Professional Documents
Culture Documents
DATE:
STRUCTURAL MARK:
PREPARED BY:
PROJECT NAME:
CONCRETE STRENGTH
TRUCK
TIME
O.R. NO.
NO.
SLUMP (in.)
VOL. (m3)
AIR
CONTENT
(%)
REMARKS:_______________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
___________________________________________________________________________________________
_______________________________________________________
EQUIPMENT USED
SPECIFIC REQUIREMENTS
AIR (%)
THERMOMETER NO.
TEMP. (F)
SLUMP (in.)
PROJECT LOCATION:
LOCATION/GRID LINE:
CONCRETE STRENGTH:
CONCRETE
TEMP. (F)
AIR TEMP.
(F)
UNIT
WEIGHT
(lb/ft3)
NOTES
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
_______________________________________________________________________________________
____________________________________________________
SPECIFIC REQUIREMENTS
R (%)
EMP. (F)
LUMP (in.)
_____________________
QC REVIEWER
________________
DATE
M
ESTIMATED QUANTITY (m )
OTHERS
3000PSI
SPECIFY
3
SECTION/MEMBER
FOOTING/COLUMN
BEAM/SLAB
STAIRS/MISCELLANEOUS
MANPOWER
WORKERS NAME
GROUP NAME
SKILL
UNSKILL
HOURS EXPENDED
TOTAL
PREPARATION
POURING
TROWELLING
BROOMING
TORING REPORT
DATE: _______________________________
LEVEL/GRIDLINE: _____________________
POURING TIME:
START_____________
FINISH_____________
MATERIALS
ACTUAL QUANTITY (m3)
OTHERS
3000PSI
SPECIFY
OTHER MATERIALS
ITEM
UNIT
QUATITY
EQUIPMENT
EXPENDED
CURING
RETOUCH
TOTAL
DESCRIPTION
NUMBER
OPERATING
HOURS
REMARKS
FLOOR LEVEL
SECTION/ MEMBER
FOOTING
COLUMN/ WALL
FOUNDATION
BEAM/ SLAB
STAIRS/ MISC.
COLUMN/ WALL
GROUND
BEAM/ SLAB
STAIRS/ MISC.
COLUMN/ WALL
2ND LEVEL
BEAM/ SLAB
STAIRS/ MISC.
COLUMN/ WALL
3ND LEVEL
BEAM/ SLAB
STAIRS/ MISC.
COLUMN/ WALL
4ND LEVEL
BEAM/ SLAB
STAIRS/ MISC.
ESTIMATED
QUANTITY (m3)
TO DATE (m3)
TOTAL TO
REMAINING (m3)
DATE (m3)
% COMPLETE
__________
__________
REMARKS
REPORT OF ACCIDENT
TO BE COMPLETE FOR ALL ACCIDENTS, EVEN IF NO INJURIES WAS SUST
1.
2.
3.
4.
AGE
JOB CLASSIFICATION
DATE OF REPORT:______________________
CCIDENT
VEN IF NO INJURIES WAS SUSTAINED
________AM
_____________
____________
_________PM
IF INJURED
MEDICAL ATTENTION
FIRST AID GIVEN
NEEDED
_______________________________________
_______________________________________
______________________________________
____________________________________________________
___________________________________
____________________________________
__________________________________
_____________________________________
__________________________________
_______________________________________
NT/INJURY:
___________________________________
___________________________________
___________________________________
___________________________________
_______________________________________________
_______________________________________________
______________________________________________
O IS NOT NEEDED
______________________________________
______________________________________
Y IS RECORDABLE.
ESTIMATED
WEIGHT (kg)
PREVIOUS (kg)
TO-DATE (kg)
TOTAL
ISHMENT
WORKERS
TOTAL TO-DATE
(kg)
SKILLED
UNSKILLED
TOTAL
DATE: ___________________________
LEVEL/GRIDLINES: _________________
PAGE ______ OF ________
HOURS EXPENDED
SKILLED
UNSKILLED
TOTAL
REMARKS
PROJECT: _______________________________________________
PREPARED BY: ___________________________________________
BAR DESCRIPT
STRUCTURAL MARK
ITEM
DETAILS
DIAMETER
(mm)
LENGTH (mm)
BAR DESCRIPTION
GRADE
WEIGHT PER
PIECE (kg)
METHODS
NO. OF
HOOKS
MECHANIZED
NO. OF BENDS
CUTTING
EQUIPMENT
BENDING
EQUIPMENT
RK SHEET
DATE: ______________________
PAGE _______ OF _______
METHODS
OUTPUT
MANUAL
CUTTING
TOOL
BENDING
TOOL
# OF PCS.
TOTAL
WEIGHT
WORKERS
SKILL
UNSKILL
___________
WORKERS
# OF HOURS
WORK
RATE (kg/mhr)
REMARKS
PROJECT:
CONTRACT NO.:
