PILING WORKS, MAIN BUILDING WORKS, ANCILLARIES BUILDINGS, EXTERNAL WORKS, MECHANICAL & ELECTRICAL WORKS - STP SDO

CAPACITY 19,950 PE
WBS

Name

DurationStart

SEWAGE TREATMENT PLANT AUSTIN HEIGHT

299 days

Wed 7/9/16

Wed 5/7/17

3%

299 days

Wed 7/9/16

Wed 5/7/17

3%

73 days

Wed 7/9/16

Sun 20/11/16

22%

15 days

Wed 7/9/16

Fri 23/9/16

100%

15 days

Wed 7/9/16

Fri 23/9/16

100%

30 days

Sat 24/9/16

Sun 23/10/16

13%

30 days

Sat 24/9/16

Sun 23/10/16

13%

1.1
1.1.1
1.1.1.1
1.1.1.1.1
1.1.1.2
1.1.1.2.1
1.1.1.3

PROJECT MANAGEMENT
PRELIMINARIES
Contract
Setting Out Boundary
Site Requirement
Access And Egress

%
Schedule

Jul

Sep
E/7

Nov

B/9

M/10

30 days
0%
73 days

Sun 20/11/16

15%

Thu 22/9/16

100%

1.1.1.3.2

Wash Trough

10 days

Fri 23/9/16

Sun 2/10/16

50%

1.1.1.3.3

Temporary Silt Trap

5 days

Mon 3/10/16

Fri 7/10/16

0%

1.1.1.3.4

Consultans Site Office

14 days

Sat 8/10/16

Fri 21/10/16

0%

1.1.1.3.5

Site office, Storage & Accommodation

14 days

Sat 22/10/16

Fri 4/11/16

0%

0%

1.1.1.3.6

Hording & Fencing

14 days

Sat 22/10/16

Fri 4/11/16

0%

0%

1.1.1.3.7

Signboard

30 days

Sat 22/10/16

Sun 20/11/16

0%

1.1.1.3.8

Tem. Drainage

14 days

Sat 22/10/16

Fri 4/11/16

0%

Sat 5/11/16

Fri 18/11/16

0%

Wed 7/9/16

Sat 15/10/16

51%

1.1.2.1

Setting Out

7 days

Wed 7/9/16

Wed 14/9/16

100%

1.1.2.2

Piling Works

30 days

Thu 15/9/16

Sat 15/10/16

40%

Sun 21/5/17

0%

1.1.3

ANCILLARY BUILDING

217 days Sun 16/10/16

1.1.3.1

Compact Sub

50 days

Sun 16/10/16

Sun 4/12/16

0%

1.1.3.2

Primary Screen + Pump Sump (Architectural


Works)

88 days Sun 16/10/16

Thu 12/1/17

0%

1.1.3.2.1

Base Slab

22 days Sun 16/10/16

Sun 6/11/16

0%

1.1.3.2.2

Wall

20 days

Mon 7/11/16

Sat 26/11/16

0%

1.1.3.2.3

Top Slab

14 days

Sun 27/11/16

Sat 10/12/16

0%

1.1.3.2.4

Staircase

7 days

Sun 11/12/16

Sat 17/12/16

0%

1.1.3.2.5

Plinth

3 days

Sun 18/12/16

Tue 20/12/16

0%

1.1.3.2.6

Pumping Room

22 days Wed 21/12/16

Thu 12/1/17

0%

SUPER STRUCTURE (AN, AE, SST & CLARIFIER TANK)


