You are on page 1of 557

B/W Boundary Wall

Assumptions
1
2
3
4

Considered Square Land


Approx Dimension of the plot 10m x 10m, Length of Boundary wall : 40 mtr
Pillar / Angle post Spacing : 2500 Max, Total Brick pillar / Angle Post : 16 Nos
Considered normal soil till founding level, -0.75 m from Existing Ground Level

Sl no.
1
2
3
3.1
3.2
3.3
4
4.1
4.2
4
4.1
4.2
5
6
7
8
9

Measurements
L
B

Description

Unit

Excavation
PCC M 10 Grade
Brick Work
Pillars
Walls below GL
Walls above GL
Sub Total Brick Work
Plaster 20 mm thick
Walls
Pillars
Sub Total Plaster
M15 grade Concrete
Coping
Grouting
Sub Total M 15 concrete
Shuttering for Coping
Structural Steel Post ISA 50*50*5
Barbed Wire ( Mat + Lab )
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length

CuM
CuM

4
4

10.46
10.46

0.46
0.46

CuM
CuM
CuM

16
4
4

0.46
8.16
8.16

0.46
0.46
0.23

SqM
SqM

2
16

40
0.8

CuM
CuM

1
16

40
0.23

0.23
0.23

SqM
Kg
M
M
LS

8
16
3
2
1

10
1.02
40
40
40

0.15
3.925

Nos

Cost Per Meter


RRM ( Random Rubble Masonry ) Boundary Wall
Assumptions
1
2
3

Sl no.
1
2
3
3.1
3.2
3.3

Considered Square Land


Approx Dimension of the plot 10m x 10m, Length of Boundary wall : 40 mtr
Considered normal soil till founding level, -0.75 m from Existing Ground Level

Description
Excavation
PCC M 10 Grade
RRM walls
Pillars
Walls below GL
Walls above GL
Sub Total Brick Work

Unit

Nos

Measurements
L
B

CuM
CuM

4
4

10.46
10.46

0.46
0.46

CuM
CuM
CuM

16
4
4

0.46
8.16
8.16

0.46
0.46
0.35

4
5
5.1
5.2
6
7
8
9
10

Flush Pointing
M15 grade Concrete
Coping
Grouting
Sub Total M 15 concrete
Shuttering for Coping
Structural Steel Post ISA 50*50*5
Barbed Wire ( Mat + Lab )
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length

SqM

40

CuM
CuM

1
16

40
0.23

0.23
0.23

SqM
Kg
M
M
LS

8
16
3
2
1

10
1.02
40
40
40

0.15
3.925

Cost Per Meter


GI Chain Link Fencing
Assumptions
1
2
3
4

Considered Square Land


Approx Dimension of the plot 10m x 10m, Length of Fencing : 40 mtr
Angle post Spacing : 2500 Max, Total Angle Post : 16 Nos
Considered normal soil till founding level, -0.75 m from Existing Ground Level

Sl no.
1
2
3
4
4.1
4.2
5
6
7
8

Measurements
L
B

Description

Unit

Excavation
PCC M 10 Grade
RCC M20 in foundations
Structural Steel Post ISA 50*50*5
Straight
Inclined
Sub Total
GI Chain Link Fencing
Barbed Wire ( Mat + Lab )
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length

CuM
CuM
CuM

24
24
24

0.45
0.45
0.45

0.45
0.45
0.45

Kg
Kg

16
8

2.58
2

3.925
3.925

SqM
M
M
LS

1
3
5
1

40
40
40
40

1.8

Nos

Cost Per Meter


Barbed Wire Fencing
Assumptions
1
2
3
4

Sl no.

Considered Square Land


Approx Dimension of the plot 10m x 10m, Length of Fencing : 40 mtr
Angle post Spacing : 2500 Max, Total Angle Post : 16 Nos
Considered normal soil till founding level, -0.75 m from Existing Ground Level

Description

Unit

Nos

Measurements
L
B

1
2
3
4
4.1
4.2
5
6
7
8

Excavation
PCC M 10 Grade
RCC M20 in foundations
Structural Steel Post ISA 50*50*5
Straight
Inclined
Sub Total
Barbed Wire Straight
Barbed wire inclined
Line Wire 4 mm thk ( Mat + Lab )
Hardwares & Fittings
Sub Total - 40 M length

CuM
CuM
CuM

24
24
24

0.45
0.45
0.45

0.45
0.45
0.45

Kg
Kg

16
8

2.58
2

3.925
3.925

SqM
M
M
LS

12
32
5
1

40
3.5
40
40

Cost Per Meter


Structural Steel Gate
Sl no.
1
2
3
4
5
6
7
8
9
10

Description

Unit

Excavation for pedestal


PCC M 10
RCC M 20
Structural steel post 2*ISMC 150
40 NB Pipe frame
ISA 20*20*3 frames for signages
MS plate for signages 18G/1mm
Chain link Panelling
Flat 25 x 5
AL drops, Hinges, tower bolts etc.

CuM
Cum
Cum
Kg
Kg
Kg
Kg
Sqm
Kg
Kg

Nos
2
2
2
2
2
2
2
2
2
LS

Measurements
L
B
0.6
0.6
0.6
2.6
6.39
3.195
0.59
1.395
6.39

0.6
0.6
0.6
33.6
4.43
0.95
0.59
1.8
0.98

Cost Per No.

Sl no.
1
1.1
1.2

Description
Excavation
Footings
Plinth Beams

Shelter 100 SqFt SBC 50 KN/m2


Measurements
Unit
Nos
L
B
M3
M3
M3

4
2
2

1.8
3.5
2.87

1.8
0.23
0.23

M3
M3
M3
M3

4
2
2
1

1.7
3.5
2.87
3.07

1.7
0.23
0.23
2.87

M3
M3
M3

4
4
2

1.5
0.3
3.5

1.5
0.23
0.23

Sub Total
2
2.1
2.2

PCC
Footings
Plinth Beams

2.3

Grade Slab

Sub Total
3
3.1
3.2
3.3

RCC M 20 grade Concrete


Footings
Columns
Plinth Beams PB 1

3.4
3.5
3.6
3.7
3.8

Plinth Beams PB 2
Tie Beams TB 1
Tie Beams TB 2
Slabs
Grade Slab

M3
M3
M3
M3
M3

2
2
2
1
1

2.87
3.5
2.87
5
3.57

0.23
0.3
0.3
3.4
2.87

M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2

4
2
2
2
2
2
1
2
1
2
2
1

1.5
0.3
3.5
2.87
3.5
3.5
2.87
2.87
4.77
3.17
4.77

2.87

2
2
2
2
4

3.5
2.87
4.03
3.33
0.45

0.23
0.23
0.23
0.23
0.115

4.77

3.27

Sub Total
4
4.1
4.2
4.3
4.4
4.5
4.6
4.7

Form work / Shuttering


Footings
Columns
Plinth Beams PB 1
Plinth Beams PB 2
Tie Beams TB 1 sides
Tie Beams TB 1 bottom
Tie Beams TB 2 sides
Tie Beams TB 2 bottom
Roof Slab side
Roof Slab Bottom

0.23

Sub Total
5

Reinforcement

MT

Brick work

M3
M3
M3
M3
M3

Plaster 20 mm thick

M2

Plaster 12 mm thick internal

M2
M2

Sub Total
9

Internal Plastic Paint

M2

10

External Snowcem Paint

M2

11

Brick Bat Coba Water proofing

M2

4.07

2.97

12

Underdeck PUF Insulation

M2

3.17

2.87

13

Antistatic PVC Flooring

M2

3.17

2.87

14

HMPS Doors

M2

1.2

15

Boulder Soling

M3

5.97

3.07

16

Steps for entry

LS

17

IPS Flooring

M2

3.57

2.87

18

PVC Antistatic flooring

M2

3.57

2.87

Total Cost

Sl no.
1
1.1
1.2

Description
Excavation
Footings
Plinth Beams

Shelter 200 SqFt SBC 50 KN/m2


Measurements
Nos
L
B
Unit
M3
M3
M3

4
2
2

2.1
5.9
3.07

2.1
0.23
0.23

M3
M3
M3
M3

4
2
2
1

1.9
5.9
3.07
5.97

1.9
0.23
0.23
3.07

M3
M3
M3
M3
M3
M3
M3
M3

4
4
2
2
2
2
1
1

1.8
0.3
5.9
3.07
5.9
3.07
7.4
5.97

1.8
0.23
0.23
0.23
0.3
0.3
3.4
3.07

M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2
M2

4
2
2
2
2
2
1
2
1
2
2
1

1.8
0.3

Sub Total
2
2.1
2.2

PCC
Footings
Plinth Beams

2.3

Grade Slab

Sub Total
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8

RCC M 20 grade Concrete


Footings
Columns
Plinth Beams PB 1
Plinth Beams PB 2
Tie Beams TB 1
Tie Beams TB 2
Slabs
Grade Slab

Sub Total
4

Form work / Shuttering

4.1
4.2

Footings
Columns

4.3
4.4
4.5

Plinth Beams PB 1
Plinth Beams PB 2
Tie Beams TB 1 sides
Tie Beams TB 1 bottom
Tie Beams TB 2 sides
Tie Beams TB 2 bottom
Roof Slab side

4.6
4.7

Roof Slab Bottom

Sub Total

0.23
5.9
3.07
5.9
5.9
3.07
3.07
7.33
3.53
6.8

3.07

Reinforcement

MT

Brick work

M3
M3
M3
M3
M3

Plaster 20 mm thick

M2

Plaster 12 mm thick internal

M2
M2

2
2
2
2
4

5.9
3.07
7.1
3.53
0.45

0.23
0.23
0.23
0.23
0.115

6.8

3.07

Sub Total
9

Internal Plastic Paint

M2

10

External Snowcem Paint

M2

11

Brick Bat Coba Water proofing

M2

6.8

3.07

12

Underdeck PUF Insulation

M2

5.97

3.07

13

Antistatic PVC Flooring

M2

5.97

3.07

14

HMPS Doors

M2

1.2

15

Boulder Soling

M3

5.97

3.07

16

Steps for entry

LS

17

IPS Flooring 40 mm thick

M2

5.97

3.07

18

PVC antistatic flooring 5 thk

M2

5.97

3.07

Total Cost
Brick Manhole : 1000 x 1000 x 1650 mm
Measurements
Description
Nos
L
B
Unit

Sl no.
1
2
3

Excavation
PCC
Brick work

Sub Total
Plaster from Inside

m3
m3
m3
m3

1
1
2
2

1.76
1.56
1.46
1

m2

1.76
1.56
0.23
0.23

4
5

RCC Preacst Cover


RCC M 25 incl shuttering & R/f

m3

1.46

1.46

Sub Total
RCC Cast In situ - Manhole : 1000 x 1000 x 1650 mm
Measurements
Description
Nos
L
B
Unit

Sl no.
1
2
3

3
4
5

Excavation
PCC
RCC M 20 Grade
Sub Total
Form work
RCC Preacst Cover
RCC M 25 incl shuttering & R/f
Structural Steel Frames

m3
m3
m3
m3

1
1
1
4

1.6
1.4
1.15
1.15

m2

1.15

m3
Kg

1
1

1.46
4.6

1.6
1.4
1.15
0.15

1.46
0.25

Sub Total
RCC Precast Manholes - 1000 mm dia x 1650 mm
Measurements
Description
Nos
L
B
Unit

Sl no.
1
2
3
4
4

Excavation
PCC
Preacst Hume pipe
Erection of Hume pipe
RCC Preacst Cover
RCC M 25 incl shuttering & R/f

m3
m3
m
m

1
1
1

1.6
1.4
1.5

1.6
1.4

m3

1.46

1.46

Sub Total
Shetlter / Container Paltform 100 Sq ft 3800 x 3100 mm size
Measurements
Description
Nos
L
B
Unit

Sl no.
1
2
3
4
4.1

Eaxcavation
Boulder Soling
PCC 50 mm thcik
RCC
Inverted Beams

4.2
5

Platform Slab
Sub Total
Formwork

Reiinforcement

m3
m2
m3

1
1
1

3.8
3.3
3.8

3.1
2.6
3.1

m3
m3
m3

2
2
1

3.8
2.6
3.3

0.25
0.25
2.6

m2
m2

2
2

3.8
3.1

Kg

Total
Shetlter / Container Paltform 200 Sq ft 6200 x 3300 mm size

Sl no.

Description

1
2
3
4
4.1

Eaxcavation
Boulder Soling
PCC 50 mm thcik
RCC
Inverted Beams

4.2
5

Platform Slab
Sub Total
Formwork

Reiinforcement

Measurements
L
B

Unit

Nos

m3
m2
m3

1
1
1

6.2
5.7
6.2

3.3
2.8
3.3

m3
m3
m3

2
2
1

6.2
2.8
5.7

0.25
0.25
2.8

m2
m2

2
2

6.2
3.3

Kg

Total
DG Foundations
Sl No
1
2
3
4
5
6
7
8
9
10
11
12
13
14

Description
Excavation
PCC
RCC M25
Shuttering
Shuttering
Reinforcement
brick work 115 mm thick
brick work 115 mm thick
Sand Filling
Sand Filling
PCC for Plinth Protection
PCC for Plinth Protection
RCC M 15 for Plinth Protection
RCC M 15 for Plinth Protection

Unit

m3
m3
m3
m2
m2
kg
m3
m3
m3
m3
m3
m3
m3
m3

Measurements
Nos L
B
1
1
1
2
2

4.13
3.13
2.50
2.50
1.25

2.88
1.88
1.25

2
2
2
2
2
2
2
2

2.72
1.47
2.60
1.35
4.15
2.75
4.00
1.25

0.115
0.115
0.1
0.1
0.61
0.61
0.75
0.75

ED

CST

12.36%

1%

Transp
& Hand
3%

11.89

1.08

2.89

Total

Sr. No.
1

COST OF CABLES
Cost /
mtr

Cables
2

0.65/1.1kV ,2C 6mm Cu/PVC/PVC,N-ARM,FRLS LT Cable


96.2

0.65/1.1kV ,2C 16mm Cu/PVC/PVC,N-ARM,FRLS LT Cable


217

26.82

2.44

6.51

0.65/1.1kV ,2C 35mm2 Cu/PVC/PVC,N-ARM,FRLS LT Cable


475

4
5
6
7

58.71

5.34

14.25

80.46

7.31

19.53

114.45

10.40

27.78

936

115.69

10.52

28.08

0.65/1.1kV ,4C 6mm Cu/PVC/PVC,N-ARM,FRLS LT Cable


181

22.37

2.03

5.43

0.65/1.1kV ,2C 50mm Cu/PVC/PVC,N-ARM,FRLS LT Cable


651
0.65/1.1kV ,2C 70mm Cu/PVC/XLPE,N-ARM,FRLS LT Cable
926
2

0.65/1.1kV ,4C 35mm Cu/PVC,ARM,LT Cable


2

0.65/1.1kV ,1C 16mm2 Cu/PVC,N-ARM,FRLS,Green LT 110


Cable

13.60

1.24

3.30

ements

Qty

Rate

0.75
0.15

14.43
2.89

160
3700

2,310
10,682

2.4
0.5
1.9

8.13
7.51
14.26
3400

101,647

210

13,146

4400
300
85
15
10
10

6,929
3,600
5,466
1,800
800
400
146,779

29.90
1.9
1.9

43.90
18.70

62.60
0.15
0.23

Kg/M

Amount

1.38
0.19

1.57
12.00
64.31
120
80
40

3,669

dary Wall

ements

Qty

Rate

0.75
0.15

14.43
2.89

160
3700

2,310
10,682

2.4
0.5
1.9

8.13
7.51
21.71
2890

107,908

37.34

Amount

1.9

43.90

0.15
0.23

1.38
0.19

Kg/M

1.57
12.00
64.31
120
80
40

100

4,390

4400
300
85
15
10
10

6,929
3,600
5,466
1,800
800
400
144,284

3,607

ements

Qty

Rate

0.9
0.15
0.9

4.37
0.73
4.37

160
3700
5100

700
2,697
22,307

Kg/M
Kg/M

161.77
75.36
85
125
15
10
10

20,156
9,000
1,800
2,000
400
59,061

237.13
72.00
120
200
40

Amount

1,477

ements
H

Qty

Rate

Amount

0.9
0.15
0.9

4.37
0.73
4.37

Kg/M
Kg/M

161.77
75.36

237.13
480
112
200
40

160
3700
5100

700
2,697
22,307

85
15
15
10
10

20,156
7,200
1,680
2,000
400
57,141

1,429

ements
H
1.05
0.15
0.9
kg / m
kg / m
kg / m
7.85 kg/m
kg / m

Qty

Rate

0.76
0.11
0.65
174.72
56.62
6.07
5.47
5.022
12.52
10

160
3700
5100
85
85
85
85
125
85
85

Amount
121
400
3,305
14,851
4,812
516
465
628
1,065
850

27,012

2
ements
H
1.075
0.3
0.3

Qty

160

2,369.77

3700

6,466.06

0.87
0.12
0.10
0.66

1.75
0.3
3.17
0.3

Amount

13.93
0.48
0.40

14.81
0.075
0.075
0.075
0.075

Rate

2.7
0.87
0.48

0.3
0.23
0.23
0.15
0.15

0.40
0.48
0.40
2.55
1.54

9.42

0.3
3.17
3.17
0.3
0.3
0.08
0.3
0.08
0.3
0.15
0.15

3.1
3.1
0.45
0.45
3.1

5100

48,041.62

27.98

300

8,395.29

1.18

64500

75,948.15

11.25

3500

39,370.94

48.91

210

10,270.68

64.51

117

7,547.19

64.51

70

4,515.41

48.91

50

2,445.40

12.09

400

4,835.16

9.10

500

4,548.95

9.10

350

3,184.27

3.24

3500

11,340.00

4.22

365

1,538.63

1.80
1.90
1.46
2.10
1.72
0.56
1.05
0.46
0.86
1.43
0.95
13.69

4.99
4.09
0.83
0.69
0.64

###
###

2.7
0.23

1.00

1500

1,500.00

10.25

230

2,356.56

10.25

500

5,122.95

###

2
ements

Qty

Rate

Amount

H
1.075
0.3
0.3

18.96
0.81
0.42

20.20
0.075
0.075
0.075
0.075

3700

10,238.11

5100

70,185.31

300

11,748.72

3.89
0.87
0.81
0.42
0.81
0.42
3.77
2.75

13.76

0.3
3.17
3.17
0.3
0.3
0.08
0.3
0.08
0.3
0.15
0.15

3,232.14

1.08
0.20
0.11
1.37

2.77
0.3
3.17
0.3
0.3
0.23
0.23
0.15
0.15

160

2.16
1.90
1.46
3.54
1.84
0.94
1.77
0.49
0.92
2.20
1.06
20.88

39.16

1.72

64500

110,954.71

15.63

3500

54,716.66

67.97

210

14,273.91

88.85

117

10,395.10

88.85

70

6,219.29

67.97

50

3,398.55

20.88

400

8,350.40

18.33

500

9,163.95

18.33

350

6,414.77

2.7

3.24

3500

11,340.00

0.23

4.22

365

1,538.63

1.00

1500

1,500.00

18.33

230

4,215.42

18.33

500

9,163.95

3.1
3.1
0.45
0.45
3.1

8.41
4.38
1.47
0.73
0.64

67.97
20.88

###

0 mm
ements

Qty

Rate

Amount

H
1.725
0.075
1.5
1.5
1.5

5.34
0.18
1.01
0.69
1.70
6.00

160
3700

854.94
675.32

3500
210

5,940.90
1,260.00

0.15

0.32

10000

3,197.40

###

x 1650 mm
ements
H
1.725
0.075
0.15
1.5

Qty

Rate

Amount

160
3700

706.56
543.90

1.5

4.42
0.15
0.20
1.04
1.23
3.45

5100
300

6,290.21
1,035.00

0.15
31.3 kg/m2

0.32
36.00

10000
85

3,197.40
3,059.58

###

1650 mm
ements

Qty

Rate

Amount

H
1.725
0.075

4.42
0.15
1.50
1.50

160
3700
3450
230

706.56
543.90
5,175.00
345.00

0.15

0.32

10000

3,197.40

9,967.86

x 3100 mm size
ements
H
0.28
0.05
0.5
0.5
0.15
0.2
0.2

Qty
3.30
8.58
0.59
0.95
0.65
1.29
2.89
1.52
1.24
2.76
288.7

Rate

Amount

160
365
3700

527.74
3,131.70
2,179.30

5100

14,723.70

300
64.5

18621.15

###
x 3300 mm size

ements

Qty

Rate

Amount

H
0.28
0.05
0.5
0.5
0.15
0.2
0.2

5.73
15.96
1.02
1.55
0.70
2.39
4.64
2.48
1.32
3.8
464.4

160
365
3700

916.61
5,825.40
3,785.10

5100

23,684.40

300
64.5

1,140.00
29953.8

###

Qty

H
1.1
0.1
1.2
1.2
1.2
0.9
0.9
0.9
0.9
0.05
0.05
0.1
0.1

Rate

13.08
0.59
3.75
6
3
375.00
0.56
0.30
0.47
0.24
0.25
0.17
0.60
0.19

160
3700
5100
300
300
64.5
3500
3500
1150
1150
3700
3700
4450
4450

Amount
2,093.41
2,177.23
19,125.00
1,800.00
900.00
24,187.50
1,967.02
1,061.39
538.20
279.45
936.66
620.68
2,670.00
834.38

###

Sub
Total

Contractor's
OH@P

Total

112.06

11.21

123

252.77

25.28

278

553.30

55.33

609

758.31

75.83

834

1078.64

107.86

1187

1090.29

109.03

1199

210.84

21.08

232

128.13

12.81

141

RATE ANALYSIS FOR CIVIL WORKS


EARTH WORK AND FILLING
Earth Work Excavation
Mass Excavation using
JCB within a lead of 5
Km

Description

Excavation in Or
Upto 1.50m

Excavation rate in m3

50.00

75.00

Total per Cum

50.00

75.00

Earth Filling
Filling
earth

Description
Material
Earth
Sand
Soling
Chips

with

available Filling
with
earth
brought from outside

Available

110.00

40.00%
0

110

Labour

40.00

40.00

Total
Consolidation

40.00

150.00

0.80

3.00

40.80

153.00

Water and curing charges


Total per Cum

2.00%

Disposal
Description

Carting away earth


within a lead of 100m

Disposal of excavated earthwith tipper

75.00

Total per Cum

75.00

PLAIN CEMENT CONCRETE


PLAIN CEMENT CONCRETE

CC 1:5:10
40mm & downsize

Description
Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Wastage

1.00%

Total for material in m3


Labour per m3
Cost of Mixer machine per m3
Shuttering Constant
Shuttering cost
Sub Total
Water and curing charges
Total per Cum

2.00%

CC 1:4:8
40mm & downsize

2.85
641.25
16.77
402.48
33.54
402.48
1446.21
14.46

3.5
787.50
16.51
396.24
33.02
396.24
1579.98
15.80

1460.67

1595.78

150.00

175.00

40.00

40.00

1650.67
33.01
1683.69

1810.78
36.22
1847.00

REINFORCED CEMENT CONCRETE


CAST-IN-SITU Concrete

CC 1:2:4 with 20mm and down size

Column footing

Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Total for material in m3
Labour per m3
Cost of Mixer machine per m3
Sub Total
Tools &plants
Water and curing charges

1.00%
2.00%

Column

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

165.00

300.00

45.00

45.00

2886.64
28.87
57.73

3021.64
30.22
60.43

Shuttering constant m2/M3


Shuttering cost
Total per Cum

2.00
193.68
3166.92

CC 1:1.5:3 with 20mm and down size

Column footing

Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Total for material in m3
Labour per m3
Cost of Mixer machine per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

1.00%
2.00%

CC 1:1:2 with 20mm and down size

Labour per m3
Cost of Mixer machine per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

1.00%
2.00%

Column

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

165.00

300.00

45.00

45.00

3213.94
32.14
64.28
2.00
193.68
3504.03

3348.94
33.49
66.98
13.00
1,678.56
5127.96

Column footing

Material
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Aggregate Constant (cft)
Aggregate Rate
Total for material in m3

13.00
1,678.56
4790.85

Column

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

165.00

300.00

45.00

45.00

3740.76
37.41
74.82
2.00
193.68
4046.66

3875.76
38.76
77.52
13.00
1,678.56
5670.59

READY MIX CONCRETE


(CC 1:4:8)
M7.5

Description
Material

CC 1:3:6
M10
2289

2364

Total for material in m3

2289.00

2364.00

Labour per m3

40.00
2329.00
23.29
46.58

40.00
2404.00
24.04
48.08

2398.87

2476.12

Tools &plants
Water and curing charges

1.00%
2.00%

Total per Cum

M15 grade concrete (CC1:2:4)

Column footing

Material
Total for material in m3
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

1.00%
2.00%

M20 grade concrete (CC1:1.5:3)

Total for material in m3


Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum
M25 grade concrete (CC1:1:2)

2670

2670

2670.00

2670.00

30.00

250.00

2700.00
27.00
54.00
2.00
193.68
2974.68

2920.00
29.20
58.40
13.00
1,678.56
4686.16

Column footing

Material

1.00%
2.00%

Column

Column

2799

2799

2799.00

2799.00

30.00

250.00

2829.00
28.29
56.58
2.00
193.68
3107.55

3049.00
30.49
60.98
13.00
1,678.56
4819.03

Column footing

Column

Material
Total for material in m3
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

1.00%
2.00%

M30

Total for material in m3


Labour per m3

1.00%
2.00%

M35

Total for material in m3


Labour per m3

M40
Material
Total for material in m3

2877.00

2877.00

30.00

250.00

2907.00
29.07
58.14
2.00
193.68
3187.89

3127.00
31.27
62.54
13.00
1,678.56
4899.37

1.00%
2.00%

Column

2978

2978

2978.00

2978.00

30.00

250.00

3008.00
30.08
60.16
2.00
193.68
3291.92

3228.00
32.28
64.56
13.00
1,678.56
5003.40

Column footing

Material

Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

2877

Column footing

Material

Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

2877

Column

3134

3134

3134.00

3134.00

30.00

250.00

3164.00
31.64
63.28
2.00
193.68
3452.60

3384.00
33.84
67.68
13.00
1,678.56
5164.08

Column footing

Column

3185

3185

3185.00

3185.00

Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

1.00%
2.00%

M45

30.00

250.00

3215.00
32.15
64.30
2.00
193.68
3505.13

3435.00
34.35
68.70
13.00
1,678.56
5216.61

Column footing

Material
Total for material in m3
Labour per m3
Sub Total
Tools &plants
Water and curing charges
Shuttering constant m2/M3
Shuttering cost
Total per Cum

1.00%
2.00%

Column

3240

3240

3240.00

3240.00

30.00

250.00

3270.00
32.70
65.40
2.00
193.68
3561.78

3490.00
34.90
69.80
13.00
1,678.56
5273.26

STEEL WORK
Description
Basic Rate for reinforcement steel
Wastage
Binding wire @ Rs.30 /kg (10kg - 1MT)
Material Cost
Labour rate in Kg
Sub total

Reinforcement steel

3.00%
10.00

Structural steel

26,000.00
780.00
380.00

32000
960

27,160.00

32960

2,250.00

14000

29,410.00

46,960.00

Size stone masonry in


CM 1:8
for Sub Structure

Size stone masonry in


CM 1:6
for Super Structure

MASONRY
Description

Material
Masonry constant ( Nos)

125

125

Masonry cost
Cement Constant (bags/m3)
Cement Rate
Sand Constant (cft)
Sand Rate
Boulders Constant (in cft)
Boulders Rate
Total for material in m3

500.00
1.8
405.00
17.28
414.72
6.00
54.00
1373.72

500.00
1.8
405.00
12.96
311.04
6.00
54.00
1270.04

Labour per m3

175.00

175.00

1,548.72
15.49
30.97
1,595.18

1,445.04
14.45
28.90
1,488.39

Sub Total
Scaffolding
Water and curing charges
Total per Cum

1.00%
2.00%

Coursed rubble masonry


Dressing Rs.4 per no of block
125 Nos * 4 = 500
Total per cum

500
1,988.39

PLASTERING

CM 1:4
12mm thick masonry in 15mm thick masonry in
CM 1:4
CM 1:4
(in m2) with lime
(in m2)

Description

Material
Cement Constant (bags/m2)
Cement Rate
Sand Constant (cft)
Sand Rate
Lime cost
Sponge

0.1
22.50
0.60
14.40
3.00

0.15
33.75
0.80
19.20
3.00

Total for material in m3

39.90

55.95

Labour per m2

43.04

43.04

82.94
0.83
1.66
85.43

98.99
0.99
1.98
101.96

Sub Total
Scaffolding
Water and curing charges
Total per SQM

1.00%
2.00%

Internal plastering

External plastering

(in m2) with lime

(in m2) with sponge

Material
Cement Constant (bags/m2)
Cement Rate
Sand Constant (cft)
Sand Rate
Lime cost
Sponge

0.18
40.50
0.90
21.60
3.00

Total for material in m3

65.10

70.00

Labour per m2

43.04

53.80

108.14
1.08
2.16
111.38

123.80
1.24
2.48
127.51

Sub Total
Scaffolding
Water and curing charges
Total per SQM

0.2
45.00
1.00
24.00
1.00

1.00%
2.00%

JOINERY
D1
Item No
Basic Cost of TW
Frame Section Size
Cutting Size
Plank
Wastage %
Frame Qty
Styles & Rails Sect
Cutting Size
Styles & Rails Qty
Planks Cutting Size
Planks Qty
Lipping Section
Lipping length
Lipping Qty
Total TW Qty
TW Cost
SS Hinges
T Bolt
Handle (Only fixing)
Lock (Only fixing)
Stoppers
PVC Bush
Eye piece
Labour for Making
Labour for fixing
Hold fasts
Glass
Shutters Area
Shutter Basic Rate

D2
Double Leaf

Main Door
1800
9 x 3

1800
9 x 2.5

0.2088
1
5
39.5
4.5 x 1.5
0.06
52.50
0.10
48
0
0
0.00
17.09
30763.36
600
875
125
250
150
40
75
3840
720
360
0
0
0

0.1766
0
5
23.5
0
0
0
0
0
0.0061
46
0.28
4.65
8374.16
600
875
125
250
150
40
0
2880
720
360
0
56
122

Shutter Rate
Size
OH & P @ 25%
Total
Cost per Sft

0
37198.36
48.00
9299.59
46497.95
968.71

6832
20662.16
56.00
5165.54
25827.70
461.21

Cost per Sqm

10423.29

4962.61

FLOORING

Description
Basic Rate of Material
Wastage %
Wastage
Nosing
Sub Total
Cement Constant
Cement Basic Rate
Cement Rate
Sand Constant
Sand Basic Rate
Sand Rate
Labour i/c polishing
Aquamix Sealer Coat
POP protection
Cleaning
Water and curing charges
Total per Sqft
Total per Sqm

