CONOCO INDONESIA INC. LTD.

PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
2 of 23

REVISION CONTROL SHEET


LATEST REV

DATE ISSUED

PREPARED

REVIEWED

APPROVED

COMMENTS

14 Aug 02

B.Burn

S.Malkin

A.McIntosh

1 Oct 02

B.Burn

R.Ford

A.McIntosh

Issued For Use


Logo & Attachment
Changes

1 Mar 03

B.Burn

R.Ford

A.McIntosh

Check with Document Control for latest available Revision

Department Name
Change

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
3 of 23

TABLE OF CONTENTS
1.

INTRODUCTION.....................................................................................................4

2.

PURPOSE ..............................................................................................................4

3.

SCOPE ...................................................................................................................4

4.

DEFINITIONS .........................................................................................................5

5.

REFERENCES........................................................................................................5

6.

PROCESS ..............................................................................................................6

7.

RECORD APPROVALS .........................................................................................8

8.

ATTACHMENTS.....................................................................................................9
A

CRITICALITY RATING SCORE SHEET

QUALITY PROGRAM REQUIREMENTS SHEET

GUIDANCE ON FLUID HAZARD CLASSIFICATION

INSPECTION AND TESTING REQUIREMENTS SHEET, P501

MANUFACTURERS DATA ATTACHMENT, INQ-4

CRITICALITY RATING SUMMARY SHEET

QUALITY PROGRAM REQUIREMENTS CHECKLIST

Check with Document Control for latest available Revision

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

1.

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
4 of 23

INTRODUCTION
Quality activities are driven by a formal criticality rating process, which considers:
a)

Safety and operability consequences and

b)

Probability factors, design complexity, and maturity of design.

In addition, criticality is also driven by the degree of quality planning, extent of


inspection, oversight, and verification.
The Engineering and Quality Departments are responsible for using this criticality
rating process as a tool to communicate the importance of each equipment
package so that quality plans may be developed.
2.

PURPOSE
To describe a standard system for reviewing and defining the criticality of
procured items and for identifying a consistent and appropriate level of quality
surveillance during the manufacturing cycle.
This procedure is also intended to communicate the basis for establishing
inspection requirements.

3.

SCOPE
Covers design review, safety, environmental and quality aspects when
considering the criticality of procured equipment and complex fabricated items.
Criticality Rating Assessment shall be applied to those items considered critical
such as:

ESD and Subsea Valves including Actuators

Linepipe

Vessels, e.g., Reactors, Drums, Towers

Heat Exchangers, including Fired Heater Heating Coils

Machinery, e.g., Turbines, Pumps, Compressors

Mechanical Equipment, e.g., Filters, Dryers, Craneage

Electrical Equipment e.g. Motors, Variable Speed Drives, Switchgear,


Transformers, UPS and DC.

Instrumentation, e.g., DCS, ESD

Non-standard Life Saving Equipment.

Induction Bends.

Check with Document Control for latest available Revision

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
5 of 23

The Project Equipment List shall be used as the baseline for mutually agreeing
between Contractor and Company those equipment packages which require
assessment. A modified version is contained in Attachment F (Criticality Rating
Summary Sheet) which is based on the latest Project Equipment List.
4.

DEFINITIONS
Criticality: Characteristics of a product or service which present a measurable risk
of failure resulting in varying levels of significance with regard to cost, plant
operation, health, safety, loss of life and damage to the environment.
Criticality Rating: A comparative, numerical indication of the importance of a
product or service when assessed against specific criteria.
Criticality Elements: Standardized essential criteria which aid as guidance for
assessing the importance of such criteria The six (6) main criticality elements
used in this procedure are:
A.

Health, Safety, and Environmental

B.

Facility Consequences

C.

Fluid Characteristics

D.

Design Factors

E.

Manufacturing/Supplier Experience

F.

Quality System

Each main element contains four (4) sub elements ranging from low to medium to
high levels of significance on a score of 1 to 4 where, for example, 2 is a higher
risk rating than 1.
Criticality Rating Code: A summary rating taken from the total score awarded
against all sub elements and which is selected as Low Criticality (L), Medium
Criticality (M) or High Criticality (H).
Review Team: The Review Team consists of a Contractor engineering
representative (e.g. Engineering Manager, Lead Engineer) and a Company
Engineering Representative.
5.

REFERENCES
84501-9200-1L-025

Positive Material Identification

Check with Document Control for latest available Revision

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

6.

