Insulators
1
4
5
7
8
9
10
11
12
13
Bid Offer
IEC 60383
IEC 60383
kV
125
250
kV
50
95
kN
10
10
(IEC 60437)
BS 60305
480
(IEC 60437)
BS 60305
1040
kV
mm
kV
Page 1/5
LPA - EEPCo
STRAIN INSULATORS
General Specification for Insulators
Dry Impulse withstand
Material (Porcelain or Glass or
Composite)
Wet 50Hz 1 Min. Withstand (Type Test
IEC 60383)
Mechanical Failing Load
Puncture @ 50Hz. Sample Test IEC
60383
Pinhole gauge test, Sample Test - this
specification and see also BS 60383,
60305
Radio Interference
Maximum RIV at 1MHz
No of disks required for 22kV system at
pollution level II
No of disks required for 45kV system at
pollution level II
Overall Leakage/Creepage distance
Weight per unit
Page 2/5
kV
IEC 60305
125
kV
50
kN
70
kV
Sample Test
(IEC 60437)
BS 60305
No
No
mm
kg
480
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
LPA - EEPCo
Requirement
Bid Offer
Manufacturer
Manufacturer's Code N"
Type of insulator
Material
Colour of glaze if porcelain
Standard
IEC
Type
IEC
Dimension:
Line Post
Line Post
Porcelain or Glass
Porcelain or Glass
Brown or Grey
Brown or Grey
C10-125
C10-250
60273
60273
305 1
560 1
mm
mm
mm
kV
24
52
mm
>480
>1040
kV
50
95
kV
125
250
kN
10
10
Cantilever strength
kN
12.5
12.5
mm
mm
Weight
kg
kV
Page 3/5
LPA - EEPCo
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
Requirement
Strain/suspension
Strain/suspension
Composite polymer
Composite polymer
kV
kV
15
33
24
52
mm
480
1040
Grey
Grey
Stainless Steel
Stainless Steel
50
95
kV
125
250
kN
70
70
Bid Offer
Manufacturer
Manufacturer's Code
Type of insulator
Material
Standard
IEC, ANSI
Designation
Dimension (D x L)
Nominal System Voltage:
- Nominal
- Highest
Equipment Highest Voltage
Overall creepage length
mm x mm
kV
kV
Number of Shed
End fitting type
Page 4/5
No
20
21
22
23
24
25
Item
Unit
Requirement
Bid Offer
LPA - EEPCo
Requirement
Bid Offer
kg
Cantilever strength
kN
mm
mm
Weight
kg
12.5
Page 5/5
12.5
EEPCO
SPECIFICATION
TS-CO-06
Spun Concrete Poles and Accessories
SECTION 1 - SCOPE
SPECIFICATION TS-CO-06
EEPCO
Date
Brief Description
Rev 0
25/1/2011
First Issue
Rev 1
Feb 2013
Rev 2
Mar 2013
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: i , 4-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-CO-06
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
SPUN CONCRETE POLES & ACCESSORIES
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
4.
INSPECTION AND TESTING
1
5.
DESIGN OF POLES
4
6.
POLE LENGTH, SHAPE AND DESIGN LOADING
5
7.
POLE ACCESSORIES
6
8.
MARKING AND PACKAGING
10
9.
SCHEDULES
10
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: ii , 4-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-CO-06
EEPCO
SCOPE
This specification covers the Design, Manufacture, Testing and delivery of spun
concrete poles and their accessories
2.
3.
REFERENCE STANDARDS
The requirements of the following standards / specifications shall be met where
applicable unless otherwise stated in this specification.
ASTM C39
ASTM C143
ASTM C150
ASTM C172
ASTM C494
BS 4190
BS 5896
3.1
CONFLICT
See Spec .TS-GN-02 General Contractual obligations
4.
4.1
TESTING ARRANGEMENT
Poles shall be tested in the horizontal position in a testing frame. The testing
arrangement shall be provided with sufficient supports to ensure that bending
moments developed by the self-weight of the pole are minimal. These supports
shall be detailed to give no horizontal resistance to the applied test load. The
accuracy of all load and deflection measuring equipment shall be 2 percent.
Note -To eliminate the effects of movement of the reaction blocks at ground level
and the butt of the pole, the zero position of the deflections measuring ruler at
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 1 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
the top of the pole must be corrected before each deflection reading. This
correction can be made each time by projecting the line between centre marks at
the butt and ground level reaction posts.
4.2
COST OF TESTING
The cost of all pole testing shall be allowed for in the Bid Price. This shall include
any additional testing instructed to be carried out by the Purchaser to prove that a
class of pole satisfies all design requirements. These shall be carried out before full
scale manufacture of a class of pole commences, after any changes are made to
the approved design of a class of pole, or at any time the Purchaser 's
Representative considers necessary to confirm that any class of pole still satisfies
the design requirements.
4.3
TYPE TEST
These shall be carried out before full scale manufacture of a class of pole
commences, after any changes are made to the approved design of a class of pole,
or at any time the Purchaser's Representative considers necessary to confirm that
any class of pole still satisfies the design requirements.
A sample consisting of three of each pole class (selected at random) for each
loading shall be subjected to the Type Test. The test results shall comply with the
acceptance criteria at the end of this Section.
Type tests shall be carried out in 2 stages:
1stStage:
The load shall be gradually and uniformly applied in increments of 10% of the
ultimate design load up to 125% of the design working load. At each increment of
load the deflection of the pole tip shall be measured. Deflections shall be graphed
against the applied load and the graph shall indicate a consistent relationship
between load and deflection.
When measuring deflection at the tip of the pole, allowance shall be made for any
strain movement in the reaction posts of the testing arrangement.
The loads at which any cracks become visible shall also be recorded as well as
their location and their extent. A volatile liquid such as methylated spirits (methyl
alcohol) shall be applied to the concrete surface so that cracks may be readily
observed at all load increments.
The 125% loading shall be maintained for 5 minutes, and the pole shall be
inspected for any cracks. The load shall then be gradually reduced to zero and the
amount of permanent deflection of the pole top recorded.
2nd Stage:
The test load shall be gradually reapplied up to the design working load and the
deflection recorded. The load shall then be increased in 10% increments until
failure occurs. At each load increment the load and deflection shall be recorded.
The following particulars shall be recorded for both types of test:
(i)
(ii)
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 2 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
(iii)
(iv)
Date manufactured.
(v)
Date tested.
(vi)
(vii)
Increments of load.
(viii)
Deflections at each increment of load -for both Stage 1 and Stage 2 loads.
(ix)
(x)
Location of all cracking on a plan and elevation drawing of the pole, and the loads
when cracking occurred.
(xi)
Load at failure.
(xii)
Nature of failure.
Colour photographs along the axis of the pole at design working and design
ultimate loads, plus photographs of the failure zone on the pole.
A sample of three poles for each pole class shall be considered acceptable if:
(xiii)
No visible cracking occurs up to 125% of the design working load in any of the
poles tested.
(xiv)
Permanent deflection of the tip of each pole, after the 1st stage test loading is
removed, does not exceed 1 mm per meter of pole length.
(xv)
The average failure strength of the three poles tested equals or exceeds the
specified ultimate design strength, and the failure strength of any single pole is not
less than 0.90 times the ultimate design strength.
The Contractor shall keep records of all Type Tests, and provide three copies to
the Employer's Representative.
4.4
ROUTINE TESTS
Routine tests shall consist of,
4.5
(i)
Dimension checks.
(ii)
Weight checks.
(iii)
Visual checks (signs of cracks and chips, quality of surface finish, longitudinal
alignment, insufficient cover over reinforcement, treatment of stressing wires at
ends of poles, etc)
(iv)
ACCEPTANCE TESTS
This test shall be carried out on poles selected at random by the Employer at the
rate of 1 per 100 or fewer of each class of pole manufactured at the plant. Test
loadings shall be applied in the same increments as the Type Test 1st stage loading.
The poles will be considered acceptable if the deflection at each load increment
and the permanent deflection upon removal of load does not exceed by more
than 15% the average of acceptable tests of the corresponding values for 1st stage
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 3 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
loading of the Type Tests. The Contractor shall keep records of all Proof Testing,
and provide two copies to the Employers Representative.
4.6
5.
DESIGN OF POLES
5.1
GENERAL
Each type of pole shall be designed to resist without failure, the ultimate strength
bending moment at ground level defined in this specification. The proof of the
ultimate strength of each type of pole will be in accordance with the Type Tests
carried out as defined in the section on Testing of Poles"
Serviceability calculations shall also be made in accordance with an appropriate
international pre-stressed concrete design standard to ensure adequate
performance of the poles under the design working loads defined in this
specification. Refer also to the acceptance criteria defined in the section on, "Type
Testing", last paragraph.
The Contractor shall submit to the Purchaser, detailed design calculations and
construction drawings for all aspects of design of all of the pole classes scheduled
herein.
5.2
DEFLECTION
The maximum allowable top deflection under the design working load applied in
accordance with "Testing of Poles", shall be H/25 where H = total pole length.
5.3
POLE MARKINGS
All poles shall be clearly and indelibly marked at a position approximately 3.5
meters from the butt end with:
Date of manufacture and identification mark of manufacturer.
Length of pole in meters and its design working load, as defined in this
Specification.
For example a 9 meter pole with a 5 kN working load and safety factor 2.5 shall
be marked: 9/52.5.
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 4 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
Poles shall also be marked with a permanent horizontal at the design ground line
(determined as 1/10 of the pole length plus 600 mm), and at the design lifting
points.
5.4
DIMENSIONAL TOLERANCES
The permitted variation from a stated dimension or cross-sectional shape of the
finished pole shall be as follows:
Length + 15 mm, -10 mm (allowance shall be made during design for length
reduction by prestressing forces).
Cross-section Overall dimensions and dimensions of parts, 2 mm
Straightness Deviation from a straight line joining the centre of the top and the
centre of the butt of a pole, 15 mm
Deviation from a straight line on the surface of a pole measured between the
ground line and a point 50 mm below the top, 5 mm
Holes Diameter -0, + 2 mm, Relative position 5 mm
Location of steel 3 mm, but specified covers shall not be reduced, and the pole
straightness reinforcement and shall remain within the specified tolerances.
Notwithstanding all of the above, the faces of every pole shall be straight and free
of significant local variation; any departure may lead to its rejection by the
Purchaser.
5.5
SURFACE FINISHES
All poles shall have a surface finish that is smooth, hard, uniform in colour and
appearance and free from any honeycombing and air pockets exceeding 4mm in
diameter, and 3mm in depth. All fins and other projections shall be rubbed down
or ground flush with the general surface of the pole. Repair of defective concrete
will not be permitted and any pole containing defective concrete will be rejected
by the Employer.
6.
6.1
GENERAL
Each pole shall be manufactured in one piece. All holes for the mounting of
equipment shall be cast in the poles during manufacture in accordance with the
drawings.
6.2
6.3
DESIGN LOADING
The standard design working loads in the transverse direction shall be as follows:
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 5 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
9m, 2kN
14.40
9m, 5kN
36.00
9m, 8kN
57.60
12m, 3kN
29.10
12m, 6kN
58.20
12m, 9kN
87.30
14m, 4kN
45.46
14m, 6.5kN
6.5
73.88
14m, 10kN
10
113.66
The ultimate pole top load to be used for designing each class of pole shall be a
factor of safety (F.O.S.) (k = 2.5) times the appropriate standard design working
load scheduled above. Ultimate design forces to be used for the pole design shall
result from this load applied to the pole when held in the standard test frame
specified in the pole testing section of this specification.
6.4
EARTHING
Earthing shall be provided by having a length of 8 SWG Galvanised Iron(GI) wire
embedded in concrete during manufacture and the ends of the wires left
projecting out from the pole to a length of 100 mm to enable extension of
earthing wire during installation. This shall come out of the pole at the top side at
250 mm from top and about 1m from the bottom of the pole. The earth wire
shall be mechanically connected as much as possible to the steel reinforcement of
the pole.
6.5
7.
POLE ACCESSORIES
Pole accessories may or may not be order together with the poles. This shall be
specified in the scope of work and the schedule of prices. If this is part of a
turnkey contract then all accessories shall be included in the scope of works. Their
inclusion in the prices shall be stated clearly.
7.1
CROSS ARM
Cross arm shall be manufactured from channel and angle section steel, hot dip
galvanized after fabrication, particular care shall be taken so as to reduce
embrittling the steel during the galvanizing process. All holes for the mounting of
pin insulators and string insulators shall be drilled to suit the components to be
attached before galvanising.
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 6 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
Angle section cross arm shall in general be used for single and double pin and line
post insulator positions. The angle section shall have welded cleats at the pin
positions to allow the fitting of standard insulator pins and studs.
Strain (dead end) cross arm shall be constructed from channel section steel, with
suitable provision for pin and line post insulators for jumpers.
All cross arm shall be fitted with flat section hot dip galvanized steel cross arm
braces. The minimum thickness of all section shall be 6 mm.
The centre phase conductor shall be supported independently of the cross arm on
purpose designed brackets that attach directly to the pole.
All bolts associated with cross arm shall be M16 hot dip galvanized.
The conductor loads to be used for designing the cross arm and the insulator
brackets (in the case of the centre phase) shall be a factor of safety (F.O.S.) of 2.5
times the appropriate standard design working load scheduled below:
The following minimum characteristics shall apply to all cross arm:
Cross arm Type
7.2
2.0
5.0
3.0
4.0
8.0
5.0
4.0
16.0
20.0
POLE FITTINGS
The following pole fittings shall be provided: Single cross arm, complete with two
cross arm braces and all necessary nuts, bolts and washers for attachment to the
pole.
a)
Double cross arm, complete with two cross arm braces, spacers, and all necessary
nuts, bolts and washers for attachment to the pole.
b)
c)
d)
7.3
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 7 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
7.4
GALVANIZING
All ferrous parts shall be hot dip galvanized. Large steel parts shall be hot-dip
galvanized to a mean thickness of 70 m and a minimum thickness of 65 m.
Steel sheets with a thickness of less than 5 mm may be hot-dip galvanized to a
mean thickness of 60 m and a minimum thickness of 50 m.
The zinc coating shall meet the requirements according to BS 729, ASTM, A 123,
A 153, A239 and A385. The purity of the zinc in the galvanizing bath shall not be
less than 98%.
All steel shall be fully fabricated before galvanizing, no machine or shop work,
boring, punching etc., will be allowed after galvanizing.
7.5
7.6
GUYING
Materials for guying include pole eyebolts, thimbles, guy wire, guy grip dead ends,
guy insulators, and anchor rods. The design and supply of buried concrete dead
end will be the responsibility of the erection Contractor.
7.6.1
Pole eyebolts.
Galvanized steel eyebolts shall be used to attach the guy wire to the concrete
poles. The eyebolts shall be M16, of length to suit the pole dimension at the point
of fixing, with an eye of internal diameter 40mm. The thread length shall be
sufficient for the range of pole dimensions. Each eyebolt shall be supplied fitted
with 75 x 75 x 6mm square galvanized washer and two galvanized nuts. The shape
of the eye shall be such that when the eyebolt is fully tightened that the eye does
not damage the concrete pole.
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 8 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
Eyebolt thimbles
Galvanized steel thimbles are required on the eyes of pole eyebolts and anchor
rods. The thimbles shall be suitably dimensioned for the loop on the helical guy
grip dead end fittings. The minimum failing load shall be not less than 98kN. The
thimbles shall be of the open type suitable for eyes formed from both 16mm and
20mm diameter rod.
Thimbles shall be packed in durable non-ferrous containers containing
approximately 100 thimbles and suitable for outdoor storage. The containers shall
be legibly and durably marked in the English language with a description of the
contents. Multiple containers shall be secured to pallets for transport.
7.6.3
Stay wire
Galvanized steel stay wire shall be suitable for the guying of concrete poles in a
tropical outdoor environment. The stay wire shall be 7/4.00 SC/GZ, constructed
of high tensile grade strand, and of minimum ultimate breaking load 103kN. The
stay wire shall be in accordance with AS1222.1 or equivalent. Alternatives to
another recognized national standard may be proposed by the bidder provided
that it is shown they are equal or better. A copy of the relevant parts of any
alternative Standard shall be included with the bid.
The stay wire shall be packed on substantial, reinforced, non-returnable drums.
The drums shall be of robust construction suitable in all respects for international
transport, outdoor storage in a tropical climate for a least three years without
harmful deterioration, and rough on-site handling. All drums that have a gross
weight greater than 500 kg shall have a reinforced central bore. The drums shall
be fully lagged.
Each drum disc shall be legibly marked on the outside with lettering not less than
50mm high showing the makers name, stay wire stranding and material, packed
length, and gross weight. The required drum lengths are shown in the Technical
Data Sheets.
7.6.4
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 9 , 4-Apr-13
SPECIFICATION TS-CO-06
EEPCO
a description and quantity of the contents. Each box shall include full installation
instructions.
7.6.5
Guy Insulators
Guy strain insulators shall be suitable for insertion in tensioned guys in outdoor
service in a hot humid tropical climate. The insulators shall be porcelain, of a
heavily fluted profile, and glaze colour mussel grey or similar. The minimum
failing load shall be 70kN. The insulators shall have a minimum power-frequency
wet r.m.s. flashover voltage of 20kV.
8.
8.1
INSULATORS
Each insulator shall be durably and legibly marked with the name or trade mark of
the manufacturer, the year of manufacture, the catalogue number, and the
minimum mechanical failing load.
The insulators shall be packaged in heavy duty cardboard boxes containing 6
insulators. The boxes shall be packed in an outer timber crate containing
approximately 100 insulators and placed on a pallet. The packing shall afford
adequate protection for the insulators during international transportation and
rough handling during delivery to site.
8.2
ANCHOR RODS
Anchor rods are required for attachment of the stay wire to a buried dead pan or
anchor block installed with the eye close to ground level. The rods shall be of
galvanized steel, minimum failing load 98kN, 2000mm x M20, with an eye of
internal diameter 40mm. The rods shall have a thread length not less than 50mm
and be supplied fitted with one 200 x 200 x 6mm square galvanized steel washer,
and two full sized galvanized M20 nuts.
Anchor rods shall be securely bundled in packs of 10 rods. For international
transport the packs may be further bundled in packs of 10 (100 anchor rods total).
9.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
9.1
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 10 , 4-Apr-13
SECTION 9 - SCHEDULES
SPECIFICATION TS-CO-06
EEPCO
9.2
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 1 , 4-Apr-13
SECTION 9 - SCHEDULES
SPECIFICATION TS-CO-06
EEPCO
9.3
TS-CO-06 R2a Spun concrete poles and accessories C.docxRev -2- Mar 2013
Page: 2 , 4-Apr-13
LPA-GECE
EEPCo
No
Item
Unit
Manufacturer
Manufacturer's Code N0
Type
Cross-section of pole
Length of pole
mm
9000
mm
9000
mm
9000
mm
12000
10
mm
12000
11
mm
12000
12
13
14
mm
14000
mm
14000
mm
14000
15
16
mm
260
17
mm
260
18
mm
260
19
mm
350
20
mm
350
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
mm
350
mm
377
mm
377
mm
377
mm
160
mm
160
mm
160
mm
190
mm
190
mm
190
mm
190
mm
190
mm
190
Prestressed
Spun concrete
Circular
Weight of pole
Page 1
Date: 04/04/2013,
LPA-GECE
No
Item
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
EEPCo
kg
kg
kg
kg
kg
kg
kg
kg
kg
kN.m
57.6
kN.m
36
kN.m
14.4
kN.m
87.3
kN.m
58.2
kN.m
29.1
kN.m
113.66
kN.m
73.88
kN.m
45.46
Page 2
Date: 04/04/2013,
EEPCO
SPECIFICATION
TS-GN-01
SPECIFICATION TS-GN-01
EEPCO
Date
Brief Description
Rev 0
12 Dec 2012
Rev 1
Feb 2013
Rev 2
Mar 2013
SPECIFICATION TS-GN-01
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
1.
SCOPE
2.
SYSTEM PARAMETERS AND DESIGN DATA
3.
CLIMATIC & GEOGRAPHIC CONDITION
PAGE NO
1
1
2
SECTION 1- SCOPE
SPECIFICATION TS-GN-01
EEPCO
SCOPE
This specification defines and declares the System and the Environmental data
applicable to the EEPCO system.
This data forms the basis for the design and system operation and all equipment
and material specification refer to this specification by default if it is not
mentioned exclusively in the particular specification.
2.
33 kV System
15kV System
LV System
Nominal voltage Un
33 kV
15 kV
400/230 V
10%
10%
10%
36 kV
17.5 kV
440/253 V
52 kV
24 kV
0.6/1 kV
Rated frequency
50 Hz
50 Hz
50 Hz
3 phase, 3 wire
3 phase, 3 wire
3 phase, 4 wire
System configuration
1 phase, 2 wire
Earthing
Insulation co-ordination
Neutral Solidly
earthed
IEC 60071-1, -2
95 kV
50 kV
3 kV
250 kV
125 kV
6 kV
25 kA/1 sec
20 kA/1 sec
450 mm
350 mm
200 mm
SPECIFICATION TS-GN-01
EEPCO
Parameter
equipment exposed to air.
33 kV System
15kV System
LV System
400mm
300
150
20mm/kV
20mm/kV
60mm
Dyn 5
Dyn 5
Transformer
MV/LV
3.
Vector
group
Parameter
Any altitude up to 3000 m
1250 mm
June to September
Isoceraunic Level
Seismic Level
+ 250c
-50c
450c
70%
35m/s
45m/s
EEPCO
SPECIFICATION
TS-GN-02
SPECIFICATION TS-GN-02
EEPCO
Date
Brief Description
Rev 0
12 Dec 2012
Rev 1
Feb 2013
Page: i , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
GENERAL CONTRACTUAL OBLIGATIONS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
SUFFICIENCY OF THE WORKS
1
4.
DESIGN OF THE WORKS
1
5.
SUBMITTALS WITH THE BID
1
6.
SAFETY PRACTICES
2
7.
LANGUAGE
3
8.
SYSTEM OF UNITS
3
9.
STANDARDS
3
10.
INSTALLATION, OPERATING, SERVICE AND
MAINTENANCE INSTRUCTIONS
4
11.
DOCUMENTS AND DRAWINGS TO BE SUBMITTED
WITH BID
4
12.
SUPPLIER DOCUMENTS AND DRAWINGS
5
13.
GENERAL ARRANGEMENT DRAWINGS
6
14.
DETAIL DRAWINGS
6
15.
SCHEMATIC DIAGRAMS
6
16.
WIRING DIAGRAMS
7
17.
MATERIAL SELECTION
7
18.
TRANSPORT TO SITE
7
19.
PACKING AND SHIPPING
8
20.
INSPECTION, TESTING AND EXPEDITING
9
21.
TRAINING OF OPERATION AND MAINTENANCE STAFF 10
22.
CONTRACTORS CONSTRUCTION PERSONNEL
11
Page: ii , 4-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-GN-02
EEPCO
SCOPE
This specification defines and declares the General Contractual Obligations
applicable with installation contracts in the EEPCO system.
These obligations form the basis for the scope of works and basic specification of
works, equipment and materials. This is applicable by default to all scope and
specifications unless it is modified in the particular specification or scope.
2.
3.
4.
5.
5.1
GENERAL
In addition to the requirements of the General Conditions of Contract, the
Conditions of Particular Application, and the Employers Requirements, the
Bidder shall submit with the bid full technical details of all equipment/materials
and supplied for installation on the Works. This shall include but not be limited to
confirmation of:
The information listed in the Technical Schedules
Type test reports of equipment/materials offered issued by an international
test laboratory.
Page: 1 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
5.2
APPROVALS
The Contractor shall submit for approval to the Employer and/or the
Employer's Representative full technical design details of all proposed
construction. This shall include but not be limited to confirmation of:
Detailed designs supported by relevant calculations
Drawings showing the location of all works.
The designs shall show:
Constructional features of planned buildings, and substations
Overhead line routes.
Underground cable route
Standard pole configurations
Electrical ratings and equipment selection (transformer capacity, cable size,
fuse size, etc)
Approval shall be obtained before any installation or construction is
commenced. The Employers undertakes to respond to any request for
approval in a reasonable period of time.
6.
SAFETY PRACTICES
All work shall be undertaken with close attention to high standards of safety to
works, the public, and to the Employer and other owners plant equipement.
All of the Contractors personnel shall be effectively trained and competent in
safe working practices that must be adhered to at all times. All personnel shall be
issued with and use at all times relevant personal and work gang relared safety
equipment that shall be maintained in good order and condition by the
Contractor.
Personal safety equipment for linesmen and others working on the network shall
include but not be limited to :
Safety helmet
Safety clothing that covers arms and legs
Safety footwear
Protective gloves
Water proof gear.
In addition linesmen who work on poles or from ladders or elevated platforms
shall be supplied with and use at all times:
Safety belts and/or harnesses
Insulating gloves for when working on or in proximity to energised LV circuits
Suitably rated insulated gloves when operating energised MV equipment.
Page: 2 , 4-Apr-13
SECTION 7 - LANGUAGE
SPECIFICATION TS-GN-02
EEPCO
The Contractor shall encourage and adhere at al time to safe working pratices.
7.
LANGUAGE
The English language shall be used on all Contract documents and in all
correspondence between the Contractor and the Employer' Employers s
Representative, and between the Contractor and the Employer .
8.
SYSTEM OF UNITS
In all correspondence, in all technical schedules and on all drawings metric, units
of measurement (Systeme Internationals) system of units shall exclusively be used.
Dimensions in meters and millimetres unless specified otherwise
The unit of mass is the kilogram (kg)
The unit of force is the Newton (N).
9.
STANDARDS
The equipment supplied under this contract shall conform to the latest edition of
the appropriate IEC specifications or other recognized international standards.
All workmanship employed on, and materials incorporated into the Goods shall,
except where specified otherwise or where specific Standards are referred to,
comply with the latest issues of the Standards and Codes of Practice, as relevant
and appropriate, published by the following organizations:
ISO
International Standards Organization (ISO)
IEC
International Electro technical Commission standards
BSI
British Standards Institution
AASHTO
American Society of State Highway and Transportation Officials
ACI
American Concrete Institute
AISC
American Institute of Steel Construction
ANSI
American National Standards Institute
ASME
American Society of Mechanical Engineers
ASTM
American Society for Testing and Materials
AWS
American Welding Society
DIN
German Institute for Standardization
IEEE
Institute of Electrical and Electronic Engineers
JIS
Japanese Industrial Standard
SAA
Standards Association of Australia
SABS
South African Bureau of Standards
USBR
United States Bureau of Reclamation
The use of Standards and Codes of Practice other than those mentioned above
shall be subject to the approval of the Employer . The Contractor shall provide
the Employer with a complete list of all Standards and Codes of Practice that he
intends to use, other than those specified herein, within eight calendar weeks from
the Effective Date, for the approval of the Employer .
The Contractor shall provide to the Employer , English language copies of any
Standards and Codes of Practice, which the Contractor wishes to use. The
Contractor shall provide English language translations of any Standards and
Page: 3 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
Codes of Practice which the Contractor wishes to use and which are in a language
other than English.
All Goods supplied shall conform to the latest editions of the International
Electro technical Commission (IEC) Specifications unless stated otherwise.
Goods offered from a country where the relevant Standards to which the items
and components conform that are, in the opinion of the Employer, equal to or
better than IEC are acceptable, but details of the relevant Standards shall be
provided to the Employer. Full details of differences that affect the design or
performance of the Materials shall be stated in the bid and English translations of
any such alternative Standards shall be supplied by the Contractor when requested
by the Employer.
10.
11.
Auto-reclosers
Conductors, cables and accessories
CTs, VTs
Earthing materials
Guying
Insulators
LV capacitors
LV fuse switch disconnections and LV fuses
Page: 4 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
General bar chart of the manufacturing, shipping, and delivery schedule for all
items of the Goods
12.
12.1
GENERAL
The Supplier shall be responsible for the submission, re-submission and approval
as may be required of all the documents and drawings listed below, so that there
shall be no delay to the work due to the absence of such documents and drawings.
Any approval by the Employer will not relieve the Supplier of any obligations
under the Contract.
Any alterations to the documents and drawings which may be required by the
Employer for approval shall be made by the Supplier at his own expense. All
materials and work involved in their manufacture shall be as indicated in such
drawings.
Page: 5 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
No work shall be done on any part of the Goods, the design or construction of
which is dependent on the approval of such drawings or data, until such approval
has been given. The Supplier shall submit three prints of each drawing for
approval marked Proposal Drawing. One copy will be returned to the Supplier
marked up with approval or any proposed alterations.
The Supplier shall provide the same number of further prints for any drawings
that are altered. All drawings, information, design reports, etc shall be neatly type
written or drafted in the English language, and be presented as bound documents.
The documents presented shall have neatly drawn title pages that clearly show the
name of the Employer, identify the project and site name, the contract number,
the date, the revision number, etc, and shall be provided with a table of contents.
The format and content of drawing titles shall be to the Employers standard.
Translations into Amharic (Ethiopia national language) may be included as
appropriate to facilitate construction work in the field.
13.
14.
DETAIL DRAWINGS
The Supplier shall supply detail drawings that shall show sufficient detail to
demonstrate compliance with the requirements of this specification.
15.
SCHEMATIC DIAGRAMS
The Supplier shall provide schematic diagrams showing all the wiring work in all
the Equipment supplied. Schematic diagrams shall comply with the following
requirements:
Terminal numbers shall be clearly shown on the drawing and the equipment to
which they belong shall be identified.
Where a relay coil is shown, all contacts shall be indicated adjacent to it. All
contacts illustrated on another part of the diagrams shall be cross-referenced
and a brief description of their purpose given. The use of dotted lines to
associate a contact with its coil is acceptable.
All terminal numbers on panels, relays, instruments and the like shall be shown
on the schematic diagram.
It shall be possible to determine the location of any item of equipment from
the schematic diagram. All equipment labels and identification discs on valves
shall correspond with the schematic diagrams.
The schematic diagrams provided under this Contract shall show other
equipment when it is connected to equipment supplied under this Contract,
where necessary to ensure ready understanding of the drawings.
Schematic diagrams shall also be supplied for oil or any other system supplied,
and shall be prepared accordingly
Page: 6 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
16.
WIRING DIAGRAMS
The Supplier shall provide wiring tables and / or wiring diagrams.
16.1
17.
MATERIAL SELECTION
In choosing materials and their finishes due regard shall be given to the humid
tropical conditions, and at some sites proximity to a coastal environment. The
Supplier shall submit to the Employer for approval details of his practices and
recommendations to prove the appropriateness of the chosen materials.
18.
TRANSPORT TO SITE
The Contract Price shall include all expenses in connection with the transport to
the specified destinations of all equipment, materials and items including handling,
permits, taxes, duties, insurance, and other charges that the Supplier may incur.
The Supplier shall arrange and bear the cost of insurance during transport, as
specified.
The Supplier shall observe any regulations which limit loads on roads and bridges
over which material or equipment may be conveyed, or alternatively at his own
cost make arrangements for any temporary strengthening or widening which may
be necessary.
After hand over, the handling and storage of any materials and equipment at the
specified destinations shall be at the risk of the Employer, and without
responsibility to the Supplier. The Supplier shall advise the Employer of any
Page: 7 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
particular requirements for the protection of all materials and equipment against
corrosion and mechanical damage during storage and transport to the final
installation site.
The Supplier shall make all arrangements for taking delivery of the Materials, at
the various seaports or border crossing points involved, and for their
transportation to the specified destinations including the payment of port duties
and all charges. The Supplier shall allow in his programmed for any delays which
may be caused by port congestion or customs clearance, and allow for any
additional charges that may be incurred as a result of such delays.
19.
Page: 8 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
nut to distribute the pressure, and the timber shall be strengthened by means of a
bearing pad.
The Supplier shall note that the use of untreated or un-impregnated conductor
and cable drums is at the Suppliers risk. If any evidence is found of deterioration
in drums during storage or on site which in the opinion of the Employer might
lead to delays in erection work, he shall forthwith require all remaining drums to
be strengthened, suitably protected, or the contents rewound on to replacement
drums at the Suppliers cost.
All machined parts shall be thoroughly protected against corrosion. Where
practicable, items such as electric motors, switch and control gear, instruments
and panels, machine components, etc., shall be cocooned or covered and the
enclosure provided internally with an approved desiccators.
20.
Page: 9 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
The inspection and acceptance tests shall be carried out in accordance with the
provisions in the applicable standard, supplemented by the specific requirements
indicated in the technical specifications free of cost to the Employer.
At least 45 days notice of the date, time and place of all tests shall be given to the
Employer so that arrangements can be made to have the test witnessed.
21.
21.1
SITE TESTING
On completion of erection and before commissioning .the equipment shall be
fully tested to a schedule of tests previously agreed with the Employers's
Representative, to demonstrate its suitability for commercial use. The tests shall
include, but not be limited to.
Insulation resistance
Operation and load checks.
Earthing Resistance
Other tests, if any
Page: 10 , 4-Apr-13
SPECIFICATION TS-GN-02
EEPCO
21.2
SECTION 22 - CONTRACTORS
CONSTRUCTION PERSONNEL
CERTIFICATES
Suitable certificates shall be prepared and completed for these tests and for each
site as required.
22.
22.1
SUPERVISING FOREMAN
A Supervising Foreman will be required to be in overall charge of the Works at
each work site,
The Supervising Foreman shall be competent person who will not engage in the
actual physical work, but shall have oversight of all work and full control of his
staff. He shall be familiar with the Employer's and Contractor's design and safety
requirements.
22.2
LEADING HAND
A leading Hand or Working Foreman will be required to be in charge of each
Construction gang if cable installation is required.
The Leading Hand shall be a competent person with leadership qualities, be
familiar with the requirements of the Scope of Work, and shall lead his
construction gang in the execution of the Works. He shall be familiar with the
Employer's and Contractor's design and safety requirements.
22.3
LINESMEN
A minimum of four Linesmen will be required in each line construction gang.
The Linesmen will be competent and experienced, and familiar with the
requirements of the Scope of Work. They shall be familiar with the Contractor's
design and safety requirements.
22.4
CABLE LAYERS/JOINTERS
A minimum of two cable layers and two cable jointers will be required in each
construction gang if cable laying is included in the scope of works.
Cable jointers shall be experienced in terminating and jointing MV and LV XLPE
cables. Cable layers shall be responsible for installing cables in accordance with
the Employers design standards and shall be familiar with the cable
manufacturer's cable bending radius, pulling and installation recommendations.
22.5
LABOURERS
Sufficient labourers will be required in each Construction Gang to support the
linesmen, jointers and cable layers and to carry out the non-skilled tasks. This will
include the excavating of foundations for poles, earth wires, etc., handling of
equipment and digging cable trenches where mechanical excavators cannot be
used. They will assist the linesmen/cable layers in the running out of conductor
/cable without damage and to direct traffic where obstructed by the Works, etc.
Page: 11 , 4-Apr-13
SECTION 22 - CONTRACTORS
CONSTRUCTION PERSONNEL
SPECIFICATION TS-GN-02
EEPCO
22.6
ELECTRICAL FITTERS
At least two experienced and competent electrical fitters shall be available at each
site to undertake the installation of MV switchgear, LV frames and associated
items, transformers, etc.
22.7
TEST TECHNICIANS
At least two competent and experienced test technicians familiar with distribution
equipment, relevant test equipment and testing procedures shall be available as
required at each work site.
22.8
METER INSTALLERS
The Contractor shall employ a sufficient number of competent personnel to wire
and install metering Boxes Etc.
22.9
CERTIFICATION OF STAFF
All Supervising Foremen, leading hands, and linesmen shall be adequately trained
and knowledgeable in the construction of up to 33 kV lines and erection of LV
ABC, erection of distribution substation equipment, earth installation procedures,
cable installation and related tasks. All other staff shall be competent with relevant
experience in their designated tasks.
Page: 12 , 4-Apr-13
EEPCO
SPECIFICATION
TS-GN-03
General Management Requirements
SPECIFICATION TS-GN-03
EEPCO
Date
Brief Description
Rev 0
April 2013
First Issue
Page: 1 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
GENERAL REQUIREMENTS FOR INSTALLATION WORKS
1
1.
SCOPE
1
2.
DOCUMENTS AND DRAWINGS
1
3.
O&M MANUALS
2
4.
GUIDE LINES
2
4.1
4.2
4.3
4.4
4.5
2
3
3
3
4
5.
ENVIRONMENTAL POLICY.
5.1
5.2
5.3
GUIDING PRINCIPLES
5
ENVIRONMENTAL IMPACTS
5
ENVIRONMENTAL MANAGEMENT PLAN FOR DISTRIBUTION LINES 6
6.
PROJECT MANAGEMENT
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
PROJECT MANAGEMENT
REPORTING PERIOD
PROGRESS MEETINGS
TRANSMITTALS
USE OF CONSULTANTS
DOCUMENT REVIEW AND APPROVAL RIGHTS
PROJECT SCHEDULE
IMPLEMENTATION SCHEDULE [LEVEL 2]
CONTRACTOR ACTIVITIES
THE ENGINEERS ACTIVITIES
DOCUMENTATION SCHEDULE
PROGRESS REPORTING
SUGGESTED PROGRESS REVIEW MEETING AGENDA
7
7
7
7
8
8
8
9
9
10
10
10
11
11
Page: 2 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
SECTION 1 - SCOPE
SCOPE
This technical specification should be read along with general terms and
conditions of the contract. This specification covers the general requirements as
listed below
The scope of the bid covers Engineering, Procurement and Execution of the
project on a turnkey basis. The bidder shall be responsible for the following.
(i)
Engineering design,
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
Reporting
(viii)
(ix)
2.
Handing over the works to the Employer for taking into commercial service,
Page: 1 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
3.
O&M MANUALS
Six sets of nicely printed bound volumes of operation, maintenance and erection
manuals and approved drawings in English language shall be supplied covering all
the equipment erected.
4.
GUIDE LINES
Some guide lines are given in the specification to facilitate planning for systematic
and expeditious execution of the project which is obviously of common interest
to both the Employer and the Contractor. Reference is specifically invited to
General terms and conditions of contract, which are to be observed strictly,
in the execution of the contract.
The Contractor has to carry out the execution of the works as per relevant
standards and codes of practice. Although some guide lines have been given with
regard to the execution of the works, it remains the responsibility of the
contractor to do the works complying to the specifications/statutory requirements
and to the satisfaction of the Engineer, conduct the need site check and tests
(apart from factory tests of materials and equipment) before and after energisation
and commissioning of equipment and lines into service before handing over to
the Employer for commercial operation.
The contractor shall always keep in mind that the entire project is being executed
on TURNKEY BASIS.
4.1
Page: 2 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
4.2
SERVICE CONDITIONS
The materials shall be for use in moderately hot and humid tropical climate
conducive to rust and fungus growth. The environmental conditions under which
materials and equipment shall be suitable for satisfactory continuous operation
are specified in Technical specification no. TS-GN-01, EEPCO system and
Environmental data.
4.3
SAFETY PRECAUTIONS
The contractor shall observe all applicable regulations regarding safety on the site.
Unless otherwise agreed, the Contractor shall from the commencement of work
on site until taking over provide,
(i)
(ii)
Temporary roadways, footpaths, guards and fences which may be necessary for
the accommodation and protection of owners and occupiers of adjacent property,
the public and others.
4.4
The scope shall cover complete installation of all equipment and accessories
covered under this contract
(ii)
(iii)
Installation shall be carried out strictly in accordance with the approved drawings.
Modifications, if any, required to suit site conditions, shall be carried out only with
the prior approval of the Engineer. All such changes shall be incorporated in As
built drawings to be furnished by the contractor.
(iv)
(v)
(vi)
(vii)
Should the specialist called for by the Engineer, if required, the contractor shall
bear the expenditure in full.
(viii)
The contractor shall ensure that the equipment under erection as well as the work
area and the site are kept clean to the satisfaction of the Engineer. In case, the
Engineer is not satisfied about the cleanliness, he will have the right to carryout
Page: 3 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
the cleaning operations and expenditure incurred by him in this regard will be to
contractors account. Packing cases and packing materials shall be cleared from
sites.
(ix)
(x)
Where assemblies are supplied in more than one section, the contractor shall
make all necessary mechanical and electrical connections between sections
including the connections between busbars / wires. The contractor shall also do
necessary adjustments, alignments necessary for proper operation.
(xi)
Care shall be taken in handling instruments relays and other delicate devices.
Where instruments and relays are supplied separately they shall be mounted only
after the associated switchgear/control panels are erected and aligned.
4.5
CONSTRUCTION WORKS
4.5.1
Approaches
The approaches to the location of work, if necessary, will have to be formed by
the contractor at his own cost and will be an access both for personal and
equipment.
4.5.2
4.5.3
4.5.4
Site Stores
The contractor shall establish temporary stores at his own cost at the substation
site for storing cement and equipment. The stores should be dismantled and site
cleared after the work is completed.
4.5.5
Cement
Cement shall conform to the relevant standard.
Page: 4 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
a)
The contractor has to make his own arrangements for the procurement of cement
to required specifications required for the works and shall make his own
arrangements for adequate storage of cement,
b)
The contractor shall procure cement in standard packing e.g., 50 Kg., bag or
drums,
c)
The contractor shall forthwith promptly remove from the works area any cement
that the Engineer may disallow for use.
d)
The contractor shall further, at all times satisfy the Engineer on demand by
production of records and books or by submission of returns and other proofs as
directed that the cement being used is tested and approved by Engineer for the
purpose and the contractor shall at all times, keep his records up to date to enable
the Engineer to apply such checks as he may desire.
e)
Cement which has been unduly long in storage with the contractor or alternatively
has deteriorated due to inadequate storage and thus become unfit for use in the
works will be rejected by the employer and no claim will be entertained. The
contractor shall forthwith remove from the work area, any cement the Engineer
may disallow for use on work and replace it by cement complying with the
relevant Indian Standards.
4.5.6
Wastage
The contractor shall keep the additional materials required to cover wastage and
ensure that his obligations of the contract are met. The cost of such wastage shall
be deemed to be included in the contract price.
5.
ENVIRONMENTAL POLICY.
Employer has high concern for clean Environment, Ecology and sustainable
development in its every activity of power transmission.
5.1
GUIDING PRINCIPLES
The guidelines indicated below should be followed.
a)
Avoid Right of Way (RoW) through environmentally and socially sensitive areas
to minimise environmental and social Impacts.
b)
5.2
ENVIRONMENTAL IMPACTS
Attention shall be paid to the following aspects.
a)
To avoid forests, plantations in the course of line routing, care is taken to route
through a path of minimum disturbance.
b)
c)
Page: 5 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
d)
5.3
Sl.No
Environmental impact
Mitigation Measures
Responsible for
implementation
Responsible
for
monitoring
Planning :
Impact on
environmental sensitive
areas such as forest
lands, wetlands, bird or
wild life sanctuaries, bird
habitats, culturally and
historically important
resources.
While selecting
ROW for lines
sensitive areas shall
be avoided. No
impact on sensitive
areas.
EEPCO
Engineer/
Contractor
EEPCO
Engineer
Power
EEPCO
telecommunication
Engineer/
coordination
Contractor
clearances are
obtained for the
lines. The protection
measures to telecom
lines are
EEPCO
Engineer
While selection of
ROW for lines
reserve forests are
avoided.
Involvement of
forests under
distribution lines is
nil.
Loss of human
habitation
Construction:
Erosion problems at
pole locations
Electrical interference to
telecom lines due to
induced EMF
Page: 6 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
implemented.
6
Electrocution hazards
due to public access
Standard Clearances
as per Electricity
Rules are
maintained.
Guarding is
provided at all road
crossings, telecom
and power line
crossings. Danger
boards are fixed
wherever necessary
Operation and
maintenance:
Way leaves clearance
Way leaves
clearance is carried
out manually
------
Foreign materials on
lines
Checked regularly
------
6.
EEPCO
Engineer
PROJECT MANAGEMENT
This section describes the project management, schedule, quality assurance,
documentation and implementation plan requirements for the project.
6.1
PROJECT MANAGEMENT
The Contractor shall assign a Project Manager with the authority to make
commitments and decisions that are binding on the Contractor. The Project
Managers responsibility shall include interface and co-ordination with the
EEPCO Engineer and his sub-contractor(s). EMPLOYER will designate an
Engineer to co-ordinate all project activities. All project correspondence and
communications between EMPLOYER and the Contractor shall be co-ordinated
through the Project Manager. The project shall be staffed from the list of project
management, engineering, system analysis, hardware and software personnel
presented in the proposal. Principal participants shall have previous experience in
a similar position on at least two other projects of similar scope to this project.
The assignment and reassignment of the principal participants in the project shall
be subject to EMPLOYERs approval.
6.2
REPORTING PERIOD
The Project Manager shall provide updated project schedules. and complete
progress reports on a monthly basis for the duration of the project. All references
to the reporting period throughout this Specification shall refer to this monthly
period. The format of report shall be as approved by the Engineer.
6.3
PROGRESS MEETINGS
The Project Manager shall schedule and attend Progress Meetings as necessary but
not less than once every month.
Page: 7 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
6.4
TRANSMITTALS
Every document, letter, progress report, change order, and any other written
electronic media transmissions exchanged between the Contractor and
EMPLOYER shall be assigned a unique transmittal number. Discussions and
phone calls where project related information is exchanged shall be documented
in a transmittal. The Contractor shall maintain a correspondence index and assign
transmittal number consecutively for all Contractor documents. EMPLOYER will
maintain a similar correspondence numbering scheme identifying documents and
correspondence that EMPLOYER initiates.
6.5
USE OF CONSULTANTS
EMPLOYER has utilized consultancy services in the development of the project
requirements and technical specifications for the project. No limitations shall be
imposed in EMPLOYERs use of consultants in any activity related to the project.
The consultants, at the discretion of the EMPLOYER/Engineer shall participate
in project activities and be accorded the same access to the Contractors facilities
as any member of EMPLOYERs project Engineering team. The involvement of
the consultants may include, but shall not be limited to, progress and technical
meetings, conference call, documents review, and system testing/validation.
EMPLOYER shall have the option of adding consultants to the transmittal
document distribution list to receive all or selected correspondence initiated by
contractor. The consultant will be bound by the same confidentiality restrictions
imposed in EMPLOYER personnel.
6.6
Page: 8 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
6.7
PROJECT SCHEDULE
The project schedule shall consist of an implementation schedule, and
documentation schedule.
A tentative project schedule shall be included with the Tender.[level one]
6.8
Within four weeks of contract signing, the Contractor shall submit a detailed
project schedule, as described below. The project schedule shall include all tasks
to track overall direction and integration of the project from inception through to
completion. The implementation schedule shall include the project section
milestones, the Contractor activities and the EMPLOYER activities. The project
schedule shall be an accurate representation of the progress and planned activities
of the project. Activities (other than at the Contractors premises) shall be
scheduled only on customary EMPLOYER working days, i,e Monday to Saturday,
excluding EMPLOYER holidays. The Contractor shall produce and maintain the
implementation schedule using commercially available project management
software with capabilities similar to those found in Project Schedule. Microsoft
Project is the preferred project management software. A copy of the
implementation schedule files on CD shall also be provided to EMPLOYER.
(ii)
(iii)
The actual progress made to date and the scheduled delivery date for the major
plant items and the scheduled date for the completion of works shall be closely
monitored by the Contractor.
The following information shall be reported to Project Manager and Engineer in a
clear and concise manner using the tabular and graphic capabilities of the selected
project management software.
(ii)
Any change in the estimated dates since the last reporting period.
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
Page: 9 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
The content and format of the project schedule shall be subject to Engineers
approval. The Contractor shall update and submit the project schedule to
Engineer at least one week prior to each progress meeting.
6.9
CONTRACTOR ACTIVITIES
The implementation schedule shall be compiled by the Contractor summarizing
all activities and shall include but not be limited to the following.
(i)
(ii)
(iii)
(iv)
Shipment.
(v)
(vi)
Installation
(vii)
Field testing.
(viii)
Commissioning
Each scheduled task shall have an estimated duration for completion and
predefined relationships with other tasks. Relationships shall be used to enforce
the logical progression of work in as much as certain tasks cannot start until
others have been completed.
6.10
6.11
(i)
(ii)
(iii)
DOCUMENTATION SCHEDULE
The documentation schedule shall include an entry for each document and
drawing to be delivered throughout the project. Each documentation schedule
entry shall include the document or drawing title, number, revision level, actual or
future submittal date for Engineers review or approval, date of completion of
review or approval by Engineer and outcome of review or approval by Engineer.
When Engineer requires correction to any document, the documentation schedule
shall be upgraded with a new entry for the next revision of the document. The
content and format of the documentation schedule shall be subject to the
Engineers approval. The documentation schedule shall allow for at least two
submissions of each document requiring review or approval of the Engineer shall
be allowed a minimum of thirty calendar days for document review or approval.
Page: 10 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
6.11.1
Drawings
All drawings shall be no larger than A3 (B size) and shall be reproduced by
Xerographic or offset lithographic technology. All drawings shall be be given in
AUTOCAD.
6.11.2
Documents
The documents shall be written in grammatically correct English to understand
clearly. Manuals and other written documents shall be legibly printed on sheets of
standard A4 format and all shall be bound. The final versions of documents and
manuals shall be copied double-sided, review copies may be copied single-sided.
Double spaced lines are required in review and final documentation. A complete
table of contents, listing all numbered sections and the corresponding starting
page numbers, shall be included for each document. A complete identical table of
contents shall be provided in each volume of a multi-volume document. A
complete list of exhibits shall follow the table of contents. A dictionary of
acronym terms shall be included with each set of documents. An index shall also
be included with each document. Where a document is revised to reflect a change
in design, or a change for any other reason, each such revision shall be shown by a
revision number, date, and subject in a revision block, indication of official
approval by the Contractors Project Manager shall also be included. To permit
rapid location of the revisions, all changes shall be highlighted on the revised
pages of the document. Such highlighting shall be removed from the final version
of documents.
6.12
PROGRESS REPORTING
With the intent to assure quality management and project progress as per the
implementation schedule, progress reports submitted for each reporting period
and Progress Review Meetings shall focus on the following.
a)
b)
Progress review meetings shall be scheduled by the project managers and attended
by the Contractor, the Engineer and EMPLOYER to review progress of the
project. Progress meetings shall be used to review the progress reports for the
previous reporting periods, written correspondence exchanged since the last
meeting, and open action items.
c)
d)
6.13
Sl.No
Description
Page: 11 , 28-Apr-13
SPECIFICATION TS-GN-03
EEPCO
Meeting minutes
Progress review
Technical discussion
Action items
Administrative matters
Next meeting
Close
Close meeting
Page: 12 , 28-Apr-13
EEPCO
SPECIFICATION
TS-GN-05
Street light materials
SPECIFICATION TS-GN-05
EEPCO
Date
Brief Description
Rev 0
12 Dec 2012
Rev 1
Feb 2013
Rev 2
May 2013
Rev 3
June 2013
Page: 1 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
STREET LIGHT MATERIALS
0
1.
SCOPE
0
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
0
3.
REFERENCE STANDARDS
0
3.1
CONFLICT:
4.
4.1
TESTS
5.
DESIGN
5.1
5.2
5.3
DEFINITIONS
SODIUM VAPOUR LAMPS
MARKINGS
2
3
3
6.
6.1
6.2
6.3
6.4
6.5
6.6
FIXTURE
GENERAL CONSTRUCTION OF STREET LIGHT LUMINAIRES
MOUNTING
ELECTRICAL REQUIREMENTS
PHOTOMETRIC PERFORMANCE OF STREETLIGHT LUMINAIRES
MARKING
3
3
3
7
8
8
7.
8.
INSTALLATION
CONTACTOR
8
8
8.1
8.2
REQUIREMENTS
MARKINGS
8
9
9.
9.1
9.2
REQUIREMENTS
MARKINGS
9
9
10.
11.
DELIVERY
SCHEDULES
9
9
11.1
11.2
11.3
10
10
11
Page: 2 , 27-Jun-13
SECTION 1 - SCOPE
SPECIFICATION TS-GN-05
EEPCO
SCOPE
This specification defines the technical characteristics of Street lights and the
associated materials and equipment for the street light system.
Street lighting luminaires are used for the lighting of public thoroughfares and
roadways, contributing to road safety as well as public safety. The reliability and
safety of these luminaires have a direct impact on levels of customer satisfaction
as well as quality of supply.
Luminaires shall be delivered completely assembled with control gear, high
pressure Sodium Vapour lamp(250W /400W), lamp holder, reflectors, diffuser
(bowl) housing
In addition this specification defines the requirements for Electromagnetic 3-pole
three-phase contactors photoelectric control switch to be installed at the
transformer stations supplying the street light conductors.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
Specification/
Title
Standard Number
IEC 60061
Lamp caps for holders together with gauges for control of
interchangeability
IEC 60662
High pressure Sodium Lamps
IEC 60459
Ballast for high pressure Sodium lamps
IEC 60144
Degree of protection of enclosures of low voltage
switchgear and controlgear
IEC 60598
Luminaries for Roads and street lights
IEC 60188
Design and testing of lamps
SANS 475:2006
Luminaires for interior lighting, street lighting and
floodlighting - Performance requirements
ARP 035: 2005
Guidelines for the installation and maintenance of street
lighting
SANS 1088: 2004 Luminaire entries and spigots
SANS 1250: 1991 Capacitors for use with fluorescent and other discharge
lamp ballasts
SANS 1266: 2002 Ballasts for discharge lamps (excluding tubular fluorescent
lamps)
SANS 1574: 2004 Electrical cables flexible cords and flexible cables
SABS IEC
Ballasts for discharge lamps (excluding tubular fluorescent
60923:2001
lamps) Performance requirements
Page: 0 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
SABS IEC
926:1995
SABS IEC
60927:2005
SANS 529: 2001
SANS 1507: 2002
3.1
CONFLICT:
See spec TS-GN-01
4.
4.1
TESTS
The test reports shall be issued by an SANS or IEC accredited test authority.
4.1.1
a)
Type tests
The tests for ingress of dust, solid objects and moisture shall be carried out in
accordance with section 9 of SANS 60598-1 and clause 3.13 of SANS 60598-2-3.
Test reports confirming that the tests have been carried out as prescribed shall be
the only acceptable verification of IP ratings.
Note: In accordance with the test requirements of the above documents, the
luminaire shall be energised and brought to a stable operating temperature
(thermal equilibrium) at its rated voltage before commencement of the tests.
Test reports shall have been issued by SABS or a test authority accredited by
SANS.
Tests as described in clauses 3.6.3 through 3.6.5 and clauses 3.7 through 3.15 of
SANS 60598-2-3 shall be carried out and the test reports shall be supplied with
the Bid.
b)
Page: 1 , 27-Jun-13
SECTION 5 - DESIGN
SPECIFICATION TS-GN-05
EEPCO
1.No signs of material degradation
2.No cracks on any part of the luminaire; and
(ii)
(iii)
(iv)
Thermal tests
(v)
(vi)
(vii)
Photometric requirements
(viii)
Resistance to corrosion
(ix)
(x)
(xi)
5.
DESIGN
5.1
DEFINITIONS
The following definitions and abbreviations shall apply to this specification:
Socket (NEMA base): A receptacle into which a one-part control unit may
be inserted.
(i)
Luminaires shall be Class 1 as per SANS 60598-1 and shall be of totally enclosed
type.
(ii)
Luminaires shall have a high pressure Sodium vapour lamp, control gear and
spigot compartment and shall have a degree of protection rating of a minimum of
IP65 on the lamp compartment and a minimum of IP54 on the control gear
compartment.
Page: 2 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
5.2
5.2.1
REQUIREMENTS
Rated wattage.............................. 250 and 400 W
Rated voltage...........................
230 V
The lamp cap shall meet the requirement of IEC 60061 or equivalent standards.
The lamp will be used with ballast conforming to IEC 60459.
The Sodium vapour lamp shall be used with a lamp cap in a Street fixture meeting
the requirements mentioned in the relevant IEC.
5.3
MARKINGS
The marking on the lamp shall be in accordance with the IEC 662.
6.
6.1
FIXTURE
6.2
6.2.1
General
a)
Luminaires shall be robustly constructed, weather proof, hail proof, insect proof,
corrosion proof, and vandal resistant and made of LM6 high pressure die cast
Aluminium .
b)
All external parts and components of the luminaire shall be designed to shed
water and no accumulation of condensation or precipitation shall occur. An
exterior lip shall be provided on the housing to ensure that there is no direct
rainwater contact with the gasket between the housing and the diffuser, thus
ensuring that no moisture is sucked into the diffuser when the luminaire is
switched off and cools down.
c)
6.3
MOUNTING
6.3.1
General
(i)
Spigot entries shall be designed to fit easily over the bracket pipe and shall be truly
parallel to the fitting axis and shall comply with Table 1 of SANS 101088:1990 as
follows:
The luminaries and its 300 mm long shaft shall resist dynamic wind pressure
of 230N/m2 with a load safety factor of 1.4. There shall be provision for
draining of condensed water from the body.
Page: 3 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
(ii)
Spigot entries shall be designed to fit easily over the spigot and shall be truly
parallel to the fitting/lamp axis. Spigot entries shall be constructed of corrosionresistant materials and compatible with the galvanized mild steel spigot such that
deterioration by electrolytic action shall not occur.
(iii)
Luminaires shall be secured to the spigot by means of at least two stainless steel
M10 hexagonal head screws..
(iv)
6.3.2
Diffusers
(i)
Diffusers shall have no external prisms that could accumulate dirt and thus reduce
the light output of the luminaire. Diffusers shall be constructed in such a manner
that the wall thickness of the material is maintained at a constant thickness, hence
preventing the projection of lines of patterns onto the road surface.
(ii)
Diffusers shall be heat-resistant and shall not discolour, even after prolonged
exposure to light, both atmospheric and artificial. The mechanical strength shall
be sufficient to prevent warping or distortion to occur. Diffusers shall be
manufactured from injection moulded high impact acrylic. Bidders shall submit
documentation with respect to the properties of the material under service
conditions (i.e. Depreciation in light transmission over time and material
degradation). Diffusers made of polycarbonate shall not be acceptable.
(iii)
Diffusers shall have a means to prevent direct contact by rainwater with the onepiece gasket, which shall be permanently fitted into the housing (e.g. in a tongue
and groove arrangement). The gasket shall form a seal when the diffuser is in the
closed position, preventing the entry of dust, moisture and insects into the lamp
compartment. The gasket shall be made from silicon sponge, which shall not be
subject to permanent compression or deterioration in service. The gasket should
be fitted into a groove in the housing and should be kept in place by a tongue
provided on the diffuser, thus ensuring the integrity of the IP rating and shall not
work loose during maintenance of the luminaire.
(iv)
Luminaire bowls shall be capable of being removed from the luminaire body
simply by unclipping for cleaning purposes. The bowl shall not detach from the
luminaire body in the unlikely event of the bowls being left in the open or hanging
position when mounted on the pole. The diffuser should also remain attached to
the housing when hinged open for maintenance or lamp replacement. This hinge
mechanism should be incorporated into housing to ensure that it is protected
against damage during transport, installation and maintenance.
6.3.3
Lamp-holders shall comply fully with VC 8011(Standard) and be of the type E40,
and shall be capable of maintaining efficient electrical contact with the lamp
terminals without deterioration due to temperature, climatic conditions and
vibration which will be encountered in service.
Page: 4 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
(ii)
For additional insulation against ignitor spark-over a suitable fibre washer for
lamp holders shall be used.
(iii)
(iv)
A lamp fully inserted into the lamp-holder shall be rigidly held with its axis
substantially coincident with that of the lamp-holder under conditions of wind,
vibration and mechanical shock to be expected in service.
(v)
The lamp-holder shall have zero degree rake i.e. its axis shall be parallel to that of
the spigot entry.
(vi)
Lamp holder brackets and lamp supports shall accept and retain lamps which are
within the dimensional tolerances stated in the appropriate lamp standard and
shall locate the light source in the correct relationship to the optical control
devices of the luminaire. The lamp holder shall be mounted firmly to an
aluminium bracket.
Alternatively the lamp holder is to be mounted directly onto aluminium bosses,
which protrude into the lamp housing from the gear compartment.
6.3.4
Reflectors
(i)
(ii)
Reflectors or any other light-controlling component shall be such that they can
only be fitted or replaced in the correct relationship to their light source.
(iii)
Reflectors in luminaire bowls shall not deform due to heat from the lamp.
Reflectors shall be well secured into position to prevent it from deforming thus
causing false photometric performance of the luminaire.
(iv)
Where provision is made for alternative reflector positions, the adjustment means
shall be positive and be firmly retained in clearly identified positions.
6.3.5
Control Gear
(i)
Control gear shall be fully housed within the body of the luminaire and be
suitable for operation with the specified rating of lamp. Under no circumstances
shall control gear be mounted above the lamp or in a position where it may be
adversely affected by the heat generated by the lamp.
(ii)
For safety and thermal reasons, the control gear compartment shall be
manufactured from a sturdy and reliable housing of high-pressure die cast,
corrosion resistant, aluminium of grade LM6 (EC1706 AC 44100), or higher
(iii)
The control gear compartment shall be so designed that there is sufficient space
to permit repairs, replacement of components and reassembly without difficultly,
without the removal of the luminaire from its mounting. To this end, and for
maintenance reasons, preference will be given to luminaires where all control gear
is mounted onto a removable tray. Where this is provided, removable connectors
are required for disconnecting the supply to the tray for easy removal and
subsequent replacement. Control gear wiring is to be terminated in a five-way
termination block to facilitate the removal of the gear tray in the control gear
compartment.
Page: 5 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
(iv)
(v)
(vi)
All control gear shall be suitable for operation with the specified rating of the
lamp on a 230V 10% 50Hz single-phase system.
6.3.6
Ballasts
(i)
Ballasts shall comply with SANS 1266, SABS IEC 922 and SABS IEC 60923 and
shall bear the SABS mark or IEC mark.