Flooring in sft

2.00%

Italian Marble
Skirting 4 in rft
300.00
10.00
30.00

99.90
10.00
9.99

330.00
0.13
225.00
29.93
0.52
24.00
12.48
35.00
6.00
5.00
5.00
423.41
8.47
431.87

109.89
0.04
225.00
9.98
0.17
24.00
4.16
25.00
2.00
0.00
0.00
151.03
3.02
154.05

4646.95

505.27

Excavation in Ordinary soil


1.50m - 3.0m

Excavation in Soft rock


3.0m - 4.5 m

Upto 1.50m

1.50m - 3.0m

3.0m - 4.5 m

85.00

130.00

750.00

900.00

1050.00

85.00

130.00

750.00

900.00

1050.00

Sand filling

230mm thick soling

1101.83

1101.828
45.00
1146.83

22.94
1169.76

423.78
257.09
680.8732
250.00
930.87
65.22
996.09
19.92
1016.01
233.68

0.4559012
0.93502227

CC 1:3:6
20mm & downsize

CC 1:2:4
DPC 1:2:4 50mm thk
20mm & downsize 20mm & downsize

4.5
1012.50
16.10
386.40
32.20
772.80
2171.70
21.72

6.5
1462.50
15.33
367.92
30.66
735.84
2566.26
25.66

2193.42

2591.92

129.60

250.00

300.00

25.00

40.00

40.00

2483.42
49.67
2533.09

2931.92
58.64
2990.56

40.00
0.22
28.41
223.00
4.46
227.46

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64

250.00

110.00

110.00

150.00

275.00

45.00

45.00

45.00

45.00

45.00

2971.64
29.72
59.43

2831.64
28.32
56.63

2831.64
28.32
56.63

2871.64
28.72
57.43

2996.64
29.97
59.93

14.00
1,807.68
4868.47

Plinth Beam

###
1,807.68
4724.27

Roof Beams

8.00
860.80
3777.39

Roof slabs

10.00
1,614.00
4571.79

Staircase

15.00
1,936.80
5023.34

Lintel

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94

250.00

110.00

110.00

150.00

275.00

45.00

45.00

45.00

45.00

45.00

3298.94
32.99
65.98
14.00
1,807.68
5205.58

3158.94
31.59
63.18
###
1,807.68
5061.38

3158.94
31.59
63.18
8.00
860.80
4114.50

3198.94
31.99
63.98
10.00
1,614.00
4908.90

3323.94
33.24
66.48
15.00
1,936.80
5360.45

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76

250.00

110.00

110.00

150.00

275.00

45.00

45.00

45.00

45.00

45.00

3825.76
38.26
76.52
14.00
1,807.68
5748.21

3685.76
36.86
73.72
###
1,807.68
5604.01

3685.76
36.86
73.72
8.00
860.80
4657.13

3725.76
37.26
74.52
10.00
1,614.00
5451.53

3850.76
38.51
77.02
15.00
1,936.80
5903.08

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

2670

2670

2670

2670

2670

2670.00

2670.00

2670.00

2670.00

2670.00

175.00

60.00

60.00

60.00

250.00

2845.00
28.45
56.90
14.00
1,807.68
4738.03

2730.00
27.30
54.60
###
1,807.68
4619.58

2730.00
27.30
54.60
8.00
860.80
3672.70

2730.00
27.30
54.60
10.00
1,614.00
4425.90

2920.00
29.20
58.40
15.00
1,936.80
4944.40

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

2799

2799

2799

2799

2799

2799.00

2799.00

2799.00

2799.00

2799.00

175.00

60.00

60.00

60.00

250.00

2974.00
29.74
59.48
14.00
1,807.68
4870.90

2859.00
28.59
57.18
###
1,807.68
4752.45

2859.00
28.59
57.18
8.00
860.80
3805.57

2859.00
28.59
57.18
10.00
1,614.00
4558.77

3049.00
30.49
60.98
15.00
1,936.80
5077.27

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

2877

2877

2877

2877

2877

2877.00

2877.00

2877.00

2877.00

2877.00

175.00

60.00

60.00

60.00

250.00

3052.00
30.52
61.04
14.00
1,807.68
4951.24

2937.00
29.37
58.74
###
1,807.68
4832.79

2937.00
29.37
58.74
8.00
860.80
3885.91

2937.00
29.37
58.74
10.00
1,614.00
4639.11

3127.00
31.27
62.54
15.00
1,936.80
5157.61

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

2978

2978

2978

2978

2978

2978.00

2978.00

2978.00

2978.00

2978.00

175.00

60.00

60.00

60.00

250.00

3153.00
31.53
63.06
14.00
1,807.68
5055.27

3038.00
30.38
60.76
###
1,807.68
4936.82

3038.00
30.38
60.76
8.00
860.80
3989.94

3038.00
30.38
60.76
10.00
1,614.00
4743.14

3228.00
32.28
64.56
15.00
1,936.80
5261.64

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

3134

3134

3134

3134

3134

3134.00

3134.00

3134.00

3134.00

3134.00

175.00

60.00

60.00

60.00

250.00

3309.00
33.09
66.18
14.00
1,807.68
5215.95

3194.00
31.94
63.88
###
1,807.68
5097.50

3194.00
31.94
63.88
8.00
860.80
4150.62

3194.00
31.94
63.88
10.00
1,614.00
4903.82

3384.00
33.84
67.68
15.00
1,936.80
5422.32

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

3185

3185

3185

3185

3185

3185.00

3185.00

3185.00

3185.00

3185.00

175.00

60.00

60.00

60.00

250.00

3360.00
33.60
67.20
14.00
1,807.68
5268.48

3245.00
32.45
64.90
###
1,807.68
5150.03

3245.00
32.45
64.90
8.00
860.80
4203.15

3245.00
32.45
64.90
10.00
1,614.00
4956.35

3435.00
34.35
68.70
15.00
1,936.80
5474.85

Plinth Beam

Roof Beams

Roof slabs

Staircase

Lintel

3240

3240

3240

3240

3240

3240.00

3240.00

3240.00

3240.00

3240.00

175.00

60.00

60.00

60.00

250.00

3415.00
34.15
68.30
14.00
1,807.68
5325.13

3300.00
33.00
66.00
###
1,807.68
5206.68

3300.00
33.00
66.00
8.00
860.80
4259.80

3300.00
33.00
66.00
10.00
1,614.00
5013.00

3490.00
34.90
69.80
15.00
1,936.80
5531.50

Brick Masonry in CM
1:6 (230mm thick)
in m3

500

Brick Masonry in
CM 1:4 (115mm
thick)
in m2

50

Solid Block Masonry


Solid Block
Solid Block Masonry
in CM 1:6 (200mm Masonry in CM 1:6 in CM 1:6 (200mm
thick)
(200mm
thick)
8" thk
in m3
6" thk inthick)
m2
4" thk
in m2

63

12.5

12.5

1,750.00
1.3
292.50
9.36
224.64

175.00
0.2
45.00
0.96
23.04

1,921.50
1.3
292.50
9.36
224.64

287.50
0.2
45.00
1.44
34.56

218.75
0.2
45.00
0.96
23.04

2267.14

243.04

2438.64

367.06

286.79

175.00

35.00

225.00

40.00

35.00

2,442.14
24.42
48.84
2,515.40

278.04
2.78
5.56
286.38

2,663.64
26.64
53.27
2,743.55

407.06
4.07
8.14
419.27

321.79
3.22
6.44
331.44

CM 1:4
18mm thick masonry
20mm thick
25mm thick masonry
12mm thick
15mm thick masonry
in CM 1:4
masonry in CM 1:4
in CM 1:4
masonry in CM 1:5
in CM 1:5
(in m2)
(in m2)
(in m2)
(in m2) with lime
(in m2)

0.18
40.50
0.90
21.60
3.00

0.2
45.00
1.00
24.00

0.21
47.25
1.10
26.40

1.00

1.00

65.10

70.00

43.04
108.14
1.08
2.16
111.38

Ceiling plastering
(in m2) with lime

0.099
22.28
0.599
14.38
3.00

0.149
33.53
0.799
19.18
3.00

74.65

39.65

55.70

53.80

53.80

43.04

43.04

123.80
1.24
2.48
127.51

128.45
1.28
2.57
132.30

82.69
0.83
1.65
85.17

98.74
0.99
1.97
101.70

CM

0.18
40.50
0.90
21.60
3.00

65.10
48.42
113.52
1.14
2.27
116.93

D4
Single Leaf

D4a
Single Leaf
1800

9 x 2.5
0.1766
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
3.76
6774.55
300
350
125
250
150
40
0
2880
720
270
0
28.8
122

1800
5 x 2.5
0.1003
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
2.20
3959.24
300
350
125
250
150
40
0
2640
720
270
0
28.8
122

D4b
Single Leaf

D5
Single Leaf
1800

5 x 2.5
0.1003
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
2.20
3959.24
300
350
125
250
150
40
0
2640
720
270
150
28.8
122

1800
5 x 2.5
0.1003
0
5
19.5
0
0
0
0
0
0.0061
23
0.14
2.20
3959.24
300
350
125
250
150
40
0
2640
720
270
0
28.8
90

Flooring Sft

3513.6
15101.95
28.00
3775.49
18877.44
674.19

3513.6
12046.64
28.00
3011.66
15058.30
537.80

3513.6
12196.64
28.00
3049.16
15245.80
544.49

2592
11125.04
28.00
2781.26
13906.30
496.65

7254.33

5786.69

5858.74

5343.99

Indian White Marble


Skirting 4 Rft
For staircase
80.00
26.64
10.00
10.00
8.00
2.66

Flooring

88.00
0.13
225.00
29.93
0.52
24.00
12.48
22.00
3.00
0.00
2.00
157.41
3.15
160.55

29.30
0.04
225.00
9.98
0.17
24.00
4.16
12.00
2.00
0.00
2.00
59.44
1.19
60.63

80.00
10.00
8.00
30.00
118.00
0.13
225.00
29.93
0.52
24.00
12.48
24.00
3.00
0.00
2.00
189.41
3.79
193.19

1727.55

198.86

2078.76

Jaisalmer Marble
Skirting 4
90.00
29.97
10.00
10.00
9.00
3.00
99.00
0.13
225.00
29.93
0.52
24.00
12.48
22.00
0.00
2.00
2.00
167.41
3.35
170.75

32.97
0.04
225.00
9.98
0.17
24.00
4.16
12.00
0.00
3.00
2.00
64.10
1.28
65.38

1837.30

214.46

Excavation in Hard rock


Upto 1.50m

1.50m - 3.0m

3.0m - 4.5 m

1150.00

1500.00

1750.00

1150.00

1500.00

1750.00

Chejja

6.5
1462.50
19.93
478.30
30.66
735.84
2676.64
275.00
45.00
2996.64
29.97
59.93

14.00
1,506.40
4592.94

Chejja

8.2
1845.00
19.02
456.46
29.27
702.48
3003.94
275.00
45.00
3323.94
33.24
66.48
14.00
1,506.40
4930.05

Chejja

11.4
2565.00
13.41
321.84
26.83
643.92
3530.76
275.00
45.00
3850.76
38.51
77.02
14.00
1,506.40
5472.68

Chejja
2670
2670.00
250.00
2920.00
29.20
58.40
14.00
1,506.40
4514.00

Chejja
2799
2799.00
250.00
3049.00
30.49
60.98
14.00
1,506.40
4646.87
Chejja

2877
2877.00
250.00
3127.00
31.27
62.54
14.00
1,506.40
4727.21
Chejja
2978
2978.00
250.00
3228.00
32.28
64.56
14.00
1,506.40
4831.24
Chejja
3134
3134.00
250.00
3384.00
33.84
67.68
14.00
1,506.40
4991.92

Chejja
3185
3185.00

250.00
3435.00
34.35
68.70
14.00
1,506.40
5044.45

Chejja
3240
3240.00
250.00
3490.00
34.90
69.80
14.00
1,506.40
5101.10

Hollow Block
Masonry in CM 1:6
(200mm
8" thk inthick)
m3

63

Hollow Block Masonry


in CM 1:6 (200mm
thick)
6" thk
in m2

12.5

Hollow Block
Masonry in CM 1:6
(200mm
4" thk inthick)
m2

12.5

1,386.00
1.3
292.50
9.36
224.64

231.25
0.2
45.00
1.44
34.56

175.00
0.2
45.00
0.96
23.04

1903.14

310.81

243.04

200.00

35.00

30.00

2,103.14
21.03
42.06
2,166.23

345.81
3.46
6.92
356.18

273.04
2.73
5.46
281.23

CM 1:5
18mm thick masonry 20mm thick masonry 25mm thick masonry
12mm thick
15mm thick
in CM 1:5
in CM 1:5
in CM 1:5
masonry in CM 1:6 masonry in CM 1:6
(in m2)
(in m2)
(in m2)
(in m2) with lime
(in m2)

0.179
40.28
0.899
21.58
3.00

0.199
44.78
0.999
23.98

0.209
47.03
1.099
26.38

0.0984
22.14
0.60
14.36
3.00

0.1484
33.39
0.80
19.16
3.00

1.00

1.00

64.85

69.75

74.40

39.50

55.55

43.04

53.80

53.80

43.04

43.04

107.89
1.08
2.16
111.13

123.55
1.24
2.47
127.26

128.20
1.28
2.56
132.05

82.54
0.83
1.65
85.02

98.59
0.99
1.97
101.55

CM 1:6

mer Marble
Staircase
90.00
10.00
9.00

Sand Stone
Polished Slate Stone
Flooring(pathway) Flooring
Skirting 3
60.00
80.00
10.00
10.00
6.00
8.00

Calibrated Slate Stone


Flooring
26.64
80.00
10.00
10.00
2.66
8.00

99.00
0.13
225.00
29.93
0.52
24.00
12.48
24.00
0.00
4.00
3.00
172.41
3.45
175.85

66.00
0.13
225.00
29.93
0.52
24.00
12.48
20.00
0.00
0.00
3.00
131.41
2.63
134.03

88.00
0.05
225.00
11.25
0.52
24.00
12.48
10.00
7.00
4.00
3.00
135.73
2.71
138.44

29.30
0.03
225.00
5.63
0.17
24.00
4.16
10.00
9.00
4.00
3.00
65.09
1.30
66.39

88.00
0.05
225.00
11.25
0.52
24.00
12.48
10.00
9.00
5.00
4.00
139.73
2.79
142.52

1892.18

1442.20

1489.66

217.76

1533.56

CM 1:6
18mm thick
masonry in CM
(in1:6
m2)

0.1784
40.14
0.90
21.56
3.00

20mm thick
25mm thick
masonry in CM masonry in CM
(in1:6
m2)
(in1:6
m2)

0.1984
44.64
1.00
23.96

0.2084
46.89
1.10
26.36

1.00

1.00

64.70

69.60

74.25

43.04

53.80

53.80

107.74
1.08
2.15
110.97

123.40
1.23
2.47
127.10

128.05
1.28
2.56
131.89

ed Slate Stone
Skirting 3

Flooring
26.64
15.00
4.00
30.64
0.03
225.00
5.63
0.17
24.00
4.16
10.00
9.00
4.00
3.00
66.42
1.33
67.75
222.22

20mm Polished Granite


Skirting 3
for Staircase
Flooring
160.00
53.28
160.00
15.00
15.00
15.00
24.00
7.99
24.00
35.00
184.00
61.27
219.00
0.12
0.06
0.12
225.00
225.00
225.00
26.76
13.38
26.76
0.52
0.17
0.52
24.00
24.00
24.00
12.48
4.16
12.48
26.00
16.00
28.00
0.00
0.00
0.00
5.00
4.00
5.00
4.00
3.00
4.00
258.24
101.81
295.24
5.16
2.04
5.90
263.40
103.85
301.14
2834.19

340.62

3240.27

10mm Polished Granite


Skirting 3
80.00
26.64
10.00
10.00
8.00
2.66
88.00
0.12
225.00
26.76
0.75
24.00
18.00
18.00
0.00
5.00
3.00
158.76
3.18
161.93

29.30
0.06
225.00
13.38
0.25
24.00
6.00
15.00
0.00
4.00
3.00
70.68
1.41
72.10

1742.38

236.47

ished Granite
Ceramic tile
Pressed Clay Tile
for Staircase
Dadooing
Flooring
Skirting 3
Flooring
80.00
45.00
40.00
13.32
20.25
10.00
7.50
7.50
8.00
8.00
8.00
3.38
3.00
1.07
1.62
30.00
88.00
48.38
43.00
14.39
21.87
0.12
0.02
0.02
0.01
0.02
225.00
225.00
225.00
225.00
225.00
26.76
3.38
4.05
2.03
4.50
0.52
0.40
0.40
0.13
0.40
24.00
24.00
24.00
24.00
24.00
12.48
9.60
9.60
3.20
9.60
0.00
8.00
8.00
7.00
8.00
0.00
0.00
0.00
0.00
2.00
5.00
0.00
4.00
0.00
2.50
3.00
1.50
1.50
1.00
2.50
135.24
70.85
70.15
27.61
50.97
2.70
1.42
1.40
0.55
1.02
137.94
72.27
71.55
28.16
51.99
1484.24

777.59

769.91

92.37

559.41

Glass Mosaic Tiles


Porcelain Tiles
20mm thick Kota Slab
Flooring
Skirting 3
Flooring
Skirting 3
Flooring
Skirting 3
150.00
49.95
180.00
59.94
40.00
13.32
15.00
15.00
15.00
15.00
10.00
10.00
22.50
7.49
27.00
8.99
4.00
1.33
172.50
0.02
225.00
4.50
0.40
24.00
9.60
12.00
0.00
4.00
4.00
206.60
4.13
210.73

57.44
0.01
225.00
2.25
0.40
24.00
9.60
8.00
0.00
0.00
2.00
79.29
1.59
80.88

207.00
0.02
225.00
4.50
0.40
24.00
9.60
12.00
0.00
4.00
5.00
242.10
4.84
246.94

68.93
0.01
225.00
2.25
0.13
24.00
3.20
9.60
0.00
0.00
2.00
85.98
1.72
87.70

44.00
0.05
225.00
11.25
0.40
24.00
9.60
12.00
0.00
4.00
3.00
83.85
1.68
85.53

14.65
0.03
225.00
5.63
0.13
24.00
3.20
10.20
0.00
3.00
3.00
39.68
0.79
40.47

2267.48

265.28

2657.10

287.66

920.27

132.74

20mm thick Tandur Slab


Flooring
Skirting 3
100.00
33.30
10.00
10.00
10.00
3.33
110.00
0.05
225.00
11.25
0.40
24.00
9.60
12.00
0.00
4.00
4.00
150.85
3.02
153.87

36.63
0.03
225.00
5.63
0.13
24.00
3.20
12.00
0.00
3.00
3.00
63.46
1.27
64.72

1655.61

212.30

Analysis of Rate
A
RCC. WORK
1 R.C.C for M-30 as per Mix Design
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement
Sand

Bags
Cum

7.600
0.707

249.00
1166.00

Agg (AI+AII)

Cum

0.615

725.00

Labour:
Foreman
Beldar (M)
Coolie (F)
Mason

Each
Each
Each
Each

0.040
0.700
0.700
0.070

260.00
135.00
125.00
260.00

Waterman

Each

0.035

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Eqn

6.00%

Add for OH & C.P & Tax

15.00%

Total Amt.
Cost Per 1 Cum (Rs.)

1 Providing & laying R.C.C for M-15 (1:2:4)


Sr.
no

Item

Unit

Quantity

Rate
(Rs.)

A)

B)

C)

Materials:
1 Cement
2 Sand

Bags
Cum

6.300
0.440

0.00
1166.00

3 Agg (AI+AII)

Cum

0.880

725.00

Sub-Total of Material (M)


Labour:
1 Supervisor
2 Forman
3 Mason (Con.)
4 Unskilled Labours
5 Curing Labour
6 Mixer operator
7 Vibrator Operator

Each
Each
Each
Each
Each
Each
Each

8 Lift operator

Each

0.04
0.04
0.13
1.40
0.04
0.04
0.04
0.04

300.00
300.00
260.00
150.00
150.00
350.00
300.00
300.00

Sub-Total of Labour (L)


Eqn (E)
1 Mixer
2 Vibrator

hour
hour

0.50
0.50

3 Lift for material

hour

0.50

250.00
75.00
100.00

Sub-Total of Eqm (E)


Total (M+L+E)
Add for OH & C.P & Tax

15.00%

Total Amt.
Cost Per 1 Cum (Rs.)

2 R.C.C for M-25


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement
Sand

Bags
Cum

10.71
0.37

230.00
600.00

Agg (AI+AII)

Cum

0.74

625.00

Each

0.040

300.00

Sub-Total of Material (M)


B)

Labour:
Foreman

Beldar (M)
Coolie (F)
Mason

Each
Each
Each

0.700
0.700
0.070

200.00
200.00
260.00

Waterman

Each

0.035

200.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Eqn

8.00%

Add for OH & C.P & Tax

15.00%

Total Amt.
Cost Per 1 Cum (Rs.)

3 Providing,fabricating and fixing FE415 steel.for 1MT


Sr.No.

Descritption

Qty

Material
1 Rein.Steel Bars + 5% wastage
2 Binding Wire

Unit

1.05 Mt
5.00 Kg

Rate

28,000.00
30.00

Total for Material


Labours
1 Blacksmith

10.00 Day

250.00

2 Beldar

10.00 Day

150.00

Total for Labour


Total M+L
Add for Tools & Ele.2%
Add O.H.& Profit 15%
Total for 1M.T. 4 Rate Anly.for Supply ,fixing ,Removing Shuttering & Stagging 150 sqm
A

Material
1 18 mm thk.Marine Ply
2 Vertical Ballis (Saru)
3 Wood Patlis 25 x100mm

Sqm
Nos
Cum

230.00
150.00
2.40

495.00
144.00
28,248.00

4 4" thk.Chabbis
5 Shikanja

Cum
Nos

0.45
95.00

28,248.00
200.00

Nos
Nos

23.00
23.00

300.00
200.00

Total - M
Assuming usage 10times
B

Labours
6 Carpenter
7 Helper
Total- L
Total

C
D

2% Nails,Oils & Bolts Etc.


2% Equip.Ele Etc.
TotalM+L

Add 15% for O.H. & Profit


Total for 150 sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs
Date:

Tremix Paving of 75 mm thk per m2 using M25 grade concrete


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement
Sand
Aggregate
Colour Pigment & Hardener

Bags
Cum
Cum
Kgs

0.83
0.03
0.06
5.00

249.00
1158.00
698.00
30.00

Shuttering

Sqm

0.30

160.00

Labour:
Mason
Skilled Labour
Unskilled Labour

Each
Each
Each

0.01
0.06
0.06

250.00
135.00
125.00

Carpenter

Each

0.06

250.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)

C)

Mechinary
Mixer with Operater
Vibrator with Operater

Cum
Cum

0.12
0.12

200.00
100.00

Trimix Float Finish with Operater &


Labour

Sqm

1.00

135.00

Sub-Total of Mechinary
D)

Total (M+L)
Add W.C & Electricity

1.50%

Add for OH & C.P

15.00%

Cost per Sqm (Rs)


Cost per Sft (Rs)
B

BRICKWORK
1 9'' Brick work With Silpoz (1 :6)
Sr.
no
A)

Item

Unit

Materials:
9" thk Brick
Cement

Nos
Bags

Silpoz

Quantity

Rate
(Rs.)

110.00
0.35

3.12
249.00

Cft

2.10

65.27

Sft

10.76

7.00

Sub-Total of Material (M)


B)

Labour:

Labour
Sub-Total of Labour (L)
Total (M+L)
C)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

1.00%
1.00%
15.00%

4'' Brick work (1 :4) for 100 Sqm


Sr.
no
A)

B)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
4" thk Brick
Cement

Nos
Bags

5320.00
14.45

4.00
249.00

Silpoz

Cum

2.02

1175.00

Sub-Total of Material (M)


Labour:
Supervisor
Mason

Each
Each

0.50
16.00

300
260

Helper

Each

23.00

200.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

2 8" thk. Siporex Blocks (1:4) with Sand


Sr. No.

Descriptions
8" thk. Siporex Blocks (1:4)
8" Blocks (200x240x650 mm)
Less Discount @ 33%

Unit

Qty.

Rate (Rs.)

No.
No.

6.06
-6.06

157.00
51.81

No.

6.06

7.59

Bag

0.125

249

Total
Add Tax @ 12.5%
Add Transport @ 3000/- per Truck
Total
5% Wastage
Total Block Cost
Cement

Sand

C.ft.

0.50

32.26

Labour

S.ft.

10.76

7.00

Total per Sqm (Rs.)


Total per Sft (Rs.)

3 9" Thk.Brick Work 1:4 with Sand


Sr. No.

Descriptions
9" thk. Bricks (1:4)
9" thk. Bricks
5% Wastage
Total Bricks Cost
Cement
Sand
Labour

Unit

Qty.

Rate (Rs.)

No.

110.00

3.12

Bag
C.ft.

0.35
1.40

249.00
32.36

S.ft.

10.76

7.00

Total per Sq.mtr. (Rs.)


Total Per Sft (Rs.)
230 mm Brick Work C:M 1:5 for 10 cum
Sr.
no
A)

Item

Unit

Materials:
Cement
Sand

bag
Cum

Brick

Nos

Quantity

Rate
(Rs.)

25.00
4.38

249.00
1113.00

5000.00

3.70

Sub-Total of Material (M)


B)

Labour:
Mason

Each

8.50

235.00

Helper

Each

16.00

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P & Taxs
Total Amt.

0.50%
1.00%
15.00%

Cost for 10 Cum (Rs.)


Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)

PAINTS

Date : 130908
1 Comparative between Elastoseal Paint v ICI Weather Sheild Max

Sr.No
1
2
3
4
5

Description
Rate Per Sqft + Taxes
Labour cost per Sft
Total Amt
Protection Against Fungus & Algae
Guarantee (Water Proofing)
Colour

Coat

7
8
9

Water Requirement Ratio


Area Coverage
Polymer Certificate

ICI
Weather
Elastose Sheild Max
al Paint Acrylic
13.25
7.25
2.00
2.00
15.25
9.25
5 Years 7 Year
5 Years No Guarantee
White
Various Colour
1 Coat 1 Coat Self
Elasto
Priming +2
Prime 25 Coat
For 1 Litre
+ 2 Coat Weater
Paint +300
Elastose Sheild
Max
ml Clean
al+Stain
No Requi Water
er
26-28 Sqf 50-60 Sft/litre
In House Not Available

2 3 Coat Ext. Paint with Asian Weather Shield for 100 Sqm
Sr.
no
A)

Item

Quantity

Materials:
Prime Coat
Prime Paint one coat

Litre

6.00

80.00

Weather Sheild Paint 3 coat

Litre

30.00

165.00

Sub-Total of Material (M)


B)

Unit

Rate
(Rs.)

Labour:

Painter

Each

17.00

200.00

Male Coolie

Each

17.00

135.00

Male Coolie
C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

3 3 Coat Snowcem Cement Ext. Paint for 100 Sqm


Sr.
no
Item
Unit
A)
Materials:
Prime Coat
Prime Paint one coat
Litre
Paint 3 coat
Litre
Sub-Total of Material (M)
B)

C)

Labour:
Painter
Male Coolie
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

Each
Each

Quantity

Rate
(Rs.)

6.00
30.00

80.00
60.00

17.00
17.00

200.00
135.00

1.00%
1.00%
15.00%

Internal Paint with Asian Plastic Emulsion for 10Sqm (2Coates)


Sr.
no
Item
Unit
Quantity
A)
Materials:
Asian Brand

Rate
(Rs.)

Plastic Emulsion Paint

Litre

1.25

237.50

Each
Each

0.60
0.50

250.00
135.00

Sub-Total of Material (M)


B)

C)

Sr.
no
A)

Labour:
Painter
Male Coolie
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries & Contingencies
Brushes Sand Paper Putty Etc.
Add for Scaffolding Ladder Etc.
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

Materials:
Asian Brand
Primer
Oil Paint

3.00%
5.00%
2.50%
0.50%
15.00%

Internal Paint with oil Paint for 10Sqm (2Coates)


Rate
Item
Unit
Quantity
(Rs.)
Litre
Litre

0.75
1.25

100
180.00

Each
Each

0.60
0.50

250.00
135.00

Sub-Total of Material (M)


B)

C)

Labour:
Painter
Male Coolie
Sub-Total of Labour (L)
Total (M+L)
Add for Sundries & Contingencies
Brushes Sand Paper Putty Etc.
Add for Scaffolding Ladder Etc.
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

PLASTER

3.00%
5.00%
2.50%
0.50%
15.00%

Date :- 130908
1 12mm thk Internal Plaster with 5 mm thk Birla Putty CM 1:4 per 100 Sqm Material Only
Sr.no
A

Item

Unit

Internal Palster
1 Cement
2 Sand

5mm Birla Putty

Quantity

Rate (Rs.)

Bag
Cum

12.00
1.60

249.00
1139.00

Kg

72.00

72.00

Total Amt
5% Wastage
Total Amt with Wastage
Total Amt per Sqm
Total Amt per Sft

2 12mm thk Internal Plaster with 8 mm thk (1st POP) CM 1:4 per 100 Sqm material only
Sr.no
A

Item

Unit

Internal Palster
1 Cement
2 Sand

Quantity

Bag
Cum

8 mm 1 st POP

Kg

Rate (Rs.)

12.00
1.60

249.00
1139.00

115.00

5.50

Total Amt
5% Wastage
Total Amt with Wastage
Total Amt per Sqm
Total Amt per Sft

3 12 mm thk Internal Plaster with Birla Putty CM 1:4 per 100 m2


Sr.
no
A)

Item
Materials:
Cement

Unit
Bags

Quantity
12.00

Rate
(Rs.)
249.00

Sand

M3

1.60

1139.00

Brila Putty

Kg

600.00

29.00

Sub-Total of Material (M)


B)

Labour:
1st Class Mason
Belder

Each
Each

13.00
13.00

260.00
135.00

Waterman

Each

1.50

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
4 12 mm thk Internal Plaster with POP (1st) CM 1:4 per 100 m2
Sr.
no
A)

Item

Unit

Materials:
Cement
Sand

Bags
M3

Pop (1st)

Kg

Quantity

Rate
(Rs.)