168 days Tue 18/10/16

Tue 4/4/17

0%

Tue 15/11/16

0%

1.1.3.3

100%
0%
0%
0%

0%
0%
0%
37 days
100%
70%
217 days
0%
88 days
0%
0%
0%
0%
0%
0%
168 days
0%

1.1.3.3.1

Base Slab

29 days Tue 18/10/16

1.1.3.3.2

Wall

87 days Wed 16/11/16

Sat 11/2/17

0%

1.1.3.3.3

Top slab & Walk Way

38 days

Sun 12/2/17

Tue 21/3/17

0%

1.1.3.3.4

Inter piping system

7 days

Wed 22/3/17

Tue 28/3/17

0%

1.1.3.3.5

Flow Control Box

7 days

Wed 29/3/17

Tue 4/4/17

0%

0%

1.1.3.3.6

Maintenance Platform

14 days

Wed 22/3/17

Tue 4/4/17

0%

0%

1.1.3.4

DIVERTION INCOMING SEWERAGE TO STP

7 days

Wed 5/4/17

Tue 11/4/17

0%

1.1.3.5

CHLORINATION CHAMBER AND SECONDARY


SCREEN, G&G CHAMBER

52 days

Sun 5/2/17

Tue 28/3/17

0%

1.1.3.5.1

Base Slab

7 days

Sun 5/2/17

Sat 11/2/17

0%

1.1.3.5.2

Wall

45 days

Sun 12/2/17

Tue 28/3/17

0%

26 days

Wed 22/3/17

Sun 16/4/17

0%

1.1.3.6

Sand Bed G&G, Odour, Grit Clasifier & Sand Bed


Clarifier

1.1.3.6.1

Base

7 days

Wed 22/3/17

Tue 28/3/17

0%

1.1.3.6.2

Wall

15 days

Wed 29/3/17

Wed 12/4/17

0%

1.1.3.6.3

Perforated Pipe

2 days

Thu 13/4/17

Fri 14/4/17

0%

1.1.3.6.4

Sand Filling

2 days

Sat 15/4/17

Sun 16/4/17

0%

34 days

Wed 22/3/17

Mon 24/4/17

0%

Sun 26/3/17

0%

1.1.3.7

Dewatering Sludge Room and Toilet

1.1.3.7.1

Base Slab

5 days

Wed 22/3/17

1.1.3.7.2

Column

5 days

Mon 27/3/17

Fri 31/3/17

0%

1.1.3.7.3

Beam

5 days

Sat 1/4/17

Wed 5/4/17

0%

1.1.3.7.4

Roof Truss & Matel Deck Installation

5 days

Thu 6/4/17

Mon 10/4/17

0%

1.1.3.7.5

Brickworks and plasterer

9 days

Tue 11/4/17

Wed 19/4/17

0%

1.1.3.7.6

Installation for roof structure and Matel Deck

5 days

Thu 20/4/17

Mon 24/4/17

0%

BLOWER HOUSE, CONTROL ROOM & OFFICE

45 days

Wed 22/3/17

Fri 5/5/17

0%

12 days

Wed 22/3/17

Sun 2/4/17

0%

1.1.3.8
1.1.3.8.1

Fotting and Base Slab

1.1.3.8.2

Column

5 days

Mon 3/4/17

Fri 7/4/17

0%

1.1.3.8.3

Beam

7 days

Sat 8/4/17

Fri 14/4/17

0%

1.1.3.8.4

Top Slab

8 days

Sat 15/4/17

Sat 22/4/17

0%

1.1.3.8.5

Brickworks and Plasterer

9 days

Sun 23/4/17

Mon 1/5/17

0%

1.1.3.8.6

Door & Window Installation

2 days

Tue 2/5/17

Wed 3/5/17

0%

1.1.3.8.7

Ducting

2 days

Thu 4/5/17

Fri 5/5/17

0%

27 days

Tue 25/4/17

Sun 21/5/17

0%

Tue 25/4/17

Thu 27/4/17

0%

1.1.3.9

GUARD HOUSE

