Professional Documents
Culture Documents
Description de lessai
Analyse granulomtrique
ASTM C-136
DIN EN 1097-2
Max. 35%
NF EN 1097-1
Max. 30%
DIN EN 1097-2
NF EN 1097-1
Max. 60%
colonne ballaste doit tre arrte soit la profondeur de conception, soit au refus de vibreur, selon
la premire ventualit rencontre.
Le Constructeur peut choisir la mthode dexcution, laquelle il considrera la plus approprie pour
satisfaire aux critres de performance.
A. Si la mthode dalimentation par le haut, voie humide est utiliser:
a.
The first 30 cm lift of stone is placed. The vibrator will then be lowered to the design depth
and stone will be added as necessary.
b. The vibrator will be repeatedly raised and lowered such that on each re- penetration, the
tip of the vibrator advances to within the previous penetration depth an amount to be defined
by the Contractor (e.g. 0,6 m), or refusal (whichever comes first). The vibrator will not be raised
more than 1,0 m at any time unless the stone stops flowing to the bottom of the vibrator.
For the wet installation, process water is required for jetting purposes during the installation
process. This water shall be obtained from the sea utilizing flexible pipe and suction pump.
Alternatively, Water for the vibro replacement process shall be obtained by installing well
points. The location for the installation of well points shall be provided by the Contractor.
During the stone column installation operation excess and process muddy water rises around
the vibrator from the ground to the site surface. It is normally gathered at the surface and
collected in silt ponds from where it shall be recycled to be reused for further installations of
stone columns and at the end shall be disposed during the Mud removal process.
B. If the Dry, Bottom Feed method of construction is used
a. The vibrator will be lowered to the design depth and stone delivered through hopper/by pass
system.
b. The vibrator will be repeatedly raised and lowered such that on each repenetration, the tip
advances to within the previous penetration depth a distance to be defined by the C
ontractor (e.g. 0,6 m), or refusal (whichever comes first). The vibrator will not be raised more
than 1,0 m at any time unless the stone stops flowing to the bottom of the vibrator.
C. In the case, the Dry, Bottom Feed method is used by the Contractor
Short term water jetting by lances outside the vibrator or predrilling may be necessary to assist
in penetrating localized hard layers. The Contractor shall evaluate whether water jetting and/or
predrilling aid is required to meet design requirements.
D. Tolerances:
a.
Setting out:
Setting out shall be carried out from reference lines and points defined by the owner and
indicated in the construction drawing. Immediately before installation of the stone column,
the stone column positions shall be marked with suitable identifiable pins or markers using
appropriate surveying equipment.
b. Position:
The maximum permitted deviation of the stone column center from the center point shown on
the setting out drawing shall be 150 mm.
c. Verticality:
Stone columns shall be constructed as near vertical as possible. The axis of the stone column
shall not be inclined from the vertical more than 60 mm in 3 m (2%) as indicated by the tilt of t
he vibrator and follower tubes.
E. Working Platform
Prior to the treatment execution, the working platform will be adequately set up, in order
to allow site operations and crane movements with same material of stone column. The
superficial layer will be improved with supply of coarse compacted material and made sui
table to bear the actions coming from the crane. After the treatment execution of the sto
10
ne column, the working platform shall be connected to the top of stone columns in order
to meet the anti-liquefaction design.
2.1.7 Monitoring
During the construction process the consistency of the compaction achieved shall be monitored and
recorded.
2.1.8 Documentation
On a daily basis, the records of stone column installation of the day shall be summarized on the
daily Construction summary sheet, containing additional information such as average volume of
backfill material consumed per column and total production per rig and shift. The daily record shall be
submitted to the Engineer for certification on the following working day.
2.1.9 Testing
Test shall be carried out for quality assurance measure for the working stone columns. The test
shall be carried out at Foundation level. The maximum load shall be 1.5 times the working load. The
frequency to perform the full scale load test(zone load test) shall be one in 40,000m2 area and the
individual single column test(plate load test) shall be one in 20,000m2 area.
A. Trial Tests
Trial Tests are required to validate the capability of the equipment to meet the design
assumptions (e.g. installation depth, column diameter) and to adjust the installation parameters
(e.g. lift height, re-penetration depth, etc.). The trial tests shall be located in the vicinity of the soil
investigation points. A minimum of 3 number trial tests shall be carried out at each zone
previous to commencement of stone column production. Additional trial tests may be required, if
the acceptance criteria cannot be met in these tests.
B. Stone Column Records
The installation rigs shall be equipped with automatic units in order to record continuously
depth, power consumption and current (ampere) over time. The records of each column
shall include:
a. Stone column reference number,
b. date of installation,
c. start and completion time of each treatment point,
d. power consumption during penetration,
e. current during penetration,
f. volume and weight of stone backfill in each column,
g. actual versus theoretical stone consumption (control of column diameter),
h. time
required
for installation,
flushing, compaction
and
overcoming
obstructions,
i. details of construction, delays and unexpected ground conditions,
j. depth of treatment.
C. Continuity and compaction of the column
The continuity and compaction of the column shall be controlled by in situ test such as CPT
or SPT or PMT or equivalent. The tests shall be carried out on 0,1% of randomly selected
columns, a minimum number of 5 stone columns within each zones.
D. Static Load Testing
Static load testing will consist of full scale static load test(Zone load test) and individual single
column tests(Plate load test) to be provided by the Contractor to validate design assumptions
and control specification compliance.
11
a.
The full scale load test shall be performed at an actual foundation location
chosen by the Engineer. The foundation area shall allow the test of a group of 4 columns in
the center of a group of 16 columns.
b. The load tests shall be erected, performed, and evaluated by the Contractor at
the Contractors expense.
c. The load tests will be monitored by the Owner.
d. The load tests shall be planned and executed in accordance to CFMS 2011 or ASTM
D 1196 or equivalent. The test foundation shall be loaded to 1.5 times the total load of the
group of columns. Settlements of the test foundation shall be measured halfway between the
center and each of the four corners with displacement gages having a sensitivity of 0.01
mm. The average of the four readings shall be used to confirm acceptance of the required
settlement criteria. The contractor shall submit a method statement for the load test including
a schematic plot of the test arrangement prior to load testing.
12