PROCESS

6.1

Determination of Criticality Ratings

REV
2

DATE
1 Mar 03

PAGE
6 of 23

6.1.1 Technically competent personnel representing Engineering Management,


Process and Specialist Engineering Disciplines shall perform criticality ratings
assessments. Safety and Quality representatives shall be involved to ensure that
the criteria are interpreted to maximize safety and environmental protection and
to optimize quality requirements.
6.1.2 Criticality Ratings and the extent of inspection shall be assessed for each
procurement package meeting the criteria summarised in Section 3 above.
6.1.3 The Contractor Pipeline/Wellhead Engineering Manager or his designee shall
determine the equipment packages required to be assessed and a list of such
equipment shall be made. This list shall be reviewed and mutually agreed
between Contractor and Company.
6.1.4 Criticality assessment shall be limited to packaged equipment. Bulk materials will
not be subject to assessment.
6.1.5 Packaged equipment shall be assessed as a whole i.e. criticality rating
assessments shall be conducted on the package as a whole and not for
component items.
6.1.6 The lead discipline engineer (structural, process, mechanical etc), using the
Criticality Rating Score Sheet (refer Attachment A) shall assess the equipment
and report the Final Criticality Rating (CR) on the Criticality Rating Summary
Sheet.
6.1.7 The Criticality Rating Index (CR Index) shall be established from the highest
criticality index number to lowest (i.e. 2 is higher than 1), determined for safety
factors, facility or financial consequences, etc.
6.1.8 Criticality Elements can be added or deleted from the risk rating based on a
variety of factors such as experience or knowledge of vendor strengths and
weaknesses.
6.1.9 Any additions or deletions to standard Criticality Elements shall clearly be
identified by striking through those elements to be deleted or italicizing
additional elements.
6.1.10 An assessment for each of the six Criticality Elements should be made and
entered into the column CR Assigned.
6.1.11 The CR Assigned for each of the elements should be totalled on the Criticality
Rating Score Sheet in order to determine the Critical Rating Total Score. Using
this total the criticality rating code is determined based on the table at the bottom
of the scorecard.
Check with Document Control for latest available Revision

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
7 of 23

6.1.12 The criticality rating code may be amended based on knowledge and experience
of the equipment being assessed. However, prior written approval shall be
obtained from the Contractor Pipeline/Wellhead Engineering Manager.
6.1.13 In the event that the criticality rating code is amended, the Criticality Rating Score
Sheet must record the justification for the change.
6.1.14 The Final Criticality Rating (CR) is determined by the final Criticality Rating Total
Score, in conjunction with any further amendment by the lead discipline engineer.
However, Final Criticality Ratings shall be mutually agreed between Contractor
and Company.
6.1.15 The lead discipline engineer shall sign off the Criticality Rating Score Sheet and
shall be responsible for logging the Final Criticality Rating on the Criticality
Rating Summary Sheet (Refer Attachment F).
6.1.16 Following bid analysis and purchase award to the successful vendor, the
assessment may be amended based on actual factors specific to the awarded
vendor, such as experience and knowledge of vendors systems, capabilities, etc.
to achieve a correct rating for the actual vendor. Any revision of rating shall be
noted on the Criticality Rating Score Sheet and the Criticality Rating Summary
Sheet.
6.2

Quality Program Requirements

6.2.1 When the lead discipline engineer has defined the Final Criticality Rating (CR)
then a Quality Program Requirements Sheet shall be prepared (Refer Attachment
B) for each procured item.
6.2.2 These requirements shall serve as the basis for review of all Inspection and Test
Plans and/or Quality Plans submitted by the Vendor. Inspection and Test Plans
and/or Quality Plans submitted by the Vendor will be made available for
Company review.
Comments may be annotated in the remarks column as guidance to inspection
events during the course of manufacture or fabrication.
6.2.3 The lead discipline engineer shall then prepare an Inspection and Testing
Requirements Sheet, form Contractor P501 (Refer Attachment D) and a
Manufacturers Data Attachment, form Contractor-INQ-4 (Attachment E)
6.2.4 All inspection requirements and manufacturing data shall be defined by using the
Quality Program Requirements sheet as the basis.
6.2.5 The Quality Program Requirements sheets, Inspection and Testing Requirements
and the Manufacturers Data Attachments shall be attached to the Material
Requisition and will form part of the Request for Quotation (RFQ).

Check with Document Control for latest available Revision

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
8 of 23

6.2.6 During bid evaluation and clarification the Quality Program Requirements
Checklist (refer Attachment G) may be used as guidance and as a checklist to
ensure all relevant points are covered.
6.2.7 Note that alloy component of equipment and materials may require Positive
Material Identification (PIM). Guidance regarding the extent of parts to be
checked, sampling requirements, approved test methods, acceptance/rejection
criteria and marking requirements are contained in Positive Material Identification
Specification, Document No: 84501-9200-1L-025
6.2.8 It is extremely important that, when the criticality rating and the level of inspection
has been determined, candidate Vendors are advised at the earliest opportunity
(i.e. RFQ stage) of the intended quality program requirements.
6.3

Records

6.3.1 In general and as a minimum, records of Criticality Rating assessments shall


include:
6.3.1.1

Any instances in which quantitative Criticality Ratings are "overridden"


to a higher or lower value, along with the justification for the action.

6.3.1.2

Any modifications to the "standard" criteria shown in Appendices.

6.3.1.3

The points scored for each criterion, the summary of points scored and
the final rating, documented on the Criticality Rating summary sheet.