1.1.3.9.1

Site Preparation & Excavation

3 days

1.1.3.9.2

Base Slab

3 days

Fri 28/4/17

Sun 30/4/17

0%

1.1.3.9.3

Column

4 days

Mon 1/5/17

Thu 4/5/17

0%

1.1.3.9.4

Beam

4 days

Fri 5/5/17

Mon 8/5/17

0%

1.1.3.9.5

Top Slab

4 days

Tue 9/5/17

Fri 12/5/17

0%

1.1.3.9.6

Brickworks & Plastering works

7 days

Sat 13/5/17

Fri 19/5/17

0%

1.1.3.9.7

Door & Window Installation

2 days

Sat 20/5/17

Sun 21/5/17

0%

72 days

Wed 22/3/17

Thu 1/6/17

0%

Wed 22/3/17

Fri 31/3/17

0%

1.1.4

MAIN BUILDING WORKS

1.1.4.1

Footing

10 days

1.1.4.2

Soffit Beam

10 days

Sat 1/4/17

Mon 10/4/17

0%

1.1.4.3

Column

10 days

Tue 11/4/17

Thu 20/4/17

0%

1.1.4.4

Top Beam

14 days

Fri 21/4/17

Thu 4/5/17

0%

1.1.4.5

Brickworks and Plasterer

40 days

Fri 21/4/17

Tue 30/5/17

0%

1.1.4.6

Roof Truss

7 days

Fri 5/5/17

Thu 11/5/17

0%

1.1.4.7

Installation Of Metal Deck

1.1.4.8

Air Ventilation Ducting

1.1.5
1.1.5.1
1.1.5.2
1.1.6

MECHANICAL AND ELECTRICAL WORKS


ELECTRICAL SYSTEM
ACMV SYSTEM
EXTERNAL WORKS

7 days

Fri 12/5/17

Thu 18/5/17

0%

14 days

Fri 19/5/17

Thu 1/6/17

0%

75 days

Tue 28/3/17

Sat 10/6/17

0%

45 days

Tue 28/3/17

Thu 11/5/17

0%

30 days

Fri 12/5/17

Sat 10/6/17

0%

194 days Thu 1/12/16

Tue 13/6/17

0%

0%
0%
0%

0%
52 days
0%
0%
26 days
0%
0%
0%
0%
34 days
0%
0%
0%
0%
0%
0%
45 days
0%
0%
0%
0%
0%
0%
0%
27 days
0%
0%
0%
0%
0%
0%
0%
72 days
0%
0%
0%
0%
0%
0%
0%
0%
75 days
0%
0%
194 days

1.1.6.1

Seweline and Manhole

120 days

Thu 1/12/16

Fri 31/3/17

0%

0%

1.1.6.2

Retaining Wall Structure

90 days

Sun 1/1/17

Fri 31/3/17

0%

0%

1.1.6.3

Fencing and gate

64 days

Sat 1/4/17

Sat 3/6/17

0%

1.1.6.4

Drainage works

30 days

Sat 1/4/17

Sun 30/4/17

0%

1.1.6.5

Rendering

30 days

Mon 1/5/17

Tue 30/5/17

0%

1.1.6.6

Signage

2 days

Wed 31/5/17

Thu 1/6/17

0%

1.1.6.7

Water Stand Pipe

2 days

Fri 2/6/17

Sat 3/6/17

0%

1.1.6.8

Road works

10 days

Sun 4/6/17

Tue 13/6/17

0%

154 days Tue 10/1/17

Mon 12/6/17

0%

64 days

1.1.7
1.1.7.1

PIPING AND EQUIPMENT

Mon 3/4/17

Mon 5/6/17

0%

1.1.7.1.1

Plate Screen & SS Screen Mounted

5 days

Mon 3/4/17

Fri 7/4/17

0%

1.1.7.1.2

Stainless Steel & Hot Dip GI Handrailing c/w Kicker 14


Plate
days

Sat 8/4/17

Fri 21/4/17

0%

1.1.7.1.3

Cat ledder & Basket (Collection Trough)