(ii)
(iii)
6.3.7
Capacitors
(i)
Capacitors shall comply with SANS 1250, SABS IEC 61048 and SABS IEC 61049
and shall bear the SABS mark or IEC mark.
(ii)
(iii)
All capacitors shall be fully encapsulated and filled with self-extinguishing resin.
6.3.8
Ignition Devices
(i)
Ignitors shall comply with SANS 101630 and shall bear the SABS mark or IEC
mark. Ignitors shall be of the superimposed-pulse solid-state electronic trigger
type.
(ii)
Ignitors shall be of the standard type to allow striking of the lamp without
switching the power off after replacement of a faulty ignitor.
(iii)
Ignitors shall be suitable for operating any make of lamp in conjunction with any
make of ballast at temperatures up to 90 C. The ignitor shall be connected in
series with the ballast and installed between the ballast and lamp holder. Systems
that operate with the ignitor in parallel with the lamp, or with special tapped
ballasts, will not be acceptable.
Page: 6 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
(iv)
6.4
All ignitors shall be suitable for connection in the circuit so that the ignition pulse
is confined between the ignitor and lamp holder.
ELECTRICAL REQUIREMENTS
(i)
All Internal wiring of the luminaires shall comply with clause 3.10 of SANS
60598-2-3.It shall be flexible and suitably rated and insulated to withstand the
voltages and temperatures encountered in service. All wiring shall comply with the
requirements of SANS 1507 and, where applicable, SANS 529. The wiring colours
to be used shall be as follows: live - red (or brown), neutral black (or blue) and
earth green/yellow.
(ii)
The neutral conductor of the incoming supply shall be connected to the screw
thread portion of Edison screw type lampholders and the live conductor shall be
connected to the central contact and the internal wiring shall be arranged
accordingly.
(iii)
Terminals and electric connections shall comply with clause 3.9 of SANS 605982-3. In addition, the luminaire shall incorporate a terminal block mounted in a
reasonably accessible position as close to the point of entry as possible. The
material of the terminal block shall be non-tracking and the terminals shall be
made of non-corroding material such as brass. Terminals made of aluminium shall
not be acceptable.
(iv)
Any wiring passing through metal shall have suitable grommets or otherwise
protected to avoid abrasion of the insulation.
(v)
(vi)
Metal parts of luminaires which may become alive in the event of an insulation
fault and which are not accessible, when the luminaire is mounted, but which are
liable to come into contact with the supporting surface, shall be permanently and
reliably connected to an earth terminal and shall withstand the test specified in
SANS 60598-2-3. An earth terminal shall be provided in all instances, even if the
luminaire is fully insulated and even if all conductive parts, which could become
alive in the event of an insulation fault, are not accessible. This is to facilitate
future wiring should a unit, which requires an earth connection, replace the
luminaire.
(vii)
Protection against electric shock (of at least IP 2X) shall be maintained for all
methods and positions of installation in normal use. Protection shall also be
maintained after removal of all parts that can be removed by hand.
(viii)
(ix)
All earth connections shall be effected by means of suitable lugs. All possibility of
electrolytic corrosion shall be avoided.
(x)
The luminaire shall be able to be supplied with the following optional extras:
(xi)
A flat glass or shallow diffuser option for very specific light sensitive areas.
(xii)
A bottom entry casting, incorporated into the spigot compartment and not
attached as a side entry.
Page: 7 , 27-Jun-13
SECTION 7 - INSTALLATION
SPECIFICATION TS-GN-05
EEPCO
6.5
6.6
Photometric data shall be supplied with the tender. This data shall be issued by
the SABS or SANAS accredited lighting laboratory. The photometric
requirements as listed in SANS 475, Clause 4.7.1.1, shall be provided.
(ii)
MARKING
The marking on the fixture shall be in accordance with the relevant IEC or
equivalent standard.
7.
INSTALLATION
The fixtures shall be mounted on concrete poles with the following dimensions.
Maximum pole top diameter
7-9m
8.
CONTACTOR
Contactors will be utilised and associated with each transformer supplying the
street light system, together with the photoelectric switch described later.
8.1
REQUIREMENTS
The contactors shall meet the following requirements:
Rated thermal current
125 A, 200 A
230V
Utilization category
AC - 1
230 V
Rated frequency
50 Hz
Mechanical endurance
Page: 8 , 27-Jun-13
SPECIFICATION TS-GN-05
EEPCO
8.2
MARKINGS
The contactors shall be marked according to IEC 158 or equivalent standard.
9.
9.1
REQUIREMENTS
Rated voltage
230 V
Rated current
10 A
Rated frequency
50Hz
6 kV
2kV
>=IP54
3 70 lux
Terminal shall be suitable for copper conductors. The switch shall be equipped
with a connecting cable. Connecting cable shall be made of multi-core stranded
copper of at least 1.5 mm2 cross section. Connecting cable must have black,
weather-resistant sheath. The length of the cable shall be at least 1.5m.
The light sensitiveness of the switch shall be adjustable. The switches shall be
adjusted to sensitiveness of 10 lux before dispatch from the manufacturers works
in case such an adjustment is tedious to do in operation. The switch shall have a
delay mechanism against nuisance switching e.g. due to sudden darkness.
Preference shall be given to switches integrating the sensitive part and the
switching part.
All plastic parts shall be weather-resistant.
9.2
MARKINGS
Switches shall be marked with the name or trademark of the manufacturer and the
rated voltage and current.
10.
DELIVERY
The photocell shall be delivered complete with connection cable, mounting
bracket and fixing screws ready for installation on concrete poles.
11.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
Page: 9 , 27-Jun-13
SECTION 11 - SCHEDULES
SPECIFICATION TS-GN-05
EEPCO
11.1
11.2
Page: 10 , 27-Jun-13
SECTION 11 - SCHEDULES
SPECIFICATION TS-GN-05
EEPCO
11.3
Page: 11 , 27-Jun-13
LPA-GECE
EEPCo
Item
Manufacturer
Country of Origin
Type designation
Standard referred
Rated wattage
Nominal life, hours
Rated voltage
Warm-up lamp current as a percentage
of rated current
Warm-up
voltage at lamp terminal
Operating noise of ballast
Warm-up time
Compensated Lamp current
Minimum open circuit voltage for
Stable
Power operation
factor with reference to ballast
Illumination
Rated luminous flux, lumen
Lamp external diameter
Lamp total length
Standard package size, pcs
Unit
W
hrs
V
%
V
db
min
A
V
lm/m2
lm
mm
mm
pcs
400W
IEC 662
250
24000
230
1.3
125V
<40
4.5min
3
200 V
0.43
>=60
Min.30000
IEC 662
400
24000
230
1.3
125V
<40
4.5min
4
200 V
0.43
>=77
Min.50000
LPA-GECE
EEPCo
Item
Manufacturer
Country of origin
Type designation
Standard referred
Rated wattage
Rated voltage
Length of luminary shaft
Tolerance of material thickness
Wind area of the luminary
Power factor with rated wattage
Lamp holder size
Capacitor size
Material of REFLECTOR
Material of body
Length of wire
Cross-section of wire
Protection class (IEC 144)
Thickness of zinc coating
Weight of complete luminaries
Requirement
W
V
mm
%
SANS475/2006
250 or 400
230
300
0.05
m2
%
F
m
mm2
m
kg
Bid Offer
>90%
E-40
>=30
Corrugated
Aluminum
High pressure
3diecast LM6
Sufficient to carry
rated
IP54- current
IP66
>=45
LPA-GECE
EEPCo
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
Item
Manufacturer
Country of origin
Rated operational current
Type designation
Standard referred
Protection class
Utilization class
Power dissipation with thermal Current
Rated frequency
Rated operational voltage
Rated insulation voltage
Rated thermal current
Rated making current
Rated breaking current
Maximum fuse protecting (HRC, DIN)
Short circuit current Carrying capacity, 1s
Coil control voltage, AC
Drop-out voltage in percentage of rated control voltage
Can the coil be replaced?
Number of normally open auxiliary contacts
Permissible operation frequency per hour
Electrical life of contacts
Unit
23
cycles
24
Mounting arrangement
Requirement
Bid Offer
Requirement
Bid Offer
W
Hz
V
V
A
A
A
A
kA
V
%
Yes/No
IEC 158-1
IP20
AC-1
90
50
230/400
1.2 kV
125
IEC 158-1
IP20
AC-1
132
50
230/400
1.2 kV
200
230
230
Yes
Yes
600,000
700,000
hrs
LPA-GECE
EEPCo
No
25
25.1
Item
Main circuit terminals
Material
25.2
25.3
25.4
Design
Conductor range
Terminal screw size
26
Unit
Requirement
Bid Offer
Requirement
Copper
Copper
6mm2 up to 70mm2
6mm2 up to 70mm2
Copper
Copper
27
28
PVC or other
equivalent materials
PVC or other
equivalent
materials
29
30
mm2
Bid Offer
kg
LPA-GECE
EEPCo
Item
Manufacturer
Country of origin
Type designation
Standard referred
Time constant of switching
Light sensitiveness adjustment range
Rated voltage
Rated insulation voltage
Rated current
Rated breaking capacity
Rated marking capacity
Power frequency withstand voltage
Impulse withstand voltage
Number of mechanical operating cycles
Number of electrical operating cycles
Protection class (IEC 144)
Connecting wire cross-sectional area
Material of contacts
Color of cover
Standard package size
Net weight
Unit
Sec
lux
V
V
A
A
A
kV
kV
1 sec
3 70 lux
230
230V
10A
10A
10A
3
6
mm
pcs
g
>=IP54
min 1.5
Silver
200 g
EEPCO
SPECIFICATION
TS-GN-06
SPECIFICATION TS-GN-06
EEPCO
Date
Brief Description
Rev 0
20 May 2013
First Issue
Rev 1
6 June
Revision of scope
SPECIFICATION TS-GN-06
EEPCO
CONTENTS
DESCRIPTION
1.
PAGE NO
INTRODUCTION .............................................................1
1.1
2.
2.1
2.1.1
Control Centre Equipment -- One control centre with equipment
listed for each Town in the lot........................................................................ 4
2.1.2
Feeder Remote Terminal Units (F RTUs) ......................................... 5
2.1.3
Electronic Trivector Meters ............................................................... 5
2.1.4
Radio Links ....................................................................................... 6
2.1.5
Training ............................................................................................. 6
3.
4.
5.
GENERAL REQUIREMENTS............................................................. 19
Servers ............................................................................................... 19
Workstations ....................................................................................... 21
Monitors .............................................................................................. 21
Front-End Servers .............................................................................. 21
Large Scale Display System ............................................................... 22
Printers ............................................................................................... 22
Networks ............................................................................................ 23
SPECIFICATION TS-GN-06
EEPCO
6.
7.
8.
DATA ACQUISITION.......................................................................... 33
Data Conversion ................................................................................. 34
Dynamic Network COLOURING and Circuit Tracing .......................... 35
Data Processing ................................................................................. 36
Supervisory Control ............................................................................ 38
Alarms and Events Processing ........................................................... 39
Tagging .............................................................................................. 42
Disturbance Recording and Play-back ............................................... 43
Historical Data Management .............................................................. 43
Data Communication with Other Control CENTRES .......................... 44
POWER Distribution Network Information System (NIS) .................. 45
FRTU .............................................................................45
8.1
8.2
8.3
8.4
8.5
8.6
8.7
8.8
General............................................................................................... 45
COMMUNICATION PORTS ............................................................... 46
ANALOGUE INPUTS ......................................................................... 47
STATUS INPUT.................................................................................. 48
SEQUENCE OF EVENTS (SOE) FEATURE ..................................... 48
CONTROL OUTPUTS ........................................................................ 48
CONTACT MULTIPLYING RELAYS (CMRs) ..................................... 50
TIME FACILITY .................................................................................. 50
SPECIFICATION TS-GN-06
EEPCO
11.5
11.6
GENERAL .......................................................................................... 59
SYSTEM DOCUMENTATION ............................................................ 60
EquipmentDocumentation .................................................................. 60
OPERATING AND MAINTENANCE MANUALS................................. 61
ADDITIONAL INFORMATION ............................................................ 61
INTRODUCTION ................................................................................ 62
SCADA MAINTENANCE TRAINING .................................................. 62
RADIO LINK MAINTENANCE TRAINING .......................................... 62
OPERATOR TRAINING ..................................................................... 63
SPECIFICATION TS-GN-06
SECTION 1 - INTRODUCTION
EEPCO
1.
INTRODUCTION
This technical specification is for the implementation of SCADA & DMS facility
for Monitoring and Control of 15 kV MV network in 7 towns namely Mekele,
Bahir Dar, Dessie, Nazareth, Dire Dawa, Jimma, Awassa, of Ethiopian Electric
Corporation under 8 Town Distribution Rehabilitation project
The 8 Town Distribution Rehabilitation project financed by the World Bank
under IDA credit No. IDA 5126-ET.The project Network design and bid
documents are developed by the consultants London power associates, in
association with Global Energy Consulting Engineers India and Hagbes, Ethiopia.
The consultant will also be responsible for supervising together with the EEPCo
authorities for Project Implementation.
The Project is subdivided into three lots as follows.
LOT -1: Design, supply, installation on site, testing and commissioning of a
section of LV distribution network rehabilitation, respective distribution
transformer rehabilitation in Addis Ababa city, No SCADA and DMS component
in LOT 1.
LOT -2 : Design, supply, installation on site, testing and commissioning of a) MV
Overhead line & Under Ground cables, b) Installation of new distribution
transformers c) Installation of LV ABC network and d) removal of existing lines
in Mekele, Bahir Dar and Dessie, d) SCADA &DMS System for Mekele, Bahir
Dar and Dessie
Lot-3: Similar to Lot 2 but for the cities of Nazareth, Dire Dawa, Jimma, Awassa.
The bidders can submit offers for one or two or three lots. The SCADA &DMS
component is an integral part of Lot 2 and LOT 3. Separate Bid for SCADA
&DMS alone is not permitted
1.1
Description
item
of Dessie
Mekele
Bahir-Dar
Total
Area of Town
sq.km
34.4
78.3
46.5
159.2
Population of
Town
185745
273528
272757
732030
Location of
town
132 kV or 66kV
/15 kV
SPECIFICATION TS-GN-06
SECTION 1 - INTRODUCTION
EEPCO
substations
5
15 kV feeders
10
19
15 kV line length
km
178.03
315.74
259.05
752.82
15 kV /400Volts
Distribution
Transformers
245
410
400
1055
15 kV Ring main
switch boards
12
15 kV Automatic
Sectionalizers
14
22
10
15 kV Switched
capacitors
10
30
43
83
11
15 kV Automatic
Voltage Boosters
12
15 kV
autoreclosers
13
15 KV
substation feeder
circuit breakers at
132 kV or 66
KV substations
10
19
15 kV
transformer
Circuit Breakers
at 132 kV or 66
KV substations
14
Description
item
of Nazret
Area of Town sq
.km
Population of
Town
Location of town
Jimma
Dire-Dawa
Awassa
65.0
29.2
32.2
44.4
271500
149132
386464
350143
8.55N
39.27E
740N
3650E
Total
170.8
1157239
SPECIFICATION TS-GN-06
EEPCO
4
132 kV or 66kV
/15 kV
substations
15 kV feeders
12
26
15 kV line length
km
223.09
83.89
232.25
345.82
885.05
15 kV /400Volts
Distribution
Transformers
402
168
356
408
1334
15 kV Ring main
switch boards
18
15 kV Automatic
Sectionalizers
11
10
15 kV Switched
capacitors
22
21
26
76
11
15 kV Automatic
Voltage Boosters
12
15 kV
autoreclosers
13
15 KV
substation feeder
circuit breakers at
132 kV or 66 KV
substations
12
26
15 kV
transformer
Circuit Breakers
at 132 kV or 66
KV substations
14
2.
SCOPE OF WORK
The scope of supply of the Contractor - as defined in this section of the Tender
Documents shall include all equipment and software required to ensure
satisfactory operation of the systems and facilities. All materials, parts, devices and
services that are essential or necessary for the proper functioning of the complete
installations shall be supplied, even if not explicitly called for.
In addition to supply of equipment and software the Contractor shall provide:
SPECIFICATION TS-GN-06
EEPCO
Procurement services
Manufacturing services
Documentation
Training services
2.1
SYSTEM FACILITIES
All systems and facilities defined hereafter shall be provided in strict accordance
with the technical specifications. However, the drawings enclosed to the Tender
Documents are tentative only and prepared for sole purpose of illustrating the
Scope of Supply. The Contractor shall be responsible for the final design, subject
to approval by the Employer.
Before starting the design work, the Contractor shall visit the Sites of this contract
to obtain all necessary information, drawings and documents for radio link path,
adaptation and modification engineering. The cost of the site survey shall be at the
Contractors expense.
All temporary offices, housing facilities, plants and equipment as well as other
temporary structures and works, which will be used or needed for the
performance of the works, shall be considered part of the contract.
Moreover, the Contractor shall provide all the tools, machinery, testing equipment
and other required auxiliaries as well as consumables necessary for proper
implementation of the works.
2.1.1
Item
Qty
Description
SCADA server with dual Xeon Processor of 2.5 GHZ or more 5x1 TB
hard Disk with Raid, and 2 x500 GB Internal Disk drive, 512 GB Ram in
Hot standby mode, Windows 2012 Server 10 cal License
SPECIFICATION TS-GN-06
EEPCO
Web Server .
11
12
1 set
13
2 set
UPS
14
2 set
10
2.1.2
2.1.3
SPECIFICATION TS-GN-06
EEPCO
2.1.4
Radio Links
The bid shall include radio links from the Control Centre to the FRTUs installed
on Distribution network. The bid shall include an antenna tower of height 30 m,
guyed type, to Control Centre Site. The bid shall include a steel tube of height 5 m
for antenna installation at RTU Sites. Cables
The bid shall include cables for Plant Adaptation, Radio Links, Power supplies,
etc. The Bidder shall assess the required lengths during the compulsory site visits
arranged in connection with the compulsory pre-bid meeting.
2.1.5
Training
The bid shall include the training packages specified in Item 13. Training
3.
3.1
3.1.1
Environmental Conditions
The environmental conditions for Control Centre sites and substations are:
3.1.2
The voltage tolerance of all the equipment not supplied from the UPS shall be as
follows:
SPECIFICATION TS-GN-06
EEPCO
The voltage tolerance of all the equipment, e.g. RTUs and Radio Link terminals,
supplied from 48 V DC systems shall be:
3.2
Nominal voltage 48 V DC
Positive on earth
3.3
SYSTEM ARCHITECTURE
The proposed
in Appendix -2
3.4
SPECIFICATION TS-GN-06
EEPCO
3.5
3.6
MAINTAINABILITY
The supplied system shall involve, with reference to maintenance, the following
minimum features:
a comprehensive and detailed set of alarms to alert operation staff and identify
any malfunction within the system,
SPECIFICATION TS-GN-06
EEPCO
3.7
3.7.1
General Requirements
It is a fundamental requirement that the System (and individual items of
equipment within it) shall be designed for high reliability and that hardware and
standard existing software used within the System should have been proven in
service.
The System availability shall be at least 99.95%, assuming an 8-hour Mean Time
To Repair (MTTR) for equipment at the Control Centre. This figure includes
availability of all critical functions that is the SCADA functions (Historical Data
Management function not included) and all the Real-time Network Analysis
applications.
The following facilities are the minimum that shall be available with this
probability:
All real time functions for which the system is designed, including:
Data acquisition, without the compilation of historical data records
Supervisory controls
The availability of the system shall be confirmed by the fact of record of past
experience in delivering control systems delivered to Electric Utilities.
3.7.2
AVAILABILITY CALCULATIONS
Theoretical and practical figures used for this calculation shall be given in the
Tender Schedules for the reliability of each individual unit of the System in terms
of Mean Time Between Failures (MTBF). Reliability figures of existing equipment
shall be supported by evidence from operational experience at similar types of
installation.
Calculations for the availability of the System shall be included in the Supplier's
offer.
These calculations shall be based upon the MTBF data of items of equipment and
a MTTR data stated above.
SPECIFICATION TS-GN-06
EEPCO
From those data, the unavailability of each sub-system shall be calculated taking in
account each item redundancy. The global availability shall then be calculated
from those different unavailability data. This calculation shall lead to the failure
probability and equivalent global MTBF data for the control centre system.
The overall assessment of System availability shall be provided in the form of an
overall System block diagram with each main item shown, complete with its
reliability data. The calculation of overall availability shall be provided with this
diagram.
3.7.3
Availability Evaluation
The availability data will be collected on site by the Employers personnel and his
representative for each component of the control system during the availability
test period of one month.
The results of the availability calculations will govern the delivery of the relevant
Acceptance Certificates.
For each of these components the number of` outages will be counted. Outage
time will be calculated as follows:
The time required for spare part procurement, on-site delivery and installation
is not taken into account.
With each failure, regardless of whether or not it causes an outage, the
Employer staff will troubleshoot and Supplier will be immediately advised
thereof. Supplier's staff shall then diagnose and repair. If the failure did cause
an outage, the total repair time (diagnosis time plus actual repair time plus time
to put function back in service) will be counted as outage time.
All outage time will first be counted but if it can be proven to be caused by
hardware or software not of Supplier's supply, it will then be deducted.
For each deducted or excluded outage time, the same amount of time will be
deducted from the cumulative period.
Only outages on critical function will be cumulated as downtime.
3.8
SPECIFICATION TS-GN-06
EEPCO
3.9
PERFORMANCES
According to the Distribution Network size and to the operating scenarios, the
system shall answer the performance requirements stated hereunder.
The provider shall demonstrate its ability to reach the performance requirements.
Performance tests shall be carried out during the Factory Acceptance Tests.
3.9.1
Computer Start Up
Total time for the start-up of a computer, including automatic program load,
initialization and database updating, shall not exceed five minutes for critical
functions (SCADA, front-ends servers). Automatic restart following a power
outage shall also not exceed five minutes.
Complete SCADA functionality shall be available within a further five minutes
following a start-up or automatic restart of the last computer in the minimum set
of computers required to be running to support this functionality. Updates from
RTUs may extend beyond this time but the full update of the System with data
from the field shall not exceed a further five minutes. Thus, a complete restart of
the System, including full update from the field, shall not exceed 15 minutes.
3.9.2
Transfer of Operation
No operational feature of the SCADA System shall be unavailable for more than
30 seconds at any time due to the transfer of operation from one processor to
another following processor failure (e.g. fail-over to a hot standby computer or
reconfiguration of networked tasks) or for any other reason. Immediately after
fail-over, all functions shall be available to the operators. The operators shall not
need to login again and the display selections should remain as they were prior to
the fail-over. No data shall be lost during the transfer of operation.
3.9.3
SPECIFICATION TS-GN-06
EEPCO
The Supplier shall provide detailed calculation that demonstrates that the
proposed system has the capacity and response capability to meet the full
requirements for performance initially and when a fully expanded. The
calculations shall demonstrate that there is sufficient processing power to achieve
the requirements.
Normal
Activity
High
Activity
10
20
b) Other measurements
20
40
30
30
15
Description
SPECIFICATION TS-GN-06
EEPCO
4.
4.1
OPERATING SYSTEM
Operating system for the main servers:
In order to allow a high level of independency concerning the server machines
and their technological evolution and availability on the market, SCADA real
time software shall be designed to be portable and running on both Windows
and Linux Operating systems, or substantially equivalent.
The provider shall demonstrate such portability, by detailing existing
references on the two Operating systems.
Operating system for the work stations, peripheral servers and communication
interfaces:
The Operating System for peripheral servers, workstations, communication
interfaces shall be Microsoft Windows or substantially equivalent.
In order to optimize the maintenance, the spare parts and the system
administration tasks, a all Windows solution shall be preferred (with
Windows 2008 for servers, Windows 2008 for workstations), or
substantially equivalent.
4.1.1
General
The SCADA computers at the Master Station shall form the main means of
controlling the power network. These shall be of high integrity, industrial units.
The Master Station shall provide for data acquisition from RTUs, storage in a
logically structured database, alarm management and real-time data presentation
(in text and graphic form). It must also provide all the system support functions
associated with providing the above operational functions. The facility to remotely
control plant via the RTUs shall be provided.
All points shall be identified by a unified referencing system. The numbering
system to be incorporated will be determined during the Contract and will be
assigned by the Engineer. The system shall accommodate point reference
numbers of at least seven (7) alpha-numeric characters for location, at least
twenty-four (24) alpha-numeric characters for point descriptions and at least eight
(8) alpha-numeric characters for parameter type.
SPECIFICATION TS-GN-06
EEPCO
4.2
4.2.1
General requirements
A set of software shall be provided to enable maintenance of application software
and development of new software in software development mode.
All hardware and software facilities shall be provided to allow creation,
modification and debugging of programs in all languages that are supplied.
The following shall thus be possible:
Program and data editing
Program compiling and assembling
Linking
Loading, executing and debugging program.
In addition, Supplier shall demonstrate that the software being delivered has been
developed and is maintained using software management tools. These tools shall
at least support the following features:
Software components identification
Version management
Concurrent development capability
Easy to use build procedures.
The software management tools shall be delivered along with the system, so that
the Owner can use it for:
His own software development
System upgrades.
All those tools must be also available on engineers PCs running Microsoft
Windows for ease of use by programmers and engineers. It shall therefore be
possible to compile applications and run executable images on these
PCs for engineers to develop and test extensions of the system.
Source code should be available for SCADA applications used by operators.
4.2.2
Command language
A complete command language shall be provided that allows interactive use of
any console to interactively create, modify and debug programs in all languages
provided.
It should also be possible to create and save command procedure file and to
execute it sequentially.
4.2.3
Programming languages
Language compiler shall be provided for all languages that are used in application
software. In addition, the following language compilers shall be provided:
C, C++
SPECIFICATION TS-GN-06
EEPCO
FORTRAN.
All compilers should, as far as possible, have the ability of optimizing the object
code in order to increase speed of execution and better use of main memory.
For all languages, diagnostic data, error summary and cross-reference listings shall
be available.
The output lists and error messages shall be clear and comprehensive.
4.2.4
4.2.5
Debugger
A debugger shall be provided to allow halting execution of a program at
predefined points, reading and modifying the registers and memory locations and
executing step by step a program.
Tender shall describe the features of debuggers for each type of equipment.
4.2.6
General utilities
The following utilities shall be provided for all computers in the configuration:
Full screen editor
Library management
Programs allowing to copy and print any data or program files
Media conversion to copy from one support device to another (e.g. disk to
magnetic tape)
File comparison
Sort and merge package
Programs that allow to partially save and recover volumes
Core and memory dump.
In addition all specific utilities that are used by the application software shall be
provided.
4.3
4.4
SPECIFICATION TS-GN-06
EEPCO
4.5
4.6
4.6.1
SPECIFICATION TS-GN-06
EEPCO
SPECIFICATION TS-GN-06
EEPCO
4.6.4
4.6.5
4.6.6
On-line Help
On-line help facilities for Database Construction & Maintenance, Documentation
management, System Operation, Applications and Diagnostics shall be provided
along with each of the software module.
A dual LAN shall be offered or an alternative system that offers equal or better
security.
All main computers, workstations, communication servers and other equipment
essential for the continuous operation of the SCADA system shall be connected
to both networks.
4.7
MAIL SYSTEM
A mail system shall be provided for multi-users applications. In particular, the
mail system shall be interfaced with the alarm management system and the
network-monitoring tool.
SPECIFICATION TS-GN-06
EEPCO
The interface with the alarm management system shall provide a filtering utility to
allow sending of only main events.
4.8
4.8.1
4.8.2
Diagnostic programs
Diagnostic programs shall be provided for all the servers, workstations, and
LAN/WAN. They shall be simple to operate including interactive procedures and
print out or hard copy facilities.
5.
HARDWARE CONFIGURATION
5.1
GENERAL REQUIREMENTS
The proposed system shall be designed for an open & scalable configuration, to
ensure inter-compatibility with other systems of the Utility, the future smooth
expansion as well as the easy maintainability. The proposed hardware
configuration should be extended by adding either CPU processors / memory
boards / disks etc. in delivered units or additional units for capacity extension. All
hardware shall be manufactured, fabricated, assembled, finished, and documented
with workmanship of the highest production quality and shall conform to all
applicable quality control standards. The hardware architecture shall be based on
open system with a very high level of operational security and safety.
All computer equipment shall be current models from main world-wide computer
manufacturers selected for efficient operation of a real-time system.
No proprietary hardware will be accepted for workstations, servers,
communication front-end computers. No modification of the Operating System
software is allowed.
The processors shall include facilities for orderly shutdown and resumption of
processor operation upon detection of power loss and subsequent resumption of
power.
Redundancy of equipment supporting critical functions is mandatory.
The hardware shall be connected to a SCADA LAN. The system architecture
shall ensure fast communication between servers and workstations. The SCADA
LAN shall include the redundant local networks at the Control Centre.
5.2
SERVERS
The servers shall be of high performance type with:
power supply (redundant as option)
fan system (redundant as option)
SPECIFICATION TS-GN-06
EEPCO
5.2.2
Communication servers
Redundant and non-proprietary communication servers shall be linked through an
appropriate number of signal loops to the RTUs and other metering equipment
connected in point-to-point configuration or to data concentrators collecting data
from several Remote Terminal Units.
Each processor, running preferably under Windows operating system or
substantially equivalent, of a redundant set of servers shall be connected to both
LANs in order to cope with the high availability requirements.
Communication Server interfacing to the RTUs shall be based on the standard
asynchronous IEC 870-5-101 or 104 and DNP 3 protocol. Free slots shall be
made available inside the FE server, so as additional communication boards can
be plugged-in to meet the network future expansion. Each channel shall be
assigned a different protocol and the front-end shall be able to manage several
protocols in parallel.
The redundancy of front-end servers shall allow handling of RTUs connected
either through single channel or redundant channels. In both cases, one FE server
shall be able to take control of all RTUs channels. In order to meet networks
expansion behind the full capacity of a pair of FE servers, it shall be possible to
connect additional FE servers pairs to the LANs.
Off-the-shelf, multi-source communication boards are required. Each
communication line shall be able to support its own communication protocol.
The Communication Servers shall be able to process time stamped data and
shall also provide automatic start-up functions.
Both servers can be active at a time (but not simultaneously for the same RTU
channel).
5.2.3
5.2.4
Auxiliary devices
A gong shall provide an acoustic signal when an alarm occurs. It must be
integrated in each operator console.
A GPS clock shall be provided for time synchronization.
SPECIFICATION TS-GN-06
EEPCO
5.2.5
Hardware Configuration
Servers of core system should be rack mounted, in cubicles.
Sufficient space shall allow mounting of network equipment (switches, routers,
firewalls, etc.) and proper cabling.
Adequate mechanical devices shall allow easy access to equipment, allowing
maintenance intervention on individual equipment without disruption of others.
Two separate power distribution units in cubicles shall feed the servers redundant
power supplies.
5.3
WORKSTATIONS
Each Operator Workstation shall be equipped with two (2) screens, and be able to
support up to four (4) screens for future extension.
It shall be possible to assign different applications to each screen, such as, for
example a minimum for each operator, a screen with the network general display,
a screen with the substations displays, a screen with the alarms and events
displays, a screen with analogues Trending.
5.4
MONITORS
Screens provided shall be of flat TFT. Workstations for operators shall be fitted
with minimum two (2) full graphics screens, with the ability to be extended
ultimately to four (4). Size shall be 20 inches minimum.
Minimum resolution shall be of 1280 x 1024 pixels at a minimum of 75 Hz.
Automatic detection of, and switching to, all resolutions and refresh rates shall be
provided.
Glare reduction features such as tinted, anti-glare screen coating, shall also be
proposed; devices attached to the monitor are not acceptable.
5.5
FRONT-END SERVERS
Redundant Front-End servers (FE) shall be provided to handle communications
with RTUs. The FE servers shall be able to communicate with and to handle all
RTUs located in the various substations and power stations. They shall preprocess the RTUs data and send them to the data servers for further processing.
The front end computers shall be able to simultaneously communicate with
different equipment using different protocols.
Moreover, different types of processing shall be available.
These Front-End servers shall be able to communicate with RTUs on WAN (IP
based protocols) and/or serial communication channels.
Supported serial channels shall be either point to point or point to multi point.
Asynchronous (byte protocols) and synchronous communications (bit protocols)
shall be supported.
The Front-Ends shall support the IEC 60 870-5-101 and 104 and DNP3.0 (serial
and over IP) protocols for the links to the RTUs.
SPECIFICATION TS-GN-06
EEPCO
The Supplier will give the list of protocols supported in standard by its SCADA
product as well as the type of RTUs to which it is already interfaced with.
Each of the FE servers shall offer at least 64 data channels. Free slots shall be
made available inside the FE server, so as additional communication boards can
be plugged-in to meet the network future expansion.
Each channel shall be assigned a different protocol and the front-end shall be able
to manage several protocols in parallel.
The redundancy of front-end servers shall allow handling of RTUs connected
either through single channel or redundant channels. In both cases, one FE server
shall be able to take control of all RTUs channels.
In order to meet networks expansion behind the full capacity of a pair of FE
servers, it shall be possible to connect additional FE servers pairs to the LANs.
Proprietary hardware shall not be accepted. Off-the-shelf, multi-source
communication boards or interfaces are required.
In case of a problem on the SCADA server, the front-end server shall be able to
provide to the operator a display showing a clear and comprehensive view of the
network current state. In such a case, the front-end server shall also be able to
inform the operator of the communication links state toward the RTUs that it is
managing.
5.6
5.7
PRINTERS
At least, the following set of printers shall be provided in order to enable proper
operation of the SCADA system:
Two Black & White printers, laser technology, all sizes up to A3 format
One Colour printer, laser technology, all sizes up to A3 format, reasonably
good colour print engine speed (4 pages per minute), colour calibration
facilities
For logging, historical data review and printing shall be available from any
workstation on operator request.
SPECIFICATION TS-GN-06
EEPCO
5.8
NETWORKS
5.8.1
Standards
Communications within and among the computing networks supplied by the
Supplier shall conform to standards, in particular:
IEC 60 870-5-101 and 104, and DNP 3.0 (serial/over IP) for the
communication links between the Front End computers and the RTUs in the
primary substations.
IEC 60 870-6 ICCP protocol for the communication between control centre
systems,.
Proprietary protocols for RTUs and inter-centre links will not be accepted.
Emphasis shall be placed on security features as described hereunder in Office
LAN chapter.
5.8.2
System LAN
The communication between the equipment of the SCADA system at the control
centre shall be made through high performance redundant (two independent
LAN sets in parallel) LAN switches with minimum throughput of 10/100 Mbits
auto-sense per connection ports. Full duplex connections are preferred (no
connection grouping through hub or concentrator).
5.8.3
Office LAN
WAN Connections with other local systems shall be secured through firewalls.
Firewall appliances are preferred. Furthermore, when applicable (depending on
external system capability), communication shall be encrypted (SSL sockets, VPN,
etc.).
5.8.4
Maintenance link
It shall be possible to diagnose and maintain the system through a secure Virtual
Private Network (VPN) channel.
5.8.5
6.
USER INTERFACE
The network diagrams shall be displayed by two-dimensional graphical
representation. The principal interface between users and the SCADA will be the
consoles. Console is an operating position consisting of one or more monitors
and user interaction devices. The interface shall support the following functions:
SPECIFICATION TS-GN-06
EEPCO
6.1
6.2
ACCESS SECURITY
A mechanism for defining and controlling user access to the SCADA system shall
be provided. This security scheme shall be in addition to that included with the
operating system. That is, even though a user has logged onto the windows
SPECIFICATION TS-GN-06
EEPCO
User Login
Password security shall be provided for access to the SCADA. A system manager
or analyst selectively assigns levels of capability through access rights to consoles,
specific computers, and/or individual users.
It shall be possible to assign a level of security for either the consoles or the
physical people. When a physical individual connects it-self to the system via a
workstation, access rights associated to this session shall depend on the access
right defined for the user and the ones granted to the workstation:
If the workstation has been defined by the system manager as User centric,
then any user connecting him-self to the system via this workstation shall
benefit from the access rights associated to him
If the workstation has been defined by the system manager as Workstation
centric, then any user connecting him-self to the system via this workstation
shall benefit from the access rights associated to the workstation
Finally, if the workstation has been defined by the system manager as
Hybrid, then any user connecting him-self to the system via this workstation
shall benefit only from the access rights common to the user and to the
workstation.
Encrypted passwords and/or strong authentication (one time password,
certificates) shall be proposed.
The transfer of access rights from a physical individual to another shall be
possible for the monitoring of critical areas on the Distribution network. When
none of the workstations normally connected to these critical areas, then, the
system shall automatically grant the corresponding access rights to another
workstation designed in advance as backup workstation.
Each log-on and log-off shall be reported as an event. The event message shall
indicate the date and time the procedure was executed, the name of the console
and the identification of the user. The log-in status of the user shall be unaffected
by any failure recovery procedure of the SCADA system.
6.2.2
6.3
SPECIFICATION TS-GN-06
EEPCO
6.3.1
Windows
The User Interface must be a multi-windows system. It shall be possible to
manage as many as desired displays on the same screen. The system manager shall
be able to limit the number of windows a user can open on a single screen.
Each screen shall support the simultaneous presentation of at least four userdefined windows. These windows shall be in addition to those dedicated for the
common display features. The presentation of any display in any window shall be
allowed. Window position and dimensions shall be independently adjustable to a
screen resolution of four pixels or less. The windows shall be displayed in either
overlapping or tiled fashion depending on the window definition of the user. In
addition to the defined windows, user definition of windows shall be supported.
Efficient techniques for switching between windows on a screen and between
screens shall be provided.
6.3.2
Display Selection
Rapid, convenient, and reliable selection of displays shall be provided using the
following methods:
Selection from a menu display
Cursor target selection on any menu, graphic, or tabular display
Selection of an alarm: in this case, it shall call up the one-line display
containing the alarms location,
Entry of a display name in a display select field,
Forward and backward paging through a series of displays,
Selecting a display recall command. This shall cause the display that was on
view immediately prior to the current display to be recalled, and,
Selecting function keys or cursor targets dedicated to displays.
The user shall be provided window selection techniques to independently direct a
display to any window on any screen at the console.
6.3.3
SPECIFICATION TS-GN-06
EEPCO
Panning speed shall be proportional to the distance between the cursor and the
point from which the panning operation was initialized.
6.3.4
6.3.5
Data Acquisition
Blocking of data acquisition to prevent data gathered by RTUs from updating the
database. Blocking should be possible for individual data points, points belonging
to a bay or a whole station.
Alarm Processing
Command
It should be possible to block remote control for individual power system device,
power system device belonging to a bay or a whole station.
In the display pictures of a blocked data point shall be marked with a special
colour indicating the type of blocking. Blocking and de-blocking actions should be
logged in the event list.
6.3.6
Inactivity Timeout
The progress of all user operations shall be monitored. If the user does not
complete to a step within a multi-step operation within a pre-defined time, the
process shall reset, and the user shall be informed of the reset. A partially
completed action shall be reset if the user begins another non-related sequence.
6.3.7
User Guidance
The SCADA shall respond to all user actions indicating whether the action was
accepted, was not accepted, or is pending. For multi-step procedures, the SCADA
shall provide feedback at each step. Indications such as text messages, colour
changes, and blinking shall provide this feedback.
SPECIFICATION TS-GN-06
EEPCO
6.3.8
User Help
General and specific context-sensitive on-line help shall be available to the
SCADA user. Context sensitive means that the help information provided shall be
applicable to the next steps or steps in the sequence being performed. Access to
user help shall be available by:
A Help command on the window menu bar;
A Help button in a dialog box; and
Topics from a Help menu
Pressing help key or poke target on the specific field.
The Help menu shall present a list of topics available for reference. The topics
shall refer to the SCADA user documents. The ability to scroll through the topics
explanatory text shall be supported.
The Help button in a dialog box and help key shall present the text of the
SCADA user documents where use of the dialog box is explained. The user shall
be able to scroll through this text. Exit from the help facility shall return the user
to the same point in the sequence for which help was requested.
Context sensitive help facilities shall be provided for each application software
package and operator display. The capability to easily edit or add additional help
facilities in the future shall be provided.
The provided help facility shall also support:
search mechanism
navigation links between related topics within the help documents
select/copy mechanism
print facilities
6.4
TRENDING
The SCADA shall include facilities to generate graphic trend curves for real-time
and historical data.
Selection of a trend shall be automatically called and displayed, by selecting any
value by the operator, without the need to go back in the configuration tools.
Selecting a point and designating a trend curve shall result in the display of a
dialog box where the user can enter information on how the selected point is to
be displayed:
Value name
Trend direction
Scaling factor
Offset
Trend number and colour (for multiple trends on one display)
Time base values
SPECIFICATION TS-GN-06
EEPCO
Trend rate
Trend start time (historical data)
Trend period (historical data).
Minimum of sixteen tracks shall be displayable in the same window.
6.5
DISPLAY HARDCOPY
A means shall be provided to produce printed copies of any display on printer.
Colour displays shall be translated for black and white printers using a mapping
table (or similar) that can be changed by the user.
6.6
DISPLAYS
6.6.1
6.6.2
6.6.3
SPECIFICATION TS-GN-06
EEPCO
The user shall be able to navigate to other substation displays from poke points
on distribution line segments on the one-line. The user shall also be able to call-up
the associated substation tabular display from a poke point on the one-line.
6.6.4
Substation Tabular
These displays list the value of measured and calculated data associated with each
substation as well as related information such as alarm limits. The user shall be
able to interact with the substation tabular displays to perform any associated user
interactions such as data entry, supervisory control, tagging and scan requests. The
user shall be able to call-up the associated substation one-line display from a poke
point located on the tabular display.
These displays shall be built-in displays of the SCADA; no modelling shall be
required to obtain them. Upon call-up, they shall display all the current contents
of the database. Points displayed shall be all non-spare database points that are
associated with the substation:
For status points - The information displayed for each point shall include :
Name descriptors
All data attributes
Current status
Quality codes and tags
Unique point ids.
For analogue points - The information displayed for each point shall include :
Name descriptors
All data attributes
Current value
All limit values
Quality codes
Unique point ids.
For accumulator points - The information displayed for each point shall
include :
Name descriptors
All data attributes
Current value
Quality codes
Unique point ids
For calculated points - The information displayed for each point shall include :
Name descriptors
All data attributes
Current value
SPECIFICATION TS-GN-06
EEPCO
6.6.6
6.6.7
Alarm Summary
Alarm summaries shall be provided to show power system alarms. When called to
a screen or window, the most recent alarms shall be presented first. The user shall
be able to acknowledge and delete messages on the display. Flashing shall identify
unacknowledged alarms (to facilitate reading unacknowledged messages, only the
time field shall flash).
When the full complement of alarm messages will not fit on a single page,
multiple pages shall be provided and a message shall appear on each page of the
display, indicating there are more alarm messages on other pages. If the capacity
of the alarm summaries is limited and an alarm summary display becomes full, the
oldest messages shall be automatically deleted and the newest messages shall be
added. It shall be possible to perform any alarm interaction from the alarm
summary displays.
A single user action shall be used to call an alarm summary that presents only
those alarms for the jurisdictions assigned to the console from which the display is
called. All alarms in all classes shall be presented. The user shall be able to filter
the alarms to present selected classes.
6.6.8
6.6.9
Abnormal Summary
This display shall list devices and values that are not in their normal state.
Measured, calculated, and manually entered status, analogue, and accumulator data
points shall be included. The displays shall show the off-normal data points in the
following groups:
Status points for which the present measured state is different from the normal
state stored in the database; and
SPECIFICATION TS-GN-06
EEPCO
Analogue and accumulator points that current values exceeding alarm limits
For those points with an undefined normal state, the system shall provide a
convenient mechanism for redefining their normal states. The off-normal status
displays shall use dynamic colouring facilities to identify the different conditions
associated with the points.
6.6.10
6.6.11
Tag Summary
This display shall list and describe all active tags for all devices. The user shall be
able to place or remove a tag from this summary. Information on this display shall
list each device tagged and shall include: date and time of tag placement, user who
placed the tag, tag level, station identifier, device identifier, and comment field.
6.6.12
6.6.13
6.6.14
6.6.15
Memos
From the consoles or through web, users shall be able to assign memos that
contain directly entered free-form text and graphics to displays. It shall be
possible to assign memos to any display and at any location within a display. A
unique icon or indicator shall be provided that will visually highlight to the user
that a memo is assigned to the display. The memo icon shall be visible at all declutter levels during a zoom operation.
SPECIFICATION TS-GN-06
EEPCO
7.
SCADA FUNCTIONS
The main SCADA functional areas shall be as follows:
SCADA and distribution network functions should run on the same server.
7.1
DATA ACQUISITION
The data acquisition module shall receive telemetered data from front end
computers used to communicate with field devices.
7.1.1
Operator Requests
Operators shall be given the opportunity:
to issue demand scans to scan RTUs.
and to remove or restore from service entire parts of the communication
system (communication lines, RTUs, groups of data, etc.)
7.1.2
SPECIFICATION TS-GN-06
EEPCO
It shall be possible to report the values defined for a specific group of points or to
issue a command to the RTU. It shall be used for infrequent scans and special
scanning functions.
7.1.3
Report by Exception
All status changes shall be reported by exception. Accumulator readings shall also
be reported by exception as soon as they are presented by the RTU.
For analogue data, it shall be possible to report a new value if the difference
between this value and the previous one exceeds a specific dead-band to be
specified by the operator.
7.1.4
Integrity Scanning
It shall be possible to report the values of all scanned points (regardless of
whether they changed) in the following cases:
On start-up of the system,
After loss of communication with the RTUs,
Periodically while running
On operators request.
7.1.5
7.1.6
7.1.7
7.1.8
Statistics Gathering
On the hourly basis, the SCADA server shall request communication statistics
from the communication equipment.
7.2
DATA CONVERSION
The SCADA system shall provide a data conversion function taking telemetered
data received from the RTUs and converting it to a standard internal form for
further processing.
7.2.1
SPECIFICATION TS-GN-06
EEPCO
7.2.2
7.2.3
7.2.4
7.2.5
7.3
7.3.1
Automatic Colouring
Electrical conditions shall be automatically identified on the distribution single
line diagrams. Distribution lines and cables shall be coloured using a set of userpredefined colours according to their electrical status:
overload conditions
participation in a loop (limited to lines in the radial part of the network)
energization / de-energization status
earthing status.
7.3.2
On-demand Colouring
The on-demand colouring function shall provide the SCADA operator with the
capability to highlight electrically connected elements of a designated feeder. This
designation shall be performed by direct point and click operation on any of the
feeder branches on the distribution single line diagrams.
Two different modes shall be provided:
SPECIFICATION TS-GN-06
EEPCO
feeder colouring mode, where the entire feeder shall be coloured with the same
uniform representation
Circuit tracing mode, where the two parts of the feeder, upstream and
downstream of the designated branch, shall be coloured with two different
representations. For the upstream part, all actual paths to the feeder source
shall be coloured. In case of loop conditions, the different sources of the
feeder shall also be coloured.
A set of predefined colours shall be allocated to the on-demand colouring.
Selection of the colour amongst this set shall be possible in order to differentiate
neighbouring feeders.
7.4
DATA PROCESSING
Data processing involves a value which has been converted to internal form and
analysed for violations of limits. The data processing shall set various data
attributes depending on the results of the checks and shall trigger any additional
processing or calculation.
There shall be several normal sources of SCADA data:
telemetry
calculation
manual entry
host external process to SCADA.
Different data quality flags shall be provided about data quality, status points,
analogues, special calculations and accumulators, with a minimum of fifteen basic
flags.
It shall be possible to manually replace SCADA values. Acquired values shall be
first removed from service by the operator. This shall allow the operator to
replace the current value by a manual value. The SCADA status of the replaced
value shall become manually replaced. This status shall also be propagated to all
calculated values using the replaced value as an input argument.
A summary display shall show all the currently replaced values.
At any time, it shall be possible to put a replaced value back in service.
7.4.1
Data Quality
Data quality shall be indicated to the operator through quality flags associated to
each data.
Those flags are the ones transmitted by the RTUs according to the
communication protocol in use and completed by the ones issued by the checking
operations made on the data by the SCADA acquisition function, with, as a
minimum:
Un-initialized value: no meaningful amount has been stored in the value.
Bad value: the value is likely to be incorrect because it came from RTU
determined to be bad.
SPECIFICATION TS-GN-06
EEPCO
Converter overflow: the value may not be as large (or small) as it shall be
because the analogue value was at the physical limit of the A / D converter
7.4.2
7.4.3
Analogue Processing
An analogue value shall have one or more limits assigned to it to be checked each
time its value changes. For each analogue value, there shall be two basic types of
limits: on the analogue value itself and on the rate of change of that analogue:
Value limits: They shall be used to check the current value of the analogue
against limit values. Up to four limit values can be set. Limit values shall always
come in pair, a high limit and a low limit.
Reasonability limits: There shall be on each analogue a pair of reasonability
limits beyond which no value is even believable. If a value violates these limits,
then the checked value shall be kept and marked old.
Forbidden range limit: A forbidden range is a limit pair which is considered to
be violated when the value of the analogue falls within the pair. A forbidden
range would be used if there were a particular area where operation must be
prevented.
Limit dead-band: To minimize cycling between the violated and un-violated
states, a dead-band shall be specified on the return of a limit to the un-violated
state. Dead-bands shall be individually specifiable for each limit pair either as
an engineering units value or as a percentage of the range between the high
and low limits.
Rate of change limits: They are those which check the rate at which an
analogue value changes. There shall be a positive limit and a negative limit to
catch excessive rises in the analogue value.
7.4.4
SPECIFICATION TS-GN-06
EEPCO
Accumulator Processing
The system shall be able to store accumulator history.
Two methods of storing accumulator history shall be provided: a method that
stores data only once per hour and a method that stores data each time new data
enters the system.
It shall be possible to use the two methods concurrently for any pulse
accumulator, making it possible to maintain two records for data that are read
more than once an hour.
7.5
SUPERVISORY CONTROL
The operator shall be able to request digital status control, set-point control and
raise/lower control on selected points and analogues.
7.5.1
7.5.2
Set-point Controls
A set-point involves a numerical value being sent to an RTU, resulting either a
digital or analogue value out of the RTU to external equipment.
Several conditions shall be checked before a requested set-point action is actually
allowed to be sent as for example: the set-point is in service .
SPECIFICATION TS-GN-06
EEPCO
7.5.3
7.5.4
Sequence Switching
The Switching Sequence Management function shall enable the SCADA operator
to edit online and subsequently execute sequences consisting of remote controls
such as switching operations or analogue set-points.
7.5.5
Editing
Online editing facilities shall be provided for the operator to:
create, modify or delete sequences, and
add, modify, or delete control operations within a sequence.
Addition of operations shall be possible by direct point and click from the
network single line diagram, without the necessarily entering manually the
identification of the device. However, manual editing shall also be possible.
A configurable period of time shall be entered for each operation, as a time-out at
execution time.
Verification
Verification of the sequence shall be performed before a sequence can be put in
service and executed. An operator action shall be required to allow the sequence
to be actually used and executed.
Execution
Two modes shall be provided for the execution of the sequences: either fully
automatic after selection by the operator, or step-by-step with an operator action
required to initiate each operation.
Completion of the current operation shall be required before proceeding to the
next operation.
In case of failure of one operation in automatic mode, the sequence shall be
paused, an alarm shall be generated and control shall return to the dispatcher.
7.6
SPECIFICATION TS-GN-06
EEPCO
The visual indicators shall include a dedicated display region linked via
poke-points to other displays that provide more detailed information about
the state of the power system.
7.6.2
Annotating Logs
The operator shall be able to annotate or add comments to the messages of the
system activity log.
7.6.3
SPECIFICATION TS-GN-06
EEPCO
7.6.5
Logging Facility
It shall be possible to print:
Power system events,
Data processing, tele-control and telecommunication system events.
It shall be easily possible to direct any of these events printing to any printer on
the SCADA LAN.
A spooling area shall be provided in order to limit the number of lost messages or
statements in case of temporary unavailability of a printer.
7.6.6
SPECIFICATION TS-GN-06
EEPCO
This tool shall reduce in a significant way, the number of alarms to be managed by
the operator while facilitating his understanding of the incident and his decision
process.
Very different criteria shall be proposed in order to regroup the alarms; for
example:
cutting out of a well-defined network component
re-closing scenarios following a line fault
malfunction of the network protection system.
As needed, the operator shall be able to define him-self some alarms grouping.
For each diagnostic, the tool shall be able to display on the screen the regrouped
alarms or events detail; it shall then be possible to choose between an automatic
alarm acknowledgement, made by the tool itself, or a manual, and individual,
acknowledgement made by the operator.
This tool shall not lead to any overload of the computerized control system.
7.7
TAGGING
The system shall allow the user to place tags on devices in order to warn or
inform operators of special conditions in the power system. Placing tags on
devices usually prevents controlling these devices.
7.7.1
Tagging Definition
The tagging definition function shall enable the system analyst to define tag types.
A tag type defines the effects of tags when placed on a device. Tag types shall
have one or more of the following characteristics:
Inhibit opening and/or closing of a device
Restrict opening and/or closing of a device.
Place on only opened or closed device.
Each tag type shall also specify a priority which allows the different tag types to be
uniquely identified on the SCADA one-line diagram.
7.7.2
Tag Placement
The tag placement function shall allow the operators to place tags on devices to
prevent them from closing or opening, or to inform the operators of any special
condition. Tags could be also placed at substations for informational purposes.
Operators shall be able to enter informational texts associated to the tags.
7.7.3
Tag Removal
Operators shall be allowed to remove tags. The system shall keep track of tag
placements along with the name of the operator who issued the request.
7.7.4
Tag Group
A set of individual tags shall be able to be grouped together.
For example, when a distribution line segment needs to be electrically isolated,
several breakers or switches may need to be opened. Each breaker or switch is
SPECIFICATION TS-GN-06
EEPCO
tagged. The tags may then be grouped together using a tag group to track the
association between the tags. This information can be kept through a displays
note as described in the following chapter.
7.7.5
Displays Notes
A tool shall be provided for operators to make notes on displays so that they can
communicate information to the next shift or other. A rich text editor supporting
text and pictures shall be provided for this doing.
Display notes, as the name suggests, shall be a repository for information and can
be placed at an arbitrary location on a display. They can be used to indicate a work
permit.
Display notes shall be created for informational purposes, but shall also be
associated with a group of tags. When the display note is created, a movable
picture representing the display note shall appear on the display which the user
can position anywhere on the display.
7.8
7.9
7.9.1
Data Capture
A general utility shall be provided for transferring data from real time database to
a relational database supporting the SQL standard. The relational database shall be
a commercially available product (such as ORACLE or MS SQL Server). For
interoperability with other software products, Microsoft ODBC interface shall be
supported. The primary functionality of the Historical Data Management software
(HIM) shall be to allow collecting historical data from a real-time system into the
relational database, from where a variety of tools can be used to produce statistics
and reports.
The HIM system shall take care of the definition of the real-time data to be stored
along with the periodicity of sampling and duration of storage.
As an example, the following data shall be stored in the historical system:
All the analogues, calculated or coming from the RTUs, sampled every 15
minutes and stored in daily tables on a duration of two (2) months
All the events of the system stored in monthly tables on a duration of two (2)
months
SPECIFICATION TS-GN-06
EEPCO
7.9.2
Reports Facility
Within its offer, the supplier must propose a tool in order to enable operators to
build and customize reports from the historical data gathered into the database of
the man machine interface product. This tool has to be able to build in a userfriendly manner, reports about all the systems data.
For example, the supplier shall provide the following reports:
Daily report
Weekly report
Monthly report
With the possibility to operate processes such as averages, sums, comparisons on
the data presented in the report.
The product may be a third party product, reports built with this third party
product must be displayable through an Internet browser.
Resulting reports must be exportable in several formats such as Excel spread
sheets, ASCII format, CSV format, etc.
7.10
SPECIFICATION TS-GN-06
EEPCO
7.11
SECTION 8 - FRTU
8.
FRTU
8.1
GENERAL
The Feeder Remote Terminal Unit (FRTU) shall be installed at Ring Main Units
(RMUs), sectionaliser locations FRTU shall also be used for control of switching
devices such as breaker, isolator switches etc. inside RMU panel, sectionaliser etc.
from Master station(s). The supplied FRTUs shall be interfaced with the RMUs,
FPI, communication equipment, power supply distribution boards; for which all
the interface cables, TBs, wires, lugs, glands etc. shall be supplied, installed &
terminated by the Contractor.
8.1.1
DESIGN STANDARDS
The FRTUs shall be designed in accordance with applicable International Electrotechnical Commission (IEC), Institute of Electrical and Electronics Engineer
(IEEE), American National Standards Institute (ANSI), and National Equipment
Manufacturers association (NEMA) standards, unless otherwise specified in this
Technical specification. In all cases the provisions of the latest edition or revision
of the applicable standards in effect shall apply.
8.1.2
FRTU Functions
All functional capability described herein shall be provided by the Contractor even
if a function is not initially implemented.
As a minimum, the FRTU shall be capable of performing the following functions:
Acquiring analogue values from Multifunction Transducers or alternatively
through transducer- less modules and the status inputs of devices from the
substation, processing and transmitting to Master stations. Capability to
acquire analogue inputs from analogue input cards receiving standard signals
viz current loops 4-20Ma, RTD etc.
Receiving and processing digital commands from the master station(s).
Data transmission rates - 300 to 19200 bps for Serial ports for MODBUS. And
10/100 mbps for TCP/IP Ethernet ports. Use of IEC 60870-5-104/101
protocol to communicate with the Master station(s).
Use of MODBUS over RS485 interface, Protocol to communicate with the
MFTs.
Have required number of communication ports for simultaneous
communication with Master station(s), MFTs and FRTU configuration &
maintenance tool.
SPECIFICATION TS-GN-06
EEPCO
SECTION 8 - FRTU
8.2
COMMUNICATION PORTS
The RTUs shall have following communication ports to communicate with
master station MFTs and configuration & maintenance terminal.
FRTU shall have one TCP/IP Ethernet port for communication with
Master station(s) using IEC 60870-5-104/101 protocol or serial port in case
IEC60870-101.
FRTU shall have required number of RS 485 ports for communication with
MFTs/ to be connected in daisy chain using MODBUS protocol. Minimum
15 analogue values (including 4 energy values) to be considered per energy
meter.. The RTU shall be designed to connect maximum 5 MFT per port.
Further, bidder to demonstrate during testing that all analogue values
updated within 2 sec.. The updating time shall be demonstrated during
testing. 5.
FRTU shall have one port for connecting the portable configuration and
maintenance tool for FRTU. SSL/VPN,NERC/CIP complaint
SPECIFICATION TS-GN-06
EEPCO
SECTION 8 - FRTU
8.3
ANALOGUE INPUTS
The real time values like, Active power, Reactive Power, Apparent power three
phase Current & Voltage and frequency, and power factor & accumulated values
of import /export energy values will be acquired FRTU from the following in the
given manner:
MFTs installed in RMU/DTs
RTU shall also take 4-20 mA, 0-20mA, 0- -10mA, 0-+10mA, 0-5V etc. as
analogue inputs to acquire DC power supply voltage etc.
The FRTU analogue-to-digital (A/D) converters shall have a digital resolution of
at least twelve (12) bits plus sign. The overall accuracy of the analogue input
system shall be at least 0.2 %( i.e. 99.8%) at 25 C of full scale. Mean accuracy
shall not drift more than 0.002% per degree C within the temperature range of 5
to +55 degree Linearity shall be better than 0.05%. The FRTU shall be designed
to reject common mode voltages up to 150 Vac (50 Hz). For dc inputs, normal
mode noise voltages up to 5 Vac shall be rejected while maintaining the specified
accuracy.
Each input shall have suitable protection and filtering to provide protection
against voltage spikes and residual current at 50 Hz, 0.1 ma (peak-to-peak) and
overload. Loading up to 150% of the input value shall not sustain any failures to
the FRTU input.
The ability of the FRTU to accommodate dc inputs shall include the following
signal ranges:
SPECIFICATION TS-GN-06
EEPCO
SECTION 8 - FRTU
The total burden imposed by the FRTU analogue input circuit shall not exceed
0.5 volt-ampere for current and voltage inputs. As an option, contractor may also
provide transducer less solution to connect direct CT/PT secondaries.
8.4
STATUS INPUT
RTU shall be capable of accepting isolated dry (potential free) contact status
inputs. The RTU shall provide necessary sensing voltage, current, optical isolation
and de-bounce filtering independently for each status input. The sensing voltage
shall not exceed 48 Vdc/220VAC.
The RTU shall be set to capture contact operations of 20 ms or more duration.
Operations of less than 20 ms duration shall be considered no change (contact
bounce condition). The RTU shall accept two types of status inputs i.e. Single
point Status inputs and Double point status inputs.
To take care of status contact chattering, a time period for each point and the
allowable number of operations per time period shall be defined. If the allowable
number of operations exceed within this time period, the status change shall not
be accepted as valid. Single point status input will be from a normally-open (NO)
or normally-closed (NC) contact which is represented by 1-bit in the protocol
message.
The Double point status input will be from two complementary contacts (one
NO and one NC) which is represented by 2-bits in the protocol message. A
switching device status is valid only when one contact is closed and the other
contact is open. Invalid states shall be reported when both contacts are open or
both contacts are closed.
All status inputs shall be scanned by the FRTU from the field at 1 millisecond
periodicity.
8.5
8.6
CONTROL OUTPUTS
The FRTU shall provide the capability for a master station to select and change
the state of digital output points. These control outputs shall be used to control
power system devices such as Circuit breakers, isolator, reset, relay disable/enable
and other two-state devices, which shall be supported by the RTU.
SPECIFICATION TS-GN-06
EEPCO
SECTION 8 - FRTU
A set of control outputs shall be provided for each controllable device. On receipt
of command from a master station using the select check-before-execute operate
(SCBO) sequence, the appropriate control output shall be operated for a pre-set
time period which is adjustable for each point from 0.1 to 2 seconds.