12.00
1.60

249.00
1139.00

600.00

5.50

Sub-Total of Material (M)


B)

Labour:
1st Class Mason
Belder

Each
Each

13.00
13.00

260.00
135.00

Waterman

Each

1.50

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P

1.00%
1.00%
15.00%

Total Amt.
Cost For 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

5 Plaster (1:8) with Silpoz 15mm thk. Ex.Scaffolding


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

Bags

0.16

249.00

Silpoz

Cum

0.06

2304.94

10.76

7.5

Sub-Total of Material (M)


B)

Labour:

Labour for Plaster

Sft

Sub-Total of Labour (L)


Total (M+L)
C)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)
6 Plaster (1:4) with Sand 15mm thk.Ex.Scaffolding
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

Bags

0.16

249

sand

Cum

0.03

1139

Sub-Total of Material (M)

B)

Labour:

Labour for Plaster

Sft

10.76

7.5

Sub-Total of Labour (L)


Total (M+L)
C)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

7 12 mm thk Plaster C:M (1:3) for 100 Sqm


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement
Sand

bag
Cum

14.10
1.41

249.00
1113.00

Scaffolding

Sqm

100.00

25.00

Labour:
Mason

Each

17.50

260.00

Helper

Each

25.00

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add vat & Service tax
Add for OH & C.P & Taxs
Total Amt.
Cost for 100 Sqm (Rs.)

0.50%
1.00%
9.12%
15.00%

Cost Per 1 Sqm (Rs.)


Cost per 1 Sft (Rs.)
Gypsum Plaster Internal
unit 1 M2
Sr.no
Item
A
Material
1 Cement
2 Sand
3 Chemicals
4 Gypsum
Subtotal material

Unit

Quantity

Bags
M3
Lts
Bags

Rate

0.17
0.022
0.04
0.06

Add wastage

245.00
1113.00
155.00
155.00
5%

Total Material
B

Labour
Labour cost
Subtotal Labour
Total Labour

M2

45.00

Total M+L
Total Cost per M2
Add contigencies water electricity
Add T & P

2%
2%

Tax
Add profit

10%
15%
Total Cost per M2
Say

Rs.

8 20 mm thk Ext.Plaster C:M (1:3) for 100 Sqm up to 3.00 m ht.


Sr.
no
A)

Item
Materials:
Cement
Sand
Scaffolding

Unit

Qty.

Rate

bag
Cum
Sqm

20.00
2.40
100.00

249.00
1113.00
31.00

Each

17.50

260.00

Sub-Total of Material (M)


B)

Labour:
Mason

Helper

Each

25.00

135.00

Sub-Total of Labour (L)


Total (M+L)
Add W.C & Electricity 2%
Add for OH & C.P & Taxs 15%
Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

TILING
1 Marble Mosaic
Sr.
no
A)

Item

Unit

Materials:
Marble Mosaic

Sqm

White cement for slurry over base @


3.3 Kgs/Sqm
Sand

Tonne
Cum

Cement

Rate
(Rs.)

Quantity
1

162.00

0.0033
0.03

80000.00
1300.00

Bags

0.14

249.00

Labour:
Tile mason

Each

0.5

250.00

Coolie (M)

Each

0.5

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Cost Per Sqm


Cost Per Sft
2 Kota stone flooring
Sr.
no
A)

Item

Unit

Materials:
Kota Stone

Sqm

White cement for slurry over base @


3.3 Kgs/Sqm
Sand

Tonne
Cum

Cement

Rate
(Rs.)

Quantity
1

485.00

0.0033
0.03

80000.00
1300.00

Bags

0.14

249.00

Labour:
Tile mason

Each

0.5

250.00

Coolie (M)

Each

0.5

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Cost Per Sqm


Cost Per Sft

3 Glaze Ceramic
Sr.
no
A)

Item
Materials:

Unit

Quantity

Rate
(Rs.)

Glaze Ceramic

Sqm

250.00

White cement for slurry over base @


3.3 Kgs/Sqm
Sand

Tonne
Cum

0.0033
0.03

80000.00
1300.00

Cement

Bags

0.14

249.00

Labour:
Tile mason

Each

0.5

250.00

Coolie (M)

Each

0.5

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Cost Per Sqm


Cost Per Sft

4 Supply & Fixing PVC Door with Baroda Green Marble frame (2.1x 0.75) with hardware & lab.
Sr.no

Item
1 PVC Door Shutter
2 Laminate
3 baroda Green Marble (20 mm)
4 French Polish
a Wooden Frame
b Shutter Edge
5 Lipping Patti

Unit
Sqm
Sqm
-

Total Amt
5% Wastage on Marble
1

Quantity Rate (Rs.)


1.58
1750.00
1.05
538.00

Hardware
Fixing
Total Amt for 1.58 Smq

Total amt for 1 Sqm


Total Amt for 1 Sft

5 Baroda Green Marble


Sr.
no
A)

Item

Unit

Materials:
Baroda Green Marble

Sqm

White cement for slurry over base @


3.3 Kgs/Sqm
Sand

Tonne
Cum

Cement

Rate
(Rs.)

Quantity
1

538.00

0.0033
0.03

80000.00
1300.00

Bags

0.14

249.00

Labour:
Tile mason

Each

0.5

250.00

Coolie (M)

Each

0.5

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Cost Per Sqm


Cost Per Sft

6 Supply & Fixing PVC Door with Nazarana Marble frame (2.1x 0.75)
Sr.no

Item
1 PVC Door Shutter
2 Laminate

Unit
Sqm
-

Quantity Rate (Rs.)


1.58
1750.00
-

3 Nazarana Marble (20 mm)


4 French Polish
a Wooden Frame
b Shutter Edge

Rmt

5 Lipping Patti

5.25

538.00

Quantity

Rate
(Rs.)

Total Amt
5% Wastage on Marble
Total Amt for 1.58 Smq
Total amt for 1 Sqm
Total Amt for 1 Sft
7 Tremix Paving of 150mm thk per m2(1:1:2)
Sr.
no
A)

Item

Unit

Materials:
Cement
Sand

Bags
Cum

0.91
0.06

249.00
1139.00

Aggregate

Cum

0.12

753.35

Labour:
Mason
Female Coolie
Male Coolie

Each
Each
Each

0.02
0.12
0.12

250.00
200.00
200.00

Waterman

Each

0.05

200.00

Sub-Total of Labour (L)


Mechinary
Mixer
Vibrator

Sqm
Sqm

0.15
0.15

0.00
0.00

Trimix

Sqm

1.00

0.00

Sub-Total of Material (M)


B)

C)

Sub-Total of Mechinary (Me)


D)

Total (M+L+Me)
Add W.C & Electricity
Add for OH & C.P
Cost per Sqm (Rs)
Cost per Sft (Rs)

1.50%
15.00%

8 Con. Block Paving of 140mm thk per m2


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Paving Block
Sand

Nos
Cum

40.00
0.05

14.00
1139.00

Fine Sand

Cum

0.01

1139.00

Labour:
Mason

Each

0.02

250.00

Male Coolie

Each

0.11

135.00

Sub-Total of Material (M)

B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add W.C & Electricity

1.50%

Add for OH & C.P

15.00%

Cost per Sqm (Rs.)


Cost per Sft (Rs.)

9 Vitrified Tiles
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Tile (600 mm X 600 mm) + 5%
Wastage
Sand

Sqm
Cum

1
0.03

300.00
600.00

Cement

Bags

0.2

230.00

Each

0.5

250.00

Sub-Total of Material (M)


B)

Labour:
Tile mason

Coolie (M)

Each

0.5

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Cost Per Sqm


Cost Per Sft
10 Wooden Tile Flooring
Sr.
no
A)

Item

Unit

Rate
(Rs.)

Quantity

Materials:
Tile (600 mm X 600 mm) + 5%
Wastage

Sqm

White cement for slurry over base @


3.3 Kgs/Sqm
Sand

Tonne
Cum

Cement

3766.00

0.0033
0.03

80000.00
1139.00

Bags

0.14

249.00

Labour:
Tile mason

Each

0.5

250.00

Coolie (M)

Each

0.5

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Cost Per Sqm


Cost Per Sft

11 20mm thk Granite cutting & fixing with sand for 5 Sqm C:M 1:6 Curved Surface Lab.only
Labour Only
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Sand

Cum

0.17

1113.00

Labour:
Tile mason
Helper

Each
Each

6.73
6.73

250.00
135.00

Supervisor

Each

1.00

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.
Add Mortar for pointing in
White/colour cement

0.50%
0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add Service Tax
Add W.C & Electricity

5.00%
12.36%
1.00%

Add for OH & C.P

15.00%

Cost Per 5 Sqm


Cost per Sqm
Cost Per Sft

12 20mm thk Granite cutting & fixing with sand for 5 Sqm CM 1:6 Flat Surface lab.only
Sr.
no
A)

Item
Materials:

Unit

Quantity

Rate
(Rs.)

Sand

Cum

0.17

1113.00

Labour:
Tile mason
Helper

Each
Each

5.97
5.97

250.00
135.00

Supervisor

Each

1.00

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add Service Tax
Add W.C & Electricity

5.00%
12.36%
1.00%

Add for OH & C.P

15.00%

Cost Per 5 Sqm


Cost per Sqm
Cost Per Sft

13 20mm thk Pebble fixing with sand for 100 Sqm Lab.only
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Sand

Cum

5.52

1113.00

Labour:
Tile mason
Helper

Each
Each

10.5
20

250.00
135.00

Supervisor

Each

2.00

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add Service Tax
Add W.C & Electricity

5.00%
12.36%
1.00%

Add for OH & C.P

15.00%

Cost Per 100 Sqm


Cost per Sqm
Cost Per Sft

14 Granite Skirting cutting & fixing with sand of 4" for 50 Rmt CM 1:6 lab. only
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Sand

Cum

0.17

1113.00

Labour:
Tile mason
Helper

Each
Each

6.73
6.73

250.00
135.00

Supervisor

Each

1.00

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add Carriage of Tiles cement etc.

0.50%

Add Mortar for pointing in


White/colour cement

0.50%

Add for sundires i/e Tool & Plants &


Contingencies
Add Service Tax
Add W.C & Electricity

5.00%
12.36%
1.00%

Add for OH & C.P

15.00%

Cost Per 50 Rmt


Cost per Rmt
Cost Per Rmt

15 IPS Flr. 30mm thk.for 100Sqm


Sr.No. Description
Material
IPS Flr.1:6 (30mm thk.)
a Cement
b Fine & Coarse Agg.
c Flooting Cement slurry 3Kg/Sqmt

Unit

Qty

Rate

Bag
Cum
Bag

15.91
3.30
6.00

249.00
1,158.00
249.00

Nos
Nos
Nos

25.00
35.00
1.00

250.00
200.00
300.00

Total
Add 5 % Wastage
Total M
Labour
1 Mason
2 Mazdoor
3 Supervisor/HeadMason
Total L
Total M+L

Add for Vat & Service Tax 9.12%


Contractors Profit & O.H.15%
G.Total for 100Sqm
Rate For 1Sqm
Rate For 1Sft

DOOR & WINDOW


1 Supply & Fixing Wooden Door with Wooden frame (2.1x 0.75) with fixing and hardware
Sr.no

Item
1 Block Board
2 Laminate
3 Wooden Frame
4 French Polish

Unit
Sqm
Sqm
Rmt

Quantity Rate (Rs.)


1.58
715.00
1.58
667.00
5.25
497.00

a Wooden Frame
b Shutter Edge

Sqm
Rmt

1.98
5.70

48.50
24.60

5 Lipping Patti

Rmt

5.70

82.00

Total Amt
5% Wastage
1

Hardware

Fixing
Total Amt for 1.58 Smq
Total Amt for 1 Sqm
Total Amt for 1 Sft
Date :- 130908

2 Supply & Fixing Wooden Door with Wooden frame (2.1x 0.75)
Without labour & hardware
Sr.no
Item
1 Block Board
2 Laminate
3 Wooden Frame
4 French Polish
a Wooden Frame
b Shutter Edge

Unit
Sqm
Sqm
Rmt

5 Lipping Patti

Quantity Rate (Rs.)


1.58
715.00
1.58
667.00
5.25
497

Sqm
Rmt

1.98
5.7

48.5
24.6

Rmt

5.7

82

Total Amt
5% Wastage
Total Amt for 1.58 Smq
Total Amt for 1 Sqm
Total Amt for 1 Sft

3 Jindal Windows Sections 3 track(1.83x1.2)


Sr.
no
A)

Item
Materials:
Windows 3 track
Handles
6mm clear float glass

Unit
Kg
Nos
Sqm

Quantity
15.74
2.00
6.39

Rate
(Rs.)
175.00
50.00
387.36

PVC Gasket
Wheel
Screws

Rmt
Nos
Cent

51.10
8.00
50.00

16.40
10.00
1.00

Power Coated

Kg

15.74

43.75

Sub-Total of Material (M)


B)

Labour:
Carpanter
Mistry

Each
Each

1.89
1.10

260.00
260.00

Helper

Each

1.10

135.00

Sub-Total of Labour (L)


Total (M+L)
C)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 2.19 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

4 Wooden Door (0.75X2.1)


Sr
no
A)

Item

Quantity

Materials:
Marine Ply shutter (35mm thick)
Laminate
Wooden Frame
Hinges
Tower bolt
Handles

Sqm
Sqm
Rmt
Nos
Nos
Nos

1.58
3.15
4.95
3.00
1.00
2.00

1291.20
235.00
211.68
75.00
75.00
120.00

Screws

Cent

48.00

1.00

Sub-Total of Material (M)


B)

Unit

Rate
(Rs.)

Labour:

Carpenter
Beldar

Each
Each

0.40
0.40

260.00
135.00

Mistry

Each

0.05

260.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Sundries & Contingencies


Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

5 FRP with Marble Frame Door (0.75X2.1)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
35 mm thick FRP Door with Vinayl
Finsih
Marble Frame (60 mm wide)
Hinges
T-tower bolt
Handles

Sqm
Rmt
Nos
Nos
Nos

1.58
4.95
3.00
1.00
2.00

3550.80
1076.00
75.00
75.00
120.00

Screws

Cent

48.00

1.00

Labour:
Carpenter
Beldar

Each
Each

0.40
0.40

260.00
135.00

Mistry

Each

0.05

260.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

6 MS DOOR (1.2X2.1) Fabricated


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
MS Angle (50x30x5mm)
20 G Ms Sheet
Hinges
Tower bolt
Handles

Rmt
Sqm
Nos
Nos
Nos

7.80
5.04
3.00
1.00
1.00

165.00
400.00
75.00
75.00
125.00

Screws

Cent

48.00

1.00

Labour:
Fabricated
Beldar

Each
Each

2.00
2.00

225.00
135.00

Mistry

Each

0.05

260.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 2.52 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

7 MS DOOR (1.2X2.1) Factory Made

1.00%
1.00%
15.00%

Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Door
Hinges
Tower bolt
Handles

Sqm
Nos
Nos
Nos

2.52
3.00
1.00
1.00

1829.20
75.00
75.00
125.00

Screws

Cent

48.00

1.00

Labour:
Carpenter

Each

0.40

225.00

Beldar

Each

0.40

135.00

Mistry

Each

0.05

260.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 2.52 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

8 Jindal Windows Sections 4 track(3.65x1.75)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws

Kg
Nos
Sqm
Rmt
Nos
Cent

40.87
2.00
6.39
21.30
8.00
50.00

210.00
150.00
387.36
16.40
10.00
1.00

Anodizing 20-22 micron

Sqm

6.39

215.20

Sub-Total of Material (M)


B)

Labour:
Carpanter
Mistry

Each
Each

5.50
3.20

260.00
260.00

Helper

Each

3.20

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost for 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

9 Euro Windows Sections 4 track(3.65x1.75)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws

Kg
Nos
Sqm
Rmt
Nos
Cent

40.87
2.00
6.39
21.30
8.00
50.00

210.00
150.00
387.36
16.40
10.00
1.00

Anodizing 20-22 micron

Sqm

6.39

215.20

Labour:
Carpanter
Mistry

Each
Each

5.50
3.20

260.00
260.00

Helper

Each

3.20

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)

C)

Add for Sundries & Contingencies


Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

10 Windows Sections 4 track (3.65x1.75)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws

Kg
Nos
Sqm
Rmt
Nos
Cent

40.87
2.00
6.39
21.30
8.00
50.00

210.00
150.00
387.36
16.40
10.00
1.00

Anodizing 20-22 micron

Sqm

6.39

215.20

Labour:
Carpanter
Mistry

Each
Each

5.5
3.2

260.00
260.00

Helper

Each

3.2

135.00

Sub-Total of Material (M)

B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

1.00%
1.00%
15.00%

11 Windows Sections (3.65x1.75) with Insect Net


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Windows 4 track
Handles
6mm clear float glass
Alu. Insect Net
PVC Gasket

Kg
Nos
Sqm
Sqm
Rmt

40.87
2.00
3.19
3.19
21.30

210.00
150.00
387.36
215.20
16.40

Wheel
Screws

Nos
Cent

8.00
50.00

10.00
1.00

Anodizing 20-22 micron

Sqm

6.39

215.20

Labour:
Carpanter
Mistry

Each
Each

5.5
3.2

260.00
260.00

Helper

Each

3.2

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

12 7' Wooden Door (1.2X2.1)


Sr.
no
A)

Item
Materials:

Unit

Quantity

Rate
(Rs.)

Marine Ply shutter (35mm thick)


Laminate
Wooden Frame
Hinges
Tower bolt
Handles
Rubber buffer

Sqm
Sqm
Rmt
Nos
Nos
Nos
Nos

2.52
5.04
5.40
3.00
1.00
2.00
1.00

1291.20
235.00
211.68
75.00
225.00
350.00
15.00

Screws

Cent

48.00

1.00

Labour:
Carpenter
Beldar

Each
Each

0.40
0.40

260.00
135.00

Mistry

Each

0.05

260.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

13 Wooden Door (1.2X2.4)


Sr.
no
A)

Item
Materials:
Marine Ply shutter (35mm thick)
Laminate
Wooden Frame
Hinges
Tower bolt
Handles
Rubber buffer

Unit
Sqm
Sqm
Rmt
Nos
Nos
Nos
Nos

Quantity
2.88
5.76
5.60
3.00
1.00
2.00
1.00

Rate
(Rs.)
1291.20
235.00
211.68
75.00
225.00
350.00
15.00

Screws

Cent

48.00

1.00

Labour:
Carpenter
Beldar

Each
Each

0.60
0.60

260.00
135.00

Mistry

Each

0.10

260.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

14 Aluminum Louvers (0.97x2.8)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Top & bottom horizontal frame
127x38.1x1.74mm Wt/rmt= 1.518
Vertical frame 50x50x2mm thk (4' c/c)
Wt/rmt = 1.036
Sutter
Frame wt/rmt =0.593
6mm clear float glass (0.97x 2.8)
Handles
PVC Gasket
Hinges
Tower bolt
Alu.Stopper
Screws

Kg
Sqm
Nos
Rmt
Nos
Nos
Nos
Cent

13.22
2.72
1.00
7.54
3.00
1.00
1.00
50.00

210.00
387.36
150.00
16.40
100.00
225.00
225.00
1.00

Anodizing 20-22 micron

Sqm

2.72

215.20

Sub-Total of Material (M)

B)

Labour:
Carpanter
Mistry

Each
Each

5.5
3.2

260.00
260.00

Helper

Each

3.2

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add Vat & Serivce Tax
Add W.C & Electricity

1.00%
9.12%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 2.72 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

15 Windows Sections 4 track (3.65x1.75)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Windows 4 track
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws

Kg
Nos
Sqm
Rmt
Nos
Cent

40.87
2.00
6.39
21.30
8.00
50.00

210.00
150.00
387.36
16.40
10.00
1.00

Anodizing 20-22 micron

Sqm

6.39

215.20

Labour:
Carpanter
Mistry

Each
Each

5.5
3.2

260.00
260.00

Helper

Each

3.2

135.00

Sub-Total of Material (M)

B)

Sub-Total of Labour (L)

C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 6.39 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

16 Windows RCC Louvers (0.6 x 0.75)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Frame of RCC (0.6 x 0.75= 0.42)

Nos

1.00

364.50

Labour:
Mason

Each

1.00

260.00

Helper

Each

2.00

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add vat & Service tax
Add for OH & C.P & Taxs
Total Amt.
Cost for 0.42 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

FALSE CEILING

0.50%
1.00%
9.12%
15.00%

1 Rate Anly for Acrylic False Ceiling 3.55sqmt.


Material
1 L-Patti 18 guage
2 T-Patti
3 Acrylic Sheet 4mm
4 Powder Coating

Rmt
Rmt
Sqm
Sqm
Sqm

12.24
6.98
3.55
1.22
0.70

67.00
67.00
603.00
124.00
124.00

nos.
nos.

2.25
3.50

260.00
165.00

Rmt
Rmt
Sqm

12.24
6.98
3.55

67.00
67.00
75.00

nos
nos

2.00
2.50

275.00
200.00

Total
Add 5 % wastage
Screws & Suspenderes 5%
Total-M
Labours
Carpenter
Male majdoor
Total-L
Total M+L
2% for Equip.Ele.etc.
Add 15% for O.H.& Profit
Total for 3.55sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs
2 Rate Anly for POP False Ceiling 3.55 sqmt.
Material
L-Patti 18 guage
T-Patti
POP Sheet 4mm
Total
Add 5% for Wastage
Screws & Suspenderes 5%
Total -M
Labours
Carpenter
Male majdoor
Total-L
Total-M+L

2% for Equip.Ele.etc.
Add 15% for O.H.& Profit
Total for 3.55 sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs

3 Rate Anly for Gypsum False Ceiling 3.55 sqmt.


Material
L-Patti 18 guage
T-Patti
Gypsum Sheet 12.5mm

Rmt
Rmt
Sqm

12.24
6.98
3.55

67.00
67.00
135.00

nos
nos

2.00
2.50

260.00
165.00

Total
Add 5% for Wastage
Screws & Suspenderes 5%
Total -M
Labours
Carpenter
Male majdoor
Total-L
Total-M+L
2% for Equip.Ele.etc.
Add 15% for O.H.& Profit
Total for 3.55 sqm.Rs
Total for 1 sqm.Rs
Total for 1 sqft.Rs
H

PIPES & FITTING

1 UPVC Pipe for 100 Rmt.


Sr.No.

Description

Unit

Qty

Rate

Material
1 50 mm UPVC Pipe
2 Coupling

Rmt
Nos

100.00
17.00

55.00
14.00

Labour
1 Fitter
2 labour

Nos
Nos

1.00
1.00

200.00
150.00

Total
Add 2% Contengencies
Add Vat & S.Tax 9.12%
Add OH & Profit 15%
G.Total
Rate Per/Rmt.

2 G.I.Pipe for 100 Rmt.


Sr.No.

Description
Material
1 50 mmG.I. Pipe
2 Coupling

Unit
Rmt
Nos

100.00
17.00

276.00
97.00

Labour
1 Fitter
2 Labour

Nos
Nos

1.00
1.00

200.00
150.00

Total
Add 2% Contengencies
Add Vat & S.Tax 9.12%
Add OH & Profit 15%
G.Total
Rate Per/Rmt.

Qty

Rate

3 HDPE Pipe for 100 Rmt.


Sr.No.

Description
Material
1 50 mmHDPE Pipe

Unit

Qty

Rate

Rmt

100.00

133.00

Labour
1 Fitter

Nos

1.00

200.00

Total
Add 2% Contengencies
Add Vat & S.Tax 9.12%
Add OH & Profit 15%
G.Total
Rate Per/Rmt.

4 PVC 110mm dia.of 6kgf/cm2 for 6 Rmt with Pocket in wall & Grouting
Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Pipe (6M)
Bend
Coupler
PVC Solution

rmt
No
No
Ls

1.00
1.00
1.00
1.00

1562.00
260.00
75.00
100.00

Grouting

No

1.00

225.00

Each
Each

1.00
1.00

200.00
135.00

Sub-Total of Material (M)


B)

Labour:
Plumber
Helper
For trenching and refilling etc:-

Helper

Each

1.00

135.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Sundries & Contingencies


Add W.C & Electricity
Add Vat & Service Tax

0.50%
1.00%
9.12%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 6 Rmt(Rs.)
Cost Per 1 Rmt (Rs.)
Cost per 1 Rft (Rs.)

Date: 3rd D
5 160 mm dia Supreme UPVC (6 kg pressure) Pipe line (6 Mtr Long)
Sr.
no
A)

B)

Item

Unit

Materials:
1 Pipe (6kg)
2 Bend
3 Coupler

Nos
Nos
Nos

4 Pvc Solution

Ls

Quantity
1.00
1.00
1.00

3297.00
1108.00
230.00

Ls

100.00

6.00

90.00

Sub-Total of Material (M)


Labour:
Labour Cost

Mts

Sub-Total of Labour (L)


C)

Rate
(Rs.)

Total (M+L)
Add
Vat & other Taxes

5%

Contractor Profit

10%

Total Amt. for 6 Rmt (Rs.)


Cost Per 1 Rmt (Rs.)
Cost per 1 Rft (Rs.)

6 160 mm dia Supreme Eco-Drain Pipe line (6 Mtr Long)


Sr.
no
A)

B)

Item

Unit

Materials:
1 Pipe (6kg)
2 Bend
3 Coupler

Nos
Nos
Nos

4 Solution

Ls

Quantity

Rate
(Rs.)

1.00
1.00
1.00

1914.00
1108.00
230.00

Ls

100.00

6.00

90.00

Sub-Total of Material (M)


Labour:
Labour Cost

Mts

Sub-Total of Labour (L)


C)

Total (M+L)
Add
Vat & other Taxes

5%

Contractor Profit

10%

Total Amt. for 6 Rmt (Rs.)


Cost Per 1 Rmt (Rs.)
Cost per 1 Rft (Rs.)
Note.1. Rate of Prince make is much higher then the Supreme make
2. Rate: Prince make 100 mm dia 3 mtr long is Rs.2046.00
3. Rate : Supreme make 110 mm dia 6 mtr long is Rs.1562.00

SANITARY WARE

1 Wall Mounted W.C with 6.5 litres P.V.C Flush Tank


Sr.
no
A)

Item
Materials:
W.C

Unit
Nos

Quantity
1.00

Rate
(Rs.)
4500.00

6.5 litres PVC flush Tank

Nos

1.00

900.00

Clamp

Nos

4.00

75.00

Labour:
Plumber
Mistry

Each
Each

1
0.5

225.00
260.00

Helper

Each

135.00

Sub-Total of Material (M)

B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add Vat & Service Tax

9.12%

Add for OH & C.P

15.00%

Total Amt.
Cost Per No (Rs.)

FABRICATION

Date: 3rd D
1 Fabricated M.S. Man- hole Cover
Sr.
no
A)

B)

Item

Unit

Quantity

Materials:
M.S Angle (65x65x6mm)

Rmt

8.00

319.00

Chequred Plate 10mm

Sqm

1.00

4000.00

Sub-Total of Material (M)


Labour:
Fabricated

Each

2.00

225.00

Coolie

Each

1.00

135.00

Sub-Total of Labour (L)


C)

Rate
(Rs.)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P

1.00%
1.00%
15.00%

Total Amt.
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)

2 Ductile Iron Man-hole Cover


Sr.
no
A)

B)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
M.S Angle (65x65x6mm)

Rmt

2.60

319.00

Ductile Iron cover (0.4x0.9)

No

1.00

6124.00

Sub-Total of Material (M)


Labour:
Fabricated

Each

1.00

225.00

Coolie

Each

1.00

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

10.00%

Total Amt. for .36 sqm


Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)

VIDEO DOOR PHONE


1 B/W Video Door Phone
Sr.
no

Item
1 B/W Video Door Phone with Fitting

Color Video Door Phone

Unit
Nos

Quantity
1.00

Rate
(Rs.)
7000.00

Sr.
no

Item

Unit

1.00 Color Video Door Phone with fitting

Quantity

Nos

1.00

Rate
(Rs.)
13000.00

WATERPROOFING
1 Inclined Surface Gradient Available

Date
Sr.No. Description
Material
For 100 Sqmt.
1 Dr Fixit Pidiproof 2k for BaseCoat
2 Screed Plaster 1:3 (15mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag

Unit

Kg

Qty

Rate

154.00

110.00

Bag
Cum
Kg.

18.00
1.80
3.60

249.00
1,158.00
84.00

Nos
Nos
Nos

15.00
21.00
0.63

250.00
150.00
300.00

Total
Add 5 % Wastage
Total M
Labour
1 Mason
2 Mazdoor
3 Supervisor/HeadMason
Total L
Total M+L

Add for Vat & Service Tax 9.12%


Contractors Profit & O.H.15%
G.Total for 100Sqm
Rtae For 1Sqm
Rtae For 1Sft

2 Flat Surface Gradiant Not Available

Date
Sr.No. Description
For 100Sqm
A
Material
1 Dr Fixit Pidiproof 2k for Base Coat
2 Screed Plaster 1:3 (15mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag
3 BrickBat 110 mm thk.70%

Unit

Kg

Qty

Rate

154.00

110.00

Bag
Cum
Ltrs.
Cum

18.00
1.80
3.60
7.70

249.00
1,158.00
84.00
1,129.00

Mortar 30% of 1:3 & add 25 % for Wet


4 Mortar
Cum
a Cement
Bag
b Fine & Coarse Agg.
Cum
c Dr Fixit Pidiproof LW 200ml Per Bag Ltrs.

4.13
30.00
3.09
6.00

249.00
1,158.00
84.00

37.00
59.00
2.00

250.00
150.00
300.00

Total
Add 5% For Wastage
Total M
B

Labour
1 Mason
2 Mazdoor
3 Supervisor /Head Mason

Nos
Nos
Nos
Total L
Total M+L

Add for Vat & Service Tax 9.12%


Contractors Profit & O.H.15%
G.Total for 100Sqm
Rate For 1Sqm
Rate For 1Sft
3 Inclined Surface Gradient Available (40mm thk.Screed plaster)

Date
Sr.No. Description
Material
For 100 Sqmt.
1 Dr Fixit Pidiproof 2k for BaseCoat
2 Screed Plaster 1:3 (40mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag

Unit

Kg

Qty

Rate

154.00

110.00

Bag
Cum
Kg.