10 days

Sat 22/4/17

Mon 1/5/17

0%

1.1.7.1.4

Hot Dip Chequer Plate and Grating

15 days

Tue 2/5/17

Tue 16/5/17

0%

1.1.7.1.5

I Beam & Trolley Bin

15 days

Wed 17/5/17

Wed 31/5/17

0%

1.1.7.1.6

A - Frame & Lifting Davit

7 days

Mon 3/4/17

Sun 9/4/17

0%

1.1.7.1.7

Stop Board C/w Spindle Slidegate

10 days

Mon 10/4/17

Wed 19/4/17

0%

1.1.7.1.8

Maintenance Platform

5 days

Thu 20/4/17

Mon 24/4/17

0%

1.1.7.1.9

Wier Flow Control Box

7 days

Tue 25/4/17

Mon 1/5/17

0%

1.1.7.1.10

Parshall Flume

7 days

Tue 2/5/17

Mon 8/5/17

0%

1.1.7.1.11

Chlorination Tube C/w holder

5 days

Tue 9/5/17

Sat 13/5/17

0%

1.1.7.1.12

Sign board

3 days

Sun 14/5/17

Tue 16/5/17

0%

1.1.7.1.13

Chain Block c/w rollers

5 days

Wed 17/5/17

Sun 21/5/17

0%

1.1.7.1.14

Door & Window Installation

15 days

Mon 22/5/17

Mon 5/6/17

0%

127 days Tue 10/1/17

Tue 16/5/17

0%

1.1.7.2

STEEL WORKS

SDO Stage

1.1.7.2.1

Fabrication

1.1.7.2.2

Delivery

1.1.7.2.3

Installation

1.1.7.3

MECHANICAL WORKS

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
127 days

30 days

Mon 17/4/17

Tue 16/5/17

0%

71 days

Mon 3/4/17

Mon 12/6/17

0%

Mon 3/4/17

Tue 2/5/17

0%

0%
0%

Mon 3/4/17

Tue 2/5/17

0%

15 days

Wed 3/5/17

Wed 17/5/17

0%

1.1.7.3.4

Grit Classifier

3 days

Thu 18/5/17

Sat 20/5/17

0%

1.1.7.3.5

Dewatering System (Sludge Treatment)

14 days

Sun 21/5/17

Sat 3/6/17

0%

1.1.7.3.6

Valve and fittings

3 days

Mon 3/4/17

Wed 5/4/17

0%

1.1.7.3.7

Pendestal Penstok & Hoisting Facilities

7 days

Thu 6/4/17

Wed 12/4/17

0%

1.1.7.3.8

Exhaust Fan & Switchboards

4 days

Thu 13/4/17

Sun 16/4/17

0%

1.1.7.3.9

Rectingular Scrapper

15 days

Mon 17/4/17

Mon 1/5/17

0%

1.1.7.3.10

Screens

6 days

Tue 2/5/17

Sun 7/5/17

0%

1.1.7.3.11

Air Blowers & Ventilation Duckting

7 days

Mon 8/5/17

Sun 14/5/17

0%

1.1.7.3.12

Odour System

14 days

Mon 15/5/17

Sun 28/5/17

0%

1.1.7.3.13

Others

15 days

Mon 29/5/17

Mon 12/6/17

0%

60 days

Thu 6/4/17

Sun 4/6/17

0%

1.1.7.4.1

Control Panel

10 days

Thu 6/4/17

Sat 15/4/17

0%

1.1.7.4.2

Cabling works

50 days

Sun 16/4/17

Sun 4/6/17

0%

31 days

Mon 5/6/17

Wed 5/7/17

0%

30 days

Mon 5/6/17

Tue 4/7/17

0%

1 day

Wed 5/7/17

Wed 5/7/17

0%

Handing Over

0%

0%

30 days

1.1.8.2

0%

0%

Pumpsets

T&C

154 days
64 days

Sun 9/4/17

DI Main Pipe (M&E)

1.1.8.1

0%

Sun 16/4/17

1.1.7.3.3

TESTING AND COMMISSIONING

0%

Tue 10/1/17

1.1.7.3.2

1.1.8

0%

Mon 10/4/17

30 days

ELECTRICAL WORKS

0%

7 days

G.I Pipe Works

1.1.7.4

0%
0%

90 days

1.1.7.3.1

M/6

15 days

Wed 7/9/16

14 days

B/5

100%

Wed 7/9/16

37 days

E/3

299 days

14 days

Temporary Water and Power

May

M/2

73 days

73 days

PILING WORK STAGE

Mar

B/1

299 days

Plant & Equipment

1.1.2

Jan
E/11

1.1.1.3.1

1.1.1.3.9

Temporary Works

Finish

0%
0%
0%
71 days

0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
60 days
0%
0%
31 days
0%
0%

Critical

Milestone

Rolled Up Critical

Inactive Task

Duration-only

Finish-only

Critical Split

Slippage

Rolled Up Critical Split

Inactive Milestone

Manual Summary Rollup

Deadline

Task

Summary

External Tasks

Inactive Summary

Manual Summary

Progress

Split

Project Summary

External Milestone

Manual Task

Start-only

You might also like