You are on page 1of 21

WELCOME

DEBORAH M. CLARK
PRINCIPAL, MARK T. SKINNER WEST ELEMENTARY SCHOOL

REMARKS
WALTER BURNETT,
27TH WARD ALDERMAN, CITY OF CHICAGO

PROJECT PLAN
MARY DERUNTZ
CHIEF OF CAPITAL IMPROVEMENTS, CHICAGO PUBLIC SCHOOLS

Tentative Project Plan


New Annex:
15 classrooms
o 8 standard classrooms
o Diverse learner classrooms
o Pull-out spaces
o Computer lab
o Science lab
o Art room
Fully accessible to people with disabilities
Existing Campus
38 classrooms (including 5 at branch)

Sample
Site plan*

* Graphics are for illustration purposes only final design pending

Sample
Floorplan*

* Graphics are for illustration purposes only final design pending

Annex: First Floor Example*

* Graphics are for illustration purposes only final design pending

Annex: Second Floor Example*

* Graphics are for illustration purposes only final design pending

Annex: Third Floor Example*

* Graphics are for illustration purposes only final design pending

Annex: Elevations Example*

* Graphics are for illustration purposes only final design pending

Annex: Renderings Example*

* Graphics are for illustration purposes only final design pending

BUILDING DESIGN
FELICIA S. DAVIS
EXECUTIVE DIRECTOR, PUBLIC BUILDING COMMISSION

Oriole Park Elementary School Annex

Wildwood World Magnet School Annex

Classroom at Nathan Hale Elementary School Linked Annex

Science Classroom at Edgebrook Elementary School Addition

Art Classroom at Alexander Graham Bell Elementary School

Project Development Schedule


PHASE I

SITE PREPARATION

3 9 MONTHS

PHASE II

PLANNING AND DESIGN

6 9 MONTHS

PHASE III

BIDDING AND AWARD

2 MONTHS

PHASE IV

CONSTRUCTION

13 15 MONTHS

Economic Sustainability

Contract provisions:
Employment of female and minority laborers, apprentices, and journey
workers
At least 50% of the total hours worked on a project must be worked by
residents of Chicago
At least 7.5% of the total hours worked on a project must be worked by
residents of the area immediately surrounding a project
At least 26% of the total general construction contract value must be
performed by a Minority Business Enterprise (MBE)
At least 6% of the total general construction contract must be performed by
a Women Business Enterprise (WBE)
Local Business Participation requirements

Our Commitment to Community Hiring

In 2015, 3,754 people


earned over $32 million
working on PBC projects

Question & Answer Session

PBC Point of Contact


Bryant Payne
Director of Communications
312-742-0878
Bryant.Payne@cityofchicago.org