48.00
4.80
9.60

249.00
1,158.00
84.00

Nos
Nos
Nos

25.00
35.00
1.00

250.00
150.00
300.00

Total
Add 5 % Wastage
Total M
Labour
1 Mason
2 Mazdoor
3 Supervisor/HeadMason
Total L
Total M+L

Add for Vat & Service Tax 9.12%


Contractors Profit & O.H.15%
G.Total for 100Sqm
Rate For 1Sqm
Rate For 1Sft

Landscaped Area

DateSr.No. Description
For 100Sqm
A
Material
1 Filling 25 Sqm 1:4 25mm thk
Cement

Unit

Bag

Qty

Rate

8.00

249.00

Coarse Agg.
Cum
2 Dr Fixit Pidiproof 2k for Base Coat
Kg
3 Screed Plaster 1:4(15mm thk.)
a Cement
Bag
b Fine & Coarse Agg.
Cum
c Dr Fixit Pidiproof LW 200ml Per Bag Ltrs.
4 BrickBat 110 mm thk.70%
Cum
4 Mortar 30% of 1:4 & add 25 % for Wet Cum
a Cement
Bag
b Fine & Coarse Agg.
Cum
c Dr Fixit Pidiproof LW 200ml Per Bag Ltrs.
5 Metal 15 mm thk 70%
Cum
Mortar 30% of 1:4 & add 25 % for Wet Cum
a Cement
Bag
b Sand
Cum
6 Rough Finish Plaster 1:4(15mm thk.)
a Cement
Bag
b Fine & Coarse Agg.
Cum

0.78
154.00

725.00
110.00

18.00
2.40
3.60
7.70
4.13
30.00
4.12
6.00
1.05
0.56 30.00
4.12

249.00
1,158.00
84.00
1,129.00
249.00
1,158.00
84.00
1,158.00

18.00
2.40

249.00
1,158.00

50.00
77.00
4.00

250.00
135.00
300.00

249.00
1,158.00

Total
Add 5% For Wastage
Total M
B

Labour
1 Mason
2 Mazdoor
3 Supervisor /Head Mason

Nos
Nos
Nos
Total L
Total M+L

Contractors Profit & O.H.10%


G.Total for 100Sqm
Rate For 1Sqm
Rate For 1Sft

Demolishing Brick Work inculiding disposal of material with in 50 m lead

Date
Sr.No. Description
Unit
Detail of cost of demolihing 1 cum brick work
Labour
2 Mazdoor (M)
Nos
3 Mazdoor (F)
Nos
4 Supervisor/HeadMason
Nos

Qty

Rate

0.95
0.85
0.10

135.00
125.00
300.00

Total L
Total L
Add for Cost & Sharpening of
Chisels sledge hammers
Add for Service Tax
Add for sundries & Contingencies
Contractors Profit & O.H.15%

5%
10.30%
3%
15%

G.Total for 1 Cum


Rate For 1 Cum
Rate For 1 Cft

Dismantling Doors, Windows of area 3 sqm and below & stacking with in 50 m lead

Date
Sr.No. Description
Unit
Detail of cost of Dismantling Doors, Windows
Labour
1 Carpenter
Nos
2 Mazdoor (M)
Nos
4 Supervisor/HeadMason
Nos
Total L
Total L

Qty

Rate

0.10
0.25
0.10

260.00
135.00
300.00

Add for Cost & Sharpening of


Chisels sledge hammers
Add for Service Tax
Add for sundries & Contingencies
Contractors Profit & O.H.15%

3%
10.30%
3%
15%

G.Total for 1 Nos


Rate For 1 Nos

Demolishing Tile flooring laid in cement mortar inculiding disposal of material with in 50 m

Date
Sr.No. Description
Unit
Detail of cost of demolishing 10 Sqm
Labour
2 Mazdoor (M)
Nos
3 Mazdoor (F)
Nos
4 Supervisor/HeadMason
Nos

Qty

Rate

1.50
0.65
0.10

135.00
125.00
300.00

Total L
Total L
Add for Service Tax
Add for sundries & Contingencies
Contractors Profit & O.H.15%

10.30%
3%
15%

G.Total for 10 Sqm


Rate For 1 Sqm
Rate For 1 Sqm

Water Proofing in Lift Pit with Socket Grouting & Metal Coving
Sr.No. Description

Unit

Qty

Rate

For 23.4 Sqm


Material
1 Dr Fixit Pidiproof 2k for Base Coat
2 Screed Plaster 1:3 (15mm thk.)
a Cement
b Fine & Coarse Agg.
c Dr Fixit Pidiproof LW 200ml Per Bag
3 Metal Coving 300 mm thk.70%

Kg

29.57

110.00

Bag
Cum
Ltrs.
Cum

3.00
0.30
0.60
0.88

249.00
1,158.00
84.00
698.00

Mortar 30% of 1:3 & add 25 % for Wet


4 Mortar
Cum
a Cement
Bag
b Fine & Coarse Agg.
Cum
c Dr Fixit Pidiproof LW 200ml Per Bag Ltrs.

0.47
3.35
0.35
0.67

249.00
1,158.00
84.00

Socket Grouting of 5 Sqm Hollow


5 Surface Consider
a Cement Water Slurry
b Dr Fixit Pidiproof LW 200ml Per Bag

Ltrs.
Ltrs.

6.00
0.03

251.00
84.00

Nos
Nos
Nos

9.50
15.00
0.50

250.00
150.00
300.00

Total
Total M
B

Labour
1 Mason
2 Mazdoor
3 Supervisor /Head Mason
Total L
Total M+L
Contractors Profit & O.H.15%
G.Total for 23.4Sqm
Rate For 1Sqm
Rate For 1Sft

Rate Anly for Eracting & Removing of Scaffolding for 30 Sqm


Material
Unit
Qty.
No. Bamboo
Nos
37.00
Katha
Nos
40.00

Rate
100.00
2.00

Total- M
Labours
Male mazdoor
Supervisor

nos
nos

4.00
0.10

135.00
300.00

Total-L
Total-M+L
1% Add for Sundries & Contingencies
Add Tax Vat & Service Tax
Add 10% for O.H.& Profit

1.00%
9.12%
10.00%

Total for 30 sqm.Rs


Total for 1 sqm.Rs
Total for 1 sqft.Rs
@ 33%Only for Labour Per 1 sft Rs.
* Protective Glass film 78 Rs/Sft Considered

Sand Bed/Filling for 2.3 Cum of 230 mm thick


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Sand Bed 1x10x0.1

Cum

1.00

1176.00

Sand Filling 1x10x0.13 25%

Cum

0.33

1176.00

Each

0.13

260.00

Sub-Total of Material (M)


B)

Labour:
Mason

Mazdoor

Each

1.10

135.00

Supervisor /Head Mason

Each

0.10

300.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P

15.00%

Total Amt.
Cost Per 2.3 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)
Cost per 1 Sft (Rs.)

Raised & Cut Pointing to Stone work for 10 sqm


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

Bag

0.32

249.00

Sand

Cum

0.03

1176.00

Labour:
Mason
Mazdoor

Each
Each

2.00
2.15

260.00
135.00

Supervisor

Each

0.10

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P


Total Amt.
Cost Per 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

UCR Masonry 1:6 CM for 10 cum

15.00%

Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Stone
Cement

Cum
Bag

12.5
10.50

700
249.00

Sand

Cum

2.20

1175.00

Labour:
Mason
Mazdoor

Each
Each

25.00
35.00

260.00
135.00

Supervisor

Each

0.50

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P

D)

Tax Service Tax & Vat

15.00%
9.12%

Total Amt.
Cost Per 10 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)

Date: 26.06.09
Aluminium Louvers (0.6 x 0.9) with 5mm Clear Float Glass using Powder Coating
Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Aluminium Louver (0.6 x 0.9)

Nos

1.00

1300.00

5 mm Clear float glass with 10%


wastage
Screws

Sqm
Cent

0.59
50.00

388.00
1.00

Powder Coat with 15% wastage

Sqm

0.41

108.46

Sub-Total of Material (M)

B)

Labour:
Fitter
Mazdoor

Each
Each

0.40
0.40

260.00
135.00

Supervisor

Each

0.10

300.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for S & C
Add for W.C & Elec.

1.00%
1.00%

Add O.H & C.P

15.00%

Total Amt.
Cost Per 0.54 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

1 Casting of R.C.C.Pole With using M-15 Grade Concret of Size -2.74mx0.15mx0.15 m


Sr.
no
A)

Item
Materials:
Cement
Sand
Agg (AI+AII)
Steel
materials:

Unit

Quantity

Rate
(Rs.)

Bags
Cum
Cum
Kg
Sqm

0.370
0.026
0.053
2.160
1.230

249.00
1175.97
643.10
45.00
250.00

Each
Each
Each
Each

0.002
0.043
0.043
0.004

260.00
135.00
125.00
260.00

Sub-Total of Material (M)


B)

Labour:
Foreman
Beldar (M)
Coolie (F)
Mason

Waterman

Each

0.002

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Eqn

6.00%

Add for OH & C.P & Tax

15.00%

Total Amt.
Cost Per 1 Cum (Rs.)

Est.Dpt

RR Masonry 1:6 CM for 10 cum (Only Labour )


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Stone
Cement

Cum
Bag

12.5
10.50

700
249.00

Sand

Cum

2.20

1175.00

Labour:
Mason
Mazdoor

Each
Each

12.00
20.00

260.00
135.00

Supervisor

Each

0.50

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P

D)

Tax Service Tax & Vat


Total Amt.
Cost Per 10 Cum (Rs.)
Cost Per 1 Cum (Rs.)

15.00%
0.00%

Cost per 1 Cft (Rs.)

RR Pitching 225 mm thk for 10 sqm (only Labour)


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Stone + wastage 15%

Cum

2.59

700.00

Sand Filling 1x10x0.225 25%

Cum

0.56

1175.00

Labour:
Mason
Mazdoor

Each
Each

2.10
4.00

260.00
135.00

Supervisor /Head Mason

Each

0.10

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P

15.00%

Total Amt.
Cost Per 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

Internal Paint with ICI Acyelic Emulsion for 10Sqm (2Coates)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Asian Brand
Plastic Emulsion Paint

Litre

1.67

162.00

Sub-Total of Material (M)


B)

Labour:
Painter
Male Coolie

Each
Each

0.80
0.60

250.00
135.00

Supervisor

Each

0.20

300.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Brushes Sand Paper Putty Etc.
Add for Scaffolding Ladder Etc.
Add W.C & Electricity

3.00%
5.00%
5.00%
0.50%

Add for OH & C.P

15.00%

Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

Internal Paint with ICI Weather Sheid for 10Sqm (2Coates)


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Asian Brand
Plastic Emulsion Paint

Litre

1.82

149.85

Scaffolding Eraction

Sqm

10.00

35.20

Labour:
Painter
Male Coolie

Each
Each

0.80
0.60

250.00
135.00

Supervisor

Each

0.20

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies

3.00%

Brushes Sand Paper Putty Etc.


Add W.C & Electricity

5.00%
0.50%

Add for OH & C.P

15.00%

Total Amt.
Cost For 10Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

7 mm thk POP for 10 Sqm up to 3.00 m ht.


Sr.
no
A)

Item

Unit

Materials:
Plaster of Paris
Scaffolding

Qty.

Rate

bag
Sqm

4.12
10.00

70.00
31.00

Labour:
Mason
Helper

Each
Each

1.65
2.29

260.00
135.00

Supervisor

Each

0.15

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
Add W.C & Electricity 2%
Add for OH & C.P & Taxs 15%
Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

230 mm Brick Work C:M 1:5 for 10 cum

Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

bag

25.00

249.00

Sand

Cum

4.38

1176.00

Brick

Nos

5000.00

3.22

Sub-Total of Material (M)


B)

Labour:
Mason

Each

8.50

235.00

Helper

Each

16.00

135.00

Supervisor

Each

1.00

300.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for hire & maintatance of


mixer,lift,pump

3.00%

Add for scaffolding, challi,ropes

3.00%

Add W.C & Electricity

1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 10 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Addition 1% per floor till 21st floor
(Terrace)

21%

Total Cost till 21st floor per 1 Cum (Rs.)


Cost Per 1 Cft(Rs.)
Cost per 1 Sft(Rs.)

20 mm thk Ext.Plaster C:M (1:3) for 100 Sqm up to 3.00 m ht.


Sr.
no

Item

Unit

Qty.

Rate

A)

Materials:
Cement

bag

20.00

249.00

Sand

Cum

2.40

1113.00

Scaffolding

Sqm

100.00

31.00

Mason

Each

17.50

260.00

Helper

Each

25.00

135.00

Sub-Total of Material (M)


B)

Labour:

Sub-Total of Labour (L)


Total (M+L)
Add W.C & Electricity 2%
Add for OH & C.P & Taxs 15%
Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
21%

Cost for 21st floor add 1% per floor


Total Amt. upto 21st floor
Cost upto 21st floor (1 Sft)

150 mm thk RCC Coping Work 1:3:6


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

Bags

4.560

249.00

Sand

Cum

0.470

1175.00

Agg (AI+AII)

Cum

0.930

643.00

Steel @ 8mm dia

Kgs

52.000

35.12

Each

0.040

260.00

Sub-Total of Material (M)


B)

Labour:
Foreman

Beldar (M)

Each

0.700

135.00

Coolie (F)

Each

0.700

125.00

Mason

Each

0.070

260.00

Waterman

Each

0.035

135.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Eqn

6.00%

Add for OH & C.P & Tax

15.00%

Total Amt.
Cost Per 1 Cum (Rs.)
Cost per 1 Sqm (Rs.) of 150mm thk
Cost Per 1 Sft (Rs.)
21%

Cost for 21st floor add 1% per floor


Total cost for 21st floor (Sft)

Making Teak Wooden Frame 2 m x 1 m


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Timber

Cum

0.0363

27519

Labour:
Carpenter 1 Class

Each

0.65

260.00

Beldar

Each

0.65

135.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
Add for scaffolding, Contingencies

3.00%

Add W.C & Electricity

1.00%

Add for OH & C.P & Taxs

15.00%

Cost Per 0.025 Cum (Rs.)


Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)

French Polishing on Wood 10sqm


Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Assian Varnish

Litre

0.228

141

turpentine oil

Litre

1.63

70

Labour:
Painter

Each

3.20

200.00

Supervisor

Each

0.20

300.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
Add for pigment,carriage of material,
turpentine oil,sand paper,putty,wood
filler,white woollen cloth,linseed
oil,cotton etc.

7.50%

Add for scaffolding, Contingencies

3.00%

Add W.C & Electricity

1.00%

Add for OH & C.P & Taxs

15.00%

Cost Per 10 Sqm (Rs.)


Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

Jindal Casecase Windows Sections (1.1*1.3)


Sr.
no

Item

Unit

Quantity

Rate
(Rs.)

A)

Materials:
Casecase Windows
Handles
6mm clear float glass
PVC Gasket
Wheel
Screws

Kg
Nos
Sqm
Rmt
Nos
Cent

11.20
2.00
1.43
11.44
8.00
50.00

175.00
145.00
387.36
16.40
10.00
1.00

Power Coated

Kg

11.20

43.75

Sub-Total of Material (M)


B)

Labour:
Carpanter
Mistry

Each
Each

1.89
1.10

260.00
260.00

Helper

Each

1.10

135.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 1.43qm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

P.C.C of M10 for 1 cum


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

bag

4.43

249.00

Sand

Cum

0.47

1175.00

M-I,M-II

Cum

0.92

644.00

Each

0.14

260.00

Sub-Total of Material (M)


B)

Labour:
Mason

Helper

Each

2.00

200.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Sundries & Contingencies

0.50%

Add W.C & Electricity

1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 1 Cum (Rs.)
Cost per 1 Cft (Rs.)

230 mm Brick Work C:M 1:6 for 10 cum


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

bag

20.00

249.00

Sand

Cum

4.20

1175.00

Brick

Nos

5000.00

3.70

Sub-Total of Material (M)


B)

Labour:
Mason

Each

8.50

235.00

Helper

Each

16.00

135.00

Sub-Total of Labour (L)


Total (M+L)
C

Add for OH & C.P & Taxs


Total Amt.
Cost for 10 Cum (Rs.)
Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)

15.00%

100 mm Brick Work C:M 1:6 for 100 sqm


Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

bag

13.00

249.00

Sand

Cum

4.74

1175.00

Brick

Nos

5000.00

3.70

Sub-Total of Material (M)


B)

Labour:
Mason

Each

8.50

235.00

Helper

Each

16.00

135.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Sundries & Contingencies

0.50%

Add W.C & Electricity

1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)

150 mm Brick Work C:M 1:6 for 100 sqm


Sr.
no
A)

Item

Quantity

Materials:
Cement

bag

19.00

249.00

Sand

Cum

4.05

1176.00

Brick

Nos

5000.00

3.70

Sub-Total of Material (M)


B)

Unit

Rate
(Rs.)

Labour:

Mason

Each

8.50

235.00

Helper

Each

16.00

135.00

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Sundries & Contingencies

0.50%

Add W.C & Electricity

1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)

Providing,fabricating and fixing FE415 steel.for 1MT


Sr.No.
Descritption
Qty
Unit
Material
1 Rein.Steel Bars + 5% wastage
1.05 Mt
2 Binding Wire
5.00 Kg

Rate
32,239.00
50.00

Total for Material


Labours
1 Blacksmith
2 Beldar

10.00 Day
10.00 Day

250.00
135.00

Total for Labour


Total M+L
Add for Tools & Ele.2%
Add O.H.& Profit 15%
Total for 1M.T. -

Crazy Pattern Flame Granite /Ikon Brown Flooring 18mm thk on the C.C.1:2:4 Bed

Sr.
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Subgrade -For 10Sqm ,25mm thk
Cement
Sand
Coarse Agg.

bag
Cum
Cum

1.53
0.11
0.21

249.00
1139.00
643.00

Top Layers Granite chips


Granite
Add 5% wastage
Cement Slurry
White Cement

Sqm
Sqm
Kg
Kg

10.00
0.50
40.00
36.50

1725.00
1725.00
5.00
12.00

Colour Pigment @3.5Kg=50kg Cement

Kg

2.55

30.00

Labour:
Supervisor
Mason

Each
Each

0.9
1.75

300
235.00

Male Coolie

Each

5.12

135.00

Sub-Total of Material (M)


Add 5% On Material Wastage(M)
Sub-Total of Material (M)
B)

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

0.50%
1.00%

Add for OH & C.P & Taxs

15.00%

Total Amt.
Cost for 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 sft (Rs.)

4 Wooden Bench 6.00' X 2.00'


Sr
no

Item

Unit

Quantity

Rate
(Rs.)

A)

Materials:
Wood 20mm thk.

Cum

0.02

35000.00

Horizontal Support =3" thk.


Verticle Legs =4"

Cum
Cum

0.03
0.01

35000.00
35000.00

Screws/Hardware

L.S.

1.00

100.00

Carpenter
Beldar

Each
Each

0.30
0.30

260.00
135.00

Supervisor

Each

0.05

260.00

Sub-Total of Material (M)


B)

Labour:

Sub-Total of Labour (L)


Total (M+L)
C)

Add for Sundries & Contingencies

1.00%

Add W.C & Electricity

1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 1.08 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

4'' Brick work (1 :4) for 100 Sqm


Sr.
no
A)

B)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
4" thk Brick
Cement

Nos
Bags

5,320.00
14.45

4.00
249.00

Sand

Cum

2.02

1,175.00

Sub-Total of Material (M)


Labour:
Supervisor
Mason

Each
Each

0.50
16.00

300.00
260.00

Helper

Each

23.00

200.00

Sub-Total of Labour (L)

C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

15 mm thk Plaster (1 :4) for 100 Sqm


Sr.
no
A)

B)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Cement

Bags

10.72

249.00

Sand

Cum

1.56

1,175.00

Sub-Total of Material (M)


Labour:
Supervisor
Mason

Each
Each

0.25
17.50

300.00
260.00

Helper

Each

25.00

200.00

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 100 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

Dummy beam for 10 Rmt


Sr.
no

Item

Unit

Quantity

Rate
(Rs.)

A)

B)

Materials:
Channel (100 x 50 mm)
Baseplater
Anchor Fastern

Kgs
Kgs
No

230.00
15.00
16.00

50.00
55.00
50.00

Gypsum Sheet

Sqm

14.00

135.00

Sub-Total of Material (M)


Labour:
Labour

35%

0.35

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity

1.00%
3.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 10 Rmt (Rs.)
Cost Per 1 Rmt (Rs.)
Cost per 1 Rmt (Rs.)

Glass Partition for 10 Sqm


Sr.
no
A)

B)

Item

Unit

Materials:
Channel (1" x 1 "x2.5 mm)
Glass
Track 2

Rmt
Sqm
Rmt

Fitting

LS

Quantity
3.00
10.00
3.00

82.00
1,560.78
1,198.00

1.00

2,700.00

Sub-Total of Material (M)


Labour:
Labour

25%

0.25

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.

Rate
(Rs.)

1.00%
1.00%
15.00%

Cost Per 10 Sqm (Rs.)


Cost Per 1 Sqm (Rs.)
Cost per 1 Sqm (Rs.)

H-FRAME FOR FOR 100 SQ.MT.


Sr.
no
A)

B)

Item

Unit

Materials:
rate per rolling per sq.mt. =22.5/for 100 sq.mt.
nail

Rmt
Sqm
kg.

jute rassi

Quantity

Rate
(Rs.)

100.00
0.50

22.50
45.00

kg.

10.00

10.00

0.60

Sub-Total of Material (M)


Labour:
Labour for staging and removing
Sub-Total of Labour (L)

C)

Total (M+L)
Add transportation charges

3.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 100 Sqmt. (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sqm (Rs.)

RATE ANALYSIS

Rate analysis of providing and laying of 25mm thick shalitex board for expansion
sr.no.

Quantity - 100 sq.mt.


particular
MATERIAL

unit

quantity

rate

Providing 25mm thick shalitex board forsq.mt.


expansion joint (1.2 x 1.2 ) mts.
add wastage 10%
sq.mt.
LABOUR ( cutting and fixing )
unskilled for unloading and handling
superviser
Skilled labour
unskilled labour

no.
no.
no.
no.

100

625

10

625

4
0.5
4
4

200
350
300
250

total material + labour


Add for tool , electricity and work
establishment charges 3%
Add for contracter profit 15 %
cost for 100 sq.mt. in rs.
cost for 1 sq.mt. in rs.

Glass Partition for 10 Sqm


Sr.
no
A)

B)

Item

Unit

Materials:
Channel (1" x 1 "x2.5 mm)
Glass
Track 2

Rmt
Sqm
Rmt

Fitting

LS

Quantity
3.00
10.00
3.00

82.00
1,560.78
1,198.00

1.00

2,700.00

Sub-Total of Material (M)


Labour:
Labour

25%

0.25

Sub-Total of Labour (L)


C)

Total (M+L)
Add for Sundries & Contingencies

Rate
(Rs.)

1.00%

Add W.C & Electricity

1.00%

Add for OH & C.P

15.00%

Total Amt.
Cost Per 10 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sqm (Rs.)

Filling of Siprox Block with 110 Thk C:M 1:4 for 1.32 Cum
Sr
no
A)

Item

Unit

Quantity

Rate
(Rs.)

Materials:
Siprox Block

Cum

1.21

3600.00

Sand

Cum

0.60

1590.00

Labour:
Mason
Helper

Each
Each

0.66
4.80

300.00
200.00

Supervisor /Head Mason

Each

0.10

350.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P


Total Amt.
Cost Per 1. 32Cum (Rs.)
Cost Per 1 Cum (Rs.)
Cost per 1 Cft (Rs.)

15.00%

Filling of Siprox Block with 400 thk C:M 1:4 with top slurry of 12 mm thk C:M 1:4 for 4.8 Cum
Sr
no
A)

Item

Unit

Rate
(Rs.)

Quantity

Materials:
Siprox Block

Cum

4.32

3780.00

Sand

Cum

0.60

1590.00

Labour:
Mason
Helper

Each
Each

2.40
15.00

300.00
200.00

Supervisor /Head Mason

Each

0.25

350.00

Sub-Total of Material (M)


B)

Sub-Total of Labour (L)


Total (M+L)
C)

Add for OH & C.P

15.00%

Total Amt.
Cost Per 4.8 Cum `
Cost Per 1 Cum `
Cost per 1 Cft `

RATE ANALYSIS OF SURFACE DRESSING OF EXCAVATED EARTHWORK NOT EXCEED


300MM LEAD UP TO 50MTS. LIFT UP TO 3 MTS. Quantity ( 100 sq.mt. )
Sr
no

Item

Unit

Quantity
-

A)

Materials:

Sq.mt.

B)

Sub-Total of Material (M)


Labour:
Beldhar

each

Rate
(Rs.)

350

coolie

each

2.1

Sub-Total of Labour (L)


Total (M+L)
C)

Add for sundries & contingencies

D)

Add for OH & C.P


Total Amt.
Cost per 100 sq.mt.
Cost per 1 sq.mt.
Cost per 1 sq.ft

5%
15%

250

1 R.C.C for M-15


Amount.
(Rs.)

Sr.
no
A)

1892.40
824.59
445.52
3162.52

Item
Materials:
Cement
Sand

Bags
Cum

Agg (AI+AII)

Cum

Sub-Total of Material (M)


B)

10.4
94.5
87.5
18.2

Labour:
Foreman
Beldar (M)
Coolie (F)
Mason

Each
Each
Each
Each

4.725

Waterman

Each

215.33

Sub-Total of Labour (L)

3377.84
202.67

C)

506.68

Total (M+L)
Add for Eqn
Add for OH & C.P & Tax

4087.19

Total Amt.

4087.19

Cost Per 1 Cum (Rs.)

1
Amount.
(Rs.)

Unit

0.00
513.04
638.00
1151.04
12.00
12.00
32.50
210.00
6.00
12.25
12.00
12.00
308.75
125.00
37.50
50.00
212.50
1672.29
250.84
1923.13
1923.13

R.C.C for M-20 (1:1.5:3)


Amount.
(Rs.)

Sr.
no
A)

2463.30
222.00
462.50
3147.80

Unit

Materials:
Cement
Sand

Bags
Cum

Agg (AI+AII)

Cum

Sub-Total of Material (M)


B)

12.00

Item

Labour:
Foreman

Each

140.00
140.00
18.20

Beldar (M)
Coolie (F)
Mason

Each
Each
Each

7.00

Waterman

Each

317.20
3465.00
277.20

Sub-Total of Labour (L)


C)

519.75

Total (M+L)
Add for Eqn
Add for OH & C.P & Tax

4261.95

Total Amt.

4261.95

Cost Per 1 Cum (Rs.)

R.C.C for M-20 (1:1:2)


Amount

29,400.00
150.00

Sr.
no
A)

29,550.00
2,500.00
1,500.00

Item
Materials:
Cement
Sand

Bags
Cum

Agg (AI+AII)

Cum

Sub-Total of Material (M)


B)

4,000.00
33,550.00
671.00
5,032.50

Labour:
Foreman
Beldar (M)
Coolie (F)
Mason

Each
Each
Each
Each

Waterman

Each

Sub-Total of Labour (L)


Total (M+L)

39,253.50

C)

Add for Eqn


Add for OH & C.P & Tax
Total Amt.
Cost Per 1 Cum (Rs.)

113,850.00
21,600.00
67,795.20

Unit

12,711.60
19,000.00
234,956.80
23,495.68
6,900.00
4,600.00
11,500.00
34,995.68
699.91
699.91
36,395.51
5,459.33
41,854.83
279.03
25.93
Date: 11.02.09
Tremix Paving of 75 mm thk per m2 using M25 grade concrete
Amount.
(Rs.)

Sr.
no
A)

206.67
34.74
41.88
150.00
48.00
481.29

Item

Unit

Materials:
Cement
Sand
Aggregate
Colour Pigment & Hardener

Bags
Cum
Cum
Kgs

Shuttering

Sqm

Sub-Total of Material (M)


B)

Labour:
Mason
Skilled Labour
Unskilled Labour

Each
Each
Each

15.00

Carpenter

Each

32.85

Sub-Total of Labour (L)

2.25
8.10
7.50

C)
24.00
12.00

Mechinary
Mixer with Operater
Vibrator with Operater

Cum
Cum

135.00

Trimix Float Finish with Operater


& Labour
Sqm

171.00

Sub-Total of Mechinary

685.14
10.28

Total (M+L)
Add W.C & Electricity

D)

102.77

Add for OH & C.P

798.19

Cost per Sqm (Rs)

74.181

Cost per Sft (Rs)

1 9'' Brick work With (1 :6) For 1Cum


Amount.
(Rs.)

Sr.
no
A)

Item

Unit

343.20
87.15

Materials:
Brick-4"X3.5"X9"
Cement

Nos
Bags

137.07

Sand

Cum

567.42

Sub-Total of Material (M)


B)

Labour:
Supervisor
Mason

Nos
Nos

75.32

Mazdoor

Nos

75.32

Sub-Total of Labour (L)

659.90

Total (M+L)
C)

19.80
13.20

Add for Sundries &


Contingencies
Add W.C & Electricity

98.98

Add for OH & C.P

791.88

Total Amt.

791.88

Cost Per 1 Cum (Rs.)

73.59

Cost per 1 Cuft (Rs.)

Amount.
(Rs.)
21280.00
3598.05
2373.50
27251.55
150
4160
4600
4600.00
31851.55
138.00
92.00
690.00
32771.55
32771.55
327.72
30.46

1 8" Block work With (1 :6) For 1Cum


Amount (Rs.)

Sr.
no
A)

928.28
-313.97
614.31
76.79
46.00
737.10
36.85
773.95
31.125

Item

Unit

Materials:
Block-4"X8"X26"
Cement

Nos
Bags

Sand

Cum

Sub-Total of Material (M)

B)

Labour:
Supervisor
Mason

Nos
Nos

16.13

Mazdoor

75.32

Sub-Total of Labour (L)


Total (M+L)
C)

896.53
83.32

Add for Sundries &


Contingencies
Add W.C & Electricity
Add for OH & C.P
Total Amt.
Cost Per 1 Cum (Rs.)

Amount Sqm (Rs.)


343.20
17.16
360.36
87.15
45.30
75.32
568.13
52.80

Amount.
(Rs.)
6225.00
4874.94
18500.00
29599.94

1997.50
2160.00
4157.50
33757.44
168.79
339.26
5114.51
39379.99

Cost per 1 Cuft (Rs.)

Nos

39379.99
3938.00
111.62

Amount.
(Rs.)

480.00
4950.00
5430.00

3400.00
2295.00
5695.00
11125.00
333.75
222.50
1668.75
13350.00
13350.00
133.5
12.41

Amount.
(Rs.)
0.00
1800.00
1800.00
3400.00
2295.00
5695.00
7495.00
224.85
149.90
1124.25
8994.00
8994.00
89.94
8.36

Amount.
D-200309
(Rs.)

ates)

296.88
296.88
150.00
67.50
217.50
514.38
15.43
25.72
12.86
2.57
77.16
648.11
648.11
64.81
6.02
Amount.
D-200309
(Rs.)
75
225.00
225.00
150.00
67.50
217.50
442.50
13.28
22.13
11.06
2.21
66.38
557.55
557.55
55.76
5.18

Date :- 130908

nly

Amount. (Rs.)
2988.00
1822.40
5184.00
9994.40
499.72
10494.12
104.94
9.75

Amount. (Rs.)
2988.00
1822.40
632.50
5442.90
272.145
5715.045
57.15
5.31

Amount.
(Rs.)
2988.00

1822.40
17400.00
22210.40

3380.00
1755.00
202.50
5337.50
27547.90
826.44
550.96
4132.19
33057.48
33057.48
330.57
30.72

Amount.
(Rs.)
2988.00
1822.40
3300.00
8110.40

3380.00
1755.00
202.50
5337.50
13447.90
403.44
268.96
2017.19

16137.48
16137.48
161.37
15.00

5 Plaster (1:8) with Silpoz 20mm thk. Ex.Scaffolding


Amount.
(Rs.)

