Professional Documents
Culture Documents
Version:
Issue Date:
Review By Date:
Owned By:
Authorised By:
1.1
August 2006
June 2008
Engineering Manager D & P
Executive Manager D & P
LINE ERECTION
REVISION TABLE
Version No
Date of Revision
1.0
June 2006
1.1
August 2006
Details of Amendment
Initial Release
Numbering changed to represent previous revision
The above table lists in summary the amendments which have been made with most recent issues of this standard.
The table is updated with each re-issue. The latest amendments within the documents are marked with a change
indicator (|) in the outer margin.
CONTACT
This standard is the responsibility of the
Development and Projects Division, ElectraNet.
Please contact the indicated owner of the standard
with any inquiries.
ElectraNet
52-55 East Terrace, Adelaide, South Australia 5000
PO Box 7096, Hutt Street Post Office,
Adelaide, South Australia 5000
Ph (08) 8404 7966, Fx (08) 8404 7104
L I M I TATI O N O F L I A B I L I T Y AN D
D I S C L A I M E R O F W AR R A N T Y
ElectraNet makes no representation or warranty as
to the accuracy, reliability, completeness or
suitability for particular purposes of the information
in this document. ElectraNet and its employees,
agents and consultants shall have no liability
(including liability to any person by reason of
negligence or negligent misstatement) for any
statements, opinions, information or matter
(expressed or implied) arising out of, contained in
or derived from or for any omissions from the
information in this document, except in so far as
liability under any statute cannot be excluded.
2006 ElectraNet Pty Limited trading as ElectraNet. No part of this document may be reproduced
or copied in any form or by any means (graphic, electronic, mechanical, including photocopying,
recording, taping or information retrieval systems) without the prior written permission of ElectraNet.
LCM24
ElectraNet
TABLE OF CONTENTS
24.1
SCOPE......................................................................................................................................................3
24.2
GENERAL...............................................................................................................................................3
24.3
24.3.1
24.3.2
24.3.3
24.3.4
GENERAL............................................................................................................................................3
CARE OF CONDUCTOR AND OPGW...................................................................................................3
DAMAGE REPAIR................................................................................................................................3
STRINGING EQUIPMENT......................................................................................................................4
24.4
24.5
24.5.1
24.5.2
24.5.3
24.5.4
24.5.5
24.5.6
24.6
GENERAL............................................................................................................................................5
ECONOMICAL USE OF CONDUCTOR....................................................................................................6
CROSSING OF OBSTRUCTIONS............................................................................................................6
RESTRICTIONS ON THE USE OF JOINTS FOR CONDUCTORS.................................................................7
TENSION STRINGING METHOD...........................................................................................................7
HANDLING OPTICAL GROUNDWIRE TAILS.........................................................................................8
SAGGING OF CONDUCTORS AND OPTICAL GROUNDWIRES (OPGW)...............................8
24.6.1
24.6.2
24.6.3
24.7
GENERAL............................................................................................................................................8
INITIAL CONDITION METHOD.............................................................................................................9
MEASUREMENT OF SAG......................................................................................................................9
INSTALLATION OF INSULATORS AND LINE FITTINGS.........................................................10
24.7.1
24.7.2
24.7.3
24.7.4
24.7.5
24.7.6
24.7.7
24.7.8
24.7.9
24.7.10
24.7.11
24.8
JOINTING COMPOUND.......................................................................................................................10
INSULATORS......................................................................................................................................10
COMPRESSION FITTINGS...................................................................................................................10
WEDGE TYPE TENSION FITTINGS.....................................................................................................11
TENSION AND SUSPENSION ASSEMBLIES..........................................................................................11
BRIDGING ASSEMBLIES.....................................................................................................................11
VIBRATION DAMPERS.......................................................................................................................12
SPACERS............................................................................................................................................12
CORONA RINGS.................................................................................................................................12
OPGW DOWN LEAD CLAMP ASSEMBLIES.......................................................................................12
BIRD DIVERTERS...............................................................................................................................12
24.8.1
24.8.2
24.8.3
24.9
24.10
EARTH BONDING...............................................................................................................................13
24.10.1
24.10.2
EARTHWIRE BONDING.......................................................................................................................13
BONDING TO OVERHEAD STEELWORK..............................................................................................13
24.1 SCOPE
This Section specifies requirements for the
installation of conductor and OPGW and
includes earthing of structures, running out,
sagging and clamping of conductor and
installation of line hardware and insulators.
