Professional Documents
Culture Documents
Table of Content
NO
Title
Pages
Cover page
Table of Content
Introduction
3-6
Content/Technical Observation
7-23
24-28
29
This is a report on a
construction site
site visit to a
incorporating the
objectives of site visit, the introduction of the site and technical observations made on
site including the proposed learning outcome of the site visit.The report consist of the
combination of 3 subjects which are Measurement 1,Construction Technology 1 and
Building Materials.The site visit event was organized by Mrs.Ang Fuey Lin,Mrs
Azrina bt Mhd Yaakob and Mrs Aishah Kamarazaly.held on 23rd November 2016 at
IMPIAN MURNI construction site,which is located at Shah Alam,Selangor.
The development name of the construction we visited is Taman Impian Murni.It is a
project of developing 42 units of double storey terrace house and three storey terrace
house. The construction of this housing development was started from March 2016
and is expected to be completed by October 2017.The contract value of this Taman
Impian Murni construction is approximately RM 11 million.
Architect
PUCRON SDN.BHD.)
Tanck Architect
Civil&
StructuralEngineer
Mechanical & Electrical
Engineer
Contractor
Objective
The following are the purposed objective of the assignment.
1.Understand the basics of the construction process and witness the usage of
construction equipments on site including mechanical plants.
2.Explore and identify various types of building materials and technology on site.
Technical Obesrvations
We went to the site by car or carpooled and all of us gathered at the site at
9.00am that day.The project manager of this construction,Mr Lim,gave us a briefing
on some site safety procedure at first.Before entering the site,safety helmets were
provided by the contractor for each.We were divided into two groups in order to have
a visit to particular corners of the site under the guidance of contractor.
The facilities available around the site are shopping
mall,supermarket,schools,hospital and others,like restaurants,banks.
As we were entering the site,we saw a few temporary works installed at the
site.The first thing we saw was the construction site accommodation near the entrance
of the site, which means to provide workers accommodation during the construction
period.Besides,the whole construction area is fenced by vertical hoarding.The closeboarded fence is to prevent unauthorized person access to the site,and it also provides
resistance to wind loads.As we walked along,we can see bricks and blocks which
majorly used in construction of brickwall of the house being stacked in stable piles on
a level,as well as covered with the polythene sheets.Bricks were stacked close to the
site of work so that less effort was required to unload and transport the bricks again by
loading on pallets or in barrows.Scaffolding is also an important element during the
construction to provide workers accessibility to place of work.
Figure19: Falseworka
temporary framework structure
used to support a building during
its construction,for
example,supporting the column
formwork so that the formwork
does not fall.
10
Mr Lim explained to us that an architect is someone who plans,designs and
reviews the construction of buildings.They usually design the building from ground to
the top,whereas the civil engineers usually done the other way around,which
calculates the load transferred to the piles from top to bottom,but the construction is
always start from the ground to the above as well.
Foundations
Types of foundation used in this project are piling and is covered by strip
footing.
Pile foundations are deep foundations. They are typically used for large structures,
and in situations where soil is not suitable to prevent excessive settlement.Pile
foundations are formed by long cylinders typically made from steel or reinforced
concrete, or sometimes timber,pushed into the ground to act as a steady support for
structures built on top of it. There are two types of pile foundations--end bearing piles
and friction piles.End bearing piles allow the load of the building being transferred
through the pile onto the strong layer,for example a layer of strong soil or rock.On the
other hand,friction piles transfer the load of the building to the soil across the full
height of the pile by friction. Each of which works in its own way.
same time.
The project is using cast in situ method,which is the most typical and conventional
construction method,where all the concrete will be casted on the spot after
constructing the formwork and falsework at the building site.This method provides
flexibility compared to pre-cast concrete when there is geometric shapes,and the
structure will be more monolithic.There is another trending construction method
today,which is called Industrialised Building System(IBS System),where the houses
are being built like legos,as all the components are prefabricated and manufactured
either at site or off site before placing and assembling into construction
works.However,one of the challenges of using IBS System will be the requirement of
economies of skill.It requires the ability of building a lot of quantities at once,depends
on the materials and the type of IBS system used.Therefore,typical cast in situ
construction method will be more recommended for small project like this.
12
Concrete work
Figure22: The process of making concrete to be used at site.
provide thermal insulation, which protects the reinforcement bars from fire
3.