Sr.
no
A)

Item

Unit

Materials:
Cement

Bags

138.30

Silpoz

Cum

178.14

Sub-Total of Material (M)

39.84

B)

80.7
80.70

Labour:
Supervisor
Mason

Nos
Nos

Mazdoor

Nos

Sub-Total of Labour (L)

258.84

Total (M+L)
C)

6.57
4.38
32.85

Add for Sundries &


Contingencies
Add W.C & Electricity
Add for OH & C.P

302.64

Total Amt.

302.64

Cost Per 1 Sqm (Rs.)

28.13

Cost per 1 Sft (Rs.)


6 Plaster (1:4) with Sand 20mm thk.For 100Sqm Ex.Scaffolding

Amount.
(Rs.)

Sr.
no
A)

Item

Unit

39.84

Materials:
Cement

Bags

34.17

sand

Cum

74.01

Sub-Total of Material (M)

B)

80.7
80.70

Mazdoor

Nos

Total (M+L)
C)

12.11

Nos
Nos

Sub-Total of Labour (L)

154.71
2.42
1.61

Labour:
SuperVisor
Mason

Add for Sundries &


Contingencies
Add W.C & Electricity
Add for OH & C.P

170.85

Total Amt.

170.85

Cost Per 1 Sqm (Rs.)

15.88

Amount.
(Rs.)
3510.90
1569.33
2500.00
7580.23

4550.00
3375.00
7925.00
15505.23
77.53
155.83
1414.08
2349.16
19501.82
19501.82

Cost per 1 Sft (Rs.)

195.02
18.12

Amount.
41.65
24.49
6.20
9.30
81.64
4.08
85.72
45.00
45.00
45.00
130.72
130.72
2.61
2.61
135.95
13.59
20.39
169.93
165.00

Amount.

4,980.00
2,671.20
3,100.00
10,751.20

4,550.00

3,375.00
7,925.00
18,676.20
373.52
2,801.43
21,851.15
21,851.15
218.51
20.31

Amount.
(Rs.)
162.00
264.00
32.50
34.86
493.36

125.00
67.50
192.50
685.86
3.43
3.43
6.86
6.86

102.88
809.31
75.22

Amount.
(Rs.)
485.00
264.00
32.50
34.86
816.36

125.00
67.50
192.50
1008.86
5.04
5.04
10.09
10.09
151.33
1190.45
110.64

Amount.
(Rs.)

250.00
264.00
32.50
34.86
581.36

125.00
67.50
192.50
773.86
3.87
3.87
7.74
7.74
116.08
913.15
84.87

) with hardware & lab.


Amount. (Rs.)
2765.00
564.9
3329.90
28.25
810.00
540.00
4708.15

2979.84
276.94

Amount.
(Rs.)
538.00
264.00
32.50
34.86
869.36

125.00
67.50
192.50
1061.86
5.31
5.31
10.62
10.62
159.28
1252.99
116.45

Amount. (Rs.)
2765.00
-

2824.5
5589.50
141.23
5730.73
3627.04
337.09
Tremix Paving of 100mm thk per m2(1:1:2)
Amount.
(Rs.)

Sr.
no
A)

Item

Unit

226.59
72.90

Materials:
Cement
Sand

Bags
Cum

87.39

Aggregate

Cum

386.87

Sub-Total of Material (M)


B)

Labour:
Mason
Female Coolie
Male Coolie

Each
Each
Each

Waterman

Each

0.00
0.00

Sub-Total of Labour (L)


Mechinary
Mixer
Vibrator

Sqm
Sqm

0.00

Trimix

Sqm

0.00

Sub-Total of Mechinary (Me)

4.50
24.00
24.00
9.00
61.50
C)

448.37
6.73

D)

Total (M+L+Me)
Add W.C & Electricity

67.26

Add for OH & C.P

522.36

Cost per Sqm (Rs)

48.546

Cost per Sft (Rs)

Con. Block Paving of 200 X 200 X 60mm per m2


Amount.
(Rs.)

Sr
no
A)

560.00
56.95
11.39
628.34

Item

Unit

Materials:
Paving Block
Sand

Nos
Cum

Fine Sand

Cum

Total of Material (M)


Add 10% for Wastage
Sub-Total of Material (M)
B)

Labour:
Mason

Each

15.12

Male Coolie

Each

19.32

Sub-Total of Labour (L)

4.20

647.66
9.71

C)

Total (M+L)
Add W.C & Electricity

97.15

Add for OH & C.P

754.52

Cost per Sqm (Rs.)

70.12

Amount.
(Rs.)

300.00
15.00
46.00
361.00

125.00

Cost per Sft (Rs.)


Note-Sand Bed Considered of 50mm thk.& fine sand layer of 10mm thk.

67.50
192.50
553.50
2.77
2.77
5.54
5.54
83.03
653.13
60.70

Amount.
(Rs.)

3766.00
264.00
28.48
34.86
4093.34

125.00
67.50
192.50
4285.84
21.43
21.43
42.86
42.86

642.88
5057.29
470.01

d Surface Lab.only
Amount.
(Rs.)
183.65
183.65

1682.50
908.55
300.00
2891.05
3074.70
15.37
15.37
153.73
380.03
30.75
461.20
4131.16
826.23
76.79

rface lab.only
Amount.
(Rs.)

183.65
183.65

1492.50
805.95
300.00
2598.45
2782.10
13.91
13.91
139.10
343.87
27.82
417.31
3738.02
747.60
69.48

Amount.
(Rs.)
6143.76
6143.76

2625.00
2700.00
600.00
5925.00
12068.76
29.63

296.25
732.33
59.25
888.75
14074.97
140.75
13.08

. only
Amount.
(Rs.)
183.65
183.65

1682.50
908.55
300.00
2891.05
3074.70
15.37
15.37
153.73
380.03
30.75
461.20
4131.16
82.62
25.19

Amount

0.00
3,821.40
0.00
3,821.40
191.07
4,012.47
6,250.00
7,000.00
300.00
13,550.00
17,562.47

1,601.70
2,634.37
21,798.54
217.99
20.26

ng and hardware
Amount. (Rs.)
1126.13
1050.53
2609.25

96.03
140.22
467.4
5489.55
274.48
2600.00
540.00
8904.03
5635.46
523.74
Date :- 130908

Amount. (Rs.)
1126.13
1050.53
2609.25
96.03
140.22
467.4
5489.55
274.48
5764.03
3648.12
339.04

Jindal Windows Sections 3 track(1.83x1.2)


Amount.
(Rs.)
2754.93
100.00
2474.26

Sr.
no
A)

Item
Materials:
Windows 3 track
Handles
6mm clear float glass

Unit
Kg
Nos
Sqm

838.04
80.00
50.00

PVC Gasket
Wheel
Screws

Rmt
Nos
Cent

688.73

Anodizing 20-22 micron

Kg

6985.97

Sub-Total of Material (M)


B)

491.03
285.48

Labour:
Carpanter
Mistry

Each
Each

148.23

Helper

Each

924.74

Sub-Total of Labour (L)

7910.70

Total (M+L)
C)

79.11
79.11

Add for Sundries &


Contingencies
Add W.C & Electricity

1186.61

Add for OH & C.P & Taxs

9255.52

Total Amt.

9255.52

Cost for 2.19 Sqm (Rs.)

4226.27

Cost Per 1 Sqm (Rs.)

392.78

Amount.
(Rs.)
2033.64
740.25
1047.82
225.00
75.00
240.00
48.00
4409.71

Cost per 1 Sft (Rs.)

104.00
54.00
13.00
171.00
4580.71
45.81
45.81
687.11
5359.43
5359.43
3392.04
315.25

Amount.
(Rs.)

5592.51
5326.20
225.00
75.00
240.00
48.00
11506.71

104.00
54.00
13.00
171.00
11677.71
116.78
116.78

1751.66
13662.92
13662.92
8647.42
803.66

Amount.
(Rs.)
1287.00
2016.00
225.00
75.00
125.00
48.00
3776.00

450.00
270.00
13.00
733.00
4509.00
45.09
45.09
676.35
5275.53
5275.53
2093.46
194.56

Amount.
(Rs.)
4609.58
225.00
75.00
125.00
48.00
5082.58

90.00
54.00
13.00
157.00
5239.58
52.40
52.40
785.94
6130.31
6130.31
2432.66
226.08

Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59

13210.87

1430.00
832.00
432.00
2694.00
15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65

Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87

1430.00
832.00
432.00
2694.00
15904.87

159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65

Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87

1430.00
832.00
432.00
2694.00
15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65

Amount.
(Rs.)
8582.70
300.00
1237.13
687.30
349.32
80.00
50.00
1374.59
12661.04

1430.00
832.00
432.00
2694.00
15355.04
153.55
153.55
2303.26
17965.39
17965.39
2811.49
261.29

Amount.
(Rs.)

3253.82
1184.40
1143.07
225.00
225.00
700.00
15.00
48.00
6794.30

104.00
54.00
13.00
171.00
6965.30
69.65
69.65
1044.79
8149.40
8149.40
5157.85
479.35

Amount.
(Rs.)
3718.66
1353.60
1185.41
225.00
225.00
700.00
15.00

48.00
7470.66

156.00
81.00
26.00
263.00
7733.66
77.34
77.34
1160.05
9048.39
9048.39
5726.83
532.23

Amount.
(Rs.)

2775.99
1052.07
150.00
123.66
300.00
225.00
225.00
50.00
585.34

5487.06

1430.00
832.00
432.00
2694.00
8181.06
81.81
746.11
81.81
1227.16
10317.95
10317.95
3793.36
352.54

Amount.
(Rs.)
8582.70
300.00
2474.26
349.32
80.00
50.00
1374.59
13210.87

1430.00
832.00
432.00
2694.00

15904.87
159.05
159.05
2385.73
18608.70
18608.70
2912.16
270.65

Amount.
(Rs.)
364.50
364.50

260.00
270.00
530.00
894.50
4.47
8.99
81.58
135.52
1125.06
1125.06
2500.14
232.36

820.34
467.77
2,140.65
151.28
86.80
3,666.85
183.34
183.34
4,033.53
585.00
577.50
1,162.50
5,196.03
103.92
779.40
6,079.36
1,712.49
159.15

820.34
467.77
266.25
1,554.37
77.72
77.72
1,709.80
550.00
500.00
1,050.00
2,759.80

55.20
413.97
3,228.97
909.57
84.53

Est Dpt

820.34
467.77
479.25
1,767.37
88.37
88.37
1,944.10
520.00
412.50
932.50
2,876.60
57.53
431.49
3,365.62
948.06
88.11

Amount

5,500.00
238.00
200.00
150.00
6,088.00
121.76
555.23
913.20
7,678.19
76.78

2 G.I.Pipe for 100 Rmt.


Amount

Sr.No.

27,600.00
1,649.00

1
2

200.00
150.00

1
2

29,599.00
591.98
2,699.43
4,439.85
37,330.26
373.30

Amount
13,300.00
200.00
13,500.00
270.00
1,231.20
2,025.00
17,026.20
170.26

4 PVC 110mm dia.of 6kgf/cm2


Amount.
(Rs.)

Sr.
no
A)

1562.00
260.00
75.00
100.00
225.00
2222.00
B)
200.00
135.00

135.00
470.00
2692.00
C)

13.46
27.05
245.51
407.86
3385.88
3385.88
564.31
172.05

Date: 3rd Dec'2008

Amount.
(Rs.)
3297.00
1108.00
230.00
100.00
4735.00
540.00
540.00
5275.00
263.75
553.875
6092.63
1015.44
94.37

Amount.
(Rs.)
1914.00
1108.00
230.00
100.00
3352.00
540.00
540.00
3892.00
194.6
408.66
4495.26
749.21
69.63

Amount.
(Rs.)
4500.00

900.00
300.00
5400.00

225.00
130.00
135.00
490.00
5890.00
58.90
58.90
537.17
883.50
7428.47
7428.47

Date: 3rd Dec'2008

Amount.
(Rs.)
2552.00
4000.00
6552.00
450.00
135.00
585.00
7137.00
71.37
71.37
1070.55

8350.29
8350.29
776.05

Amount.
(Rs.)
829.40
6124.00
6953.40
225.00
135.00
360.00
7313.40
73.13
73.13
731.34
8191.01
22752.80
2114.57

Amount.
(Rs.)
7000.00

Amount.
(Rs.)
13000.00

1 Waterproofing for Ramp Basecoat With Screed Plaster


Date-160109
Amount

16,940.00
4,482.00
2,084.40
302.40
23,808.80
1,190.44
24,999.24

Sr.No.

Descripti
Material
For 100 Sqmt.1:3 (15mm thk.
1 Dr Fixit Pi
2 Screed Plaster 1:3 (15mm thk
a Cement
b Fine & Coa
Total
Add 5 % Wastage

3,750.00
3,150.00
189.00

Total M
Labour
1 Mason
2 Mazdoor
3 Superviso

7,089.00
32,088.24

Total L
Total M+L

2,926.45

Add for Vat & Service Tax 9.1

4,813.24

Contractors Profit & O.H.15%

39,827.92
398.28
37.01

G.Total for 100Sqm


Rate For 1Sqm
Rate For 1Sft

2 Providing IPS Flooring with 1:2:4 of 75mm thk


Date-160109
Amount

Sr.No.
A

16,940.00
4,482.00
2,084.40
302.40
8,693.30

Total

7,470.00
3,578.22
504.00
44,054.32
2,202.72
46,257.04
9,250.00
8,850.00
600.00
18,700.00
64,957.04

5,924.08

Descripti
For 100Sqm
Material
1 Cement
2 Sand
a Aggraegat
b Cement Sl

Add 5% For Wastage


Total M
Labour
1 Mason
2 Mazdoor
3 Superviso
Total L
Total M+L

Add for Vat & Service Ta

Contractors Profit & O.H.15%


G.Total for 100Sqm
Rate For 1Sqm
Rate For 1Sft

9,743.56
80,624.67
806.25
74.93

Date-160109
Amount

16,940.00
11,952.00
5,558.40
806.40
35,256.80
1,762.84
37,019.64
6,250.00
5,250.00
300.00
11,800.00
48,819.64

4,452.35
7,322.95
60,594.94
605.95
56.31

Date-02.03.09
Amount

1,992.00

565.50
16,940.00
4,482.00
2,779.20
302.40
8,693.30
7,470.00
4,770.96
504.00
1,215.90
7,470.00
4,770.96
4,482.00
2,779.20
66,659.92
3,333.00
69,992.92
12,500.00
10,395.00
1,200.00
24,095.00
94,087.92

9,408.79
103,496.71
1,034.97
96.19

Est.Dpt

lead
Date-190309
Amount

128.25
106.25
30.00
264.50
264.50

13.23
27.24
7.94
39.68
352.58
352.58
9.99

h in 50 m lead
Date-190309
Amount

26.00
33.75
30.00
89.75
89.75

2.69
9.24
2.69
13.46
117.84
117.84

material with in 50 m lead


Date-190309
Amount

202.50
81.25
30.00
313.75
313.75
32.32
9.41
47.06
402.54
40.25
3.74

Amount

3,252.70
747.00
347.40
50.40
612.70
834.15
408.20
56.28

1,506.00
2.52
7,817.35
7,817.35
2,375.00
2,250.00
150.00
4,775.00
12,592.35
1,888.85
14,481.20
618.85
57.51

Est Dpt
Dt : 080609

Amt.
3,700.00
80.00
3,780.00
540.00
30.00
570.00
4,350.00
43.50
400.69
479.42
5,273.61
175.79
16.34
5.39

Est Dpt

Amount.
(Rs.)
1176.00
382.20
1558.20

33.80

148.50
30.00
212.30
1770.50
265.58
2036.08
2036.08
885.25
25.09
5.77

Amount.
(Rs.)
79.68
35.28
114.96

520.00
290.25
30.00
840.25
955.21
143.28
1098.49
1098.49
109.85
10.21

Amount.
(Rs.)
8750.00
2614.50
2585.00
13949.50

6500.00
4725.00
150.00
11375.00
25324.50
3798.68
2656.03
31779.21
31779.21
3177.92
90.08

Date: 26.06.09
er Coating
Amount.
(Rs.)
1300.00
230.47
50.00
44.90
1625.37

104.00
54.00
30.00
188.00
1813.37
18.13
18.13
272.01
2121.65
2121.65
3928.98
365.15

Est.Dpt

Date-270609
Rev-00

.15mx0.15 m
Amount.
(Rs.)
92.13
31.14
34.06
97.20
307.50
562.03
0.63
5.76
5.34
1.11

0.29
13.13
575.16
34.51
86.27
695.95
695.95

Est.Dpt

Amount.
(Rs.)
8750.00
2614.50
2585.00
13949.50

3120.00
2700.00
150.00
5970.00
19919.50
2987.93
0.00
22907.43
22907.43
2290.74

64.93

Est Dpt

Amount.
(Rs.)
1813.00
658.00
2471.00

546.00
540.00
30.00
1116.00
3587.00
538.05
4125.05
4125.05
412.51
38.34

Est Dpt

m (2Coates)
D-200309
Amount.
(Rs.)

270.54

270.54

200.00
81.00
60.00
341.00
611.54
18.35
30.58
30.58
3.06
91.73
785.83
785.83
78.58
7.30

(2Coates)
D-200309
Amount.
(Rs.)

272.73
352.00
624.73

200.00
81.00
60.00
341.00
965.73
28.97

48.29
4.83
144.86
1192.67
1192.67
119.27
11.08

Amount.

288.40
310.00
598.40

429.00
309.15
45.00
783.15
1,381.55
27.63
207.23
1,616.41
1,616.41
161.64
15.02

Date: 03.08.09

Amount.
(Rs.)
6225.00
5150.88
16100.00
27475.88

1997.50
2160.00
300.00
4457.50
31933.38
958.00
958.00
319.33
4790.01
38958.72
38958.72
3895.87
818.13
4714.01
133.62
30.73

Est.Dpt
Date:03.08.09
Amount.

4,980.00
2,671.20
3,100.00
10,751.20

4,550.00
3,375.00
7,925.00
18,676.20
373.52
2,801.43
21,851.15
21,851.15
218.51
45.89
264.40
24.57

Est Dpt
Date: 03.08.09

Amount.
(Rs.)
1135.44
552.25
597.99
1826.24
4111.92
10.4

94.5
87.5
18.2
4.725
215.33
4327.25
259.63
649.09
5235.97
5235.97
785.39
72.99
15.33
88.32

Est.Dpt

Amount.
(Rs.)
998.94
998.94

169.00
87.75
256.75
1255.69
37.67
12.56
188.35

1494.27
59770.83
1694.18

Amount.
(Rs.)
32.148
114.10
146.25

640.00
60.00
700.00
846.25

63.47
25.39
8.46
126.94

1070.50
107.05
9.95

Amount.
(Rs.)

1960.00
290.00
553.92
187.62
80.00
50.00
490.00
3611.54

491.03
285.48
148.23
924.74
4536.28
45.36
45.36
680.44
5307.44
5307.44
3711.50
344.93

Amount.
(Rs.)
1103.07
552.25
592.48
2247.80

36.40

400.00
436.40
2684.20
13.42
26.98
406.68
3131.27
3131.27
88.75

Amount.
(Rs.)
4980.00
4935.00
18500.00
28415.00

1997.50
2160.00
4157.50
32572.50
4885.88
37458.38
37458.38
3745.84
106.17

Amount.
(Rs.)
3237.00
5569.50
18500.00
27306.50

1997.50
2160.00
4157.50
31464.00
157.32
316.21
4767.03
36704.57
36704.57
367.05
34.14

Amount.
(Rs.)
4731.00
4762.80
18500.00
27993.80

1997.50
2160.00
4157.50
32151.30
160.76
323.12
4871.16
37506.34
37506.34
375.06
34.89

Amount
33,850.95
250.00
34,100.95
2,500.00
1,350.00
3,850.00
37,950.95
759.02
5,692.64
44,402.61

on the C.C.1:2:4 Bed


Date-031109

Amount.
(Rs.)

380.97
120.73
136.32
17250.00
862.50
200.00
438.00
76.50
19465.02
973.25
20438.27

270
411.25
691.20
1372.45
21810.72
109.05
218.11
3271.61
25409.49
25409.49
2540.95
236.15

Amount.
(Rs.)

756.00
945.00
210.00
100.00
2011.00

78.00
40.50
13.00
131.50
2142.50
21.43
21.43
321.38
2506.73
2506.73
2321.04
215.71

Amount.
(Rs.)
21,280.00
3,598.05
2,373.50
27,251.55
150.00
4,160.00
4,600.00
4,600.00

31,851.55
955.55
637.03
4,777.73
38,221.86
38,221.86
382.22
35.52

Amount.
(Rs.)
2,669.28
1,836.53
4,505.81
75.00
4,550.00
5,000.00
5,000.00
9,505.81
150.00
100.00
750.00
10,505.81
10,505.81
105.06
9.76

Amount.
(Rs.)

11,500.00
825.00
800.00
1,890.00
15,015.00
5,255.25
5,255.25
20,270.25
608.11
405.41
3,040.54
24,324.30
24,324.30
2,432.43
741.59

Amount.
(Rs.)
246.00
15,607.80
3,594.00
2,700.00
22,147.80
5,536.95
5,536.95
27,684.75
830.54
553.70
4,152.71
33,221.70

33,221.70
3,322.17
308.64

Amount.
(Rs.)
2,250.00
22.50
100.00
2,372.50
1,423.50
1,423.50
3,796.00
113.88
569.40
4,479.28
4,479.28
44.79
4.16

x board for expansion joint.


amount

62500
6250

800
175
1200
1000
71925
2157.75

10788.75
84871.5
84871.5
848.715

Amount.
(Rs.)
246.00
15,607.80
3,594.00
2,700.00
22,147.80
5,536.95
5,536.95
27,684.75
830.54

553.70
4,152.71
33,221.70
33,221.70
3,322.17
308.64

Amount.
(Rs.)
4356.00
954.00
5310.00

198.00
960.00
35.00
1193.00
6503.00
975.45
7478.45
7478.45
5665.49
160.59

hk C:M 1:4 for 4.8 Cum


Amount.
(Rs.)
16329.60
954.00
17283.60

720.00
3000.00
87.50
3807.50
21091.10
3163.67
24254.77
24254.77
5053.08
143.23

HWORK NOT EXCEEDING


tity ( 100 sq.mt. )
Amount.
(Rs.)
1400

525
1925
1925
96.25
2021.25
303.1875
2324.4375
` 2500
` 25
`2.3

Quantity

Rate
(Rs.)

Amount.
(Rs.)

6.320
0.440

230.00
600.00

1453.60
264.00

0.880

625.00

550.00
2267.60

0.040
0.700
0.700
0.070

250.00
135.00
125.00
250.00

10
94.5
87.5
17.5

0.035

135.00

4.725
214.23

6.00%

2481.83
148.91

15.00%

372.27
3003.01
3003.01

Quantity

Rate
(Rs.)

Amount.
(Rs.)

8.000
0.420

249.00
1176.00

1992.00
493.92

0.850

645.00

548.25
3034.17

0.040

300.00

12

0.700
0.700
0.070

200.00
200.00
260.00

140
140
18.2

0.035

200.00

7
317.20

8.00%

3351.37
268.11

15.00%

502.71
4122.19
4122.19

Quantity

Rate
(Rs.)

Amount.
(Rs.)

11.000
0.900

249.00
1176.00

2739.00
1058.40

0.780

645.00

503.10
4300.50

0.040
0.700
0.700
0.070

300.00
200.00
200.00
260.00

12
140
140
18.2

0.035

200.00

7
317.20
4617.70

8.00%

369.42

15.00%

692.66
5679.77
5679.77

25 grade concrete

Tremix Paving of 100 mm thk per m2 using M25 g

Quantity

Rate
(Rs.)

Amount.
(Rs.)

0.83
0.03
0.06
5.00

249.00
1945.00
775.00
30.00

206.67
58.35
46.50
150.00

0.30

160.00

48.00

Sr.
no
A)

Item
Materials:
Cement
Sand
Aggregate
Colour Pigment & Hardener
Shuttering

509.52

Sub-Total of Material (M)


B)

0.01
0.06
0.06

300.00
200.00
200.00

2.70
12.00
12.00

Labour:
Mason
Skilled Labour
Unskilled Labour

0.06

250.00

15.00

Carpenter

41.70

Sub-Total of Labour (L)

C)
24.00
12.00

Mechinary
Mixer with Operater
Vibrator with Operater

135.00

Trimix Float Finish with


Operater & Labour

171.00

Sub-Total of Mechinary

1.50%

722.22
10.83

Total (M+L)
Add W.C & Electricity

15.00%

108.33

Add for OH & C.P

841.39

Cost per Sqm (Rs)

78.196

Cost per Sft (Rs)

0.12
0.12
1.00

Quantity

200.00
100.00
135.00

Rate
(Rs.)

Amount.
(Rs.)

500.00
1.32

2.00
230.00

1000.00
303.60

0.28

600.00

165.60
1469.20

0.5
0.8

250
225

125
180

1.6

150.00

240
545.00
2014.20

1.00%
1.00%

20.14
20.14

15.00%

302.13
2356.61
2356.61
66.74

D)

Quantity

Rate
(Rs.)

Amount.
(Rs.)

75.00
0.40

114.00
249.00

8550.00
99.60

0.09

1139.00

97.04
8746.64

0.5
0.8

300
250

150
200

1.6

150.00

240
590.00
9336.64

1.00%

93.37

1.00%

93.37

15.00%

1400.50
10923.87
10923.87
309.37

lding

Quantity

Rate
(Rs.)

Amount.
(Rs.)

7.93

249.00

1,974.57

2.16

2,182.80

4,714.85
6,689.42

0.50
10.00

300.00
250.00

150.00
2,500.00

15.00

150.00

2,250.00
4,900.00
11,589.42

1.00%
1.00%

115.89
115.89

15.00%

1738.41
13559.62
135.60
12.60

m Ex.Scaffolding

Quantity

Rate
(Rs.)

Amount.
(Rs.)

14.28

249.00

3,555.72

2.00

1,139.00

2,278.00
5,833.72

0.50
10.00

300.00
250.00

150.00
2,500.00

15.00

150.00

2,250.00
4,900.00
10,733.72

1.00%
1.00%

107.34
107.34

15.00%

1610.06
12558.45
125.58
11.67

Quantity

Rate
(Rs.)

Amount.
(Rs.)

0.83
0.03

249.00
1945.00

206.67
58.35

0.06

755.00

45.30
310.32

0.02
0.12
0.12

300.00
200.00
200.00

5.40
24.00
24.00

0.05

200.00

9.00
62.40

0.15
0.15

200.00
100.00

30.00
15.00

1.00

135.00

135.00
180.00

1.50%

552.72
8.29

15.00%

82.91
643.92
59.844

m2

Quantity

Rate
(Rs.)

Amount.
(Rs.)

25.00
0.05

15.00
1984.00

375.00
99.20

0.01

1984.00

19.84
494.04
49.40
543.44

0.02

350.00

5.88

0.11

200.00

22.40
28.28

1.50%

571.72
8.58

15.00%

85.76

e sand layer of 10mm thk.

666.06
61.90

Quantity
15.74
2.00
6.39

Rate
(Rs.)
175.00
50.00
387.36

Amount.
(Rs.)
2754.93
100.00
2474.26

51.10
8.00
50.00

16.40
10.00
1.00

838.04
80.00
50.00

15.74

93.00

1464.05
7761.28

1.89
1.10

260.00
260.00

491.03
285.48

1.10

135.00

148.23
924.74
8686.02

1.00%
1.00%

86.86
86.86

15.00%

1302.90
10162.64
10162.64
4640.48
431.27

G.I.Pipe for 100 Rmt.


Description
Unit
Material
50 mmG.I. PipeRmt
Coupling
Nos
Labour
Fitter
Labour

Nos
Nos
Total

Qty

Rate

100.00
17.00
1.00
1.00

Amount

276.00 27,600.00
97.00 1,649.00
200.00
150.00

200.00
150.00
29,599.00

Add 2% Contengencies

591.98

Add Vat & S.Tax 9.12%

2,699.43

Add OH & Profit 15%

4,439.85

G.Total

37,330.26

Rate Per/Rmt.

373.30

PVC 110mm dia.of 6kgf/cm2 for 6 Rmt with Pocket in wall & Grouting

Unit

Quantity

Rate
(Rs.)

Amount.
(Rs.)

Item
Materials:
Pipe (6M)
Bend
Coupler
PVC Solution

rmt
No
No
Ls

1.00
1.00
1.00
1.00

1562.00
260.00
75.00
100.00

1562.00
260.00
75.00
100.00

Grouting

No

1.00

225.00

225.00

Sub-Total of Material (M)


Labour:
Plumber
Each
Helper
Each
For trenching and refilling etc:-

2222.00

1.00
1.00

200.00
135.00

200.00
135.00

Helper

Each

1.00

Sub-Total of Labour (L)

Add for OH & C.P & Taxs

135.00
470.00

Total (M+L)
Add for
Sundries &
Contingencies
Add W.C & Electricity
Add Vat & Service Tax

135.00

2692.00

0.50%
1.00%
9.12%

13.46
27.05
245.51

15.00%

407.86

Total Amt.

3385.88

Cost for 6 Rmt(Rs.)

3385.88

Cost Per 1 Rmt (Rs.)

564.31

Cost per 1 Rft (Rs.)

172.05

With Screed Plaster


Unit

Qty

Rate

Date-220409
Amount

For 100 Sqmt.1:3 (15mm thk.)


Kg
154.00

110.00

16,940.00

Screed Plaster 1:3 (15mm thk.)


Bag
16.00
Cum
1.68

249.00
1,139.00

3,984.00
1,913.52
22,837.52
1,141.88
23,979.40

Add 5 % Wastage

Nos
Nos
Nos

13.00
19.00
0.63

250.00
150.00
300.00

3,250.00
2,850.00
189.00
6,289.00
30,268.40

Add for Vat & Service Tax 9.12%

2,760.48

Contractors Profit & O.H.15%

4,540.26
37,569.13
375.69
34.92

of 75mm thk
Unit

Qty

Date-220409
Amount

Rate

For 100Sqm
Bag
Cum
Cum
Bag

46.00
3.20
6.40
15.00

249.00
1,139.00
698.00
249.00

11,454.00
3,644.80
4,467.20
3,735.00
23,301.00
1,165.05
24,466.05

Nos
Nos
Nos

37.00
50.00
1.88

250.00
150.00
300.00

9,250.00
7,500.00
562.50
17,312.50
41,778.55

Add for Vat & Service Ta

3,810.20

Contractors Profit & O.H.15%

6,266.78
51,855.54
518.56
48.19
Est.Dpt.