Version: 1.1
Page 2 of 13
ElectraNet
LCM24
24.2 GENERAL
The Contractor shall install the necessary line
materials, including all fittings, in accordance
with this Section, using conductors, insulators
and OPGW supplied by the Superintendent as
set out in Section 2 of this Specification. All
other materials required to complete the works
shall be provided by the Contractor.
24.3 REQUIREMENTS
CONDUCTOR
STRINGING
24.3.1
FOR
General
24.3.2
Care of Conductor
and OPGW
Conductor and OPGW shall be protected from
damage at all stages of handling and
installation. In particular scratching or other
departure from the smooth surface condition
of the conductor strands shall be avoided.
Conductor and OPGW shall be handled using
only approved equipment and in such a
manner as to prevent bird caging,
overtensioning or other deformation or
damage.
Version: 1.1
24.3.3
Damage Repair
Page 3 of 13
LCM24
ElectraNet
24.3.4
Stringing
Equipment
All stringing equipment shall be suitable for
its intended use and in particular it shall meet
the requirements outlined below.
(i)
Minimum
Diameter
Sheave
(ii)
(iii)
Minimum
Sheave
Diameter
Version: 1.1
(iv)
(v)
(vi)
Tensioning
machine
bull
wheel dimensions shall be as
follows (where D is cable
diameter):
Minimum Diameter
Minimum Groove Radius
times D
Minimum Groove Depth
times D
Tensioning
machine
bull
wheel grooves shall be lined
with neoprene or other
suitable material subject to the
approval
of
the
Superintendent.
Woven wire cable hauling
grips shall be used for the
pulling out of conductor and
OPGW. Each grip shall be
attached to the pilot wire with
a swivel to permit the pilot
wire and cable to rotate
independently of each other at
all hauling tensions.
Counter weights and links
shall be applied to the OPGW
at the swivel position to stop
the OPGW from rotation when
being pulled through the
sheaves. The counter weights
and links shall be approved by
the Superintendent.
Only non-rotating type steel
pilot wires shall be used for
hauling
or
tensioning
conductor and OPGW. Nylon
or other polymer pilot ropes
may be used for hauling pilot
wires.
Hauling devices for tensioning
the conductor may be of the
Page 4 of 13
ElectraNet
LCM24
woven, preformed, bolted
clamp or sliding jaw type. The
type used shall be selected by
the Contractor with due regard
to the nature and size of the
wire to be tensioned so that no
damage or deformation of the
wires occurs during tensioning
operations.
Special precautions shall be
taken to avoid damage to the
OPGW from hauling devices.
Only those devices approved
by the OPGW manufacturer
shall be used on the OPGW.
After removal of the hauling
device, the wires in the
vicinity of the device shall be
thoroughly inspected, and any
damage shall be repaired as
directed
by
the
Superintendent.
24.4 SAFETY
PRECAUTIONS
DURING STRINGING
Minimum safety precautions as specified in
the Specification are to be observed during the
period when pilot wire, conductor and OPGW
are being run out, tensioned and finally
clamped.
For those sections of the
transmission line nominated in Section 2 of
this Specification or by Superintendent as
being subject to high induction exposure,
additional safety precautions for high
induction exposure, as detailed in the
Specification, shall be implemented. These
precautions are necessary to avoid possible
hazards to personnel caused by induction.
Notwithstanding these specified precautions,
the safety of personnel working on the line
remains the responsibility of the Contractor.
All costs associated with the implementation
of "Routine Safety Precautions" and "High
Exposure Safety Precautions, as set out in the
Specification shall be deemed to be included
in the scheduled rates for stringing.
Version: 1.1
24.5 RUN-OUT
CONDUCTORS
OPTICAL
GROUNDWIRES
(OPGW)
24.5.1
OF
AND
General
24.5.2
Economical Use of
Conductor
Whenever possible the Superintendent shall
arrange for the jointing of the OPGW on strain
or terminal structures, however, limitations in
maximum achievable drum lengths may
necessitate the location of OPGW joints on
suspension structures.