6.3.2 The Master Equipment List shall be used to summarise all criticality assessments
conducted by the Engineering Dept. (Refer Attachment F)
6.3.3 All criticality records shall be retained and maintained by the Engineering
Manager. Such records shall consist of:

The Master Equipment List (modified to include Criticality Rating Summary)

Criticality Rating Score Sheets

Quality Program Requirements Sheets

Inspection and Testing Requirements Sheets

6.3.4 All records shall be maintained in purchase order number sequence and shall be
made available for review by Contractor Quality Assurance if required.
7.

RECORD APPROVALS

7.1

All records shall, prior to issue for purchase be summarily checked by the Project
Quality Control Co-ordinator and approved by the Engineering Manager or their
nominated delegate(s).

Check with Document Control for latest available Revision

CONOCO INDONESIA INC. LTD.


PROJECTS DEPARTMENT
SPECIFICATION
TITLE
EQUIPMENT CRITICALITY RATING

DOCUMENT NUMBER
84501-9200-9P-005

REV
2

DATE
1 Mar 03

PAGE
9 of 23

8.

ATTACHMENTS

Criticality Rating Score Sheet

Quality Program Requirements Sheet

Guidance on Fluid Hazard Classification

Inspection and Testing Requirements Sheet, form Contractor P501

Manufacturers Data Attachment, form Contractor - INQ-4

Criticality Rating Summary Sheet

Quality Program Requirements Checklist (for use as guidance during Bid


Clarification)

Check with Document Control for latest available Revision

ATTACHMENT A

CRITICALITY RATING SCORE SHEET


Item/Equipment Title:
Requisition No:

Item/Equipment No:

CR
CR
Index
Assigned
A. HEALTH, SAFETY, AND ENVIRONMENTAL. (Note : Due to potential consequences of health, safety and environmental failure this
element requires a minimum C. R. of 2
A catastrophic failure would lead to:

Criticality Elements

A.1 Risk leading to loss of life, permanent damage to environment

A.2 Possible injury to personnel, temporary damage to the environment

A.3 Medium risk, limited by emergency shutdown system, integrated safety systems in design

A.4 No assessable damage to environment, personnel or adjoining equipment

B. FACILITY CONSEQUENCES What impact would equipment failure have on plant/unit operation?
B.1 Equipment is of high complexity and failure would results in long term production shutdown due to mobilisation
time of repair equipment or fabrication time for replacement parts
B.2 Equipment is of medium to high complexity and failure would cause operational upset and/or production downtime
of more than 24 hours.
B.3 Equipment is of low to medium complexity and failure would result in moderate impact so as to inhibit full
production and require emergency maintenance and control operations.
B.4 Equipment is of low complexity and failure would only result in convenience to plant operation and result in
operational difficulties without loss of process operations.
C. FLUID CHARACTERISTICS What level of danger is posed by the medium transported?

4
3
2
1

C.1 Toxic Gases or liquids, highly corrosives transported in complex equipment with multiple gaskets / seals or bolted
connections.

C.2 Toxic Gases or liquids, highly corrosives transported in equipment with gasket / seals, or bolted connections

C.3 Toxic Gases or liquids, highly corrosives transported in equipment of medium complexity without gaskets / seals or
bolted connections

C.4 Innocuous gas or liquid transported in equipment of flanged, solid or welded construction.

D. DESIGN FACTORS Are there critical or new design features which warrant special engineering or inspection follow-up?
D.1 New innovative design with unproven reliability or non-code based requirements.

D.2 Extrapolation of proven design with limited reliability data or previous experience.

D.3 Modification of proven design with known reliability and past experience

D.4 Frequently used and well-proven design with easily obtained spare parts

E. MANUFACTURING/SUPPLIER EXPERIENCE What is the past experience in obtaining goods/services from the list of suppliers short
listed?
E.1 Past experience with manufacturers is poor, containing either design errors or consistent history of nonconforming
4
products.
E.2 No historical experience dealing with suppliers, or poor industry reputation of some possible suppliers

E.3 Manufacturers have supplied goods to company in the past with varied results

E.4 Manufacturers have provided goods/ services repeatedly of good quality during the past 5 years

F. QUALITY SYSTEM Manufacturers / suppliers quality system required for the equipment supplied
F.1 Manufacturer / Supplier may have to be accepted, which has quality system below industry standard.

F.2 Manufacturer / Supplier must have basic Quality System in line with industry standard.