4 Wooden Door (0.75X2.1)


Sr
no
A)

Item
Materials:

Unit

Quantity

Rate
(Rs.)

Hinges

Nos

3.00

75.00

Tower bolt
Handles

Nos
Nos

1.00
2.00

75.00
120.00

Screws

Cent

48.00

1.00

Sub-Total of Material (M)


B)

C)

Labour:
Carpenter

Each

0.40

260.00

Beldar

Each

0.40

135.00

0.05

260.00

Mistry
Each
Add for
Sub-Total of Labour (L)
Sundries &
Total
(M+L)
Contingencie
s

1.00%

Add W.C & Electricity

1.00%

Add for OH & C.P


Total Amt.
Cost Per 1.58 Sqm (Rs.)
Cost Per 1 Sqm (Rs.)
Cost per 1 Sft (Rs.)

15.00%

per m2 using M25 grade concrete

Unit

Quantity

Rate
(Rs.)

Bags
Cum
Cum
Kgs

1.10 249.00
0.04 1945.00
0.08 775.00
6.68
30.00

Sqm

0.40

160.00

Amount.
(Rs.)
273.90
77.80
62.00
200.40
64.00
678.10

Each
Each
Each

0.01
0.06
0.06

300.00
200.00
200.00

2.70
12.00
12.00

Each

0.06

250.00

15.00
41.70

Cum
Cum

0.12
0.12

200.00
100.00

24.00
12.00

Sqm

1.00

135.00

135.00
171.00

1.50%

890.80
13.36

15.00%

133.62
1037.78
96.45

Amount.
(Rs.)
225.00
75.00
240.00
48.00
588.00

104.00
54.00
13.00
171.00
759.00
7.59
7.59
113.85
888.03
888.03
562.04
52.23

ILA + ROADM
Rate Analysis - Maharashtra
Sl No.
1

Basic Cost of Materials


Description
UOM
Labour Rates

1.1
1.2

Skilled
Unskilled

Material Rates

2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10

Cement
Aggregate 20 mm Dn
Sand
Bricks
Boulders
Reinforcement Steel
Structural Steel
Ply Wood 10 Mm thk
Hard Wood
Wire Nails

Sl no.
1
2
3
4
5
6

Rate

M-Day
M-Day

232
225

Bags
CuM
CuM
Nos
CuM
MT
MT
Sq M
Cft
Kg

300
850
1000
3.5
800
48000
50000
650
400
60

Excavation in SOIL incl backfilling & disposal of surplus earth


Measurements
Description
Unit
Nos
L
B
USL excavation
manday
0.50 ( I USL can excavate 2 m3 /day )
manday
0.07 ( I USL can backfill 15 m3 /day )
USL back filling with available earth
Supervisor
manday
0.05
( 1 supervisor per 10 USL )
Sub Total
Contractor's OH & P
Sub Total
per m3
Excavation in SOFT ROCK

Sl no.

Description

Unit

1
2
3
4
5
6

USL excavation

manday
manday
manday

USL back filling with available earth

Supervisor
Sub Total
Contractor's OH & P
Sub Total

per m3

Excavation in HARD ROCK


Sl no.

Description

Unit

1
2
3

USL excavation

manday
manday
manday

USL back filling with available earth

Supervisor

incl backfilling & disposal of surplus earth


Measurements
Nos
L
B
1.33 ( I USL can excavate 0.75 m3 /day )
0.07 ( I USL can backfill 15 m3 /day )
0.13
( 1 supervisor per 10 USL )

incl backfilling & disposal of surplus earth


Measurements
Nos
L
B
2.00 ( I USL can excavate 0.5 m3 /day )
0.07 ( I USL can backfill 15 m3 /day )
0.20
( 1 supervisor per 10 USL )

4
5
6

Sub Total
Contractor's OH & P
Sub Total

Sl no.

Description

1
1.1
1.2
1.3
2
3
4
4.1
4.2
5
6
7
8
8.1
8.2
8.3
8.4
8.5
9
10
11

Material per sq ft
Ply 10 mm thk
Hard wood
Wire nails
Sub total
Wastage
Manpower
Carpenter
Helper
Sub Total cost per sq m
Nos of repetitions
Cost per repetition
Cost of fixing
Carpenter
Helper
Wire nails
Shuttering oil
Leads & Lifts & Transportation
Sub Total
Contractor's OH & P
Total

per m3

Unit
Sq m
Cuft
kg

Form Work
Measurements
Nos
L
B
1.00
2.00
0.625

2%
man days
man days

0.07 ( 1 carpenter + 2 helper can make 1


of board )
0.07

man days
man days
kg
LS

0.10 ( 1 carpenter + 2 helper can make 1


of board )
0.10
0.625

15%

Sl no.

Description

Unit

1
2
3
4
5
6
7
8
9
10
11
12

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of RMC M10

bag
m3
m3
3%
5%
LS
man day
manday

PCC M 10 Grade
Measurements
Nos
L
B

1
0.1

(1 manday per m3 )

Sl no.

Description

Unit

1
2
3
4
5
6
7
8
9
10
11
12

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Tools & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of M15

bag
m3
m3
3%
5%
LS
man day
manday

Sl no.

Description

Unit

1
2
3
4
5
6
7
8
9
10
11
12

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of M20

bag
m3
m3

Sl no.

Description

3%
5%
LS
man day
manday

Unit

1 Reinforcement FOR site incl taxes


MT
2
Wastage
MT
3
Rolling Margin
MT
4
Realisation of scrap
MT
5
Sub Total cost of reinforcement
6 Labour for cutting bending & fixing
7
Skilled
mandays
8
Unskilled
mandays
9
binding wires
kg
10
Transportation

RCC M15 Grade


Measurements
Nos
L
B

1
0.1

(1 manday per m3 )

RCC M 20 Grade
Measurements
Nos
L
B

1
0.1

(1 manday per m3 )

Reinforcement
Measurements
Nos
L
B
-

5
10

I fitter & 2 helper can carry out


0.20 MT per manday
6

11
12
13

Sub Total cost of reinforcement


contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5
6
7
8
9
10

cost of brick
cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total

230 mm thick brick work


Measurements
Unit
Nos
L
B
nos
450.00
bag
1.80
cft
11.00
3%
mandays
mandays

Sl no.

Description

Unit

1
2
3
4
5
6
7
8
9
10
11

cement
sand
sub total
wastage
skilled mason
unskilled
Lead and lifts
Scaffolding
sub total
contractor's OH & P
Total

bag
cft

Sl no.

Description

1
2
3
4
5
6
7
8
9

cement
sand
sub total
wastage
skilled mason
unskilled
Lead and lifts
Scaffolding
sub total

3%
mandays
mandays

0.67
1.33

1 mason & 2 helpers can do 1.5


m3 of brick work per day

Flush Pointing
Measurements
Nos
L
B

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

12 mm thick plaster 1:4


Measurements
Unit
Nos
L
B
bag
cft
3%
mandays
mandays

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

10
11

contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

cement
sand
sub total
wastage
manpower for 1st coat
skilled mason
unskilled
manpower for 2nd coat
skilled mason
unskilled
sand facing
Lead & Lifts
Scaffolding
sub total
contractor's OH & P
Total

20mm thick plaster sand faced in 2 coats


Measurements
Unit
Nos
L
B
bag
cft
3%
mandays
mandays

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

mandays
mandays

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

Sl no.

Description

Unit

1
2
3
4
5
6
7
8
9
10
11

Rubble
Breaking
Cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total

m3
m3
bag
cft

Rubble masonary
Measurements
Nos
L
B
1.35
1.35
1.80
11.00

3%
mandays
mandays

Sl no.

Description

Unit

1
2

Cost of Materials
Wastage Unacountable

MT
MT

0.67
1.33

1 mason & 2 helpers can do 1.5


m3 of RRM per day

Structural Steel
Measurements
Nos
L
B
1
1

2%

3
4
5
6
6.1
6.2
6.3
6.4
6.5
6.6
6.7
6.8
6.9
6.10
6.11
6.12

Wastage acountable
Scrap Value Realisation
Sub Total Cost of Materials
Fabrication & Erection
Fitter
Gas Cutter
Welder
Helper
Riggers
Consumables ( Past Experience )
Power
Cranage & Handling
Galvanisation - Zinc
Galvanisation Manpower
Transportation to Site
Sub Total
Vendor's OH & P

MT
MT
MT

1
1
1

M-day
M-day
M-day
M-day
M-day
MT
MT

1
1
1
3
7

Kg
MT
MT

60

3%
-3%

Output 1 MT/Day
Output 1 MT/Day
Output 1 MT/Day
Output 1 MT/Day
Output 1 MT/Day

LS Considered

@15%

Total

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11

Rubble
Breaking
sub total
wastage
Sub Total Materials
Cost of 230 mm thick soling
skilled mason
unskilled
sub total
contractor's OH & P
Total

Sl no.

Boulder Soling 230 mm Thk


Measurements
Unit
Nos
L
B
m3
1.35
m3
1.35
3%
m2
mandays
mandays

Description

1
Cost of M 15 grade concrete
2
Shuttering for panels
3
sub total
4
wastage
5
Sub Total Materials
6
Addl Cement
7 Addl Manpower for smooth finish
9
sub total for 9 m2
10 contractor's OH & P on addl items
11
Total

Unit
m3
m2

0.07
0.13

1 mason & 2 helpers can do 15


m2 of RRM per day

IPS 40 mm thick
Measurements
Nos
L
B
1.00
3
3
2.00
3

3%
m2
m2

1.00
1.00

3
3

3
3

12

Cost per m2

f surplus earth
ts
H
avate 2 m3 /day )
ckfill 15 m3 /day )
or per 10 USL )

Qty
0.50
0.07
0.05

Rate Amount
225
225
232

113
15
12
139
21
160

al of surplus earth
ts
Qty
Rate Amount
H
vate 0.75 m3 /day )
1.33 225
300
ckfill 15 m3 /day )
0.07 225
15
or per 10 USL )
0.13 232
31
346
52
398

sal of surplus earth


ts
Qty
Rate Amount
H
vate 0.5 m3 /day )
2.00 225
450
ckfill 15 m3 /day )
0.07 225
15
or per 10 USL )
0.20 232
46

511
77
588

ts
H

Qty

Rate Amount

1.00
###
0.625

650
400
60

650
800
38
1,488
30

+ 2 helper can make 15 m2


of board )

232
225

15
15
1,548
10
155

+ 2 helper can make 10 m2


of board )
0.625

232
225
60

23
23
38
5
10
253
38
291

ts
H

Qty

Rate Amount

4.20 300
0.52 1000
0.85 850

1
0.1

225
232

1,260
520
723
2,503
75
125
250
225
23
3,201
480
3,681

0.21
0.934

ts
H

Qty

Rate Amount

6.20 300
0.52 1000
0.85 850

1
0.1

ts
H

Qty

225
232

ts
H

lper can carry out


per manday

Qty
1.00
0.03
0.05
-0.02

5
10
###

0.31

Rate Amount

8.00 300
0.52 1000
0.85 850

1
0.1

1,860
520
723
3,103
93
155
250
225
23
3,849
577
4,426

225
232

2,400
520
723
3,643
109
182
250
225
23
4,432
665
5,097

Rate Amount
48000 ###
48000 1,440
48000 2,400
48000 (720)
###
225
232
60

1,125
2,320
360
1,000

0.4

15%

ts
H

elpers can do 1.5


k work per day

Qty

###
8,389
###

Rate Amount

450
1.80
11

3.5
300
28

0.67
1.33

232
225
15%

1,575
540
308
2,423
73
155
300
2,950
443
3,393

0.0625
0.311
8.784

tuck pointing , flush pointing, rise pointing

ts
H

helpers can do
ck work per day

Qty

Rate Amount

0.05
0.26

300
28

0.07
0.13

232
225

15%

15
7
23
1
15
30
5
5
79
12
91

0.1446759259
0.00736

Is it for per m2 ??

ts
H

helpers can do
ck work per day

Qty

Rate Amount

0.10
0.51

300
28

0.07
0.13

232
225

31
14
45
1
15
30
5
5
102

15%

oats
ts
H

Qty

15
117

Rate Amount

0.17
0.85

300
28

51
24
75
2

helpers can do
ck work per day

0.07
0.13

232
225

15
30

helpers can do
ck work per day

0.07
0.13

232
225

15
30
5
5
5
183
27
210

15%

ts
H

Qty
1.35
1.35
1.80
11.00

elpers can do 1.5


RM per day

0.67
1.33

Rate Amount
800
50
300
28

232
225
15%

ts
H

1,080
68
540
308
1,996
60
155
300
2,510
377
2,887

Qty

Rate Amount

1
0.02

50000
50000

###
1,000

0.03
-0.03

50000
50000

1,500
###
51,000

1 MT/Day
1 MT/Day
1 MT/Day
1 MT/Day
1 MT/Day

1
1
1
3
7

232
232
232
225
232

60

225

onsidered

232
232
232
675
1624
1500
200
500
13500
1500
2000
73,195
10,979

###

ts
H

Qty
1.35
1.35

helpers can do 15
RM per day

0.07
0.13

Rate Amount
800
50

232
225
15%

ts
H
0.04
0.04

3 kg/m2

Qty

Rate Amount

0.36 ###
0.24
300

27
9

1,080
68
1,148
34
1,182
272
15
30
317
48
365

6
10
15%

1,620
72
1,692
51
1,743
162
90
1,995
37.80
2,033

226

4.976

nting, rise pointing

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Sl.
Short
No.
Description
A Earth Work
1 EXCAVATION IN
SOIL-NGL TO 3M
DEPTH

B Disposal
2 CARTING beyond
3KM LEAD
3 EXTRA FOR
CARTING
BEYOND
C Filling
SPECIFIED LEAD
4 BACKFILL MURRUM/YELLO
W EARTH
BROUGHT FROM
OUTSIDE

D Formwork

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 1 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

5 P&F FORMWORK
BLW FGL

6 P&F FORMWORK
ABOVE FGL TO
10M HT

7 P&F FORMWORK
> 10M TO 20M HT

8 P&F FORMWORK
20M AND ABOVE

10 Extra for
CurvedShuttering
- Plywood
E Reinforcement
Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 2 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

11 FIXING OF
REBAR - BELOW
FGL

12 FIXING REBAR ABOVE FGL TO


10M HT

13 FIXING REBAR HEIGHT ABOVE


10M TO UPTO
20M
14 FIXING REBAR HEIGHT ABOVE
20M

F Plain Cement Concrete

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 3 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

22 P&L M10 BELOW


FGL

23 P&L M15 BELOW


FGL

G Plum Concrete
24 P&L M10 GRADE
PLUM
CONCRETE

H Reinforced Cement Concrete


25 P&LAYING M30
RCC RMC
BELOW FGL
26 P&Laying M20
RCC RMC Above
FGL to 5m Ht

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 4 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

27 P&LAYING M30
RCC RMC
ABOVE FGL TO
upto 10M HT
28 P&LAYING M30
RCC RMC >10M
UPTO 20M HT
29 P&LAYING M30
RCC RMC >20m

I Anchor Fasteners, Inserts & Misc. Steelwork


34 Fixing Anchor
Fastener M16 to
M25
35 Fixing Anchor
Fastener M16 to
M26

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 5 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

36 S,F,P&E OF MS
INSERT PLATES

J Miscellaneous Items
37 P&F SHALITEX
BOARD 12MM
THICK
38 P&F SHALITEX
BOARD 25MM
THICK
39 P&F SHALITEX
BOARD 50MM
THICK

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 6 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

40 P&A
PRECONSTRUCT
ION
ANTITERMITETR
EATMENT

41 P&L 75MM THK


PLINTH
PROTECTION IN
M15
42 P&L 230MM THK
RUBBLE SOLING

43 Dismantling&Disp
osal-RCC in
Substructure
44 Dismantling&Disp
osalRCCinSuperstruct
45 Forming
Isolation
ure
Joints

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 7 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

46 POCKET
0.025SQM AREA
& UPTO 300MM
47 DPTH
POCKET >0.0250.05SQM & DPTH
>300-600MM
48 SUPPLY &
FABRICATION OF
MS TEMPLATES
49 C13601-P/F
FOUNDATION
BOLT
50 Providing,MIXING
& LAYING
CEMENT GROUT
51 P&A NS GROUT
AT EQP
FOUNDATIONS
52 P&L Sand

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 8 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

53 Providing & Laying


50-75mm Thick
Screed Concrete

54 Providing & fixing


Thermocol
Sleeves
55 Core Cutting 150
mm Dia upto
200mmDepth
56 Core Cutting
150mmDia >200
to 300mmDepth
57 Core Cutting
150mmDia >300
to 400mmDepth
58 Core Cutting 250
mm Dia upto
200mmDepth

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 9 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

59 Core Cutting
250mmDia >200
to 300mmDepth
60 Core Cutting
250mmDia >300
to 400mmDepth
61 Expansion Joints

62 Al. Sheet 450mm


wide on Exp Joint
63 P&F 230MM
DUMB BELL
SHAPE PVC
WATER BAR
64 PILE CUTTING
ABV CUTOFF
LVL&DISPSL
UP2KM

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 10 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

65 P & F Barricading

K Masonry
P&L BW 230MM
66 AT ALL
ELEVATIONS
P&C BW 115MM
67 AT ALL
ELEVATIONS
P & L LIGHT
WEIGHT BLOCK
68
MASONRY
200MM TK.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 11 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L BW 350MM
69 AT ALL
ELEVATIONS

70

C1060401-P&L
DPC 40mm & M15

L Plastering
P&L 12MM THK
71 smooth PLASTER
- CM 1:4

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 12 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

C11302-P/A
72 gypsum Plaster 12
mm

P&L 6-8MM THK


CEMENT
73
PLASTER - CM
1:3
P&L 20MM THK
74 SAND FACED
W/P PLASTER
P&A WHITE
75 CEMENT BASED
PUTTY

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 13 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&F GI CHICKEN
76 WIRE MESH
300MM WIDE
8MM X 8MM
77 GROOVE IN
PLASTER
P&F ALU.PLATE
OVER
78
EXPSN.JOINT3MMX100MM
M Waterproofing and Insulation

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 14 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L POLYMER
BASED
WATERPROOFIN
79
G-TERRACE
WITH BRICKBAT
COBA

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 15 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L MEMBRANE
80 TYPE WP
TREATMENT

Protective layer
81 M15 screed with
neat cement finish

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 16 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

Short
Description

82

P&L OVER DECK


INSULATION

FR-ZR-5017 Rev. 00 Sheet 3 of 3

83

P&L CHINA
MOSAIC
FLOORING
Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 17 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description
P&L CHINA
MOSAIC
FLOORING

84

P&L
WATERPROOFIN
85 G-POLYMER
BASED IN
TOILETS

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 18 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L BRICKBAT
86 COBA FOR SUNK
PORTION

S&A OF WP
87 TREATMENT IN
SERVER HALLS

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 19 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

S&F110MM LEAF
TRAP W/UPVC
88
KHURRA
W/FLANG
S&F160MM LEAF
TRAP W/UPVC
89
KHURRA
W/FLANG
N Roof sheeting and cladding
S&F PRECOATED
90 GALVALUME
SHEET IN ROOF

S&F PRECOATED
GALVALUME
91 SHEET IN
RIDGE/GUTTER/
FLASING

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 20 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

S&F PRECOATED
91-a GALVALUME
SHEET IN RIDGE

S&F PRECOATED
GALVALUME
91-b
SHEET IN
FLASING
S&F PRECOATED
GALVALUME
91-C
SHEET IN
FLASING

S&F PRECOATED
GALVALUME
91-D
SHEET IN
GUTTER
O Painting
Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 21 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

Short
Description

92

P&A - Whitewash
2 coats

FR-ZR-5017 Rev. 00 Sheet 3 of 3

P&A INTERNAL
93 ACRYLIC
EMULSION PAINT

S&A EXTERIOR
94 GRADE ACRYLIC
EMULSION PAINT

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 22 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&A ANTI
95 CARBONATION
PAINT
P FLOORING
96

P&L GRANITE IN
FLOORING

P&L VITRIFIED
97 TILES IN
FLOORING
P&L NON-SKID
98 VITRIFIED TILES
IN FLOORING

99

P&L 40MM THICK


IPS FLOORING

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 23 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P/L IPS
100 FLOORING 50MM
IN CC1:2:4

101

P&L 75MM THICK


IPS FLOORING

P&L KOTA
102 STONE IN
FLOORING

103

S&A OF EPOXY
FLOORING

P&L 40MM THK


104 PCC M15 IN
FLOOR SCREED

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 24 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L 12MM THK


105 ACID/ALKALI
RESISTANT TILE

P&L COMPOSITE
106 MARBLE
FLOORING

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 25 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L 600MM HIGH


COMPOSITE
109
MARBLE
SKIRTING

P&F GRANITE IN
110 SKIRTING-100MM
HIGH

P&L KOTA
STONE IN
111
SKIRTING-100MM
HIGH

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 26 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P/L 100 MM
112 VITRIFIED TILE
SKIRTING

P&L KOTA
STONE IN
113
SKIRTING-300MM
HIGH

P&L KOTA
STONE IN
114
SKIRTING-300MM
HIGH

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 27 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

P&L KOTA
STONE IN
115
TRAPEZOIDAL
SKIRTING

116

P&L VITRIFIED
TILES IN DADO

117

P&L GLAZED
TILES IN DADO

118

P&F GRANITE IN
TREAD

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 28 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

Short
Description

119

P&F GRANITE IN
RISER

FR-ZR-5017 Rev. 00 Sheet 3 of 3

P&L KOTASTONE
120 IN STAIRCASE
TREAD
P&L KOTASTONE
121 IN STAIRCASE
RISER
P&L GRANITE IN
122 PANTRY
PLATFORM

124

Lift Lobby L-0,L-1,


L-2, L-3,L-4

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 29 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

Short
Description

125

Lift Lobby L-0 &


L-1

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Q STRUCTURAL STEEL
SHOP - LIGHT
STEEL
STRUCTURE

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 30 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description
SHOP - MEDIUM
STEEL
STRUCTURE

SHOP - HEAVY
STEEL
STRUCTURE

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 31 of 557

SCHEDULE OF QUANTITY / RATE

Sl.
No.

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Short
Description

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 32 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Excavation from NGL up to 3m depth using contractor owned P&M in all types of soil including hard murrum, soft rock and disintegrated rock but
excluding hard rock, including necessary dewatering, demucking, shoring/strutting, segregation of reusable excavated earth from vegetation and
debris, disposal up to 200m lead including spreading, stacking the excavated material, removing loose excavated matter from the excavated area etc.
complete as per drawing, specifications and as directed by EIC.
Note: Measurement shall be made as per theoretical maximum plan dimensions of PCC details in the drawing. Separate/ extra payment shall not be
made for working space.

Charges for Loading & Carting away/ carting in surplus/ unusable


excavated earth/ rock or any other material, beyond 200m and up to 3Km lead complete as directed by EIC
Extra for carting away or carting in surplus earth/ earth from borrow pits /rock/debris etc. beyond specified lead complete as directed by EIC.
Note: One-way linear distance to be considered for payment.
Backfilling using Contractor owned P&M, in and around embankments, foundation pits, trenches, plinth etc. in layer not exceeding 200mm thickness
with selected good quality murrum / yellow earth brought from borrow pits (Approx. lead 20 Km) outside Owner's premises including watering and
compacting to 90% modified proctor density, dressing, trimming etc. complete as per drawing, specifications and as directed by EIC.
Note: Payment shall be made based on certified excavation quantity less volume occupied by the structure for foundations, pits and trenches and
theoretical backfill quantity for plinth.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 33 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and fixing below FGL to correct level, line & plumb, plain formwork made of plywood/ MS shuttering/ planks for horizontal/ vertical RCC
members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during concreting and
removing after the specified curing period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note:
Form work measurement will be on contact area of concrete only.
Providing and fixing above FGL up to 10m height to correct level, line & plumb, plain formwork made of plywood/MS shuttering/planks for horizontal/
vertical RCC members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during
concreting and removing after the specified curing
period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note: Form work measurement will be on
contact area of concrete only.
Providing and fixing above 10m up to 20m height to correct level, line & plumb, plain formwork made of plywood/MS shuttering/planks for horizontal/
vertical RCC members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during
concreting and removing after the specified curing
period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note: Form work measurement will be on
contact area of concrete only.
Providing and fixing above 20m height to correct level, line & plumb, plain formwork made of plywood/MS shuttering/planks for horizontal/ vertical RCC
members for all RCC works including necessary staging, strutting, scaffolding, bracing etc., keeping the same in position during concreting and
removing after the specified curing
period and including all consumables etc. complete as per drawing, specifications and as directed by EIC. Note: Form work measurement will be on
contact area of concrete only.
Extra over for providing, making and fixing in position Formwork made of plywood in circular/ curved shape. Note: Form work measurement will be on
contact area of concrete only

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 34 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Fixing in position below FGL MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at designated place, straightening,
cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details, binding with contractors own 1820 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost of necessary staging/ scaffolding
etc. complete as per drawing, specifications and as directed by EIC.
Fixing in position above FGL to 10m height MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at designated
place, straightening, cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details, binding with
contractors own 18-20 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost of necessary
staging/ scaffolding etc. complete as per drawing, specifications and as directed by EIC.
Fixing in position at height greater than 10m upto 20m height MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at
designated place, straightening, cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details,
binding with contractors own 18-20 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost
of necessary staging/ scaffolding etc. complete as per drawing, specifications and as directed by EIC.
Fixing in position at height greater than 20m height MS/ Tor Steel/ HYSD bar for RCC Work including transportation, handling and stacking at
designated place, straightening, cleaning, cutting, bending, placing and tying in position, binding to shape and length as per approved drawing details,
binding with contractors own 18-20 SWG black soft annealed binding wire, placing with approved quality cover blocks, supports, chairs, spacers, cost
of necessary staging/ scaffolding etc. complete as
per drawing, specifications and as directed by EIC.

Concrete

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 35 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and laying RMC/ weigh-batched machine-mixed M-10 grade plain cement concrete below FGL in any shape, position, thickness and
including side shuttering, tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing and finishing the top surface etc.
complete as per drawing, specifications and as directed by EIC.

Providing and laying RMC/ weigh-batched machine-mixed M-15 grade plain cement concrete below FGL in any shape, position, thickness and
including side shuttering, tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing and finishing the top surface etc.
complete as per drawing, specifications and as directed by EIC.

e
Providing and laying RMC/ weigh-batched machine-mixed M-10 grade plum concrete consisting of 80% PCC mix 1:3:6 and 20% rubble stone
maximum size of 150mm laid in layers at all depths below FGL up to plinth level in foundations, drains, fillings, pavements and ramps etc. in any
shape, position, thickness and including side shuttering, tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing and
finishing the top surface etc. complete as per drawings, specifications and as directed by EIC.

ment Concrete
Providing & Laying Contractor supplied RMC of M - 30 Grade Reinforced Cement Concrete below FGL in any shape, position, thickness and
including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing etc. complete as per drawing, specifications and as
directed by EIC.
Providing & Laying Contractor supplied RMC of M20 grade Reinforced Cement Concrete above FGL upto 5m Height in any shape, position, thickness
and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc complete as
per drawing, specifications and as directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 36 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing & Laying Contractor supplied RMC of M - 30 Grade Reinforced Cement Concrete above FGL up to 10m height in any shape, position,
thickness and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc.
complete as per drawing, specifications and as directed by EIC.
Providing & Laying Contractor supplied RMC of M - 30 Grade Reinforced Cement Concrete above 10m up to 20m height in any shape, position,
thickness and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc.
complete as per drawing, specifications and as directed by EIC.
Providing & Laying Contractor supplied RMC of M30 grade Reinforced Cement Concrete at height greater than 20m in any shape, position, thickness
and including tamping, spreading to the slopes, ramming, vibrating, consolidating, compacting, curing, cost of necessary scaffolding etc complete as
per drawing, specifications and as directed by EIC.

ers, Inserts & Misc. Steelwork


Supplying, transporting, handling and installing chemical anchor fasteners ( Hilti or equivalent make) M12,M16 or M20 of all lengths at all elevations
including drilling of holes all as per manufacturer's specification and as directed by EIC.
Supplying, transporting, handling and installing mechanical anchor fasteners ( Hilti or equivalent make)M12, M16,M20 or M24 of all lengths at all
elevations including drilling of holes all as per manufacturer's specification and directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 37 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Supply, fabrication, painting and erection of MS insert plates at all heights including (i) Supply of structural steel as per Indian Standard. (ii) Fabrication:
Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting of joints and completing the work as per drawings,
specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for fabrication shall be carried out. Trial assembly if required
shall be in contractor's scope. Provision of all type to staff and workmen, provision of all required lifting tools-tackles including P&M, all type of welding
and cutting consumables and gases are in contractor's scope. (iii) Painting: including blasting of steel with grits & shots with one coat of red oxide
primer and two coat of enamel paint using airless spray gun as per specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/
modules at all heights including fixing & removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary
staging, bolting to required torque, touch up painting, completing the work in all respect as per drawings, specifications and codes as per the
instructions of EIC and fulfilling owner's safety norms & practices at work site including NDT as per requirement & specification.

Items
Providing and Fixing 12mm thick Shalitex board of Shalimar make or approved equivalent conforming to IS: 1834 (Part 1) 1983 in expansion joint
including any wastage complete as per drawing, specification and as directed by EIC.
Providing and Fixing 25mm thick Shalitex board of Shalimar make or approved equivalent conforming to IS: 1834 (Part 1) 1983 in expansion joint
including any wastage complete as per drawing, specification and as directed by EIC.
Providing and Fixing 50mm thick Shalitex board of Shalimar make or approved equivalent conforming to IS: 1834 (Part 1) 1983 in expansion joint
including any wastage complete as per drawing, specification and as directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 38 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and applying pre-construction anti termite treatment under and around foundation pits, wall trenches, basement excavation, top surface of
plinth filling, junction of wall and floor, along the external perimeter of building, expansion joints, surrounding areas of pipes, ater conduits and at all
other locations identified by EIC. Work will be carried out by approved specialised agency for termite/ pest control using chloropyriphos emulsifiable
1.0% concentration by weight applied as per specifications and as directed by EIC. The work shall carry a guarantee for satisfactory performance for a
minimum period of 10 (Ten)years on Rs. 100 Stamp Paper.
Note: Plinth area of the treated building at Ground level excluding open courts, porches and basements shall be measured for payment.

