You are on page 1of 21

ATTACHMENT 4

SCOPE OF JOB & TECHNICAL SPECIFICATIONS

(TENDER ENQUIRY NO- 11000014 HB 12350 dated: 09-09-2011)


1.0 SCOPE:
The scope of work is defined in detail under the schedule of quantities & technical
specifications. The various facilities covered under the scope of this tender are detailed
below. However the scope specified below is only indicative but not exhaustive and the
vendor is required to carryout any other scope as per the site requirement within the
items available under this tender. The works to be performed under this tender enquiry
consists of providing all labour, materials including cement and steel, scaffolding,
construction equipment, tools and plants, supplies, transportation, all incidental items
not shown or specified, but reasonably implied or necessary for successful completion
of work including Contractors supervision and in strict accordance with the drawings
and specifications.
a.
b.
c.
d.

Construction of Un-course Rubble Masonry Boundary Wall


Providing & Fixing 600 mm Concertina Barbed Razor Wire on the top of boundary wall
Painting of Boundary Wall
Supply, Fabricate & Fixing Entrance Gate (03 Nos)

1. I) SEQUENCE OF JOB:
A) FOR CONSTRUCTION UNCOURSED RUBBLE MASONRY WALL:
A. 1. CLEARING/EXCAVATION:
Excavation to grade and level up to a maximum depth of 2.0 meter below existing ground level
in any type of soil including hard rock. Rate to include clearing of site of any obstruction, grass,
shrubs of any vegetation bailing out of water etc. Dressing the sides and preparing bottom to all
grade and level. All excavated materials to be carted away to an unobjectionable place inside/
outside the plant premises within a lead up to 0.5 km and as directed at site.
A. 2. PLAIN CEMENT CONCRETE - M10 (1: 3: 6) FOR FOUNDATION & BEDDING
Supply, providing, mixing and placing in position CC 1: 3: 6 (M20) for any thickness as per
specifications with 20 mm down grade coarse aggregates including providing and fixing of
suitable shuttering, scaffolding, machine/hand mixing as the case may be, vibrating, curing for at
least 14 days. Concrete shall conform to IS 456 1978. Cost of shuttering to be included in the
rate.
A. 3. IN-SITU CEMENT CONCRETE M20 (1: 1.5: 3) FOR RCC BEAM / FOUNDATION
Supply, providing, machine mixing and placing in position etc. in situ Cement Concrete (M20)
(1:1.5:3) using downgraded crushed aggregates. Job also includes providing and fixing
shuttering, machine/hand mixing, compacting, curing etc. complete. Concreting to be done as
per IS 456 and as per attached specifications and drawings.
A. 4. STEEL REINFORCEMENT:
Supply, providing, cutting, bending, placing in positions with necessary cover blocks, tying with
wire (including providing 16 gauge annealed binding wire) steel reinforcement as per drawings,

Page 1 of 21

specifications & as directed by Engineer in charge complete. Rods to be supplied shall be


HIGH YIELD STRENGTH DEFORMED (HYSD) TMT (THERMO MECJANICALLY TREATED)
BARS conforming to IS 1786 (Latest Revision) Steel bars sizes will be of dia 12 mm to 8 mm.
payment shall be made as per theoretical weights including all authorized hooks and laps. The
rate shall be applicable for any height & depth.
A.5. UNCOURSED RUBBLE MASONRY:
Providing un-coursed rubble masonry of trap stone in Cement Mortar 1:6 in plinth and wall
including racking of joints when plastering is to be done / striking out joints, watering &
scaffolding etc. Complete.
A.6. CEMENT POINTING:
Providing flush pointing with Cement Mortar 1:3 to stone masonry including scaffolding & curing
etc. complete.
B) FOR CONCERTINA BARBED RAZOR WIRE:
B.1 Supply & fixing of 600 m dia hot dip galvanized barbed razor tape concertina coil fencing.
The same shall be tied using FIVE lines of straight razor runner wires to Y angles at sides and
bottom, one at the Top and one at middle with U nails, clips etc.
B.2 Supply , fabrication, erection & painting of structural steel work for Y angles on top of
compound wall including the cost of all labour, material, equipment complete as per
specifications, approved drawings and as directed by engineer-in-charge.
C) PAINTING OF BOUNDRY WALL:
C.1 Painting of Compound wall with SNOWCEM Cement Paint externally as well as internally as
per the specifications & instructions given by Officer-in-charge.
D) SUPPLY, FABRICATE & FIXING OF ENTRANCE GATE:
D.1 Supply, fabricate & fixing of Main Gate (03 nos) as per drawing using MS pipes, plates, bars
etc including cutting, welding, fixing with hinges, rollers, locking arrangement, aligning,
balancing for smooth operation, grouting the hinges in the RCC column etc complete. The gate
shall be finished with two coats of enamel paint / aluminum paint over two coats of Zinc
Chromate primer after due cleaning , grinding to get smooth surface after welding etc complete.
2.0 General:
Specifications of materials and workmanship shall be as described in the Central Public
Works Department Specifications including amendments, unless otherwise specified.
These CPWD specifications shall be deemed to form part of this contract. The
Contractor shall procure and maintain copies of the CPWD specifications at site for
reference.
These particular specifications shall be supplementary to the specifications contained in
the CPWD specifications, where at variance, these particular specifications shall take
precedence over the provisions in the CPWD specifications.
Wherever IS specifications, codes of practice are specified in the specifications,
reference shall be to the latest edition.