Each control output shall consist of one set of potential free NO contact. The
output contacts shall be rated for at least 0.2 Amp. at 48 Vdc. These output
contact shall be used to drive heavy duty relays. In case Control output module of
FRTU does not provide potential free control output contact of this rating, then
separate control output relays shall be provided by the contractor. These relay
coils shall be shunted with diodes to suppress inductive transients associated with
energizing and de-energizing of the relay coils & shall conform to the relevant
IEC requirements.
8.6.1
8.6.2
8.6.3
8.6.4
SPECIFICATION TS-GN-06
EEPCO
8.7
SECTION 8 - FRTU
8.8
TIME FACILITY
The internal FRTU time base shall have a stability of 100 ppm. The RTU shall be
synchronised through synchronisation message from master station at every 5
minutes (configurable from 5 minutes to 60 minutes) over IEC 60870-5104/101/NTP/SNTP
8.8.1
DIAGNOSTIC SOFTWARE
Diagnostic Software shall be provided to continuously monitor operation of the
FRTU and report RTU hardware errors to the connected master stations. The
software shall check for memory, processor, and input/output ports errors and
failures of other functional areas defined in the specification of the RTU.
8.8.2
SPECIFICATION TS-GN-06
EEPCO
SECTION 8 - FRTU
The FRTU shall have adequate protection against reversed polarity, over current
and under voltage conditions, to prevent the RTU internal logic from being
damaged and becoming unstable causing mal-operation.
8.8.3
ENVIRONMENTAL REQUIREMENTS
The FRTU will be installed in inside RMU Panel or in open environment with no
temperature or humidity control.
The RTUs shall be capable of operating in ambient temperature from 0 to +55
degree C with rate of temperature change of 20 degree C/hour and relative
humidity less than 95%, non-condensing. FRTUs to be installed in the hilly region
with the history of snowfall, the same the lower ambient temperature limit shall be
-5 degree C.
8.8.4
8.8.5
FRTU PANELS
At least 50% of the space inside each enclosure shall be unused (spare) space that
shall be reserved for future use. The Contractor shall provide required panels
conforming to IEC 529 for housing the FRTU modules/racks, relays etc. and
other required hardware. The panels shall meet the following requirements:
shall be pole/ wall mounted compact size cabinet. The size shall be preferably
in the order of 400 mm. All doors and removable panels shall be fitted with
long life rubber beading. All non-load bearing panels/doors shall be fabricated
from minimum 1.6 mm thickness steel sheet and all load bearing panels,
frames, top & bottom panels shall be fabricated from minimum 2.0 mm
thickness steel sheet
shall have maintenance access to the hardware and wiring through lockable
doors.
shall have the provisions for bottom cable entry
The safety ground shall be isolated from the signal ground and shall be
connected to the ground network. Safety ground shall be a copper bus bar.
The contractor shall connect the panels safety ground of to the owners
grounding network. Signal ground shall be connected to the communication
equipment signal ground.
All panels shall be supplied with 230 Vac, 50 Hz, single-phase switch and
15/5A duplex socket arrangement for maintenance.
All panels shall be provided with an internal maintenance lamp, space heaters
and gaskets.
All panels shall be outdoor, dust-proof with rodent protection, and meet class
of protection. IP41 if housed in RMU panel & IP54 in case of in open
outdoor.
SPECIFICATION TS-GN-06
EEPCO
SECTION 8 - FRTU
WIRING/CABLING REQUIREMENTS
The FRTU panels shall gather all signals from and to the devices located in
Control & Relay panels in the substation control room. All wires that carry lowlevel signals shall be adequately protected and separated as far as possible from
power wiring. All wires shall be identified either by using ferrules or by colour
coding. In addition, cables shall be provided with cable numbers at both ends,
attached to the cable itself at the floor plate where it enters the cubicles.
Shielded cables shall be used for external Cabling from the FRTU panels. The
external cables (except communication cables) shall have the following
characteristics:
All cables shall have stranded copper conductor.
Minimum core cross-section of 2.5 mm2 for PT cables, 4 mm2 for CT cables, if
applicable and 2.5 mm2 for Control outputs and 1.5mm2 for Status inputs
Rated voltage Uo/U of 0.6/1.1KV
External sheathing of cable shall have oxygen index not less than 29 &
temperature index not less than 250. Cable sheath shall meet fire resistance test
as per IS 1554 Part- I.
Shielding, longitudinally laid with overlap.
Dielectric withstand 2.5 kV at 50 Hz for 5 minutes
External marking with manufacture's name, type, core quantity, cross-section,
and year of manufacture.
The Communication cable shall be of shielded twisted pairs and of minimum
0.22sq mm size.
8.8.7
SPECIFICATION TS-GN-06
EEPCO
9.
Three phase Energy meters of 0.5 class are connected to each feeder in 3phase 4-wire configuration for gathering instantaneous values of phase wise
currents, voltages. 6to 8 of such feeder meters are connected on a RS485 LAN
in a multidrop configuration. Each of these meters supports MODBUS RTU
protocol.
A data concentrator (DC) connected to the feeder meters on a RS485 LAN
interrogates each meter (poles) on a MODBUS RTU protocol and gathers
meter data at pre-programmed intervals. Further the information gathered
from each meter is stored in the Data Concentrator till it is transmitted to
Control centre The DC is connected to the control centre through MARS and
communicates in MODBUS RTU protocol.
9.1
10.
10.1
10.1.1
System Description
The UPS System to be provided shall be of 3-phase On-line Double Conversion
type (EN 50091-3 VFI, Voltage and Frequency Independent), i.e. the critical loads
shall be fed through rectifier/inverter, thus the output voltage/frequency being
independent from the input voltage/frequency.
The rectifier unit of the UPS shall be so dimensioned that it is capable of feeding
the total critical load current to the inverter and simultaneously- charge the
SPECIFICATION TS-GN-06
EEPCO
Technical Requirements
Environmental requirements as per Item 3 of the technical specifications, with the
addition that the noise level shall not exceed 60 dB(A), measured at 1 meter
distance.
AC supply to UPS system according to Item 3 of the technical specification, with
the exception that the input voltage shall be 3-phase, 400/230 VAC.
The input power factor of UPS system shall be >0.95 and the total efficiency
>85%.
Output voltage:
Output requirement:
400/230 VAC, 5%
Frequency:
50 Hz, 0.5%
Distortion (THD):
Phase displacement:
Max. down time due to
switching operations:
Back-up time:1)
< 10 ms
>2 h at full load
Rated output power For one UPS equipment and battery bank
Adequate to supply the master station including all related peripherals. Provision
for emergency lighting (0.5 kVA) as well as 30 % provision for future extensions
shall be provided (master station + peripherals + 0.5 kVA < 70% of rated output
power).
10.2
48 V DC AT CONTROL CENTRE
The Control Centre shall be equipped with two rectifier/battery charger units, for
supplying 48 V DC to the Radio Link terminals at the Control Centre.
SPECIFICATION TS-GN-06
EEPCO
Each unit (one rectifier and battery bank) shall be capable of supplying the total
load of radio link terminals plus 50% spare capacity. The back-up time (of one
rectifier and battery bank) shall be > 2 h at full load.
10.3
48 V DC AT SUBSTATIONS
The Switching stations and Other locations where FRTUs and Radio Link
terminals will be located are equipped with 60V DC rectifiers which provide the
required DC voltage for the station.
11.
11.1
SYSTEM DESCRIPTION
The specified radio link equipment shall provide data stream between the links
from the Control Centre to each FRTU site
The system delivery shall be complete including antenna towers, installation
accessories, antennae, etc.
The availability (measured over a month) shall be equal or better than the
following:
Equipment redundancy such as hot stand-by is not required. The equipment shall
be powered from a 48 V DC bus, existing or otherwise to be supplied in this
Contract.
11.2
11.2.1
Capacity
The equipment shall support user data rates up to 9.6 kbit/s. The bid shall
describe possibilities to upgrade the data rate up to 64 kbit/s. However, the
possibility for the upgrade is not a mandatory requirement.
The Bidder shall state the bandwidth, modulation used combined with the
required SNR.
11.2.2
11.2.3
11.2.4
Transmitter
Frequency Range
The radio equipment shall be programmable. The Bidder shall propose the
transmission frequency he considers most favourable under the prevailing
SPECIFICATION TS-GN-06
EEPCO
Receiver
RF Input Impedance
The RF input impedance shall be 50 ohms.
Sensitivity
-6
Sensitivity for a data rate of 9.6 kbit/s and BER of 10 should be at least
90dBm.
Spurious Responses
The spurious responses attenuation shall be better than -60 dBc below carrier
level.
Spurious Emissions
Total spurious emissions shall be less than 5(10) nW from the antenna socket.
Reverse Polarity
The equipment shall be protected against reverse polarity at the supply input.
Adjacent Channel Selectivity
The adjacent channel selectivity shall be better than 70 dB.
11.3
ANTENNAE
11.3.1
Directional Antennae
The Bidder shall offer a robust directional antenna with a Gain of > 10 dB. The
actual antenna for each site may be adjusted according to the result of the detailed
site survey.
The type offered shall be fully described and shall be supplied complete with the
necessary mounting hardware to enable the installation at all locations.
The antenna mountings shall permit adjustment of the antenna in elevation and
azimuth after installation. The amount of adjustment provided shall be stated in
the Tender.
SPECIFICATION TS-GN-06
EEPCO
The following information shall be provided in the Bidder 's technical proposal in
respect of each type and size of antenna offered:
The forward gain with respect to a standard half wave dipole.
The beam-width at the half power points.
The VSWR.
A plot of the polar radiation pattern of a typical antenna of each main type, in
a horizontal plane.
11.3.2
Antenna Feeders
All antenna feeder cables and terminations required to complete the installations
shall be provided and correctly fitted.
The provision and installation of any feeder support gantries, catenary wires, etc.
is the responsibility of the successful Bidder under this project, as it is the
installation of the feeder cables on the building structures with appropriate
clamping devices and at existing and new masts.
All feeder cables of the co-axial type shall be of the solid of foam dielectric
construction and not require pressurisation. Low loss cables shall be used.
The attenuation per 100 meters of all types of cable offered for the antenna
system, at a stated nominal frequency, shall be given in the Tender.
11.3.3
Antenna Structures
The purpose of this Item 11.3.3 is to have comparable bids. The actual heights of
antenna structures shall be defined after the Contractors detailed Site Survey
specified in Item 11.6.
The Tender shall include an antenna tower of height 30 m, guyed type, for
Control Centre Site in town Regarding the other sites, the Bidder shall base his
Tender on the assumption that a 5 m steel tube installed can be used at the
remote station . The Tender shall include these steel tubes with all the necessary
mounting accessories.
The unit prices shall be complete including the design (including soil
investigation), fabrication, shipment, erection and grounding of all antenna
towers.. The Contractor shall also be responsible for provision of aircraft warning
lights and painting, as applicable. The Tender shall submit details of proposed
antenna towers with his tender. The Contractor shall prepare and submit for
approval strength calculations.
11.4
CABLING
11.4.1
General
All cabling shall be arranged in such a way that disturbances on the other systems
at control centre and substations are avoided both during normal conditions and
faults. All cables except the grounding wires shall be marked in accordance with
the cable and numbering plan. All cabling shall be rated for continuous service
under climatic conditions stated. Protection against rodents shall be considered
when designing cubicle external cabling.
SPECIFICATION TS-GN-06
EEPCO
All grounding shall be made with sheathed copper cable. The sheath shall have
green-yellow colour. All connections to the grounding grid of the station shall be
made with a minimum cable area of 16mm2. Grounding wires inside cubicles can
be made with thinner grounding cable but dimensions less than 10mm2 should be
avoided.
Outdoor cables shall be armoured. Indoor cables shall normally be shielded.
Vertical cables running outdoor or through floor indoors shall be mechanically
protected up to a height of 1 m over the floor or ground. The latter also applies
for the antenna cable included in the delivery.
11.4.2
11.4.3
11.4.4
11.5
SPECIFICATION TS-GN-06
EEPCO
SECTION 12 - DOCUMENTATION
Brief description of the extent of the civil works is given below, however, the
Bidder should familiarise himself with the subject matter during the compulsory
site visit.
Cable routes, either trenches or conduits need to be constructed from the existing
cable trenches to the locations of the new panels, as required. Some facilities to
house the equipment shall rehabilitated. This mainly consists of cleaning-up, rust
removal and rust proofing as well as of touch-up painting.
11.6
12.
DOCUMENTATION
12.1
GENERAL
All drawings and documentation shall be in English. The number of copies and
the dates of submission of the documentation shall be as follows:
Six(6)hardcopysetsofAsBuiltdrawingswithinthree(3)monthsaftersuccessfully
performed SAT.
SPECIFICATION TS-GN-06
EEPCO
SECTION 12 - DOCUMENTATION
Two (2) softcopy (pdf) sets of As Built drawings within three (3) months
after successfully performed SAT.
System documentation
Equipment documentation
Test documentation
Installation documentation
System operating instructions shall be included with the above. With a computer
based project the software task definition documentation may be presented in
such a way that it can also be used as the system operating instructions.
The documentation detailed above shall be in three major divisions, drawings,
operating manuals and maintenance manuals.
All drawings shall be to scale where applicable, be fully detailed and shall not
normally exceed A3 size. All dimensions shall be given in metric units.
All drawings shall have a title, drawing number, issue record, contract number,
and where appropriate a graphic scale and site reference. The revision notes shall
detail the nature of each revision.
12.2
SYSTEM DOCUMENTATION
Block diagrams shall show the flow of information between the identifiable parts
of a system, with thickening of lines where necessary, to show the main flow of
information.
Cubicle wiring diagrams and charts shall show the inter-unit wiring within cubicles
in addition to miscellaneous services provided, i.e. supplies, distribution, alarms
etc.
Interconnecting diagrams and charts shall show the necessary connections
between cubicles of equipment and all items connected to the equipment by
means of external cables. They shall show the type of cable to be used for these
connections and any special arrangements for terminating.
Maintenance manuals shall be supplied covering all subsystems. The maintenance
manuals shall be written round the fault location levels which the Contractor
recommends for on-site maintenance. This documentation shall include all fault
tracing and clearance procedure.
12.3
EQUIPMENTDOCUMENTATION
Equipment instruction manuals shall include circuit diagrams for each unit, subunit and plug- in board used in the complete equipment.
SPECIFICATION TS-GN-06
EEPCO
SECTION 12 - DOCUMENTATION
Equipment drawings shall show the layout of equipment in racks for cubicles, and
the essential mechanical features of all racks, cubicles, units and sub-units.
The circuit diagram for any one unit shall be completely self-contained, selfexplanatory, readily to other diagrams and shall include such information as
supply voltage values and interconnections. Components external to a unit or subunit but essential to its operation shall be shown on the circuit diagram enclosed
in dotted lines and be appropriately identified. All component symbols shall be
marked with their circuit references and the nominal value of components shall be
marked on the circuit diagram where the component list is not included on the
same diagram. The function of all controls, switches and indicating devices shall
be indicated in accordance with the inscription on the equipment. Spare contacts
fitted to relays and switches shall be shown on the diagram.
Component lists shall state the value, tolerance, rating, type number,
manufacturer, and the Contractor's circuit reference number.
12.4
12.5
ADDITIONAL INFORMATION
The Contractor shall also provide all the drawings and documentation required
for successful installations and commissioning as well as for subsequent
operations and maintenance of the plant.
As a minimum requirement, the following shall be included
Material specifications
Principle drawings of process adaptation
Location (layout) drawing of new equipment installations
Cable routes drawing
IFC panel internal circuit diagrams
Cable list
Wiring (connections) schedule for RTU IFC cables
Wiring (connections) schedule for IFC - Process cables
Up-date of existing process drawings: the Contractor shall up-date the existing
process circuit diagrams regarding the modifications / additions to the existing
process. Connections of signals readily available on terminal blocks are not
SPECIFICATION TS-GN-06
EEPCO
SECTION 13 - TRAINING
13.
TRAINING
13.1
INTRODUCTION
The Contractor shall make suitable and adequate arrangements for the training of
Employer's maintenance and operational staff, during the engineering,
manufacture, construction, commissioning and defects liability periods.
The Contractor shall submit for the approval of the Employer a training
programme for the staff who are to maintain and operate the equipment.
Training for the following categories of staff shall be included in the contract. In
below, the quantities of courses and staff are per Control Centre System i.e. the
bid shall include two complete sets of training packages.
13.2
13.3
SPECIFICATION TS-GN-06
EEPCO
13.4
SECTION 13 - TRAINING
OPERATOR TRAINING
The Operator training package shall be for thirteen (13) persons in total. Operator
training will be organised on Site at Control Centre.
The objective of the Operator training is to provide the trainees with in-depth
knowledge of the use of the various functions, for effective day-to-day operation
of the power system from the Control Centre.
SECTION 14 - SCHEDULES
SPECIFICATION TS-GN-06
EEPCO
14.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
14.1
Item
Unit
Requirement
Bid Offer
General
1.1
1.2
1.3
1.4
1.5
2
2.1
2.2
2.3
2.4
2.
3
3.1
3.2
4
4.1
4.2
4.3
4.4
5
5.1
5.2
5.3
5.4
5.5
ts-gn-06 r1 scada for 7 regional towns 2013-06-06
SECTION 14 - SCHEDULES
SPECIFICATION TS-GN-06
EEPCO
14.2
SECTION 14 - SCHEDULES
SPECIFICATION TS-GN-06
EEPCO
14.3
SPECIFICATION TS-GN-06
EEPCO
15.
SPECIFICATION TS-GN-06
EEPCO
16.
LPA-GECE
EEPCo
Item
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7
5
5.1
5.2
5.3
5.4
5.5
5.6
5.7
6
6.1
Main server
Name of manufacturer
Country of origin
Type
Processor
Processing speed
HDD with Raid
Internal Didk drive
RAM speed
FEP servers
Name of manufacturer
Country of origin
Type
Processor
Processing speed
HDD
RAM speed
Unit
Requirement
GHz
TB
GB
GB
Xeon
>2.5
1
500
256
GHz
TB
GB
Xeon
>2.5
1
256
GHz
TB
GB
Xeon
2.5
1
256
GHz
TB
GB
Xeon
2.5
1
256
GHz
GB
GB
Xeon
2.5
500
16
Bid Offer
i7 quad
Page 1 Date: 12/06/2013,
LPA-GECE
No
6.2
6.3
6.4
7
7.1
7.2
7.3
7.4
7.5
8
8.1
8.2
8.3
8.4
8.5
9
9.1
9.2
9.3
9.4
10
10.1
10.2
10.3
10.4
11
11.1
11.2
11.3
11.4
11.5
12
12.1
12.2
12.3
12.4
13
13.1
13.2
13.3
13.4
14
14.1
14.2
EEPCo
Item
Unit
Requirement
Processing speed
HDD
RAM speed
GPS Receiver
Name of manufacturer
Country of origin
Type
Type tested
Standard to which complies
WAN Router
Name of manufacturer
Country of origin
Type
Type tested
Standard to which complies
Modem
Name of manufacturer
Type
Type tested
Standard to which complies
Video Projection System
Name of manufacturer
Type
Type tested
Standard to which complies
UPS
Name of manufacturer
Main system
Battery
Type tested
Standard to which complies
Dual Master MAR Radio system
Name of manufacturer
Type
Type tested
Standard to which complies
Remote MAR Radios
Name of manufacturer
Type
Type tested
Standard to which complies
Communication Link Equipment at Remote
Station
Name of manufacturer
Type
GHz
TB
GB
2.5
1
32
Baud
19.2
Bid Offer
Ah
LPA-GECE
No
14.3
14.4
15
15.1
15.2
15.3
15.4
16
16.1
16.2
16.3
16.4
17
17.1
17.2
17.3
17.4
18
18.1
18.2
18.3
18.4
19
EEPCo
Item
Unit
Requirement
Bid Offer
Type tested
Standard to which complies
Data Concentrator
Name of manufacturer
Type
Type tested
Standard to which complies
Electronic Trivector Meter
Name of manufacturer
Type
Type tested
Standard to which complies
FRTU
Name of manufacturer
Type
Type tested
Standard to which complies
Diagnostic Test Kit
Name of manufacturer
Type
Type tested
Standard to which complies
Protocol Test Set H/W and S/W
LPA-GECE
EEPCo
Description
Requirement
Bid Offer
Normal Activity
1
2
High Activity
1
2
1
4
2
2
2
2
4
4
10
20
30
20
40
30
15
APPENDIX-1
SCADA/DMS Control Centre CONFIGURATION
INKJET PRINTE
VPS
LASER PRINTER
GPS RECEIVERS
#2
LAN
SWITCH
COMMUNICATION
SERVERS
MASTER MAR RADIOS
EEPCo
ENGG.& TRAINING
SERVERS
WEB SERVERS
15kV LINES
SECTLISER
SECTLISER
15kV LINE
15kV LINE
CAPACITOR
CAPACITOR
DTR METER
15kV LINE
15kV LINE
DTR METER
RMU
RMU
CAPACITOR
CAPACITOR
15kV LINE
FRTU
15kV LINE
FRTU
DTR METER
DTR METER
EEPCO
SPECIFICATION
TS-IN-01
SPECIFICATION TS-IN-01
EEPCO
Date
Brief Description
Rev 0
Mar 2013
First Issue
Rev 1
April 2013
Enhancements in installation.
Page: i , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
INSTALLATION OF OVERHEAD LINES AND POLE MOUNTED
EQUIPMENT
1
1.
SCOPE
1
2.
REFERENCE STANDARDS
1
2.1
CONFLICT:
3.
4.
1
2
4.1
4.2
4.3
4.4
4.5
SUPERVISION
QUALITY OF MATERIAL
STANDARD OF WORKMANSHIP
WAYLEAVES AND ACCESS TO SITE
TREES
2
2
2
2
4
5.
6.
EXTENT OF INSTALLATION
ESTABLISHING PROPOSED ROUTE OF LINE
4
5
6.1
6.2
6.3
6.4
6.5
6.6
5
5
5
6
6
6
7.
7.1
7.2
7.3
7.4
7.4.4
7.5
7.5.1
7.6
7.7
GENERAL
LINE TO GROUND CLEARANCE
CLEARANCE TO BUILDINGS
CLEARANCES BETWEEN POWER LINES
Clearances to communication lines
RAILWAY CLEARANCES
Minimum Clearance between Railway track and overhead lines
TELEPHONE LINE CROSSINGS
RIVER CROSSING
7
7
8
9
9
10
10
10
11
8.
11
8.1
8.2
8.3
11
12
12
9.
ERECTION OF POLE
13
9.1
9.1.1
9.2
13
13
14
Page: ii , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
9.3
9.4
9.5
9.6
9.7
9.8
9.8.1
9.8.2
9.8.3
BASE CONCRETING
POLE ERECTION
POSITION OF POLE
BACK FILLING
ERECTION OF DOUBLE POLE (D.P) STRUCTURE
CONCRETING OF POLES
Locations to be Concreted
Size of Concrete
Guidelines for Concreting
15
15
15
15
16
16
16
16
16
10.
17
10.1
10.2
10.3
FACTORS OF SAFETY
NEW 33KV AND 15KV OVERHEAD NETWORK
LV BARE OVERHEAD LINES
17
18
19
11.
19
11.1
11.2
11.3
11.4
11.5
LOCATION OF GUYS
COMPONENTS OF GUY ASSEMPBLEY
GUIDELINES FOR ERECTION OF GUYS
STAY WIRE
GUY INSULATORS
19
19
19
21
21
12.
21
12.1
12.2
12.3
12.4
12.5
12.6
12.7
12.8
12.9
12.10
12.11
21
21
21
22
22
22
22
22
22
22
23
13.
23
13.1
13.2
13.3
13.4
13.5
13.6
13.7
13.8
23
23
24
24
25
26
26
13.9
13.10
27
28
29
SPECIFICATION TS-IN-01
EEPCO
14.
15.
30
30
15.1
15.2
15.3
30
30
31
16.
INSTALLATION OF EQUIPMENT
32
16.1
16.2
16.3
16.4
LINE DISCONNECTOR
LINKS
DROP OUT FUSES (DO'S)
SURGE ARRESTERS
32
32
32
32
17.
18.
33
33
18.1
18.2
18.3
18.4
18.5
33
33
34
34
34
19.
EARTHING
34
19.1
19.2
19.3
19.4
19.5
GENERAL
COMMON REQUIREMENTS
MV EARTHING REQUIREMENTS
LV SYSTEM EARTHING REQUIREMENTS
EARTHING OF CONCRETE POLES
34
35
36
37
38
20.
21.
38
39
21.1
21.2
21.3
21.4
21.5
39
40
40
41
41
Page: iv , 26-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-IN-01
EEPCO
SCOPE
This specification includes the installation requirements of Overhead Line of bare
or insulated conductor as well as the installation of Pole mounted Distribution
Transformers
2.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
2.1
TS-GN-01
TS-CO-01
AAA conductors,
TS-CO-02
TS-CO-05
Insulators,
TS-CO-06
CONFLICT:
See spec TS-GN-02 General Contractual obligations.
3.
The site survey of the overhead line routes for use in the Contractors detail
design.
The supply of all sundry materials and equipment not provided by the
Employer required for the erection of the overhead lines, transformers,
switchgear, distribution pillars, and all other items as required in the
Specification and Schedules.
Page: 1 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
If applicable the taking Over from the Employer, delivery to site, erection,
site testing and setting to work in accordance with the manufacturers
instructions the equipment and materials as listed.
Final route planning of the overhead lines, and site location of transformers
and all other equipment together with the provision of the drawings for
wayleaves, municipal approval purposes and final records.
The digging and clearing after pole installation of ground around the poles.
The erection, site testing, setting to work and remedying of defects of the
items of work in accordance with the Specification and Schedules.
The Contractor must allow for all material, plant and labour required for the
supply and erection of the structures as indicated on the detail drawings and
as per the Bill of Quantities.
Bidders must allow for the supply and installation of all material required
for the service connection to each consumer.
4.
GENERAL REQUIREMENTS
4.1
SUPERVISION
All work on site shall be supervised by a sufficient number of representatives of
the Contractor who are fully experienced in work of the type covered by the
Specification.
4.2
QUALITY OF MATERIAL
Only new and unused material of superior quality may be used. All materials shall,
where relevant comply with the applicable Standard and specification. It should be
noted that all materials supplied under this contract as being IEC, BS approved
shall bear the relevant approving body mark unless no such mark is applicable for
a specific item.
4.3
STANDARD OF WORKMANSHIP
The electrical installation of this contract must be carried out by qualified
electricians and cable jointers in accordance with the best modern methods.
The Project Manager reserves the right to reject any work which, in his opinion, is
not completed in a neat and orderly fashion and in accordance with accepted
practice.
4.4
Page: 2 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
such facilities will not include facilities for storing material. The necessary
agreements for both the removal of obstructions such as trees and pipes and for
the removal or guarding of telephone and power lines will be arranged by the
Employer.
The Contractor shall, at his own expense, do what is necessary to make every
access suitable for his use and shall take all reasonable precautions to avoid
damage to land, property, roads, crops, field drains, fences, walls, hedges, gates
and the like and shall ensure that the work is adequately supervised so that
damage is reduced to the minimum. The Contractor will be liable for all damage
arising by or in consequence of the works except damage to crops and shall pay
compensation or make good at the option of the Employer. The Contractor shall
dispose of all spoil and surplus material after erection.
The Contractor shall at all times keep sites free from obstruction, waste materials
and rubbish and shall remove from the sites at his own expense all surplus
materials and temporary works as soon as they are no longer required for the
erection of the Works. On completion of the Works, the Contractor shall leave
the sites clean and in a workmanlike condition to the satisfaction of the Project
Manager.
The Contractor shall be responsible for maintaining agreed access routes, without
undue widening, in a usable condition for the duration of the Contract and the
wayleave grantor shall not be put to any inconvenience in gaining access to his
land or buildings and no unauthorised access route shall be taken by the
Contractor.
Adequate provision shall be made by the Contractor to prevent the straying of, or
damage to, livestock during the execution of the Works and until the permanent
reinstatement of fences, walls, hedges, gates and the like is completed.
The Contractor shall be liable for any damage to or loss of livestock due, in the
opinion of the Project Manager, to failure to comply with the above requirements.
By the date for access to the overhead line and underground cable routes stated
by the Contractor in his Master Programme, the Employer shall (subject to the
Contractor being then ready to commence work) provide over the whole length
of the routes such right of access for the Contractors staff to carry out survey
work, investigation of the general foundation conditions, construction, testing and
commissioning of the required Works in accordance with the Specification.
The Contractor shall make all necessary arrangements (other than questions of
wayleaves and access) with the occupiers of the routes, but if any difficulty shall
arise the Contractor shall inform the Project Manager thereof. The Project
Manager shall thereupon take such steps as may be necessary to resolve the
difficulty.
The Contractor shall make any necessary arrangements and take any necessary
precautions where the routes cross roads, tele-communication lines or cables,
buildings, power lines or cables, orchards, gardens, or other obstacles or ground
over which erection cannot be carried out in the normal manner. The Contractor
shall provide all necessary temporary works to overcome the obstacles and shall
comply with all reasonable requirements of the Authorities concerned.
Page: 3 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
The Contractor shall give the Project Manager at least 14 days notice of his
intention to install any service connection, to enable the Employer to make the
necessary arrangements for access to the consumers premises.
4.5
TREES
No trees shall be damaged, cut or pruned during the execution of the contract
unless specifically authorised by the owner of the plot/s nearest to the tree.
Should any trees have to be removed by the Contractor he shall arrange for the
complete uprooting and trimming of tree trunks as well as the stacking of all
trunks and branches. Holes caused by the uprooting shall be filled and
consolidated. Rubble shall be removed to leave the site neat and tidy. The
Contractor shall be held responsible for any damage which may occur during the
felling of trees.
Where trees are to be pruned, this shall be done neatly to the satisfaction of the
Project Manager.
5.
EXTENT OF INSTALLATION
The scope of overhead line installation work is subdivided into several parts and is
given below.
(i)
(ii)
(iii)
Erection of poles,
(iv)
Concreting of poles,
(v)
(vi)
(vii)
(viii)
Earthing,
(ix)
(x)
Miscellaneous items,
(xi)
Page: 4 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
6.
6.1
(ii)
Conduct reconnoitre survey of the area in which the line has to pass,
The following points shall be kept in view while conducting survey.
(iii)
(iv)
(v)
(vi)
(vii)
Provision shall be made for failure containment cut points / DP angle poles,
(viii)
(ix)
All road crossings river crossings should be perpendicular and not diagonal after
different cross points(buildings),
(x)
(xi)
6.2
AREAS TO BE AVOIDED
The areas to be avoided for routing the line are,
(i)
Proximity to Aerodromes,
(ii)
(iii)
(iv)
(v)
Sensitive areas such as, bird or wild life sanctuaries, bird habitants, culturally and
historically important resources, gardens,
(vi)
6.3
PROFILE OF ROUTE
(i)
Having provisionally fixed the route on the survey map, perform detailed survey
and fix angle points and mark with survey stones,
(ii)
Prepare a route map showing the proposed line and various railway lines,
communication lines, HV power lines, rivers and stream crossing on survey map
of at least 1:1,000 and details on scale as required, providing sufficient details.
(iii)
All LV lines along with pole locations are to be marked on local map to scale
1:1000.
(iv)
After fixing the angle points, intermediate spans are to be fixed, keeping the spans
uniform in length. They shall be as near as possible to the basic design span.
Page: 5 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
6.4
(v)
(vi)
For 15kV and 33kV lines, prepare a ground profile with pole positions, conductor
sags and ground clearances marked,
(vii)
Care shall be taken to see that protruding pegs marked during survey are not
damaged.
6.5
WAY LEAVES
After finalizations of the route, the proposals for following way leaves and right
of way, as applicable have to be obtained from the following organizations.
6.6
Forest approval
TREE CUTTING
Tree cutting shall be done as mentioned in Table 6.6
Table 6.6
Sl.
No
Voltage
1.
LV
NIL
2.
15kV
Spur
lines
Nil
3.
15kV
trunk
lines
Nil
Relaxation
Page: 6 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
7.
Mark the trees for felling, by a ring of white paint at one meter height from
ground level and submit the proposals to the competent authorities for
granting permission.
If the line has to pass through gardens, orchards requiring tree cuttings, pay
compensation to the owners as fixed by the concerned authorities
(Department of Horticulture or department of forest etc.,) before tree
cutting,
Take all possible steps to see that standing crops etc., are not damaged while
attending to tree cutting,
Arrange to remove the cut trees as soon as possible, stack them neatly in
one place and hand over to the authorities.
7.1
GENERAL
For the purpose of computing, the vertical clearance of an overhead line the
maximum sag of any conductor shall be calculated on the basis of the maximum
sag in still air and the maximum temperature as specified in the Ethiopian
Building Code EBCS-10 Electrical Installation of Buildings.
Similarly, for the purpose of computing, any horizontal clearance of an overhead
line the maximum deflection of any conductor shall be calculated on the basis of
the wind pressure specified in the EBCS-10 (or may be taken as 350, whichever is
greater).
7.2
Upto
0.75kV
0.7515kV
15-50kV
Along streets
5.5
6.1
6.7
Across streets
5.5
6.1
6.7
Page: 7 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
7.3
CLEARANCE TO BUILDINGS
7.3.1
7.3.2
(i)
When the line passes adjacent to the building a horizontal clearance of 1.2 m shall
be maintained,
(ii)
Any conductor so situated as to have a clearance less than that specified above,
shall be adequately insulated and shall be attached by means of metal chips at
suitable intervals to have earthed bearer wire having a breaking strength of not
less than 350 kg.
(iii)
2.5m
35kV
2.55 m
45kV
2.65 m
60kV
2.8 m
110kV
3.3 m
The horizontal clearance between the nearest conductor and any part of such
Building shall, on the basis of maximum deflection due to wind pressure be not
less than:For high voltage lines up to and including15kV
1.2 m
2.0 m
Voltage in kV
L.V
132kV
1
2
3
0.40
15
33
1.22
1.33
2.44
2.44
2.44
2.44
3.05
3.05
4.83
Page: 8 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
7.4
7.4.1
7.4.2
Voltage in
kV
Up to
0.75
0.75 to
8.7
8.7 to
50
Up to 0.75
0.61
0.61
1.22
0.75 to 8.7
0.61
0.61
1.22
8.7 to 50
1.22
1.22
1.22
Voltage Rating
7.4.4
Table 7.4.3
Clearance between
circuits in meters
(Vertical formation)
15kV
1.10
0.90
33kV
1.37
1.37
Up to 0.75kV
0.75kV to 8.7kV
8.7kV to
50 kV
1.22
1.83
1.22
Page: 9 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
7.5
RAILWAY CLEARANCES
7.5.1
7.5.2
Inside
Station
Area
Outside
Station
Area
Inside
Station
Area
Outside
Station
Area
Remarks
Upto and
including
15kV
By UG Cable only
Above 15kV
including
33kV
10.06
7.62
8.84
Above 33kV
including
66kV
Subject to approval
by railways
6.40 otherwise U.G
cables or crossing
by tower lines
10.36
7.92
9.15
6.71
Voltage
7.5.3
Table 7.5.2
For Broad, Meter and Narrow Gauges
Inside Station Area, m
By UG Cable only
15.06
13.06
15.56
13.56
7.6
Page: 10 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
The angle of crossing of power and telecom lines shall be as near to the right
angle but not less than 60o in any case.
Standard guarding is to be provided and earthed at crossings of telecom lines and
power lines
7.7
RIVER CROSSING
Minimum clearance of 3mts would be required for the conductors over the
highest flood level in at least last 50 years
Structures should be located at such places that they could be approached under
flood condition also. The foundation of structure should be sound so that it may
not get eroded or damaged due to rain water.
In case of navigable rivers, consultation with navigation authorities is necessary, to
determine the minimum clearance required.
8.
8.1
8.1.1
General Description
The line shall be constructed as single circuit, three phase three-wire, single phase
two-wire (live-live) or single phase single wire earth return on earthed Spun
concrete pole with steel cross arms. These may be either single or double circuit
lines. Poles shall normally be directly embedded in the ground. The poles shall be
provided with stays at angle and terminal positions.
(i)
(ii)
Designs Spans
Pole height
Basic span
50m
Line Conductor
The preferred conductor sizes are,100 and 150 and in some places 200mm, for
main lines.
(iii)
(iv)
Insulators
Pin or post insulators shall be used at intermediate and light angle positions. For
heavy angle and terminal positions, disc insulators complying with shall be used.
To achieve phase to earth clearance for jumper connections, additional insulators
shall be used, wherever necessary.
(v)
Page: 11 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
8.2
(ii)
Design spans
Pole Height
(iii)
9m, 12m
Line conductors:
The preferred conductor sizes are 50, 100, 150 and 200mm2.
Express lines shall be 200mm2.
The preferred conductor size for the main line is 150mm2
The preferred conductor sizes for spur lines are 50 mm and 100 mm2.
(iv)
(v)
Insulators
Pin or post type insulators shall be used at intermediate and light angle positions.
For heavy angle and terminal positions, disc insulators post insulators may also be
used for heavy angle position provided it can be established that the insulators are
capable of containing the forces in the line. To achieve phase to earth clearance
for jumper connections, pin insulators shall be used, where necessary.
(vi)
8.3
General Description
The lines shall be constructed as single circuit/double circuit 3-phase four-wire, 1
phase 2-wire or 1 phase 3-wire lines on 9m poles. 9m poles shall be used for
construction activities in the urban centres.
The 9m poles shall also be used for rural electrification and on spur lines in the
urban areas. On minor roads they should be limited to stringing two conductors
on either side of the poles.
The lines shall be constructed on spun concrete poles with spool type insulators.
Poles shall normally be directly embedded in the ground. At angle and terminal
positions, the poles shall be stayed.
Bundled Aerial Conductors (ABC) may be used at the discretion of the Project
Engineer.
Page: 12 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
(ii)
Factors of Safety
As described in relevant clause of this specification
(iii)
Design Spans
Basic Span 50-60m
b)
Line Conductor
The preferred conductor size are 100 mm and in certain places based on the
requirement 150mm is also used. 50mm. 25mm2 AAAC conductors may be used
on spur distribution lines.
(i)
(ii)
Insulators
To achieve phase to earth clearance for jumper connections, insulators shall be
used, where necessary.
(iii)
(iv)
Conductor Clearance
As described in relevant clause of this specification
(v)
Proximity to Buildings
As described in relevant clause of this specification
(vi)
(vii)
Poles
9m poles shall be used for rural electrification and at urban locations where major
roads are not likely to be crossed. At minor road crossings, two parallel wires shall
be strung on either side of the pole in the vertical plane.
9.
ERECTION OF POLE
9.1
9.1.1
Page: 13 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
The pits for the supports shall be excavated in the direction of the line, as
this will facilitate the easy erection of supports, in addition to giving greater
lateral stability.
The pits are to be excavated to a size of 1.2 meters x 0.6 meters with its
longer axis in the direction of line.
9.2
Planting Depth in
Ground (Mts)
1.5
1.8
2.0
Exceptions
In wet soil and black cotton soil
depth may be increased by 0.2 to
0.3 m and limit wind span
FOUNDATIONS
Depending on type of soils, the sub soil water table and the presence of surface
water five types of foundation designs will be used for locations classified in the
following manner.
9.2.1
Wet type
To be used at locations, where sub soil water is met at 1.8 meters or more below
the ground level ; Locations where surface water for long period with water
penetration not exceeding one meter below the ground level eg: paddy fields.;
Locations in black cotton soils.
9.2.2
9.2.3
9.2.4
Rocky Type
To be used at locations where hard rock is met with and where the bond strength
between the rock and the concrete will be very high.
9.2.5
Dry Type
When the subsoil water is met at more than 1.8 meters below the ground level and
only dry crops are raised and soils are normal dry cohesive or non cohesive.
Prepare a statement of type of foundations to be used for each location for
approval by the Engineer.
The factor of safety for foundations shall be at least 2.20
Page: 14 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
9.3
BASE CONCRETING
Check alignment again after the excavation of pole pits is completed,
After satisfying with the alignment a pre-cast R.C.C Base plate of size 450x450x75
mm or 200x200x6mm MS Plate as Base Plate shall be put in the pit. Or
alternatively cement concrete padding of 1.2*0.6*0.075 mm depth with 1:3:6 mix
(0.05M cu mtr may be used to increase the surface contact between the pole and
the soil. The levelling of Base plate / cement concrete padding shall be checked to
ensure a level base for erection of the pole. The design details of the R.C.C Base
plate are furnished in the enclosed drawing (B1). If cement concrete padding is
provided, curing of concrete is to be done for a period of 14 days by covering the
concrete with gunny bags.
9.4
POLE ERECTION
The pole erection is done by five methods
Deadmans method
Bipod Method
9.5
POSITION OF POLE
All poles in the tangent / intermediate locations shall be positioned in the pit and
that the bigger section modulus of the pole is always transverse to the length of
the line.
At tension points the bigger section modulus of the pole shall be in the length of
the line.
9.6
BACK FILLING
Back filling shall normally be done with excavated soil, unless it consists of large
boulders / stones in which case the boulders shall be broken to a maximum size
of 80mm.
The back filling materials should be clean and free from organic or other foreign
materials.
Page: 15 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
The earth shall be deposited in maximum 200 mm layers, levelled and wetted and
rammed properly before another layer is deposited.
9.7
9.8
CONCRETING OF POLES
9.8.1
Locations to be Concreted
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
9.8.2
Size of Concrete
The size of concrete shall be as mentioned in Table 9.8.2
Table 9.8.2
1
Size of Support(m)
Concrete size(m)
1.
9.0
2.
12 to 14.0
3.
Stay Concrete
Curing of concrete is to be done for 14 days by covering the concrete with gunny
bags and the balance portion of the pit shall be back filled with earth. The back
filling shall be done as per the specification.
9.8.3
Page: 16 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
(i)
The cement concrete used for the foundations shall be of 1:3:6 Grade or as per
the schedule of quantities.
(ii)
The sand used for the concrete shall be composed of hard silicon materials and
well sieved. It shall be clear and of a sharp angular grit type and free from earthy
or organic matter and deleterious salts.
(iii)
The aggregate shall be of clean broken hard granite approved by the Engineer. It
shall be hard, close grained quality. It shall also be as far as possible cube like,
preferably angular, but not flaky, perfectly clean and free from earth, organic or
other deleterious matter. 20mm aggregate shall be used for base concreting and 38
mm aggregate for pole concreting.
(iv)
The water used for mixing concrete shall be fresh and it should be clean and free
from oil, acids and alkali. Saltish or brackish water should not be used.
(v)
(vi)
After concreting to the required height, the top surface should be finished
smooth, with slight slope towards the outer edge to drain off the rain water falling
on the concrete.
(vii)
In wet locations, the site must be kept completely de-watered both during the
placing the concrete and for 24 hours after completion. There should be no
disturbances of the concrete by water during this period.
(viii)
The forms of moulds shall not be removed before a lapse of about 24 hours after
the completion of concreting. After removal of the form moulds, the concreted
surfaces, wherever required, shall be repaired with a rich cement and sand mortar
in the shortest possible time.
10.
10.1
FACTORS OF SAFETY
The following factors of safety shall be maintained in all design and construction,
allowing for conductor sag and swing.
Conductor
2.5
2.0
2.0
2.0
Cross arms
2.5
Foundations
2.0
Page: 17 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
10.2
10.2.1
10.2.2
Poles
Predominant poles for 15kV and 33kV lines shall be 12 and 14 m high
respectively in the Towns. 9 &12m (respectively) poles may be used depending on
the terrain of the project location.
The poles shall be of spun concrete type and in selected instances they may be
wood or steel as it may be mutually agreed.
At pole mounted substations, voltage regulators, expulsion fusegear and load
isolator positions, consideration shall be given to the use of single class two poles,
unless the designs at these positions do not allow the use of single poles.
"H" pole structures shall be used where the installations of the above equipment
do not permit the use of single poles. The H structure shall be erected with
1.8m pole members and shall be in line or perpendicular to the overhead line as
appropriate.
10.2.3
Binding-in Wire
On 33kV and 15kV pin insulators, the conductor shall be bound-in on the top
groove, using two suitable stirrups in each case. The bind shall be formed of a
single layer of closely wound wire, extending at least 40mm beyond the stirrups.
The bind shall be wound in opposite directions, on each side of the insulator.
With Copper conductors, the bind shall be formed of a 2.0mm diameter annealed
copper binding wire.
In the case of Aluminium conductors, the bind shall be formed of two stirrups,
with 2.5mm diameter Aluminium binding wire. In addition, Aluminium chafe tape
shall be used, wrapped in a direction opposite to that of the conductor lay. The
chafe tape shall cover the portion of the conductor which is in contact with the
insulator, and extend at least 40mm under the bind, on each side.
Aluminium chafe tape shall also be used on Aluminium earth-wire, underneath
the clamps or binds. Where a clamp is used (on existing poles only), the chafe tape
shall extend at least 10mm beyond the bearing surface.
At 33kV and 15kV angle and terminal pole positions where disc type strain
insulators are used, the conductors shall be held in suitable strain clamps,
manufactured to an approved design, and of a material suitable for the
conductors.
Page: 18 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
10.3
11.
11.1
LOCATION OF GUYS
Guys are to be provided to counter balance the load on the supports due to
pulling of the conductors, so that the supports remain straight in vertical position
without bending in any direction.
The guys shall be provided at the following locations.
(i)
Angle locations
(ii)
(iii)
(iv)
(v)
Two numbers storm guys to the central pole between two cut points
Perpendicular to the line direction.
11.2
Anchor Plate
Anchor Rod :
Table 11.2
R.C.C plate of size 450x450x 75mm or MS plate of
200 x 200 x 6MM.
16 1800mm length for 7/10 stay wire.
20 1800mm length for 7/8 or 7/10 stay wire
11.3
Eye Bolt
Turn buckle
M.S washer
50 x 50 x6 m
Thimble
As per drawing
Excavation of pit
Page: 19 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
(ii)
Fixing of base plate to the stay rod and concreting and back filling of the pit.
(iii)
Fastening guy wire to the support along with stay clamp and turn buckle, after
fixing guy insulator(s) as per the drawing.
(iv)
(v)
The marking of the guy pit for excavation, the excavation of pits and setting of
the anchor rod must be carefully carried out. The stay rod shall be placed in a
position such that the angle of inclination of the rod with the vertical face of the
pit is 45o.
(vi)
The anchor plate shall be of size 450 x 450 x 75mm, made of RCC with 1:2:4 ratio
and using 20mm machine crushed granite metal. Alternatively M.S. Plate of size
450 x 450 x 10mm or 600*1200*75mm (DWG. No B2) may also be used. The pit
shall be filled with 1:2:4 cement concrete using 20mm granite metal. The size of
concrete block shall be 600x1200x0.075mm at the bottom covering the anchor
plate completely. The concrete shall be cured for 14 days and balance portion of
the pit back filled with earth as per the specification 10.0.
(vii)
Proper form of moulds adequately braced to retain proper shape shall be used.
The moulds should be made water tight so that cement cream will not come out.
After concreting to the required height the top surface should be finished smooth,
with 1:6 slopes towards the outer edge to drain off water.
(viii)
In wet locations, submerged locations and marshy locations, the site shall be
completely dewatered during concreting and for 24 hours after completion.
Moulds shall not be removed before a lapse of 24 hours after completion of
concreting. After removal of form boxes, the concrete surfaces where ever
required shall be plastered with a rich mix of cement and sand mortar in the
shortest possible time.
(ix)
After the curing time of concrete is over, the free end of the guy wire is passed
through the eye of the anchor rod, bent back parallel to the main portion of the
guy and bound after inserting the G.I. Thimble. The loop is protected by G.I.
Thimble where it bears on the anchor rod. Where the existence of guy wire
proves hazardous, it should be protected with suitable asbestos pipe of 50 mm
diameter and 2mts length, filled with concrete, duly painted with black and white
stripes with enamel paint of approved quality and make, so that it may be visible
at night.
(x)
The Turn buckle shall be mounted at the pole end of the stay and guy wire so
fixed that the eye bolt is half way in the working position, thus giving the
maximum movement for tightening or loosening.
(xi)
Where stay angles of less than 45o are unavoidable the use of stay angles from 30o
to 44o or bow guys or flying stays shall only be done with the approval of the
Engineer. The anchoring and providing of guys for supports shall be done as per
the drawing no G11.
Page: 20 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
11.4
STAY WIRE
The stay wires used for anchoring shall conform to BS 183. The individual wire
used to form stranded stay wire is to be of tensile grade 4 having minimum
tensile strength of 1000N /mm2.
The Sizes of stay wire used shall be as mentioned in Table 10.2.3
Table 10.2.3
11.5
S. No.
Size of Wire
Safe Working
Load
1.
7/2.65
1000 kg
2.
1450 kg
3.
7/4.0 or 7/8
2340 kg
GUY INSULATORS
(i)
(ii)
Guy insulators shall be provided to prevent the lower part of the guy from
becoming electrically energized by contact with the upper part of the guy, when
the conductor snaps and falls on them or due to leakage. No guy insulator shall be
located at less than 3.5mts (vertical distance) from the ground. The minimum
distance along the stay between the point of contact with the pole and the top of
stay insulator is 1.8mts
(iii)
12.
12.1
12.2
12.3
Page: 21 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Only G.I bolts and nuts and G.I Flatwashers and spring washers shall be used for
fixing the pole fittings. The bolts and nuts and washers used .
12.4
12.5
12.6
OFFSET ARRANGEMENT
Where it is not possible to maintain clearances to buildings etc., line conductors
shall be supported offset from the pole by means of a side arm and strut. In such
cases A type pedastals fabricated with 50x8 flat shall be used for fixing pin
insulators. The A type pedastal to be hotdip galvanished before fixing.
12.7
LV
50 x 6 mm
15kV
65 x 8 mm
33kV
75 x 8 mm
12.8
12.9
GENERAL
A rubber packing of 3 to 4mm thickness is to be provided between back clamp
and the support. The cross arm shall be perpendicular to the line direction and
both ends shall be horizontal to the spirit level.
12.10
GALVANIZING
Galvanisation shall be done by hot dip process where any materials is to be
galvanised it should be free form greases and paint etc., During and after
Page: 22 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
galvanising there shall be no logging of blow holes due to the stay of zinc in the
holes after galvanising.
Tests on galvanised samples shall be carried out regularly strictly in accordance
with the relevant standard.
12.11
FIXING OF INSULATORS
The pins for insulators shall be fixed in the holes provided in the cross arm and
the pole top brackets. The hexogonal nut provided to the pin shall be tightened
fully. Spring washer shall necessarily be provided to the pins. The insulators shall
be mounted in their places over the pins and tightened. Slacken the Pin and align
the top groove of the insulator to the conductor direction Retighten pin. Strain
fittings are to be provided at all tension points. One strap of the strain fittings is
placed over the cross arm before placing the bolts in the hole of the cross arms.
The nut of the straps is so tightened that the strap can move freely in horizontal
direction, as this is necessary to fix the strain insulator. The insulators shall be
cleaned and examined for defects before fixing. Insulators with cracks or chips
shall not be used. Disc insulators are to be used for 15kV and 33kV lines and
shackle insulaors for LT lines, at all tension points.
13.
13.1
Jointing of conductors,
13.2
Page: 23 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
13.3
13.4
Page: 24 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Insert the conductor smoothly to the center stop, referring to the mark to assure
complete insertion.
After both ends have been inserted, pull down on the splice to set the Jaws for
permanent installation.
Ensure that, after Jointing the conductor and splice are in straight alignment.
13.5
Page: 25 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
strian on the poles, cross arms, pin insulators, tie wires and conductors, which
might lead to ultimate failure.
The initial stress of the conductor also has to be taken out in order to avoid the
gradual increase in sag, due to setting down of the individual wire. This may be
done by pulling up the conductor to a tension a little above the theoretical tension
for the prevailing temperature and fixed up at that tension with a corresponding
reduced sag. After certain time the conductor will settle down to the corect sag
and tension. A tension of six to seven percent more than the theoretical value
mentioned in the sag tables needs to be given.
Final tensioning and sagging shall be in accordance with the sag and tension chart
of the particular conductor used.
It shall be ensured that maximum tension at 0oC with maximum wind pressure
and no ice loading not to exceed 50% of the ultimate strength.
Tension at 32.2oC (90oF) and still air not to exceed 25% of the ultimate tensile
strength.
The sag should be adjusted in middle span in short sections of line of about five
to six spans and at two spans in other sections. Even when the sheaves are used it
may be necessary to bounce the conductor at intermediate points with a handline
in order to equalise the tension in the various spans. Soaping the conductor
grooves at the supports so that the conductor will slide more freely may also be
resorted to.
13.6
13.7
Page: 26 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
released gradually. If the tension is released with a jerk, an abnormal stress may be
transferred to conductor and support, which may result in the failure of the cross
arms, stay or pole in some cases.
After stringing is completed, all poles, cross arms, insulators, fittings conductor
joints etc are to be checked up to ensure that there have been no deformities etc.
The temporary guys provided at the anchoring supports may be removed .
The excess conductor is to be cut by leaving sufficient length for jumpering. The
ends of the conductor shall be taped properly before cutting.
Once again it shall be checked and ensured that sag is uniform through out the
length and sufficient ground clerances are maintained as per IE rules.
13.7.1
13.8
Page: 27 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Before tying the conductor to the insulators two layers of aluminium tape should
be wrapped over the conductor in the portion where it touches the insulator. The
width and thickness of aluminium tape to be used shall be as specified in the hand
books of aluminium conductor manufacturers. For 15kV and 33kV lines main
conductor to be reinforced with another conductor piece of 500 mm length and
same size and quality as that of main conductor, bent upwards at right angles at
both ends to a height of 50mm. The ends of the stiffner piece to be wrapped with
aluminium tape or provided with binding.
13.8.1
Rules of Tying
Only fully annealed tie wire to be used.
SWG No 6 sizeof aluminium tie wire shall be used.
Sufficient length of tie wire for making the complete tie including an end
allowance for gripping with the hands shall be used. Normally the wire length
varies from one meter for LT lines to 4 meters in 33 KV lines. The extra length
should be cut at each end after the tie is completed. The binding shall be for
400mm length on stiffner piece and 30mm on either end of the stiffner piece.
Tie should provide a secure binding between line conductor, insulator and stiffner
piece.
There shall be positive contacts between the line wire and the tie wire so as to
avoid any chafing contacts.
Use of pliers shall be avoided
Nicking the line conductor shall be for bidden.
Tie wire which has been previously used shall not be used
Harddrawn or AAAC wires or fire burned wires shall not be used, since they are
either partially annealed or injured by over heating.
13.8.2
13.9
JUMPERING
After the stringing is completed jumpering shall be given at the tension points
with the same line conductor by using P.G.Clamps. Two numbers double bolted
P.G.Clamps shall be provided for each jumper. Under no circumstances
P.G.Clamps or binding, to the main line conductors shall be permitted while
providing jumpering except at Tee-off poles, where jumpers are to be given on
the main conductor. Hence precaution has to be taken to leave sufficient
conductor at each tension point for jumpering purpose
Page: 28 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
13.10
13.10.1
Dos
Use proper equipment for binding aluminium conductors at all times.
Use skids or similar method for lowering conductor drums from transport.
Examine reel before unreeling for presence of nails or any other object which
might damage conductor.
Rotate the reel while unwinding the conductor in the direction marked on the reel.
Grip all strands while pulling out the conductor.
Control the unreeling speed with a suitable braking arrangement.
Use wooden rods for suitable braking arrangement.
Use long straight, parallel jaw grip with suitable liners when pulling conductor,
thus avoiding nicking or kinking of the conductor.
Use free running sleeves or blocks with adequate grooves for drawing / paving
conductors.
Use proper sag charts.
Mark conductors with adhesive tape which will not damage the strands.
Make all splicing with proper tools
Chromite or graphite conducting oxide inhibiting grease, should be applied before
cleaning with wire brush, where ever jointing takes place.
13.10.2
Donts
Do not handle conductor without proper tools at any stage.
Do not pull conductors without ensuring that there are no obstructions on the
ground.
Do not pull out excess quantity of conductor than is required.
Do not make jumper connections on dirty or weathered conductor; clean the
conductor using wire brush.
Do not handle aluminium conductor in a rough fashion but handle it with a care it
deserves.
Page: 29 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
14.
15.
15.1
The Fuse cut out shall be cross arm mounted above the transformer and
positioned so that the fuses can be safely operated by pulling stick from a ladder
or platform from the opposite face of the pole from the transformer.
The surge arresters shall be mounted adjacent to the Fuse cut out and connected
on the upstream side of the fuses. The surge arresters shall be directly earthed to
the substation MV grid. Alternatively the Surge Arrester may be an integral part of
the transformer.
The drop lead from the MV line, the connection to the surge arresters and also
the drop lead to the MV bushings shall be single core 35 mm2 XLPE covered. An
insulated boot shall be provided over the exposed metal parts of the MV bushing
to protect against interruptions from bird, snakes, wind-blown debris, etc.
15.2
Page: 30 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
15.2.1
a)
b)
Transformer Rating
50 and 100 kVA 3 phase
All Single phase
If ABC cable is used then the same cable shall be used for the above connections.
15.3
Page: 31 , 26-Apr-13
SECTION 16 - INSTALLATION OF
EQUIPMENT
SPECIFICATION TS-IN-01
EEPCO
The overhead LV distributor tails for the outgoing LV circuits shall be left
sufficiently long to reach the LV cabinet. Where these cables are less than 2.5m
above ground suitable mechanical protection shall be provided. Where
underground LV cable is installed for the outgoing LV circuits the cable shall be
routed from the LV cabinet and provided with suitable mechanical protection.
All cables fixed to the poles shall be nearly secured by stainless steel banding at
intervals of not more than 750 mm.
16.
INSTALLATION OF EQUIPMENT
16.1
LINE DISCONNECTOR
Three-phase line disconnector, of the solid link type, shall be provided at all
points shown on the drawings.
The disconnector shall be mounted on galvanised steel cross-arms as indicated on
the relevant drawings.
The actuator in question shall operate, causing all three links to operate via a
common operating shaft, thus isolating the secondary circuit.
16.2
LINKS
Links shall be provided within the MV rings positioned as shown on the layout
drawings. Line links shall be three single phase units to be operated by means of a
link stick.
The three single phase units shall be bolted to a sturdy "U" channel or cross arm
which in turn shall be clamped to the pole by means of two "U" bolts. All metallic
parts shall be hot dip galvanised after cutting, drilling and welding.
16.3
16.4
SURGE ARRESTERS
Surge arresters will be installed at the following places:-
a)
b)
c)
d)
Page: 32 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
17.
18.
MISCELLANEOUS ITEMS
18.1
18.2
Page: 33 , 26-Apr-13
SECTION 19 - EARTHING
SPECIFICATION TS-IN-01
EEPCO
18.3
18.4
18.5
WORKMANSHIP
It shall be ensured that for the correct erection of line as per specification /
approved drawings and their correct setting and alignment, If the supports and
D.P. Structures after the erection are found to differ from approved route maps
and drawings or to be out of alignment is noticed, they shall dismantle and re
erect them correctly .The supports must be truly vertical and in plumb after
erection and no straining will be permitted to bring them to vertical position.
Verticality of each support shall be checked by the by the Engineer.
Maximum permissible tolerance is 50 mm in respect of verticality.
19.
EARTHING
19.1
GENERAL
Earthing shall be provided in accordance with the requirements of Ethiopian
Building Code(EBCS-10)Electrical installation of buildings and in particular as
mentioned below.
All metallic supports shall be provided with earthing as per drawing G3.
For spun concrete poles, the metal cross arms and insulator pins shall be bonded
and earthed at every pole with earthing as per drawing G3.
Page: 34 , 26-Apr-13
SECTION 19 - EARTHING
SPECIFICATION TS-IN-01
EEPCO
All special supports on which AB Switches etc are mounted shall be provided
with pipe earth as per drawing G4.
Supports on either side of the road, railway track or river crossing shall be
provided with pipe earthing as per G4.
At all tension points at double pole locations the steel and metal parts are to be
provided with pipe earthing as per drawing G4.
All AB Switch handles to be earthed with pipe earth plus operators earth mat as
per drawing G4.
Bentonite shall be used as shown in the drawing No. G3 and G4. Charcoal and
salt shall not be used under any circumstances.
The earthing shall be as per the drawings enclosed to the specification (Drawing
No G3 & G4).
19.2
COMMON REQUIREMENTS
All MV connections of the buried earthing grid shall be constructed with bare
copper conductor not less than 35 mm in cross section. Copper conductor for
earthing may be hard drawn or soft drawn.
1) Earthing rods
All earth rods shall be extensible copper clad steel (or hot dip galvanized) nominal
length 1,500 x 15 mm diameter. Earth rods shall be used singly or jointed as
necessary to achieve a satisfactory earth test. Rods shall be driven so that the top
is not less than 500 mm below ground surface.
Each earth rod assembly shall be fitted with a purpose-designed clamp suitable for
up to three 35 mm2 copper conductors
2) Earthing grids
The conductors and the tops of the earthing rods shall be not less than 500mm
from the natural ground surface.
3) Down conductors
Where the pole top equipment require to be connected to the earthing grid this
shall be of stranded galvanized bare steel 70mm.
For mechanical protection, the earth lead between 2.5 m above ground to 400
mm below ground shall be installed inside a 20 mm diameter black polyethylene
pipe. The polyethylene pipe and conductor shall be secured to the pole by
stainless steel banding at intervals of not less than 500 mm.
The earth lead to each of these earth grids shall be fitted with a test link located
on the pole immediately above the polyethylene pipe and arranged to isolate the
system neutral from the earth grid for testing.
The test link shall be insulated or positioned so that it does not make electrical
contact with the pole or adjacent metal when it is opened.