13
Figure23: Mr Lim
was explaining to
us the reason why
concrete cover
need to be
embedded in
column and beam.
the
are
beams or the columns correctly
Check theFigure25:
structuralConcrete cover
added in column.
drawings whether
reinforcement bars
placed inside the
4. Make sure all the falsework (supportive members to formwork) being placed
correctly and carefully
Reinforcement
14
Reinforcement bar
Concrete is a material that is very strong in compression and it is very hard,however,it
is vey brittle and virtually without strength in tension,which means it possess weak
tensile strength.
To strengthen the concrete structure,steel bar is used widely to act as reinforcement to
concrete.Steel is a material which strong in both compressive strength and tensile
strength,therefore steel rebar is commonly used as a tensioning devise to reinforce
concrete to help hold the concrete in a compressed state,and to help concrete
withstand tension forces.Or else,the concrete without reinforcement bars will be
cracking and breaking a lot due to the loads applied.
Figure26&27&28: Traditionally,bending of
reinforcement bars has been done using manually
powered benders with long handles to give the
required leverage. It is advantageous to modify or
fabricate it on site to suit specific needs although
most builders will prefer to have all their
reinforcing steel delivered to site pre-bent and
ready for tying into cages.
15
tension stresses in a concrete beam. The stirrup typically wraps around the bottom and
top bars of the beams.
Link has the similar function with stirrup,it is used to hold the longitudinal bars in
columns in position,preventing them from buckling outward by bursting the thin
concrete cover.
16
17
Beam
A beam is a structural member which spans horizontally between supports and carries
loads which act at right angles to the length of the beam.It transfer its loadings to
columns.When erecting the beam, the piers must be already cast in the ground.
18
Column
Column is a vertical structural element that transmits the weight of the structure
above to other structural elements below through compression.It is used to support
beams or arches on which the upper parts of walls or ceilings rest A Column transmits
the load from ceiling or roof slab and beam, including its own weight to the
foundation.
19
Concrete slab
Non-suspended slab
Non-suspended slab,or ground floor slab,sits directly on the ground,it is supported by
the ground and ground beam.
Three types of construction method of ground floor slab that we have learned so far:
Concrete slab
DPC
Hardcore
Non-suspended type--Construct
the ground beams first,means that
concrete the full depth of
beams,then the concrete slab will
go in between the ground beams
Ground beams
Suspended typeConstructing
concrete slab together with
ground beams
20
21
Bricks (Masonry)
Clay bricks are used in the wall between the houses,while cement sand bricks are used
within the houses itself .According to Malaysia bined law,fire fighting will need 2
hours.The thickness of clay bricks used in the wall between houses,which is the wall
shared between neighbours will be minimum 150mm thick,as generally clay bricks
which possess thickness of 150mm will give 120 minutes(2 hours)of fire
resistance.Cement sand bricks are less costly than clay bricks,however,they are not
suitable to use in wall between houses as the noise insulation and fire resistance of it
are not as good as clay bricks.
22
According to Mr Lim,the houses are constructed by double brick cavity wall. Double
brick cavity wall consists of two layers of brick with a cavity in between separating
the two panels of masonry bricks. Sometimes, concrete blocks are used instead of
bricks and the two panels are tied together with metal ties.The cavity may fill with
insulating material.
Double brick cavity wall reduces thermal transmission and prevents moisture being
transferred directly from the outside wall face to the interior of the building,so the
house will be warmer or cooler in the various seasons. It is also a heavier building
alternative which will require properly engineered designed foundations or concrete
slabs.
23
Appendix
24
25
Figure45&46: A
lintel is a horizontal
member which
placed across the
openings like doors
and windows.It
takes the load
coming from the
structure above it
and gives support.
Finishes
Figure53
Figure52
Figure54
Figure55
ConclusionFigure56
28
Figure57
I was excited about this site visit event since when we were informed by the
lecturers during the beginning of the semester.After visiting the construction site,there
are many valuable information and knowledge gained by me.First of all,I have a
chance to experience the life and the working environments being a Quantity
Surveyor.I realized that working at a construction site is much more difficult than I
thought,a lot of risks involved and the weather is hot usually,thus a series of
precautions must be taken to work in this type of working condition.
Besides,I also have a chance to see how several machines look like,and how do
they work.The process impressed me as I have never had the chance to see it that
close.There are different type of materials and tools available at the site too.I had
learned the construction methods used at site by the explanation of Mr Lim.This is a
totally different experience for me from just look at the relevant pictures online and
makes me to understand more about the things in the construction industry.
29