F.3 Manufacturer / Supplier must have Quality System in accordance with industry standard (ISO 9000, API, etc)

F.4 Manufacturer / Supplier must have ISO 9000, Q1 or equivalent system certification in place

Point Score

Criticality Rating Code

18 24 Points

High Criticality

12 17 Points

Medium Criticality

6 11 Points

Low Criticality

Criticality Rating Total Score


Input/Justification for amending Criticality Rating Code

Final Criticality Rating


(CR)

Established Rating

Name:

Prepared by: (Lead Discipline Engineer)


Name :

Checked by: (QA/QC Dept)

Approved by: (Engineering Manager)


Name:

Sign/Date:

Sign/Date:

Sign/Date:

10 OF 23

1)

ATTACHMENT B
QUALITY PROGRAM REQUIREMENTS SHEET
MRR No.: ..
CRITICALITY
Equipment. Name:
RATING
PO No.:
REQUIREMENTS
H
M
L COMMENTS
X
X
Assessment of suppliers by one of the X
following methods:

The Specific Project Approved suppliers


list
Pre-commitment Assessment
Previous experience/historical data
Documentation Review
Certified Products and quality registration
schemes

2)

Notification of Requirements of Inspections/QC


Plan (ITP) with order placement. Requirement
for Draft ITP within 30 days of order
placement.

3)

Pre-inspection meeting prior to Manufacture.

4)

Project Specific Inspection / QC Plan to be


approved after order placement.

5)

Design
documentation,
drawings
Procedures to be reviewed by engineering

or

6)

Notification of Sub-suppliers and location


required within 30 days of order placement.

7)

In Process Audit of Supplier

Dependent upon complexity of equipment


and experience with vendor. Audits will be
per approved audit schedule. Where
materiel is identified as medium criticality
then in process audits shall be reconciled on
a case-by-case basis.

8)

Monitoring
of
vendor
production/manufacturing.

during

Expediting visits (when applicable)

9)

Witness of specific major inspection points as


agreed on ITP. (i.e., Hydrotest, functional test,
Shipping, etc.)

10) Witness pressure testing.

11) Review of Material Test reports

12) Preservation/packing/loading inspection.

13) Approve Mechanical Data Project Books and


Fabrication Dossiers.

14) Resident inspection required.

X
Dependent on critically of delivery

If specified by Project Engineer


All inspection requirements are dependent
on the individual items, project procedures
and or when specified by the purchaser.

11 OF 23

ATTACHMENT C

GUIDANCE ON FLUID HAZARD CLASSIFICATION


Where available information prohibits quantitative assessment the following procedure
should be applied:
1.

Identify the chemicals in the process fluid.


Sheets).

2.

Check in NFPA Fire Protection Guide on Hazardous Materials for each hazard
classification. (Note: Usually no data is given if the chemical is innocuous).
a)

Toxicity (Health)
-

b)

Innocuous (materials which offer no health hazard)


Low (slight health hazard, may be desirable to use self-contained
breathing apparatus).
Moderate (health hazard, use self-contained breathing apparatus).
High (extremely hazardous to health, areas may be entered with
extreme care, full protective clothing must be used, no exposed skin).

Flammability
-

c)

(Check Hazardous Materials Data

Innocuous - non-flammable (material is not combustible).


Low (material must be preheated to initiate ignition, most solids).
Moderate (liquids which, when released, may give off combustible
vapours).
High - dangerous (liquids which can be ignited under all normal
conditions, liquids at or above their flash points, fibrous solids which are
combustible.

Reactivity
-

Innocuous - non-explosive (material is stable even under fire conditions


and not reactive with water).
Low (materials normally stable but which may become unstable at
elevated temperatures and pressures, or which may react with water
with a low energy release).
Moderate (materials which in themselves are normally unstable and
undergo chemical change but not detonation, but which react violently
with water with high energy release).
High (materials which in themselves detonate or decompose with large
energy release when initiated by a strong source, sensitive to thermal or
mechanical shock, or which react explosively with water.)

12 OF 23

ATTACHMENT D
P501
PAGE 1 OF 1

TO BE COMPLETED BY CONTRACTOR
Rev. No.

Contractor's Name
INSPECTION AND TEST REQUIREMENTS
Item Description:

Req'n.

Progress & Vendor

Fac.

05/08/02

R2216-014001

P.O. No.

SAND REMOVAL SKID

Insp'n Type:

Date:

Final & Vendor

Final &

Fac.

Export Packer

Final & Receiving


Location

1. VISUAL INSPECTION/WITNESSING BY BUYER'S REPRESENTATIVE


2. CERTIFICATES/RECORDS/DATA TO BE CHECKED BY BUYER'S REPRESENTATIVE
3. CERTIFICATES/RECORDS/DATA TO BE PROVIDED BY VENDOR
01

Manufacturers Certificates

02

Mill Test Certificates

03

Heat Treatment (Certificates), if required

04

Heat Treatment (Charts), if required


!

05

Welder Qualification Records

Welding Procedure Qualification Records (H)

07

Workmanship, Material, Surface Defects, Components, Dimensions

08

Compliance with P.O. Description, Specifications, Certified Drawings, Catalogue Description, Paint Specification

09

Quality Control Manual

10

Non-Destructive Testings (NDT) if required

Tests and Inspection per Specifications

Other Requirements (as per Specifications)

06

11
12
13
14
15
16

17
18
19
20
21
22
23
24
25

Notes:

13 OF 23

ATTACHMENT E
INQ-4
PAGE 1 OF 6
MANUFACTURER'S DATA ATTACHMENT
REQN. NO.
SELLER
MANUFACTURERS DATA FOR

:
:
:

R2216-014001
SAND REMOVAL SKID
INSTRUCTIONS

1.