The connection of the down conductor to the earthing grid will be shall be made
with suitable bimetallic clamps for the sizes of cables to be installed.
Page: 35 , 26-Apr-13
SECTION 19 - EARTHING
SPECIFICATION TS-IN-01
EEPCO
For mechanical protection, the earth lead between 2.5m above ground to 400 mm
below ground shall be installed inside a 20 mm diameter polyethylene pipe, colour
black. The polyethylene pipe and conductor shall be secured to the pole by
stainless steel banding at intervals of not less than 750 mm. All buried earth
conductors shall be not less than 500 mm below the ground surface.
All above ground connections on earth leads shall be made with bolted or
compression fittings rated for not less than the 3-second fault rating of the
associated conductor.
19.3
MV EARTHING REQUIREMENTS
1) Earthing of frames/matalwork
Within the MV network all exposed metalwork not normally alive shall be directly
earthed to a locally established earth system fitted with a test line Locations
include distribution transformer, ABCs, LBS's, MV Capacitor installation, voltage
regulators, etc. Concrete poles, steel cross arm and similar items on other poles do
not require direct earthing. The maximum resistance of the local earth grid for the
metalwork/frames earthing shall be 30 ohm.
2) Earthing of MV surge arresters
MV lightning arresters shall be earthed by an independent connection and shall be
less than 10 ohms. A test link must not be inserted in any lighting arrester earth
connection.
3) Common earthing of lightning arrester and frames
The HV Equipment frame earth and the lightning arresters earth may be
effectively a single earthing system provided that the overall MV earthing
resistance grid at the transformer is less than 10 Ohms.
4) Construction of earthing grid
The MV buried earth grids shall comprise not less than three standard earth rods
spaced 3m or more in a triangular pattern and the prop up structure, substation,
or equipment building. Where site conditions make this impractical the earth grid
shall comprise not less than three standard earth rods spaced 2m or more installed
in a straight line underneath the line of the overhead MV distributor. If additional
earthing is required to achieve the 10 ohm minimum resistance, the earthing grid
shall be extended in a radial pattern with bare copper conductor and rods at not
less than 2 m spacing or the length of the earthing rod whichever is greater.
5) Connection of equipment to earthing grid
All exposed metal at the substation including transformer tank, transformer
bearers, MV fuse supports, LV cubicle frame, etc, shall connected to the earthing
grid with down conductors . The equipment connection shall preferably be in a
ring circuit so that the failure of anyone lead or connection does not leave any
item isolated from earth.
Within buildings and at package substations a suitably rated earth bar shall be used
to connect all earth leads. Two separate earth leads shall be installed from the
equipment above ground to different parts of the buried earth grid. Each lead for
indoor equipment shall be not less than 35 mm2 copper PVC covered
Page: 36 , 26-Apr-13
SECTION 19 - EARTHING
SPECIFICATION TS-IN-01
EEPCO
19.4
Page: 37 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Example 2. For a feeder earthed at the first pole and the distance from this
earthed pole to the end of the feeder is say 500m, the feeder neutral shall be
earthed at one intermediate point and at the end of the feeder.
Earth connections along the LV distributor and at the ends of the distributor shall
comprise a single earth stake solidly connected to the neutral conductor with
galvanized steel 70mm installed inside a 20 mm diameter polyethylene pipe,
colour black.
Where LV distributors from adjacent transformers meet, the neutrals shall be
interconnected and earthed.
19.5
20.
Sufficient back filled earth is lying over each foundation pit and it is adequately
compacted.
(ii)
(iii)
(iv)
Checks weather the guy / stays is straightened and weather the guy / stays are
intact.
(v)
Check weather the earthing connection of supports and fittings are intact.
Measure the earth resistance with earth tester.
(vi)
(vii)
(viii)
(ix)
All the accessories and insulators are strictly as per the drawing and are free from
any defects or damages, whatsoever.
(x)
All the bolts and nuts and pole fittings are galvanized and as per contractual
provisions.
Page: 38 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
(xi)
The stringing of the conductors has been done as per the approved sag and
clearances as per IE rules are available.
(xii)
(xiii)
At all tension points, jumpers are provided to each phase with two Nos.
aluminium alloy PG clamps.
(xiv)
In addition to the above testing, it shall be ensured that the total and relative sags
of the conductors are within the specified tolerance. Such tests shall be carried out
at selected points along the route as required.
(xv)
After satisfactory tests on the line and approval by the Engineer the line shall be
energized at full operating voltage before handing over.
21.
POLE SCHEDULES
Pole schedules are to be prepared in Proforma mentioned below and hand it over
to the Engineer. All approach roads available and power lines crossing locations
shall be marked in the drawings.
The pole schedules shall be prepared in the following formats.
21.1
S. No
Top cleat
12
23
Loc. No
Horizontal x arm
13
Coil earth
24
Type of
support
14
Pipe earth
25
Height
(Mts.)
Pedestal clamps
15
SP/DP/4P
16
Danger boards
27
Structure
pole
Discs
17
28
Type / HT
Metal parts
18
29
Span length
Bracing sets
P.G. Clamp
30
Ground
clearance
Back clamps
20
Conductor joints
31
Size of
conductor
10
Stay clamps
21
32
Page: 39 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Guy insulators
(No)
V cross arm 11
21.2
22
33
S. No
15 Guy insulators No
29
Loc. No
15 KV pins with
insulators
16 Pipe earth
30
Type of support
15 KV discs
17 Coil earth
31
Span length
15 KV metal parts
18 A type pedestals
32
Size of conductors HT
LV pins with
insulators
33
No of LT conductors
LT
34
Size of LT conductor
L.V shackles
21
Ground clearance
CI. Knobs
22 P.G. Clamps
36
Clearance between
HT<
L.V. Straps
23 Conductor joints
37
V cross arm
10
Back clamps
24 Danger boards
38
Top cleat
11
Stay clamp
25 Anti-climbing devices
39
LT 3 cross arm
(Type)
12
Strut pole
26 Guard-rings
40
LT S x-arm (Type)
13
Stay sets
41
Horizontal X-arm
14
42
21.3
35
S. No
Pins with
insulators
14 Danger boards
27
Loc. No
Shackles
28
Type of support
C.I. Knobs
29
Height (m.)
Straps
17 P.G. Clamps
30
Top cleat
18 Conductor joints
31
Page: 40 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Strut pole
Back clamp
32
Type / Height
AB cable size
33
Span length
Stay clamp
21 Guarding (length)
34
No of conductors
35
Size of conductors
(Phase)
10
Coil earth
23 Ground clearance
36
Size of conductor
(Neutral)
11
Pipe earth
24
12
Guy insulators
(No)
25
13
Pole concrete
Full/sleeve/ Nil
26
X arm / type
S X arm type
21.4
37
21.5
S. No
Pipe earth
10
Loc. No
LAS
11
Voltage
12
Type of support
Stays
13
Span
Strut
14
Size of cable
15
Length of cable
Back clamps
16
Angle of crossing
End of terminal
17
GUARDING DETAILS
The details of Guarding are given in Table 21.5.
Table 21.5.
S. No
10
Loc
11
Voltage
Size of lacings
12
Type of support
No of guard wires
13
Page: 41 , 26-Apr-13
SPECIFICATION TS-IN-01
EEPCO
Height of support
No of lacings
14
Span length
15
Earth resistance
16
Angle of crossing
17
Page: 42 , 26-Apr-13
EEPCO
SPECIFICATION
SP-IN-02
SPECIFICATION SP-IN-02
EEPCO
Date
Brief Description
Rev 0
Mar 2013
First Issue
Rev 1
25 April 2013
Page: i , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
INSTALLATION OF AERIAL BUNDLED CABLES
1.
SCOPE
2.
HANDLING OF AERIAL BUNDLED CABLE
3.
ERECTION OF AERIAL BUNDLED CABLES
3.1
3.2
3.3
3.4
3.5
3.6
3.7
PAGE NO
1
1
1
1
TOOLS
PULLING OF AB CABLE
INSTALLATION PROCEDURE
STRINGING OPERATION
ATTACHMENT OF SUSPENSION CLAMPS
MAKING AN AB CABLE JOINT
JOINING OF THE PHASE CONDUCTORS AND THE STREET LIGHTING
CONDUCTOR
2
3
3
4
4
5
4.
4.1
4.2
4.3
4.4
CLEARANCES TO GROUND
CLEARANCES TO BUILDINGS AND STRUCTURES
RUNNING ABC THROUGH TREES
REPLACEMENT OF OPEN WIRE SYSTEMS WITH ABC
6
7
7
7
5.
6.
8
8
Page: ii , 26-Apr-13
SECTION 1 - SCOPE
SPECIFICATION SP-IN-02
EEPCO
SCOPE
This Section covers Installation of Low Voltage Aerial Bundled Cable. LV Aerial
Bundled Cable shall conform to IEC 60811, VDE 0276 part 626, NFC 33-0211998, NFC 33-041-1998, NFC 33-020 - 1998, NFC-004-1998.The bidder may
refer the technical specification TS-CO-02 for AB cables.
2.
3.
(i)
(ii)
The Aerial Bundled Cable drums must not be thrown down from the
transportation vehicles. The drums shall be unloaded using crane or skids as is
done during loading,
(iii)
When handling the cable, contact with sharp articles shall be avoided,
(iv)
When pulling the Aerial Bundled Cable it must not touch the ground,
(v)
When using a fork lift, damaging the cable with the fork shall be avoided.
(vi)
The Aerial Bundled Cable shall be cut with a special cutter to prevent the strands
from spreading,
(vii)
Nylon ties shall be used to prevent the cable from spreading after the cutting. The
end of the cable on the drum shall be stapled to prevent loosening,
(viii)
The protective boards from the Aerial Bundled Cable drum shall not be removed
before the drum is set in alignment for pulling
(ix)
When moving the drum by rolling it on the ground always roll the drum in the
direction indicated by the arrow on the flange. When pulling the cable the
spinning direction must be opposite.
(x)
The drums shall not be stored on wet soil, sandy or humid places. Improve the
ground if necessary.
(xi)
The accessories shall be stored in good order to enable quick and easy
installation.
Page: 1 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
1. Route map, location for keeping the cable drums , tools etc. Approved by the
Project Engineer/EEPCO.
2. Permission from Municipal authorities for road digging etc taking support of
the Project Engineer,
3. Intimation and acknowledgement copy to the local traffic police regarding the
tentative dates of the cable laying work and traffic diversion timings required.
Before the work is started, the condition of all the required tools and equipment
shall be checked and that all necessary materials are at the work site.
When installing a cable across a road, warning signs should be put on the road.
Crossing protections should be made and traffic should be stopped/diverted on
the Road where the cable is pulled.
3.1
TOOLS
The tools used for the ABC line erection work, i.e. installation of Cross arms and
conductor stringing are mentioned below. The tools are in two parts, one which
consists of tools common for the whole group and one which consists of
personal tools.
3.1.1
(ii)
Tackles,
(iii)
(iv)
Swivels,
(v)
Winch,
(vi)
(vii)
(viii)
Pulling ropes,
(ix)
Dynamometers,
(x)
(xi)
Pulling socks,
(xii)
Wire cutters,
(xiii)
Levels,
(xiv)
3.1.2
Individual tools:
(i)
Tool box,
(ii)
Torque wrench,
(iii)
(iv)
(v)
Articulated spanners,
Page: 2 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
(vi)
Wire brush,
(vii)
Fork wrench,
(viii)
Wedges,
(ix)
Skinning knife
(x)
Joint compound
(xi)
Brace,
(xii)
(xiii)
Pliers,
(xiv)
Safety belt,
(xv)
Safety helmet,
(xvi)
Climbing shoes,
(xvii)
Hammer.
3.2
PULLING OF AB CABLE
The principle is to pull the Aerial Bundled Cable, under mechanical tension so
that contact with the ground or any other obstacle is avoided. The AB cable
should never be dragged on the ground. Normal care should be taken to assure a
smooth passage of the whole cable through the pulleys, especially on the first pole
and on angle poles. One worker should act as a brake-man at the cable drum so
that the cable is not loosened during pulling. One worker should follow the cable
going through the pulleys and stop the pulling e.g. with a walkie-talkie order if
anything is going wrong.
The important steps of pulling operation are described below.
(i)
(ii)
The cable drum is set in alignment with the line to be strung and fixed about 1520 m distance from the pole holding the first pulley. Open the cover of the drum.
Check that the insulation is not damaged,
(iii)
The pulling Winch is fixed to the last pole of the line to be pulled,
(iv)
The suspension clamp and pulley are hung to each suspension hook,
(v)
The double pulley is used on angle pole if the line deviates more than 60 degrees,
(vi)
(vii)
Install the pulling rope with the pulling sock to the cable. When using the swivel
between pulling sock and pulling rope, torsion stresses are avoided,
(viii)
The cable is pulled through the pulleys by using pulling winch Dolmar.
3.3
INSTALLATION PROCEDURE
The procedure for installation of the Aerial Bundled Cable and its attachment
hooks on the pole is described below ,
(i)
Not to leave sharp strands that may damage the cable later
Page: 3 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
(ii)
All joints should comply with electrical requirements. The joint compound shall
be applied sparingly but adequately.
(iii)
(iv)
(v)
The hook shall be installed straight towards the line on terminal poles. If there are
angles on the line, the hook shall be attached on the inner angle side.
3.4
STRINGING OPERATION
The important steps of stringing operation are described below:
(i)
Fix a dead-end clamp to the messenger at the last pole of the line,
(ii)
Fix the heat shrinkable dead-end tubes to the conductors by using gas heating
equipment,
(iii)
(iv)
Rewind the slack cable length back to the cable drum. First make the pre-stringing
of the cable near to the right tension or sag. The pre-stringing can be carried out
by man-power, pulling winch, Motor car etc.
(v)
(vi)
(vii)
(viii)
Suspend the dead-end clamp on the hook and install it onto the messenger,
3.5
(ix)
(x)
(xi)
Check the length of the cable needed and cut it at an appropriate length.
ATTACHMENT OF SUSPENSION CLAMPS
The procedure of attachment of suspension clamps is described below.
3.5.1
Straight line
Open the back support of the pulley from the hook. Separate the messenger wire
from the conductors using wedges. Lift the messenger to the open groove of the
suspension clamp and tighten the bolt using a 20 Nm torque. Remove the pulley
from the hook.
3.5.2
Angle pole
Attach a pull lift and come-alongs to the cable in each direction. Separate the
messenger wire from the phase conductors by using wedges. Tighten the pull-lift
until the cable comes close the suspension clamp. Lift the messenger wire, into
the open groove of the suspension clamp and remove the pulley from the hook.
Tighten the bolt in the suspension clamp by using 20 Nm torque. Remove the
Page: 4 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
pull-lifts and come-alongs. Bind the conductors together on both sides of the
suspension clamp by using nylon ties.
3.6
3.6.1
Standard
Jointing of AB Cable shall conform to the relevant standard.
3.6.2
Joining Messenger
Cut the neutral messenger about one meter from the end of the first Cable,
Push the ends of the messengers into the tension joint and pretension by pulling
the messengers to the opposite directions.
3.7
Remove the insulation from the conductors at the length of the connector
without damaging the aluminium conductor,
(ii)
Brush the conductors with the steel wire brush and apply a thin film of jointing
compound over the conductor ends,
(iii)
Push the conductors into the grooves of the connector. Tighten the bolts with a
20 Nm torque using the articulated spanner holding fast with the fork spanner,
(iv)
Cut the necessary holes in the insulation covers for the conductors and street
lighting conductor together around the messenger using a few nylon ties,
(v)
Put the conductors into the connectors and tighten the bolts using the articulated
spanner by applying 20 Nm torque, holding fast with the fork spanner,
(vi)
Cut the necessary holes in the insulation covers for the conductors, using a knife
and attach the covers,
(vii)
3.7.2
Page: 5 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
the conductors in the covers, if necessary, and place the covers around the
connectors. Bind the phase conductors around the messenger using nylon ties.
(ii)
3.7.3
Branching line
Install a hook on the branching pole and put the dead-end clamp on it. Cut off
about one meter of the neutral messenger of the branching cable. Fix the
messenger to the dead-end clamp. Cut off about 200 mm of one phase conductor
and about 400 mm of another phase conductor of the branching cable.
(i)
(ii)
4.
4.1
CLEARANCES TO GROUND
Where the ABC is erected as an aerial system supported on poles the minimum
clearance to ground level shall be as given in Table 4.2.1.
Table 4.2.1
GROUND TYPE
MINIMUM CLEARANCE
Roadways
5.8m
4.0m
5.2m
Page: 6 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
Where the ABC is installed as an under eaves ( roof space) system attached to the
surface of buildings, the minimum clearances to ground level between buildings
shall be given in Table 4.2.2 .
Table 4.2.2
GROUND TYPE
MINIMUM CLEARANCE
3.5m
It should be noted that the clearances given above are minimum design
clearances. When establishing actual clearances account should be taken of, the
use of the land, vegetation growth, the possibility of vehicular access under or
close to the line and future maintenance requirements of adjacent structures.
4.2
4.3
3.0m
Shall be
1.0m
(assumed to be in still
air)
Shall be
not less
than
500mm
under deflected cable
conditions
Shall be
not less
than
300mm
in the deflected
condition
4.4
Page: 7 , 26-Apr-13
SPECIFICATION SP-IN-02
EEPCO
SECTION 5 - PRE-COMMISSIONING
CHECKS AND TESTS
The following precautions shall be adhered to in all such cases, if supports are
designed to carry open conductor LV system alone.
(i)
The two systems must only be up together for a short period of time.
(ii)
Prior to work commencing, check all poles for decay (including 0.3m below
ground level).
(iii)
Strung the ABC on the opposite pole face at, or lower, than the level of the
Neutral conductor of the open wire system without infringing minimum ABC
ground clearances.
(iv)
Secure the ABC at all the terminal and suspension points and then make it live.
(v)
Transfer the services, one at a time, from the open wire to the ABC main.
(vi)
When all the services are transferred to the ABC, disconnect the open wire
conductors and remove from the supports.
5.
6.
(i)
All cable, clamps fittings etc., used are as per the approved drawings /
specification
(ii)
Jointing of messenger wire and phase conductors is done as per the approved
method statement.
(iii)
(iv)
Span lengths and working stresses are with in the limits mentioned in technical
standards.
EARTHING
Page: 8 , 26-Apr-13
EEPCO
SPECIFICATION
SP-IN-03
Underground Cable Installation
SPECIFICATION SP-IN-03
EEPCO
Date
Brief Description
Rev 0
Mar 2013
First Issue
Rev 1
25 April 2013
Additions - modifications
Page: i , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
UNDERGROUND CABLE INSTALLATION
1.
SCOPE
2.
GENERAL
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
PAGE NO
1
1
1
1
1
1
2
3
3
3
3
3
3.
4.
4
5
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
GENERAL
EXCAVATION
SHORING AND WATER - LOGGING
ROAD CROSSING
CABLE DUCTS FOR ROAD & RAIL CROSSING
BACKFILLING
CABLE AND CABLE ROUTE PROTECTION
TEMPORARY REINSTATEMENT OF SURFACES
ROADS CROSSING
JOINT HOLES
PRICING AND MEASUREMENT OF EXCAVATIONS
TIMBER LEFT AND BUILT IN
5.
5.1
5.2
5.3
5.4
GENERAL PRECAUTIONS
ADITIONAL PROCEEDURES FOR SINGLE CORE CABLES
PULLING FORCE ON CABLES USING WINCHES
CLEARANCES
15
16
17
17
6.
7.
CABLE LAYING
CABLE INSTALLATION FINISHING
17
20
7.1
7.2
7.3
20
21
21
8.
21
5
5
8
8
9
10
12
13
13
14
14
15
Page: ii , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
8.1
8.2
8.3
8.4
GENERAL
CHECK LIST FOR LAYING CABLES
DOCUMENTATION DRAWINGS ROUTE PLAN
CABLE INSTALLATION RECORD
21
21
22
22
9.
23
9.2
9.3
9.4
24
24
24
10.
24
10.2
10.3
10.4
10.5
10.6
24
24
25
25
26
SPECIFICATION SP-IN-03
EEPCO
SECTION 1 - SCOPE
SCOPE
This specification covers the requirements and procedures for the installation of
Underground Cables.
2.
GENERAL
2.1
2.2
2.3
Page: 1 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
SECTION 2 - GENERAL
The Contractor shall at his own expense do what is necessary to make every
access suitable for his use and shall take all reasonable precautions to avoid
damage to land, property, roads, crops, field drains, fences, walls, hedges, gates
and the like and shall ensure that the work is adequately supervised so that
damage is reduced to minimum.
The Contractor will be liable for all damage arising by or in consequence of the
works except damage to crops and shall pay compensation or make good at the
option of the Client. The Contractor shall dispose of all spoil and surplus materiel
after erection.
The Contractor shall at all times keep sites free from obstruction, waste material
and rubbish and shall remove from the sites at his own expense all surplus
materials and temporary works as soon as they are no longer required for the
erection for the Works. On completion of the Works the Contractor shall leave
the sites clean and in a workmanlike condition to the satisfaction of the Engineer.
The Contractor shall be responsible for maintaining agreed access routes, without
undue widening, in a usable condition for the duration of the Contract and the
way-leave grantor shall not be put to any inconvenience in gaining access to his
land or buildings and no unauthorised access route shall be taken by the
Contractor.
Adequate provision shall be made by the Contractor to prevent the straying of, or
damage to livestock during the execution of the Works and until the permanent
reinstatement of fences, walls, hedges, gates and the like is completed.
The Contractor shall be liable for any damage to or loss of livestock due, in the
opinion of the Engineer, to failure to comply with the above requirements.
By the date for access to the overhead line and underground cable routes stated
by the Contractor in his Master Programme, the Client shall (subject to the
Contractor being then ready to commence work) provide over the whole length
of the routes such right of access for the Contractors staff to carry out survey
work, investigation of the general foundation conditions, construction, testing and
commissioning of the required Works in accordance with the Specification.
The Contractor shall make all necessary arrangements (other than questions of
wayleaves and access) with the occupiers of the land but if any difficulty shall arise
the Contractor shall inform the Engineer thereof. The Engineer shall there upon
take such steps as may be necessary to resolve the difficulty.
The Contractor shall make any necessary arrangements and take any necessary
precautions where the routes cross roads, telecommunication lines or cables,
buildings, power lines or cables, orchards, gardens or other obstacles or ground
over which erection cannot be carried out in the normal manner.
The Contractor shall provide all necessary temporary works to overcome the
obstacles and shall comply with all reasonable requirements of the Authorities
concerned.
2.4
RISK OF FIRE
All apparatus connections and cable installations shall be designed and installed to
minimise the risk of fire and any damage which may be caused in the event of fire.
Page: 2 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
SECTION 2 - GENERAL
Enclosed vertical runs of cables shall be provided with fire stops to limit the
spread of fire and shall be sealed to prevent chimney effects.
Wherever cables pass through floors, walls or other partitions a suitable method
of sealing shall be used. This sealing shall consist of one hour fire resisting
material, the whole being arranged to prevent the spread of fire, smoke and fumes
through each partition. Cable ways containing a large number of cables shall be
enclosed in one hour fireproof material. All large cable rooms, cable floors and
cable ways shall be divided by fire barriers which shall segregate cables as required
by the Engineer. Access shall be provided through fireproof doors.
2.5
MATERIALS HANDLING
It is the Contractors responsibility to take care of all kinds of dangerous materials
for the environment, contaminated water or oil products etc.
The material used belongs to the Employer and therefore he must be informed
and approval shall be obtained before such disposal.
If the contractor ignores this, he will pay the damages/ penalties according to the
local laws and regulations or in the way that is equivalent to damage of the
environment.
2.6
SAFETY
The Contractor is fully responsible for the safety of third person, installed material
etc. until the Employer fully takes over and a certificate is issued.
2.7
WORKING HOURS
Construction is normally to be carried out on ordinary days as agreed between
Employer and Contractor. (Daily time-period has to be agreed). However, the
Employer may call the contractor for twenty-four (24) hour service or for
weekends working, if they deem that necessary.
2.8
TRAFFIC MANAGEMENT
The Contractor shall include provision for road signs, guards, fence, lighting, road
barriers, the stringing of danger tapes and the positioning of warning lamps
between sunset and sunrise. Flashing type warning lamps shall also be positioned
at strategic points in the construction areas to caution motor vehicle traffic. A
flagmen and watchmen may also be required. The measures shall be according to
the Employer and the local authorities requirements for the protection and safety
of all persons and adjacent properties.
2.9
OBSTRUCTION
When in the course of the Contract Works obstructions are encountered which
necessitate diversion of existing electric, water or sewage installations,
communication cables or other underground works, or alterations to buildings or
foundations or when conditions necessitate the adoption of a special form of
trench, the Contractor shall immediately notify the Engineer, who will instruct the
Contractor in writing of the action necessary, to overcome the obstruction.
Page: 3 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
2.10
3.
Page: 4 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
4.
CABLE TRENCHES
4.1
GENERAL
4.1.1
The cable laying route should be decided keeping in view the immediate and
ultimate use of the cable as an integral part of the transmission and distribution
system,
(ii)
The side of the street which presents the least obstacles and the fewest roadway
crossings shall be chosen,
(iii)
Special attention should be paid to the load bearing capacity of the bridges and
culverts and other obstructions which fall en-route,
(iv)
If possible, cables should be laid along the foot path rather than the carriage way.
(v)
The route should be, as far as possible, away from parallel running gas, water
pipes and telephone/telecommunication cables.
(vi)
Suitable locations for cable joints and end terminations should be selected as
required.
The laying of the cables, pipes, etc. shall generally be performed according to the
drawings. However, when obstructions are encountered which necessitate
alterations or when conditions necessitate adoption of a special form of trench,
the Contractor shall immediately notify the Employer and propose a solution for
approval before the work proceeds. The cost for adoption of a special form of
trench and increase in the width of trench, if required to suit actual field
conditions and the required capacity of the cables should be undertaken at no cost
to the Employer.
The exact location of each trench and pit shall be as approved by the Employer
before beginning of the excavation work on the site.
The cables shall be laid along the routes and in the locations as finally approved.
The Employer shall have the right to alter the cable routes and locations, where
considered necessary.
4.2
EXCAVATION
Before opening a section of trench, the Contractor shall make sure that the line of
the trench is clear of underground obstructions, by taking out trial holes on the
line of the trench.
Trenches shall be kept as straight as possible and shall be excavated to approved
formations and dimensions.
All excavations may be carried out mechanically but the final shaping and
trimming of the soil close to other cables, pipes, foundations etc. shall be done by
hand-shovel if this is so required to achieve a suitable cable laying bed.
The trench shall be excavated in such a way that a free distance of min. 100 mm is
available between the outer cables or plastic pipes and the trench walls.
The edges of the trench shall be cleared to prevent stones and other debris from
falling into the trench and affecting the protection filling or damaging the cables.
Page: 5 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
The Contractor shall take all precautions necessary to prevent damage to the road
or ground surface due to a slippage or breaking away from the walls of the trench.
If necessary the trench sides shall be close timbered and strutted to prevent
subsidence.
Where trenches pass from a foot path to a roadway or at other positions where a
change of level is necessary, the bottom of the trench shall rise and fall gradually.
In some areas, the existing level may be more or less than the value below the
surrounding level, etc. thus the Contractor shall backfill to stated levels of soil
upon the uppermost cable as a minimum in any case subject to the Employers
approval. The Contractor shall also ascertain the levels and related particulars.
In cases where the existing ground level is higher than the expected final ground
level, cables shall be laid to a depth as measured from the above-mentioned final
ground level.
Whenever trenches run parallel to existing services (such as water pipes, cables
etc.), the Contractor shall maintain a distance of at least 0.5 m between the
existing services, cables, etc. and the edge of the new trench .The Contractor shall
cross above/under existing services with utmost care and shall ensure that the
cables etc. are adequately protected. He shall obtain approval from the Employer
concerning the method and acceptable free distance of crossing existing services
in advance.
The Contractor is fully responsible for the protection of all cables, conduits,
pipes, ducts etc. that are existing close or crossing the trench being excavated.
Warning signs must be present until all excavation; construction, backfilling etc.
are done. Where there is necessary sturdy concrete or steel beam stoppers shall
be used to hinder vehicles to enter into the trench.
Warning signal lights and (or) powerful reflectors must be installed when
construction is carried out during night time.
At house entrances, shop entrance etc. excavated areas must be covered with steel
plates and secured to avoid accidents, of sufficient thickness to provide a
temporary path way.
The Contractor is fully responsible for the required covering materials and such
arrangements.
4.2.1
Installation requirement
Depth (mm)
750
300
15 and 22 kV cables
900
500
33kV cables
1100
600
1800
800
600
Page: 6 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
Installation requirement
Depth (mm)
1000 to 1200
600
above
Cables at railway level crossings (measured
from bottom of sleepers to the top of pipe)
(minimum if less than above
If more than one circuit is required then the width shall be increased to allow
separation between circuits as stated below.
There must be a clearance from the cable (center) to the wall of about 150mm
4.2.2
Cable Spacing
Cables installed in the same trench shall be laid parallel to each other with the
following spacing between cables (LV; MV; HV):
Where MV and LV cables have to be installed in the same trench, the MV cable
shall be laid on the one side of the trench (away from the road and if no road
exists in the South- East side ) at the MV above and then covered with 300mm of
soil. The LV kV cable shall then be laid on the other side of the trench, i.e. not
above the MVV cable, and then completely backfilled.
Cables for telephones, communications systems and other low voltage systems
(less than 50V) shall be separated from power cables by at least 1m. All control or
pilot cables shall be laid at least 300mm from power cables.
Cables shall not be buried on top of each other unless layers are specified. The
minimum spacing between layers shall be 200mm.
4.2.3
Excavated Materials
All excavated materials which may be re-used later in the Works shall be
deposited and stored at places approved by the Employer so that these materials
cause as little damage and inconvenience as possible.
The materials excavated from each trench shall be placed so as to prevent
nuisance or damage to adjacent hedges, trees, ditches, drains, gateways and other
property or things. Excavated material shall be stacked so as to avoid undue
interference with traffic. Where, owing to traffic or for reasons of safety or other
considerations, this is not permissible the excavated material shall be removed
from the Site and returned for refilling the trench on completion of the laying.
Surplus material shall be disposed of by and at the cost of the Contractor, up to a
distance of 15 km from the Site.
In order to facilitate the re-use of excavated materials for road foundations and
surfacing, the excavated material shall be separated into hard road material, soil
and other materials.
Page: 7 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
Mechanical excavators
Power driven mechanical excavators may be used for trenching operations
provided that they are not used in close proximity to other plant, services or other
installation likely to be damaged by the use of such machinery.
The use of power driven mechanical excavators shall be subject to the approval of
the Local Authorities/The Project Manager. Should the excavator produce
trenches that exceed the required dimensions, payment based on volumetric
excavation rates will be calculated on the required dimensions only.
4.3
4.4
ROAD CROSSING
Excavations across road shall be carried out with the minimum of inconvenience
to the public and the authorities.
Excavations across main roads where the width of the road between kerbs is 9
meters or more, shall be carried out in half road widths so that the flow of traffic
can be maintained.
Where tarred road surfaces are cut, such cuts shall be neat and straight and no
jagged edges shall be tolerated.
Road crossings shall be attempted to be at land plot boundary peg unless
otherwise shown.
The excavations shall be of such depth that the dimension from the top of pipe
ducts to the road surfaces shall not be less that the depth specified in this
document or as otherwise specified on detailed drawings.
The Contractor shall be responsible for the provision of road warning signs as
specified in the relevant section in this document.
Page: 8 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
4.5
4.5.1
Concreting of pipes
If the pipes require to be encased in concrete, the type of concrete shall be agreed
with the engineer. If there is no other pricing mechanism for the concrete, the
Page: 9 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
cost shall be deemed to be twice the purchase cost or market cost of ready-mix.
The cost shall be measured per cubic meter of concrete poured.
The cost of concrete installation shall include the steel mesh reinforcement that
may be required above and below the pipe encasing.
This provision is for intended mainly for road crossing where circumstances
dictate the need to protect the cables and provide the load bearing for the road.
4.5.2
4.5.3
Spare pipes/ducts/sleeves
At road crossings when installing cables two spare sleeve shall be installed and
marked on the appropriate drawing.
All pipes intended for future use shall be clear inside and shall be sealed
appropriately to avoid materials and sediment to settle in.
Spare pipes shall be 150mm in diameter.
4.6
BACKFILLING
The Contractor shall not commence with the backfilling of trenches without prior
notification to the Project Manager so that the cable installation may be inspected.
Should the Contractor fail to give timely notification, the trenches shall be
reopened at the Contractors cost. Such an inspection will not be unreasonably
delayed.
The Contractor shall have allowed in his tender for the importation backfill
material if required.
The backfilling of the trench shall be carried out in maximum 200 mm layers,
which shall be well compacted and consolidated. Watering of the layers may be
necessary to achieve the best compactness.
The backfilling may consist of material from the excavation of the trench
consisting of clay, sand, silt and gravel fragments. The material shall not contain
any refuse, vegetation or organic material.
The Contractor shall be solely responsible for ascertaining whether the soil is
chemically active and for taking special precautions to protect the cables against
chemical action and/or termite attack. The Contractor shall take precautions to
avoid electrolytic and/or electro-chemical action occurring in situations where the
cable and accessories are likely to be installed in close proximity to other dissimilar
metals in the presence of moisture.
4.6.1
Page: 10 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
riddled soil or sand or similar material having the required soil thermal resistivity
of maximum 1.5 km/W at a normal dried out condition. The filling shall be well
tamped down to a minimum thickness of 100 mm to form a proper bed for the
cables.
The Contractor shall measure and record the thermal resistivity of the backfilling
material after reinstatement every 500 meters and all efforts shall be made to
obtain uniform thermal resistivity all along the cable routes. Other ways to
guarantee the thermal resistivity may be adopted with the approval of the
Employer.
The cost for thermal resistivity tests is deemed to be included in the contract
price.
The protection filling shall be free from sharp stones or stones with a size larger
than 4 mm.
At places where there is a risk that the protection filling will pass through the
trench walls/bottom, special fibre-cloth or geo-textile filter shall be placed in the
trench to hinder the material migration and such contingency shall be deemed to
be included in the Contract.
Pulling of cables shall not commence until the Employer has inspected and
approved the depth of the trench and the bed of sand including its thickness.
4.6.2
4.6.3
Page: 11 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
4.7
4.7.1
500 to 1000
mm
Width
350 mm
Thickness
50 mm
Concrete quality
20 MPa
The slabs shall be constructed of and each slab shall be reinforced with one
longitudinal and three transverse mild steel rod of minimum diameter 8 mm. The
slabs shall be manufactured in such a way that the slabs interlock with each other
thus avoiding shifting of the slabs after installation.
4.7.2
4.7.3
Page: 12 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
The tape shall be Yellow colour with black colour warning letters. Warning signs
shall be printed at intervals of about 1m along its length. The sign shall consist of
a black-triangle and an electric flash symbol and the words "Danger, Electric
cable" or other appropriate sign approved by the Utility.
4.8
4.9
ROADS CROSSING
4.9.1
4.9.2
Boring - Trusting
Where required the contractor shall bore under roads to install cable sleeves for
pulling the required cables.
No work on headings, tunnels or thrust borings shall be undertaken without the
approval of the Engineer. The Contractor shall take all reasonable precautions to
ascertain and record the position of all sewers, drains, pipes, structures and things,
on cross sectional drawings to be submitted for approval before work is
commenced.
If the thrust bore method is chosen (optional) a cross section drawing of the
road crossing trench shall be submitted with the Bid showing details of
configuration, type of layers, thickness of layers, pipe types etc. The current curing
capacity at the crossing shall not be lower than for the other parts of the land
route. Calculations and measures to obtain this shall be performed and included in
the scope of work by the Contractor.
Alternatively the contractor shall employ directional drilling for the installation of
cables. A lining shall be installed following the directional drilling.
Page: 13 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
The boring shall be quoted per linear meter of road crossing and each sleeve,
including one meter on either side of the road.
The costs hall include all works from mobilisation to clearing the site to establish
the required holes. It shall also include the opening of any trench for the
installation of equipment. If this cost cannot be included in the linear meter
measurement the contractor shall introduce an additional cost item.
4.10
JOINT HOLES
Where cable joints are required to be made in the course of a cable run, a joint
hole shall be excavated of sufficient size to enable the cable jointer to work
efficiently and unimpeded. Where necessary joint holes shall be shuttered to
prevent subsidence and damage. During jointing, the joint holes shall be
adequately covered with tents or other waterproof sheeting suitably supported to
ensure suitable conditions and prevent as far as possible wind borne material
entering the joint.
The depth of the trench at the joint location shall be adjusted in such a manner
that the upper surface of the joints is buried to the same depth as the upper
surface of the cables.
The Contractor shall submit a dimensional drawing showing details of the jointing
area for the Employers approval before commencement of the work.
4.11
a)
b)
c)
d)
e)
f)
Supplying and covering the cables with a layer of sifted solid after the cables have
been laid and spaced and after the inspection and approval of the Engineer.
g)
h)
i)
j)
k)
4.11.2
Page: 14 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
The standard trench width shall include the extra width required for the cable
joints / terminations.
4.11.3
4.11.4
4.12
5.
5.1
GENERAL PRECAUTIONS
The general precautions to be observed while drawing and laying cables are listed
below.
1) Examine the cable for exterior damage if any, after the drum planks have been
removed,
2) Cable should not be pulled across hard and sharp objects to avoid damage to the
protective covering and the insulation of the cable,
3) Cable should not be bent in an inadmissible way,
Page: 15 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
4) Cable should always be pulled off the top of the drum by placing, the drum in
such a way that the painted arrow points to the opposite direction of the pulling,
5) Cable drum shall be jacked up with a drum axle to such a height that the plank
needed for braking is not jammed. Heavy drums should be jacked up with
hydraulic drum pedestals.
6) When pulling the cable, the drum shall be turned by hand in order to avoid
excessive tensional stress, which may damage the cables, particularly smaller unarmoured cables.
7) A drum brake is necessary to avoid further rolling and consequent buckling of the
cable in the event of a sudden stop. A simple plank can serve as drum brake.
8) The kinks (nooses) are particularly dangerous and should be avoided.
9) Cables should be warmed before laying out, if the temperatures are below 3C;
otherwise the bending would damage the insulation and protective coverings of
the cables. The cable laying must be carried out swiftly, so that the cable does not
cool down too much.
10) Warming of cables may be achieved by storing the cables for adequately longer
period (not less than 24 hours) in a heated building or in a tent with hot air
beaters. However, the cables should be heated to a minimum of about 10C to
facilitate easy laying,
11) The leading end of the cable is untied from the cable drum and a cable stocking
placed over it and secured firmly. A rope is attached to the cable stocking pulling
eye. No pull should be exerted on the end of the cable.
12) Identification strips/tags of metal or plastics should be attached to the cables,
particularly if several are laid in parallel, 8 to 10 m apart. Identification tags should
also be attached at every entry point into the buildings and at the cable end
termination.
5.2
Page: 16 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
5) If several single-core cables are laid per phase, these should be arranged to ensure
balanced current distribution.
5.3
Type of installation
In trenches without large bends
15-20 %
20-40 %
50-60 %
5.4
Up to 100 %
CLEARANCES
The desired minimum clearance to be maintained between other lines is given
below.
Power cable to other cables
0.2 m
0.3 m
0.3 m
6.
CABLE LAYING
Cables shall be laid directly from the drums into the trenches and special rollers
placed at close intervals shall be employed for supporting the cables while pulling
and laying them. Rollers used during the laying of cables shall have no sharp
projecting parts which may damage the cables.
Cable rollers shall be used as far as possible to run out cables. Rollers shall be
spaced so that the length of cable in the trench will be totally suspended during
the laying operation and sufficiently close to prevent undue sagging and the cable
from touching the ground. Rollers shall also be placed in the trench in such a
manner that the they will not readily capsize. Cables rollers shall have no shape
projecting parts liable to damage the cables.
Alternatively cables may be laid off a lorry loaded with suitable drum unwinding
facilities but never laid off the side of the drum.
Page: 17 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
Bending radius during laying and installation shall be as large as possible, and the
minimum shall be 15 x D along the route, and 10 x D adjacent to joints and
terminations (D being the overall diameter of the cable).
Instructions received from the cable manufacturer shall be followed during the
cable laying and installation.
Covering of cables/pipes with protection filling shall not commence until the
Employer has inspected and approved the laying and placement of cables, pipes
etc. in the trench.
The position of all the cables/pipes along the trench shall also be performed by
the Contractor with adequate equipment and with an agreed tolerance before
covering. The cost thereof shall be deemed to be included in the contract price.
6.1.1
6.1.2
Page: 18 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
6.1.3
Jointing
Joints in cable runs will not be allowed unless specified in the Detail Technical
Specification or authorised by the Project Manager.
Jointing shall be carried out strictly in accordance with the manufacturers
instructions and by personnel competent in jointing the types of cables used.
During outdoor jointing operations, the joint bays shall be adequate covered by
tents of waterproof material suitably supported. Where necessary a trench shall be
excavated around the bay to prevent the ingress of moisture. The sides of the hole
shall be draped with small tarpaulin or plastic sheeting to prevent loose earth from
falling in during jointing operations.
The joint shall not impair the anti-electrolysis characteristics of the cable.
The Contractor shall notify the Project Manager in time, of the day on which
jointing is to be carried out in order than an inspection may be arranged if so
required. Any cable joint not inspected by the Project Manager because of
insufficient notice being given, shall be opened for inspection and redone at the
discretion of the Project Manager at the cost of the contractor.
Joints shall be fully water and air tight and shall be free of voids and air pockets.
The crossing of cores in joints will not be permitted under any circumstances.
Where cold pouring resin compound is used the manufacturers mixing and
pouring instructions shall be strictly adhered to when filling joint sleeves.
Care shall be taken to ensure that jointing compounds, resins etc., are in a
satisfactory state after storage and in a suitable condition for achieving a reliable
joint.
The Contractor shall ensure the correctness of continuity throughout the cable
lengths to achieve correct identification of all terminations.
The joints may be placed directly in the soil and completely surrounded by the
protection filling.
At the joint bays the joints shall be staggered over the length to minimize the
width of the trench.
A record shall be kept of all joints made. This record shall include the names of
the jointer and his mate, the cable drum number(s), the date of making, the date
of testing and weather conditions prevailing and the particular events that have
happened during installation.
6.1.4
Terminations
The Contractor shall be wholly responsible for the termination into sealing ends
or end boxes of all cables erected under this contract. Cable sealing and jointing
shall be in accordance with the best current practices and of first-class
workmanship.
A record shall be kept of all terminations made. This record shall include the
names of the jointer and his mate, the cable drum number(s), the date of making,
the date of testing and weather conditions prevailing and the particular events that
have happened during installation.
Page: 19 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
7.
7.1
Page: 20 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
has been carried out and should be supplied with a stainless steel plate with
relevant information about the buried cables (proposal to be submitted to the
Employer).
Markers shall be installed at all joint positions, at all places where the route
changes the direction, and on straight routes at distances not exceeding 25 meters
in the city area and 50 meters in the countryside.
The Engineer shall approve the location of the markers.
The cost of providing and installing markers shall be deemed to be included in the
contract price.
7.2
7.3
8.
8.1
GENERAL
The following five activities have to be undertaken to complete laying /
installation of cable.
(i)
(ii)
(iii)
(iv)
(v)
Documentation Drawings
(vi)
Installation Plan
8.2
Check again to see that all the cable ends are undamaged and sealed.
Page: 21 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
8.3
(ii)
If trench is partially filled with water, cable ends should be kept clear off water as
far as possible.
(iii)
If cable has to be cut, both the cable ends should be resealed immediately Lead
cap for paper cable and plastic cap or Heat Shrinkable cap for PVC, XLPE cable
should be used.
(iv)
Cable ends should overlap at the joint box point by at least half the length of
latter.
(v)
The ends may be looped to provide extra lengths in case of extruded dielectric
cables.
(vi)
Each cable length should be aligned immediately after it is laid, starting from one
end. To enable the cable to be laid on the inner or outer side of the trench, a
certain amount of slack is provided all along the cable by raising each one to
about the top edge of the trench every 20 to 30m from the beginning.
(vii)
When aligning the cable, it should be ensured that there is no external damage.
(viii)
(ix)
The duct should be cleaned before pulling the cable through it!
(x)
Long steel or plastic duct sections should be checked with a gauge and coated on
the inside with lubricant (for plastic and concrete ducts, boiled-down soap with a
low alkali content: for steel ducts, grease: and for PVC cables graphite powder can
be used as a lubricant).
Depth of cable
Position of cable from reference points, such as distance from road centre,
fences, buildings
8.4
Page: 22 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
(i)
(ii)
(iii)
(iv)
Year and month of laying cable and jointing schedule of starting and completion
dates).
(v)
(vi)
(vii)
Profile drawings of Location of cables and joints (joint bay) in relation to certain
fixed reference points, for example, buildings, hydrant, boundary stones, etc.
(viii)
(ix)
(x)
9.
(ii)
Measuring of IR values
(iii)
Page: 23 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
9.2
9.3
MEASURING OF IR VALUES
IR values of all the three cores i.e., R, Y, B with reference to earth and other
phases are to be measured. If the values are quite reasonable and satisfactory, the
cable is healthy.
9.4
10.
Manufacturing defect
b)
c)
Improper laying
d)
e)
Improper Loading
f)
10.2
Diagnosis
(ii)
Pre-Location
(iii)
Pre-conditioning
(iv)
Pin Pointing
10.3
STAGE 1: DIAGNOSIS
The objective of this stage is to ascertain the exact condition of the cable i.e.,
whether the cable is faulty or not. For this, purpose the following tests are
conducted
Page: 24 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
a)
Measurement of Insulation resistance of cable between the (i) Core and earth (ii)
Core to Core with a suitable insulation tester / meger. If the IR values measured
are equal and reasonable the cable may not be faulty.
b)
High voltage test is carried out and if the cable stands for the test with the
minimum leakage current i.e., 0.1mA to 0.4mA, the cable is certified to be healthy
and can be taken back into service. If the values are not equal, the particular core
in which the value is less can be identified.
c)
From this, the faulty core and the nature of fault resistance can be arrived at to
proceed to the other stages of fault location.
From the IR values, the nature of fault i.e., (a) High Resistance (b) Low Resistance
and (c) open circuit can be identified. If the resistance of the fault is low, the test
can be directly conducted in the PRE LOCATION stage. If the resistance is high,
it has to go through the second stage Le, PRE-CONDITIONING.
10.4
10.5
STAGE 3: PRE-LOCATION
In this stage the cable is actually connected to the testing circuit and the fault
distance is arrived at from the testing end by Impulse Current equipment Method
described below.
Impulse Current Equipment Method works on the principle of wave propagation
theory of travelling waves. The test set-up is as below:
This equipment operates at 230 volts, single-phase supply. There is a step up
transformer, which steps up from 230 volts to 7.5kV or 15kV. The stepped up
voltage is converted into DC by the rectifier R in the circuit. This voltage is
applied across the capacitor and this capacitor gets charged and energy to the
extent of CV2 is stored in the capacitor. This energy is discharged into the
faulty cable through the test leads by closing the switch S, which travels along the
faulty core. When the energy reaches the low resistance faulty point, it creates a
spark and travels further. The spark created generates a travelling wave, which
travels back to the instrument through the earth of the cable. This wave has both
the current and voltage transients. The current transients are picked up by LCS
(Linear Coupler Selector) and feed it into the ICE (Impulse Current Equipment),
which is a microprocessor based analyser, which analyses the wave and display the
wave in the OSC (Oscilloscope). This wave is studied and the time of travel of
wave from the fault to the instrument and back to fault is measured by sending a
signal along the wave, (say T Sec). Once the time of travel is measured, the same
Page: 25 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
is converted into distance by multiplying the time with the velocity of the
propagation VP/2 (mts/ Sec). The velocity of propagation depends on the type
of dielectric (insulating material) used for the cable. The distance of the fault
measured in meters is
Df
10.6
After obtaining the distance of fault in the previous methods, the documentation
drawings (as laid drawings) are verified and the approximate physical location of
the fault is arrived at.
(ii)
To pick up the signal generated at the fault (both magnetic and acoustic) the
signals are to be made available continuously. This is achieved by connecting a
timer in the circuit and the timings are set such that at the set time interval there
will be charging and discharging of the capacitor and the energy stored will be
sent into the faulty core creating sparking over subsequently.
b)
(i)
When the ground microphone of the seismophone is kept in the area of the
acoustic disturbance near the fault, both the acoustic and magnetic sensors start
sensing the respective signals and indicate simultaneous movements in the
amplifying unit. This confirms to the testing engineer that the fault location is
being approached. The ground microphone is shifted at subsequent intervals
towards the fault, the effect of acoustic disturbance will increase and the point at
which both the indicators move simultaneously with maximum indications is
confirmed as the exact point of fault and this is called pinpointing of fault. On
final confirmation of the fault, the instrument is kept off.
(ii)
The nature of the fault is identified on exposure of the trench and necessary
rectification of the cable is done to restore the supply.
Page: 26 , 26-Apr-13
SPECIFICATION SP-IN-03
EEPCO
10.6.2
Permanent reinstatement
The Contractor shall make his own arrangements for obtaining the Standard
and/or specification for permanent reinstatement from the responsible authority.
The cables are to be partly buried within streets and some of them consist of a
concrete base covered by asphalt. This concrete base has to be cut or broken and
may be used for back-filling or original state is reinstated by a method approved
by the responsible authority.
Stone and pre-cast concrete paving kerbs, channels etc. shall also be finally
reinstated by the Contractor.
All costs for reinstatement shall be included in the contract price.
10.6.3
Approval
Before finally leaving the site, the Contractor shall obtain clearance from the
concerned local authority relieving the contractor of his responsibility of
permanent reinstatement, and all costs incurred shall be deemed to have been
included in the Contract price.
The whole of the site and any other areas disturbed by the Works shall be
reinstated to equal the conditions existing prior to the commencement of the
Works and shall be left clean and tidy.
Page: 27 , 26-Apr-13
EEPCO
SPECIFICATION
TS-MA-02
Earthing Materials
SPECIFICATION TS-MA-02
EEPCO
Date
Brief Description
Rev 0
1 May 2013
First Issue
Page: i , 1-May-13
SPECIFICATION TS-MA-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
1.
SCOPE
1
2.
SYSTEM PARAMETERS AND SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
TYPE TESTS
5.
DESIGN
5.1
5.2
EARTH RODS
EARTHING ACCESSORIES
2
2
6.
7.
3
5
7.1
7.2
5
6
Page: ii , 1-May-13
SECTION 1 - SCOPE
SPECIFICATION TS-MA-02
EEPCO
EARTHING MATERIALS
1.
SCOPE
This specification covers the design, manufacture, supply, delivery and
performance requirements of earthing materials.
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/ or other recognised international standards. In particular,
Specification /
Standard Number
Title
IEC-60364
IEC 60228
ANSI C114.1
BS 7884
BS6485
BS EN 10137
Weldable steels
3.1
CONFLICT
See Specification TS-GN-02
4.
4.1
TYPE TESTS
In addition to the tests as per the standards mentioned, the following tests shall be
conducted.
a)
Page: 1 , 1-May-13
SECTION 5 - DESIGN
SPECIFICATION TS-MA-02
EEPCO
Peeling of the jacket by the steel plates or the jaws of the vice is acceptable, but
there shall be no evidence of separation of the jacket from the steel core.
b)
Bend Test
There shall be no evidence of cracking of the jacket if at room temperature a
length of rod is rigidly held in a clamp or vice and the free end bent by applying a
force normal to the rod at a distance from the clamping device equal to 40 times
the rod diameter. The magnitude of the force and the direction of application
shall be such that the rod is permanent bent through a 30 degree angle. There
should be no evidence of cracking or splitting of the steel or the copper.
5.
5.1
DESIGN
EARTH RODS
Solid copper clad steel earthing rods for earthing of low voltage lines and high
voltage equipment. The rods shall be extensible and suitable for driving into the
ground by a hand held hammer.
The copper exterior shall be electrolitycally applied to the steel core to form a
metallurgical bond between the steel core and the copper. The copper thickness
shall not be less than 0.33mm. Earthing rods of the steel bar(low carbon steel)
type with an external copper tube are not acceptable. Earth rods shall be 1500m in
length and not less than 15mm in diameter. The rods shall have a 45-degree
conical driving point, for electrode entry into the ground. At each installation the
rods shall be driven so that than 500mm below the finished ground level. A
minimum of four rods shall be provided for each transformer.
5.2
EARTHING ACCESSORIES
Earthing accessories shall include but not limited to,
5.2.1
Page: 2 , 1-May-13
SPECIFICATION TS-MA-02
EEPCO
5.2.2
5.2.3
Earthing Conductor
The following Types of earthing conductors shall be used:
Bare hard drawn stranded copper wire, conductors in the following sizes,
35, 70, and 185mm2 1000V insulated,
stranded soft drawn copper wire in the following sizes:
150mm2 and 50mm2.
5.2.4
5.2.5
6.
serial number,
(ii)
cable type/size,
(iii)
number of cores,
(iv)
cable length,
(v)
(vi)
year of manufacture,
(vii)
drum measurements,
(viii)
Page: 3 , 1-May-13
SPECIFICATION TS-MA-02
EEPCO
(ix)
Contractor's name,
(x)
(xi)
Contract number,
(xii)
(xiii)
(xiv)
(xv)
(xvi)
(xvii)
(xviii)
(xix)
description of contents;
(xx)
case measurements;
(xxi)
country of origin;
(xxii)
Page: 4 , 1-May-13
SPECIFICATION TS-MA-02
EEPCO
7.
7.1
Page: 5 , 1-May-13
SPECIFICATION TS-MA-02
EEPCO
7.2
Page: 6 , 1-May-13
LPA-GECE
EEPCo
Description
Earthing Rods
Length
Diameter
Thickness of copper coating
Bonding process ( copper t
steel)
Clamps
Thickness
Diameter
Material
Split bolt connectors
Bolt Thread length
Slot width of the nut
Unit
mm
mm
mm
1500
15
0.33
mm
mm
mm
mm
Min. 8.3
Min.
Polyethylene
Page 1
Date: 1/5/2013,
EEPCO
SPECIFICATION
TS-ME-01
SPECIFICATION TS-ME-01
EEPCO
Date
Brief Description
Rev 0
30 April 2013
First Issue
SPECIFICATION TS-ME-01
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
TARIFF METERS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
4.
ELECTRICAL SYSTEM CHARACTERISTICS
2
5.
TESTS
2
5.1
5.2
5.3
5.4
ROUTINE TESTS
TYPE TESTS
ADDITIONAL TYPE TEST
TYPE TEST CERTIFICATES
2
3
3
4
6.
7.
8.
9.
10.
11.
METER TYPES
CONSTRUCTIONAL FEATURES
COMMUNICATION & SOFTWARE
COMMUNICATION PROTOCOL
ELECTRICAL CHARACTERISTICS OF METERS
RECORDING FACILITIES FOR ELECTRONIC METERS
4
5
9
10
11
12
11.1
GENERAL
12
12.
13.
14.
15.
16.
17.
BIDDER INFORMATION
PACKING
CONTRACT DRAWINGS AND INFORMATION
SPARE PARTS
QUALITY ASSURANCE
MANUFACTURERS QUALIFICATIONS
13
14
14
14
15
15
17.1
17.2
MANUFACTURING EXPERIENCE
SUPPLEMENTARY QUALIFICATIONS
15
15
18.
SPECIFIC REQUIREMENTS FOR KWH METERS
HAND HELD METER READERS (HHMR)
1.
SCOPE
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
3.
BASIC FUNCTIONS
4.
HARDWARE REQUIREMENTS
5.
DISPLAY
6.
KEYBOARD
7.
BATTERY
8.
MEMORY
9.
ENVIRONMENTAL CHARACTERISTICS
10.
SOFTWARE REQUIREMENTS
11.
RADIO FREQUENCY READING FUNCTION
LPA GECE / ts-me-01 r0 tariff meters and hhmrs.docx
1
1
1
1
1
1
2
2
2
2
2
3
3
SPECIFICATION TS-ME-01
EEPCO
12.
13.
14.
3
4
4
14.1
14.2
GENERAL
COMPUTER SOFTWARE
4
4
15.
16.
17.
18.
5
5
5
6
18.1
18.2
18.3
6
7
8
SPECIFICATION TS-ME-01
SECTION 1 - SCOPE
EEPCO
SCOPE
This specification covers the general requirement of design, manufacture and
testing of Tariff Meters and hand held meter readers (HHMRs). The Electronic
Meter is used for customer tariff meter in this project while Electro-Mechanical
Meter is optional.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards. In particular:
BS EN 50160
IEC 61036
IEC 60521
SPECIFICATION TS-ME-01
EEPCO
4.
50 Hz
LV system
System
earthing:
solidly earthed
Connection
arrangement:
5.
TESTS
5.1
ROUTINE TESTS
The following routine tests as per IEC 60521 or its replacement shall be carried
out on all the meters ordered;
400% basic current, reference voltage and at 0.5 lagging power factor.
200% basic current, reference voltage and at 0.5 lagging power factor.
SPECIFICATION TS-ME-01
EEPCO
5.2
SECTION 5 - TESTS
Register test.
TYPE TESTS
The Type Tests shall be carried out at the rated system LV voltage of 230V and at
a reference frequency of 50 Hz.
a)
b)
Heating.
c)
d)
e)
Adjustment
f)
g)
Effect of high temperature Test as per Clause 9.4 of this Standard. The test
certificates shall clearly identify the kWh meter tested, showing the following;
5.3
Manufacturer's identity.
Model / type number.
Type of register.
Type of rotor bearing, break magnet and other basic parameters.
SPECIFICATION TS-ME-01
EEPCO
5.4
0.5 when the meter operates on Ib at unity power factor and when the meter
operates on Ib at 0.5 lagging. (where Ib = base current).
6.
METER TYPES
All meters types shall comply to the relevant IEC standards above.
They shall be of the following types and ratings (Ib/lmax) of mechanical or
electronic type as specified in the Technical schedules:
Meter Code
Meter Type
Electro /
Mechanical
Electro
nic /
Mecha
nical
SPECIFICATION TS-ME-01
EEPCO
1ph-5/20-M
1 2 wire
230
5(20)
Yes
Mecha
nical
1ph-5/40-M
1 2 wire
230
5(40)
Yes
Mecha
nical
1ph-5/40-E
1 2 wire
230
5(40)
1ph-10/100-M
1 2 wire
230
10(100)
Yes
Mecha
nical
1ph-20/120-M
1 2 wire
230
20(120)
Yes
Mecha
nical
1ph-5/100-E
1 2 wire
230
5(100)
Electr.
3ph-5/100-E
3 4 wire
400
5(100)
Electr.
Electr.
CT connected meters
1ph-5/20-E-CT
1 2 wire
CT driven
230
5(10)
Electr.
3ph-5/20-E-CT
3 4 wire
CT driven
400
5(10)
Electr.
3ph-5/20-ECT-VT
3 4 wire
CT/VT
driven
100
5(10)
Electr.
The meter coding above will be used for quick meter referencing purposes.
7.
CONSTRUCTIONAL FEATURES
The meters shall have the following constructional characteristics as minimum:
7.1.1
Meter Fixing/Mounting
The meter will be fixed mounted in the meter box or generally on any surface
internal or external using a fixing method that will prevent removing the meter
without removing the terminal cover.
The fixing shall not require the opening of the metering compartment of the
meter and shall not interfere with the IP rating of the meter.
No adjustments for the levelling of the meter shall be necessary.
7.1.2
IP Protection
Protective class II.
Overall Metering compartment shall be IP 54 or better.
Meter terminal section shall be IP 33.
7.1.3
Housing
Base and terminal block shall be manufactured by high quality non-conductive,
high impact, smooth finish, durable, non-flammable, UV stabilized, UV resistant
and high resistance to weathering material.
SPECIFICATION TS-ME-01
EEPCO
Main cover and terminal cover design and sealing facilities shall be such that
access to working parts and adjustments is only possible by breaking the seal and
opening the meter cover.
Design of the meter shall be such that it shall not be possible to remove the meter
cover without removing the terminal cover.
The meter cover shall be secured by sealable screws.
7.1.4
7.1.5
Reading Window
If the meter cover is not made from transparent materials the meter reading
window shall be made of glass or a clear/transparent - flame retardant, high UV
resistance, high tensile and impact strength, permanently fastened to the meter
cover. It shall not be possible to remove the cover without breaking it.
7.1.6
7.1.7
Electrical Diagram
Meter connection diagram shall be engraved inside the terminal cover or it shall
be printed on material that can be fixed inside the cover without deterioration
with time.
7.1.8
Terminal Cover
A long extended terminal cover shall be provided. This shall be made of high
quality rust-proof material, non-flammable, UV stabilized, high tensile and impact
strength. It shall be fastened in position from the front by sealing screws.
SPECIFICATION TS-ME-01
EEPCO
7.1.9
7.1.10
7.1.11
Registers displays/Counters
Registers for Electromechanical meters
Digital- jumping mechanical registers shall be provided.
A 5 digit large jumping cyclometer register with the least significant digit to be 1s
of kWh. In addition, a display of fractions of kWh to 1/10th KWh resolution with
10 subdivisions, for test purposes and to be clearly identifiable as such.
Registers shall be registering energy regardless of connection polarity as positive
consumed, i.e. if the meter connection is reversed the meter shall continue to
register correctly the consumed energy.
Registers for Electronic Meters
Electronic meters shall be fitted with reverse running stop or reverse power
indicator (reset to require action by the Utility, such as disconnection of supply, or
software reset).
It shall also be possible to configure the meter to register the energy consumed
regardless of the direction of flow to account for reversal of current connections.