Conductor and OPGW drums shall be
positioned so as to ensure economical usage of
cable. Short lengths of conductor of more
than 30 m may be included in the line,
providing they are used as the first length from
a strain position and providing that not more
than one such length is used in any one span of
one conductor. Lengths of conductor of less
Page 5 of 13
LCM24
ElectraNet
24.5.3
Crossing
Obstructions
of
Version: 1.1
Page 6 of 13
ElectraNet
LCM24
24.5.4
Restrictions
on
the Use of Joints for
Conductors
A mid-span joint in a conductor shall be not
closer than 8m to a suspension insulator string
or closer than 30 m to a tension string to avoid
interference with vibration control equipment.
Not more than one joint shall be used in any
one conductor in any one span. A mid-span
joint shall not be located in spans crossing
railway lines. All OPGW cable shall be
brought to ground level at nominated towers
for jointing or terminating of the optical fibres.
OPGW is not suitable for mid span jointing.
Where a compression fitting is to be pulled
over a stringing sheave it shall be protected by
an approved oversleeve. The design and use
of protective oversleeves shall be subject to
the approval of the Superintendent. The
sleeves shall be numbered to aid in
identification. Protective oversleeves shall not
be pulled under tension through a structure
having a resultant conductor deviation angle
greater than 25 degrees.
Where compression fittings are required to
pass through deviation angles greater than 25
degrees, the Contractor shall submit a Work
Method to the Superintendent, in accordance
with the Specification.
24.5.5
Tension
Method
Stringing
Version: 1.1
24.5.6
Handling
Optical
Groundwire Tails
The pulling method and rigging of equipment
shall be in accordance with the manufacturer's
installation guidelines. Additional care is
required in manoeuvring the OPGW into its
final position and clipping it to the outside
face of a non-climbing tower leg.
In rigging an earthwire installation such that
the pulling bond and OPGW are routed from
the tower peak to puller/tensioner equipment
outside the body of the tower, extra care has to
be taken at the following times:
(a)
Page 7 of 13
LCM24
(b)
ElectraNet
When the OPGW tail is fed
through to its final position
outside the body of the tower
and on a non-climbing leg.
Version: 1.1
24.6 SAGGING
CONDUCTORS
OPTICAL
GROUNDWIRES
(OPGW)
24.6.1
OF
AND
General
Page 8 of 13
ElectraNet
LCM24
The temperature of the OPGW and conductor
shall be deemed to be their core temperature.
Conductor temperatures shall be measured at
their installed average elevation above ground
level while exposed to sun and wind.
Sagging shall not take place when the wind is
gusting at velocities in excess of 10 m/s (20
knots), or while it is raining.
Under no circumstances shall the conductor or
OPGW be sagged through an accumulated line
deviation angle of greater than 90 degrees
without the written approval of the
Superintendent.
No more than two nominal drum lengths or
twenty spans, whichever is the lesser, shall be
final sagged at any one time without the
written approval of the Superintendent.
24.6.2
Initial
Method
Condition
24.6.3
Measurement
Sag
of
Version: 1.1
24.7 INSTALLATION
INSULATORS
LINE FITTINGS
OF
AND
24.7.1
Jointing
Compound
The Contractor shall supply an approved
jointing compound that shall be used in all
compression joints, ball socket joints and
bolted palm joints.
Two approved jointing compounds are:
Aluminox;
Page 9 of 13
LCM24
ElectraNet
24.7.2
Insulators
Version: 1.1
24.7.3
Compression
Fittings
Mid span joints and termination fittings
supplied by the Superintendent for conductors
will be of the compression type unless
otherwise specified.
All compression joints shall be made in the
presence of the Superintendent and in
accordance
with
the
manufacturer's
recommendations and their requirements.
The inside of all compression fittings and the
exposed steel core (for ACSR) shall be
thoroughly cleaned and immediately liberally
coated with an approved jointing compound
before compression. In preparing ACSR cable
for jointing particular care shall be taken to
ensure that the steel strand of the core is not
cut or nicked by the cutting tool. The
innermost aluminium layer shall be only
partially cut and then broken off. The lay of all
the conductor strands and core shall be
maintained
during
preparation
and
compression of the joint.
The outer strands of the conductor shall be
thoroughly cleaned, then scratch-brushed
through the approved jointing compound,
ensuring the whole area is liberally coated
with the approved jointing compound, before
compression of the outer sleeve. The joint as a
whole and the line of compressions along the
outer sleeve shall be straight after
compression.