DOCUMENT INDEX
THE LIST ON PAGES 2 & 3 OF INQ-4 IS AN INDICATIVE GENERALISED LIST ONLY. WHERE
REQUESTED SELLER SHALL SUBMIT A SPECIFIC DETAILED LIST OR INDEX OF ALL
DOCUMENTS/DRAWINGS UNDER THE TITLES SPECIFIED IN PAGES 2 & 3 WHICH ARE TO BE
TREATED AS HEADING OR CATEGORIES AS APPLICABLE TO THE ORDER ALONG WITH SCHEDULED
DATE OF ISSUE FOR EACH DATA/DOCUMENT ITEM ON THE LIST. AS A MINIMUM. A DETAILED LIST
OF THE KEY DOCUMENTS INDICATED BY (*) MARKED ON PAGES 2 AND 3 OF 6 (INQ-4) SHALL BE
SUBMITTED WITH PROPOSAL. SEE FORMAT ON PAGE 4.
WE DEEM IT NECESSARY TO EMPHASIZE THIS POINT AND GIVE IT DUE CONSIDERATION IN
AWARDING PURCHASE ORDER.
SELLER SHALL SUBMIT UPDATED INDEX ALONG WITH EVERY TRANSMITTAL.

2.

DOCUMENT SUBMISSION QUANTITY/SCHEDULE


PLEASE COMPLETE & RETURN THIS FORM INDICATING LENGTH OF TIME NECESSARY TO SUPPLY
THE QUANTITY OF DATA REQUESTED.
SELLER SHALL PAY PARTICULAR ATTENTION TO THE QUANTITY OF DRAWINGS TO BE SUBMITTED
"FOR APPROVAL" AND BE SPECIFIC AS TO THE TIME (NUMBER OF CALENDAR DAYS) REQUIRED TO
SUBMIT THESE DRAWINGS.
SELLER SHALL BE REQUIRED TO FURNISH THE SPECIFIC DATA IN QUANTITIES AS INDICATED.

3.

G.A. DRAWINGS
DRAWING SHALL SHOW ALL DIMENSIONS WHICH MAY BE REQUIRED BY PURCHASER FOR INSTALLATION
AND FOR CLEARANCE TO ADJACENT EQUIPMENT WHEN INSTALLED.

4.

ACCURACY
SELLER SHALL ASSUME FULL RESPONSIBILITY FOR THE ACCURACY OF ALL DRAWINGS AND DATA
SUBMITTED BY HIM.

5.

DOCUMENT IDENTIFICATION
ALL MANUFACTURER'S DATA MUST BE IDENTIFIED WITH : " CONTRACTOR'S PURCHASE ORDER NO.,
REQUISITION NO., EQUIPMENT NO., (TAG NO.), PROJECT/CONTRACT NO. AND A CONTRACTOR DOCUMENT
NO. (CONTRACT NO.-REQUISITION NO.-ITEM CODE-SEQ.)

6.

DOCUMENT SIZE
DRAWING SHALL BE A1, A2, A3 OR A4 SIZE
OTHER DOCUMENTS SHALL BE ON A4 OR A3 SIZE PRINTS
ALL DRAWING PRINTS/DOCUMENTS ABOVE A3 (297 MM X 420 MM) SHOULD BE FOLDED.
AT "FOR APPROVAL" STAGE, VENDOR SHALL SUBMIT AT LEAST ONE REPRODUCIBLE OF ALL
DRAWINGS OR DOCUMENTS ABOVE A3 SIZE.

7.

FINAL AS-BUILT DATA


ALL FINAL CERTIFIED DATA SHALL BE MANUFACTURER'S "AS-BUILT": DRAWINGS/DOCUMENTS.
THEY SHALL BE PROPERLY INDEXED, ORGANIZED AND COMPILED IN A FORMAT SPECIFIED BY
PURCHASER COMPLETE WITH RELEVANT QUANTITY OR REPRODUCIBLE INDICATED.
FINAL VENDOR DATA BOOK (S) SHALL BE GROUPED INTO:
(A)
EQUIPMENT DATA BOOK (S).
(B)
EQUIPMENT CERTIFICATE (S).
DATA BOOK (S) SHALL BE BINDED IN THE 3 HOLES BINDER (S) AND ALL DRAWING
PRINTS/DOCUMENTS ABOVE A3 SHALL BE FOLDED IN THE PLASTIC FOLDER.

8.

LANGUAGE
ALL DOCUMENTS SHALL BE LEGIBLE AND PRESENTED IN ENGLISH LANGUAGE.

9.