A 5 or 6 digit display with non-volatile memory (not battery backed), with the
least significant digit to be 1s of kWh. The display must be easy to read under the
normal expected conditions of service. A configurable display should not show
fractions of a kWh when in service. Reconfiguration at the Meter Test Station to
show fractions of kWh (to at least 1/100th kWh resolution) for test purposes is
then a requirement. Where this is not possible, 5 significant digits, a clear decimal
point and then 2 digits of decimals is an acceptable alternative.
Register counter shall be protected from external magnetic fields.
Large easy to read backlit LCD.
Also electronic meters with mechanical register will be acceptable if so specified in
the technical schedules.
Programmable display.
SPECIFICATION TS-ME-01
EEPCO
7.1.12
Meter Markings
All nameplate markings shall be in English languages. Other languages shall not
be used.
The phases and number of wires shall be marked in text, not graphical symbols
All markings shall be resistant to solar radiation.
The meter constant shall be marked, product trademark, type, model, serial
number, voltage, basic/rated current, frequency, rev/kWh, class, IP,
manufacturing year.
The nameplate shall be marked "Property of EEPCo.
In addition to the requirements of IEC 62052-11, 62053-21 and IEC 61036,
61030, each meter shall have a unique identification number indelibly marked on
the nameplate. The identification number sequence will be advised at the time of
ordering. This identification shall be additional to the maker's serial number.
Supplied with bar-coded type code/serial number label.
7.1.13
Pulse output
Where specified in the technical schedules pulse output shall be provided.
7.1.14
SPECIFICATION TS-ME-01
EEPCO
8.
8.1.1
8.1.2
Infrared
An infra-red device shall be an integral part of the meter with the following
characteristics.
Modulating Infrared.
ANSI standard optical port minimum 12,000 Baud rate.
IEC 62056-21 communication requirements.
ANSI C12.18 communications protocol.
CENELEC A-band power line communication channel.
It shall be able to be read at any time of the day or night.
SPECIFICATION TS-ME-01
EEPCO
a)
8.1.3
8.1.4
Inductive Loop
Inductive loop method of communication shall be provided as an integral part of
the meter. It shall be possible to read the meter from a distance of 0.5m
8.1.5
8.1.6
9.
COMMUNICATION PROTOCOL
The meter shall communicate using standard international protocols.
Data error checking in every data block.
As a minimum it shall accommodate the IEC 1107 and 62056.
At the moment no metering code exists in the country.
The required software to be installed in any computer of the clients office shall be
provided with the supply of meters. If the software is to be priced separately the
bidder must provide a separate entry in the bill of quantities and prices. If there is
no such entry it shall be deemed that the price for the software is included in the
supply price of the hand held meter readers.
The contractor shall install and configure the software for the meter reading on
the clients computers. A standard software set-up disk shall be produced which
can enable to load the meter program on other locations if the client established
another meter reading locations within his business.
The protocol used for the communication shall be disclosed to the client to
enable the integration of the meters to the existing systems. In the cases where the
protocol is considered intellectual property and cannot be disclosed the supplier
shall undertake to reprogram or enable in any case the existing equipment of the
client to communicate with the meters provided.
SPECIFICATION TS-ME-01
EEPCO
SECTION 10 - ELECTRICAL
CHARACTERISTICS OF METERS
The cost for modifying existing equipment shall be deemed to be included in the
price of the meter supplies unless it is included separately in the Bill of quantities.
If it is a separate cost then this will be considered as part of the bid price.
10.
10.1.1
Electromagnetic compatibility
To meet the Electromagnetic Compatibility Requirements and, as a minimum, to
withstand the supply conditions described in BS EN 50160.
10.1.2
Power Loss
Maximum Power Loss shall be as stated in the technical schedules.
10.1.3
Accuracy
The accuracy class of the meter shall be according to IEC62053.21, as stated in
the particular meter type requirements below and technical schedules.
10.1.4
Adjustments
Meters shall be fitted with a ready means of adjustment for all factors that affect
the calibration.
The low load, power factor and full load adjustments shall be indelibly marked
and easy access to the same shall be available.
These shall be stable, sensitive and easily accessible and shall not comprise of
parts, which are fragile or complicate.
The adjustments devices would preferably be by means of micro screws.
The rotation direction of the adjustment devices shall be clearly indicated.
Full load adjustment shall be independent from low load adjustment.
Adjustment/Calibration are accessible from the front and do not require any
special tool.
10.1.5
10.1.6
SPECIFICATION TS-ME-01
EEPCO
withstand voltage test (on 1.2/50s) shall be not less than 6 kV. In addition to the
requirements of IEC 60521 and IEC 61036, bidders are invited to submit
evidence of enhanced performance to withstand short-time overvoltages.
11.
11.1
GENERAL
Recorded items used for consumer invoicing quantities shall be retained on nonvolatile memory. Other data shall be retained for a minimum of one month.
There shall be no batteries used for the purposes of retaining information in case
of supply disconnections, unless the battery life will suit the recalibration period
of the meter which shall be a minimum of 10 years or as stated in the technical
schedules whichever is higher.
Recordings of the following quantities shall be stored depending of technical
requirements as stated in the technical schedules:
11.1.1
11.1.2
Period reading
1) Periodic Recording since last reading (Resettable during meter reading)
2) Energy (kWh) consumed since last reading
3) Reactive energy KVArh consumed since last reading
4) Reactive energy KVArh produced since last reading
5) Maximum (kW) demand since last reading (resettable)
6) Maximum Current (A) since last reading on each phase and total (resettable)
7) Maximum voltage (V) in each phase
8) Minimum voltage (V) in each phase (not including interruptions)
9) Number of power disruptions (resettable)
10) Total time of disruption
11) Event recording memory of not meeting statutory requirements
SPECIFICATION TS-ME-01
EEPCO
11.1.3
Present values
1) kW in each phase and total
2) Amperes in each phase
3) Volts in each phase
4) Power factor in each phase and total
12.
BIDDER INFORMATION
The following shall be furnished with the offer.
1) A full technical description of the meter(s) offered shall be provided with the bid.
All information shall be in English language. The bid shall include all technical
information listed in the Technical Schedules.
2) Type test certificates shall be provided with the bid. The certificates shall be less
than five years old.
3) Catalogues describing the meter and indicating the type and model number.
4) Literature describing the operational features of the meter.
5) Constructional features, materials used for components and relevant technical
literature for the following shall be furnished;
For Mechanical meters if applicable
Permanent magnet.
Magnetic bearing.
Register.
Voltage coil.
SPECIFICATION TS-ME-01
EEPCO
SECTION 13 - PACKING
13.
PACKING
If the meter does not form part of an integrated equipment then the following
shall apply.
Each meter shall be securely packed in an individual cardboard box. The box shall
be labelled in English language on the outside with a description of the contents.
Delivery, boxes shall be additionally packed in a weather protected outer box or
carton containing approximately 20 meters. This container shall be marked in
English language with a description of the contents.
The type, rating and serial numbers of the item shall be clearly stated on the box
labels.
14.
15.
SPARE PARTS
With the supply of meters, the manufacturer shall provide the following spare
parts to the nearest highest number:
Terminal covers :
0.5%
1.0%
SPECIFICATION TS-ME-01
EEPCO
16.
QUALITY ASSURANCE
The manufacturer shall possess ISO 9001 : 2000 Quality Assurance Certification
for the design, manufacture and testing of kWh meters. In the event the meters
are manufactured in a plant under the licence of the manufacturer, the
manufacturing plant shall possess ISO 9001 : 2000 Quality Assurance Certificate
for manufacturing and testing of Single Phase kWh Meters.
The Bidder shall furnish a copy of the ISO Certificate certified as true copy of the
original from the manufacturers, along with the offer.
If the following items are purchased from other manufacturers, they shall have
ISO 9001 Quality Assurance Certification for the manufacture of same for the
plant where the manufacture is done. The Bidder shall furnish copies of the ISO
Certificates certified as true copies of the originals from the manufacturers, along
with the offer;
Permanent magnet.
Magnetic bearing.
Register.
Manufacturer shall have in-house meter testing facility comply with the
requirements of ISO/IEC : 17025 : 2005.
Proof document shall be submitted to prove this accreditation.
17.
MANUFACTURERS QUALIFICATIONS
The items listed below are considered important for safeguarding the quality of
the meters to be supplied and the Bid may be rejected if in the opinion of the
evaluating body the Bidder has not demonstrated that the meters offered meet the
quality requirements through the certification required.
17.1
MANUFACTURING EXPERIENCE
The meter manufacturer shall have at least ten years (10) of experience in the
manufacture of Energy Meters. Documentary proof for the manufacturing
experience shall be provided.
In addition, sufficient documentary evidence such as name of purchaser, year of
sale, quantity sold, purchase orders, model numbers of the meter sold etc. for the
last 10 years shall be furnished for at least 10 main major with the offer.
The meter manufacturer shall guarantee that the offered meters will operate
within the stipulated error limits for the period specified under calibration section
above without requiring re-calibration.
17.2
SUPPLEMENTARY QUALIFICATIONS
The following supplementary qualifications will be considered in the evaluation of
bids. Hence if the equipment offered meets any one or more of the following
criteria the bidder shall further qualify for the selection;
Certificates for Service life
SPECIFICATION TS-ME-01
EEPCO
SECTION 17 - MANUFACTURERS
QUALIFICATIONS
SPECIFICATION TS-ME-01
EEPCO
18.
1ph5/20
-M
1ph5/40
-M
1ph5/40
-E
1ph10/100
-M
1ph20/120
-M
1ph5/100
-E
1ph5/20
-E-CT
3ph5/100
-E
3ph5/20
-E-CT
3ph5/20-E
-CT-VT
1
1.1
General Characteristics
M
1.2
1.3
1.4
1.5
1.6
1.7
1.8
1.9
2
2.1
No. of Wires
230
230
230
230
230
230
230
400
400
110
10
20
20
40
40
100
120
100
10
100
10
10
No. of Tariffs
CT Operated
No
No
No
No
No
No
Yes
No
Yes
Yes
Reading
communication
IR
IR
IR
IR
IR
GPRS
No
No
No
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
Yes
No
Yes
Yes
2.2
3
3.1
3.2
3.3
4
Mechanical Electronic
(M/E)
No. of Phases
Communication
Yes
Registers Continuous
Active Energy kWh
Reactive Energy
kVArh
Load profile
SPECIFICATION TS-ME-01
EEPCO
4.1
4.2
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
5
5.1
5.2
5.3
5.4
5.5
1ph5/20
-M
1ph5/40
-M
1ph5/40
-E
1ph10/100
-M
1ph20/120
-M
1ph5/100
-E
1ph5/20
-E-CT
3ph5/100
-E
3ph5/20
-E-CT
3ph5/20-E
-CT-VT
No
No
Yes
No
No
No
Yes
No
Yes
Yes
No
No
Yes
No
No
No
Yes
No
Yes
Yes
No
No
Yes
No
No
No
Yes
No
Yes
Yes
No
No
Yes
No
No
No
Yes
No
Yes
Yes
No
No
Yes
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
Yes
No
Yes
Yes
No
No
No
No
No
No
Yes
No
Yes
Yes
Max Voltage
No
No
No
No
No
No
Yes
No
Yes
Yes
Min Voltage
No
No
No
No
No
No
Yes
No
Yes
Yes
No. of disruptions
No
No
No
No
No
No
Yes
No
Yes
Yes
Registers- Instantaneous
Power (kW)
No
No
No
No
No
No
Yes
No
Yes
Yes
Power (KVA)
No
No
No
No
No
No
Yes
No
Yes
Yes
Current (A)
No
No
No
No
No
No
Yes
No
Yes
Yes
Volts (V)
No
No
No
No
No
No
Yes
No
Yes
Yes
Power factor
No
No
No
No
No
No
Yes
No
Yes
Yes
SPECIFICATION TS-ME-01
EEPCO
SECTION 1 - SCOPE
SCOPE
This specification defines the requirements for the design, manufacture, and
supply of hardware and software of hand held meter readers to be used in
conjunction with the meters to be supplied under the contract. The hand held
meter readers shall be used to read meters from other manufacturers and as such
the supplied equipment shall have suitable communication facilities to enable
them to communicate effectively and accurately with other manufacturers meters.
2.
3.
BASIC FUNCTIONS
The handheld data collection device shall have the capability to collect and store
readings at any time of the meter reading route by any of the following methods
unless otherwise stated so in the technical schedule:
The unit shall be able to obtain all readings stored in the energy meters on any
particular route without requiring:
Reprogramming of the handheld computer.
Physical change of software contained within the unit while in the field.
Access through special software menus contained within a given
route/program.
The meter shall be able to read meters manually and through infrared without
changing the program. If RF option is installed than the meter shall be able to
read the pre-programmed meters in the route when within range.
The instruction manual shall state clearly the procedure to follow to achieve the
method of meter reading.
4.
HARDWARE REQUIREMENTS
The handheld data collection device must be PC compatible and run under the
software interface program which the vendor shall provide free of charge.
The handheld devise shall be ergonomically designed to be comfortable for
handheld meter reading.
A hand strap must
be provided with each unit and must provide ease of use for
right- or left-handed operators.
SPECIFICATION TS-ME-01
EEPCO
5.
SECTION 5 - DISPLAY
DISPLAY
The handheld screen must be easily readable screen of more than 5 x5 cm visible
during the day and night. The size of the display characters must be selectable,
allowing the use of larger characters that are easiest to read.
There must also be a manual contrast adjustment feature which will allow the user
to adjust the contrast.
The display must have no degradation when exposed to temperatures stated in the
technical schedules
6.
KEYBOARD
The keyboard must have independent large keys of durable construction with
adequate separation for use with gloved hand.
The keyboard must provide tactile feedback
It shall be alphanumeric.
There must be an audible feedback on key press.
7.
BATTERY
The battery capacity must be sufficient for a minimum of 8 hours of meter
reading.
Preferred type shall be lithium ion rechargeable batteries.
However easily replaceable rechargeable batteries available in the market shall also
be possible to be used with the meter.
8.
MEMORY
The handheld data collection device must include sufficient memory to register at
least 5000 meter readings or as it may be specified in the technical schedule. The
unit shall retain the information in its memory even if the batteries are removed
(non-volatile memory)
The unit shall be able to accept a flash card type of external memory that can be
easily used to transfer information from the unit to the PC
9.
ENVIRONMENTAL CHARACTERISTICS
The handheld must include but not be limited to the following:
The unit must operate in temperature range specified in the environmental
specifications.
The device shall be water resistant, capable of unlimited exposure to spray or
splash (such as rain).
The device must be protected against static discharge.
The device must be shock resistant exceeding IEC 68-2-32 method 1 (a 1meter drop on concrete).
SPECIFICATION TS-ME-01
EEPCO
10.
SOFTWARE REQUIREMENTS
The handheld software must be easy to use and give the meter reader control over
the route in searching for accounts, tagging accounts for later action, entering
related notes and manually reading meters.
The handheld software must include entry of meter readings.
In addition, the handheld software shall include but shall not be limited to the
following basic features:
Allows manual or automatic entry of meter readings, ID numbers of meters
and note codes.
Performs high/low test on readings.
Date and time stamped to each reading.
Identifies type of reading manual keyed, probed or RF MIU.
Must be able to read encoders via either wireless probed reading or via RF
MIU.
Performs unread meter search.
Forward and reverse walk order allowed.
Data search capability
Auto-Search for automatic reading of encoded meters.
Displays the number of read and unread accounts on demand.
11.
12.
SPECIFICATION TS-ME-01
EEPCO
13.
14.
14.1
GENERAL
Communication facilities shall be provided to enable the hand held unit to
communicate effectively and efficiently with the host computer system. In
addition, the following basic features must be included:
Extensive error checking is provided to assure data integrity during
communications between the handheld and the PC.
A typical route could be loaded or unloaded in less than one minute.
Once loaded, routes may be individually selected on the handheld.
The communication shall be either through infrared or serial cables with or
without cradle.
Multiple handhelds must be able to be connected to the host computer.
14.2
COMPUTER SOFTWARE
The required software to be installed in any computer of the clients office shall be
provided with the supply of meters. If the software is to be priced separately the
bidder must provide a separate entry in the bill of quantities and prices. If there is
SPECIFICATION TS-ME-01
EEPCO
no such entry it shall be deemed that the price for the software is included in the
supply price of the hand held meter readers.
The contractor shall install and configure the software on the clients computers.
A standard software set-up disk shall be produced which can enable to load the
meter program on other locations if the client established anther meter reading
locations within his business.
The computer bases software shall be able to store the data in excel and database
format compatible with billing systems.
The stored data in excel shall also be able to be manipulated such as in cases of
substation metering data to determine the required information and analysis.
The supply of a billing system is outside the scope of this specification.
15.
16.
OTHER INFORMATION
The bidder shall state clearly the functions of the meter in addition the ones stated
above.
17.
TRAINING
The bidder shall provide training for the use of the meter readers and the
associated software to be provided for the base computers.
SPECIFICATION TS-ME-01
EEPCO
18.
SECTION 18 - SCHEDULES
SCHEDULES
If the technical schedules are to be included in the same file then use this section
18.1
SECTION 18 - SCHEDULES
SPECIFICATION TS-ME-01
EEPCO
18.2
NON-COMPLIANCE SCHEDULE
Schedule Ref TS-ME-01-NC1
The bidder shall provide a list of non-compliances with this specification,
documenting the effects that such non-compliance is likely to have on the
equipments life, operating characteristics and system performance. Each noncompliance shall make reference to the relevant specification clause.
Specification
Clause
SECTION 18 - SCHEDULES
SPECIFICATION TS-ME-01
EEPCO
18.3
Non-compliance description
LPA-GECE
EEPCo
Please fill more schedules if more types of equipment offered that can fit on this sheet.
No
Item
Unit
Requirement
Bid Offer
1 Schedule Reference
TS-ME-01-S1-2
Requirement
TS-ME-01-S1-3
Meter Code
1ph-5/20-E-CT
3Ph-5/20-E-CT-3
1 phase electronic
meter with CT
3 phase electronic
meter with CT
Yes
Yes
No of Phases
No of Wires
2.2
2.3
2.4
2.5
2.6
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
Bid Offer
Manufacturer
Catalogue No
Manufacturer's Description if Item
Model
Country of Origin
Basic Meter Characteristics
Electronic type
Maximum Current
10
10
% of Ib
0.02
0.002
mA
10
10
Operating Voltage
230
400
% of rating
+20
+20
% of rating
-35
-35
degr C
-5
-5
degr C
+65
+65
Hz
50
50
Frequency
LPA-GECE
No
Item
1 Schedule Reference
2
3.15
3.16
3.17
4
4.1
5.11
5.12
5.13
Requirement
Bid Offer
Requirement
TS-ME-01-S1-2
TS-ME-01-S1-3
1ph-5/20-E-CT
3Ph-5/20-E-CT-3
Hz+/-
IP
54
54
Yes
Yes
Yes/No & m
Yes
Yes
Yes/No & m
No
No
Yes/No & m
No
No
Yes/No
Yes
Yes
Yes/No & m
No
No
Digital
Digital
IP Rating
CT Operated
Bid Offer
Communication
Infrared or similar remote hand held meter
reading accessory
Unit
Meter Code
Frequency tolerance
EEPCo
RS 485 Link
Communication Protocol Provided
GPRS
Registers
Type of Register
No of Tariffs
min
kWh
Yes
Yes
kVArh
Yes
Yes
kW
Yes
Yes
KVAr
Yes
Yes
kVA
Yes
Yes
kVA
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
LPA-GECE
No
Item
1 Schedule Reference
2
Unit
Requirement
Bid Offer
Requirement
TS-ME-01-S1-2
TS-ME-01-S1-3
1ph-5/20-E-CT
3Ph-5/20-E-CT-3
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
N/R
Yes
Load Profile
Yes
Yes
Yes
Yes
Power Factor
Yes
Yes
English
English
Meter Code
5.14 Volts
5.15 Maximum Voltage over period (resetable)
5.16 Minimum voltage over period during operation
5.17
5.18
5.19
5.20
5.21
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12
6.13
6.14
6.15
6.16
EEPCo
(resetable)
Number of power disruptions (resetable)
Bid Offer
Other Data
Language of Labels
Burden of each potential coil
VA
10
VA
0.5
2max
2max
EEPCo
EEPCo
0.5
0.5
Power Consumption
Meter constant
Rev/kWh
Reference Temperature
Temperature Co Efficient
%oC
Overload capacity
b)For thermal consideration
b) Ib to Imax at unit PF
c) Ib at 0.5 PF lagging
LPA-GECE
No
Item
1 Schedule Reference
2
Unit
6.20
7 Packaging & Other Details
7.1 Material of Meter Case
Bid Offer
Requirement
TS-ME-01-S1-3
1ph-5/20-E-CT
3Ph-5/20-E-CT-3
90
As per general
requirements
90
As per general
requirements
kV
kA
Requirement
TS-ME-01-S1-2
Meter Code
EEPCo
%
V
mm
7.6
7.7
7.8
7.9
7.10
mm
Weight of Meter
kg
Yes
Yes
Yes
Yes
Yes
Yes
7.11
7.12
7.13
7.14
7.15
Catalogue enclosed
Yes/No
Yes
Yes
Guaranteed Lifetime
years
25
25
Recalibration period
years
min 10 years
min 10 years
Warrantee Period
Months
36
36
Yes
Yes
Bid Offer
LPA-GECE
No
Item
1 Schedule Reference
2
7.16
7.17
7.18
7.20
Unit
Meter Code
Standard to which manufactured
Cable Terminal connection size
mm2
EEPCo
Bid Offer
Requirement
TS-ME-01-S1-2
TS-ME-01-S1-3
1ph-5/20-E-CT
3Ph-5/20-E-CT-3
IEC 62052,53,
IEC 62052,53,
16
16
As per spec
As per spec
Bid Offer
Yes/No
EEPCO
SPECIFICATION
TS-ME-02
SPECIFICATION TS-ME-02
EEPCO
Date
Brief Description
Rev 0
30 April 2013
First Issue
Rev 1
1 May 2013
SPECIFICATION TS-ME-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
METER CABINETS & METER CTS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
CONSUMER METER CABINETS
1
3.1
3.2
3.3
GENERAL REQUIREMENTS
SPECIFIC REQUIREMENTS FOR CONSUMER METER BOXES
SPARES FOR CONSUMER METER BOXES
1
6
7
4.
4.1
4.2
4.3
4.4
4.5
7
10
11
12
12
5.
12
5.1
5.2
5.3
5.4
PACKING
TESTS
FULL TEST PROGRAM ON SAMPLES
INSPECTION PROCEDURE
12
12
13
13
6.
13
6.1
6.2
6.3
6.4
6.5
6.6
6.7
GENERAL DESCRIPTION
STANDARDS
CHARACTERISTICS
CONSTRUCTION
CURRENT TRANSFORMER LABELLING
TESTING
DOCUMENTS TO BE PROVIDED
13
14
14
15
15
15
16
7.
SCHEDULES
17
7.1
7.2
7.3
17
17
18
SPECIFICATION TS-ME-02
EEPCO
SECTION 1 - SCOPE
SCOPE
This specification covers the general requirement of design, manufacture and
testing of a) Consumer Meter Cabinets b) Transformer Meter Cabinets and c)
Meter CTs.
2.
3.
3.1
GENERAL REQUIREMENTS
3.1.1
Usage
Two types of meter cabinets are specified namely for a) three meter arrangement
and b) 5 meter (not through CTs) arrangement.
The meters shall be directly connected.
All meter cabinet types (3 and 5 meter) shall be used for single phase consumer
supply connections.
The three single phase meter type may also be used to supply one 3 phase
consumer, using three single phase meters if necessary.
3.1.2
3.1.3
Cabinet mounting/Installation
The cabinet shall be suitable for the following mounting:
SPECIFICATION TS-ME-02
EEPCO
IP Rating
The cabinet shall provide protection of IP43 or better standard with the meter
door closed according to IEC 60529.
In addition the meter box shall be able to withstand the mechanical protection of
impact energy 20 joules (hammer of 5 kg falling from a height of 40 cm).
3.1.5
Cabinet door
The cabinet shall be designed with a door.
The door may be of two types a) removable and b) hinged on the side,
a)
b)
SPECIFICATION TS-ME-02
EEPCO
Padlock facilities shall also be provided for all door types to take a hasp of up to
10mm.
The padlock mechanism shall also keep the door in the closed position if the
sealing screw is loosened or removed.
The cabinet door fitting shall be such that rain water shall not enter the cabinet
(IP43).
The lock closing/opening mechanism shall be operated through a standard
triangular key of 10mm sides.
3.1.6
3.1.7
3.1.8
3.1.9
a)
SPECIFICATION TS-ME-02
EEPCO
The gland sizes shall be suitable to accommodate 8-35mm2 single core PVC
covered aluminium cable.
The other two entry wholes shall be constructed with knock-out type entry points
and shall be easy to tap-open the knockouts provided. These positions may be
used if the meter box is required to be used as a 3 phase consumer box.
b)
c)
d)
Spare glands
One spare glad shall be provided with each box supplied loose in the box in a
plastic bag.
3.1.10
Wiring
The cabinets shall be pre-wired for both meter box types (3 and 5 meter).
Each meter position shall be pre-wired with connections from the supply terminal
to the meter position and from the meter position to the consumer MCBs.
The connection philosophy that will be applied is as follows. The utility supply
will be terminated to the Utility terminal blocks. From the Utility terminal
blocks with pre-installed cables, connection will be made to the meter. From the
meter with pre--installed wired connection will be made to the consumer
MCBs.
The consumer connections will terminate on the load side (bottom) of the MCBs.
The wiring shall be with double insulated PVC, LV, single core 6 or 10mm2
copper cables as specified in the technical schedule.
The wiring colour from the supply point to the meter shall be Red and Black.
The wiring colour from the meter to the MCBs shall be Brown and Black
SPECIFICATION TS-ME-02
EEPCO
Black colour shall be used for the neutral in both cases and the red or brown for
the phase conductor.
3.1.11
3.1.12
SPECIFICATION TS-ME-02
EEPCO
The MCB thermal characteristic shall be trip free, type C unless specified
otherwise in the technical schedules.
The preinstalled/ internal wiring shall be connected to the top of the MCB and
the consumer terminals at the bottom of the MCB.
The MCBs shall be trip-free IP 30, rated for fault rating of at least 6kA.
The MCBs shall be installed on rigid DIN rails for snap on fitting.
The MCB general construction and quality requirements shall be according to
IEC standard 60898 and 60947-2.
Electrical endurance shall be at least 4,000 operations
Mechanical endurance shall be at least 20,000 operations
Three (3) or five (5) double units shall be installed and wired in the three meter
or five meter type cabinet respectively.
3.1.13
Cabinet Marking
The exterior of the door shall be permanently embossed with the Client logo and
EEPCo in letters not less than 10 mm height.
Equipment code shall also be provided according to engineers instructions.
For the five meter box one nameplate shall be provided with dimensions 60 x
250mm.
For the three meter box two nameplates shall be provided of size 60x 120mm.
The nameplates shall be mounted on the meter box door, between the windows.
Predrilled holes shall be provided on the front door. The name plates shall be
fixed through two pre-drilled holes. Fixing screws shall be provided including a
spare screw with every box. The name plates shall be 3mm thick of good quality
aluminium and the edges shall me smooth.
3.2
MCB/isolator sets
Terminal sets
Name plates
Key
SPECIFICATION TS-ME-02
EEPCO
3.3
4.
Item
Quantity
Terminal
blocks.
1% of total quantity
Meter cabinet
locking./sealing
screws
1%
Windows
Pole
Installation
straps
4.1
4.1.1
SPECIFICATION TS-ME-02
EEPCO
Cabinet mounting/Installation
The cabinet shall be suitable for the following mounting:
On all type of wood poles, concrete poles (round and square), or steel poles.
For pole fixing the cabinet shall be supplied with all necessary brackets and parts.
Fixing to wall shall be with screws not less than M8 accessible only from the
inside of the cabinet.
The complete set of installation straps for pole mounting shall be provided as lose
items with each meter box.
Alternatively the pole mounting straps may be provided as a separate item but
included in the meter cabinet cost.
Additional straps shall be provided as extra installation material as specified in the
spares requirements below.
The meter shall be installed at a height of about 2m measured from the ground to
the bottom of the meter box.
It must be noted that due to the multiple uses of poles, staff may stand on the
mounted meter boxes. The brackets and the support inside the boxes shall be
strong enough to support a person standing on the mounted box of weight 100kg,
The stainless steel strap shall also be of suitable strength to support the above
meter box mounting requirements.
4.1.3
IP Rating
The cabinet shall provide protection of IP43 or better standard with the meter
door closed according to IEC 60529.
In addition the meter box shall be able to withstand the mechanical protection of
impact energy 20 joules (hammer of 5 kg falling from a height of 40 cm).
4.1.4
Cabinet door
The cabinet shall be designed with a door.
SPECIFICATION TS-ME-02
EEPCO
The door may be of two types a) removable and b) hinged on the side,
a)
b)
4.1.5
4.1.6
SPECIFICATION TS-ME-02
EEPCO
4.1.7
Cabinet Marking
The exterior of the door shall be permanently embossed with the Client logo and
EEPCo in letters not less than 10 mm height.
Equipment code shall also be provided according to engineers instructions.
Two nameplates shall be provided of size 60x 120mm to mark the meter cabinet
with the required installation details. These details will be marked by the client or
the installation contractor...
The nameplates shall be mounted on the meter box door. Predrilled holes shall be
provided on the front door. The name plates shall be fixed through two predrilled holes. Fixing screws shall be provided including a spare screw with every
box. The name plates shall be 3mm thick of good quality aluminium and the
edges shall me smooth.
4.2
Power cables
The cables from the transformer LV shall run through the top of the meter box
from left to right through the ring type CTs.
Only the three phases will run through the meter box.
The position of the cable entries and the current transforms shall be such that the
cable run inside the box shall form an upward bend to prevent rain water from
leaking along the cables and inside the meter box.
Cable glands shall be provided for the power cables such that they shall cushion
the cable entry and seal the meter box entry. These may be made of durable
rubber suitable for the purpose. Also a two part gland may be acceptable to form
a seal and protection for the cable entry/exit.
The power cables shall form a drip line curve before entering the meter box.
b)
Neutral cable
A separate neutral cable from the transformer terminal shall run directly to the
meter.
The neutral cable shall enter the meter box from either side of the box through a
cable gland, below the power cables of at the bottom of the cabinet. The cable
shall be at least 10 mm2 double insulated cable.
The cable shall be connected to the transformer neutral terminal point through
dedicated cable lug. The connection shall be made either directly on the
Transformer neutral lug or it shall be connected on the main supply take-of lug.
c)
Voltage supplies
The voltage reference for the energy measurements shall be derived from an IPC
type line taps connector used with ABC conductors. The taps shall be made on
the three phase main cables running through the meter box on the outgoing side
of the cables. These taps shall be completely sealed and not be possible to
dismantle without destroying them...
SPECIFICATION TS-ME-02
EEPCO
These voltage connections (from the main supply cables) shall be connected to
the meter directly without any intervening terminals or MCBs.
The voltage wiring shall be with double insulated PVC, LV, single core 4mm2
copper colour coded cables - Red Yellow Blue.
d)
CT Connections
Connections from the CTs to the kWh meter shall be made using double
insulated PVC, LV, single core 4mm2 copper colour coded cables - Red Yellow
Blue.
4.3
4.3.1
a)
b)
On the pole
If the meter box is installed on the LV pillar then the CT/Voltage cables shall run
through a hole between the meter box and the LV pillar, with suitable grommets
and sealing of the cables. Double insulated single core multistring cables may be
used.
If the meter box is installed on a pole then a multicore control cable shall be
installed between the LV pillar and the Meter box. The control cable shall run in a
protective steel or aluminum conduit.
4.3.2
SPECIFICATION TS-ME-02
EEPCO
4.4
4.5
METER INSTALLATION
Meters will be provided separately and included in the Bill of Quantities. They
shall be installed in the meter box.
5.
5.1
PACKING
The meter box shall be supplied fully assembled, packing each box inside a
transparent plastic bag and paper separators between boxes and into individual
cartons.
5.2
TESTS
The meter box unit must successfully pass the following type test program.
The quality process of the manufacturer for the production of glass-fibber
reinforced polyester boxes must be certified by a qualified association according
to international quality standard ISO 9001 or ISO 9002. Bidders that will not be
accompanied by certificates ISO 9001 or ISO 9002 will not be evaluated and will
be rejected.
5.2.1
Routine test
The following routine tests shall be performed to each box
SPECIFICATION TS-ME-02
EEPCO
5.3
= 1mm
3) Temperature rise test: Heating limit 65C for electrical parts; 40 C for accessible
parts.
4) Accelerated wet heat test: Equivalent to IEC 68-2-4 cycles of 24 hours, 30C to
57C, Hr 95%.
5) Dielectric test: Impulse 6 kV - industrial frequency 3 kV.
6) Temperature variation and UV test: Equivalent to IEC 68-2-4 and 68-2-5: 20
cycles of 12 hours UV during 5h/12h- temperature 70C to - 25C in 7h; - 25C
to 70C in 2h; 70C during 3h.
7) Heating test: 100 during 5 h.
8) Solidity of screws and nuts.
9) Protection degree: IP 439 as per IEC 529. 20 Joules as per IEC 68.2.2 on window
and the centre of the GRP tank and cover.
10) Resistance to heat and fire: Ball test: applying a steel 5 mm diameter ball during 1
h at 125 with 20N force: deformation < 2 mm. Self-extinguishibility: IEC 695-21; 960C.
A test to prove the mounting arrangements of the box to withstand a person
standing on the box once mounted of weight 100kg.
5.4
INSPECTION PROCEDURE
The Purchaser representatives will inspect the meter boxes for the routine tests.
If type test certificates are not available the Full test program on samples
described above will be organised and executed by the manufacturer and will be
witnessed by the clients representative. The Contractor or his subcontractor shall
provide all reasonable facilities and assistance, including access to drawings and
production data at no charge to the Purchaser.
The costs for the meter boxes shall include the full cost of inspection and shall
include travel expenses from the clients place to the manufacturers premises,
local transport and reasonable accommodation.
6.
6.1
GENERAL DESCRIPTION
The LV current transformers for billing metering must be certified or at least be
certifiable. Full range transformers are to be used (i.e. transformers which
SPECIFICATION TS-ME-02
EEPCO
maintain the specified measuring accuracy throughout the range from 0 to the
permitted maximum current).
The current transformers shall be ring type.
The internal dimensions of the transformer are to correspond to the technical
regulations covering current carrying capacity (cross-section, bus-bar);
Single ratio CTs shall be provided.
6.2
STANDARDS
IEC 60044-1 - Instrument Transformers- Part 1 Current Transformers
IEC 60185 Instrument Transformers Withdrawn Replaced with 60044-1
6.3
CHARACTERISTICS
Primary current transformers shall be of the preferred transformation values of:
a)
b)
Ratios
Primary
nominal current,
In (A)
100
200
300
400
600
800
1000
1500
2000
Secondary
nominal current,
In (A)
5
5
5
5
5
5
5
5
5
Item
Ratings
Thermal short-time
current:
Maximum voltage:
Dynamic short-time
current:
Thermal nominal
continuous current:
Over-current factor
Insulating material class
Electricity accounting
approval
Ith = 20 x IN
Umax = 0.72 kV
IDyn = 2.5 x Ith
ID = 1.2 x IN
M5 (10% total error up to 5 times the
primary nominal current)
E (continuous thermal stability up to
120C)
class 1.0
SPECIFICATION TS-ME-02
EEPCO
6.4
CONSTRUCTION
According to IEC 60044-1
The CTs shall be of ring type CTs without primary bar, suitable for outdoor use.
The core aperture shall be not less than 40mm diameter in order to accommodate
up to two 300mm2 copper cables.
The current transformer shall be of the cast epoxy resin insulated type suitable for
operation in outdoor tropical climatic conditions as stipulated in climatic
conditions specification. The insulation shall be suitably treated to prevent
deterioration due to ultra violet radiation of sunlight. The dielectric strength shall
not be less than the stipulated in the technical requirements.
The relative polarities shall be permanently marked on the current transformers as
per IEC 60044-1.
Nickel-plated secondary terminals each with 2 plus minus combined screws M5 x
10 mm for the connection of copper conductors up to max. 4 mm2.
Terminals and Terminal Covers
The secondary terminals of the current transformer shall be housed in a weather
resistant and waterproof terminal box with rubber grommet to take out the CT
leads. It shall not be possible for insects to enter the terminal cover.
Secondary terminal housing shall be sealable.
Terminal covers shall preferably be made of transparent material to easily inspect
the terminal conditions without opening the terminal.
6.5
Manufacturer
Transformer type
Instrument number
Accuracy class
6.6
TESTING
6.6.1
Routine Tests
The Routine Tests shall be carried out on all Current Transformers as per IEC 441 and the test report shall be submitted to the Clients representative.
1) Verification of terminal Markings
2) Power frequency withstand on primary winding
SPECIFICATION TS-ME-02
EEPCO
Type tests
Type test certificates according to IEC 60441-1 shall be provided namely:
1) Short time current curves
2) Temperature rise tests
3) Impulse withstand tests
4) Switching impulse test
5) Wet tests for outdoor type transformers
6) Determination of errors
7) Radio interference
8) Dielectric test
6.7
DOCUMENTS TO BE PROVIDED
a)
b)
SECTION 7 - SCHEDULES
SPECIFICATION TS-ME-02
EEPCO
7.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
7.1
7.2
SECTION 7 - SCHEDULES
SPECIFICATION TS-ME-02
EEPCO
7.3
LPA-GECE
EEPCo
Type
1
Manufacturer
Catalogue No
Country of Origin
IP rating
10
Rated current
11
12
MCB
13
Neutral of MCB
14
IP rating
15
Fault rating
16
Electrical endurance
operation
17
Mechanical endurance
operation
43 or better
A
IEC 60898,
60947-2
kA
19
21
mm
22
mm
23
24
25
20
27
Locking Mechanism
28
Padlock Manufacturer
29
Non Metal
Standard Padlock
mm/mm /mm
650x400x250
Material
31
Thickness of walls
32
Glass fibre
reinforced moulded
polyester (SMC)
mm
at least 3 mm
ivory or light grey
LPA-GECE
EEPCo
No
Item
33
Fire resistant
34
Construction/Design
35
Type of fibers
36
Cabinet Door
37
Humidity
Unit
Requirement
Fire resistant
glowing wire
960Cand flame
retardant.
Hot moulded by
compression
Long fiber multi
direction
removalbe with
hook up, or Hinged
door
60 to 95
Bid Offer
39
Material
As per scope
Thickness of walls
Wiring
40
41
meter to MCBs
42
Wiring size
mm
2.5
LPA-GECE
EEPCo
Manufacturer
Catalogue No
Country of Origin
Type designation
VOLTAGE DATA
i) Rated voltage
720
Hz
50
kV peak
kV
kV peak
10
11
12
13
400
14
15
16
kA
150
17
18
19
20
-metering cores
-protection cores
21
22
40 oC ambient temperature
23
CT CORE DATA
24
i) Rated output:
oC
25
-core 1
VA
10
26
-core 2
VA
10
27
-core 3
VA
10
28
29
-core 1
Class
30
-core 2
Class
31
-core 3
Class
32
33
-core 1
ohms
34
-core 2
ohms
35
-core 3
MASS, DIMENSIONS &
MISCELLANEOUS
ohms
36
LPA-GECE
No
EEPCo
Unit
Requirement
37
degr C
-35
38
degr C
+65
39
kV
2.5 Ith
40
41
%
ID
10
1.2 IN
42
IEC
60044-1
43
mm
44
kg
45
46
Bid Offer
shrouded
EEPCO
SPECIFICATION
TS-ME-03
Consumer Service Cables
SPECIFICATION TS-ME-03
EEPCO
Date
Brief Description
Rev 0
May 2013
First Issue
Page: i , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERNECE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
2
2
3
5.
DESIGN REQUIREMENTS
5.1
5.2
3
3
6.
7.
8.
9.
10.
MARKING
CONCENTRIC CABLE CONSTRUCTION DATA
PACKING
SCHEMATIC DRAWINGS OF CONCENTRIC CABLES
SCHEDULES
4
5
1
3
4
10.1
10.2
10.3
4
4
5
Page: ii , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
SERVICE CABLES
1.
SCOPE
This specification covers the design, manufacture, supply, delivery and performance
requirements of Service Cables.
2.
3.
REFERNECE STANDARDS
The materials supplied shall conform to the latest edition of appropriate IEC
standard and/or other recognised international standards. In particular,
Specification
Standard Number
3.1
/ Title
IEC 60121
Commercial annealed
conductor wire
aluminium
electrical
IEC 60228
IEC 60287
IEC 60391
IEC 60446
IEC 60502
IEC 60540
IEC 60811
VDE 0271
TS-GN-01
CONFLICT
See specification TS-GN-02.
4.
Page: 1 , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
4.1
TYPE TESTS
Details of tests and requirements for the various sizes of service cables are as follows,
(i)
Test for low and high temperature response of insulation and outer sheath,
(ii)
Bending test,
(iii)
Elongation test,
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
(x)
(xi)
(xii)
(xiii)
(xiv)
High Voltage (1.8kV AC) Test for 4 hours as per VDE 0271, Clause 6.
(xv)
Determination of the Insulation Volume Resistivity as per IEC 60502, Clause 16.2.1
at,
(xvi)
(a)
(xvii)
(b)
4.2
ROUTINE TESTS
Routine tests shall be carried out on all lengths of cables being supplied.
(i)
4kV AC (or 12kV DC) 5 min. voltage withstand test in accordance with Clause 6 of
VDE 0271 (1986).
(ii)
(iii)
(iv)
Length of cable on drum - this shall vary by not more than 5% from the specified
value.
(v)
Resistance Tests.
Page: 2 , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
4.3
ACCEPTANCE TESTS
(i)
(ii)
(iii)
Cable construction to be such that the sheath can be stripped from insulation and the
cores can be separated from extruded bedding.
(iv)
(v)
(vi)
5.
DESIGN REQUIREMENTS
5.1
5.1.1
5.1.2
Size mm
Usage
16
16
25
Large workshops
Insulation
The insulation on the cores shall be a different colour for each core. Insulation
colour for Single core and three core cables shall be according to IEC requirements.
Conductor Insulation EPR (ethylene-propylene-rubber insulation), extruded
insulation
Outer sheath shall be black, elastomeric such as PCP (Polycloroprene)
5.2
Size mm2
Usage
10
16
16
Page: 3 , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
No. Of cores
Size mm2
Usage
25
35
Large workshops
6.
MARKING
The cable outer sheath shall be marked at every meter interval as follows,
" Electric cable 600/1000V, Size (eg 3x16mm), Material (Al), Maker, Year of
manufacture, running metrage (m) "
The marking shall be either embossed on the cable with the same colour or shall be
painted with indelible paint on the sheath of the cable.
The height of letters and numerals shall not be less than 3mm in the case of single
core cable and 4mm in the case of three core cable.
Page: 4 , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
7.
1X6/6
1x16/16
3X6/6
3x16/16
3x25/25
3x35/35
3x50/50
3.1
5.1
3.1
5.1
6.4
7.5
8.9
19
1.04
1.70
1.04
1.70
2.14
1.52
1.78
30
25
120
83
86
73
77
0.5
0.93
0.25
0.5
0.6
0.8
0.9
1.0
1.0
1.0
1.0
1.2
1.2
1.4
1.4
1.4
1.8
1.8
1.8
1.8
1.9
12
16
21
25
28
32
3.11
1.16
3.11
1.16
0.74
0.53
0.39
3.11
1.16
3.11
1.16
0.74
0.53
0.39
150
100
100
100
500
500
500
500
500
500
500
Page: 5 , 1-May-13
SECTION 8 - PACKING
SPECIFICATION TS-ME-03
EEPCO
8.
PACKING
Cables shall be placed on drums, reels or delivered in coils as appropriate.
Three copies of each packing list shall be sent to the Client prior to dispatch.
Drums, reels and coils shall be labelled with
(i)
serial number,
(ii)
cable type/size,
(iii)
number of cores,
(iv)
cable length,
(v)
(vi)
year of manufacture,
(vii)
drum measurements,
(viii)
(ix)
Contractor's name,
(x)
(xi)
Contract number,
(xii)
(xiii)
(xiv)
(xv)
(xvi)
(xvii)
(xviii)
Page: 1 , 1-May-13
SECTION 8 - PACKING
SPECIFICATION TS-ME-03
EEPCO
(xix)
description of contents;
(xx)
case measurements;
(xxi)
country of origin;
(xxii)
Page: 2 , 1-May-13
SPECIFICATION TS-ME-03
EEPCO
9.
1.
Round
stranded
conductor
tinned
copper
2.
EPR INSULATION
3.
4.
PCP SHEATH
1.
Round
stranded
conductor
2.
EPR INSULATION
3.
4.
5.
PCP SHEATH
tinned
copper
Page: 3 , 1-May-13
SECTION 10 - SCHEDULES
SPECIFICATION TS-ME-03
EEPCO
10.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
10.1
10.2
Page: 4 , 1-May-13
SECTION 10 - SCHEDULES
SPECIFICATION TS-ME-03
EEPCO
10.3
Page: 5 , 1-May-13
EDTL
Distribution
Schedule: TS-ME-03-S1
Technical Schedule for Copper Concentric Consumer Service Cables
Item
Unit
Require
Require
Require
Require
Require
Bid Offer
Bid Offer
Bid Offer
Bid Offer
Bid Offer
ment
ment
ment
ment
ment
No
1
Manufacturer
Catalogue No
Country of Origin
Cable Type - No of cores X number of
conductors / cross section mm2:
Conductor and screem Material
1X6/6
1x16/16
3X6/6
3x16/16
3x25/25
Cu
Cu
Cu
Cu
Cu
ERP
ERP
ERP
ERP
ERP
ERP
ERP
ERP
ERP
ERP
10
Black
Black
Black
Black
Black
11
No
12
No
30
25
120
83
86
13
mm
1.2
14
mm
1.4
1.4
1.8
1.8
1.8
15
/km
3.11
1.16
3.11
1.16
0.74
16
/km
3.11
1.16
3.11
1.16
0.74
17
18
mohm/km
19
pF/core/m
20
1000/400
1000/400
1000/400
1000/400
1000/400
21
kV
1.1
1.1
1.1
1.1
1.1
22
23
24
oC
90
90
90
90
90
25
Kg
26
27
Drum length
500
500
28
Drum weight
Kg
29
YES
YES
mm2
ohm/km
kA at 1 sec
N/mm2
YES
YES
Page 1/1
YES
EEPCO
SPECIFICATION
TS-SG-01
SPECIFICATION TS-SG-01
EEPCO
Date
Brief Description
Rev 0
25/1/2011
First Issue
Rev 1
Jan 2013
Rev 2
Feb 2013
Page: i , 4-Apr-13
SPECIFICATION TS-SG-01
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED MV DROP OUT FUSES
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS& SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
1
2
2
5.
DESIGN
5.1
5.2
5.3
GENERAL
CONSTRUCTION
FINISH
2
4
8
6.
7.
PACKING
SCHEDULES
9
9
7.1
7.2
7.3
9
10
11
Page: ii , 4-Apr-13
SPECIFICATION TS-SG-01
EEPCO
SCOPE
This Specification covers the design, manufacturing, testing, supply, delivery and
performance requirements of 15kV and 33kV Pole mounted Dropout Fuses.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
Specification/
Standard Number
Title
IEC 60060
IEC 60129
IEC 60282-2
IEC 60383
IEC 60437
IEC 60507
IEC 60694
NEMA SG2
IEEE C37.41
ANSI C37.42
CONFLICT:
See spec TS-GN-01
4.
4.1
TYPE TESTS
The following type tests as per the relevant standard shall be conducted on the
equipment of identical design to prove that the offered equipment satisfies all the
design requirements set out in this specification.
Page: 1 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
a)
b)
4.2
ROUTINE TESTS
Routine tests shall be carried out on the Equipment in accordance with
IEC60129, IEC 60282. All routine tests will be free of charge to the Employer
and any item not meeting the routine test requirements shall be rejected.
The following tests shall be conducted.
(i)
Visual inspection,
(ii)
(iii)
(iv)
4.3
ACCEPTANCE TESTS
The following acceptance tests shall be conducted.
(i)
Visual inspection,
(ii)
(iii)
Checking of the result of the routine and type test as per IEC,
(iv)
(v)
5.
DESIGN
5.1
GENERAL
5.1.1
Definitions
a)
Dropout Fuse
It is that in which the fuse holder automatically drops into an open position after
the fuse has interrupted the circuit.
b)
Fuse Holder
A fuse holder is an assembly of a fuse tube together with parts necessary to
enclose and provide means of making contact with the conducting element and
the fuse contacts. The fuse holder does not include the fuse link.
c)
Fuse Link
Page: 2 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
e)
f)
g)
The rated interrupting current of a fuse is the designated highest available R.M.S
short-circuit current at which the fuse is designed to perform its disconnection
function under stated conditions.
h)
Recovery Voltage
Recovery voltage is the voltage, which occurs across the terminals of a pole of a
circuit interrupting device after an interruption of the current.
i)
Break Distance
The break distance of a fuse or switch is the minimum open-gap distance between
the live parts when the fuse holder is in the open position.
5.1.2
15kV
33kV
24kV
52kV
100A
100A
125kV
250kV
130kV
260kV
Rated one minute power frequency withstand voltage (dry & wet)
To earth and between poles (rms)
50kV
95kV
76kV
105kV
250mV
250mV
65C
65C
Terminals
50C
50C
Page: 3 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
Metal parts acting as springs
12kA
16kA
5.2
CONSTRUCTION
5.2.1
a)
b)
Fuse holder,
c)
Fuses.
1) The MV Pole-Mounted Dropout Fuse Sets shall be of the outdoor type, and
completely assembled and tested at the manufacturers workshop. The equipment
in the MV Pole-Mounted Dropout Fuse Sets shall be installed with necessary
clearances, easy access to the HRC fuses for testing, maintenance, removal and
normal operation and to provide safety measures against all possible hazards.The
MV Pole-Mounted Dropout Fuse Sets of similar ratings shall have the same
dimensions having components and devices interchangseable with those of other
units.
2) These Dropout Fuse Sets shall be designed to ensure that thermal interaction
does not unduly affect the performance of any of the components.Each set of
MV Pole-Mounted Dropout Fuse Sets shall include a cross-arm mounting
bracket.The MV Dropout Fuse Sets shall be supplied with mounting bolts, nuts
and washers. Bolt threads shall conform to ISO. The nuts shall have a proper fit
so that the nut can be run over the entire length of the threads without an undue
force.
3) The MV Pole-Mounted Dropout Fuse Set shall be installed on cross-arms at PoleMounted MV/0.4 kV Transformer Substations.
4) Dropout Fuse Sets shall be hand-operated from ground level using a glass fibre
tube stick, which shall also be designed to facilitate replacement of the fuse links.
Dropout Fuse Sets shall be of single-phase type.
5) Contacts of the fuse cut-out shall be suitable to terminate the line conductors.
6) Fixing brackets, bolts, nuts, hooks and washers for mounting of the cut-outs shall
be provided.
7) Fuses shall be co-ordinated with the ratings of the related distribution
transformers.
8) The cut outs shall be of single vent type (downward) having a front connected
fuse carrier suitable for angle mounting.
Page: 4 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
(ii)
5.2.2
All ferrous parts shall be hot dip galvanised in accordance with the relevant
standard .Nuts and bolts shall conform to IEC.Spring washers shall be electrogalvanised.
FUSE BASE TOP ASSEMBLY
The top current carrying parts shall be made of a highly conductive copper alloy
and the contact portion shall be silver plated for corrosion resistance and efficient
current flow. The contact shall have a socket cavity for latching and holding
firmly the fuse carrier until the fault interruption is completed within the fuse.
The top contact shall be actuated by a strong steel spring which keeps it under
sufficient pressure to maintain a firm contact with the fuse carrier during all
operating conditions. The spring shall also provide flexibility and absorbs most
of the stresses when the fuse carrier is pushed into the closing position.
The current carrying parts of the assembly shall be protected from water and dust
formation by a stainless steel top cover.
The top contact assembly shall have a robust galvanised steel hook to align
and guide the fuse carrier into the socket latch even when the fuse carrier is
closed at an off-centre angle.
The top assembly shall have an aluminium alloy terminal connector
The top assembly shall be robust enough to absorb the bulk of the forces during
the fuse carrier closing and opening operations and shall not over-stress the
spring contact. It shall also prohibit accidental opening of the fuse carrier due to
vibrations or impact.
5.2.3
5.2.4
Page: 5 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
to the fuse link. It shall make a firm contact with the button head of the fuse
link and shall provide a protective enclosure to the fuse link to check the
spreading of the arc during fault interruptions.
The fuse carrier shall be provided with a cast bronze opening eye (pull ring)
suitable for operation with a hook stick from the ground level to pull-out or closein the fuse carrier by manual operation.
5.2.5
5.2.6
5.2.7
FUSE TUBE
The fuse tube shall be made of moulded fibre glass reinforced polyester
coated with ultraviolet inhibitor on the outer surface and having arc quenching
bone fibre liner inside. The tube shall have high bursting strength to sustain
high pressure of the gases during fault interruption. During switching operation
circuit interruption shall be accomplished entirely within the interrupter without
Page: 6 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
external arc or flame. As the blade begins to open, the current shall be
transferred to the interrupter by a shunt contact against the interrupters
external contact before the current carrying main contacts part, followed by the
arc extinction in the interrupter. During closing, the sequence shall be reversed.
The fuse tube cap may be of the expendable type.
The inside diameter of the fuse tube shall be 17.5mm. The solid cap of the fuse
carrier shall clamp the button head of the fuse link, closing the top end of the
fuse tube and allowing only the downward venting during fault interruption.
The assembly shall be designed such that the fuse tube can be closed without
using much undue care even when the closing force is applied from an angle. A
lifting eye shall be provided on the fuse tube and designed for use with a hookstick. The fuse tube shall be permanently marked with the following:
Supplier/Manufacturer, model, maximum continuous current rating, rated
maximum voltage phase to phase, rated symmetrical amperes as per IEC
requirements.
5.2.8
MOUNTING ARRANGEMENT
The cut outs shall be provided with a suitable arrangement for mounting these
on suitable channel cross arm in such a way that the centre line of the fuse base
is at an angle of 15o to 20o from the vertical and shall provide the necessary
clearances from the support. Mounting arrangement shall be made of high
strength galvanised steel flat and shall be robust enough to sustain the various
stresses encountered during all operating conditions of the cut out.
The strength of the component shall be determined by clamping the member
with the shorter leg at the top to a rigid support by M-10 carriage bolts. A
downward force shall be applied along the axis of M-14 carriage bolt parallel to
the longer leg and in the direction of the longer leg of the member under test. A
load of 50 Kg. shall be applied and then removed to take up any slack in the
mounting arrangement before the measurement of the position is taken. The
permanent set measured at the axis of the M-14 carriage bolt shall not exceed
1.6mm when a load of 425 Kg. is applied and removed.
The strength of the M-14 bolt shall in no case be less than1900 Kg. and the
strength of M-10 bolts not less than 3500 Kg.
5.2.9
TERMINAL CONNECTIONS
The cut out shall be provided with two aluminium alloy terminal connectors at
top and bottom of fuse base assemblies to receive aluminium conductors of
diameters between 6.3mm to 10.05mm. These terminals shall be easily accessible
irrespective of the cut out location with respect to the pole. The terminals shall
meet the test requirements of relevant construction standard..
5.2.10
Earthing
The metal structure shall have a provision for earthing. Earthing terminals shall be
suitable for accepting copper conductors of the diameter of 6 to 11 mm. The
terminals shall be made of copper and shall be tin-plated. All metal parts not
meant to carry current shall be connected to a double earthing system and suitable
earthing terminals shall be provided with all the equipment.
Page: 7 , 4-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-01
EEPCO
Operating Gear
a)
Each unit must be provided with the necessary operating gear to allow the load
isolator disconnector to be operated from the ground the operating handle being
mounted about 1.25 metres above the ground,
b)
The operating handle shall be arranged to take a standard padlock with 6mm
hasp,
c)
d)
A suitable insulating insert shall be fitted in the operating link to safeguard any
person operating the disconnector,
e)
The insulating medium to be used shall be stated by the Supplier in the attached
schedule,
f)
The length of the operating link shall allow its use on poles which have a
maximum over-ground height of 11 meters.
5.2.12
5.2.13
Connections
a)
The terminals on the load isolator units for connection of the line conductors
shall be such that the danger of connections working loose due to vibration is
minimised,
b)
c)
The terminals shall be suitable for accepting both aluminium and copper
conductors without the risk of corrosion. The conductor tightening bolts shall
consist of silicon bronze,
d)
5.2.14
5.3
FINISH
All iron and steel parts shall be protected against corrosion by hot dip galvanising
to BS EN ISO 1461 or equivalent.
Page: 8 , 4-Apr-13
SECTION 6- PACKING
SPECIFICATION TS-SG-01
EEPCO
6.
PACKING
The drop out fuses shall be packed securely. Please see also TS-GN-02.
7.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
7.1
Page: 9 , 4-Apr-13
SECTION 7- SCHEDULES
SPECIFICATION TS-SG-01
EEPCO
7.2
SECTION 7- SCHEDULES
SPECIFICATION TS-SG-01
EEPCO
7.3
LPA-GECE
EEPCo
Technical Schedule for Pole mounted MV Drop out Fuses (15 and 33kV)
Please complete schedule as required
No
Item
Unit
Requirement Bid Offer Requirement Bid Offer
Nominal System Voltage
1
Name of manufacturer
Country of manufacture
Type
Type tested
5
6
Standards
Rated operating Line Voltage
7
8
15kV
Pole Mounted
33kV
Pole Mounted
Yes
Yes
kV
IEC/ VDE
15
IEC/ VDE
33
kV
24
36
kVp
125
250
9.1
(1
min.,
phase
to wet)
earth
kV
50
95
9.2
kV
76
80
10
kVp
kV
kV
75
95
170
195
11
Rated frequency
Hz
50
50
12
Rated current
100
100
13
kA
12
16
14
mm
480
1040
15
single phase
drop out fuse
single phase
drop out fuse
10.1
10.2
16
Page 1
Date: 04/04/2013,
EEPCO
SPECIFICATION
TS-SG-02
MV Surge Arrestors
SPECIFICATION TS-SG-02
EEPCO
Date
Brief Description
Rev 0
12 Dec 2012
Rev 1
Feb 2013
Rev 2
Mar 2013
Page: 1 , 10-Mar-13
SPECIFICATION TS-SG-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
MV SURGE ARRESTORS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TEST
ACCEPTANCE TEST
2
3
3
5.
DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
5.13
5.14
5.15
GENERAL
BASIC CHARACTERISTICS OF SURGE ARRESTERS
USE 4
INTERFACIAL SEALING
TERMINALS
MOUNTING ARRANGEMENTS
PROOF AGAINST MOISTURE
DROP OUT FEATURE
OVER PRESSURE RELIEF
WEIGHT
CREEPAGE DISTANCE TO EARTH.
GALVANIZING
POLLUTION PERFORMANCE
MARKING
PACKING MARKING AND DELIVERY
3
4
6.
7.
6
7
7.1
7.2
7.3
7
7
8
5
5
5
5
5
5
5
6
6
6
6
6
Page: 2 , 10-Mar-13
SECTION 1 - SCOPE
SPECIFICATION TS-SG-02
EEPCO
MV SURGE ARRESTORS
1.
SCOPE
This specification covers the design, testing and performance requirements for
gapless metal oxide surge arresters (SA) for outdoor use, in the clients system
nominal voltages of 15kV and 33 kV.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. The following IEC
publications or other national or international standards, which ensure equal or
higher quality, shall be applicable
Standard
Title
IEC
IEC-60071-1
IEC-60071-2
IEC 60099-4
IEC 60099-5
IEC TC 37
IEEE C62.1
NEMA LA1
Surge Arresters
BS EN ISO 1461
Page: 1 , 10-Mar-13
SPECIFICATION TS-SG-02
EEPCO
3.1
CONFLICT:
International Standard IEC 60099-4: Surge arresters - Part 4 Metal-oxide surge
arresters without gaps for a.c. systems shall apply except where modified by this
Technical Specification.
Also See spec. TS-GN-01 General System Data
4.
4.1
TYPE TESTS
Type tests shall be carried out in accordance with the practices and tolerances of
IEC 60099, with the exception of the High Current Impulse Withstand Test.
Before proceeding with the high current impulse withstand test, the dry power
frequency spark over voltage and peak residual voltage at rated current shall be
measured according to the relevant clauses of IEC 60099. After the high current
impulse withstand test, which shall then be carried out in accordance with IEC
60099, these measurements shall be repeated. The test specimens shall be judged
by their physical conditions and by comparison of the oscillograms taken during
the residual voltage tests.
The dry power frequency spark over voltage shall not have changed by more than
10% and the residual voltage shall not have changed by more than 20%.
The following tests shall be conducted.
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
Operating-duty test
(ix)
Pressure-relief tests
(x)
(xi)
(xii)
(xiii)
(xiv)
(xv)
Sealing test
To prove the effectiveness of sealing of the surge arresters, either of the following
two tests shall be carried out:
Page: 2 , 10-Mar-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-02
EEPCO
1) Bubble Test
A positive pressure shall be created inside the arrester and it shall be immersed in
water to check if there are any bubbles.
2) Pressure/Vacuum Test
Leakage shall be checked by measuring leak rate either by monitoring drop in
pressure or rise in vacuum level with time or by
4.2
ROUTINE TEST
a)
b)
c)
d)
e)
f)
g)
4.3
ACCEPTANCE TEST
The Acceptance test procedure for any delivery of equipment are as follows:
(i)
(ii)
Standard lightning - voltage impulse spark over test on the complete arrester
(iii)
Residual voltage test at the nominal discharge current on the complete arrester or
sections
(iv)
(v)
(vi)
5.
