Contents
Introduction
History of Artificial Islands
Proposed Reclamation Projects in Hong Kong
The Hong Kong Zhuhai Macao Bridge (HKZMB) Project
Performance Verification
Discussion & Conclusion
Future Recommendation
Constructing Artificial Islands
Page 2
Introduction
Crannogs
Constructed in prehistoric Ireland
and Scotland.
Wooden piles were driven into
lakebed to form artificial islands.
Constructing Artificial Islands
Page 4
Tenochtitlan, Mexico
Artificial Island founded on piles of
canes covered by dirt and held in
place by stakes.
Page 7
(3) The HKLR connects the HZMB Main Bridge and the HKBCF. It includes sea viaduct, tunnel and atgrade road section along the east coast of Airport Island, which will be approx. 12km long dual 3-lane
carriageway. The HKBCF is located at an artificial island at the waters off the northeast of the HKIA,
connecting Zhuhai and Macao via the HKLR and HZMB Main Bridge. The HKBCF, which will be
approx. 150ha in area [including approx. 20ha southern landfall of the Tuen Mun - Chek Lap Kok Link
(TM-CLKL)].
Constructing Artificial Islands
Page 8
Page 9
Page 11
Page 12
Jack-up
System used
in Terminal
Page 13
Page 14
Rainbowing
Construction of Rock Break Water
The Palms
Page 15
Page 18
Sub-sea Tunnel
For construction of the HZMB Main Bridge, AECOM has been engaged by the JV
Contractors to be responsible for the PMCM work comprising a Sub-sea Tunnel of about
6.7km connected by 2 man-made islands.
The project commenced in mid-December 2010 by constructing west artificial island with
the objective that island should be completed within 20 months or shorter so that the
preparation work for the laying the first section of the IMT can be established.
Constructing Artificial Islands
Page 20
Page 21
The construction of west island is divided into two phases. The front portion where the IMT is
connected to the cut and cover tunnel would be reclaimed first.
The front portion has been reclaimed first by installing 22nos. of 22m diameter steel tubes.
The rest of the portion is installed by 45 nos. of similar tubes.
67 nos. of tubes (of 16mm thickness) have been installed in total with average depth of 41.5m,
and weigh 450 tonnes.
Constructing Artificial Islands
Page 22
Page 23
Page 24
Page 25
Page 26
Page 27
Page 28
Page 29
Page 30
Page 31
Transporting
Page 32
Installing
Page 33
Installing
Page 34
Filling
Page 35
Making Web
Page 36
Installing Web
Page 37
Installing Web
Page 38
Forming
Page 39
Forming
Page 40
Page 41
Page 42
Page 43
Page 44
Page 45
Surcharging
Page 46
Site Formation
Page 47
Site Formation
Page 48
Page 49
Installation of JGP
Page 50
Installation of JGP
Page 51
Installation of SCP
Page 52
Page 53
Page 54
Work Intensified
Page 55
Making Progress
Page 56
Making Progress
Page 57
Making Progress
Page 58
Making Progress
Page 59
Geo-matress Revetment
Containment Dyke
Page 61
Page 62
Page 63
Artificial Islands
Page 64
Page 65
Geo-matress Revetment
- Colombo South Container Terminal Project
Page 67
Page 68
Page 69
Page 70
Page 71
Page 72
Page 73
Page 74
Page 75
Filling
Page 76
Filling
Page 77
Performance Verification
Performance Verification
The verification is to apply observational method using
instrumentation.
Inclinomter and settlement plates are installed to measure
the lateral and vertical deformation for both cases.
For selective location, piezometers are installed as option
to monitor the excess pore pressure behaviour.
After more than 6 months, the completed steel tube/ sand
bag cofferdams are remained stable.
Page 79
Page 81
- Mitigation
Filled asap
Cut and erect
Install additional element
Page 82
Tilted Cofferdam
Page 83
Tilted Cofferdam
Page 84
- Mitigation
Installed asap
Site repair
Protect with armour rock
Page 85
Page 86
Page 87
Future Recommendation
Standardized with proper design and construction
procedures
By Design Code
By Performance Specification
By Material Specification
By Verification
Page 88
References
Technical Standards and Commentaries of Port and
Harbour Facilities in Japan (1999 edition),,published by
Overseas Coastal Area Development Institute
Geosynthetics and geosystem in hydraulic and coastal
engineering, krystian W pilarczyk, AA Balkema, 2000.
Page 89
Page 90
Page 91
Page 92
Page 93
Page 94
Page 95
Page 96
Thank You
February, 2013