GENERAL

9.1

COST OF FULLY COMPLYING WITH ALL THE INSTRUCTIONS AND DATA REQUIREMENTS IN INQ-4 SHALL BE
INCLUDED IN SELLER'S QUOTE.

9.2

SELLER'S FINAL INVOICE WILL BE WITHHELD PENDING BOTH:


(A)
RECEIPT OF MATERIAL
(B)
RECEIPT OF ALL MANUFACTURER'S DATA AND FULL COMPLIANCE OF THIS INQ-4 INSTRUCTIONS
WHICH IS INTEGRAL PART OF PURCHASE ORDER

9.3

RESPONSIBLE CONTACT
SELLER SHALL FURNISH THE NAME, TITLE, AND TELEPHONE NO. OF THE PERSON WHO WILL BE
RESPONSIBLE FOR COMPLYING WITH OUR REQUIREMENTS AND TRANSMITTING SAME TO US.
TITLE:
TEL:
NAME :

9.4

NON-COMPLIANCE REPORT
PURCHASER SHALL COMPLETE AND ISSUE THIS REPORT (PAGE-5) TO SELLER, WHEN APPLICABLE ON
EACH TRANSMITTAL FROM SELLER TO MONITOR COMPLIANCE.

14 OF 23

ATTACHMENT E
INQ-4
PAGE 2 OF 6
TO BE COMPLETED BY CONTRACTOR

FURNISH
WITH
PROPOSAL

ITEM
CODE

MANUFACTURER S DATA

QTY.

INDICATE LENGTH OF TIME NECESSARY TO


SUPPLY THE QTY OF DATA REQUESTED
BELOW
FOR
APPROVAL

QTY.

TIME
REQ
ARO

REFERENCE OF FINAL
CERTIFIED DWGS. &
MFR'S DATA (SEE
INSTRUCTION 7 OF PG 1)
QTY.

1.

KEY VENDOR DOCUMENT INDEX (SEE NOTES 1 AND 2 ON PG 1)

2.

COMPLETE VENDOR DOCUMENT INDEX (SEE NOTES 1 AND 2 ON PG 1)

7P

6P

3.

FLOW DIAGRAMS / P&ID

5P

7P

6P

4.

GENERAL ARRANGEMENT DRAWINGS

5P

7P

6P

5.

DETAILED SPECIFICATION / DRAWINGS

7P

6P

6.

ELECTRICAL ONE-LINE DIAGRAMS

7.

SYSTEM BLOCK DIAGRAMS

7P

6P

8.

CONTROL SCHEMATICS

7P

6P

9.

WIRING DIAGRAMS

7P

6P

10.

CAUSE & EFFECT DIAGRAMS

7P

6P

11.

INSTRUMENT INDEX

7P

6P

12.

DATA SHEETS

7P

6P

13.

PERFORMANCE CURVES

7P

6P

14.

CALCULATIONS

7P

6P

15.

CODE REPORTS

7P

6P

16.

PART LIST WITH RECOMMENDED SPARES PRICED FOR START-UP

17.

PARTS LIST WITH RECOMMENDED SPARES PRICED FOR 2 YEARS


OPERATION

18.

INSTALLATION / OPERATING, MAINT. INSTRUCTIONS / MANUAL

19.

TECH. CATALOGUES AND DATA

20.

GUARANTEE (S) WARRANTY

5P

TIME REQ.
AFTER APP'L
DWG MARK-UPS

6P
7P

6P
6P

5P

6P
6P

21.

TEST CERTIFICATES (FUNC., HYDRO, ETC.)

6P

22.

HYDROTEST CHARTS AND CERTIFICATES

6P

23.

TEST PROCEDURES (FUNC., ETC.)

24.

INSTRUMENT CALIBRATION CERTIFICATES

6P

25.

SIGNED VENDOR AND/OR SUB-CONTRACTOR / INSPECTOR TEST


REPORTS

6P

26.

LUBRICATION SCHEDULE

7P

6P

27.

PAINTING PROCEDURES

7P

6P

28.

PAINTING INSPECTION REPORTS

29.

WELDING PROCEDURES SPECIFICATIONS

7P

6P

30.

WELDING PROC. QUALIFICATION RECORDS

31.

NON-DESTRUCTIVE EXAMINATION PROCEDURE

7P

6P

32.

NON-DESTRUCTIVE EXAMINATION REPORTS

6P

33.

MANUFACTURERS CERTIFICATES

6P

34.

MILL MATERIAL CERTIFICATES

6P

7P

6P

6P

6P

IF ANY PORTION OF THE ABOVE IS NOT APPLICABLE, PLEASE ADVISE IN WRITING.


P
- PRINTS
R
- REPRODUCIBLE
ARO - AFTER RECEIPT OF ORDER OR TELEX OF INTENT (TOI) OR TELEX OF AWARD (TOA) WHICHEVER IS EARLIER.