DESIGN
5.1
GENERAL
The surge arresters shall be of the zinc oxide (ZnO) type without spark gaps. The
surge arresters shall be delivered complete with NEMA pattern mounting
brackets for mounting on steel cross arm and bearers. The surge arresters shall
conform to IEC 60099-4 where applicable together with draft IEC TC 37 WG4
suitable for given service conditions.
The surge arresters shall meet the following Performance Characteristics
requirements:
Any weather-exposed steel parts shall be hot-dip galvanized.
Page: 3 , 10-Mar-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-02
EEPCO
5.2
15kV
33kV
18 kV
36kV
14.4kV
28.8kV
10kA peak
10kA peak
Rated frequency
50 Hz
50 Hz
480 mm
1040 mm
Short-circuit capability
10 kA
10 kA
59 kV
108kV
53
97
<1.5
<1.5
<1.5
<1.5
108kV peak
5.3
USE
The arresters will used to protect:
Page: 4 , 10-Mar-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-02
EEPCO
5.4
5.5
TERMINALS
Live conductor terminals of SAs covered by this specification shall accept copper
or aluminium conductors without danger of corrosion. To this end, the arrester
terminal shall be cadmium plated or some other alternatives acceptable to the
Purchaser.
Terminals shall be suitable for use with the following ranges of conductor sizes:
Copper conductor- 35 to 70 mm2
Aluminium conductor - 50 to 200 mm2
The earthing terminal shall be suitable for stranded earth lead conductor
galvanised/stainless-steel or aluminium 25-75 mm2.
5.6
MOUNTING ARRANGEMENTS
Arresters shall be suitable for horizontal, vertical or at an angle mounting. The
arresters shall be connected between phase and earth.
Distance between the arresters and the protected transformer shall not be more
than 2.5 m.
Mounting brackets shall be provided and supplied with each surge arrester
packaging to facilitate mounting of arresters on channel and angle iron crossarms.
5.7
5.8
5.9
WEIGHT
The Bidder shall state the net weight of the arrester(s) offered.
Page: 5 , 10-Mar-13
SPECIFICATION TS-SG-02
EEPCO
5.10
a)
b)
5.11
GALVANIZING
All exposed ferrous components, unless of stainless steel, shall be hot dip
galvanized in accordance with BS EN ISO 1461.
5.12
POLLUTION PERFORMANCE
The required creepage for housings is classified as medium pollution level with
specific creepage of 20 mm/kV (Um) at sea level.
5.13
MARKING
Each arrester shall be provided with a nameplate, according to IEC 60099-4
5.14
6.
Page: 6 , 10-Mar-13
SECTION 7 - SCHEDULES
SPECIFICATION TS-SG-02
EEPCO
7.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
7.1
7.2
Page: 7 , 10-Mar-13
SECTION 7 - SCHEDULES
SPECIFICATION TS-SG-02
EEPCO
7.3
Page: 8 , 10-Mar-13
LPA-GECE
EEPCo
No
Item
System nominal voltage
Unit
Requirement
kV
15
Bid Offer
Requirement
Bid Offer
33
Manufacturer
Country of origin
Applicable Standards
kV
18
IEC 60099-4,
IEC 60099-5
IEC TC 37
WG4,
36
kV
14.4
28.8
kA
10
10
Discharge class
kV
53
97
Hz
50
50
10
mA
<1.5
<1.5
11
mA
<1.5
<1.5
kV
59
108
53
Suitable for
Alloy of copper
and aluminum
105
97
Suitable for
Alloy of copper
and aluminum
25-100
25-100
Galvanized,
stainless steel
No
No
Galvanized,
stainless steel
No
No
See TS-GN-01
See TS-GN-01
See TS-GN-01
See TS-GN-01
See TS-GN-01
See TS-GN-01
See TS-GN-01
See TS-GN-01
12
IEC 60099-4,
IEC 60099-5 IEC
TC 37 WG4,
kV
Maximum residual voltages at switching
13.1 impulse
at 0.5 kA
kV
13.2
kV
13
at 1.0 kA
14
16
17
18
19
20
23
24
25
26
Altitude range, m
Lightning impulse protection level
Creepage distance of bushing, mm
21
22
kV
kV
mm2
Yes/No
C
M
kV(peak)
Date: 10/3/2013,10:54
EEPCO
SPECIFICATION
TS-SG-03
SPECIFICATION
EEPCO
Date
Brief Description
Rev 0
Jan 2013
First Issue
Rev 1
Feb 2013
Rev 2
25 April 2013
Page: i , 27-Apr-13
SPECIFICATION
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED DISTRIBUTION BOX MCCBS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
4.4
4.5
4.6
4.7
TYPE TESTS
1
ON COMPLETE LV DISTRIBUTION BOX
1
MCCB
2
ROUTINE TESTS
2
ACCEPTANCE TESTS
2
TESTING & MANUFACTURING FACILITIES:
2
CTL(COMMITTEE OF TESTING LABORATORIES) TESTING OF MCCBERROR! BOO
5.
BOX DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
GENERAL
BUSBARS AND CONNECTIONS
NEUTRAL BAR
EARTH BAR
DISTRIBUTION BOX CONSTRUCTION
CABLE TERMINATIONS
3
3
3
3
3
5
6.
MCCBS
6.1
GENERAL
7.
8.
9.
7
7
8
9
9.1
9.2
Page: ii , 27-Apr-13
SECTION 1 - SCOPE
SPECIFICATION
EEPCO
SCOPE
This specification covers the design, manufacturing, testing, supply of pole
mounted Distribution Box with MCCBs to be employed with distribution
transformer substations.
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
Specification/ Standard
Number
Title
IEC 60144
BS 5486 part-12
IEC 60408
Lowvoltageairbreakswitches,airbreak
disconnectorsandfusecombinationunits
DIN 43620
IEC 61439
CONFLICT:
See spec TS-GN-02
4.
4.1
TYPE TESTS
Type tests shall be carried out on Distribution boxes being offered, in accordance
with the relevant IEC/ BS standard.
4.2
(ii)
(iii)
Page: 1 , 27-Apr-13
SPECIFICATION
EEPCO
(iv)
(v)
4.3
MCCB
All type tests on MCCB as per IEC/BS
4.4
ROUTINE TESTS
These tests shall be carried out per IEC at the manufactures works to ensure that
the product is in accordance with the design offered. The manufacturer shall
supply a certificate indicating the result of the entire test carried out on the
equipment.
4.5
ACCEPTANCE TESTS
The Acceptance test procedure for any delivery of the equipment are as follows:
(i)
Visual inspection
(ii)
(iii)
(iv)
4.6
4.7
(i)
(ii)
(iii)
(iv)
Welding machines,
(v)
Assembling tools.
SAMPLE TESTING
To ensure the quality of MCCB, routine & acceptance tests on MCCBs may be
carried out at the works of original manufacturer. Besides this, dimensional
checking on one No MCCB from each lot may be carried out by dismantling the
MCCB and compare the same with the internal drawing of type tested MCCB.
Page: 2 , 27-Apr-13
SPECIFICATION
EEPCO
5.
BOX DESIGN
5.1
GENERAL
The requirement is for a standard box design to accommodate
Types of circuits
Small
Large
630A
630A
Busbar rating
The MCCBs are connected between the bus bars in the Box and the outgoing
cables for distribution loads.
5.2
5.3
NEUTRAL BAR
The neutral bar shall be rated at the full rating of the phase bus bars. It shall be
insulated from the frame of the distribution box but a bolted link shall be
provided to connect it to the frame.
5.4
EARTH BAR
A copper earth bar shall be fitted near the bottom of the Distribution box. A
number of copper lugs shall be provided bolted to the earth ready to accept
outgoing cables. The earth bar shall be insulated from the frame but connected to
the neutral bar by a removable strap/bar.
5.5
5.5.1
General
The L.V. Distribution boxes shall be designed for installation on the D.P.
structure of the outdoor 15/0.4 KV Pole Mounted Distribution substation. These
Distribution Boxes shall be fabricated with 2 mm CR sheet steel.
Page: 3 , 27-Apr-13
SPECIFICATION
EEPCO
The body of the boxes shall have sufficient reinforcement with suitable size of
channels keeping a provision for fixing these boxes on pole structure.
The roof of the box shall be slightly slanting both sides or to the back with an
overhang of 50mm all around.
The Distribution Box should be preferably of IP-54 protective category
There shall be provision for fluorescent lighting inside the cabinet which shall be
operated with a dedicated switch.
5.5.2
Cable entries
Cable entries shall be designed for ABC cables of sizes between 35, 50 and 95mm2
XLPE.
The bottom of the box shall have a 3.15 mm thick steel plate for securing the
outgoing/incoming cables. The plate shall be provided with knockout holes
suitable for cable sizes indicated. The bottom plate shall be provided with two air
vents with perforated M.S. sheet of 1.25mm thick welded from inside. Suitable
size of stainless steel cable glands should be provided for these holes.
A complete set of screw type compression cable glands shall be provided with
each box suitable for outdoor use with those cables specified in the schedules. The
glands shall not be PVC or plastic. Each gland shall be capable of carrying the
short circuit current rating of its associated cable and be provided with such
fittings necessary for fixing in tapped or untapped entry hole.
Alternatively 70mm pipe with smoothed edges of suitable size shall be welded
with each hole where the cable can enter and then sealed with a suitable hardening
compound to act as a gland. The compound can be a flexible bitumastic setting
compound.
5.5.3
Ventilation
Four sets of louvers shall be provided on the sides or doors to ensure that the
temperature inside the enclosure is not substantially different from that of the
atmosphere. The louvers shall be backed with perforated M.S. sheet of 1.25 mm
welded from inside the LV Distribution Box. The nuts, bolts, washers used in the
box shall be galvanized to avoid corrosion.
5.5.4
Finishing
All sheet metal works shall undergo the 7 tank chemical and mechanical cleaning
process before final paint. The entire box shall be duly acid treated.
Two coats of red oxide and two coats of final paints shall be applied. Colour of
outside/inside surface shall be mentioned in this specification. Electrostatic
painting with oven drying will also be acceptable.
M.S. parts such as Bolts& Nuts, washers etc. shall be electro galvanized for nonelectrical use.
5.5.5
Size of Box
The box shall be of standard design and size to take up to outgoing and incoming
circuits
Page: 4 , 27-Apr-13
SPECIFICATION
EEPCO
5.5.6
Earthing
The box shall have a solid earthing point and an earthing bar for the earthing of
the outgoing cables. Box earthing point shall be provided both on the inside and
the outside of the box, to allow earthing according to local requirements.
5.5.7
5.5.8
Miscellaneous
All joints for current carrying parts shall be made using non-magnetic stainless
steel bolts or brass, 2 nuts & spring washers. The nuts and bolts should be of
hexagonal type with groove for bolt.
Electrolytic grade copper bus bars are mounted on epoxy resin cast bus insulators
fixed on suitable fixing arrangement. The bus bars shall be conveniently placed so
as to provide adequate clearance from the body of the box conforming to the
relevant standard.
The distribution boxes shall be duly wired with suitable size of PVC insulated
copper /aluminum flat. Cable glands of sufficient size and cable cleats for support
of the cables shall be provided. The bus bars shall be fitted with lugs of suitable
size for receiving the incoming cables from the transformer. Proper arrangement
shall be made for connection between the bus bars and the MCCBs and outgoing
cables. Sufficient space shall be provided for bending and termination of the
cables. Access shall be provided for insertion of clip on meters for taking load
readings on the feeders.
Instruction leaflet in Amharic should be provided as sticker in the LV Distribution
Box.door from inside.
The Danger marking with fluorescent paint shall be provided on one door and a
danger plate shall be riveted on another door, on front side.
5.6
CABLE TERMINATIONS
Cable terminations shall be provided for the transformer incoming cables to the
Busbars as well as the outgoing circuits.
Page: 5 , 27-Apr-13
SECTION 6 - MCCBS
SPECIFICATION
EEPCO
6.
MCCBS
6.1
GENERAL
These MCCBs shall be conforming to IEC61439 or any other relevant standard.
6.1.1
Rated current
Min. 18kA
Sequence of operation
At 0.4 PF
0.4 (lag)
Trippingtime(T)
1.05In
2.5hrs.
1.2In
>10min.and<2hrs
1.3In
30min.
1.4In
10min.
2.5In
1min.
4.0In
Notlessthan2sec.
5.0In
<5sec
12In
Instantaneousi.e.<40ms
The Distribution Box shall have 3 Nos. of single pole MCCBs per circuit to
control and protect outgoing circuits. The MCCBs shall be manually operated type
and shall have quick make quick break mechanism.
Page: 6 , 27-Apr-13
SPECIFICATION
EEPCO
The Terminal Connector strips of the MCCB shall be projecting out of the MCCB
for minimum length of 40 mm on bus bar side and 60 mm on outgoing cable side
connected through lugs.
All nut bolts used for assembly and connections shall be of non-magnetic stainless
steel only.
The MCCBs shall be marked with Brand Name of manufacture and Ics in kA by
embossing only whereas other particulars may be marked as per the manufacturers
standard practice.
The contacts of MCCB should be self-wiping type so as to keep the contacts clean
and milli-volt drop low.
7.
8.
Page: 7 , 27-Apr-13
SPECIFICATION
EEPCO
9.
9.1
Page: 8 , 27-Apr-13
SPECIFICATION
EEPCO
9.2
Page: 9 , 27-Apr-13
LPA-GECE
EEPCo
No Item
Unit
Box Reference
4 way
6 way
Name of manufacturer
Country of manufacture
Type Designation
Standard
I
1
DISTRIBUTION BOX
Thickness of MS sheet on all sides
mm
mm
3.15
3.15
3
4
5
II
1
2
3
4
5
6
Protective category
Colour
Total weight of the Distributio Box
BUSBARS
Size of main busbars HxW
Rating of Busbar
Size of dropper links
Outgoing circuit ways
Size of Neutral busbars
Rating of Busbars
IP-43
Gray
IP-43
Gray
630 Minimum
630
0.4
1000
0.4
1000
IEC 61439
kg
mm
A
mm
No
mm
kV
V
LPA-GECE
No Item
3
4
5
6
7
8
9
10
11
EEPCo
Unit
kA
kA
kA
kA
kV
kA
mm2
mm
mm
mm
mm
kN
400
1.2
1.2
20
10
3
8
IP23
Up to 300
400
1.2
1.2
20
10
3
8
IP23
Up to 300
Up to 2x90
Up to 2x90
92
80
92
80
As per IEC
60947
80
As per IEC
60947
80
LPA-GECE
EEPCo
No
Item
MCCB current rating reference
Name of manufacturer
Country of manufacture
Type Designation
Standard
No. of poles
4
5
Unit
A
IEC 61439
kV
0.23
0.23
0.23
0.23
0.23
0.23
63
100
125
160
200
300
90%
90%
90%
90%
90%
90%
kA
>18
>18
>18
>18
>18
>18
kA
10
10
10
10
10
10
7
8
9
10
11
12
13
IV
1
2
3
4
hrs.
min.
sec
sec
millisec
kV
kA
2.5
1
2
<5
<40
3
8
2.5
1
2
<5
<40
3
8
2.5
1
2
<5
<40
3
8
2.5
1
2
<5
<40
3
8
2.5
1
2
<5
<40
3
8
2.5
1
2
<5
<40
3
8
mm
mm
mm
kg
EEPCO
SPECIFICATION
TS-SG-04
SPECIFICATION
EEPCO
Date
Brief Description
Rev 0
Jan 2013
First Issue
Rev 1
Feb 2013
Rev 2
April 2013
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: i , 27-Apr-13
SPECIFICATION
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED DISTRIBUTION BOX WITH FUSE CUT OUT
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
4.4
4.5
TYPE TESTS
ON COMPLETE LV DISTRIBUTION BOX
ROUTINE TESTS
ACCEPTANCE TESTS
TESTING & MANUFACTURING FACILITIES:
1
1
2
2
2
5.
BOX DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
GENERAL
BUSBARS AND CONNECTIONS
NEUTRAL BAR
EARTH BAR
DISTRIBUTION BOX CONSTRUCTION
CABLE TERMINATIONS
3
3
3
3
3
5
6.
6.1
6.2
6.3
6
6
6
7.
8.
9.
7
8
9.1
9.2
8
10
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: ii , 27-Apr-13
SPECIFICATION
EEPCO
SCOPE
This specification covers the design, manufacturing, testing, supply of Fuse cut out
with catridge fuse links in a pole mounted Distribution Box for use at Pole
mounted distribution transformer substations for LV lines .
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
Specification/ Standard
Number
Title
IEC 60144
IEC 60269-1
DIN 43620
BS 88
3.1
CONFLICT:
See spec TS-GN-02
4.
4.1
TYPE TESTS
Type tests shall be carried out on Distribution boxes being offered, in accordance
with the relevant IEC/ BS standard.
4.2
(ii)
(iii)
(iv)
(v)
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 1 , 27-Apr-13
SPECIFICATION
EEPCO
4.2.2
between live parts and exposed conductive parts with the fuse link and fuse
carrier in place.
(ii)
(iii)
This test shall be carried out in accordance with Clause 8.3 of BS 88,
(iv)
(v)
Test No. 1 on Table 8(a) in Clause 8.5 of BS 88, Part 6 shall be carried out on
complete assembly of fuse link and fuse cut out,
4.3
ROUTINE TESTS
These tests shall be carried out per IEC at the manufactures works to ensure that
the product is in accordance with the design offered. The manufacturer shall
supply a certificate indicating the result of the entire test carried out on the
equipment.
4.4
ACCEPTANCE TESTS
The Acceptance test procedure for any delivery of the equipments are as follows:
(i)
Visual inspection
(ii)
(iii)
(iv)
4.5
(ii)
(iii)
(iv)
Welding machines,
(v)
Assembling tools.
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 2 , 27-Apr-13
SPECIFICATION
EEPCO
5.
BOX DESIGN
5.1
GENERAL
The requirement is for a standard box design to accommodate
Types of circuits
Small
Large
630A
630A
Busbar rating
The fuse-links are connected between the bus bars in the Box and the outgoing
cables for distribution loads.
5.2
5.3
NEUTRAL BAR
The neutral bar shall be rated at the full rating of the phase bus bars. It shall be
insulated from the frame of the distribution box but a bolted link shall be
provided to connect it to the frame.
5.4
EARTH BAR
A copper earth bar shall be fitted near the bottom of the Distribution box. A
number of copper lugs shall be provided bolted to the earth ready to accept
outgoing cables. The earth bar shall be insulated from the frame but connected to
the neutral bar by a removable strap/bar.
5.5
5.5.1
General
The L.V. Distribution boxes shall be designed for installation on the D.P.
structure of the outdoor 15/0.4 KV Pole Mounted Distribution substation. These
Distribution Boxes shall be fabricated with 2 mm CR sheet steel.
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 3 , 27-Apr-13
SPECIFICATION
EEPCO
The body of the boxes shall have sufficient reinforcement with suitable size of
channels keeping a provision for fixing these boxes on pole structure.
The roof of the box shall be slightly slanting both sides or to the back with an
overhang of 50mm all around.
The Distribution Box should be preferably of IP-54 protective category
There shall be provision for fluorescent lighting inside the cabinet which shall be
operated with a dedicated switch.
5.5.2
Cable entries
Cable entries shall be designed for ABC cables of sizes between 35, 50 and 95mm2
XLPE.
The bottom of the box shall have a 3.15 mm thick steel plate for securing the
outgoing/incoming cables. The plate shall be provided with knockout holes
suitable for cable sizes indicated. The bottom plate shall be provided with two air
vents with perforated M.S. sheet of 1.25mm thick welded from inside. Suitable
size of stainless steel cable glands should be provided for these holes.
A complete set of screw type compression cable glands shall be provided with
each box suitable for outdoor use with those cables specified in the schedules. The
glands shall not be PVC or plastic. Each gland shall be capable of carrying the
short circuit current rating of its associated cable and be provided with such
fittings necessary for fixing in tapped or untapped entry hole.
Alternatively 70mm pipe with smoothed edges of suitable size shall be welded
with each hole where the cable can enter and then sealed with a suitable hardening
compound to act as a gland. The compound can be a flexible bitumastic setting
compound.
5.5.3
Ventilation
Four sets of louvers shall be provided on the sides or doors to ensure that the
temperature inside the enclosure is not substantially different from that of the
atmosphere. The louvers shall be backed with perforated M.S. sheet of 1.25 mm
welded from inside the LV Distribution Box. The nuts, bolts, washers used in the
box shall be galvanized to avoid corrosion.
5.5.4
Finishing
All sheet metal works shall undergo the 7 tank chemical and mechanical cleaning
process before final paint. The entire box shall be duly acid treated.
Two coats of red oxide and two coats of final paints shall be applied. Colour of
outside/inside surface shall be mentioned in this specification. Electrostatic
painting with oven drying will also be acceptable.
M.S. parts such as Bolts& Nuts, washers etc. shall be electro galvanized for nonelectrical use.
5.5.5
Size of Box
The box shall be of standard design and size to take up to outgoing and incoming
circuits
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 4 , 27-Apr-13
SPECIFICATION
EEPCO
5.5.6
Earthing
The box shall have a solid earthing point and an earthing bar for the earthing of
the outgoing cables. Box earthing point shall be provided both on the inside and
the outside of the box, to allow earthing according to local requirements.
5.5.7
5.5.8
Miscellaneous
All joints for current carrying parts shall be made using non-magnetic stainless
steel bolts or brass, 2 nuts & spring washers. The nuts and bolts should be of
hexagonal type with groove for bolt.
Electrolytic grade copper bus bars are mounted on epoxy resin cast bus insulators
fixed on suitable fixing arrangement. The bus bars shall be conveniently placed so
as to provide adequate clearance from the body of the box conforming to the
relevant standard.
The distribution boxes shall be duly wired with suitable size of PVC insulated
copper /aluminum flat. Cable glands of sufficient size and cable cleats for support
of the cables shall be provided. The bus bars shall be fitted with lugs of suitable
size for receiving the incoming cables from the transformer. Proper arrangement
shall be made for connection between the bus bars and the MCCBs and outgoing
cables. Sufficient space shall be provided for bending and termination of the
cables. Access shall be provided for insertion of clip on meters for taking load
readings on the feeders.
Instruction leaflet in Amharic should be provided as sticker in the LV Distribution
Box.door from inside.
The Danger marking with fluorescent paint shall be provided on one door and a
danger plate shall be riveted on another door, on front side.
5.6
CABLE TERMINATIONS
Cable terminations shall be provided for the transformer incoming cables to the
Busbars as well as the outgoing circuits.
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 5 , 27-Apr-13
SPECIFICATION
EEPCO
6.
6.1
6.2
400A
230/400V
400A
400A
50Hz
5kV
IP23
6.3
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 6 , 27-Apr-13
SPECIFICATION
EEPCO
and end tags attached to the outside of the end caps and electrically connected to
the element. The fuse-links shall meet the requirements of IEC 269-1. The rated
current of the fuse link shall be carried continuously without deterioration and
shall be marked on it.
The fuse link shall be suitable for use with the fuse cut out described above.The
maximum value of power dissipation shall be in accordance with BS 88, Part 5.
The rated breaking capacity of the fuse link shall be 46kA as per BS 88, Part 5.
The pre-arcing characteristic for each fuse rating offered (to comply with BS 88)
and the operating time-current characteristic for each fuse rating offered shall be
provided.
All plastic parts shall be weather-resistant. All ferrous parts shall be protected by
hot dip galvanizing.
Fuse links once inserted into position the contacts shall be tightened with
insulated screw holders to ensure good contact.
Fuse link shall have a means to indicate whether the fuse has operated or not. The
fuse-links shall meet the following electrical characteristics:
1) Rated voltage of network 230/400 V,
2) Rated frequency 50 Hz,
3) Rupturing capacity 46 kA,
Current ratings of the fuse cut out sets required are given in the schedule of
prices.
The fuse links shall be designed to be removed safely from the fuse base without
any special tools while the circuit is alive.
The fuse links shall be designed to be inserted onto a faulty circuit safely from the
fuse base without any special tools while the circuit is alive. Under no
circumstances the insertion of the fuse link onto a faulty circuit shall endanger the
operator.
7.
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 7 , 27-Apr-13
SPECIFICATION
EEPCO
8.
9.
9.1
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 8 , 27-Apr-13
SPECIFICATION
EEPCO
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 9 , 27-Apr-13
SPECIFICATION
EEPCO
9.2
TS-SG-04 R2 Pole mounted Distn. box with fuse cut out 2013-04-28.docx
Rev -2- April 2013
Page: 10 , 27-Apr-13
LPA-GECE
EEPCo
Unit
Box Reference
Requirement
Bid Offer
Requirement
4 way
6 way
Name of manufacturer
Country of manufacture
Type Designation
Standard
DISTRIBUTION BOX
mm
mm
3.15
3.15
Protective category
IP-43
IP-43
Colour
Gray
Gray
II
BUSBARS
Rating of Busbar
630 Minimum
630 Minimum
mm
No
mm
Rating of Busbars
Bid Offer
IEC
61439
kg
mm
A
File:TS-SG-04-S R2 Pole mounted Distn. box with fuse cut out 2013-04-28.xlsm - sheet:TS-SG-04-S1
LPA-GECE
EEPCo
Unit
Requirement
Bid Offer
Requirement
Bid Offer
Rated Voltage
Rated insulation voltage
0.4
1000
0.4
1000
400
400
kA
1.2
1.2
kA
1.2
1.2
kA
20
20
kA
10
10
kV
kA
8
IP23
Up to 300
8
IP23
Up to 300
mm2
mm
Up to 2x90
Up to 2x90
92
92
mm
80
80
mm
16 Mechanical endurance
kN
As per IEC
60947
80
As per IEC
60947
80
21
Net weight
kV
V
mm
kg
File:TS-SG-04-S R2 Pole mounted Distn. box with fuse cut out 2013-04-28.xlsm - sheet:TS-SG-04-S1
LPA-GECE
EEPCo
No
Item
1
2
3
Reference
Name of manufacturer
Country of manufacture
Type Designation
Rated Voltage
6
7
2
2
Pre-arcing joule integral, I t, A S
9
10
11
12
13
Recovery voltage
Size according to IEC 269-1
14
Material of contacts
15
16
Net weight
Standard package
Unit
A
Require
ment
63
Bid Offer
Require
ment
100
Bid Offer
Require
ment
160
Bid Offer
Require
ment
200
Yes
Yes
Yes
Yes
kV
0.4
0.4
0.4
0.4
A
kA
63
120
100
120
160
120
200
120
A
A
1.6xIn
1.25xIn
1.6xIn
1.25xIn
1.6xIn
1.25xIn
1.6xIn
1.25xIn
780
II
Copper
with
silver
surface
780
II
Copper
with
silver
surface
780
II
Copper
with
silver
surface
780
II
Copper
with
silver
surface
Bid Offer
kg
Pcs.
File:TS-SG-04-S R2 Pole mounted Distn. box with fuse cut out 2013-04-28.xlsm - sheet:TS-SG-04-S2
LPA-GECE
EEPCo
No
Item
1
2
3
Reference
Name of manufacturer
Country of manufacture
Type Designation
Rated Voltage
6
7
9
10
11
12
13
14
Material of contacts
15
16
Net weight
Standard package
Unit
A
Require
ment
250
Bid offer
Require
ment
300
Bid offer
Require
ment
350
Bid offer
Require
ment
400
Yes
Yes
Yes
Yes
kV
0.4
0.4
0.4
0.4
A
kA
250
120
300
120
350
120
400
120
A
A
V
1.6xIn
1.25xIn
780
II
Copper
with
silver
surface
1.6xIn
1.25xIn
780
II
Copper
with
silver
surface
1.6xIn
1.25xIn
780
II
Copper
with
silver
surface
1.6xIn
1.25xIn
780
II
Copper
with
silver
surface
Bid offer
kg
Pcs.
File:TS-SG-04-S R2 Pole mounted Distn. box with fuse cut out 2013-04-28.xlsm - sheet:TS-SG-04-S3
EEPCO
SPECIFICATION
TS-SG-06
15kV Pole Mounted Load Break Switch
SPECIFICATION TS-SG-06
EEPCO
Date
Brief Description
Rev 0
Jan 2013
First Issue
Rev 1
Feb2013
Rev 2
Mar 2013
Rev 3
23 May 2013
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 1 , 30-May-13
SPECIFICATION TS-SG-06
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
15KV POLE MOUNTED LOAD BREAK SWITCH
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
1
2
2
5.
DESIGN
5.1
5.2
5.3
5.4
GENERAL
CONSTRUCTION
MATERIALS
MOUNTING
2
3
3
4
6.
7.
8.
MARKINGS
PACKING
SCHEDULES
4
4
4
8.1
8.2
8.3
4
1
2
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 2 , 30-May-13
SPECIFICATION TS-SG-06
EEPCO
SCOPE
This specification covers the design, manufacturing, testing, supply, delivery and
performance characteristics of Out door 15kV Pole mounted Load Break Switch for
manual operation.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
Specification/Standard
Number
Title
IEC 60120
IEC 60129
IEC 60265
IEC 60471
BS 3288
CONFLICT
See spec TS-GN-01
4.
4.1
TYPE TESTS
The following type tests as per the relevant standard shall be conducted on the equipment
of identical design to prove that the offered equipment satisfies all the design
requirements set out in this specification
The supplier shall confirm on the attached schedule that the following tests have been
performed according to the relevant IEC
(i)
Dielectric test (Impulse and one minute wet power frequency withstand voltages)
(ii)
(iii)
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 1 , 30-May-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-06
EEPCO
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
Mechanical Endurance
(x)
Electrical Endurance
4.2
ROUTINE TESTS
Routine tests shall be carried out on the Equipment in accordance with the relevant The
following tests shall be conducted.
(i)
(ii)
(iii)
Operating test
4.3
ACCEPTANCE TESTS
(i)
(ii)
Checking of the result of the routine and type test as per IEC
(iii)
(iv)
5.
DESIGN
5.1
GENERAL
5.1.1
15kV
Rated current
400A
125kV
135kV
50kV
60kV
65 C
ii)Terminals
50 C
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 2 , 30-May-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-06
EEPCO
5.2
400A
20A
20kA peak
Mechanical endurance
1000 Operations
Electrical endurance
CONSTRUCTION
The switch shall be suitable for single pole mounting on concrete pole 9m or 12m length.
The load break switch shall be manually-operated triple-pole type with either singlebreak or double-break operation. The operation of the switch shall be through rotating
motion of the post insulators. All phases must open and close simultaneously.
The switch shall be fitted with a special interrupter unit to absorb the arc energy in an
insulated chamber. The interrupter unit shall be easily replaceable.
The contacts shall be made of silver-faced bronze/copper.
The speed of breaking of load shall be independent of the speed of operation.
The incoming and outgoing terminals shall be such as to directly receive AAAC
200sq.mm without the use of lugs. The terminals shall be suitable for current ratings
stipulated above. The terminals shall be so designed as to avoid bimetallic corrosion.
The frame of each of switch shall be provided with a separate earthing terminal/for
each phase for connection to an earthing conductor having a clamping bolt of not less
than 16mm dia. The terminal shall be marked with Earth symbol.
The vertical operating rod shall comprise of not less than 40mm (nominal bore)
Galvanised Steel tube (medium class) The length of the operating rod shall be 9m.
Provision shall be made for earthing of the operating handle.
Pipes shall be galvanised in compliance with the relevant standard and other metal parts
shall be hot dip galvanised.
Phase clearance i.e. centre-to-centre distance between the insulators of adjacent phase in
the assembled position of the switch shall not be less than 1200mm.
The centre-to-centre distance between insulators of the adjacent poles of the same phase
in the assembled position of the switch shall not be less than 600mm.
All similar materials and removable parts of similar equipment shall be interchangeable
with each other.
5.3
MATERIALS
The insulator material shall be porcelain or toughened or annealed glass or cast resin. The
terminal shall be compatible and ready connecting with aluminium conductor.
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 3 , 30-May-13
SPECIFICATION TS-SG-06
EEPCO
5.4
6.
SECTION 6 - MARKINGS
MOUNTING
(i)
The load break switch shall be suitable for mounting on single concrete pole and shall be
ready for mounting and operation. It shall be complete with all necessary items such as:
(ii)
Operating rod and handle for manual control with necessary fixing accessories and
padlock. The switch shall have pad lock arrangement both for ON and OFF positions
from the ground level..
(iii)
Cross arm where insulators strings with clevises can be fixed. Clevises are according to
IEC 471 or BS 3288 for ball eye of standard coupling size according IEC 120 and BS
3288 with minimum failing load 40KN.
(iv)
(v)
Clamps for connecting all aluminium conductors of AAAC 200 mm2 both for incoming
and outgoing side.
(vi)
(vii)
The length of the load break switch cross arm shall be preferably 1900mm. However,
alternatives may be quoted. The switch disconnected cross arm shall be suitable for
installing tension insulator strings of cap and pin type. The load break switch shall be
supplied with complete accessories and structures to mount on a single concrete/steel
pole. The purchaser should not use additional material to mount the load break switch on
a single pole.
MARKINGS
The load break switch shall be marked according to requirements of IEC 60265.
7.
PACKING
The Drop out Fuses shall be packed securely ..Please see also TS-GN-02
8.
SCHEDULES
If the technical schedules are to be included in the same file then use this section.
8.1
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 4 , 30-May-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-06
EEPCO
8.2
Specification
Clause
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 1 , 30-May-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-06
EEPCO
8.3
Specification
Clause
TS-SG-06 R3 15kV Pole mounted Load break switch.docx Rev -3- May 2013
Page: 2 , 30-May-13
LPA-GECE
EEPCo
Item
1
2
3
4
5
6
Name of manufacturer
Country of origin
Type
Type tested
Standards
Rated voltage
yes/no
kV
15
kV
24
kVp
125
kVp
135
10
kV
50
11
kV
60
12
Rated frequency
Hz
50
13
13a
14
A
A
kA
400
400
20
15
10
16
Creepage distance
mm
480
17
17.1
17.2
17.3
18
19
20
21
22
m
Yes/No
kg
N
mm
23
24
25
26
27
28
29
30
31
32
Unit
Requirement
Bid Offer
Yes
mm
mm2
mm2
200
200
Copper
Silver plated
porcelain
microns
N
mm
mm
Page 1
Date: 30/5/2013,
EEPCO
SPECIFICATION
TS-SG-07
Pole mounted 15kV Air Break Switch
SPECIFICATION TS-SG-07
EEPCO
Date
Brief Description
Rev 0
12 Dec 2012
Rev 1
Feb2013
Rev 2
April 2013
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: i , 11-Apr-13
SPECIFICATION TS-SG-07
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED 15KV AIR BREAK SWITCH
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS& SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
1
2
2
5.
DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
5.7
GENERAL
CONSTRUCTION
MOUNTING
MECHANICAL STRENGTH
SWITCH TERMINALS
LOCKING ARRANGEMENTS
POST INSULATORS
2
3
3
4
5
5
5
6.
7.
8.
MARKINGS
PACKING
SCHEDULES
5
5
6
8.1
8.2
8.3
6
6
7
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: ii , 11-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-SG-07
EEPCO
SCOPE
This specification covers the design, manufacturing, testing, supply, delivery and
performance characteristics of outdoor 15kV ground operated, Pole mounted Air
Break Switch for manual.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
Specification/Standard
Number
Title
IEC 60129
IEC 60265
IEC60168
IEC 60273
IEC 61109
CONFLICT:
See spec TS-GN-02
4.
4.1
TYPE TESTS
The following type tests as per the relevant standard shall be conducted on the
equipment of identical design to prove that the offered equipment satisfies all the
design requirements set out in this specification
The supplier shall confirm on the attached schedule that the following tests have
been performed according to the relevant IEC
(i)
Dielectric test (Impulse and one minute wet power frequency withstand voltages),
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: 1 , 11-Apr-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-07
EEPCO
(ii)
(iii)
(iv)
(v)
(vi)
4.2
ROUTINE TESTS
Routine tests shall be carried out on the Equipment in accordance with the
relevant standard. The following tests shall be conducted.
(i)
(ii)
(iii)
Operating test
4.3
ACCEPTANCE TESTS
(i)
(ii)
Checking of the result of the routine and type tests as per IEC
(iii)
(iv)
5.
DESIGN
5.1
GENERAL
5.1.1
15kV
24kV
Rated current
400A
125kV
145kV
50kV
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
65 C
Page: 2 , 11-Apr-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-07
EEPCO
ii)Terminals
50 C
20A
5.2
CONSTRUCTION
5.2.1
General
The switch shall be suitable for pole mounting on concrete 9m or 12m length
with the top diameter ranging from 160mm to 190 mm.
The Air Break switch shall be triple-pole gang operated type with single-break
manual operation. All phases must open and close simultaneously.
The contacts shall be made of silver-faced bronze/copper.
The speed of breaking of load shall be independent of the speed of operation.
The terminals shall be suitable for current ratings stipulated in the Contract .The
terminals shall be so designed as to avoid bimetallic corrosion.
The frame of each of switch shall be provided with a separate earthing
terminal/for each phase for connection to an earthing conductor having a
clamping bolt of not less than 12mm dia. The terminal shall be marked with
Earth symbol.
The vertical operating pipe shall comprise not less than 25mm (nominal bore)
Galvanised Steel tube (medium class). The length of the operating pipe shall be
suitable and adjustable to suit for the installation. Guide brackets should be fixed
to the down pipe. 2 Nos. guide brackets should be fixed / welded to the down
pipe.
Provision shall be made for earthing of the operating handle.
Tubes shall be galvanised in compliance with the relevant standard and other
metal parts shall be hot dip galvanised.
All current carrying parts shall be made of nickel plated 99.9% electrolytic copper
and shall be provided with stainless steel bolts.
The arcing horns shall be made of stainless steel rod of 5 mm dia & phosphor
bronze sheet of 14 guage and shall have spring assisted for operation.The arcing
horns are positioned in such a way that they are separated after opening of the
main contacts and close before the main contacts are closed. The speed of
breaking of load current shall be independent of the speed of operation.
The spacing between the phases shall be adjustable between 600 mm to 760 mm
suitable for mounting on single pole structure.
5.3
MOUNTING
The phase assembly shall have suitable sheet steel folded in the form of a channel
with a plate dimension of thickness 4 mm for mounting two 24kV Solid core
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: 3 , 11-Apr-13
SPECIFICATION TS-SG-07
EEPCO
SECTION 5 - DESIGN
5.4
(i)
Clamps for connecting all aluminium conductors of AAAC from 50 to200 mm2
both for incoming and outgoing side.
(ii)
MECHANICAL STRENGTH
The isolating switches shall be capable ofr withstanding the rated mechanical
terminal loads and electro magnetic forces, without effecting the operation and
current carrying properties. The switches, complete with the operating mechanism
should not come out of their own in closed position due to the effect of gravity,
wind pressure, vibrations and reasonable shocks. Their construction should be
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: 4 , 11-Apr-13
SPECIFICATION TS-SG-07
EEPCO
SECTION 6 - MARKINGS
such that they do not open under the influence of the short circuit current.
5.5
SWITCH TERMINALS
The terminal pad shall be made of rolled/ extruded electrolytic grade copper flat
having a cross sectional area equal to that of the blade. It shall be so constructed
that an intimate contact with the contact element is ensured. The connector to the
switch terminal shall be suitable for 50 to 200mm AAAC conductor. The
Aluminium connectors of appropriate size shall be supplied for each end and for
each phase of the switch.
5.6
LOCKING ARRANGEMENTS
The AB (Air Break) switches shall be constructed with suitable arrangement to
provide pad-lock the operating handle on ON and OFF positions. A pad
lock of reputed make shall be provided.
The insulators for the isolating switches shall be of porcelain solid core type and
shall be in accordance with the relevant IEC.(Polymer type insulators conforming
to IEC61109 are also accepted). The assembly of the metal parts and
porcelain/polymer shall be in such a manner that the metal and
porcelain/polymer part shall not have any deteriorating effect or create undue
stresses adversely affecting the mechanical and electrical strength of the unit
arising out from any harmful expansion. The insulators (porcelain and polymer
type) shall be of standard make.
5.7
POST INSULATORS
The porcelain / polymer insulators shall be sound, free from defects, thoroughly
vitrified and smoothly glazed.
Unless otherwise specified, the glaze shall be brown in colour. The glazes shall
cover all the exposed porcelain parts of the insulators except those areas, which
serve, as supports during firing and required to be left un-glazed.
The threads of the tapped holes in the post insulator metal fittings shall be cut
after giving anti-corrosive protection and shall be protected against rust by
greasing other similar means.
The insulator material shall be porcelain or toughened or annealed glass or cast
resin. The terminal shall be compatible and ready connecting with aluminium
conductor.
6.
MARKINGS
The Air break switch shall be marked according to requirements of IEC 60265.
7.
PACKING
The Air break switch shall be packed securely .Please see also TS-GN-02
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: 5 , 11-Apr-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-07
EEPCO
8.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
8.1
8.2
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: 6 , 11-Apr-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-07
EEPCO
8.3
TS-SG-07 R2 Pole mounted 15kV Air Break Switch.docx Rev -2- April 2013
Page: 7 , 11-Apr-13
LPA-GECE
EEPCo
No
Item
Unit
Requirement
Bid Offer
15kV
1
Name of manufacturer
Country of origin
Type
4
5
Type tested
Standards
Rated voltage
22
125
10
60
11
Rated frequency
Hz
50
12
13
Rated current
Rated short circuit current
A
kA
400
10
16
Creepage distance
mm
480
17
18
19
20
21
Accessories included?
Weight of complete AB Switch
Min. clearances in air between poles
Yes/No
kg
mm
suitable length
for operator to
use it from
ground
22
mm
23
24
25
26
27
28
29
30
31
Material of terminals
Material of coating
Material of insulating parts
Thickness of zinc coating of steel
Maximum operating force
Length of cross-arm
Spacing between poles
8
9
Yes
yes/no
145
50
50-200
50-200
mm
mm
Copper
Silver plated
porcelain
microns
N
mm
mm
Page 1
Date: 11/4/2013,
EEPCO
SPECIFICATION
TS-SG-09
Pole Mounted MVAuto-reclosers
SPECIFICATION TS-SG-09
EEPCO
Date
Brief Description
Rev 0
Jan 2013
First Issue
Rev 1
Feb 2013
Rev 2
6 April 2013
Page: i , 11-Apr-13
SPECIFICATION TS-SG-09
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED MV AUTO-RECLOSERS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS& SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
TYPE TESTS
ROUTINE TESTS AND ACCEPTANCE TESTS
2
2
5.
DESIGN
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
PERFORMANCE CHARACTERISTICS
MODE OF OPERATION OF THE AUTOMATIC RECLOSERS
MANUAL OPERATION
TANK FABRICATION
INDICATORS
POLE MOUNTING BRACKET
LIFTING LUGS
GROUNDING TERMINAL
BUSHINGS AND TERMINALS
INTERRUPTING MEDIUM
RECLOSER CONTROL
COMMUNICATION SYSTEM
3
3
4
4
5
5
5
5
5
5
5
6
6.
7.
MARKING
SCHEDULES
6
8
7.1
7.2
7.3
8
8
9
Page: ii , 11-Apr-13
SECTION 1- SCOPE
SPECIFICATION TS-SG-09
EEPCO
SCOPE
This specification covers the design, manufacturing, testing, supply, delivery and
performance characteristics of pole mounted automatic re closers, both 15kV and
33kV.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
Specification/Standa Title
rd Number
3.1
IEC 60056
IEC 60137
IEC 60296
IEC 60376
IEC 60437
ISO 2063
CONFLICT:
See spec TS-GN-02
4.
LPA/GECE/Page: 1, 11-Apr-13
SPECIFICATION TS-SG-09
EEPCO
4.1
TYPE TESTS
The following type tests as per the relevant standard shall be conducted on the
equipment of identical design to prove that the offered equipment satisfies all the
design requirements set out in this specification
4.1.1
Auto-Recloser
a)
b)
c)
d)
e)
f)
g)
4.1.2
Current Transformers
a)
b)
c)
d)
e)
f)
g)
h)
Impulse voltage test for current transformers for service in electrically exposed
installations
4.2
4.2.1
Autoreclosers
a)
b)
c)
d)
e)
Calibration tests
4.2.2
a)
Current Transformers
Verification of terminal marking and polarity
LPA/GECE/Page: 2, 11-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-09
EEPCO
b)
c)
d)
e)
5.
DESIGN
5.1
PERFORMANCE CHARACTERISTICS
5.1.1
5.1.2
5.2
5.2.1
Setting-Currents
As a minimum, one over current device shall be provided for fault detection in
each phase. The over current device shall have adjustable minimum phase
trip-current settings at the values of:
Rating of
Autorecloser
15kV 400A
33kV 400A
The protective over current device shall have a adjustable inverse characteristics
LPA/GECE/Page: 3, 11-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-09
EEPCO
For series coil Autoreclosers the highest value of minimum trip current should be
equal to 140% of the continuous coil rating. These coils shall be protected by
fuses as well as phase over current an earth fault current trip facility shall be
provided.
The earth fault tripping levels shall be selectable between 50A and 400 Amps.
5.2.2
5.2.3
OPERATING DUTY
The minimum tested operating duty of the Autorecloser shall be as specified in
ANSI standard C37.60.
5.3
MANUAL OPERATION
Means shall be provided to permit manual tripping, closing and lockout of the
Autorecloser locally. These operations shall be done by hand or by operating
rods. The automatic Autorecloser shall be locked out after manual tripping and
shall reset after manual close.
5.3.1
Operation Counter
A mechanical operating counter shall be installed on the auto recloser which can
be read by a person standing at ground level. The counter shall be protected
against moisture ingress.
5.3.2
5.4
TANK FABRICATION
The tank shall be made of steel of minimum thickness 3mm and strong enough to
support dynamic short circuit forces and the vibration of the Autorecloser.
The tank and its accessories shall be adequately protected against corrosion and
the Contractor shall include a statement of the method of protection proposed.
Hot dip galvanising is preferred, where this is not practical the tanks shall be
shot-blasted and then immediately zinc sprayed to an average weight deposit of
not less than 550 g/m2 followed by a zinc chromate based primary paint, and two
coats of durable oil and weather resisting paint. Finish colour shall be grey.
The inside of tanks shall be coated with oil resisting varnish or paint so that the
oil cannot come into contact with the tank metal at any time.
The tank shall be perfectly sealed and dielectric fluid tight, with all fittings in
place. The head casting and the tank shall be weather-proof sealed under all
operating conditions.
LPA/GECE/Page: 4, 11-Apr-13
SECTION 5- DESIGN
SPECIFICATION TS-SG-09
EEPCO
5.5
INDICATORS
A contact position indicator (OFF -green, ON -red) shall be provided as well as a
"locked -out" indicator. These indicators shall be clearly visible from ground level.
5.6
5.7
LIFTING LUGS
Lifting lugs shall be provided such that the Autorecloser can be lifted with a single
hook without damage.
5.8
GROUNDING TERMINAL
All units shall be provided with a grounding terminal with a 10mm hole.
5.9
5.9.1
Bushings
The terminations shall be brought out through porcelain bushings. The bushings
used shall be rated for 24kV and 52kV respectively for 15kV and 33kV Auto
reclosers at MSL. They are rated to carry full line current and shall have in
addition spark gaps adjustable over the range 50-100mm.
Bushings shall be fitted with heavily tin plated terminals and galvanised hardware
to take tin plated aluminium compression lugs.
a)
Creepage Distance
The creepage distance of the bushings shall be 480mm and 1040mm for 15kV and
33kV, respectively.
b)
Bushing Labels
The bushings shall be clearly and unambiguously labelled. The labelling of the
phases shall be by raised lettering. Phase identification by adhesive stickers is not
acceptable.
5.10
INTERRUPTING MEDIUM
The current interrupting medium shall be vacuum breaker only.
5.11
RECLOSER CONTROL
The Autorecloser shall be fitted with a separate control box.
Protection relays for the IDMTL overcurrent and earth fault shall be installed in
this control box. This control box shall be suitable for fitting on the pole at a low
level than the Autorecloser to provide inspection maintenance and setting access
to utility personnel. All fittings required for mounting shall be supplied. All
operating parameters of the Autorecloser - minimum trip current, time - current
trip characteristics, reclosing and reset times, operating sequences - shall be
LPA/GECE/Page: 5, 11-Apr-13
SECTION 6- MARKING
SPECIFICATION TS-SG-09
EEPCO
controlled from the control box. All settings shall be either a) through a suitable
interface pad/keyboard designed for the harsh operating environment of the
Autorecloser, b) positive step selector switches or c) plug-in components. Ratings
shall be clearly marked in relevant units of measure with no interpretation
multipliers or conversion being required.
Each unit shall be equipped with an electronic control armoured capable of
operating in the environmental conditions specified in spec. No. TS-GN-01. The
cable shall be protected in either a metallic non rusting tube or a metallic cover
that can be fitted over the cable. The cable protection shall be securely fixed on
the pole and appropriate permanent fixings shall be provided. The fixings shall
not be plastic tie wraps. Stainless steel tie wraps are permitted.
5.12
COMMUNICATION SYSTEM
Remote control shall be provided for the Autorecloser if so specified in the
technical schedule. The remote control shall be achieved through a
communication link between control centre and the Autoreclosers and necessary
provision shall be incorporated in the control box.
GSM/GPRS/ CDMA service is available in 7 towns and is proposed to be
deployed for communication between Control Centre and this device.
Alternatively communication may be provided through a radio link with the
Control room.
The Unit shall incorporate the necessary remote terminal interface equipment to
enable linkage between the unit control and the communication system.
The Unit shall incorporate an energy storage system to enable the equipment to
operate within one month of being disconnected/ powered-off from the network.
Full details and rights to use protocols for communication and operation of the
device shall be provided to the client/purchaser to enable the SCADA system to
interface with the unit. The cost of the provision of any protocol look up tables
etc. shall be included in the cost of the device. Full details shall be included with
the supply of the device to enable the Unit to be integrated with the SCADA
system.
6.
MARKING
Each Autorecloser shall be fitted with an easily readable nameplate of weather
proof material giving the following details:
(i)
Type of Autorecloser
(ii)
Manufacturer's Name
(iii)
(iv)
Year of Manufacture
(v)
Rated Frequency
(vi)
Rated Voltage
(vii)
(viii)
LPA/GECE/Page: 6, 11-Apr-13
SECTION 6- MARKING
SPECIFICATION TS-SG-09
EEPCO
(ix)
(x)
(xi)
(xii)
(xiii)
(xiv)
Gross Weight
LPA/GECE/Page: 7, 11-Apr-13
SECTION 7- SCHEDULES
SPECIFICATION TS-SG-09
EEPCO
7.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
7.1
7.2
LPA/GECE/Page: 8, 11-Apr-13
SECTION 7- SCHEDULES
SPECIFICATION TS-SG-09
EEPCO
7.3
LPA/GECE/Page: 9, 11-Apr-13
LPA-GECE
EEPCo
Item
kV
15
33
kV
24
52
kVp
125
250
Sec.
1 to 60
1 to 60
Sec.
5,10,15, & 20
5,10,15, & 20
3
4
5
Unit
Requirement
Bid Offer
Requirement
400
400
20 to 400
20 to 400
10 to 400
10 to 400
kA(rms)
12.5
16
10
11
12
13
Value(rms)
Interrupting Rating max.Asymm.
Value(rms)
Interrupting Rating Max.
Maximum Making Current
Bid Offer
kA(rms)
A (peak)
kA (peak) 2 times of breaking
current
kV
2 times of
breaking current
14
15
kV
50
95
16
Creepage Distance
mm
480
1040
17
mm
50-100
50-100
Page 1
Date: 11/4/2013,
LPA-GECE
EEPCo
Item
18
Vacuum
Vacuum
19
Control Method
Electronic
Electronic
20
250
250
21
22
Yes
Radio
Yes
Radio
Unit
Requirement
Bid Offer
Requirement
Bid Offer
Page 2
Date: 11/4/2013,
EEPCO
SPECIFICATION
TS-SG-12
15kV SF6Extensible Ring Main Units
SECTION 1 - SCOPE
SPECIFICATION TS-SG-12
EEPCO
Date
Brief Description
Rev 0
Feb 2013
First Issue
Rev 1
Feb 2013
Rev 2
April 2013
Rev 3
30 April
RTU enhancements
Page: i , 30-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-SG-12
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
15KV SF6 RING MAIN UNITS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
4.4
4.5
TYPE TESTS
ROUTINE TESTS AND ACCEPTANCE TESTS
TESTS DURING MANUFACTURE
ADDITIONAL TESTS
TEST FACILITIES
1
2
2
2
2
5.
DESIGN
5.1
5.2
5.3
5.4
2
3
3
3
6.
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
CONSTRUCTIONAL FEATURES
LOAD BREAK SWITCH
CIRCUITBREAKER
INTERLOCKS
CABLES & CONNECTORS :
VOLTAGE INDICATORS
PROTECTION
EARTH FAULT LOCATORS
CTS
AUTOMATION FOR REMOTE CONTROL AND INDICATION
5
5
6
6
7
7
7
8
8
8
7.
7.1
7.2
7.3
RTUS
RADIO MODEM
CONTROL CENTRE
9
10
11
8.
SAFETY& TESTING
11
8.1
8.2
SAFETY
TESTING EQUIPMENT
11
11
9.
12
9.1
9.2
9.3
9.4
EARTHING
PAINTING
TROPICALISATION
INFORMATION LABELS
12
12
12
12
Page: ii , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
SECTION 1 - SCOPE
9.5
9.6
9.7
9.8
CLEARANCES
OPERATING HANDLE
CONTROL MECHANISMS
LIST OF DRAWINGS AND DOCUMENTS
13
13
13
13
10.
11.
13
13
11.1
11.2
11.3
11.4
11.5
SCOPE :
STANDARDS :
SYSTEM DETAILS :
POWER SUPPLY RATINGS :
TECHNICAL PARAMETERS :
13
13
14
14
14
12.
13.
PACKING
SCHEDULES
16
16
13.1
13.2
13.3
16
16
18
SECTION 1 - SCOPE
SPECIFICATION TS-SG-12
EEPCO
SCOPE
This Specification covers the design, manufacturing, testing, supply, delivery and
performance requirements of 15kV SF6 Extensible Ring Main Units for
Distribution transformer control and also feeder switching.
2.
3.
REFERENCE STANDARDS
The equipment supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular
3.1
Specification / Standard
Number
Title
IEC 60265
IEC 60282
IEC 60298
IEC 60420
IEC 60529
IEC 60056
IEC 60273
IEC 60129
IEC 60694
CONFLICT
See Specification TS-GN-02
4.
4.1
TYPE TESTS
The following type tests shall be carried out in accordance with the relevant IEC,
a)
Page: 1 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
b)
c)
d)
e)
f)
4.2
SECTION 5 - DESIGN
4.3
a)
b)
c)
d)
4.4
ADDITIONAL TESTS
The Employer reserves the right of having at contractors expense any other
tests(s) of reasonable nature carried out at Bidders premises, at site, or in any
other place in addition to the aforesaid type, acceptance and routine tests, to
satisfy himself that the equipment complies with the specification.
In case of failure in any type test, the Bidder is required to modify the design of
the equipment and type tested again for the modified design, without any extra
cost to the Employer. No delivery extension shall be given for this additional
testing.
4.5
TEST FACILITIES
The Bidder shall indicate the details of the equipment available with him for
carrying out the various tests as per relevant Standards.
Tests as per applicable standards should be carried out in respect of porcelain
bushings, galvanization, relays and meters.
5.
DESIGN
5.1
Page: 2 , 30-Apr-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-12
EEPCO
5.2
5.3
5.4
PERFORMANCE CHARACTERISTICS
I
Overall Unit
a)
Service
Outdoor
b)
Type
Metal enclosed
c)
Number of Phases
d)
System Voltage
e)
Rated Frequency
50 Hz (+/- 5%)
Page: 3 , 30-Apr-13
SECTION 5 - DESIGN
SPECIFICATION TS-SG-12
EEPCO
f
Insulation
SF6
II
a)
No. of poles
b)
Switch Type
c)
Rated voltage
15 kV
d)
Rated current
630 Amps
e)
f)
20 kA
g)
40 kA
h)
125kV
i)
50kV
III
a)
Type
Vacuum
b)
No. of poles
c)
Rated Voltage
15kV
d)
Rated Current
630A
e)
Breaking current
f)
Making current
40kA
g)
125kV peak
h)
50kV
IV
Bus bars
a)
Material
Copper
b)
Rated Current
630 Amps
c)
Breaking Current.
16 kA for 3 seconds
d)
e)
Anti-oxide grease
f)
Yes
Page: 4 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
Current Transformers
a)
b)
c)
To correspond to breaking
capacity circuit breaker
d)
Class of accuracy
5P10
e)
Rated burden
As designed to
protective relays
f)
125kV (peak)
d)
50kV
VI
Protection
a)
b)
drive
6.
6.1
CONSTRUCTIONAL FEATURES
the
The overall RMU unit shall be compact, modular in construction and suitable for
outdoor installation without any further covers/protection,
(ii)
All live parts except cable connections shall be insulated with SF6 enclosure. The
SF6 enclosure shall be made of stainless steel,
(iii)
The Ring Main Unit shall be tropicalised, for outdoor application with single bus
bar, and in a 2mm thick (minimum) metal enclosure provided with a pressure
relief arrangement ,
(iv)
Single line diagram indicating the operational status of the switchgear shall be
provided at the front of the cubicles, i.e. mimic diagram will be displayed on the
front of the Ring Main Unit.
(v)
The supply shall include all steel supports and necessary embedded parts and
anchor bolts for thoroughly fastening and securing the equipment.
6.2
Each load break switch shall have SF6 gas as insulating medium and SF6/Vacuum
interrupting medium.
Page: 5 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
(ii)
Each load break switch shall be triple pole and simultaneously operated,
(iii)
The mechanism of the switch shall be quick-break and quick make type, the speed
of operation being independent of operation with mechanically operated
indicator.
(iv)
Each load break switch shall be fitted with a direct manually operated mechanism
having three positions, ON, OFF and EARTH provided with pad locking
facility. All operating handles shall be located on the front panel of the Ring Main
Unit.
(v)
The operating mechanism shall be maintenance free without the need for any
lubrication during its life time.
(vi)
The LBFM switches shall be motorised for remote closing and opening operation
from remote control centre.
(vii)
6.3
CIRCUITBREAKER
The circuit breaking shall be in vacuum interrupter housed in SF6 insulated
chamber,
The circuit breaker shall be suitable for remote operation from town control
centre,
Suitable spring, motor-charging mechanism shall be provided for closing the
circuit breaker,
The spring will get automatically charged while tripping or following tripping,
Motor operation is provided for charging of springs,
Tripping of circuit breaker is provided through shunt trip coils tripping activated
by (feeder control) over current and earth fault relays. The VCB shall be provided
with closing coil for remote control.
6.4
INTERLOCKS
a)
b)
c)
d)
Suitable interlocks shall also be provided for cables test terminals and shall be
only in earth position.
e)
Integral test bushings shall be provided for cable testing on the switches for
maximum operator safety, "to prevent operation from ON position to Earth
position or vice versa in a single operation.
6.4.2
Page: 6 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
the switching device (load break switch circuit breaker or fuse switch,
isolator etc.) is in the open position.
any conducting parts, which extend outside the compartment are earthed.
opening of door or cover shall not be possible unless the Earthing switch is
closed.
a)
However the Earthing switch may be opened once the door is opened for cable
testing.
b)
(i)
6.4.3
Padlocking
Provision shall be made for padlocking the load break switches/Circuit Breaker,
and the Earthing switches in open or closed positions.
6.5
6.6
VOLTAGE INDICATORS
Capacitive voltage indication facilities for connection to the cable terminations
shall be provided through sockets at the front of the modules. It shall be possible
to test the voltage indicators before use.
6.7
PROTECTION
Suitable numerical protection relay, microprocessor based shall be incorporated
with each circuit breaker module. The protection of each module shall be and act
independently from the other modules.
The protective relay shall be driven by three CTs on the outgoing circuits.
Page: 7 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
The protection relays shall be self-powered necessary through the resin cast
current transformers and shall be equipped with suitable good quality batteries to
ensure that protection operation is according to international practices.
Protection setting range shall be as per standard protective relays for Overcurrent
and earth fault.
6.8
6.9
CTS
Three Current transformers shall be incorporated with the circuit bushings with
suitable rating to drive and provide operating power to the numerical protective
relays. The CTs shall be dual ratio as given in the technical schedules. The ratio
generally shall be designed to coordinate with the conductor sizes connected to it.
For the circuits not equipped with protection core type CTs shall be incorporated
with the incoming /outgoing cables.
6.10
7.
Sectionalisers and
Autoreclosers.
Page: 8 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
The remote control of the items above shall be achieved through a dedicated
Remote Terminal Unit (RTU) with communication for the required control and
indication via the control centre.
Two way communication system shall be accommodated between control centre
and RTUs,
The connecting cables shall be protected in either a metallic non rusting tube or a
metallic cover that can be fitted over the cable. The cable protection shall be
securely fixed on the pole and appropriate permanent fixings shall be provided.
The fixings shall not be plastic tie wraps. Stainless steel tie wraps are permitted.
7.1
RTUS
7.1.1
General
The RTUs shall be Microprocessor based intelligent control unit and shall
facilitate self-healing.
RTUs shall be of mainly two types. a) Integrated within the main unit such as
RMUs b) in a pole mounted box together with the control gear for the items such
as Sectionalisers and Autorecloser and c) in Substations .
The RTUs shall be factory wired and form part of the switchboard.
The RTUs shall receive a command from control centre, and execute the execute
for operations such as open / close and it and also transmits data acquired from
equipment back to control centre. The basic functions are
a)
b)
Status indication such as ON/ OFF status of RMU switches, capacitor switches,
Fault passage indicators, and tap position of voltage regulators etc.
c)
Analogue indication may include voltage, current, kW, kVAr etc., flowing through
RMU switches and Distribution Transformers.