Providing and laying plinth protection around building with average 75mm thick M-15 grade cement concrete broom-finished on top, laid to proper line
and level over 230 mm thick bed of hard core rubble and 300mm thick layer of consolidated murrum complete as per specifications, drawing etc.
complete as directed by EIC.
Providing and laying dry rubble soling of average thickness 230 mm in plinth, foundation etc. including hand packing, filling of voids with stone chips
and crusher dust blindage on top, watering, ramming, rolling using rollers, compacting etc. complete as per drawing, specifications and as directed by
EIC.
Dismantling of RCC in substructure including cutting of reinforcement steel with all consumables and disposal of debris within 5KM lead complete as
directed by EIC. All P&M is in the scope of the Contractor
Dismantling of RCC in superstructure including scaffolding, cutting of reinforcement steel with all consumables and disposal of debris within 5KM lead
complete as directed by EIC. All P&M is in the scope of the Contractor
Forming isolation joints around equipment's foundations / columns / pedestals / trenches, etc. including cleaning the joints of all loose material, filling
clean sand for the full depth except for top to enable sealing with approved polysulphide liquid sealing compound etc. or any other equivalent all
complete as shown on drawing and specified in manifacturer's recommendations and as directed by EIC.
Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 39 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing & fixing Pockets at all heights in correct position of plan area up to 0.025 Sqmt and up to 300mm depth in concrete for fixing foundations
bolts as per drawings & specifications including providing, fixing & removing of necessary form works and cleaning the site etc.complete as directed by
EIC.
Providing & fixing Pockets at all heights in correct position of plan area up to 0.025 Sqmt and up to 300mm depth in concrete for fixing foundations
bolts as per drawings & specifications including providing, fixing & removing of necessary form works and cleaning the site etc. complete as directed by
EIC.
Fabrication of MS Templates including supplying, cutting, grinding, edge preparation, drilling, assembly, fit-up and welding, cost of consumables etc.
complete as per drawing, specifications and as directed by EIC.
Providing & Fixing of foundation bolts with necessary cutting, fabricating, welding, hoisting and threading including all accessories like washer ,nut
angle, flat,I section, channel etc. during concreting including all cost of labour, centering and shuttering true to line, level and plumb etc. complete in all
leads and lifts as per drawings and specifications and as directed by EIC.
(Note-Templates
will be provided at no extra cost .)
Providing,Mixing and laying cement grout in 1:2 at all heights for foundation pockets, under base plates, machine frames, steel columns along with
shimplates for leveling purpose, curing, cleaning out surface as per drawing, specifications and as directed by EIC.

Providing and applying Grouting of equipment foundations at all heights with non-shrink grout of Fosroc Conbextra GP2 or approved equivalent
including surface preparation, shuttering, deshuttering, curing, cleaning, etc. complete as per manufacturer's specifications and as directed by EIC.

Providing, filling, laying and spreading approved quality sand in pits, foundations and pipe trenches etc including cost of leveling, compaction etc all
complete as directed by the EIC

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 40 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing & Laying Screed Concrete (RMC) of average thickness 50mm to 75mm at all levels to proper line, level and slope and including cost of side
shuttering if any, finishing, pond curing etc complete as per drawings, specifications and as directed by EIC.

Providing & Placing in position Thermocol/ Polysterene Sleeves around Foundation Bolts, providing and fixing mastic tape around the sleeves and
removal of sleeves after completion of the job complete as per specifications and as directed by EIC
Charges for Core Cutting 150mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth upto 200mm with Contractor-owned core cutting
machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if required, barrel end
connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 150mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 200mm upto 300mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 150mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 300mm upto 400mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 250mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth upto 200mm with Contractor-owned core cutting
machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if required, barrel end
connection, all labour, consumables etc complete as per drawing and as directed by EIC

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 41 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Charges for Core Cutting 250mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 200mm upto 300mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Charges for Core Cutting 250mm dia in RCC Floor/ Pavement/ Wall at all elevations and depth greater than 300mm upto 400mm with Contractorowned core cutting machine including cost of Hilti make diamond drill bit, drop in anchor pin, drill machine with bit for anchor, extension piece if
required, barrel end connection, all labour, consumables etc complete as per drawing and as directed by EIC
Forming expansion joints in all types of structures including cleaning the joints of all loose material, filling Shaltex board or equivalent inside the gaps
and sealing with approved polysulphide liquid sealing compound etc. or any other equivalent all complete as shown in drawing and specified in
manufacturerers recommendations & as directed by EIC.(Refer REG Specification No. SS-CS-63002) with 50mm thick filler materials. All materials in
contractors scope.
Providing and fixing 1.5mm thick 450mm wide aluminium sheet for covering expansion joint including cost of bending, groove making, consumables
etc complete as directed by EIC.
Providing & fixing in position 230mm wide dumb bell shaped white PVC water bar of CALICO or equivalent with central bulb as per drawing,
specifications and as directed by EIC

Chipping of pile concrete 600mm dia above cut off level manually/contractor owned P&M and removing debris from area and dozing at designated
disposal yard
upto lead of 2km including making of grooves with chisel upto required
level/profile as per drawing ,excess reinforcement cutting, straightning
of reinforcement in piles applying of bonding agent etc all complete as
per instructions of EIC.(Lenght of the pile cut will be considered for payment)
Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 42 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
PROVIDING AND FIXING BARRICADING STRUCTURES AS PER APPROVED DRAWING ,DRILLING IN EXISTING RCC PAVEMENT, GROUTING
OF STRUCTURAL MEMBER,PROVIDING AND FIXING GI SHEETING WITH PIPE, ENCASING BASE OF BARRICADING PIPES WITH M20
CONCRETE ETC. ALL AS PER APPROVED DRAWING AND INSTRUCTION OF EIC.INCLUDING 1 COAT OF PRIMER & 2 COATS OF ENAMEL
PAINT (STRUCTURAL STEEL REQUIRED FOR THIS JOB SHALL BE PAID UNDER RELEVANT ITEM)

Providing and constructing minimum 230mm thick Brick Masonry at all elevations with approved quality bricks (having minimum crushing strength @
50Kgf/Sqcm) in 1:4 cement mortar and including necessary scaffolding, mixing of mortar, raking out joints, curing etc. complete as per drawing,
specifications and as directed by EIC.
Providing and laying 115mm thick Brick Masonry at all elevations with approved quality bricks (having crushing strength of 50 Kgf/Sqcm) in 1:4 cement
mortar and including mixing of mortar, raking out joints, curing, laying of 2 Nos 6mm dia MS Rod at every 4th layer, necessary scaffolding etc. complete
as per drawing, specifications and as directed by EIC.
Providing & Laying of aerated concrete block (Siporex or equivalent) of 200MM thick, having minimum crushing strength of 30 kg/sqcm in cement
mortar 1:4, in superstructure, including all necessary scaffolding, raking out joints, curing etc. complete as per specifications and as directed by
Engineer In Charge.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 43 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and constructing brick masonry, 350 MM thick, at all elevations with common burnt clay bricks having minimum crushing strength of 50
kg/sqcm in cement mortar 1:4, in superstructure, including all necessary scaffolding, raking out joints, curing etc. complete as per specifications and as
directed by engineer in charge.

Providing & laying damp proof coarse (DPC) 40mm thick with cement concrete M-15 grade with necessary side shuttering, compaction, curing,
deshuttering etc. complete in all lead and lifts as per drawings and specifications and as directed by EIC with water proofing material 'Impermo' or
equivalent in cement concrete work @ 1 kg per 50 kg. of cement.

Providing and laying 12mm thick smooth finish plaster at all heights in CM 1:4 in proper line and level including surface preparation, providing drip
mould & groove if any, curing, erection and removal of scaffolding etc. complete as per drawing, specifications and as directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 44 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing, preparing and plastering readymade proprietary Gypsum plaster of approved manufacturer to internal walls and ceilings average 12mm
thick to wall surfaces of concrete, masonry work (Gypsum consumption 2.14 Kg/Sft), including doing jambs, sills, grooves, wattas, rounding of corners
etc. all complete as per architectural drawing, specification and directed by EIC, at all lift, lead and depth, doing independent double legged scaffolding,
making gypsum plaster mix as per approved EIC, providing and fixing 20 gauge GI chicken mesh 150 mm wide to junctions of concrete and masonry,
hacking closely concrete surfaces, apply chemical adhesive coating on concrete surfaces and apply scratch coat plaster etc. complete as approved by
EIC. Plastering shall be to correct line, levels and plumb including curing, cleaning etc. complete to entire satisfaction of EIC.
(To Internal surfaces)

Providing and laying 6-8mm thick single-coat plaster in ceiling at all heights in CM 1:3 in proper line and level including surface preparation, curing,
erection and removal of scaffolding etc. complete as per drawing, specifications and as directed by EIC.
Providing and laying 20mm thick sand faced waterproof plaster at all heights in two coats with base coat of 12mm thickness in CM 1:4 mixed with
Accoproof waterproofing compound (@ 2% of weight of cement of base coat) or approved equivalent and finish coat of 8mm thickness in CM 1:3
including drip mould, normal groove, curing, cost of necessary scaffolding etc complete as per drawing, specifications and as directed by EIC.

Providing and Applying two or more coats of birla white or equivalent cement based putty of approved make at all heights. Items including cost of
scaffolding, curing etc. complete as per drawing, specification and directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 45 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing & Fixing 300mm wide GI chicken wire mesh of 5mmx5mm mesh and 20 gauge thickness (weight @ 0.25Kg/ Sqmt) at junctions of concrete
and masonry surface prior to plastering and including cost of consumables etc. complete as directed by EIC.

Making of 8MM X 8 MM groove in plaster at all heights


Providing and fixing 3mm thick 100mm wide Aluminium Plate covering over expansion joint including fastening with screw on one side on floor or wall,
consumables etc complete as per drawing, specification and as directed by EIC.
and Insulation

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 46 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing cementitous polymer based waterproofing treatment to terrace of RCC slab including brick bat coba. Job consists of cleaning the RCC slab
using wire brush, chisels to make it perfectly clean. Grouting slab by fixing 20 mm dia. GI nipple at construction joint of RCC slab / any weak spot ( if
observed ) then pumping cement slury into it. Opening up any cracks in V shape & filling the same with polymer modified mortar. Providing and laying
two coats of highly flexible two components of polymer based waterproofing treatment having a coverage of 3.0 kg per sqm. or as per manufacturer's
specs over terrace. Brick bat shall then be laid in required slope to drain water for any span after cleaning and applying a coat of cement slurry
admixed with approved water proofing compound and laying brick bats in bottom layer in CM 1:5 admixed with approved waterproofing compound ,
applying cement slurry over this layer , jointing of brickbats with C.M 1 :3 admixed with approved water proofing compound and finally top finishing
average 20 mm thick layer of same mortar and providing 300 x 300 mm lining / making it rough to receive any further treatment all complete as
specified and directed. No separate treatment for bundwalls / junction of parapet wall & slab. All Material required for the job like brick bats, polymer,
sand, and any other consumables shall be arranged by contractor. Average thickness of brickbat coba water proofing is 150 mm and minimum
thickness is 50 mm.he contractor shall give ten years guarantee against all defects All above operations to be done in order and as directed and
specified by the Engineer-in-Charge.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 47 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing & Laying membrane type waterproofing treatment using Moply Mineral Finish APP Modified Membrane - 4Kg/Sqm of Texsa or equivalent
make. Job includes removal of loose particles and dust by wire brush over a pre sloped surface, Priming by providing & applying bituminous adhesive
Tikitar or equivalent product (0.3 Ltr/Sqm), providing & applying APP modified membrane Moply - Mineral Finish - 4Kg/Sqm, 3.3mm thickness of Texsa
or equivalent make by using Torch Method. The overlap for membrane shall be minimum on length side - 75mm, width side - 100mm. For termination
at edge & parapet / drop down - up to 200mm extended towards outer side of parapet including cost of all materials, manpower, consumables, tools &
tackles etc. all complete as per drawings, specifications, application methodology & as per direction of EIC. Measurement shall be considered for
actual laid area. Contractor shall carry out 1st Pond Test on completion of work and 2nd Pond Test prior to start of next monsoon as per instruction of
EIC. Contractor will provide 5-year maintenance guarantee against any defects.

Providing and laying in-situ M15 Grade (1:2:4) with 12mm down aggregates floor Screed 25mm thick laid to proper level and slope in alternate bays
floated neat with cement and providing 300 x 300 mm grid and 8mm deep lining all complete including compaction, filling joints as per specifications
and as directed by engineer in charge.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 48 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and applying cellular light weight concrete (pumpable) ( Minimum thickness 100 mm , Maximum thickness : 180 mm ,average 140 mm thk)
of approved density of type 2 as per IS 6598 to be placed in situ over the surface of RCC slab / Brick bat coba and laid in a slope of 1:120 & cured at
ambient temperature and pressure by water etc.complete at all heights and locations.
Material shall be of grade A as per IS of density apprx.320 kg / M3. Crushing strength of dry cellular concrete shal be 0.25 MPa when tested in
accordance to IS 5688. The thickness of cellular concrete shall be min 100 mm and max to achieve a thermal conductivity ( at 50 Degree C) of 0.07
W/M Deg C per Sqm.
Finished product shall for perform for the ambient temperature of range 10 deg C to 60 Deg C. Finish of top surface shall be made ready to receive the
protective screed layer ( not covered under this item for measurment and payment) Detail product specification and application procedure shall be as
per RI-ID- MHMUMB001-C-SP-210 enclosed for ready reference.
All material, machinery and consumables required for the job except cement is in the scope of contractor.The treatment shall include making vata at
the junction of floor and wall as per standard specification for which no extra payment shall be made. Rate of shall include vata making.

Providing & laying China mosaic flooring for fast drainage of rainwater on the terrace with proper ridge & valley arrangement including thorough
cleaning of the area of work, laying of cement slurry, laying bedding mortar with mix of Cement mortar (1:4) mixed with @ 200 gms of waterproofing
compound ""Pidiproof LW or equivalent"" per bag of cement & @25 Kg of neeru per bag of cement, sprikling evenly powdered cement over wet
bedding for a thickness of 5-6 mm, laying tile chips of mix colour and material, about 4 to 5 mm thk, washing with water jet and ramming with wooden
mallet for perfect adhesion with the bedding without any hollow spots beneath and the required slope & pattern, Cleaning with saw dust to get a clean
surface. complete as per drawing, specification and as directed by EIC.
China mosaic treatment is to be turned around at the interface of the parapet wall for height of minimum 12 inches with proper coving at the junction.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 49 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Curing shall be carried out after 24 hours of floor laying and shall be done by method of ponding with minimum depth of 75 mm water column and shall
be cured for minimum 10 days period. After curing period is over water to be drained out and tiles shall be cleaned with diluted HCL acid to get a
sparkling china mosaic surface. If any air holes are observed at the joints or some chips
are displaced, local repairs shall be done. Parapet/Bund walls on the periphery of the terrace slab shall be provided with the W/p plastering with drip
mould at the junction of the china mosaic (Water proof plaster shall be measured under seperate item)
China mosaic flooring shall be directly provided on screeding
All material required for the job is in the scope of contractor.
(e) The whole terrace so finished shall be flooded with water for a minimum period of two weeks for curing and for final test. The rate shall also include
curing and testing by water ponding for water tightness as required by EIC.The contractor shall give ten years guarantee against all defects All above
operations to be done in order and as directed and specified by the Engineer-in-Charge.

Providing and laying cementitous based polymer waterproofing treatment on roofs , toilets including protective cement mortar / concrete screed layer
.Job includes surface preparation consisting of cleaning the RCC slab using wire brush, chisels to make it perfectly clean, Grouting slab by fixing 20
mm dia. GI nipple at construction joint of RCC slab / any weak spot ( if observed ) and then pumping cement slury into it, Opening up any cracks in V
shape & filling the same with polymer modified mortar and than applying one coat of primer (if specified by Manufactuerer) and applying two coats of
highly flexible two components of polymer based waterproofing treatment as per manufacturer's specification for all heights and locations . Coverage
of primer and Polymer coating including Thickness of polymer shall be as per manufarturer's specifications . After 24 hrs of drying waterproof coating is
to be protected with 25 to 30 mm thick cement mortar screed using cement , sand and 6 mm stone aggregate to protect polymer coating. All Material
required for the job like polymer, sand,
and any other consumables shall be arranged by contractor. The contractor shall give ten years guarantee against all defects for the waterproofing
work done.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 50 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and filling Brickbat in 1:6 cement mortar for sunken portion of Toilet with all material at all location and heights. The item includes:
* 20mm thick bottom screed in CM 1:5
* Filling brick bats in CM 1:3 in a layers of 200 mm thick
* 20mm thick screed in CM 1:5 on top of each brickbat layer
All above operations to be done in order and as directed and specified by the Engineer-in-Charge.
Waterproofing in Server Halls :- Providing waterproofing treatment in Server Halls below False Flooring under Precission Air Conditioners having slope
1:200 with minimum thickness of 25mm (a)Providing and laying cementitous based polymer waterproofing treatment on,
including protective cement mortar / concrete screed layer .Job includes surface preparation consisting of cleaning the RCC slab using wire brush,
chisels to make it perfectly clean , Grouting slab by fixing 20 mm dia. GI nipple at construction joint of RCC slab / any weak spot ( if observed ) and
then pumping cement slury into it, Opening up any cracks in V shape & filling the same with polymer modified mortar and than applying one coat of
primer and applying two coats of highly flexible two components of polymer based waterproofing treatment as per manufacturer's specification for all
heights and locations .
Coverage of primer and Polymer coating including Thickness of polymer shall be as per manufarturer's specifications .
(b) Finishing the surface with 20 mm thick jointless cement mortar of mix 1:3 (1 cement :3 coarse sand) admixed with proprietary water proofing
compound conforming to IS : 2645 and finally finishing the surface with trowel with neat cement slurry including treating vertical surface of walls for
rounding at corners etc.
(c) All above operations to be done in order and as directed and specified by the Engineer-in-Charge.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 51 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Supplying and fixing of Leaf trap with khurra made out of UPVC with flange and grating for rainwater outlets on terrace including all necessary
grounting with sealants to make it absolutely water proof.
110 mm

Supplying and fixing of Leaf trap with khurra made out of UPVC with flange and grating for rainwater outlets on terrace including all necessary
grounting with sealants to make it absolutely water proof.
160 mm

and cladding
Supply and fixing 0.55mm thick precoated Galvalume sheets of approved quality and shade in roof and cladding including supply and fixing of
approved quality translucent FRP sheets for skylights, polycoated GI J-bolts/ L-bolts/ SDST screws, polymer washers, cost of drilling, cutting, all tools
and tackles, scaffolding etc. complete as per drawings, specifications and as directed by EIC.
Note: Net area of roof/ cladding will be measured for payment.

Supply and fixing 0.55mm precoated Galvalume sheets of approved quality and shade in ridge/ gutter/ flashing/ corner pieces etc including supply and
fixing of approved quality translucent FRP sheets for skylights, polycoated GI J-bolts/ L-bolts/ SDST screws, polymer washers, cost of drilling, cutting,
all tools and tackles, scaffolding etc. complete as per drawings, specifications and as directed by EIC.
Note: Net plan area will be measured for payment.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 52 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
For Ridge

For falsing upto 600mm

For falsing upto 600-1000mm

For Gutter 330 W X 600 D

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 53 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and applying 3 coats whitewash on walls at all heights including scafffolding as directed by EIC.
Providing & Applying 2-Coat of Premium Plastic Emulsion of Asian paint (Or any other approved manufacturer) of approved shade & colour on wall
Including surface preparation consisting of cleaning the surface to be painted using brush and sand the surface using emery paper 180 to remove all
the loose particles, apply a coat of Asian Paints Decoprime Primer (Water/solvent thinner), allow to dry for 6 to 8 Hours, smoothen the surface with 2
coats of wall Putty, allow drying for 4 to 6 Hours, sand the surface with emery paper 180 and apply another coat of Asian paints Decoprime Primer
and allow it to dry for 6 to 8 Hours. Top Coat application: Apply one coat of Asian paint Premium Plastic Emulsion Paint brush followed by Roller. Allow
drying for 3 to 4 hours and apply another coat of Premium Plastic emulsion all complete as per drawing and as directed by Engineer in Charge.
including cost of scaffolding etc. complete as per drawings, specifications and as directed by EIC.
Note: Application of acrylic emulsion paint by brush or roller.
Application gap of 8 hours is to be observed between two coats of acrylic emulsion paint and approved at every stage of painting by EIC.

Supply and application of one coat of primer and 2 coats of external acrylic decorative and protective emulsion paint of approved or equivalent of
approved shade, including surface preparation,curing, minor putty work, scaffolding etc. complete as per drawings, specifications and as directed by
EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 54 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and applying 2 coats of anti carbonation paint approved
equivalent make of approved colour and shade at all heights to
internal/external surfaces including erection & removal of scaffolding, surface preparation, providing and applying 1 coat of primer of dulux or
approved equivalent make including erection & removal of staging or scaffolding, etc. complete as per detailed drawing, manufacturer's specification
and as directed by EIC.

Providing and laying 18-20mm thick granite in flooring laid over 20-30 mm thick 1:4 cement mortar, including cost of stone cutting, filling joints with
matching colour pigments, mirror polishing etc. complete as directed by EIC. Landed Rate of Granite @ Rs. 175/- per SQFT including VAT

Providing and laying Vitrified Tiles 600mmx600mm of approved quality & shade in flooring including cost of tile cutting, 25mm - 30mm bedding in CM
1:4, filling the joints in matching colour pigments etc. complete as per drawing, specifications and as directed by EIC. Landed rate of tiles @
Rs.70/SQFT including vaT.
Providing and laying non-skid Vitrified Tiles 600mmx600mm of approved quality & shade in flooring of pantry, toilet, store, passage etc including cost of
tile cutting, 25mm - 30mm bedding in CM 1:4, filling the joints in matching colour pigments etc. complete as per drawing, specifications and as directed
by EIC. Landed rate of tiles @ Rs.45/-per SQFT including vAT

Providing and laying 40mm thick M-15 Grade IPS Flooring to proper line, level and slope in alternate bays and including cost of channels for side
shuttering, vibration, compaction, pond curing, smooth finishing, string marking if any as required etc. complete as per drawing, specifications and as
directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 55 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing & laying 50 mm thick I.P.S. flooring in cement concrete of proportion M15 laid in bays as per I.S.I. Specification including providing & fixing
4mm thick glass strip if required for paneling with all tools and tackles, PPE's as per the instruction of EIC.

Providing and Laying M20 Grade 75mm thick screed to proper line, level and slope in alternate bays and including vibration, compaction, pond curing,
side shuttering, smooth finishing, cutting of grooves or string marking if any etc. complete as per drawing, specifications and as directed by EIC

Providing and laying 28-32mm thick machine cut machine polished kota stone of reqired size in flooring laid over 20-30 mm thick 1:4 cement mortar,
including cost of stone cutting, filling joints with matching colour pigments, mirror polishing etc. complete as directed by EIC.

Supply and application of self leveling Epoxy flooring consisting of primer coat and floor topping forming total thickness of 2 mm of Sika, Ciba Geigy,
Pidilite or approved equivalent make on existing IPS flooring at all elevations & locations , including minor repairing work as required, filling dents,
holes, undulations etc. with epoxy repair mortar, surface preparation etc. complete as per manufacturer's specifications and as directed by EIC.

Providing and laying RMC/ weigh-batched machine-mixed M-15 grade plain cement concrete in floor screed of average thickness 40mm at all levels to
proper line, level and slope and including cost of side shuttering if any, finishing, pond curing etc. complete as per drawings, specifications and as
directed by EIC.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 56 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
P & L 12mm thick Acid / Alkali Resistant Tiles of size size 300 mm x 300 mm x12 mm thick using furacin cement confirming to IS 4457 Class 1 over
the concrete surface, complete as per specification, drawings and as directed by the EIC

Providing and laying of Composite marble (Artificial / Engineered) approx. 20 mm thick of approved quality, type and colour for flooring at various
location, including cutting to the required sizes, shapes & pattern as per the architectural drawings and laying to the required level / slope including all
surface preparation, laying cement mortar (1:4) bed of average thickness 25mm with cement slurry / paste spread on the top of mortar using cement
of standard specification, cleaning joints of tiles and grouting them in Temax. Sides to be cleaned with polish paper to smoothen the tiles before laying.
A thin layer of white cement to be applied over base of cement morter before placing of marble slab. Flooring is in combination of - TIBERIO (max.
size 2400 x 1200 mm) and ARCADIO (max. size 1800 x 1200 mm) of Kalingastone series of Classic Marble Company of approved variety & lot, all
complete including Polishing of Composite marble. contratctor shall follow below menioned procedure for Polishing of composite marble:- 1.Cleaning
of the Marble using required chemicals and pads. 2.Vacuuming dirty water & slurry. 3.Cutting of Marble using 800 grit diamond pads 4.Vacuuming of
dirty water & slurry. 5.Cutting of Marble using 1500 grit diamond pads 6.Vacuuming of dirty water & slurry 7. Cutting of Marble using 3000 grit diamond
pads. 8. Polishing of Marble using required buffing pads 9. Buffing tp Glossy finishes aas directed by Engineer in Charge. landed rate of stone Rs.250
per sft including VAT

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 57 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and Fixing Artifical Marble ARCADIO of Kalingastone series of classic marble company or any other approved make for Skirting 12 mm thick
of Height 600 mm of approved quality, type & colour as per the approved sample including cutting to the required sizes, shapes & pattern as per the
architectural drawings including all surface preparation like chipping of Plaster / masonary, providing & laying cement mortar (1:3) bed of average
thickness 12 to 15 mm, tile to be fixed with white cement slurry / paste as per standard specification, cleaning joints and grouting them cement paste
with pigmented additives to match shade of the stone, Mirror Polishing etc. The rate also includes curing, cleaning etc complete as directed by
Engineer in Charge.

Providing and laying 18-20mm thick granite in skirting of height upto 100mm flushed with plaster including cost of stone cutting, cutting of masonry/
RCC, cement mortar of 1:4 of 12-15mm thk, filling the joints with matching colour pigments, mirror polishing, making 6mmx6mm grooves etc. complete
as per specification and as directed by EIC. Landed Rate of Granite @ Rs. 175/- per SQFT. including VAT

Providing and laying kota stone in skirting of height upto 100mm flushed with plaster including cost of stone cutting, cutting of masonry/ RCC, cement
mortar of 1:4, filling the joints with matching colour pigments, mirror polishing, making 6mmx6mm grooves etc. complete as per specification and as
directed by EIC.
?

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 58 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and laying 100 mm high skirting of vitrified tiles including cutting of tiles & masonry work, making grooves( if required) , tiles are to be laid for
cement mortar bedding 12-15mm of 1:4, filling joints with matching pigments etc. complete as directed by the engineer-in-charge. Landed cost Rs.70/including VAT

P&L Kota Stone Skirting: Providing and fixing Kota stone 18 to 20 mm thick for Skirting of Height 300 mm of approved quality, type & colour as per
the approved sample including cutting to the required sizes, shapes & pattern as per the architectural drawings and to be fixed on cement board with
epoxy based adhesive surface preparation, cleaning joints, grouting the joints with cement paste with pigmented additives to match shade of the stone,
Mirror Polishing etc.completed as directed by engineer in charge. The Flooring joint to match that of flooring.

P&L Kota Stone Skirting: Providing and fixing Kota stone 18 to 20 mm thick for Skirting of Height 300 mm of approved quality, type & colour as per
the approved sample including cutting to the required sizes, shapes & pattern as per the architectural drawings including all surface preparation like
chipping of Plaster / masonary, providing & laying cement mortar (1:4) bed of average thickness 12 to 15 mm, tile to be fixed with cement slurry / paste
as per standard specification, cleaning joints and grouting them cement paste with pigmented additives to match shade of the stone, Mirror Polishing
etc completed as directed by engineer in charge. The Flooring joint to match that of flooring.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 59 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and laying kota stone in trapezoidal skirting 100mm/250mm high on staircase flushed with plaster including cutting of stone, cutting of
masonry/ RCC, cement mortar 1:4 with cement mortar bedding of 12-15mm thk, filling joints with matching color pigments, mirror polishing etc.
complete as directed by EIC.

Providing and laying Vitrified Tiles of approved quality & shade in dado with 1:4 cement mortar including cost of tile cutting, filling the joints in matching
colour pigments etc. complete as per drawing and as directed by EIC. Landed rate of tiles @ Rs. 70/SQFT including VAT.
Thickness

Providing and laying Glazed Tiles of approved quality & shade in dado with 1:4 cement mortar including cost of tile cutting, filling the joints in matching
colour pigments etc. complete as per drawing and as directed by EIC. Landed rate of tiles @ Rs. 45/SQFT including VAT.

Providing and fixing in staircase tread 300mm wide 18-20mm thick flame finished Granite Stone of approved quality and shade including 20-30mm
thick bedding in CM 1:4, filling the joints with matching colour pigments, full round moulding, polishing, providing 3 nos. of 4mm wide non-slip grooves
at the nosing end etc. complete as per drawings, specifications and as directed by EIC.
Landed rate of granite@ Rs.175/Sqft including VAT.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 60 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Providing and fixing in staircase riser 150mm high 18-20mm thick
pre-polished Granite of approved quality and shade including 10-12mm thick 1:3 Cement Mortar, filling the joints with matching colour pigments,
polishing etc. complete as per drawings, specifications and as directed by EIC.
Landed cost of granite @ Rs. 175/Sqft including VAT.
Providing and laying 300 mm wide kota stone in stair case treads including 20-30mm bedding in 1:5 cement mortar, filling joints with matching colour
pigments, full round nosing, 3 nos. of 3mm non-slip grooves, mirror polishing etc. complete as per drawing, specifications and as directed by EIC.