COMPONENTS
PLANS / DESIGN
1. APPROVED CUTTING LIST AT HAND?
2. APPROVED SCHEDULE AT HAND?
3. APPROVED STRUCTURAL BODY PLANS AVAILABLE?
REBARS
BEFORE PLACING
1. BARS ARE NOT MISBENT OR DAMAGED?
2. BARS ARE FREE OF DIT, LOOSE MILL SCALE, HEAVY RUST, GREASE, OR OTHER DELETERIOUS MATERIALS
3. BAR IDENTIFICATION ARE INTACT, AND LEGIBLE
AFTER PLACING REINFORCING BAR
1. BAR DIAMETER AS PER SCHEDULE?
A. MAIN BARS
B. EXTRA TOOP BARS
C. EXTRA BOTTOM BARS
D. STIRRUPS
E. LOCATION AT SPLICE
F. SHEAR BARS AT CONSTRUCTION JOINT
2. BAR SPACING AS PER SCHEDULE (COMPLIES WITH 1. A TO F)?
3. TIES AND STIRRUPS AS PER SCHEDULE?
4. BARS ARE STABLE AND WELL SUPPORTED OR CHAIRS OR CONCRETE SPACERS?
5. CHECK THE LENGTH OF DOWELS IN ACCORDANCE WITH CODES?
6. SPLICES OF CORRECT LENGTH(S) OR STAGGERED?
7. BARS AT BEAM COLUMN JUNCTION ARE NOT CONGESTED TO PREVENT PROPER CONCRETE PLACEMENT AND
8. TRIMMER BARS AROUND SLEEVES IN PLACE?
9. TRIMMER BARS AROUND BLOCKOUTS?
10. CHAIR BARS ADEQUATE AND SET PROPERLY?
11. BARS ARE FREE OF LOOSE MORTAR, RUST, GREASE, OR OTHER SUBSTANCE CAPABLE OF DESTROYING BON
12. FIELD BENDING OR STRAIGHTENING OF REBARS IS DONE IN ACCORDANCE WITH THE SPECIFICATION?
13. REBENT OR STRAIGHTENED BARS ARE FREE OF CRACKS OR DAMAGE?
FINAL CLEAN-UP
1. SURFACE ARE AIS CLEAN AND FREE OF LOOSE CONCRETE MUD, AND DEBRIS WHICH COULD JEOPARDIZE THE
FORMWORKS
1. CORRECT SETTING OUT OF LINES AND LEVELS?
2. DIMENSION OF STRUCTURE AS PER APPROVED PLAN (EACH BEAM, COLUMN, SLAB, SHEARWALL)?
3. SUPPORTING SYSTEM AS PER APPROVED DESIGN? (FORM TIE, TURN BUCKLE)
4. PERMANENT SHORES IN POSITION AND PROPERLY FIXED BASED ON FORMWORKS PLAN?
5. SHORING SET ON FIRM LEVEL BASE?
6. SCREW JACKS ARE NOT OVER EXTENDED?
7. FORMWORK SIDES AND SCAFFOLDING ARE ADEQUATELY BRACED?
8. IS FORMWORK JOINTS & SEAMS TIGHT AGAINST GROUT LEAK AND PROPERLY SEALED?
9. CORRECT LOCATION(S) AND SIZE(S) OF OPENING(S) IN FORMWORK (BLOCKOUT)?
10. IS POURING AREA CLEAN AND SEROJO AREA PROVIDED?
11. CONCRETE COVER SPACER ADEQUATELY PROVIDED?
12. CORRECT PLUMBNESS, FLATNESS, & SPACING OF PROPS?
13. CAMBER/SLOPE PER STRUCTURAL NOTES?
THIS RECORD HAS BEEN CLOSED ON DATE:
DISTRIBUTION
DATE SUBMMITED:
BUILDING AREA/LEVEL:
INSPECTION DATE:
GRIDLINE/AXES:
WORK LOCATION:
ACCEPTED
COMPONENTS
YES
E?
BEFORE PLACING
H 1. A TO F)?
E WITH CODES?
D?
NGESTED TO PREVENT PROPER CONCRETE PLACEMENT AND VIBRSTION? (NOT LESS THAN ONE INCH)
ONCRETE MUD, AND DEBRIS WHICH COULD JEOPARDIZE THE QUALITY OF STRUCTURE.
QUATELY BRACED?
OVIDED?
DED?
F PROPS?