The RTUs shall be designed to have the required number of inputs/outputs and
measurement inputs to suit the application.
The RTU shall be reconfigurable from control centre.
The RTUs shall be in general self powered from the protection CTs or VTs.
Alternatively they may powered through AC auxiliary supplies if available. RTUs
shall have internal batteries to enable them to provide uninterrupted operation
and data storage.
7.1.2
Page: 9 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
7.1.3
7.1.4
RTU Communication
A communication link is required between the Control centre and RTU 's. This
communication can be achieved :-
a)
Through the mobile telephony system ( GSM/ GPRS/ CDMA) if the services
provide a reliable system. OR
b)
7.1.5
7.2
RADIO MODEM
Radio data modem shall be designed, constructed and manufactured in
accordance with good engineering practice. It shall operate in transparent and
half-duplex mode without a need of keying control. However, Tx/Rx switching
times shall be limited to low values.
Radio data modem shall meet the following specifications.
Radio Standard
EN 300 113-1
EMC Standard
EN 301 489-1, -5
IEC 60950
Frequency Range
Page: 10 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
Number of channels
160 / 100 / 80
Frequency Stability
Carrier Power
10 mW /20 mW / 50
mW / 100 mW / 200
mW /500 mW / 1W,
software adjustable
7.3
CONTROL CENTRE
The control centre shall be located at the distribution control room in each town.
Please see separate specification for the control room.
8.
SAFETY& TESTING
8.1
SAFETY
8.2
(i)
(ii)
each switch board shall be identified by an appropriately sized label which clearly
indicates the functional units and their electrical characteristics.
(iii)
The switchgear and switch boards shall be designed so that the position of the
different devices is visible to the operator on the front of the switch board and
operations are visible as well through a window with fire proof transparent
material to see the physical isolation of contacts.
(iv)
In accordance with the standards in effect, the switch board shall be designed so
as to prevent access to all live parts during operation without the use of tools.
(v)
Any accidental over pressure inside the sealed chamber shall be limited by the
opening of a pressure limiting devices in the top rear part of the enclosure. Gas
will be released from the top rear of the switchboard away from the operator and
nearby pedestrians.
(vi)
All manual operations will be carried out on the front of the switch board.
TESTING EQUIPMENT
A gas pressure indicator or handy equipment to test the pressure of insulating gas
during the system operation shall be provided.
Page: 11 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
9.
9.1
EARTHING
The switchgear/switchboard shall have an earth bar. The earth bar shall be bolted
to the main frame and located so as to provide convenient facilities for earthing
cable sheaths and for use with earthing device. Means shall be provided for
coupling earth bars of adjacent units. The system earthing shall be such that at
least one of the neutral points of a three phase system is permanently earthed,
either solidly or through a resistor or reactance of low impedance. It shall not be
possible to remove the earth bar during operation.
All metal parts of the switchgear which do not belong to main circuit and which
can collect electric charge causing dangerous effect shall be connected to the
earthing conductor made of copper having CS area of minimum 75 mm2.Each
end of conductor shall be terminated by M12/equivalent quality and type of
terminal for connection to earth system installation. Earth conductor location
shall not obstruct access to cable terminations.
The following items are to be connected to the main earth conductor by rigid or
flexible copper conductors having a minimum cross section of 75mm (a) earthing
switches (b) Cable sheath or screen (c) capacitors used in voltage control devices,
if any.
9.2
PAINTING
All MS Structures shall be galvanized or epoxy painted in light Grey colour.
9.3
TROPICALISATION
Due regard should be given to the climatic conditions under which the equipment
is to work. Ambient temperature normally vary between -5o C and 30o C, although
direct sun temperature may reach 45o C. The climate is very humid and rapid
variations occur, relative humilities between 90% and 100% being frequently
recorded, but these values generally correspond to the lower ambient
temperatures. The equipment should also be designed to prevent ingress of
vermin, accidental contact with live parts and to minimize the ingress of dust and
dirt. The use of materials which may be liable to attack by termites and other
insects should be avoided.
9.4
INFORMATION LABELS
(i)
The name plates of the RMU functions shall be fixed on the front of the Ring
Main Unit.
(ii)
Specification plates of suitable size are to be screw fixed on the front of each
Ring Main Unit.
(iii)
Page: 12 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
9.5
CLEARANCES
(i)
Clearance between phases & earth in the insulating medium shall be as per latest
electricity rules and standards.
(ii)
(iii)
A voltage control device shall be installed on each ring cable to show if the cable
is energized or not.
(iv)
The degree of safety of persons against hazardous approach to live parts and
moving parts shall be provided strictly as per latest safety standards.
(v)
Proper sealing for the safety against entrance of small animals/insects into the
compartment shall be provided.
9.6
OPERATING HANDLE
All operating handles for the switches/circuit breaker shall be located on the front
panel of the Ring Main Unit.
9.7
CONTROL MECHANISMS
Control mechanisms of switching devices shall be independent of manual
operation or motor operation.
9.8
General outline drawing showing plan, elevation and end view dimensions,
assembly and constructional drawings of the equipment.
b)
c)
10.
b)
Spares required for trouble free operation of RMUs with their individual prices.
c)
List of recommended special maintenance Tools & Tackles together with their
individual prices for the equipment to be supplied against this specification
11.
11.1
SCOPE :
The specification covers specification of feeder Intelligent Electronic Devices (IEDs) to
be fixed control and relay panel.
11.2
STANDARDS :
The applicable standards of IEDs are specified here below :
IEC 60255-5
Impulse withstand : 5 KV
Page: 13 , 30-Apr-13
SECTION 11 - SPECIFICATION OF
PROTECTIVE DEVICES
SPECIFICATION TS-SG-12
EEPCO
11.3
IEC 60255-22-4
IEC 61000-4-3
IEC 60529
IEC 60255-21-1,
2, 3
EIA-364-65A
SYSTEM DETAILS :
The IEDs shall be suitable for outdoor and indoor installations with 3 Phase, 50 Hz,
33KV & 15KV system in which the neutral is effectively earthed and the same shall be
suitable for service fluctuations in supply voltage up to 10% and frequency variation of 3% and +2% (48.5 Hz to 51.0 Hz).
11.4
11.5
TECHNICAL PARAMETERS :
The relay should be micro processor based relay,
11.5.1
Protection Requirements
The relay should have all the protection functions in a single box like :
11.5.2
Measurement Requirements
The relay should provide Measurement for all basic and advance parameters like :
Neutral current
Voltage
Frequency
Power Factor
No. of operations
Page: 14 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
SECTION 11 - SPECIFICATION OF
PROTECTIVE DEVICES
The relays should have programmable LCD or LEDs Outputs, Digital inputs for
customized requirements.
11.5.3
General
The relay should have big alpha numerical display for showing measurement / settings
etc.,
It should be possible to withdraw the unit without prior current circuit short-circuiting.
The relay should have single button for resetting of the protection output and protection
function.
The relay should have remote and local selection provision.
11.5.4
1% to 240% of In or better
TMS
0.002 to 2.00
0.05 to 300 S
0.05 to 300 S
11.5.5
11.5.6
10 % to 2400 % of In or better
Time delay
50 ms to 20 S
1% to 100% of In or better
TMS
0.002 to 2.00
0.05 to 300 S
0.05 to 300 S
11.5.7
11.5.8
10 % to 1500% of In or better
Time delay
50 ms to 300 S
Page: 15 , 30-Apr-13
SECTION 12 - PACKING
SPECIFICATION TS-SG-12
EEPCO
11.5.9
Other facilities
The Relay should have WATCH DOG feature for continuous checking of
internal health of the relay and should have dedicated output for alarm and
tripping for the same.
The relay output should have enough capacity for energizing the direct tripping
and closing of the breaker.
The relay shall support and the user shall have a choice of curve types.
Protection tripping shall be indicated on the front of the device by a LED and
text indicating the cause of the fault.
The relay should interface with the RTU for communication
11.5.10
Guarantee
The relays shall be guaranteed for five years from the date of commissioning.
The manufacturer shall demonstrate the availability of spares for all the above
relays.
12.
PACKING
See spec. No.TS-GN-02
13.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
13.1
13.2
Page: 16 , 30-Apr-13
SPECIFICATION TS-SG-12
EEPCO
SECTION 13 - SCHEDULES
Page: 17 , 30-Apr-13
SECTION 13 - SCHEDULES
SPECIFICATION TS-SG-12
EEPCO
13.3
Page: 18 , 30-Apr-13
LPA-GECE
EEPCo
No
I
Item
1
2
General Details
Manufacturers name
3
4
Switchgear model No
Type
Unit
Requirement
Bid offer
II
Applicable Standards
Enclosure
IEC 62271-200
Circuit Breaker
IEC 62271-100
III
1
2
3
4
5
Rated voltage
Highest system voltage
Rated frequency
One minute power frequency withstand voltage
Lightning Impulse withstand voltage
kV
kV
Hz
kV
kV(peak)
15
24
50
50
125
kA
20
Sec
kA
40
9
10
Operating cycle
Minimum SF6 gas pressure at 20C
kg/cm
IV
1
Enclosure
Steel
2
3
4
SWG
SWG
Yes
14
18
5
6
V
1
2
3
4
5
6
7
kg/cm
1.35
A
kA
kA
630
20
40
kV
A
A
50
8
9
10
11
12
13
14
15
A
kV (peak)
kV (peak)
ms
ms
ms
ms
mm
VI
No. of poles
LPA-GECE
No
Item
Switch Type
3
4
5
6
7
Rated voltage
Rated current
Load breaking current
Short time Rating
Fault making capacity (kA peak/ min.)
Impulse withstand voltage to earth between
poles.
Power frequency withstand voltage to earth and
between poles
8
9
VII
1
2
3
Unit
Requirement
SF6-Single Break,
Load breaking and
fault making switch
15 kV
630 Amps
630 Amps at 0.7PF
20 kA
40 kA
Bid offer
125kV
50kV
Current Transformers
Type
Primary Transformation ratio
Secondary transformer ratio
Over current factor
4
(i)
(ii)
5
6
7
VIII
1
2
IX
1
2
3
4
5
X
Class of accuracy
Protection core
Metering core
Rated burden
Impulse flash over withstand voltage
Power frequency withstand voltage
2
3
4
XI
EEPCo
Cast resin
300-150A
to correpond to
breaking capacity
of crcuit breaker
5P10
0.2
as per requirement
125kVp
50kV
Earthing Devices
Rated short circuit withstand current
Duration of Short Circuit
kA
sec
20
3
kA
kV
20
24
Copper
SF6
Protection
RTU
Make
Model
XII
Communication
XI
1
2
3
4
Type
Make
Model
Power
Cubicle
Degree of Protection:
HV compartment
LV compartment
Whether Space Heater is provided
Radio
IP65
IP42
YES
LPA-GECE
No
XII
Item
Interlocks provided for
XIII
1
2
3
XIV
1
2
3
4
5
XV
Earthing
Earthing of Circuits
Earthing of Busbar
Method of Circuit Earthing
Service Life
Operating design life (Rated Current)
Contact Life at Rated Interrupting Capacity
Type of Power Closing Devices
Method of Opening Devices
Control voltage
Recommended Maintenance Intervals
1
2
3
4
XVI
1
EEPCo
Unit
Requirement
ELECTRICAL &
MECHANICAL
Yes
Yes
Yes
Throughout RMU
Times
Times
10000
30
Motor spring charged
Bid offer
230V a.c
Yrs/Ops
Yrs/Ops
Yrs/Ops
Yrs/Ops
Yrs/Ops
Yes
Yes
Yes
Yes
2 Isolators & 4 VCBs
mm
mm
mm
EEPCO
SPECIFICATION
TS-SG-13
Pole mounted 15kV Switched Capacitors
SPECIFICATION
EEPCO
Date
Brief Description
Rev 0
Apr 2013
First issue
Page: i , 11-Apr-13
SPECIFICATION
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED 15KV SWITCHED CAPACITORS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
ACCEPTANCE TESTS
1
2
2
5.
DESIGN OF CAPACITORS
5.1
5.2
5.3
5.4
5.5
5.6
5.7
GENERAL
PERFORMANCE CHARACTERISTICS
BUSHINGS AND TERMINALS
GROUNDING TERMINALS
TANK FABRICATION
FINISH OF TANK
RATING AND CONNECTION PLATE
3
3
4
4
4
4
4
6.
6.1
6.2
6.3
6.4
6.5
6.6
6.7
RATED VOLTAGE
RATED CURRENT
RATED CAPACITIVE SWITCHING CURRENT
RATED SHORT TIME CURRENT
RATED MAKING CURRENT
BASIC IMPULSE LEVEL (BIL)
CONTROL SUPPLY
5
5
5
5
5
5
5
7.
7.1
7.2
CENTRAL PARAMETER
OPERATING MECHANISM
6
6
8.
9.
10.
6
6
7
10.1
10.2
10.3
7
8
9
Page: ii , 11-Apr-13
SECTION 1 - SCOPE
SPECIFICATION
EEPCO
SCOPE
This specification covers the design, manufacturing, testing, supply, delivery and
performance requirements of pole mounted automatic switched capacitors for
installations comprising of,
(i)
(ii)
2.
3.
REFERENCE STANDARDS
The shunt capacitors shall comply with the latest editions of and amendments
to, the Standards/Specifications listed below.
3.1
Specification /
Standard Number
Title
IEC 60871
IEC 60129
IEC 60694
CONFLICT
See Specification TS-GN-02
4.
4.1
TYPE TESTS
4.1.1
Page: 1 , 11-Apr-13
SPECIFICATION
EEPCO
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
Endurance test.
4.1.2
Tests on switches
(i)
(ii)
Tests to prove that the temperature rise of any part does not exceed the specified
values,
(iii)
(iv)
Tests to prove the capability of the switch to carry the rated short-time current,
(v)
4.2
ROUTINE TESTS
Tests on capacitor Banks
The shunt capacitor units shall be subjected to the following Routine Tests at the
manufacturers works.
(i)
Capacitance measurement,
(ii)
Measurement of the tangent of the loss angle (tan delta)of the capacitor,
(iii)
(iv)
(v)
(vi)
Sealing test,
(vii)
4.2.2
4.3
Tests on switches
(i)
(ii)
(iii)
(iv)
ACCEPTANCE TESTS
All acceptance tests as stipulated in the relevant standards and as given below shall
be carried out by the supplier in the presence of the Employers representative.
Page: 2 , 11-Apr-13
SPECIFICATION
EEPCO
(i)
(ii)
(iii)
5.
DESIGN OF CAPACITORS
5.1
GENERAL
This specification covers the requirement for outdoor 15kV 3 phase, shunt
capacitor banks and associated equipment,
(i)
Each bank shall consist of one capacitor unit of 200 kVAr per phase complying
with the relevant IEC,
(ii)
The capacitor banks shall be suitable Pole mounting and suitable for outdoor
mounting and for upper limit of ambient temperature category of 50 C.
5.2
PERFORMANCE CHARACTERISTICS
(i)
The rated voltage of the capacitors shall be 17.5 kV (phase to phase). This
represents the highest system voltage corresponding to the nominal system
voltage of 15 kV but should be designed for insulation levels of 24kV because of
their installation at altitudes of up to 3000M.
(ii)
The standard rated output of a switched capacitor bank shall be 600 kVAr at
15kV rated voltage. The bank shall comprise of 3 single phase units of 200 kVAr
each connected in star with floating neutral.
(iii)
The maximum permissible overloads with regard to voltage, current and reactive
output shall conform to the relevant standard.
(iv)
The power loss in capacitors shall not exceed 0.2 Watt/kVAr (subject to a
tolerance of plus 10%).
(v)
(vi)
The discharge device shall reduce the residual voltage from the crest value of the
rated voltage to 50 V or less within 5 minutes after the capacitor is disconnected
from the source of supply.
(vii)
The container of each capacitor unit shall be provided with suitable earthing
terminal clearly marked as EARTH.
5.2.2
Operating Conditions
The Capacitors shall be Capable of Operating in energized condition
continuously.
5.2.3
The capacitors shall be provided with either internal or external fuses as per
standard practice of the manufacturer. In the latter case, the manufacturer shall
supply a set of external fuses together with the fixing accessories and a set of three
spare fuse links along with the capacitor bank. Necessary protection against over
voltage and inrush current shall be provided.
Page: 3 , 11-Apr-13
SPECIFICATION
EEPCO
(ii)
The capacitors shall be of non PCH type using propylene film as the dielectric.
5.3
5.3.1
Bushings
The Bushings shall conform to the relevant IEC and shall be sufficiently robust to
withstand normal transport hazards.
The bushings shall be fitted with galvanised hardware and suitable lugs to accept
the tin plated aluminium lugs or pure copper lugs,
5.3.2
Connections
For connecting to the terminals of the capacitor 16mm to 70mm Cu or 25mm
to 100mm Al. stranded conductors will be used.
5.4
GROUNDING TERMINALS
All capacitors shall be provided with a grounding terminal with a 10mm diameter
hole. The material shall be galvanised steel.
5.5
5.6
TANK FABRICATION
a)
Capacitor tanks shall not leak and shall be of hermetically sealed construction.
b)
The minimum thickness of steel used shall be 3mm. Thickness below the
minimum value will be considered only in exceptional cases, such as where special
protective finishes are used. The Contractor shall provide full information about
any such special finish, including any field experience.
FINISH OF TANK
1) The capacitor tank and its accessories shall be adequately protected against
corrosion and the Bidder shall include a statement of the method of protection
proposed.
2) The container shall be hermetically sealed by controlled arc welding process. The
metal flange of the bushing should be soldered / welded to the container covered
with epoxy compound providing a strong hermetical sealing of the container.
3) Hot dip galvanising is preferred, when this is not practical the tanks shall be
shot-blasted and then immediately zinc sprayed to an average weight deposit of
not less than 550 g/m followed by a zinc chromate based primary paint, and two
coats of durable oil and weather resisting paint. Finish colour shall be light grey.
4) Suitable mounting brackets for mounting the bank on concrete poles shall be
welded to the container.
5.7
Page: 4 , 11-Apr-13
SPECIFICATION
EEPCO
6.
6.1
RATED VOLTAGE
The rated voltage for the capacitor switches shall be 17.5 kV. This represents the
highest equipment voltage corresponding to the nominal system voltage of 15 kV.
6.2
RATED CURRENT
The standard rated normal current shall be 400 A
6.3
6.4
6.5
6.6
6.7
CONTROL SUPPLY
The capacitor switch shall be self-powered from the 15 kV line i.e., no AC or DC
control supply need be made available for its operation. The source of control
supply (auxiliary transformers etc) should work satisfactorily with voltage
fluctuations on the 15 kV line from +10% to 20%. The same supply may be
used to protect the capacitor in case of over voltage due to shifting of neutral due
to single phase fault. Suitable relay shall be included to trip the capacitor switch in
case of over voltage.
7.
Page: 5 , 11-Apr-13
SPECIFICATION
EEPCO
The metallic enclosure of the capacitor switch shall be provided with two earthing
terminals (marked with the earth symbol), inverted V type top arrangement shall
be provided to prevent stagnation of rain water. The bushings provided on the
switch shall be of high quality porcelain and shall have clamp type of terminal to
directly receive aluminium conductors up to 10mm dia. in both horizontal and
vertical directions. The terminal arrangement shall be such as to avoid bimetallic
corrosion.
7.1
CENTRAL PARAMETER
The central parameter for switching operation shall be the line current at the point
of installation of the switch. The maximum value of the line current shall be 400A
and accordingly a current transformer of 400/5A ratio shall be supplied along
with an ammeter and switch to measure the line current in one of the phases for
the purpose of control. The switch shall have adjustable value of current at which
the capacitor bank shall be switched ON or switched OFF. This adjustment shall
be available in continuous variation in steps not exceeding 5A each over a
minimum range of 10-50 amps, line current.
There shall be an inherent delay of at least 5 minutes in each switching operation
to avoid any damage to the capacitor.
7.2
OPERATING MECHANISM
The operating mechanism shall be either solenoid or motor charged spring for
which the control supply shall be as per clause 6.7 Control Supply above.
Necessary relays to sense the CT secondary current and to control the capacitor
switch shall be included in the supply.
8.
9.
9.1.1
CAPACITOR BANKS
1) Manufacturer,
2) Manufacturer's designation,
3) Rated output ,
4) Rate voltage,
5) Year of manufacture,
6) EEPCO order number,
7) Rated current,
8) Rated frequency,
Page: 6 , 11-Apr-13
SPECIFICATION
EEPCO
SECTION 10 - SCHEDULES
10.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
10.1
Page: 7 , 11-Apr-13
SECTION 10 - SCHEDULES
SPECIFICATION
EEPCO
10.2
Page: 8 , 11-Apr-13
SECTION 10 - SCHEDULES
SPECIFICATION
EEPCO
10.3
Page: 9 , 11-Apr-13
LPA-GECE
EEPCo
S.No. Item
1 Capacitor bank voltage (nominal)
2 Capacitor bank maximum Equipment
Withstand Voltage
3 Rated Equipment Withstand voltage for
bushings
4
Nominal Voltage across one capacitor unit
5
6
7
8
9
10
11
12
13
14
15
16
Number of phases
Rated frequency
VAr rating of three phase capacitor bank
Rated current for the switch
Type of fluid
Rated making current for th switch
Rated capacitive switching current
Power frequency, 1 minute
Basic impulse level
Max.Tolerance of Capacitor bank rated
Connection
17
18
Mounting
19
20
21
22
23
24
Type of fluid
Fuse rating (type)
Maximum fuse blowing time
Number of slacks
Number of racks
25
26
27
28
29
30
31
32
33
Uit
kV
Bid offer
Requirement
15
kV
17.5
kV
24
kV
8.66
Hz
Var
A
kA
kA
A
kV
kV
3
50
600
400
10
25
>30
50
125
0 to +5%
Composition
Design standards
Switchable or step units with multiple step
sequence control
Spare cans
Spare fuse links
Spare fuse holders
kV
Nos.
mm/kV
>30000/30000
20
IEC pub 60871-1 and
60871-2
Yes
10% of supplied units
20% of supplied units
20% of supplied units
Page 1
Date: 11/4/2013,
EEPCO
SPECIFICATION
TS-SG-14
SPECIFICATION TS-SG-14
EEPCO
Date
Brief Description
Rev 0
Mar 2013
First Issue.
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
LPA/GECE/Page: i , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
POLE MOUNTED 15KV LINE SECTIONALISERS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
TYPE TESTS
ROUTINE TESTS
1
2
5.
DESIGN CHARACTERISTICS
5.1
5.2
5.3
5.4
5.5
5.6
5.7
2
2
2
2
2
2
5.8
5.9
5.10
5.11
5.12
5.13
5.14
5.15
RATED VOLTAGE
RATED CURRENT
RATED BREAKING CAPACITY
RATED SHORT TIME CURRENT
RATED MAKING CURRENT
RATED BASIC IMPULSE LEVEL
RATED ONE MINUTE POWER FREQUENCY WITHSTAND
VOLTAGE
CONTROL SUPPLY
FAULT BREAKING CAPACITY
OPERATION
ELECTRICAL AND MECHANICAL ENDURANCE
FAULTY SECTION INDICATOR
DESIGN AND CONSTRUCTIONAL REQUIREMENTS
TANK
COORDINATION WITH THE SUB-STATION BREAKER
6.
7.
8.
MARKING
6
SCHEDULES
8.1
8.2
8.3
7
7
8
A-1
A-2
A-3
A-4
GENERAL
TYPE-I VOLTAGE SENSING SECTIONALISER
TYPE-II COUNTING FAULT CURRENT PASSAGES
OVERALL RECOMMENDATION
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
2
3
3
3
4
4
4
4
5
9
9
13
13
LPA/GECE/Page: ii , 11-Apr-13
SECTION 1 - SCOPE
SPECIFICATION TS-SG-14
EEPCO
SCOPE
This specification covers the design, manufacture, supply, delivery and
performance requirements of Pole mounted 3-phase 15kV Automatic Line
Sectionalisers for outdoor installation for detection of fault, isolation of the faulty
branch line and restoration of power supply to healthy section, in the event of
fault, to improve reliability.
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
Specification /
Standard Number
Title
IEC 60694
IEC 60265-1
IEC 62271-200
High Voltage switchgear and control gear Part200.A.C metal enclosed Switchgear and control gear
for rated voltages above 1kV and up to and including
52kV.
CONFLICT
See Specification TS-GN-02.
4.
4.1
TYPE TESTS
(i)
Tests
(ii)
(iii)
Tests to prove that the temperature rise of any part does not exceed the specified
values,
(iv)
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 1 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
(v)
Tests to prove the capability of the switch to carry the rated short-time current,
(vi)
(vii)
4.2
ROUTINE TESTS
(i)
(ii)
(iii)
(iv)
5.
DESIGN CHARACTERISTICS
5.1
RATED VOLTAGE
The rated voltage for the line sectionaliser shall be 17.5KV. This represents the
highest system voltage corresponding to the nominal system voltage of 15KV
for all solid insulation, oil, vacuum, gas insulated equipment. For bushing the
highest equipment voltage level shall be 24kV.
5.2
RATED CURRENT
The standard rated normal current shall be 400 A.
5.3
5.4
400A
10A
10A
10A
5.5
5.6
5.7
125 kV
150 kV
50 kV
(ii)
60 kV
(iii)
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
2 kV
Page: 2 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
5.8
CONTROL SUPPLY
The line sectionalisers are provided with Voltage transformer on one side or
either side as the case may be to sense the powered supply and provide Control
supply for operation of sectionalisers.
5.9
5.10
OPERATION
5.10.1
Purpose of sectionalisers
The sectionalisers are deployed in Distribution system to improve the reliability of
power supply. The sectionaliser is load breaking and fault making switch with
Voltage sensing and timing control mechanism. The sectionaliser has no fault
current interrupting capability and therefore always work in association with a
circuit breaker having auto reclosing facility.
5.10.2
Functions of Sectionalisers
The function of a sectionaliser is to isolate the faulty section and restore power
supply to healthy part of feeder when a permanent fault occurs on the feeder. If
the fault is transient in nature, then supply is restored after momentary
interruption on reclosing of feeder circuit breaker
5.10.3
Components of Sectionalisers
The sectionaliser consists of 3 parts
5.10.4
Load breaking and fault making SF6/ Vacuum switch called DM switch
Operation of sectionaliser
The principle of operations how the Sectionaliser operates in case of
transient fault and permanent fault on radial feeder and Loop feeder is explained
in Appendix A
5.10.5
Advantages of Sectionalisers
The advantages of Sectionaliser are
(i)
(ii)
The number of interruptions to any customer for any permanent fault is only two
irrespective of location
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 3 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
(iii)
5.11
The sectionalisers facilitates automatic power supply restoration from loop feeder
in case of fault providing supply to all healthy sections other than faulty section.
5.12
5.13
5.14
TANK
The switching contacts are housed in a steel tank of thickness 3mm. Thickness
below the minimum value will be considered only in exceptional cases where
protective finishes are used. The contractor shall provide full information where
any such special finish is used and also provide field experience, if any.
Each tank shall be provided with an explosion vent on the side (only for SF6
type) which shall safely release any over pressures developed by excessive internal
arcing. A mechanical low gas pressure interlock which prevents operation of the
sectionaliser if the gas pressure falls below certain safe pressure shall be provided.
There shall be a visible indication of low gas pressure through a window in the
tank and also through a flag which could be seen from the ground.
The sectionalisers shall be provided with a mechanically operated contact position
indicator. The provision shall also be made for manual opening and closing of the
sectionaliser from ground level using a hook stick.
A manual lock-out ring which when pulled by the hook-stick prevent operation of
the sectionaliser to take up maintenance work in the downstream of the
sectionaliser.
5.14.1
Indicators
Two nos. ON/OFF indicators shall be provided, one on the side of the tank by
the operating lever and one underneath the tank visible to the operator from
below.
Sectionaliser bushing terminals shall be designed so as to directly receive AAAC
conductor up to 200 mm size by using bolted clamps so as not to require the use
of lugs. The terminal arrangement shall be such as to avoid bimetallic corrosion.
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 4 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
5.15
SF6 LOCKOUT
If the unit is SF6 insulated then a lockout on low pressure should operate and
prevent the unit from closing.
A visual alarm shall be incorporated in case of low gas pressure.
5.16
6.
6.1
SECTIONALISER CONTROL
The Sectionaliser shall be fitted with a separate control box.
Protection and timer relays shall be installed in this control box. This control box
shall be suitable for fitting on the pole at a low level than the Sectionaliser to
provide inspection maintenance and setting access to utility personnel. All fittings
required for mounting shall be supplied. All operating parameters of the
Sectionaliser shall be controlled from the control box.
All settings shall be either a) through a suitable interface pad/keyboard designed
for the harsh operating environment of the Sectionaliser, b) positive step selector
switches or c) plug-in components.
Ratings shall be clearly marked in relevant units of measure with no interpretation
multipliers or conversion being required.
Each unit shall be equipped with an electronic control armoured capable of
operating in the environmental conditions specified in spec. No. TS-GN-01. The
cable shall be protected in either a metallic non rusting tube or a metallic cover
that can be fitted over the cable. The cable protection shall be securely fixed on
the pole and appropriate permanent fixings shall be provided. The fixings shall
not be plastic tie wraps. Stainless steel tie wraps are permitted.
6.2
COMMUNICATION SYSTEM
Remote Terminal Unit / Remote control shall be provided for the Sectionaliser if
so specified in the technical schedule. The remote control shall be achieved
through a communication link between control centre and the Sectionalisers and
necessary provision shall be incorporated in the control box.
GSM/GPRS/ CDMA service is available in 7 towns and is proposed to be
deployed for communication between Control Centre and this device.
Alternatively communication may be provided through a radio link with the
Control room.
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 5 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
SECTION 7 - MARKING
The Unit shall incorporate the necessary remote terminal interface equipment to
enable linkage between the unit control and the communication system.
The Unit shall incorporate an energy storage system to enable the equipment to
operate within one month of being disconnected/ powered-off from the network.
Full details and rights to use protocols for communication and operation of the
device shall be provided to the client/purchaser to enable the SCADA system to
interface with the unit. The cost of the provision of any protocol look up tables
etc. shall be included in the cost of the device. Full details shall be included with
the supply of the device to enable the Unit to be integrated with the SCADA
system.
Remote terminal unit (RTU) and modem is included in the standard equipment
for the automated switch.
Information on load break switch and sectionaliser states and fault values shall be
transmitted to the SCADA system
6.3
7.
Voltage
MARKING
The sectionalisers shall be provided with a name plate legibly and indelibly marked
with the following:(i)
(ii)
(iii)
(iv)
Rated frequency,
(v)
Number of poles,
(vi)
(vii)
(viii)
(ix)
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 6 , 11-Apr-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-14
EEPCO
8.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
8.1
SCHEDULE FOR POLE MOUNTED 15KV LINE
SECTIONALISERS
Please see separate technical schedule TS-SG-14 S.
8.2
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 7 , 11-Apr-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-14
EEPCO
8.3
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 8 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
SECTION 8 - SCHEDULES
APPENDIX A DESCRIPTION OF
SECTIONALISER OPERATION
A-1
GENERAL
The distribution system design is targeting to reduce power outage time and
improve power reliability. In order to achieve this it is possible to use automatic
equipment to isolate a section of the network where a fault occurred. This can be
achieved by employing Sectionalisers in conjunction with the Circuit breaker (CB)
at the substation, equipped with auto-reclosing features that will operate at the
occurrence of a fault and reclose automatically to cater for transient faults and
accommodate auto-sectionalisation of the system.
A Sectionaliser consists of 3 components basically and they are:
A-2
A-2-1
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 9 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
SECTION 8 - SCHEDULES
If the reclose relay has fault sensing facility then the breaker will see a fault in the
first section and will not close, i.e. it will remain open. Then the operator knows
that a fault occurred in the first section of the line.
If the breaker protection relay does not have a fault sensing relay or the fault is
not in the first section after a reclose time Tr the substation breaker will close.
If the fault is in the first section the substation breaker will trip for the second
time and reclose two times before locking out.
If the fault is on the second section then the sequence of sectionaliser starts after
the first re-closure.
When the Circuit Breaker (CB) at the substation closes after the 1st tripping, the
control relay TSR of sectionaliser receives voltage and it waits for a time of 10sec
before permitting closing of the DM switch. This time hereinafter called X time
of TSR relay is adjustable by programming to coordinate with the substation
reclose settings.
After the DM switch closes a timer starts to record elapsed time. This is of the
order of about 5 sec, (hereinafter called the Y time of the TSR relay) and it is
considered as the eliminating time of this lockout timer. This time is set to be the
maximum time that the substation breaker will clear any fault.
This timer is used to determine indirectly persistent faults beyond the point of the
DM switch. If the fault persists the substation breaker will trip again (within this
time) and this timer Y will effectively lock out the Sectionaliser as its time of 5 sec
has not elapsed to enable it to reset. The system has effectively determined that
the fault persists after the sectionaliser.
When the substation breaker re-closes this sectionaliser will remain open thus
isolating the faulty section.
A-2-2
If a fault occurs in section S1 the substation breaker will reclose, trip, reclose and
trip again and stay open as described in the previous case (A-2-1).
If the fault is in section 2 the operation will be also as described above.
If the fault is in section 3 the following sequence will occur.
Both Sectionalisers DM1 and DM2 open during dead time of substation reclose relay and the substation breaker is only connected to section S1, the
other two sections are disconnected.
The substation breaker recloses after time Tr and the sensing relay at 1st
Sectionaliser senses voltage.
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 10 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
SECTION 8 - SCHEDULES
After 10 seconds from sensing voltage (Tr + 10 sec) the 1st sectionaliser
S1, closes and the Y lockout timer arms and counts. Second sectionaliser S2
now sees voltage and its sensing relay Y starts counting the 10 sec it needs
before it will allow 2nd sectionaliser to close.
After 5 seconds the Y timer of the 1st sectionaler resets, hence does not lock
out.
After 10 sec from closure of 1st Sectionaliser, (ie after Tr +10 +10 sec), 2nd
sectionaliser closes to the faulty section.
As the fault is persisting the substation breaker will trip, before the Y timer
of the 2nd sectionaliser resets, hence locking out the second sectionaliser.
The substation breaker trips and recloses for the second time.
The 1st recloser will reclose normally but the 2nd will remain open, thus
removing isolating the faulty section.
All operations sequences will clear within 2 recloses of the substation breaker.
A-2-3
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 11 , 11-Apr-13
SECTION 8 - SCHEDULES
SPECIFICATION TS-SG-14
EEPCO
Fig.2
Page: 12 , 11-Apr-13
SPECIFICATION TS-SG-14
EEPCO
SECTION 8 - SCHEDULES
16) DM1 switch closes after 10 seconds or at adjusted time of TSR1 relay.
17) DM2 will not close this time as it is in lock out stage.
18) Supply of healthy section 1 & 2 is restored.
19) Thus the faulty section No.3 is isolated.
The position of the sectionaliser provides clue to patrolmen to identify the fault
A-2-4
CONCLUSION
This type of sectionaliser is suited for very long lines where more than one
Sectionalisers are required and will clear /isolate the faulted section for any
number of sectionaliser.
A-3
A-3-1
CONCLUSION
Hence it can be seen that only one sectionaliser can be reasonably accommodated
under this scheme to provide the necessary selectivity and discrimination.
These type of sectionaliser however can be very cheap and simple compared to
the type I units described above.
They can be used on laterals of long lines if fuses are not employed. If laterals are
fused then these simple units are not required.
A-4
OVERALL RECOMMENDATION
It is recommended that both types are used in the system at the appropriate places
to achieve the best value for money system design.
TS-SG-14 R0a Pole mounted 15kV Line sectionalisers.docxRev -0- Mar 2013
Page: 13 , 11-Apr-13
LPA-GECE
EEPCo
Item
Unit
kV
Requireme
nt
15
kV
17.5
kV
24
equipment
bushings
Rated acivesuch
loadasbreaking
capacity
400
10
10
kA
10
kA
20
kV
125
10
kV
50
11
kV
12
Yes/No
Yes
13
sec
0-10 sec
Bid Offer
Page 1
Date: 11/4/2013,
LPA-GECE
EEPCo
14
sec
0-10 sec
15
Yes/No
Yes
operations
Vacuum
Yes
3000
19
Mechanical endurance
operations
3000
20
Nos.
2Nos.each
21
250
22
23
16
17
18
Yes
Radio
Page 2
Date: 11/4/2013,
EEPCO
SPECIFICATION
TS-TR-01
SPECIFICATION TS-TR-01
EEPCO
Date
Brief Description
Rev 0
25/1/2011
First Issue.
Rev1
Dec2012
Rev2
Feb 2013
Rev 2a
Mar 2013
Rev 3
19 Mar 2013
Final corrections
Page i , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
SPECIFICATION CONTENTS
.
DESCRIPTION
PAGE NO
3 PHASE DISTRIBUTION TRANSFORMERS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
4.4
4.5
4.6
TYPE TESTS
ROUTINE TESTS
AIR PRESSURE TEST
ACCEPTANCE TESTS
SPECIAL TESTS
TESTS ON BUSHINGS (HV&LV)
2
2
2
2
3
3
5.
DESIGN OF TRANSFORMERS
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
3
3
4
5
5
6
6
6
7
7
7
8
6.
7.
LOSSES
TRANSFORMER TANKS
8
9
7.1
7.2
7.3
7.4
7.5
7.6
9
10
10
11
11
11
8.
9.
10.
11.
12.
13.
TRANSFORMER OIL
UNDERCARRIAGE
INTEGRAL DESIGN - LIGHTNING ARRESTORS
EARTHING TERMINAL
EQUIPMENT AND ACCESSORIES
MARKING
11
11
12
12
12
13
Page ii , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
13.1
13
14.
14
14.1
14.2
14
14.3
14.4
15.
16.
TRANSPORT
SCHEDULES
16
16
16.1
16.2
16.3
16
1
2
14
15
16
SECTION 1- SCOPE
SPECIFICATION TS-TR-01
EEPCO
SCOPE
This specification covers the design, manufacture, testing, supply, delivery and
performance requirements of 3-phase, pole and ground mounted Distribution
Transformers.
2.
3.
REFERENCE STANDARDS
The requirements of the following standards / specifications shall be met by the
Distribution Transformers where applicable unless otherwise stated in this
specification. The bid shall include typical dimensional and sectional drawings of
the transformers and accessories
3.1
.Specification/
Standard Number
Title
IEC 60076
Power Transformers
IEC60137
IEC 60214
IEC 60296
IEC 60354
IEC 60529
IEC60551
IEC 60567
Guide for sampling of gases and oil from oil filled electrical
equipment and analysis of free and dissolved gases
IECITR 60616
IEC 60722
CONFLICT
See Specification TS-GN-02shall apply.
.
Page: 1 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
4.
4.1
TYPE TESTS
In addition to the IEC requirements the following type tests shall be conducted
on the Transformers of identical design to prove that the offered transformers
satisfy all the design requirements set out in this specification..
1) Temperature Rise Test.
2) Dielectric tests
4.2
ROUTINE TESTS
The transformer shall be subjected to the following Routine Tests at the
manufacturers works..
Checking of weights, dimensions, fittings, accessories, tank sheet thickness, oil
quality, material, finish and workmanship as per Guaranteed Technical Particulars
and contract drawings.
1) Measurement of winding resistance.
2) Measurement of Voltage Ratio and check of phase displacement.
3) Measurement of short circuit impedance and load loss.
4) Measurement ofno load loss and current
5) Dielectric routine tests.
4.3
4.4
ACCEPTANCE TESTS
All acceptance tests as stipulated in the relevant standards and as given below shall
be carried out by the supplier in the presence of the Employers representative.
1) Measurement of winding resistance
2) Voltage ratio measurement and check of polarity or vector group symbol - at all
tap positions. Bushing positions shall have permanent markings at this stage of
production.
3) Measurement of impedance voltages
4) Measurement of load loss
5) Measurement of no-load loss and no-load current
6) Induced over voltage withstand test - 30kV and 66kV for 60 seconds on the 15kV
and 33kV windings respectively.
Page: 2 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
4.5
SPECIAL TESTS
Other type and routine tests, as agreed between Employer and Bidder shall also
be carried out as per the relevant standards.
4.6
5.
DESIGN OF TRANSFORMERS
5.1
5.2
GENERAL
The transformers shall be capable of operating continuously within their specified
temperature rise limits, i.e. the corrected maximum permissible temperature rise
of the oil (top oil) shall not exceed 55 C, the average temperature rise of the
winding is to be limited to 60C, and the winding hot spot temperature rise shall
not exceed 68C.
The transformers shall be capable of withstanding external short circuits for at
least 3 seconds
following application of loading conditions specified in IEC 60076-7.
Neutral points shall be brought out on a bushing to enable LV transformer
earthing.
All specific schedules of guaranteed characteristics are stipulated in the technical
schedule. The transformers shall be designed and tendered in full compliance with
all further applicable sections, articles and drawings of the Specification.
Furthermore, each transformer shall comply with the stipulations mentioned
hereunder.
Page: 3 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
The transformers of ratings 25kVA, 50kVA, 100kVA, 200kVA and 315kVA shall
be pole mounted on PMT structures with brackets. These transformers shall be
without terminal boxes.
Transformers of ratings 400kVA, 500kVA,630kVA, 800kVAand 1250kVA shall
be ground mounted on plinths.
5.3
DESIGN OF CORES
5.3.1
5.3.2
Core material
Only new materials shall be used for the core construction. The manufacturer
shall provide all necessary proof, if so required by the client. .
The design of the magnetic circuit shall be of non-ageing, Cold Rolled Grain
Oriented (CRGO) Silicon steel of high permeability without burrs and such as to
avoid static discharges, development of short circuit paths within itself or to the
earthed clamping structure and production of flux components at right angles to
the plane of laminations which may cause local heating. The flux density shall not
be more than 1.65T.Each lamination shall be insulated with high quality insulation
coating. The core and its Clamping plates shall form a rigid unit structure, which
shall maintain its form and position under the severe stresses encountered during
shipment, installation and short circuits.
Page: 4 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
5.4
WINDINGS
5.4.1
General
Bracing of Windings
The windings and connections of all transformers shall be braced to withstand
shocks which may occur during transport or due to switching and other transient
conditions during service.
Any metal pieces in contact with end rings shall be so designed and secured that
they do not weaken the electrical or the mechanical properties of the rings.
If the transformer winding is built up of sections or disc coils separated by spacers
the clamping arrangements shall be such that equal pressure is applied to all
columns of spacers. All such spacers shall be securely located, shall be of suitable
material and shall receive adequate shrinkage treatment before assembly.
5.5
MV BUSHINGS
5.5.1
5.5.2
5.5.3
Page: 5 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
5.5.4
General design
MV bushings shall be rated to withstand the highest system voltage and the
maximum fault current of the windings when connected to the 15kV or 33 kV
network and for the same period of time.
Current carrying outer parts shall be made of tinned copper, copper or copper
alloy.
It shall be possible to change the bushings without removing the transformer lid.
Each bushing shall be marked with the name of the manufacturer and type. The
marking shall be visible after assembly of the fittings.
5.6
LV BUSHINGS
Each MV bushing location shall be permanently and legibly marked on the tank
or lid with a label corresponding to the rating plate designation.
The LV bushings shall be equipped with line clamps suitable for connecting
aluminium and copper conductors as follows.
LV bushings for 3phase 25,50 and 100kVA transformers, phase clamp 95 mm2,
neutral clamp 70 mm2.
For other ratings suitable LV clamps and/or a terminal pad to take multiple
conductors shall be provided.
The clamps shall be complete with necessary screws, washers and nuts.
The position of each LV bushing shall be permanently and legibly marked on the
tank or lid with a label corresponding to the rating plate designation. The LV
neutral connection shall have a permanent, special marking, different from the
phase connections.
LV bushings shall be sufficiently rigid to take the weight of up to 95mm2 AB
cable connected between the LV bushing and the adjacent pole. Alternatively a
support bracket may be provided that can be attached to the tank of the
transformer, to offer support to ensure no damage of the bushings because of
movement of the AB cable.
5.7
5.8
Page: 6 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
5.9
5.10
5.11
ELECTRICAL DATA
5.11.1
Short-circuit Currents
The transformers shall withstand the thermal and mechanical effects of any shortcircuit that can appear at the terminal of any winding. The short-time current (3
sec(rms.) shall be for the specified system fault levels.
5.11.2
Insulation Level
The transformers shall be designed for the following insulation levels.
5.11.3
System
Highest voltage
Voltage(kV)
for equipment
Um kV (rms.)
15
24
50
125
33
52
95
250
Rated Power
The rated output at +45C maximum ambient temperature shall be one of the
preferred ratings 25, 50, 100, 200, 315, 400, 500, 630,800 and 1250kVA..
Page: 7 , 23-Mar-13
SECTION 6- LOSSES
SPECIFICATION TS-TR-01
EEPCO
5.11.4
Rated Voltage
The transformers are required to operate from the 15kV and 33 kV network as
follows:
.
.
Three-phase 4 wire LV
15,000/400-230 V
Three-phase 4 wire LV
33,000/400-230 V
.
All secondary voltage ratings shall be at full load current at nominal tap.
5.11.5
Vector Group
The vector group of the three-phase transformers shall be Dyn5..
5.11.6
5.12
Impedance Voltage
KVA
Rating
25
50
100 200
315 400
500
630 800
1250
% impedance
for15kV
4.5
4.5
4.5
5.0
5.5
5.5
% impedance
for33kV
4.5
4.5
4.5
5.0
5.0
6.0
6.0
6.0
6.5
6.5
6.
LOSSES
The maximum losses at rated load and conditions shall be as given below:
Rating
15kV Distribution
Transformer
33kV Distribution
Transformer
Rating (kVA)
No-load loss
Load loss
No-load loss
Load loss
25 Three Phase
150
570
150
570
50 Three Phase
220
1000
220
1000
360
1700
360
1700
Page: 8 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
200 Three Phase
600
2700
600
2700
820
3640
820
3640
400Three Phase
990
4500
990
4500
500Three Phase
1180
5400
1180
5400
630Three Phase
1450
6400
1450
6400
800Three Phase
1650
8000
1650
8000
2300
11000
2300
11000
The losses shall be stated and guaranteed in the technical specifications of the Bid.
Transformers with higher losses may be rejected. .
Should it be necessary for evaluation or other reasons losses will be capitalized at
the rates given below.
If the Bid currency is other than US$ the exchange rate at the time of bid
submission will be used.
If, on delivery, the tested losses exceed the guaranteed losses then losses in excess
of the guaranteed values may be capitalized at the evaluation rate and the amount
deducted from the contract price. There will be no credit for losses less than the
guaranteed value other than for evaluation purposes.
7.
TRANSFORMER TANKS
7.1
Page: 9 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
mesh against the entry of worms and nesting of birds. The diaphragm should
burst at a pressure between 0.76 kg/cm2 to 0.9 kg/cm2.
Gaskets used shall be oil resistant and made of such a material that no serious
deterioration occurs under service conditions. Rubber gaskets used for flange
connections of the various oil compartments shall be laid in grooves. Gaskets of
neoprene and/or such material which can be easily damaged by over-pressing (e.g.
any kind of impregnated/ bonded cork) are not acceptable. Use of hemp as gasket
material is also prohibited.
Heat dissipation by tank walls excluding top and bottom should be limited to 500
W/m2 up to the oil level, 250 Watts/m2 above oil level.
Lifting lugs: 4 Nos. Heavy duty suitable lifting lugs
Pulling lugs: 4 Nos. Heavy duty suitable horizontal pulling lugs.
All transformers shall be capable of giving their continuous rated output without
exceeding the specified temperature rise.
Galvanized fixing bolts, nuts and washers shall be supplied.
7.2
TANK BOTTOM
Thickness of tank bottom shall not be less than 4 mm.
7.3
CORROSION PROTECTION
The inner surfaces of the tank, and radiators shall be coated by an oil resistant
paint.
The smaller parts such as brackets, etc. shall be hot-dip galvanized. Fasteners
mounted on hot-dip galvanized or ready painted part shall be galvanized or made
of stainless steel ISO class F1 or A2.
All steel surfaces shall be sand blasted in accordance with DIN 55928 Part 4 and
shall then be painted in the following sequences.
Coat
Kind
Layer thickness
60m
One (1)
intermediate coat
Two-component polyurethane
40m
160
The final coat of painting shall be of pore free and homogeneous quality and shall
be of a uniform shade of code RAL 7032(silica grey) paint for the outside
surfaces. Manufactures are free to select the inner transformer paint colour
If any hot dipped galvanised parts are provided the same painting method shall be
applied, however instead of two primer coats one adhesive coat and one base coat
Page: 10 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
7.4
FILLING VALVES
A filling stub with an inner diameter of at least 25-mm shall be placed at the top
of the cover.
7.5
7.6
MONITORING DEVICES
Ground mounted transformers shall be equipped with an oil level indicator.
8.
TRANSFORMER OIL
The transformer shall be filled with oil before delivery. The oil shall contain at
least 0.3% by weight oxidation inhibitor of type Diter Butyl Para Bresol (DBPC)
according to IEC 60296.
Each transformer shall be supplied with standard insulating oil conforming to the
requirements of IEC 60137. The oil shall be new and satisfied to contain less than
1 ppm of PCBs. Each transformer shall be filled with the correct volume of oil at
the ambient temperature.
Mixing different products or products from different suppliers is not permissible.
Insulating liquid free of PCB and which can be mixed with insulating oil
corresponding to the Russian standard (type TK 1500) is to be used. The
manufacturer and type of insulating liquid used are to be indicated for each
transformer in the test report.
The type of insulating liquid, e.g. Mineral oil-based insulating oil pursuant to
DIN VDE 0370/relevant IEC is to be indicated on the rating plate of each
transformer..
Certification of the absence of PCB is to be submitted for each transformer.
9.
UNDERCARRIAGE
The following undercarriage shall be provided as specified in the technical
schedules.
Under frame for Pole mounted transformers
Transformers shall be fitted with an under frame suitable for bolting the
transformer to a pole mounted platform in case of pole mounted transformers. .
Under frame for Ground mounted transformers
The transformer shall be provided with skids welded to the underside of the tank
to facilitate transit over rough surfaces.
Page: 11 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
Welded to the tank on all sides; bi-directional rollers for longitudinal and
transverse travel.
The transformers should be delivered with the rollers fitted upside down. The
rollers must be stable enough to allow the transformer to be shifted at right angles
to the direction of travel.
10.
11.
EARTHING TERMINAL
Stainless steel or a galvanised mild steel earthing flag approximately 63 mm square
and a thickness not less than 6 mm with a centre hole of 14 mm diameter shall be
welded externally to the tank, one on the tank cover and one on the base frame.
12.
1V
1U
2V
2U
2W
2) Oil filling and drain valves. It shall only be possible to open these valves with a
special key/spanner to discourage tampering.
3) Tank earthing terminal. M12 size screws -2 Nos. one on the tank cover and
another on the base frame suitable for copper earthing wires.
4) Lifting fittings.
5) Oil level gauge
6) Pressure relief device
7) Oil level indicator.
Page: 12 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
13.
MARKING
Each transformer shall be provided with a rating plate showing the information
stated in the IEC standards. The plate shall be in both Amharic and English. The
words "Property of Ethiopian Electric Power Corporation", the EEPCO logo, the
contract number and loan number and a unique identification number (to be
advised by the Employer) shall also be engraved on the rating plate..
13.1
Page: 13 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
18) A diagram plate showing the internal connections and also the voltage vector
relationship of the several windings. In addition, a plan view of the transformer
giving the correct physical relationship of the terminals shall be given. When links
are provided for changing the transformer group symbol and/or ratio, then means
shall be provided for clearly indicating in which mode the transformer is
connected. The transformer ratio shall be indicated for each tap,
19) A property plate engraved to the instructions of the Engineer,
20) The above plates shall be of stainless steel or of other material capable of
withstanding continuous outdoor service and shall all be suitably mounted to
prevent vibration, rattling or corrosion.
14.
14.1
14.2
The LV CB can be either three single pole elements or a ganged three phase
unit.
Page: 14 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
The LV CB shall be closed and opened manually from the ground with a
suitable device (stick).
14.3
Page: 15 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
The LV circuit breaker shall have a set of auxiliary contacts built in for signal light
operation. These normally open contacts shall form part of the signal light
circuit.
The thermal sensing mechanism shall be set so that the signal light contacts will
close at a pre-set thermal condition, which occurs before the main latching
system opens the main contacts. This will provide for overload warning before
tripping.
The signal light mechanism does not reset itself when the load drops off; the
signal light remains energised once the signal light contacts close and can only be
turned off by manually operating the external circuit breaker handle.
14.4
15.
TRANSPORT
Irrespective of the actual method approved for transport to the individual site, all
transformers shall be suitable for transport with the transformers full of oil unless
otherwise approved.
The Contractor shall be responsible for ascertaining the methods and limitations
of transport to site and designs affected by these factors be subject to agreement.
16.
SCHEDULES
If the technical schedules are to be included in the same file then use this section.
16.1
Page: 16 , 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
16.2
Page: 1, 23-Mar-13
SPECIFICATION TS-TR-01
EEPCO
16.3
Page: 2, 23-Mar-13
LPA-GECE
EEPC
No
Item
I.
General
Manufacturer
Country of manufacture
Kind of installation
Unit
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Outdoor
pole mounted
Yes
Outdoor
Yes
Outdoor
pole mounted
Yes
Outdoor
pole mounted
Yes
Outdoor
pole mounted
Yes
pole mounted
No. of phases
three-phase
three-phase
Yes
three-phase
three-phase
Type of tank
Bolted Cover
Bolted Cover
Bolted Cover
Bolted Cover
Bolted Cover
No. of windings
Two
Two
Two
Two
Two
8
9
10
11
12
13
Dyn5
2.5
+2, -2
Yes
ONAN
Yes
Dyn5
2.5
+2, -2
Yes
ONAN
Yes
Dyn5
2.5
+2, -2
Yes
ONAN
Yes
Dyn5
2.5
+2, -2
Yes
ONAN
Yes
Dyn5
2.5
+2, -2
Yes
ONAN
Yes
14
II.
Ratings
Rated power
kVA
25
50
100
200
315
15
15.1
primary UN1
kV
15
15
15
15
15
15.2
secondary UN2
kV
0.4
0.4
0.4
0.4
0.4
16
Frequency
Hz
50
50
50
50
50
17
Principal tapping
kV
15
15
15
15
15
18
kV
24
24
24
24
24
19
4.5
4.5
4.5
20
HV Windings
20.1
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
20.2
Insulation
20.3
kV(rms) 50
50
50
50
50
20.4
kV(peak) 125
125
125
125
125
%
steps
Date: 23/03/2013,
LPA-GECE
No
Item
21
LV Windings
21.1
21.2
Insulation
21.3
22
22.1
23
EEPC
Tesla
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
max. 1.65
max. 1.65
max. 1.65
max. 1.65
max. 1.65
CRGO
CRGO
CRGO
CRGO
CRGO
45
45
45
45
45
30
30
30
Operation Details
24
30
30
25
25.1
25.2
C
C
55
60
55
60
55
60
55
60
55
60
25.3
68
68
68
68
68
26
150
220
360
600
820
27
570
1000
1700
2700
3640
28
29
kV
29.1
29.2
30
30.1
30.2
31
31.1
Primary
manufacturer
31.2
31.3
rated current
power frequency test level (at 1000 m)
A
kV
50
50
50
50
50
31.4
kV
125
125
125
125
125
31.5
mm
400
400
400
400
400
31.6
yes/no
Yes
Yes
Yes
Yes
Yes
31.7
creepage distance
mm
480
480
480
480
480
Date: 23/03/2013,
LPA-GECE
EEPC
No
Item
Unit
32
32.1
Secondary
Manufacturer
32.2
32.3
32.4
A
kV
32.5
32.6
kV
mm
32.7
32.8
33
34
35
36
kV
37
38
39
40
41
Heat-run test
42
dB(A)
43
43.1
43.2
43.3
43.4
43.5
43.6
43.7
43.8
43.9
43.1
43.11
kg
44
Drawing of dimensions
No.
45
Pamphlet
No.
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Yes
400
min. 8
Yes
400
min. 8
Yes
400
min. 8
Yes
630
min. 8
Yes
1000
min. 8
mm
60
60
60
60
60
kV,kA
18,10
18,10
18,10
18,10
18,10
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
Yes
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
Yes
Yes
Yes
Yes
Yes
kV
Yes
Yes
Yes
Yes
Yes
kV
on one unit
Yes
on one unit
Yes
on one unit
Yes
on one unit
Yes
on one unit
Yes
kV
Yes
Yes
Yes
Yes
Yes
on one unit
on one unit
on one unit
on one unit
on one unit
<44
<44
<44
<44
<44
steel
steel
steel
steel
steel
Gray
140
Gray
140
Gray
140
Gray
140
Gray
140
mm
mm
mm
mm
mm
mm
m
Date: 23/03/2013,
LPA-GECE
EEPC
No
Item
I.
General
Manufacturer
Country of manufacture
Kind of installation
4
5
Unit
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Outdoor
Outdoor
pole mounted
Yes
three-phase
6
7
Type of tank
No. of windings
Bolted Cover
Two
Bolted Cover
8
9
10
Number of steps
steps
11
12
13
19
20
20.1
20.2
20.3
Insulation
Power frequency withstand voltage
20.4
14
15
15.1
15.2
16
17
18
Outdoor
pole mounted
Yes
Yes
Outdoor
pole mounted
Yes
three-phase
Outdoor
pole mounted
Yes
three-phase
Two
Bolted Cover
Two
Bolted Cover
Two
Bolted Cover
Two
Dyn5
2.5
Dyn5
2.5
Dyn5
2.5
Dyn5
2.5
Dyn5
2.5
+2, -2
+2, -2
+2, -2
+2, -2
+2, -2
Yes
ONAN
Yes
Yes
ONAN
Yes
Yes
ONAN
Yes
Yes
ONAN
Yes
Yes
ONAN
Yes
kVA
400
500
630
800
1250
kV
kV
Hz
kV
kV
15
0.4
50
15
24
15
0.4
50
15
24
15
0.4
50
15
24
15
0.4
50
15
24
15
0.4
50
15
24
5.5
5.5
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
kV(rms) 50
50
50
50
50
kV(peak) 125
125
125
125
125
pole mounted
Yes
three-phase
Date: 23/03/2013,
LPA-GECE
No
Item
21
21.1
LV Windings
Material, wire or strip
21.2
Insulation
21.3
29.1
29.2
30
30.1
22
22.1
23
24
25
25.1
25.2
25.3
26
27
28
29
EEPC
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
max. 1.65
max. 1.65
max. 1.65
max. 1.65
max. 1.65
CRGO
CRGO
CRGO
CRGO
CRGO
C
C
45
30
45
30
45
30
45
30
45
30
C
C
C
W
W
kV
55
60
68
990
4500
55
60
68
1180
5400
55
60
68
1450
6400
55
60
68
1650
8000
55
60
68
2300
11000
Tesla
30.2
31
31.1
IV.
Bushings
Primary
manufacturer
31.2
31.3
rated current
power frequency test level (at 1000 m)
A
kV
50
50
50
50
50
31.4
kV
125
125
125
125
125
31.5
mm
400
400
400
400
400
31.6
yes/no
Yes
Yes
Yes
Yes
Yes
31.7
creepage distance
mm
480
480
480
480
480
Date: 23/03/2013,
LPA-GECE
No
EEPC
Unit
32
32.1
Secondary
Manufacturer
32.2
32.3
32.4
32.5
32.6
32.7
32.8
33
34
35
36
37
38
39
40
41
Heat-run test
42
43
43.1
43.2
43.3
height
mm
43.4
43.5
depth
width
mm
mm
43.6
43.7
43.8
43.9
43.1
mm
mm
mm
43.1
44
45
m
No.
No.
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Yes
1500
min. 8
Yes
1500
min. 8
Yes
2000
min. 8
Yes
2000
min. 8
Yes
>2500
min. 8
60
18,10
60
18,10
60
18,10
60
18,10
60
18,10
on each unit
on each unit
on each unit
on each unit
Yes
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
on each unit
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
on one unit
on one unit
on one unit
on one unit
on one unit
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
on one unit
on one unit
on one unit
on one unit
on one unit
<44
<44
<44
<44
<44
steel
steel
steel
steel
steel
Gray
Gray
Gray
Gray
Gray
140
140
140
140
140
A
kV
kV
mm
mm
kV,kA
kV
kV
kV
dB(A)
kg
Date: 23/03/2013,
LPA-GECE
EEPC
No
Item
I.
General
Manufacturer
Country of manufacture
Kind of installation
4
5
6
Unit
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
Outdoor
Outdoor
pole mounted
Yes
three-phase
Bolted Cover
7
8
9
No. of windings
Vector group symbol
Tapping range
Two
Two
Dyn5
2.5
10
Number of steps
steps
11
12
13
14
15
II.