15 OF 23

ATTACHMENT E
INQ-4
PAGE 3 OF 6
TO BE COMPLETED BY CONTRACTOR

ITEM
CODE

VENDOR'S EQUIPMENT
CERTIFICATE(S)

FURNISH
WITH
PROPOSAL

QTY.
35.

HEAT TREATMENT CERTIFICATES, IF REQUIRED

36.

HEAT TREATMENT CHARTS, IF REQUIRED

INDICATE LENGTH OF TIME NECESSARY TO


SUPPLY THE QTY OF DATA REQUESTED
BELOW
FOR
APPROVAL

QTY.

TIME
REQ
ARO

REFERENCE OR FINAL
CERTIFIED DWGS. &
MFR'S DATA (SEE
INSTRUCTION 7 OF PG 1)
QTY.

37.

PRESERVATIVE PROCEDURES

7P

6P

38.

LIFTING ARRANGEMENT

7P

6P

39.

LIFTING PROCEDURES

7P

6P

40.

5P

MFG FAB/PRODN SCHEDULE

41.

QA/QC MANUAL

7P

6P

42.

QUALITY PLAN

7P

6P

43.

INSPECTION AND TEST PLAN

7P

6P

44.

INSPECTION SCHEDULE

7P

6P

45.

CERTIFICATE OF COMPLIANCE

46.

CD ROM

47.

SPECIAL TOOLS LIST

5P

48.

PRELIMINARY ESTIMATE EMPTY / OPERATING / TEST WEIGHTS

5P

49.

UNPRICED PURCHASE ORDERS

TIME REQ.
AFTER APP'L
DWG MARK-UPS

7P

2
7P

6P

6P

IF ANY PORTION OF THE ABOVE IS NOT APPLICABLE, PLEASE ADVISE IN WRITING.


P
- PRINTS
R
- REPRODUCIBLE
ARO - AFTER RECEIPT OF ORDER OR TELEX OF INTENT (TOI) OR TELEX OF AWARD (TOA) WHICHEVER IS EARLIER.

16 OF 23

ATTACHMENT E
INQ-4
PAGE 4 OF 6
TO BE COMPLETED BY VENDOR

VENDOR DOCUMENT INDEX


ITEM CODE /
SEQUENCE
NO.**

TITLE / DESCRIPTION**

DOCUMENT NO.
VENDOR

CONTRACTOR***

REV
NO.

ISSUE DATES / PERIOD


FOR APPROVAL

FINAL

**

THE ITEM NUMBERS AND CORRESPONDING HEADINGS/CATEGORIES LISTED IN THE FIRST 2 COLUMNS ON PAGES 2 AND 3 OF
INQ-4 SHALL BE USED WHERE APPLICABLE.
- VENDOR SHALL ADD DETAILED LIST BELOW THESE APPROPRIATE HEADINGS/CATEGORIES.
- VENDOR DOCUMENT SEQUENCE NUMBERING SYSTEM SHALL BE: FOR E.G. G.A. DRAWINGS-004-001, 004-002.
- THE SEQUENCE NO. OF AN ITEM NOT FALLING UNDER THE PREDEFINED HEADINGS OR CATEGORIES ON PAGES 2 AND 3
SHALL BE THE NEXT AFTER THE PREVAILING LAST ITEM.

***

CONTRACTOR DOC. NO. SYSTEM SHALL BE [CONTRACT NO.- REQUISITION NO. - ITEM CODE - SEQ]
E.G. R2391-4001-004-001 SHALL BE THE DRAWING NO. OF A MECHANICAL G.A. DRAWING.

17 OF 23

ATTACHMENT E
INQ-4
PAGE 5 OF 6

TO BE COMPLETED BY CONTRACTOR VENDOR DATA SECTION


REQN. NO.:

R2216-014001
CONTRACTOR NAME
VENDOR DATA SECTION
INQ-4: NON- COMPLIANCE REPORT

PURCHASE ORDER NO.


REQUISITION NO.
ITEM DESCRIPTION
VENDOR TRANSMITTALL REF.
VENDOR DATA RECEIPT DATA

:
:
:
:
:

R2216-014001
SAND REMOVAL SKID

1.

THE DOCUMENT LIST IS NOT COMPLETE/UPDATED

2.

VENDOR TO CONFIRM DOCUMENT LIST IS FINAL

3.

THE DOCUMENT IS NOT AS PER VENDOR SUBMITTED DOCUMENT LIST

4.

THE DOCUMENT IS NOT AS PER INQ-4

5.

TOTAL NUMBER OF COPIES RECEIVED IS NOT AS PER INQ-4

6.

THE DOCUMENT DOES NOT BEAR A PT. JAY RAY NUMBER

7.

NO REPRODUCIBLES SUBMITTED

8.

PRINTS OF DRAWINGS LARGER THAN A3 SIZE HAVE NOT BEEN FOLDED

9.

VENDOR TO CONFIRM THE DOCUMENT IS FINAL, AS-BUILT AND AS SUCH NO FURTHER


REVISIONS TO DOCUMENT WILLL FOLLOW. IF SO, VENDOR TO STAMP "AS-BUILT".