REMARKS:
INSPECTED BY:
VERIFIED BY:
DRME - QA/QC
INSPECTION DATE:
CHECKLIST NO. :
ICS______
WORK LOCATION:
ACCEPTED
NO
INSPECTION TIME:
IN-CHARGE BUILDING
ONSTRUCTION
REVIEWED BY:
FORM NO.:
ME - Project Engineer
CHECKLIST
PROJECT:
CONTRACT NO.:
DATE SUBMMITED:
BUILDING AREA/LEVEL:
GRIDLINE/AXES:
COMPONENTS
REMARKS:
INSPECTED BY:
DRME - QA/QC
DISTRIBUTION
VERIFIED BY:
HECKLIST
INSPECTION DATE:
CHECKLIST NO. :
FORM NO.:
ICS______
WORK LOCATION:
ACCEPTED
YES
NO
INSPECTION TIME:
CORRECTIVE ACTION
TO BE TAKEN ON
(TARGET DATE)
N/A
FIED BY:
REVIEWED BY:
PROJECT:
CONTRACT NO.:
COMPONENTS
PLUMBING/ SANITARY:
4. SEWER and DRAINAGE LAYOUT
5. WATER SYSTEM LAYOUT
MECHANICAL:
6. HEATING
7. VENTILATION
8. AIR CONDITIONING
FIRE PROTECTION:
9. SPRINKLER SYSTEM (N/A)
, ACCU)
ergency)
CHECKLIST
DATE SUBMMITED:
BUILDING AREA/LEVEL:
INSPECTION DATE:
GRIDLINE/AXES:
WORK LOCATION:
ACCEPTED
COMPONENTS
YES
REMARKS:
CHECKED BY:
VERIFIED BY:
DRME - QA/QC
INSPECTION DATE:
WORK LOCATION:
ACCEPTED
NO
CHECKLIST NO. :
ICS______
INSPECTION TIME:
FLI - INSPECTION
N/A
LDING CONSTRUCTION
REVIEWED BY:
FORM NO.:
REWORK RECORD NO.:
REMARKS
INSPECTED BY:
FLI - Engineer
PROJECT:
RESIDENTIAL CONDOMINIUM BLDG. 1
PROJECT LOCATION:
CONTRACT NO.:
KEMBALI COAST
2016 - 00191
WORK LOCATION:
STRUCTURAL FOUNDATION
WORK ITEM (DEFINEABLE FEATURE OF WORK)
1 UNIT F-4
2 UNIT
F-1
TECHNICAL DATA
DESIGN MIX
O ORDINARY
SLUMP (in):
1ST
1
O 19mm or 3/4"
PLACEMENT METHOD:
(CHECK)
O DIRECT
METHOD OF CURRING:
(CHECK)
O PONDING
2ND_______
______ BATCH
3RD_______
4TH___
O 10mm or 3/8
O BUGGY
O PUMP
O CONTINUOUS SPRINKLING
O CRANE & BU
O ABSORP
ATTACHMENTS:
DISCIPLINE
N.A.
REBAR
N.A.
FORMWORKS
N.A.
MECHANICAL
N.A.
ELECTRICAL
N.A.
AUXILIARY
N.A.
FDAS/BMS
N.A.
PLUMBING/SANITARY
N.A.
FIRE PROTECTION
N.A.
ARCHITECTURAL
N.A.
PRECAST
N.A.
SAFETY
N.A.
OTHERS
N.A.
PERMITTING: BASED ON THE RECOMMENDATIONS OF THE ABOVE PERSONNEL, HAVING VERIFIED AND CERTIFIED
DRAWINGS AND MATERIALS COMPLY WITH THE LATEST APPROVAL PLANS AND SPECIFICATIONS OF THE SAID AC
SUBMITTED BY:
DRME-PROJECT IN CHARGE/MEPF
APPROVED BY:
FLI - Project Engineer
IMPORTANT NOTE:
CONCRETE POURING
DATE PREPARED:
REQUEST NO.
28-Jun-16
DRME
DRME
GRIDLINE/AXES:
FLOOR LEVEL
FOUNDATION
PLANNED
QUANTITY(m3): 3.35
DATE: JUNE 28, 2016
TIME: 5:00 PM
ACTUAL
QUANTITY (m3): 3.5
DATE: JUNE 28, 2016
TIME: 5:15 PM
SPECIFIED CONCRETE STRENGHT: 3000PSI
ESIGN)
3RD_______
4TH_______
UMP
RINKLING
O OTHERs___________________
N.A.
N.A.
N.A.
N.A.
N.A.
N.A.
FLI
N.A.
N.A.
NG VERIFIED AND CERTIFIED THAT OTHER WORKS IN THE AREA WIL NOT CONFLICT WITH THE WORK REQUESTED AND THAT SHOP
IFICATIONS OF THE SAID ACTIVITY/WORK ITEM HEREBY RECOMMENDS:
O APPROVAL
O DISAPPROVAL
NAME
SIGNATURE
FORM NO.
1
(QA/QC):
RENGHT: 3000PSI
JUNE 26, 2016
CKS: 1
IT TRANSIT MIXER,
R
REMARKS
DATE/TIME