Page 2 of 21

2.1

Site Clearing:

Site clearing means cutting bushes, shrubs, etc and pulling out of roots and stumps to
effect general cleaning of the site area. All these materials shall be removed from the
site area at the bidders expenses and responsibility. Trees, bushes, roots, stumps and
other materials shall not be disposed off by burning within the site boundaries unless
the Owner / Engineer-in-charge permits.
For work(s) where no specification is laid down in the contract as aforesaid, such
work(s) shall be carried out in accordance with the specifications decided by the
Engineer-in-charge.
2.2

Earthwork:

2.2.1

Examination of site:

The Contractor shall visit and ascertain the nature of the ground to be excavated
and work to be done and shall accept all responsibility for the cost of the work
involved.

2.2.2

Ground level and site level:

Before starting the excavation the requisite block level of the area shall be taken by
the Contractor at 5 m interval in consultation with the Engineer-in-charge and a
proper record of these levels kept which shall be jointly signed by the Contractor and
the Engineer-in-charge. A block level plan showing all levels of the plot shall be
prepared by the Contractor and shall jointly be signed by the Contractor and the
Engineer-in-charge.

2.2.3

Excavation:

Excavation shall be carried out in soil / existing RCC / asphalted road of any nature and
consistency in the presence of water or in the dry, met on the site, to the lines, levels
and contours shown on the detailed drawings and bidder shall remove all excavated
materials on site or transport for use in filling on the site or stack them for reuse as
directed by the Engineer-in-charge.
In case of trenches exceeding 2 m depth or where the soil is soft or slushy, the sides of
trenches shall be protected by timbering and shoring. The contractor shall be
responsible to take all necessary steps to prevent the sides of trenches from caving in
or collapsing.
The extent and type of timbering and shoring shall be as directed by the Engineer-incharge.

Page 3 of 21

Where the excavation is to be carried out below the foundation level of adjacent
structure, the precautions to be taken such as underpinning, shoring and strutting, etc
shall be determined by the Engineer-in-charge. No excavation shall be done unless
such precautionary measures are carried out as per the directions of Engineer-incharge.
Bidder will do all necessary dewatering as required to carry out proper excavation work
by bailing or pumping out water. Bidder shall arrange at his own cost for special
dewatering measures such as well point dewatering, deep well pumping, diaphragm
walling or any other approved dewatering method if the same is considered necessary.
Bidder shall provide suitable draining arrangements to prevent surface water from
entering the foundation pits at his own cost.
The bidder is forbidden to commence the construction of structures or to carry out
concreting before the Owner / Engineer-in-charge has inspected and accepted
excavation bottom.
2.3

Filling:

No excavation of foundation shall be filled in or covered up until all measurements of


excavations, masonry, concrete and other works below ground level are jointly
recorded.
All surplus excavated earth shall be disposed outside HPCLs premises at an
unobjectionable place as per the local statutory requirements.
Back filling of excavations in trenches, foundations and elsewhere shall consist of
one of the following materials approved by the Engineer-in-charge.

i)

Soil.

ii)

Sand

iii)

Moorum

iv)

Hardcore

v)

Stone/gravel.

Black cotton and other expansive or unsuitable soils shall not be used for filling in
foundations and plinths of buildings or in other structures including manholes, septic

Page 4 of 21

tanks, etc and shall be disposed off within the plant area marked on the drawings as
directed, leveled and neatly dressed.
All back filling materials shall be approved by the Engineer-in-charge.
2.3.1 Soil filling:
Soil material shall be free from rubbish, roots, hard lumps and any other foreign organic
materials.
Back filling around completed foundations, structures, trenches and in plinth shall be
done to the lines and levels shown in the drawings.

Filling shall be done in layers and thickness of each layer shall not exceed 15 cm with
watering and shall be compacted to obtain 95 % maximum dry density as per IS: 2720
(Part 8).
2.3.2

Sand filling:

Sand for filling under foundation concrete, around foundation and in plinth, etc shall be
fine or coarse, strong, clean, free from dust, organic and deleterious matter. Sand
material shall be approved by the Engineer-in-charge.