Ratings
Rated power
Nominal system voltage
Outdoor
pole mounted
Yes
Yes
Bolted Cover
Outdoor
pole mounted
Yes
three-phase
Bolted Cover
Outdoor
pole mounted
Yes
three-phase
Bolted Cover
Dyn5
2.5
Two
Dyn5
2.5
Two
Dyn5
2.5
Two
Dyn5
2.5
+2, -2
+2, -2
+2, -2
+2, -2
+2, -2
Yes
ONAN
Yes
Yes
ONAN
Yes
Yes
ONAN
Yes
Yes
ONAN
Yes
Yes
ONAN
Yes
kVA
25
50
100
200
315
kV
33
33
33
33
33
kV
Hz
0.4
50
0.4
50
0.4
50
0.4
50
0.4
50
17
18
19
kV
kV
%
33
45
4.5
33
45
4.5
33
45
4.5
33
45
5
33
45
5
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
95
95
95
95
95
250
250
250
250
250
Principal tapping
Maximum Continuous System withstand Voltage
Impedance voltage at rated power
20
HV Windings
20.1 Material, wire or strip
pole mounted
Yes
three-phase
Bolted Cover
20.2 Insulation
Date: 23/03/2013,
LPA-GECE
No
21
EEPC
Unit
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
LV Windings
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
max. 1.65
max. 1.65
max. 1.65
max. 1.65
max. 1.65
CRGO
CRGO
CRGO
CRGO
CRGO
45
45
45
45
45
30
30
30
30
30
C
C
55
60
55
60
55
60
55
60
55
60
68
68
68
68
68
26
150
220
360
600
820
27
570
1000
1700
2700
3640
28
29
kV
21.2 Insulation
21.3 Magnetic flux density (at rated voltage and
frequency)
22
Core Material
Tesla
III.
Operation Details
Ambient temperature (max.)
24
25
25.1
25.2
30.1
30.2
31
Bushings
Primary
31.1 manufacturer
31.2 rated current
kV
95
50
50
50
50
kV
250
250
250
250
250
mm
400
400
400
400
400
yes/no
Yes
Yes
Yes
Yes
Yes
mm
1040
1040
1040
1040
1040
Date: 23/03/2013,
LPA-GECE
No
32
EEPC
Unit
Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer Requirement Bid Offer
1040
Secondary
32.1 Manufacturer
32.2 type (DIN type or eqvt.)
32.3 rated current
32.4 power frequency test level (at 1000 m)
A
kV
Yes
400
min. 8
Yes
400
min. 8
Yes
400
min. 8
Yes
630
min. 8
Yes
1000
min. 8
kV
mm
mm
kV, kA
60
36,10
60
36,10
60
36,10
60
36,10
60
36,10
on each unit
Yes
on each unit
Yes
on each unit
on each unit
on each unit
Yes
on each unit
on each unit
on each unit
Yes
on each unit
on each unit
on each unit
Yes
33
34
35
36
V.
Tests
Routine tests: IEC 60076 and Specifications
Separate source over-voltage withstand test
Induced overvoltage withstand test,
test voltage / primary (tap 1) (IEC test standard)
kV
on each unit
on each unit
on each unit
Yes
37
kV
Yes
Yes
Yes
Yes
Yes
38
39
40
41
42
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
43
Transformer tank,material
steel
steel
steel
steel
steel
43.1
43.2
43.3
43.4
43.5
43.6
43.7
43.8
43.9
43.1
43.1
Top, mm
Bottom, mm
Sides, mm
Colour of transformer
Thickness of surface treatment
Gray
140
Gray
140
Gray
140
Gray
140
Gray
140
44
Drawing of dimensions
No.
45
Pamphlet
No.
kV
kV
dB(A)
kg
mm
mm
mm
Date: 23/03/2013,
LPA-GECE
EEPC
No
Item
I.
Unit
Requirement
Bid Offer
Requirement
Bid Offer
Requirement
Bid Offer
General
Manufacturer
Country of manufacture
Kind of installation
4
5
Outdoor
Outdoor
pole mounted
Yes
three-phase
Type of tank
No. of windings
Tapping range
10
11
12
13
Number of steps
Continuous power at all taps
Cooling method
Specification of oil ( 60296)
14
II.
Ratings
Rated power
15
three-phase
Outdoor
pole mounted
Yes
Yes
Outdoor
pole mounted
Yes
three-phase
Outdoor
pole mounted
Yes
three-phase
Bolted Cover
Bolted Cover
Bolted Cover
Bolted Cover
Bolted Cover
Two
Two
Two
Two
Two
Dyn5
Dyn5
Dyn5
Dyn5
Dyn5
2.5
2.5
2.5
2.5
2.5
steps
+2, -2
Yes
ONAN
Yes
+2, -2
Yes
ONAN
Yes
+2, -2
Yes
ONAN
Yes
+2, -2
Yes
ONAN
Yes
+2, -2
Yes
ONAN
Yes
kVA
400
500
630
800
1250
kV
33
33
33
33
33
kV
0.4
0.4
0.4
0.4
0.4
16
Frequency
Hz
50
50
50
50
50
17
Principal tapping
kV
33
33
33
33
33
18
kV
45
45
45
45
45
6.5
6.5
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
95
95
95
95
95
250
250
250
250
250
19
Impedance voltage at rated power
20
HV Windings
20.1 Material, wire or strip
20.2 Insulation
20.3 Power frequency withstand voltage, kV(rms)
20.4 Rated lightning, impulse withstand voltage,
kV(peak)
pole mounted
Yes
10
Date: 23/03/2013,
LPA-GECE
No
21
LV Windings
EEPC
Unit
Requirement
Bid Offer
Requirement
Bid Offer
Requirement
Bid Offer
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
Copper
wire/strip
max. 1.65
max. 1.65
max. 1.65
max. 1.65
max. 1.65
CRGO
CRGO
CRGO
CRGO
CRGO
45
45
45
45
45
30
30
30
30
30
55
55
55
55
55
25.2
25.3
26
27
28
29
C
C
W
W
kV
60
68
990
4500
60
68
1180
5400
60
68
1450
6400
60
68
1650
8000
60
68
2300
11000
21.2 Insulation
21.3 Magnetic flux density (at rated voltage and
frequency)
22
Core Material
22.1 Core Loss figure, Watt/kg
III.
Operation Details
23
Ambient temperature (max.)
24
25
29.1
29.2
30
30.1
30.2
31
31.1
windings / average
windings hot spot
No-load loss at rated voltage and frequency
Full load loss ,W
Rated voltage at full load (P.F=0.95)
Efficiency referred to 75oC at rated voltage and
frequency
100% rated output and P.F= 1 (%)
100% rated output and P.F= 0.95 (%)
No load current as percent of rated current
at 90% voltage (%)
at 100% voltage (%)
IV.
Bushings
Primary
manufacturer
Tesla
A
kV
95
95
95
95
95
kV
250
250
250
250
250
mm
400
400
400
400
400
yes/no
Yes
Yes
Yes
Yes
Yes
mm
480
480
480
480
480
11
Date: 23/03/2013,
LPA-GECE
No
32
Secondary
32.1 Manufacturer
32.2
32.3
32.4
32.5
32.6
32.7
32.8
EEPC
33
34
35
36
37
38
39
40
41
42
Unit
A
kV
kV
mm
mm
kV,kA
kV
kV
kV
kV
dB(A)
Requirement
Bid Offer
Requirement
Bid Offer
Requirement
Bid Offer
Yes
1500
min. 8
Yes
1500
min. 8
Yes
2000
min. 8
Yes
2000
min. 8
Yes
>2500
min. 8
60
36,10
60
36,10
60
36,10
60
36,10
60
36,10
on each unit
on each unit
on each unit
Yes
Yes
on each unit
Yes
on each unit
Yes
Yes
on each unit
on each unit
on each unit
Yes
Yes
on each unit
on each unit
on each unit
Yes
Yes
on each unit
on each unit
on each unit
Yes
Yes
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
on one unit
Yes
Yes
on one unit
<44
steel
steel
steel
steel
steel
Gray
140
Gray
140
Gray
140
Gray
140
Gray
140
Transformer tank,material
kg
43.3
height
mm
43.4
depth
mm
43.5 width
mm
m
No.
No.
12
Date: 23/03/2013,
EEPCO
SPECIFICATION
TS-TR-02
15 kV Compact Substation
SPECIFICATION TS-TR-02
EEPCO
Date
Brief Description
Rev 0
Dec 2012
First Issue
Rev 1
Feb 2013
Rev 2
April 2013
SPECIFICATION TS-TR-02
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
TYPE TEST:
ROUTINE TEST
ACCEPTANCE TEST
2
2
2
5.
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
5.13
5.14
5.15
GENERAL
DESCRIPTION OF OUTER HOUSING
ELECTRICAL INTERCONNECTIONS
EARTHING
CORROSION PROTECTION
TANK BOTTOM
RATING, DIAGRAM AND PROPERTY PLATES
LIGHTING
VENTILATION
DOORS AND WALLS
DOOR LOCKS
NOISE LEVEL
MOUNTING ARRANGEMENT
LIFTING LUGS
COLOUR
3
4
5
5
6
6
6
7
7
7
7
7
7
7
8
6.
MV COMPARTMENT
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
ELECTRICAL DATA
LOAD BREAK SWITCH
TRANSFORMER BREAKER
PROTECTION RELAYS
BUSHINGS
CABLE TERMINATIONS
EARTH FAULT INDICATOR
EARTHING
ACCESSORIES
8
8
8
9
9
9
9
10
10
7.
TRANSFORMER COMPARTMENT
10
7.1
7.2
7.3
7.4
7.5
GENERAL
TRANSFORMER TYPE
VOLTAGE RATIOS
RATINGS
TEMPERATURE RISE
10
10
10
10
10
SPECIFICATION TS-TR-02
EEPCO
7.6
7.7
7.8
7.9
7.10
7.11
11
11
12
12
12
13
8.
13
8.1
13
9.
10.
SPARE PARTS
DOCUMENTS TO BE SUBMITTED
15
15
10.2
10.3
10.4
10.5
10.6
15
16
16
16
16
11.
12.
13.
PACKING
TRANSPORT
SCHEDULES
13.1
13.2
13.3
14.
SCHEDULES
17
14.1
14.2
14.3
17
18
19
16
16
ERROR! BOOKMARK NOT DEFINED.
SECTION 1 - SCOPE
SPECIFICATION TS-TR-02
EEPCO
15 KV COMPACT SUBSTATIONS
1.
SCOPE
This specification specifies deign performance and general requirements for
outdoor Transformer compact substations for 15kV distribution network.
2.
3.
REFERENCE STANDARDS
The requirements of the following standards / specifications shall be met where
applicable unless otherwise stated in this specification.
Specification/
Standard Number
Title
IEC 61330
IEC 60076
Power Transformers
IEC 60354
IEC 60317
IEC 60137
IEC 60521
IEC 60551
IEC 60296
IEC 60722
IEC
60282-1, MCCBs
DIN VDE 0670-4
and DIN 43625
3.1
CONFLICT
See Specification TS-GN-02 General contractual Obligations
4.
SPECIFICATION TS-TR-02
EEPCO
4.1
TYPE TEST:
4.1.1
GENERAL
The type tests as per the relevant standard shall be conducted on the prefabricated
compact substations of identical design to prove that the offered equipment
satisfies all the design requirements set out in this specification.
In addition to testing of the complete substation according to the relevant IEC
standard, the transformer measurements and tests shall be carried out as
mentioned in Spec No. TS-TR-01.
4.2
ROUTINE TEST
These tests shall be carried out on each individual of the equipment offered as per
IEC at the manufactures works to ensure that the product is in accordance with
the requirements of this specification.
These tests shall include:
Winding:
15kV
LV
Voltage
50kV
3kV
a)
b)
Resistance test,
c)
No-load test,
d)
Short-circuit test,
e)
f)
g)
A test report containing the test results is to be drawn up for each transformer.
4.3
ACCEPTANCE TEST
The Acceptance test procedure for any delivery of the equipments are as follows:
a)
Visual inspection,
b)
c)
Checking of the result of the routine and type test as per IEC,
d)
e)
SPECIFICATION TS-TR-02
EEPCO
4) measurement of load loss and impedance voltage with the off circuit tap changer
in the normal position,
5) Measurement of the insulation resistance (oil, paper and press board) between
high voltage and low voltage, and tank (Meggar test),
The Corporation reserves the right to apply, penalty or reject particular equipment
in the event of non-compliance with the guaranteed losses.
5.
5.1
GENERAL
The compact substation shall be outdoor type comprising
SPECIFICATION TS-TR-02
EEPCO
5.2
5.2.1
Protection degrees:
The minimum Protection index which ensures the direct- contact protection of
each compartment is specified as follows:
MV compartment
IP43
Transformer compartment
IP23
SPECIFICATION TS-TR-02
EEPCO
LV compartment
5.2.2
IP23
Surface area
The design of the compact substation shall be such that it occupies minimum
space. The design concept is to use the substation is confined spaces.
5.3
ELECTRICAL INTERCONNECTIONS
Electrical connections to the Transformer shall be so designed that these may be
disconnected and re-connected at Site to facilitate the removal of any major
component of the unit. The inter-connection between 15kV Switchgear and
Transformer Terminals Bushings shall be by means of minimum 50 sq.mm for
sizes up to 1250kVA with plug-in type connection, of an acceptable make.
The connection between Transformer LV Bushing and the Feeder Pillar shall be
by means of flexible copper busbars passing through an air-insulated duct/flange.
5.4
EARTHING
5.4.1
General
Each unit Substation assembly shall be provided with copper Earth Bar of 40mm
x 5mm to which the Transformer LV neutral and metal frames of all items i.e.
H.V. Switchgear, Transformer and Feeder Pillar shall be connected. Two-earth
terminal shall be provided for connection to the external earthing system.
5.4.2
SPECIFICATION TS-TR-02
EEPCO
5.5
CORROSION PROTECTION
The Compact Substation housing shall be hot-dip galvanized. Galvanizing shall
consist of a continuous coating of zinc to a minimum weight of 600 g/m. The
zinc coating shall meet the requirements according to ASTM, A123, A143, A239
and A385. Other type of corrosion protection that can be shown to give a similar
protection as hot-dip galvanizing may be accepted after special agreement.
5.6
TANK BOTTOM
Thickness of housing bottom shall not be less than 4 mm.
5.7
A rating plate bearing the data specified in IEC or other approved standard
indicating the following shall be fixed on the same side as LV bushings.
b)
Name of manufacturer
c)
d)
Year of manufacture
e)
Rated power
f)
Rated frequency
g)
Rated voltages
h)
Rated currents
i)
j)
Short-circuit impedance
k)
Total mass
l)
m)
Insulation level
n)
Each bushing shall be marked with the name or trademark of the manufacturer.
o)
A diagram plate showing the internal connections and also the voltage vector
relationship of the several windings and in addition a plan view of the transformer
giving the correct physical relationship of the terminals. When links are provided
for changing the transformer group symbol and/or ratio, then means shall be
provided for clearly indicating in which mode the transformer is connected.
p)
SPECIFICATION TS-TR-02
EEPCO
5.8
LIGHTING
HV, LV and Transformer compartments shall each be fitted with a florescent
lamp controlled from door-operated switch. The lamp shall be combined with an
accumulator-cum-charger and shall be installed in such position to illuminate the
respective compartment.
5.9
VENTILATION
Adequate ventilation for natural circulation of air shall be provided to keep the
inside temperature within the limit. Ventilation apertures shall be suitably screened
and louvered to prevent the entry of vermin, dust and other foreign bodies.
5.10
5.11
DOOR LOCKS
The doors shall be securely closed and then locked close with padlocks.
Each access door shall have arrangements to lock with a handle and secured
closed with a padlocks. Suitable door handles shall be fitted to the door.
Padlocks of a top quality make with a master key system shall be provided with
each unit including one spare padlock. The master key shall be advised by the
client.
The client is already using a master key system and the same shall be applied in
this compact substation.
5.12
NOISE LEVEL
The noise level of the completely assembled package Substation shall not exceed
70 dbA, when measured one (1) meter far from package unit housing in
accordance with IEC 60551. The package Substation shall be checked after
assembly to ensure that no rattling of individual components can occur.
5.13
MOUNTING ARRANGEMENT
The package Substation shall not require casting of concrete plinth at Site. Site
preparation shall be limited to levelling only.
5.14
LIFTING LUGS
Lifting lugs shall be provided so that the completely assembled package
Substation may be lifted without damage. The lifting lugs shall be designed to
carry the weight of the Substation complete with Transformer and switchgear.
Required number of lifting spread beams shall be supplied with each unit.
SPECIFICATION TS-TR-02
EEPCO
5.15
SECTION 6 - MV COMPARTMENT
COLOUR
The surface colour of HV and LV Switchgear, Transformer and Housing shall be
RAL 7032 light grey.
6.
MV COMPARTMENT
The medium voltage switchgear is gas insulated, consisting of cable switches
disconnector (Load break switch) and transformer T-off with VCB. For other
particulars spec no.TS-SG-12 may be referred.
All individual switches shall be lockable in open position with padlock.
The switchgear shall be sealed for life. The Spring Mechanisms shall be of longlife corrosion resistant material and dust proof. Degree of Protection shall not be
less than IP54.
6.1
ELECTRICAL DATA
Ratedvoltage
15kV
HighestsystemVoltage
24kV
Numberofphases
Three
RatedFrequency
50Hz
RatedShorttimeWithstandcurrentfor1s
20kA
Powerfrequencywithstandvoltage
50kV
125kV
LightningImpulsewithstandVoltage(1.2/50s)
6.2
6.3
TRANSFORMER BREAKER
A transformer breaker shall be provided to protect and control the disitribution
transformer.
The Transformer breaker unit shall be fault-making and fault-breaking Tee-off
vacuum/SF6 circuit breaker. The CB shall have Trip Coil also connected to
Temperature Indicator of the Transformer to protect the Transformer against
over loading.
The HRC Fuse shall comply with the requirement of IEC 282. Dimensions shall
be as per DIN 43625. Details of tripping mechanism, tripping characteristics and
applicable setting shall be submitted with the Bid
SPECIFICATION TS-TR-02
EEPCO
6.4
SECTION 6 - MV COMPARTMENT
PROTECTION RELAYS
The circuit Breaker shall be equipped with self-powered numerical relay with
operating temperature of 5oC to +70oC, for OC/SC and E/F protection, which
can be adjusted to suit different Transformer capacities. The relay shall protect the
system from transformer faults, transformer through faults and transformer
overload.
6.5
BUSHINGS
MV bushings shall be rated to withstand the highest system voltage of 24 kV and
the maximum fault current of the windings when connected to the 15kV network
and for the same period of time. Current carrying outer parts shall be made of
copper or copper alloy.
Each bushing shall be marked with manufacturer name and type. The marking
shall be visible after assembly of the fittings.
The outer creepage distance for outdoor bushings shall not be less than 20
mm/kV. The insulation levels of the bushings shall be at least equal to those
specified for the windings.
6.6
CABLE TERMINATIONS
The cable boxes for Ring Circuits shall be suitable for accommodating 3 core or
single core cross-linked polyethylene insulated PVC sheathed over the range of
100 sq.mm to 240 sq.mm Copper or aluminium Conductor for Feeders.
The box shall be designed for air-insulated dry type heat shrinkable termination.
The design shall provide sufficient space for crossing of cores without damage to
core insulations. Cable glands and heat shrinkable termination kits of acceptable
make shall be supplied with the unit.
For Transformer Control Switch plug-in type Terminations of an acceptable
make, suitable for 50 sq.mm Single Core Cable shall be supplied.
6.7
SPECIFICATION TS-TR-02
EEPCO
6.8
SECTION 7 - TRANSFORMER
COMPARTMENT
EARTHING
Each unit assembly shall be provided with copper earth bar 40mm x 5mm, the
metal frames of all items shall be connected to one another firmly. Two earth
terminals shall be provided for connecting to the station earthing system.
6.9
ACCESSORIES
Each unit shall be supplied with the following accessories:
Voltage Indicator lamps fixed on the front of the panel for both feeder
switches.
7.
TRANSFORMER COMPARTMENT
7.1
GENERAL
This section specifies the detailed requirements for distribution transformers,
complete with necessary fittings for 15/0.4kV Compact substations.
The transformer shall conform to the technical specification No.TS-TR-01. A
technical schedule TS-TR-01-S shall be completed for the transformer for ground
mounted substation.
7.2
TRANSFORMER TYPE
The transformer shall be hermetically sealed, tank type, ONAN naturally cooled,
skid mounted, un-inhibited mineral oil immersed, core type and copper windings
suitable for operation outdoor in exposed location. The Transformer oil shall
confirm to BS 148 Class 1 Category / IEC 296.
7.3
VOLTAGE RATIOS
The normal voltage ratio of the Transformer on normal tapping and no-load shall
be 15 /0.4 kV.
7.4
RATINGS
The Transformer rated kVA shall be the continuous steady load rating under the
specified temperature and humidity without exceeding the average temperature
rise limits given in specification TS-GN-01.
The full rating shall be at the rated output voltage with rated input voltage.
7.5
TEMPERATURE RISE
The Transformer shall be capable of carrying full rated current continuously
under the maximum specified ambient temperature at any tapping, without the
temperature rise of oil at top exceeding 45 degree C, as measured by thermometer
and of the winding not exceeding 55 degree C and of the hot spot not exceeding
60 degree C, as measured by resistance calculations demonstrating the above shall
be submitted with the Bid.
SECTION 7 - TRANSFORMER
COMPARTMENT
SPECIFICATION TS-TR-02
EEPCO
7.6
7.7
7.7.1
Accessories
At least the following accessories shall be included for the transformer:
a)
b)
c)
d)
Oil thermometer
e)
7.7.2
Electrical Design
The transformer windings shall be designed to meet the following electrical
characteristics:
Nominal System voltage
15kV
24 kV
400 V
System frequency
50 Hz
Vector group
Dyn5
125 kV
windings
Power frequency withstand voltage for MV windings
50kV
3 kV
windings
7.7.3
400
500
630
800
1250
15
15
15
15
15
SECTION 7 - TRANSFORMER
COMPARTMENT
SPECIFICATION TS-TR-02
EEPCO
7.7.4
5.5
5.5
Sound level dB
51
53
53
54
56
Guaranteed values
The following values are guaranteed by the manufacturer as stipulated in the
guaranteed characteristic table.
1) No-load loss
2) Load loss
3) No-load current
4) short-circuit impedance
5) Voltage ratio
7.8
7.9
BUSHINGS SPACING
Transformers shall have the bushings for HV and LV which fulfil the
requirements of IEC 60137
Minimum Distances between bushings
7.10
HV
400 mm 50mm
LV
150 mm 50mm
EMERGENCY LOADING
The Tenderer shall demonstrate by calculation, the ability of the Transformer to
operate under emergency loading condition as per IEC 354 for the following
loading and ambient temperature conditions listed below with Transformer
winding hot spot temperature not exceeding 40 degree C, after thermal
equilibrium has been reached at rated load.
Transformer bushing, tap changer and terminations shall also be suitably rated for
over loading as specified in IEC 60354.
Load
(% of Rating)
40 Degree C
55 Degree C
120
ts-tr-02 r2 compact substations 2013-04-28.docx
SPECIFICATION TS-TR-02
EEPCO
130
150
7.11
LOSSES
The maximum losses at rated load and conditions shall be as given below:
Rating kVA
400
990
4500
500
1180
5400
630
1450
6400
800
1650
8000
1250
2300
11000
The losses shall be stated and guaranteed in the Bid technical specifications (no
tolerance is permitted). For evaluation or other reasons losses will be capitalized at
the rates given below.
No Load Loss : US$ 4000 per kilowatt.
Load Loss : US$ 1000 per kilowatt.
If, on delivery, the tested losses exceed the guaranteed losses then losses in excess
of the guaranteed values may be capitalized at the evaluation rate and the amount
deducted from the contract price. There will be no credit for losses less than the
guaranteed value.
8.
8.1
8.1.1
Busbars
Set of busbars of hard drawn, high conductivity, tinned copper and rigidly
supported. The busbars to be positioned to give maximum access and shall be
colour coded for identification by shrinkable insulating tube. The size of the
busbars shall be stated in the Bid as (Cross-section Area sq.mm).
SPECIFICATION TS-TR-02
EEPCO
8.1.2
LV Incoming Isolator
One incoming unit with hook operated slow make and break off load hinged
isolating switch-blade on each phase for control of the Transformer supply.
Switch- blades shall be fitted with contact tightening clamps. It shall be possible to
leave the incoming isolators open LIVE with the door closed.
8.1.3
MCCBs
The 0.4 kV switchgear shall be air insulated Moulded Case Circuit Breakers
(MCCB) for the outgoing circuits. See specification TS-SG-03 for full details
The outgoing feeder MCCB complete with overload and short circuit protection
with ratings specified in the schedule of requirements are connected to the bus
bars.
Required numbers as specified in Schedule of Bill of Quantities of 3 x MCCBs.
A separate MCCB shall be provided for street lighting.
A blank circuit label to be provided on each unit.
8.1.4
CTs
On each phase current Transformer shall be provided for operation of
instruments.
8.1.5
Energy Meter
The required wiring for connecting one electronic trivector meter at a future date
shall be complete and space made available. All wiring shall be terminated at a
meter terminating block to enable future meter installation and easy connection
8.1.6
Ameter
Three Single-Phase Ammeters with instantaneous elements plus maximum
current demand indicators of the thermal type. The ammeters shall be suitable for
operation from the current Transformers specified. The maximum demand
element shall be compensated for 55 degree Celsius ambient temperature.
8.1.7
Voltmeter
One Voltmeter 0-500V with phase selector switch.
8.1.8
Light fitting
One Light Fitting for cubicle illumination complete with a door operated switch.
The maximum demand indicator voltmeters, selector switch and light fitting to be
mounted on an instrument panel.
8.1.9
Earth Bar
An Earth Bar not less than 50mm x 10mm shall be provided at the bottom and
secured so as to give a positive electrical connection. In addition, two 12mm with
Earth terminal shall be provided on the pillar shell and connected to the earth bar.
A detachable link between neutral and earth bar shall also be provided.
8.1.10
Cable Glands
The cable glands shall be brass or stainless steel compression type as per BS
suitable for the bales provided for the LV system. The glands shall be supplied
SPECIFICATION TS-TR-02
EEPCO
complete with earth tag PVC shrouds. Cross sectional details of the cable will be
supplied to the successful Tenderers. Earth tag of each gland shall be connected
to earth bar with tinned copper flexible earthing braid of adequate cross section
having at lest 50 % of that of the phase conductor of the cable to be connected.
Each cable gland shall be supported on a removable gland plate.
8.1.11
Miscellaneous
All instrument wiring shall be 2.5 sq.mm stranded copper conductor, 600 Volt
tropical grade PVC insulated.
The Base Plate of the feeder pillar shall be supplied with knockout holes.
Necessary Nuts, Bolts for cable lugs, spacers, etc., shall be supplied fitted with
feeder pillar. Cable clamps shall be provided at the bottom of the feeder pillar to
hold the cables in position.
The gland plate of the feeder pillar shall be so positioned to allow convenient
bend on the cable.
Cable glands with earth tag and plastic shrouds, cable lugs and fuses shall be
delivered separately.
9.
SPARE PARTS
Different items ordered against spares shall be packed in separate casing with item
number and quantity clearly marked.
10.
DOCUMENTS TO BE SUBMITTED
Prior to the tests the Contractor shall submit an outline of the procedures and
tests in its plans, to demonstrate fulfilment of the requirements specified in
subsequent sections of the detailed technical specification.
During the course of fabrications, tests shall be made on samples not less than 5%
of the respective items.
The Tenderer must submit all technical descriptions, data sheets, catalogues and
other supporting material with the Offer to enable the Purchasers Engineer to
fully evaluate the proposal as to its compliance with the Tender Specification. As a
minimum the Tenderer shall submit the following:
1) Technical Schedules.
2) Copies of required Type Test Certificates.
3) ISO 9000 certification and its relevant parts.
4) All drawings and information called for by this Specification, including:
10.2
SPECIFICATION TS-TR-02
EEPCO
10.3
SECTION 11 - PACKING
10.4
LV COMPARTMENT
1) Details and characteristics of MCCBs.
2) Drawing Showing the Internal Arrangement of Feeder Pillar.
10.5
HOUSING
Construction details of the Housing.
10.6
GENERAL
1) Original Brochures and Catalogues for Standard Unit.
2) Applicable Design Specification.
3) Lists of Accessories included in the Bid.
11.
PACKING
The Compact Substations shall be packed in sea-worthy solid wall wooden cases
in a manner to avoid damage during transport, handling and storage. They shall
also be packed in such a way that no corrosion occurs on the equipments due to
salty moisture when stored at the port of destination.
Each package shall be marked with the main details of the equipment contained
therein, the type designation or the catalogue number and with the manufacturer's
name or trademark.
Each wooden case shall be clearly marked with the address of EEPCO and the
relevant contact number and title. All markings shall be legible and durable.
Bushing units shall be packed in a manner to avoid damage during transport,
handling and storage.
12.
TRANSPORT
Irrespective of the actual method approved for transport to the individual site, all
transformers shall be suitable for transport with the transformers full of oil unless
otherwise approved.
The Contractor shall be responsible for ascertaining the methods and limitations
of transport to site and designs affected by these factors be subject to agreement.
SECTION 13 - SCHEDULES
SPECIFICATION TS-TR-02
EEPCO
13.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
13.1
Item
Unit
Requirement
Bid Offer
General
1.1
1.2
1.3
1.4
1.5
2
2.1
2.2
2.3
2.4
2.
3
3.1
3.2
4
4.1
4.2
4.3
4.4
5
5.1
5.2
5.3
5.4
5.5
SECTION 13 - SCHEDULES
SPECIFICATION TS-TR-02
EEPCO
13.2
SECTION 13 - SCHEDULES
SPECIFICATION TS-TR-02
EEPCO
13.3
LPA-GECE
EEPCo
Nos.
No
Item
1.1
Manufacturer
IEC 61330
IEC 61330
IEC 61330
IEC 61330
IEC 61330
1.2
Country of origin
1.3
Type designation
1.4
Standard
1.5
1.6
1.7
1
1
1
1
1
1
1
1
1
1
1.8
II
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
Size of cubicle
Type
Protection class
Service voltage(kV)
Equipment Highest Voltage kV
Frequency, Hz
Insulation level
Power frequency withstand voltage,
Rated lightning, impulse withstand
Rated short-time withstand current for
IP
kV
kV
Hz
IP43
15
24
50
IP43
15
24
50
IP43
15
24
50
IP43
15
24
50
IP43
15
24
50
kV
kV
kV
50
125
20
50
125
20
50
125
20
50
125
20
50
125
20
2.11
2.12
2.13
2.14
A
kA
Vacuum
200
20
2.15
2.16
2.17
400
400
400
400
50
400
Page 1
Date: 28/4/2013,
LPA-GECE
No
Item
III
3.1
3.2
3.3
3.4
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
3.17
3.18
3.19
3.20
3.21
3.22
3.23
3.24
3.25
3.26
3.27
3.28
3.29
3.30
Type
Quantity
Current range, A
Voltmeter
Type
Quantity
Voltage range,V
3.5
3.6
3.7
3.8
EEPCo
IP
A
IP23
Min. 1500
4
IP23
Min. 1500
5
IP23
Min. 2000
6
IP23
Min. 2000
8
IP23
Min. 3000
8
0.4
50
3 for one
minute
kV peak
6
0.4
50
3 for one
minute
6
0.4
50
3 for one
minute
6
0.4
50
3 for one
minute
6
0.4
50
3 for one
minute
6
0.4
400
50
12
0.4
400
50
15
0.4
400
50
18
0.4
400
50
24
0.4
400
50
24
Ring type
3
400
800/5
50
Ring type
3
400
1000/5
50
Ring type
3
400
1200/5
50
Ring type
3
400
2000/5
50
Ring type
3
400
2500/5
50
1
0-400-800
1
0-500-1000
1
0-600-1200
1
0-1000-
1
0-1000-
1
0-800
1
0-1000
1
0-1200
1
0-2000
1
0-2500
1
0-500
1
0-500
1
0-500
1
0-500
1
0-500
kV
HZ
kV rms
kV
A
kA
No
V
A
Hz
VA
Page 2
Date: 28/4/2013,
LPA-GECE
No
Item
3.31
IV
4.1
4.2
Transformer compartment
Protection class
Technical characteristics of the
distribution transformer
Method of cooling
No. of phases
Standard
Frequency, Hz
Rated Continuous Power, kVA
On HV side
On LV side
Rated Voltage, kV
On HV side
On LV side
Connections (Vector Group)
No-load loss at rated voltage and
frequency, W
Full load loss ,W
Rated voltage at full load (P.F=0.95), V
4.3
4.4
4.5
4.6
4.7
4.8
4.9
4.10
4.11
4.12
4.13
4.14
4.15
4.16
4.17
4.18
4.19
4.20
4.21
4.22
4.23
4.24
4.25
4.26
4.27
EEPCo
Yes
Yes
Yes
Yes
Yes
IP23
IP23
IP23
IP23
IP23
ONAN
3
IEC 60354
50
ONAN
3
IEC 60354
50
ONAN
3
IEC 60354
50
ONAN
3
IEC 60354
50
ONAN
3
IEC 60354
50
400
400
500
500
630
630
800
800
1250
1250
15
0.4
Dyn5
990
15
0.4
Dyn5
1180
15
0.4
Dyn5
1450
15
0.4
Dyn5
1650
15
0.4
Dyn5
2300
W
V
4500
400
5400
400
6400
400
8000
400
11000
400
50
53
53
54
56
Gray
Gray
Gray
Gray
Gray
Hz
kV
%
%
%
%
%
%
%
db
Page 3
Date: 28/4/2013,
LPA-GECE
No
Item
4.28
4.29
4.30
4.31
4.32
4.33
4.34
4.35
4.36
4.37
4.38
4.39
4.40
4.41
4.42
4.43
4.44
4.45
4.46
4.47
4.48
4.49
4.50
4.51
4.53
4.54
4.55
4.56
4.57
4.58
4.59
EEPCo
m
%
140
4
140
5
140
5.5
140
5.5
140
6
>=90
>=90
>=90
>=90
>=90
60
55
60
55
60
55
60
55
60
55
CRGO
CRGO
CRGO
CRGO
CRGO
steel
steel
steel
steel
steel
Steel
Steel
Steel
Steel
Steel
Copper
round
Copper
round
Copper
round
Copper
round
Copper
round
50
125
50
125
50
125
50
125
50
125
wire or coil
wire or coil
wire or coil
wire or coil
wire or coil
oC
mm
mm
mm
kg
mm
mm
mm
kV
kV
Page 4
Date: 28/4/2013,
LPA-GECE
No
Item
4.60
4.61
4.62
4.63
LV Windings
Material
Insulation
Power frequency withstand voltage,
kV(rms)
Rated lightning, impulse withstand
voltage, kV(peak)
Complete Compact Substation
Dimension Width x Depth x Height
Weight, kg
4.64
4.65
4.66
4.67
EEPCo
Copper
Copper
Copper
Copper
Copper
kV rms
kV peak
.
mm
kg
Page 5
Date: 28/4/2013,
EEPCO
SPECIFICATION
TS-TR-06
15kV Voltage Boosters
SPECIFICATION TS-TR-06
EEPCO
Date
Brief Description
Rev 0
Mar 2013
First issue.
Rev 1
27 April 2013
Improved Specification .
Page: i , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
15KV VOLTAGE BOOSTERS
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT
4.
4.1
4.2
4.3
TYPE TESTS
ROUTINE TESTS
SAMPLE / ACCEPTANCE TEST
2
2
3
5.
BASIC FEATURES
5.1
5.2
5.3
5.4
5.5
5.6
5.7
5.8
5.9
5.10
5.11
5.12
5.13
5.14
5.15
5.16
5.17
5.18
5.19
5.20
5.21
5.22
5.23
GENERAL
TYPE OF VOLTAGE REGULATORS AND OPERATING CONDITIONS
CONTINUOUS MAXIMUM RATING
VOLTAGE RATIO
ELECTRICAL CONNECTIONS
DUTY UNDER FAULT CONDITIONS
LOSSES AND EVALUATION OF LOSSES
MAGNETIC CIRCUIT AND WINDINGS
HARMONIC SUPPRESSION
EARTHING OF MAGNETIC CIRCUIT
TANK FABRICATION FOR REGULATORS
BREATHER
TERMINAL BUSHINGS
SURGE ARRESTERS
VALVES
RADIATORS
EARTHING TERMINALS
VOLTAGE CONTROL
ON-LOAD TAP CHANGERS (OLTC)
OIL
OIL TEMPERATURE INDICATING DEVICES
GAS AND OIL-ACTUATED RELAYS (BUCHHOLZ RELAY)
TECHNICAL REQUIREMENTS
3
4
4
4
4
4
4
5
5
5
6
6
6
6
6
6
7
7
7
8
8
9
9
6.
7.
QUALITY ASSURANCE
ADDITIONAL REQUIREMENTS
10
10
7.1
7.2
7.3
7.4
SPARES
RATING PLATE
PACKING
WARRANTY
10
10
10
10
8.
10
8.1
10
Page: ii , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
8.2
8.3
8.4
11
11
11
9.
SCHEDULES
11
9.1
9.2
9.3
11
11
13
SECTION 1 - SCOPE
SPECIFICATION TS-TR-06
EEPCO
SCOPE
This specification covers oil-immersed, naturally cooled (type ONAN), outdoor
type, 50 Hz, 15kV Voltage Boosters/Regulators intended for improving voltage
regulation in 15kV lines having excessive voltage variations.
These are normally installed mid-way on long/ rural 15KV lines, where voltage
drop exceeds maximum permissible limit.
2.
3.
3.1
REFERENCE STANDARDS
Specification /
Standard Number
Title
BS 4360
BS 729
IEC 65029
IEC 60076
Power transformers
IEC 600137
IEC 600214
IEC 600354
IEC 600542
IEC60296
ANSI 57.15
CONFLICT
See Specification TS-GN-02
4.
Page: 1 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
At least 21 working days notice shall be given when the plant is ready for
inspection & tests and every facility shall be provided by the manufacturer to
enable the Client to carry out the necessary inspection and witnessing of tests.
4.1
TYPE TESTS
(i)
(ii)
(iii)
(iv)
(v)
(vi)
(vii)
(viii)
(ix)
Temperature rise ,
(x)
4.2
ROUTINE TESTS
4.2.1
General
The following Routine Tests shall be carried out on the Voltage Regulators by the
manufacturer and the test report shall be supplied with the regulator
1) Measurement of winding resistance (as per Clause No.10.2 of IEC 60076)
2) Measurement of voltage ratio and check of phase displacement (as per Clause No.
10.3 of IEC 60076)
3) Measurement of short circuit impedance and load loss (as per Clause No. 10.4 of
IEC 60076)
4) Measurement of No Load loss (as per Clause No. 10.5 of IEC 60076)
5) Characteristic of transformer oil (Break down value ,tan-delta and resistivity)
6) Dielectric routine test (as per IEC 60076-3)
High voltage power frequency test
Induced over voltage test at 125 Hz.
4.2.2
Page: 2 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
4.2.3
Magnetic Circuit
Each core completely assembled is to be tested for one minute at 2,500 volts A.C.
between core bolts, side plates, structural steel work. After the Voltage Regulator
is tanked and completely assembled, a further test is to be applied between the
core and the earthed structural steel work to prove that the core is earthed,
through the removable link, at one point only.
4.2.4
4.2.5
LV Equipment
Insulation tests shall be carried out on all LV equipment at 2 kV for one minute.
4.3
5.
BASIC FEATURES
5.1
GENERAL
The 15kV automatic Voltage Regulators will be used in long overhead radial /
open-ring feeders to improve the down-stream network supply performance.
Page: 3 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
5.2
5.3
5.4
VOLTAGE RATIO
The nominal input voltage shall be 15 kV.
The output voltage shall be 15 KV.
5.5
ELECTRICAL CONNECTIONS
Voltage Regulator windings shall be of:-
5.6
5.7
Page: 4 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
5.8
5.9
HARMONIC SUPPRESSION
The Voltage Regulator shall be designed in such a way that in the output contains
minimum amount of harmonics. The sum of 3rd, 5th, 7th harmonics shall not be
more than 3% of RMS rated value and the individual value shall not be more than
2%. For this purpose, composite low pass filters may be added, so as to get nearly
sine wave output. Voltage Regulator supplier shall demonstrate the output wave
shape.
5.10
Page: 5 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
5.11
5.12
BREATHER
The Voltage Regulator shall be fitted with an oil seal type silica gel breather. This
breather shall be at least one size larger than would be fitted for use in a temperate
climate. All breathers shall be mounted at a height not exceeding 1.5m above
ground level.
5.13
TERMINAL BUSHINGS
The Voltage Regulator shall be provided with outdoor type 24kV bushing
insulators. All bushing shall comply with IEC 60137. These requirements are for
the 15kV system operating at altitudes up to 3,000m
The bushing shall be of the oil filled type or sealed construction suitable for
service under very humid conditions. Typical section of bushing insulators
showing the internal construction, method of securing the top cap and method of
sealing shall be submitted with the Bid.
5.14
SURGE ARRESTERS
Surge arresters shall be fitted and be an integral part of the regulator.
Surge arresters shall be fitted on both sides of the regulator.
5.15
VALVES
Complete set of valves shall be provided for draining, sampling, filtering, air
release, and isolation purposes.
Valves shall be of the sluice type, have non-rising spindles and shall be closed by
turning the hand-wheel in a clockwise direction. They shall have machined flanges
with facilities for locking in the closed and open positions.
Every valve shall be provided with an indicator to show clearly the position of the
valve and each hand-wheel shall be fitted with a brass nameplate indicating the
purpose of the valve.
5.16
RADIATORS
Radiator(s), if provided, shall be designed so that all painted surface can be
thoroughly cleaned and easily painted in site with brush or spray gun. The design
shall also avoid pockets in which water can collect. If detachable type radiators are
provided they shall be connected directly to the tank and shall be provided with
machined flanged inlet and outlet branches. Plugs shall be fitted at the top and
bottom of each radiator for filling and draining.
Page: 6 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
5.17
EARTHING TERMINALS
Two earthing terminals, each capable of carrying the stipulated maximum earth
fault current shall be provided close to the base and on opposite side of the tank
structure.
5.18
VOLTAGE CONTROL
The Voltage Regulator shall have an automatic voltage control device (relay) to
control the on load tap changing type sector switch for varying the effective
transformation ratio. On-Load-Tap-Changer (OLTC) of "Machinenfabrik
Reinhausen" type design shall be provided with the Voltage Regulator.
The auxiliary supply for the automatic voltage control relay and the OLTC shall
be provided by an auxiliary winding incorporated in the Regulator main winding.
OLTC shall comply with IEC 60214 and shall be suitable for power flow in both
directions. Only designs which have been type tested in accordance with this
standard shall be accepted.
A counter shall be included with the tap change mechanism to indicate the
number of operations completed by the equipment.
All terminals shall be clearly and permanently marked with numbers
corresponding to the cables connected there to. Tap changers shall be suitable for
load flow through the Voltage Regulator as stipulated in the technical
requirements.
5.19
Page: 7 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
housed in a suitable weather, vermin and insect proof cubicle with locking
facilities.
5) During power failure the tap changer shall return to the zero position to prevent
voltage rise in the downstream.
6) When the gas and oil actuated relay operates it shall send a signal to block the
operation of the OLTC after bringing back the OLTC to the zero position.
7) Auto - Local - Manual selector switch shall be provided for operation of motor
and the operating mechanism. Provision shall also be made available to operate
the tap changer manually without the motor using a manual operating handle. The
manual operating handle shall be provided and housed in the tap changer
operating mechanism cubicle.
8) An approved mean shall be provided to safe guard the Voltage Regulator when
the tap changer mechanism fails to perform a complete tap changing operation
and the indication " Tap change incomplete" shall be initiated.
A glass window shall be provided in the tap changer operating mechanism cubicle
to view the following;
Tap position
Tap change incomplete indication
9) The following operating conditions are to apply to the on-load tap selector
controls:It shall not be possible to operate the electric drive when the manual operating
gear is in use.
Operation from local control switch shall cause one tap movement only unless the
control switch is returned to the off position between successive operations.
All electrical control switches (auto- local - manual) and manual (hand) operating
gear shall be clearly labelled in an approved manner to indicate the direction of
tap changing.
5.20
OIL
The voltage regulator oil shall be filled with oil before delivery. The oil shall
contain at least 0.3 percent by weight oxidation inhibitor of type diterbutyl
paracresol (DBPC) according to IEC 60296.
Each transformer shall be supplied with standard insulating oil to the requirement
of IEC 60137. The oil shall be new and satisfied to contain less than 1 ppm of
PCBs. Each transformer shall be filled with the correct volume of oil for the
ambient temperature.
5.21
Page: 8 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
5.22
5.23
1
2
3
4
4.1
TECHNICAL REQUIREMENTS
Line capacity
Over loading
Short time withstand current/duration
Input voltage
4.2
5
6
7
8
9
10
11
12
12.1
Insulation level
Impulse withstand voltage
12.2
13
13.1
13.2
14
15
16
17
18
Core material
19
5.2 MVA
As per IEC 60354
16kA /1 seconds
15kV Nominal
-15% of nominal
Minimum
+5% of Nominal
Maximum
15kV
3 or 1 phase units
50Hz
ONAN
50C
60C
Auto 3 phase, star or delta
connected. Single phase
units Phase-phase
125kV (1.2/50 s) kV
peak
50kV
480mm
Less than 1%
Continuous & outdoor
Copper
Mineral oil transformer oil
to BS144 IEC 60137
Cold rolled grain oriented
silicon Steel
17 Minimum
Page: 9 , 27-Apr-13
SPECIFICATION TS-TR-06
EEPCO
19.1
20
21
22
23
Marshalling box
Bucholz relay
6.
IP 54 enclosures suitable
for outdoor installation
Provided as per clause
above.
IP 54 enclosure
Provided as per Clause
above
QUALITY ASSURANCE
The Bidder shall furnish documentary proof that the manufacturer posses the
Quality Assurance conforming to ISO 9001 for the manufacture of 15kV
Transformers for the particular plant where manufacturer is carried out. The
Bidder shall certify all the documents as true copies of the originals.
7.
ADDITIONAL REQUIREMENTS
7.1
SPARES
A list of recommended spare parts (along with the detailed prices) for five years
trouble free operation shall be furnished with the offer.
7.2
RATING PLATE
The Rating Plate shall be made of stainless and shall provide the ratings and data
of the voltage as per IEC 60076. The rating plate shall be positioned on the tank
at a height of 1.5 m from the base.
7.3
PACKING
Each item shall be packed properly and protected for shipment and transport
from the place of manufacture to Client's site. The Client may require to inspect
and approve the packing before the items are despatched but the Bidder shall be
entirely responsible for ensuring that the packing is suitable for transit and such
inspection will not exonerate the Bidder from any loss or damage to faulty
packing.
7.4
WARRANTY
The Bidder shall guarantee the efficient good working of the Voltage Regulators
supplied and guarantee the to be free of defects for a period of twelve months
from the date on which the Client takes over the
8.
8.1
Page: 10 , 27-Apr-13
SECTION 9 - SCHEDULES
SPECIFICATION TS-TR-06
EEPCO
4) Overall dimensional drawings
8.2
8.3
OTHER CERTIFICATES
Test Certificates, Performance Curves etc., furnished shall be based on the Type
Tests conforming to the relevant standard .The Test Certificates shall clearly
identify the equipment concerned, showing the manufacturer's identity, Type No.
and basic technical parameters, and shall be from a recognised Testing Authority
acceptable to the Client.
Copies of the Type & Routine Test Certificates shall be certified by the Bidder as
the true copies of the originals.
Failure to furnish the particulars requested in clause 8.1 and 8.2 will result in the
offer being rejected.
8.4
9.
SCHEDULES
If the technical schedules are to be included in the same file then use this section
9.1
9.2
Page: 11 , 27-Apr-13
SECTION 9 - SCHEDULES
SPECIFICATION TS-TR-06
EEPCO
The bidder shall provide a list of non compliances with this specification,
documenting the effects that such non compliance is likely to have on the
equipments life, operating characteristics and system performance. Each non
compliance shall make reference to the relevant specification clause.
Specification
Clause
Page: 12 , 27-Apr-13
SECTION 9 - SCHEDULES
SPECIFICATION TS-TR-06
EEPCO
9.3
Page: 13 , 27-Apr-13
EEPCo
15 kV Voltage Boosters
Technical Schedule for
Please fill more schedules if more types of equipment offered that can fit on this sheet
No
1
items
10
15
15.1
15.2
15.3
15.4
15.5
15.6
16
17
18
19
20
21
22
23
23.1
23.2
23.3
23.4
24
Requirement
Bid Offer
2
3
4
5
6
6.1
6.2
7
8
9
11
12
13
14
Unit
MVA
kA
kV
kV
kV
kV
kV
kV
5.2
As per IEC 60354
12.5
15
12.75
15.75
15
24
17.5
200
233
3 or 1 phase units
Hz
50
Yes/No Yes
kV
125
kV
50
kV
60
mm
480
cm
deg.C
deg.C
kVA
Less than 1%
Continuous &
outdoor
Oil immersed with
ONAN cooling
703260
BS144 IEC 60137
55
60
2666
Copper
Continuous winding
kg
kg
EEPCo
kg
kg
kg
kg
Yes/No Yes
17 Minimum
Yes/No Yes
Yes/No Yes
Yes/No Yes
Yes/No Yes
Losses
i) Load losses at MVA rating at 75 deg.C
ii) Zero phase sequence/Phase
iii) No load current
iv) Power Factor
Total Weight including oil and auxiliaries
Ohms
EEPCO
SPECIFICATION
TS-UV-01
SPECIFICATION TS-UV-01
EEPCO
Date
29 April 2013
Brief Description
First Issue
Page: i , 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
SPECIFICATION CONTENTS
DESCRIPTION
PAGE NO
UTILITY TRUCKS AND VEHICLES
1
1.
SCOPE
1
2.
SYSTEM PARAMETERS & SERVICE CONDITIONS
1
3.
REFERENCE STANDARDS
1
3.1
CONFLICT:
4.
4.1
4.2
4.3
4.4
4.5
GENERAL
TRUCK OR TRACTOR REQUIREMENTS
CRANE REQUIREMENTS
AUGER
GENERAL COMMON REQUIREMENTS
1
2
2
2
3
5.
6.
7.
8.
3
4
4
5
8.1
8.2
5
6
Page: ii , 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
SECTION 1- SCOPE
SCOPE
This specification covers the Supply of Utility Vehicles including:
Crane and Auger, Lifting platform/beam lifter/cherry picker, twin-cab utility
vehicle and personnel vehicle.
2.
3.
REFERENCE STANDARDS
The materials supplied shall conform to the latest edition of the appropriate IEC
standards and/or other recognized international standards. In particular:
3.1
CONFLICT:
See spec TS-GN-02.
4.
4.1
GENERAL
The Truck or Tractor Mounted Hydraulic Crane with Auger shall conform in
all respects to the physical and performance requirements of this standard
and technical schedule TS-UV-01-S4.
Specification of the truck or tractor shall be furnished with the bid including
diesel engine size, manufacturer, transmission system, wheelbase and tire
size.
The crane & auger shall be mounted on Truck or tractor chassis with diesel
engine, water cooled and the supplier must furnish detailed information showing
that spare parts are available in the country of the client. Alternatively a dedicated
tractor based unit maybe employed. The unit shall be equipped with outrigger
stabilisers. It shall be suitable for use on and off the road.
Page: 1, 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
4.2
4.3
4.3.1
CRANE REQUIREMENTS
General
The boom shall be of rigid welded box design with 2 or three sections,
telescoping and with continuous 360 rotations. The fully extended length of the
boom will be no less than 12 M. It shall include a boom angle indicator fully
visible from the operator's position. All hydraulic boom fixtures should be either
totally enclosed within the boom sections or secured on the boom to ensure long
lasting performance.
The CAB instrumentation shall include at least oil pressure gauge, water
temperature gauge, fuel gauge and hour meter. All instruments must be located in
full view of the operator. The CAB shall also include combination foot and hand
throttle and all controls for safe operation of the unit, such as tipping warning and
over winding alarming device, etc.
Maximum speed on road to be specified by the bidder.
4.3.2
Crane Capacities
The crane shall be rated for no less than 3 metric tons at 4m and 1 metric
ton at 7m.
4.4
AUGER
The auger is intended to be used mainly for the planting of overhead line poles.
The auger assembly shall be permanently and securely mounted on the body of
the truck or tractor. It shall operate on a rail type sliding assembly. It shall be
hydraulically operated powered from the vehicles engine.
The vertical alignment of the auger head shall be adjustable so that the hole can
be opened to true vertical line.
The auger shall be capable of drilling a whole of minimum depth as shown in the
technical schedules without needing to change or add any components on the
auger assembly.
The auger tip shall be fitted with a head to drill a whole diameter as shown in the
technical schedules. It shall be suitable for soft and hard soil, sandy soil and loose
rocks and solid soft rock.
Page: 2, 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
Two sets of hand ramming tools for soil compaction and finishing off pole
installation shall be provided with each tractor-mounted auger.
4.5
4.5.1
4.5.2
Spare Wheels
Two spare wheels (one for the front and one for the rear wheels if different).
4.5.3
Spare Parts
The supplier will supply the crane/Auger with the recommended spare parts
4.5.4
Documentation
Each unit shall include 2 copies of complete operators instruction, maintenance,
service and parts manuals. The supplier will also propose local services with
workshop and parts backup, if any.
4.5.5
Other standards
The physical and performance requirements of truck or tractor mounted
hydraulic cranes based on other international recognized standards are
acceptable only if the requirements of such standard are equivalent to or
exceed the requirements quoted in this document.
5.
2 spare wheels.
Page: 3, 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
6.
SECTION 6- FOURTH
7.
Page: 4, 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
8.
8.1
Page: 5, 30-Apr-13
SPECIFICATION TS-UV-01
EEPCO
8.2
Page: 6, 30-Apr-13
LPA-GECE
EEPCo
Item
Requirement
Bid offer
General
Make
Model
Country of Manufacture
Standard production vehicle
Yes
Vehicle conditions
New, latest model
Designated to comply with heavy duty conditions
1.6 and rough terrain, off road, gravel and unpaved
Yes
roads
1.7 suitable for operation in humid, tropical climate
Yes
Passenger and goods
1.8 Usage
transport
2 at front,
1.9 Passenger Capacity
3 at rear seats
Removable hard canopy for the rear trunk made
Not Required,
1.1
of fibreglass or other durable material, lockable
optional
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
3
3.1
3.2
3.3
Engine
Cylinders
Valves
Nominal Engine Power
Min 2800mm
4,800 mm 500mm
1,850 mm 200mm
1,800 mm 200mm
Min 200mm
Min 500kg
Min 700kg
Min 2500kg
4 Min
16 min
>=140 hp
>300 N-m at
optimum revs/min
>2,400 cm3
Yes
Water - closed circuit
Diesel
Direct injection
Manufacturers
standard
>60 litres
LPA-GECE
No
Item
Fuel tank protection under-shield if exposed to
4.4
underside
Lockable tank filler lid or remote control from
4.5
inside cab
4.6 Fuel consumption (combined cycle)
4.7 Emissions (CO2 g/km)
5
5.1
5.2
5.3
EEPCo
Requirement
Bid offer
Yes metallic
Yes
Less than 10
litres/100km
<160
2 and 4 Wheel
05-Jan
Manual
Selectable while
driving
Yes On Rear system
Yes
Yes
Preferable but not
mandatory
Disc
Disc or drum
Yes
Steel or Alloy
Yes
Please state
Yes
Power-assisted
Yes
Manufacturers
standard
Manufacturers
standard
4
Double cab
Yes to all
White
LPA-GECE
No
Item
9.5 Upholstery
9.6 Sun visors for driver and front passenger
9.7 Front Bulbar with head lamps protection grills
9.8 External side mirrors
9.9 Internal rear view Mirror
Body construction and all fitments conform to
9.1
CAP
9.11 Airbags for driver and front passenger, min. 2
9.12 Side Door Beam Protection
Requirement
Bid offer
wear-resistant cloth,
leather, or good
quality vinyl, please
state
Yes
Yes
Yes 2
Yes
Yes
Yes
Yes/Not mandatory
as per Purchaser's
default on both side
Yes
10
10.1
10.2
10.3
Towing Facilities
Rear towing hook
Front towing hook
Front pulling cable with electric motor ( winch)
11 Accessories
11.1 Fire extinguisher
AM/FM radio with integrated CD player with
11.2
USB input,
Safety seat belts for all passenger seats front and
11.3
rear
11.4 Head rests for front seats
11.5 Head rests for rear seats
11.6
12
12.1
12.2
12.3
12.4
12.5
12.6
12.7
EEPCo
Yes
Yes
Yes
Yes
Yes
Yes
Yes
12V Nominal
>70Ah
Not mandatory
LPA-GECE
EEPCo
No Item
Requirement
13 Tools
13.1 Standard Tool Set and wheel change equipment
Yes
Manual for the operation and maintenance of the
13.2
Yes
vehicle
Documentation of availability of spare parts and
13.3
Yes
maintenance facilities
13.4 Emergency triangle
2 sets
13.5 Jump start cable set
Yes
Bid offer
3 years or 60,000
km, whichever
occurs first
Yes
Yes
LPA-GECE
EEPCo
3
3.1
3.2
3.3
Engine
Cylinders
Valves
Nominal Engine Power
3.4
Engine Torque
3.5
3.6
3.7
4
4.1
4.2
Fuel system
4.3
4.4
4.5
4.6
Min 2800mm
4,800 mm 500mm
1,850 mm 200mm
1,800 mm 200mm
Min 200mm
Min 700kg
Min 2500kg
4 Min
16 min
>=140 hp
>300 N-m at optimum
revs/min
3
>2,400 cm
Yes
Water - closed circuit
Diesel
Direct injection
Manufacturers standard
>60 litres
Yes metallic
Yes
Less than 10
litres/100km
Page 5 Date: 30/04/2013,
LPA-GECE
EEPCo
Item
Emissions (CO2 g/km)
5
5.1
5.2
5.3
5.4
5.5
5.6
6
6.1
6.3
6.4
6.5
Brake System
ABS (anti-block/lock system)
EBD (electronic Break distribution between rear
and frond wheels
Frond Brakes
Rear Brakes
Central Level Parking Break
7
7.1
7.2
7.3
7.4
8
8.1
8.2
8.3
8.4
9
9.1
9.2
9.4
Body
No of doors including rear
Cabinet
Corrosion-protected panels, under body and
fittings
Colour
9.5
Upholstery
6.2
9.3
9.6
9.7
9.8
9.9
Requirement
<160
2 and 4 Wheel
5 min
Manual
Selectable while
driving
Yes On Rear system
Yes
Yes
Preferable but not
mandatory
Disc
Disc or drum
Yes
Steel or Alloy
Yes
Please state
Yes
Power-assisted
Yes
Manufacturers
standard
Manufacturers
standard
5
Single space
Yes to all
White
wear-resistant cloth,
leather, or good quality
vinyl, please state
Yes
Yes
Yes 2
Yes
Yes
Yes
LPA-GECE
EEPCo
Towing Facilities
Rear towing hook
Front towing hook
Front pulling cable with electric motor ( winch)
11 Accessories
11.1 Fire extinguisher
AM/FM radio with integrated CD player with
11.2
USB input,
Safety seat belts for all passenger seats front and
11.3
rear
11.4 Head rests for front seats
11.5 Head rests for rear seats
11.6
12
12.1
12.2
12.3
12.4
12.5
12.6
12.7
Requirement
Yes/Not mandatory
as per Purchaser's
default on both side
Yes
Yes
Yes
Yes
Yes
Yes
Yes
12V Nominal
>70Ah
Not mandatory
Not mandatory
13 Tools
13.1 Standard Tool Set and wheel change equipment
Manual for the operation and maintenance of the
13.2
vehicle
Documentation of availability of spare parts and
13.3
maintenance facilities
13.4 Emergency triangle
13.5 Jump start cable set
Yes
Yes
Yes
2 sets
Yes
LPA-GECE
EEPCo
Item
Warranty and services
14.1 Warrantee
14.2 Full manufacturer's warranty
Address list of authorised workshops with spare
14.3
parts stock throughout the country
Requirement
3 years or 60,000 km,
whichever occurs first
Yes
Yes
LPA-GECE
EEPCo
LPA-GECE
EEPCo
Bid offer
LPA-GECE
EEPCo
Bid offer
LPA-GECE
EEPCo
Bid offer
LPA-GECE
EEPCo
Item
Maker's name
Maker's type and reference
Country of origin
Engine type
Fuel Consumption
Nominal truck length
Nominal wheel base
Truck weight
Cab as specified
Accessories as specified
Instrument panel as specified
Boom type
Unit
mA
14
15
16
17
18
kV
0
No
1
2
3
4
5
6
7
8
9
10
11
12
19
20
21
22
23
24
25
26
27
28
29
30
Requirement
Bid offer
kV
kg
diesel
5 km/l approx
5.7 m. minimum
2.7 m minimum
6000 kg, minimum
Yes
Yes
Yes
fibre glass and steel
0.5 mA leakage at 100 kV
AC
66 kV AC
-13o to +80o
Yes
20 kV AC
200 kg minimum
13 m minimum
-100o to +90o
Yes
Yes
450 kg minimum
Yes
Yes
Yes
Yes
Yes
5 years
ISO 9002 minimum
km
m
m
kg
kg
years
LPA-GECE
EEPCo
No
1
2
3
4
5
6
Item
Maker's name
Maker's type and reference
Country of origin
Complete truck
Maximum speed on the road
Total weight
7
8
9
10
11
12
13
14
15
16
Type
Fuel
Cab as specified
Controls & safety devices as specified
Outriggers
17
18
19
20
21
Lifting height
Arc of boom travel
Boom slewing angle
Winch drive
Hook speed
22
23
24
25
26
27
28
29
30
31
Hole diameter
Auger torque
Working radius
Digging depth
Instrument panel as specified
Accessories as specified
Additional attachments
Minimum manufacturing experience
Manufacturing standard
Unit
Requirement
Bid offer
Nos
Water cooled
Diesel
Yes
Yes
Four minimum
Crane
Power self contained from truck engine
Crane drive hydraulic
Truck pay load
Crane capacity
kg at 4m
kg at 7m
m
0
0
m/min
Yes
Yes
1300 kg minimum
3000 kg minimum
1000 kg minimum
12 metres minimum
-10 to +80
360o continuous
Hydraulic
40 m per minute
Auger
m
kgfm
m
m
years