Balance Civil works Completion Schedule for Juaymah 380 kv BSP project

S.No

Item Description

Date : 30.04.2016

Start date

Finish date

Status as on 02.04.2016

1
1.1
1.2

Walkway around buildings


380kV GIS building - 94% completed and balance
230kV GIS building - 88% completed and balance

work is in progress
work is in progress

31.03.2016
31.03.2016

96% Completed.
95% Completed.

1.3

Control room buiding - 85% completed and balance

work is in progress

07.04.2016

85% Completed.

Communication duct bank and CMH/ CHH - 95% completed.

2.1

Duct bank between CMH 1 to CMH 3 - 85 % Completed.

30.03.2016

100% Completed.

2.2

Duct bank between CMH 2 to Guard house

07.04.2016

Yet to start

05.04.2016

65% completed.

3
3.1

Fire Hydrant trench - 1100 RM


Fire hydrant trench - Raft concrete - 65% Completed.

work is in progress

1000 RM raft concrete completed out of 1100 RM


3.2

Fire hydrant trench - Wall concrete - 55% Completed.

90% completed
work is in progress

20.04.2016

800 RM wall concrete completed out of 1100 RM

55% Completed.
75% completed

MV and LV duvt bank - 90% completed and balance

work is in progress

07.04.2016

90% Completed.

Pump house - room readiness.

work is in progress

20.04.2016

65% completed.

SSD 1 fence system.

work is in progress

30.04.2016

Corner 3 to 4 beam concrete 20% completed


Corner 3 to 4 post fixing work 100% completed
Corner 1 to 4 wire mesh fixing work 75% completed
Corner 1 to 2 wire mesh fixing work 15% completed

Corner 1 to 2 post fixing work 60% completed


Corner 2 to 3 beam lean preparation work in progress(Part-1)
8

Crash Barrier.

work is in progress

30.04.2016

Work is in progress

10.05.2016

207 nos completed out of 274


9

40% completed. Balance


is in progress.
75% completed. Balance
is in progress.

Base coarse laying and compaction


Base coarse laying and compaction 100% completed at part
1,2&3 area
Base coarse laying and compaction 50% completed at part 4
area

40% completed

Base coarse laying and compaction 25% completed at part 10


area
Select fill compaction in progress at part 5 area
10

Asphalt pavement for substation yard area

11

Slope protection concrete

Work is in progress

01.06.2016

22.05.2016

01% completed

30.06.2016.

0% completed