10.

DOCUMENTS NOT PROPERLY COMPILED

11.

DOCUMENT BEARS THE SAME REVISION NUMBER AS THE PREVIOUS ONE SUBMITTED FOR
APPROVAL

12.

DOCUMENTS ILLEGIBLE

13.

PREVIOUS COMMENTS NOT INCORPORATED

14.

DOCUMENT SEQUENCE ITEM NUMBER IS NOT AS PER INQ-4/APPROVED DOCUMENT LIST

15.

DOCUMENTS NOT PRESENTED IN ENGLISH LANGUAGE

16.

DOCUMENTS NOT LISTED IN THE TRANSMITTAL

17.

NO TRANSMITTAL

18.

VENDOR DEVIATION/POST APPROVAL REVISION REQUEST NOTIFICATION FORM NOT


APPROVED/RECEIVED

PLEASE RESUBMIT BY

DOCUMENTS REJECTED.
.

DOCUMENTS ACCEPTED FOR


APPROVAL THIS TIME SUBJECT
TO COMPLIANCE OF THE ABOVE IN FUTURE
INQ-4

ATTACHMENT E
PAGE 6 OF 6

VENDOR DEVIATION/POST-APPROVAL REVISION


REQUEST NOTIFICATION FORM
TO BE COMPLETED BY VENDOR
P.O. NO.:

REQUEST NO.:

REQN. NO.:
EQPT TAG NO.:

DESCRIPTION:
*

SPECIFICATION DEVIATION/REQUEST

POST-APPROVAL REVISION

DESCRIPTION OF SPEC. DEVIATION OR POST-APPROVAL REVISION WITH JUSTIFICATION:


(PROVIDE ATTACHMENT IF NECESSARY; ALSO LIST ALL KEY DOCUMENTS AFFECTED BY THE REQUESTED CHANGE TOGETHER
WITH REVISED DATES)

IMPACT

COST

DOCUMENT INDEX

DELIVERY OF MATERIAL

WEIGHT

SIGNATURE
SIGNATURE

DATE
:

DATE:

RESPONSE (BY CONTRACTOR)

*
*

BACK CHARGEABLE
REVISION DEVIATION

ACCEPTED

ACCEPT WITH COMMENTS

SIGNATURE (REQUISITION ENGINEER):

DATE:

APPROVAL (PROJECT MATERIAL CO-ORD/PMT):

DATE:

APPROVAL (PROJECT ENGINEER):

DATE:

APPROVAL (Company):

DATE:

REJECTED

IMPORTANT
Specification issued with P.O. and KEY Vendor Data approval thereafter are treated as "FROZEN" BOTH BY
SELLER AND BUYER.
POST-ORDER DEVIATION OR POST-APPROVAL REVISION INITIATED BY VENDOR IS THEREAFTER
STRICTLY PROHIBITED.
Under no circumstances seller shall revise documents/drawings without receipt of prior approval on this form.
This form is intended to control post-order deviations and/or post-approval revisions.
*DISTRIBUTION:

VENDOR DATA (for inc. in Job Book)

REQUISITION ENGINEER

ORIGINAL TO VENDOR

PROJECT MANAGEMENT (CONTRACTOR)

INSPECTION

PROCUREMENT

FABRICATION

PROJECT MANAGEMENT (COMPANY)

* PLEASE TICK (!) APPROPRIATE BOX

CRITICALITY RATING
SUMMARY SHEET

Item

System

Subsystem

Tag

Equipment / Material Name

Location

Attachment F
Page 1 of 1

Rating Point
Remarks
Final
A B C D E F Criticality
Criticality
Rating
Rating (CR)
Total
Score

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21

21 OF 23

22 OF 23

ATTACHMENT G

QUALITY PROGRAM REQUIREMENTS CHECKLIST


(for use as guidance during Bid Clarification)
ALL POINTS MUST BE ANSWERED

MR/PO No.

1. Vendors Inspection and Test Plan and/or Quality Plan is required for review
with bid. (Typical plan would be acceptable.)

Y / N

2. Vendors stage inspection or QC plan is required for approval within


____weeks of order placement.

Y / N

3. Vendors to submit copies of suborders for items listed as follows:

4. Design
documentation/procedures
identified
in
the
documentation scheduled are subject to review and approval.

Y / N
Contractor's

Y / N

5. Contractor reserves the right of unrestricted access to Vendors facilities for


the purpose of inspection, expediting, audit, by Contractor/Company or
nominated third party.

Y / N

6. In the event non-conformances during manufacture, Contractor is to be


notified by Vendor immediately.

Y / N

7. Vendor concession/deviation request must be made in writing using the


Contractor Standard Form.

Y / N

8. RESIDENT inspection is required


- Contractor's inspection authority
- Independent Inspection authority (if required)

Y / N

9. Alloy verification is required for CRA material

Y / N

10. Other requirements:

23 OF 23