Providing and laying kota stone in stair case riser of height up to


150mm including 20-30mm bedding in 1:5 cement mortar, filling joints with matching colour pigments, mirror polishing etc. complete as per drawing,
specifications and as directed by EIC.
Providing and laying 18-20mm thick granite in pantry platform laid over base made of Kadapa Stone with adhesive of approved make, including granite
verticals, making cutout for sink, edge chamfering, mirror polishing, filling joints with matching colour pigments etc. complete as per drawing,
spcifications and as directed by EIC. Landed Rate of Granite @ Rs. 175/- per SQFT including VAT.
Providing and Laying 12 mm thick machine cut mirror polished artifical marble stone cladding - BANCO Venus of Kalingastone series of classic marble
company or approved make ( wall lining ) with "V" groove joint with epoxy based adhesive of approved quality ,type and colour as per the approved
sample including cutting to the required size,shape and pattern as per the architect's drawings and cladding the same in plumb.The item includes
surface preparation,fixing the marble with epoxy based adhesive including cutting of slab wherever required, curring, cleaning, polishing etc. complete
as directed by EIC. Landed cost is Rs.200/- including vAT

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 61 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Lift Archatrive:- Providing & fixing 20mm thk PORTORO of Kalingastone series of Classic Marble Company or of approved variety & lot for Lift
Archatrive ( Jambs, Soffit and Sill) with epoxy based addhesive over 12 mm thick bed of cement mortar 1:3 (1 cement : 3 coarse sand), with cement
slurry / paste spread over using to proper level and a true plumb including rubbing all complete as per drawing and as directed by Engineer in
Charge. Landed cost is Rs.250/- including vAT
STEEL
Supply, fabrication, painting and erection of light weight structures(sections wt. <= 25 Kg/m), plates <= 10mm thick including (i) Supply of structural
steel as per Indian Standard. (ii) Fabrication: Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting of joints
and completing the work as per drawings, specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for fabrication shall
be carried out. Trial assembly if required shall be in contractor's scope. Provision of all type to staff and workmen, provision of all required lifting toolstackles including P&M, all type of welding & cutting consumables and gases are in contractor's scope. (iii) Painting: including blasting of steel with grits
& shots to SA 2.5 with approved make of one coat of inorganic zincsilicate primer after Sand Blasting/Shot Basting, DFT (Microns): 75, one coat of
High Build MIO Epoxy Intermediate DFT (Microns): 125 , final coat of Aliphatic Urethane Finish DFT (Microns): 75 using airless spray gun as per
specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/ modules at all heights including tools,tackles,P&M, fixing &
removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary staging, bolting to required torque, touch
up painting, completing the work in all respect as per drawings, specifications and codes as per the instructions of EIC and fulfilling owner's safety
norms & practices at work site including NDT as per requirement & specification.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 62 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job
Supply, fabrication, painting and erection of medium weight structures (sections wt. 25 < >=75 kg/m), plates 10 < >= 20mm thick including (i) Supply of
structural steel as per Indian Standard. (ii) Fabrication: Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting
of joints and completing the work as per drawings, specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for
fabrication shall be carried out. Trial assembly if required shall be in contractor's scope. Provision of all type to staff and workmen, provision of all
required lifting tools-tackles including P&M, all type of welding and cutting consumables and gases are in contractor's scope. (iii) Painting: Painting:
including blasting of steel with grits & shots to SA 2.5 with approved make of one coat of inorganic zincsilicate primer after Sand Blasting/Shot Basting,
DFT (Microns): 75, one coat of High Build MIO Epoxy Intermediate DFT (Microns): 125 , final coat of Aliphatic Urethane Finish DFT (Microns): 75 using
airless spray gun as per specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/ modules at all heights including
tools,tackles,P&M, fixing & removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary staging,
bolting to required torque, touch up painting, completing the work in all respect as per drawings, specifications and codes as per the instructions of EIC
and fulfilling owner's safety norms & practices at work site including NDT as per requirement & specification.

Supply, fabrication, painting and erection of heavy weight structures (sections wt. 75 < >=150 kg/m), plates 20 < >= 50mm thick including (i) Supply of
structural steel as per Indian Standard. (ii) Fabrication: Straightening (if required), cutting to required size, grinding, drilling of holes, welding or bolting
of joints and completing the work as per drawings, specifications, relevant codes and directions of the EIC. Minor detailing/ layout if required for
fabrication shall be carried out. Trial assembly if required shall be in contractor's scope. Provision of all type to staff and workmen, provision of all
required lifting tools-tackles including P&M, all type of welding and cutting consumables and gases are in contractor's scope. (iii) Painting: Painting:
including blasting of steel with grits & shots to SA 2.5 with approved make of one coat of inorganic zincsilicate primer after Sand Blasting/Shot Basting,
DFT (Microns): 75, one coat of High Build MIO Epoxy Intermediate DFT (Microns): 125 , final coat of Aliphatic Urethane Finish DFT (Microns): 75 using
airless spray gun as per specification & directed by EIC. (iv) Erection: includes of all structural steel/ panels/ modules at all heights including
tools,tackles,& P&M, fixing & removal of safety net, cutting, trimming, drilling, grinding, fit up, welding, alignment & levelling with temporary staging,
bolting to required torque, touch up painting, completing the work in all respect as per drawings, specifications and codes as per the instructions of EIC
and fulfilling owner's safety norms & practices at work site including NDT as per requirement & specification.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 63 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Description of Job

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 64 of 557

SCHEDULE OF QUANTITY / RATE

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
3750
6800
2640
1100 21090

UOM

IDC

CUM

6800

CUM

1360

750

1360

525

220

4215

CUKM 5440

3000

5440

2115

880

16875

CUM

3250

4300

2370

810

16430

5700

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 65 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2700
5825
1710
1342 14827 (Rs.)

UOM

IDC

SQM

3250

SQM

1600

1800

3890

1645

3565

12500

SQM

1550

900

1945

570

2375

7340

SQM

1200

SQM

1200

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 66 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
60
188
35
32
415 (Rs.)

UOM

IDC

MT

100

MT

190

40

130

30

60

450

MT

180

20

65

10

51

326

MT

132

Reliance Engineering Group

132

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 67 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
50
300
115
64
729 (Rs.)

UOM

IDC

CUM

200

CUM

100

10

10

130

CUM

250

50

60

10

10

380

CUM

1100

500

2500

270

291

4661

CUM

50

370

850

275

1550

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 68 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
430
640
175
430
2935 (Rs.)

UOM

IDC

CUM

1260

CUM

1260

CUM

1285

Nos.

100

20

50

50

20

240

Nos.

100

20

50

50

20

240

145

215

60

290

1970

1285

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 69 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
3
8
3
2
40
(Rs.)

UOM

IDC

MT

24

SQM

SQM

SQM

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 70 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2100
2200
1100
10
9810 (Rs.)

UOM

IDC

SQM

4400

SQM

100

175

196

65

SQM

4400

2100

3300

85

45

9930

CUM

10

10

10

10

10

50

CUM

10

10

10

10

10

50

RM

50

10

20

86

Reliance Engineering Group

536

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 71 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
5
5
5
5
30
(Rs.)

UOM

IDC

EA

10

EA

10

30

MT

EA

CUM

CUM

CUM

10

15

10

20

10

65

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 72 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
85
110
30
5
240 (Rs.)

UOM

IDC

CUM

10

SQM

Nos.

10

30

Nos.

10

30

Nos.

Nos.

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 73 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

Nos.

Nos.

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
1
1
1
1
5
(Rs.)

Sqm

20

15

20

55

RM

10

10

35

55

RM

RM

420

647

FR-ZR-5017 Rev. 00 Sheet 3 of 3

200

Reliance Engineering Group

232

48

420

97 1224

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 74 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
3000 (Rs.)

CUM

2100

530

SQM

50

50

CUM

800

Reliance Engineering Group

450

90

3170

100

800

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 75 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

CUM

400

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
515 (Rs.)
50

65

60
SQM

60

26450
SQM 20000

4020

Reliance Engineering Group

1980

450

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 76 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

100

SQM 10000

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
200 (Rs.)

100

2525

656

13181
15265

SQM

8200

3770

2040

1255

26450
SQM 20000

4020

Reliance Engineering Group

1980

450

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 77 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

RMT

1000

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2250 (Rs.)
700

300

250
10000

RMT

7500

1500

1000
50

RMT

50

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 78 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

4200

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
4200 (Rs.)

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 79 of 557

SCHEDULE OF QUANTITY / RATE

UOM

SQM

IDC

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
2170 (Rs.)

1420

750

2170
SQM

1420

Reliance Engineering Group

750

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 80 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

4000

SQM

4200

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

1420

Reliance Engineering Group

750

6170

6170
SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 81 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

4200

SQM

225

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
6170

100

Reliance Engineering Group

325

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 82 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

CUM

200

SQM

2000

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
26

Reliance Engineering Group

226

2000

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 83 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

UOM

IDC

EA

EA

20

12

40

SQM

1770

1770

RMT

300

300

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 84 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

RMT

100

100

RMT

200

200

RMT

200

200

RMT

200

200

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 85 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

1200

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
300
150
1650 (Rs.)

SQM 20200

6440

1980

685

29305

SQM

3760

2040

1255

15255

8200

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 86 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

UOM

IDC

SQM

1800

SQM

520

SQM

1500

120

1620

SQM

150

70

220

SQM

5250

1200

850

3850

520

Reliance Engineering Group

200

5450

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 87 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

SQM

1400

1400

SQM

300

750

100

1150

SQM

700

140

75

915

SQM

7000

750

500

8250

SQM

1000

440

50

1490

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 88 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

100

SQM

375

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
100

Reliance Engineering Group

50

250

375

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 89 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

UOM

IDC

RMT

50

50

RMT

200

200

RMT

1720

160

Reliance Engineering Group

140

70

2090

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 90 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

UOM

IDC

RMT

900

RMT

925

925

RMT

750

750

50

Reliance Engineering Group

950

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 91 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

RMT

50

SQM

150

SQM

45

RMT

420

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

60

25

35

170

150

40

Reliance Engineering Group

85

420

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 92 of 557

SCHEDULE OF QUANTITY / RATE

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

UOM

IDC

RMT

420

RMT

80

250

15

40

385

RMT

80

250

18

40

388

SQM

15

15

SQM

1900

1900

420

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 93 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

SQM

200

MT

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)
200

245

Reliance Engineering Group

106

351

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 94 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

MT

87

38

125

MT

105

45

150

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 95 of 557

SCHEDULE OF QUANTITY / RATE

UOM

IDC

FR-ZR-5017 Rev. 00 Sheet 3 of 3

Quantity
Total Rate Amoun
Chiller
DG Substati Cooling Quanti
t
House House
on
Tower
ty
(Rs.)
(Rs.)

Reliance Engineering Group

SA
10069-SOQ-NA2CF-001

Date: 08-04-2015

Rev. 1
Sheet 96 of 557

SI no.

Description

UOM

Rate

1
1.1
1.2
1.3
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.1
2.11

Labour Rates
Skilled labour
Semi Skilled labour
Unskilled labour
Material Rates

M-day
M-day
M-day

348
316
288

Cement
Sand
Aggregates 10mm,20mm, 40mm
Reinforcement bars
Boulder 9"
Murrom
Good earth
Structural steel
Ply wood 9 mm THK
Hard Wood
Wire Nails

EA
Cum
Cum
MT
cum
CUM
Cum
MT
Sq m
Cft
Kg

350
3500
750
36000
500
250
300
40000
700

Sl no.

Description

1
3
4
5
6

USL excavation
Supervisor
Sub Total
Contractor's OH & P
Sub Total

Sl no.

Description

USL excavation

Excavation in SOIL
Measurements
Unit
Nos
L
B
H
manday
0.5 ( I USL can excavate 2 m3 /day )
manday
0.05
( 1 supervisor per 10 USL )

Qty

Rate

0.5
0.05

288

0
per m3
Excavation in SOFT ROCK
Measurements
Unit
Qty
Nos
L
B
H
manday 1.33333
( I USL can excavate 0.75 m3 /day1.333333333
)

Rate
288

3
4
5
6

Supervisor
Sub Total
Contractor's OH & P
Sub Total

Sl no.

Description

1
3
4
5
6

USL excavation
Supervisor
Sub Total
Contractor's OH & P
Sub Total

Sl no.
1
2
3
4
5

Description

manday 0.13333

( 1 supervisor per 10 USL )

0.133333333
0

per m3
Excavation in HARD ROCK
Measurements
Unit
Nos
L
B
H
manday
2 ( I USL can excavate 0.5 m3 /day )
manday
0.2
( 1 supervisor per 10 USL )

Qty

Rate

2
0.2

288

0
per m3

Disposal of excaved earth


Measurements
Unit
Nos
L
B

Shifting of Surplus earth from the


premises (Transport) upto lead of 3km
Shifting of Surplus earth from the
premises (Transport) upto lead of
beyond 3km
Sub Total
Contractor's OH & P
Sub Total
per m3

Sl no.

Description

Unit

1
1.1
1.2

Material
Good Earth
Murram

m3
m3

Qty

Rate
?
?

15%

Backfilling
Measurements
Nos
L
B

Qty

Rate
300
250

2
3
4
5
6
7

Unskilled labour
Supervisor
water charges for consolidation
Sub Total
Contractor's OH & P
Sub Total

Sl no.

Description

1
1.1
1.2
1.3
2
3
4
4.1
4.2
5
6
7
8
8.1
8.2
8.3
8.4
9
10
11

Material per sq ft
Ply 9-12 mm thk
Hard wood
Wire nails
Sub total
Wastage
Manpower
Carpenter
Helper
Sub Total cost per sq m
Nos of repetitions
Cost per repetition
Cost of fixing
Carpenter
Helper
Wire nails
Shuttering oil
Sub Total
Contractor's OH & P
Total

manday
manday

0.07 ( I USL can backfill 15 m3 /day )


0.007
( 1 supervisor per 10 USL )

0.07
0.007

288

0
per m3
Form Work (below FGL)
Measurements
Unit
Nos
L
B
Sq m
Cuft
kg

1
2
0.25

Qty

Rate

1
2
0.25

700

2%
man days
man days

0.07
0.13

( 1 carpenter + 2 helper can


make 15 m2 of board )

0.07
0.13

348
288

man days
man days
kg
LS

0.1
0.2
0.25

( 1 carpenter + 2 helper can


fix 10 m2 of board )

0.1
0.2
0.25

348
288

15%

Form Work (FGL to 10m)

Sl no.

Description

Unit

1
2

Basic Cost(upto FGL)


Scaffolding
Lifting Cost
Sub Total
Contractor's OH & P
Total

LS
LS

9
10
11

Sl no.

Description

1
2

Basic Cost(upto FGL)


Scaffolding
Lifting Cost
Sub Total
Contractor's OH & P
Total

9
10
11

Sl no.

Description

1
2

Basic Cost(upto FGL)


Scaffolding
Lifting Cost
Sub Total
Contractor's OH & P
Total

9
10
11

Sl no.

Description

Nos

Measurements
L
B

Qty

15%

Form Work (10m to 20m)


Measurements
Unit
Nos
L
B
LS
LS

Rate

Qty

Rate

15%

Form Work (Above 20m)


Measurements
Unit
Nos
L
B
LS
LS

Qty

Rate

15%

Form Work (Extra for curve shuttering)


Measurements
Unit
Nos
L
B

Qty

Rate

1
9
10
11

Curve shuttering
Sub Total
Contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11
12
13

Reinforcement
Wastage
Rolling Margin
Realisation of scrap
Sub Total cost of reinforcement
Labour for cutting bending & fixing
Skilled
Unskilled
binding wires
Transportation
Sub Total cost of reinforcement
contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5

Basic Cost (upto FGL )


Lifting Cost
Sub Total cost of reinforcement
contractor's OH & P
Total

1
15%

Reinforcement (Below FGL)


Measurements
Unit
Nos
L
B
t
t
t
t

mandays
mandays
kg

4
8
6

I fitter & 2 helper can carry out


0.25t per manday

Qty

Rate

1
0.03
0.05
-0.02

36000
36000
36000
36000

4
8
6

348
288
40

Reinforcement (FGL to 10m)


Measurements
Unit
Nos
L
B
t

Qty

Rate

Reinforcement (10m to 20m)

Sl no.

Description

Unit

1
2
3
4
5

Basic Cost (upto FGL )


Lifting Cost
Sub Total cost of reinforcement
contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5

Basic Cost (upto FGL )


Lifting Cost
Sub Total cost of reinforcement
contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11
12

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
Unskilled labour
Supervisor
Sub Total
Contractor's OH & Profit
Total Cost of RMC M 10

Nos

Measurements
L
B

Qty

Rate

Reinforcement (Above 20m)


Measurements
Unit
Nos
L
B
t

Qty

Rate

PCC M 10 Grade
Measurements
Unit
Nos
L
B
bag
m3
m3
0.03
0.05
LS
man day
manday

1
0.1

(1 manday per m3 )
supervisor can handle 10
labours in 1 manday

Qty

Rate

4.2
0.52
0.85

350
3500
750

1
0.1

288

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11
12

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
Unskilled labour
Supervisor
Sub Total
Contractor's OH & Profit
Total Cost of PCC M 15

Sl no.

Description

1
1.1
1.2
1.3
2
3
4
5
6
7
8
9

PCC M10
Cement
Sand
Aggregate (coarse)
Plum aggregate (Boulder)
Boulder breaking charge
Sub Total cost of materials
Wastage
Water & Power
Tools & Tackles
Unskilled labour
Supervisor

PCC M 15 Grade
Measurements
Unit
Nos
L
B
bag
m3
m3
0.03
0.05
LS
man day
manday

1
0.1

(1 manday per m3 )
supervisor can handle 10
labours in 1 manday

Qty

Rate

6.2
0.52
0.85

350
3500
750

1
0.1

288

Plum Concrete M10


Measurements
Unit
Nos
L
B
0.8
bag
m3
m3
0.2

3%
5%
LS
man day
manday

Qty

Rate

3.36
0.416
0.68
0.2

350
3500
750
500

0
0
1
0.1

(1 manday per m3 )
supervisor can handle 10
labours in 1 manday

1
0.1

288

10
11
12

Sub Total
Contractor's OH & Profit
Total Cost of RMC M 15

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11
12

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor
Sub Total
Contractor's OH & Profit
Total Cost of M30

Sl no.

Description

1
2
3
4
5
6
7
8
9

Cement
Sand
Aggregate
Sub Total cost of materials
Wastage
Water & Power
Toopls & Tackles
USL
Sueprvisor

RCC M30 Grade


Measurements
Unit
Nos
L
B
bag
m3
m3
0.03
0.05
LS
man day
manday

1
0.1

Qty

Rate
350
3500
750

(1 manday per m3 )
supervisor can handle 10 labours

1
0.1

288

RCC M20 Grade (Upto FGL)


Measurements
Unit
Nos
L
B
bag
m3
m3
0.03
0.05
LS
man day
manday

1
0.1

(1 manday per m3 )

Qty

Rate

8
0.52
0.85

350
3500
750

1
0.1

288

11
12
13

Sub Total
Contractor's OH & Profit
Total Cost of M20

Sl no.

Description

1
2
3
4
5

RCC M20 Basic Cost


Lead & Lifting Cost
Sub Total
Contractor's OH & Profit
Total Cost of M30

Sl no.

Description

1
2
3
4
5

RCC M30 Basic Cost


Lead & Lifting Cost
Sub Total
Contractor's OH & Profit
Total Cost of M30

Sl no.

Description

1
2
3
4
5

RCC M30 Basic Cost


Lead & Lifting Cost
Sub Total
Contractor's OH & Profit
Total Cost of M30

Sl no.

Description

RCC M20 Grade (FGL to 5m)


Measurements
Unit
Nos
L
B

Qty

Rate

RCC M30 Grade (FGL to 10m)


Measurements
Unit
Nos
L
B

Qty

Rate

RCC M30 Grade (10m to 20m)


Measurements
Unit
Nos
L
B

Qty

Rate

RCC M30 Grade (Above 20m)


Measurements
Unit

Qty

Rate

Sl no.

Description

1
2
3
4
5

RCC M30 Basic Cost


Lead & Lifting Cost
Sub Total
Contractor's OH & Profit
Total Cost of M30

Sl no.

Description

1
2
2.1
2.2
2.3
3
4
4.1
4.2
5
6
7

Anchors for site incl taxes


Drilling Hole
Drilling machine
drill bits cost
Labour for drilling hole
Sub Total cost of drilling
Installing anchor fastners
Grouting with Cement mortar
Labour for fixing anchors
Sub Total cost of drilling and fixing
contractor's OH & P
Total

Sl no.

Description

1
2
2.1
2.2
2.3
3

Anchors for site incl taxes


Drilling Hole
Drilling machine
drill bits cost
Labour for drilling hole
Sub Total cost of drilling

Unit

Nos

Qty

Rate

Chemical anchor fasteners


Measurements
Unit
Nos
L
B
each

Qty

Rate

each
each
mandays

mandays
0

Mechanical anchor fasteners


Measurements
Unit
Nos
L
B
each
each
each
mandays

Qty

Rate

4
4.1
4.2
5
6
7

Installing anchor fastners


Grouting with Cement mortar
Labour for fixing anchors
Sub Total cost of drilling and fixing
contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5

Board
Labour
Sub Total
Contractor's OH & Profit
Total Cost of Treatment

Sl no.

Description

1
2
3
4
5

Board
Labour
Sub Total
Contractor's OH & Profit
Total Cost of Treatment

Sl no.

Description

1
2
3
4

Chemical cost
Labour
Sundries and sprayer
Sub Total cost of materials

mandays
0

Shalitex Board (12mm thk)


Measurements
Unit
Nos
L
B
Sqm
1
manday

Qty

Rate

354

Shalitex Board (25mm thk)


Measurements
Unit
Nos
L
B
Sqm
1
manday

Qty

Rate

710

Anti termite treatment


Measurements
Unit
Nos
L
B
Sqft
1
manday
LS

Qty

Rate

5
6
7

Sub Total
Contractor's OH & Profit
Total Cost of Treatment

Sl no.

Description

1
2
3
4
5
6
7

Cement Concrete M15


Unskilled labour
Supervisor
Tools & Tackles
Sub Total
Contractor's OH & Profit
Total Cost of RMC M 15

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11

Rubble
Breaking
Cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total

Sl no.

Plinth Protection (75mm)


Measurements
Unit
Nos
L
B
man day
manday

supervisor can handle 10


labours in 1 manday

Qty

Rate

Rubble Soling (230mm)


Measurements
Unit
Nos
L
B
m3
1.35
m3
1.35
bag
1.8
m3
0.31
0.03
mandays
mandays

0.67
1.33

1 mason & 2 helpers can do


1.5 m3 of RRM per day

Dismantling & Disposal-RCC in Sub-structure (5 km Lead)


Measurements
Description
Unit

Qty

Rate

1.35
1.35
1.8
0.31

500
350
3500

0.67
1.33

348
288
0

Qty

Rate

Sl no.

Description

Unit

1
2
3
4
5
6
7

labour
Supervisor
Transporation
Tools & Tackles
Sub Total
contractor's OH & P
Total

mandays
mandays

Sl no.
1
2
3
4
5
6
7

Nos

Qty

Rate

LS
0

Dismantling & Disposal-RCC in Super-structure (5 km Lead)


Measurements
Description
Unit
Nos
L
B
H
labour
mandays
Supervisor
mandays
Transporation
Tools & Tackles
sub total
contractor's OH & P
Total

Sl no.

Description

Unit

1
2
3
4
5
6
7

Sand
Polysulphide Sealent
USL
Supervisor
sub total
contractor's OH & P
Total

m3
Kg

Isolation Joints
Measurements
Nos
L
B

Qty

Rate

Qty

Rate
3500
400

mandays
0

Pockets

Sl no.

Description

1
2
3
4
5
6

Formwork
USL
Supervisor
sub total
contractor's OH & P
Total

Sl no.

Description

Unit

Description

1
2
3
4

NS Grout
Water & Power
Tools & Tackles
USL

Qty

Rate

mandays
0

Cement Grout (1:2)


Measurements
Unit
Nos
L
B
bag
m3

1
Cement
2
Sand
3
Sub Total cost of materials
4
Wastage
0.03
5
Water & Power
0.05
6
Tools & Tackles
LS
7
USL
man day
8
Sueprvisor
manday
9
Formwork
sqm
10
Sub Total
11
Contractor's OH & Profit
12Total Cost of Mixing & laying Cement Grout

Sl no.

Nos

Measurements
L
B

1
(1 manday per m3 )
0.1 1 supervisor can handle 10 labours

Non Shrink Grout (for 1 m3)


Measurements
Unit
Nos
L
B
H
kg
0.05
LS
man day
1
(1 manday per m3 )

Qty

Rate

13.68
0.95

350
3500

1
0.1
1

288
348
118
0

Qty

Rate

2220

20

288

5
Sueprvisor
manday
6
Formwork
sqm
7
Sub Total
8
Contractor's OH & Profit
9Total Cost of Mixing & laying Cement Grout

Sl no.

Description

1
2
3
4
5

Concrete M15
Formwork
Sub Total
Contractor's OH & Profit
Total

Sl no.

Description

1
2
4
6
7
8

Shalitex Board (12mm)


Polysulphide Sealent
Labour
Sub Total
Contractor's OH & Profit
Total Cost

3
5

Aluminium Sheet 450mm(507mm)


Tools for bending and groove making
Wire nails
labour
sub total
Contractor's OH & Profit
total

0.1 1 supervisor can handle 10 labours

Screed Concrete M15


Measurements
Unit
Nos
L
B
m3
sqm

0.1
1

348
118
0

Qty

Rate

1
1

6079
118
0

Expansion Joints
Measurements
Unit
Nos
L
B
Sqm
1
kg
manday

Qty

Rate
354
400
288
0

kg
LS

180

Sl no.

Description

Unit

1
2
2.1
2.2
2.3
2.4

MS Sheet
Others materials
Horizontal
Vertical
Bracing
Sub Total

kg

3
4
5

Prime Coat
Enamal Paint (2 Coat)
semi Skilled Labour

sqm
sqm

6
7
8
9

Supervisor
Sub Total
Contractor's OH & Profit
Total

manday

Sl no.

Description

1
2
3
4
5
6
7
8
9
10

cost of brick
cement
sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total

Barricading
Measurements
Nos
L
B
1
2.5
2

H
0.00163

m
m
m

Qty

Rate

67.18

40

5
4
3.2
41.0

size of baricade & baricade

40

316

0.1 1 supervisor can handle 10 labours

0.1

348
0

230 mm thick brick work (1:4) per m3


Measurements
Unit
Nos
L
B
nos
bag
1.9
m3
0.26
3%
mandays
mandays

0.67
1.33

1 mason & 2 helpers can do


1.5 m3 of brick work per day

Qty

Rate

496
1.9
0.26

6
350
3500

0.67
1.33

348
288
0

Sl no.

Description

1
2
3
4

cost of brick
cement
sand
sub total
MS Rod
skilled mason
unskilled
sub total
contractor's OH & P
Total

6
7
8
9
10

Sl no.

Description

1
2
3
4
6
7
8
9
10

cost of brick
cement
sand
sub total
skilled mason
unskilled
sub total
contractor's OH & P
Total

Sl no.

Description

1
2

cost of blocks
cement

115 mm thick brick work (1:4) per Sqm


Measurements
Unit
Nos
L
B
nos
bag
m3

mandays
mandays

0.67
1.33

1 mason & 2 helpers can do


1.5 m3 of brick work per day

Qty

Rate

57
0.22
0.03

6
350
3500

6
0.67
1.33

348
288
0

350 mm thick brick work (1:4) per Sqm


Measurements
Unit
Nos
L
B
nos
bag
m3
mandays
mandays

0.67
1.33

1 mason & 2 helpers can do


1.5 m3 of brick work per day

Qty

Rate

174
0.66
0.09

6
350
3500

0.67
1.33

348
288
0

Light weight block masonry (1:4)


Measurements
Unit
Nos
L
B
m3
bag
1.80

Qty
1.00
1.87

Rate
3200
350

3
4
5
6
7
8
9
10

sand
sub total
wastage
skilled mason
unskilled
sub total
contractor's OH & P
Total

m3

0.31

3%
mandays
mandays

0.67
1.33

1 mason & 2 helpers can do


1.5 m3 of brick work per day

0.26

3500

0.67
1.33

348
288
0

12 mm thick plaster 1:4


Measurements
Unit
Nos
L
B

Sl no.

Description

cement

bag

0.090

350

2
3
4
5
6
7
8
9
10
11

sand
sub total
wastage
skilled mason
unskilled
Lead and lifts
Scaffolding
sub total
contractor's OH & P
Total

m3

0.012

3500

Sl no.

Description

1
2
3
4
5

cement
sand
sub total
wastage
skilled mason

3%
mandays
mandays
LS
LS

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

Qty

0.07
0.13

Rate

348
288

6-8 mm thick plaster 1:3


Measurements
Unit
Nos
L
B
bag
m3
3%
mandays

0.07

1 mason & 2 helpers can do


15m2 of brick work per day

Qty
0.075
0.008

0.07

Rate
350
3500

348

6
7
8
9
10
11

unskilled
Lead and lifts
Scaffolding
sub total
contractor's OH & P
Total

Sl no.

Description

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16

cement
sand
sub total
wastage
manpower for 1st coat
skilled mason
unskilled
manpower for 2nd coat
skilled mason
unskilled
sand facing
Lead & Lifts
Scaffolding
sub total
contractor's OH & P
Total

mandays
LS
LS

0.13

1 mason & 2 helpers can do


15m2 of brick work per day

0.13

288

20mm thick plaster sand faced in 2 coats


Measurements
Unit
Nos
L
B
bag
m3

Qty

Rate

0.16
0.02

350
3500

3%
mandays
mandays

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

0.07
0.13

348
288

mandays
mandays
LS
LS
LS

0.07
0.13

1 mason & 2 helpers can do


15m2 of brick work per day

0.07
0.13

348
288

Amount
144
0
144
21.6
165.6

Amount
384

0
384
57.6
441.6

Amount
576
0
576
86.4
662.4

Amount

Amount
0
0

20.16
0
20.16
3.024
23.184

Amount
700
0
0
700
14
23.2
38.4
775.6
10
77.56
34.8
57.6
10
102.4
15.36
117.76

Amount
102.4

102.4
15.36
117.76

Amount
102.4

102.4
15.36
117.76

Amount
102.4

102.4
15.36
117.76

Amount

0
0
0
0

Amount
36000
1080
1800
-720
38160
1392
2304
240
42096
6314
48410

Amount
42096
0
42096
6314
48410

Amount
42096
42096
6314
48410

Amount
42096
42096
6314
48410

Amount
1470
1820
638
3928
118
196
288
0
4530
679
5209

Amount
2170
1820
638
4628
139
231
288
0
5286
793
6079

Amount
1176
1456
510
100
0
3242
97
162
288
0

3789
568
4358

Amount
0
0
0
0
0
0
288
288
43.2
331.2

Amount
2800
1820
634
5254
158
263
288
0

5962
894
6857

Amount
6857
6857
1029
7885

Amount
288
288
43.2
331.2

Amount
288
288
43
331

Amount

Amount
288
288
43
331

Amount

Amount

Amount
354

Amount
710

Amount
6

Amount
6079

Amount
675
0
630
1085
2390
72
232
384
3078
462
3539

Amount

Amount

Amount

Amount

Amount

Amount
4788
3325
8113
243
406
288
35
118

9203
1380
10583

Amount
44400
2220
288

35
118

47061
7059
54120

Amount
6079
118

6196
929
7126

Amount
0
0
0
1221874
79676
610847

180

Amount
2687

1640
0
0
0
35
4362
654
5016

Amount
2,979
655
910
4,544
136
232
384
5,296
794
6,091

Amount
343
75
105
523
232
384
1,139
171
1,309

Amount
1,043
229
319
1,590
232
384
2,206
331
2,537

Amount
3,200
655

910
4,765
143
232
384
5,524
829
6,353

Amount
31
44
75
2
23
38

139
21
160

Amount
26
27
54
2
23

38

117
18
134

Amount
58
71
129
4
23
38
23
38

256
38
294

You might also like