Three (3) weeks prior to commencement of
stringing, the Contractor shall make up a test
sample for each size and type of cable
requiring compression fittings. Each sample
shall consist of a length of cable; one centrally
located mid-span joint and two termination
fittings. The overall length of the assembled
sample shall be between 5.5 and 6.0 metres.
Test samples shall be produced in the presence
of the Superintendent, using dies and presses
that will be in use on the job. The samples will
be subjected to tensile and other tests by the
Superintendent at the Superintendent's cost to
verify the adequacy of the Contractor's
equipment and installation techniques. Field
joints shall be made by the Contractor in the
Page 10 of 13
ElectraNet
LCM24
same manner as the test joints unless directed
otherwise by the Superintendent.
After approval by the Superintendent, no
alteration in the method of installation or
tooling shall be made without the
Superintendents approval.
24.7.4
Wedge
Tension Fittings
Type
24.7.5
Tension
and
Suspension Assemblies
Tension and suspension assemblies shall be
assembled and erected as shown on the
Drawings.
Armour grip suspension units shall be installed
such that the ends of preformed rods do not
differ by more than 15mm.
24.7.6
Bridging
Assemblies
The Contractor shall install bridging
conductors such that the electrical clearances
as nominated by the Superintendent are
maintained. Where a bridging insulator string
is employed, the conductor length shall be
such that it exerts a positive weight
downwards on the bridging insulator string.
The bridging conductors shall hang neatly
without twists and kinks.
All metallic contact surfaces between adjacent
ceramic insulator discs shall be treated with an
approved jointing compound applied in a
manner approved by the Superintendent. The
cost of the jointing compound and its
application shall be included in the appropriate
schedule rate.
Version: 1.1
24.7.7
Vibration Dampers
24.7.8
Spacers
24.7.9
Corona Rings
24.7.10
OPGW Down Lead
Clamp Assemblies
The Contractor shall install down lead clamp
assemblies to the outside of the non-climbing
leg of the structures such that all OPGWs are
securely fastened to the structure. The
contractor is to submit a fastening method for
approval by the Superintendent, 2 weeks prior
to installation. Spacing shall be nominally 2m
between assemblies or as recommended by the
OPGW manufacturer.
24.7.11
Bird Diverters
Page 11 of 13
LCM24
installed
in
accordance
manufacturers specifications.
ElectraNet
with
24.8 CONSTRUCTION
MAINTENANCE
PROCEDURES
the
&
24.8.1
ERECTION LOADS
ON STRUCTURES
Standard construction and maintenance loads
can be provided upon request from the
Superintendent.
The contractor must ensure that rigging and
construction loads do not exceed the structure
capacity.
Where OPGW terminates on suspension
structures, the Contractor shall ensure that
longitudinal forces on the earthwire peak are
equal and opposite at all times, resulting in no
longitudinal load on the earthwire peak.
All vertical and longitudinal loads on
crossarms must be square rigged to the tower
body.
24.8.2
Engineering
Review
of
Procedures
Work
24.8.3
Live
Procedures
Line
24.9 OPTICAL
GROUNDWIRE JOINTS
AND
JOINT
ENCLOSURES
Following OPGW installation and its fixing to
the tower legs by the Contractor, the
Superintendent shall provide splicing/jointing
of all optical fibres, including the housing of
these splices/joints within a joint enclosure.
It is expected that this work will be
commenced once there are sufficient joints
available to the jointing contractor, however,
this work may not necessarily commence until
at least 75% of the OPGW sagging,
termination and clamping-in has been
completed.
On completion of the jointing contractor's
work or section of work, the Contractor (line
construction), shall position and attach all joint
enclosures and final downlead clamp
assemblies to the steel tower and shall be fully
responsible for the rectification of all and any
damage to the complete joint enclosure, its
components or parts, and the complete OPGW
cable.
The installation and final positioning shall be
in accordance with the cable manufacturer's or
supplier's instructions, and shall commence
not more than 14 days after the jointing
contractor has completed the jointing work or
section of work. All costs associated with the
installation and final positioning of the OPGW
and associated enclosures are deemed to have
been included in the scheduled rates.
24.10
EARTH BONDING
24.10.1
Earthwire bonding
Version: 1.1
Page 12 of 13
ElectraNet
LCM24
unnecessary constraint
damage to components.
of
movement
24.10.2
Bonding
overhead steelwork
or
to
Version: 1.1
Page 13 of 13