2.3.3

Moorum filling:

Moorum for filling, where ordered, shall be obtained from pits and quarries which
contain silicious material and natural mixture of clay. Moorum shall not contain any
admixture of ordinary earth. Size of moorum shall vary from dust to 40 mm guage.
Moorum filling shall be done in a manner similar to earth filling. The surface shall be
flooded with water, for at least 24 hours, surface allowed to dry and then compacted
and dressed to the required level grade or slope.
2.3.4

Hardcore filling:

Hardcore shall be of gravel stone of 90 mm and down size suitable for providing a
dense and compact sub- grade. Stones shall be sound, free from flakes, dust and
other impurities. Hard core filling shall be spread and leveled in layers, 15 cm thick,
watered and well compacted with ramming or with mechanical hand compacts or by
road roller.

Page 5 of 21

2.3.5

Stone / Gravel filling:

Stone filling shall be such that size of stone fragments shall not exceed 20 cm. The
contractor shall fill in all gaps between blocks with graded granular material only. The
contractor shall spread the larger size rock fragments uniformly in the lower part of the
fill and keep these with a size less than 10 cm for the upper layers.
The contractor shall carry out the fill embankments with smooth, finished slopes, with
well shaped and aligned edges. For this purpose he shall perform, during the execution
and up to the time of handing over, the necessary refilling or cutting, trimming and
grading of slopes and berms as required.
Consolidation of fill by water flooding or water jetting shall not be used unless specified
written approval is obtained from the Engineer-in-charge.
3.0 CONCRETE WORK
3.1 Materials:
All materials shall be of approved quality
3.1.1

Cement:

Cement shall be ordinary Portland cement 43 / 53 grade conforming to IS: 8112. / IS:
12269.
3.1.2

Water:

Water used for mixing and curing concrete and mortar shall conform to the
requirements laid down in IS: 456.
3.1.3

Aggregates:

A coarse and fine aggregate for cement concrete, plain and reinforced shall conform to
the requirements of IS: 383. Before testing, the aggregates shall be tested as per IS:
2386 (relevant part).
Coarse aggregate for all cement concrete work shall be crushed stone from approved
quarries and satisfy the following requirements:
a)

Aggregate crushing value or aggregate impact value shall not exceed 45 %.

b)

Aggregate abrasion value shall not exceed 50%.

Page 6 of 21

c)

The maximum quantity of deleterious material shall not exceed the limits laid
down in IS:383 Table 1.

d)

Grading shall fall within the limits stated in IS:383 Table 2 for the respective
nominal size.

3.1.4

Sand:

Fine aggregate for concrete work shall be coarse sand from approved sources. Grading
of coarse sand shall be within grading zones I , II or III laid down in IS:383 Table-4.
3.1.5

Proportioning:

Mixes of cement concrete shall be as specified. Where the concrete is specified by


grade, it shall be prepared by mixing cement, sand and fine aggregate by weight as per
mix design. In case the concrete is specified as volumetric mix, then dry volume
batching shall be done, making proper allowances for dampness in aggregates and
bulking in sand. Equivalent volume batching for concrete specified by grade may be
allowed by the Engineer-in-charge at his discretion.
3.1.6

Mixing:

All cement concrete, plain or reinforced, shall be machine mixed. Mixing by hand may
be employed where quantity of concrete involved is small, with the specific prior
permission of the Engineer-in-charge.
3.1.7

Water Cement ratio:

Once a mix, including its water cement ratio, has been determined and specified for use
by the Engineer-in-charge, that water cement ratio shall be maintained.
3.1.8 Laying:
Concreting shall be commenced only after the Engineer-in charge has inspected and
passed the sub base / base or the centering, shuttering and reinforcement. Concrete in
slab beams, columns, footings, etc shall be laid gently in layers not exceeding 15 cm
and shall be properly consolidated by means of approved mechanical vibrators.
3.1.9

Curing:

After the concrete has begun to harden, it shall be protected with moist gunny bags ,
sand or any other materials approved by the Engineer-in-charge against quick drying.
After 24 hours of laying concrete, the surface shall be cured by flooding with water or by
covering with wet absorbent materials for 7 days.

Page 7 of 21

Approved curing compounds may be used in lieu of moist curing with the permission of
the Engineer-in-charge. Such compounds shall be applied to all exposed surfaces of the
concrete as soon as possible after the concrete has set.
3.1.10 Water tightness of concrete:
The concrete shall be made water tight / leak proof without the addition of any
admixture. However, the use of admixtures shall be permitted with the approval of the
Engineer-in-charge. These shall be in conformity with IS: 2645 and shall be used as per
the manufacturers specifications and the directions of the Engineer-in-charge. The
contractor shall produce test certificates from recognized laboratories before use of
admixtures. Admixtures containing calcium chloride shall not be used.
3.1.11 Design mix of concrete:
At the time of tendering, the bidder, after taking in to account the type of aggregates,
plant and the method of laying he intends to use, shall allow in his tender for the design
mix i.e, aggregate - cement and water cement ratios which he considers will achieve
the strength requirements specified and workability for concrete to be properly finished.
Soon after the bidder gets order to commence the work, he shall carry out preliminary
tests for design mix on trial mixes proposed by him to satisfy the Engineer-in-charge
that the characteristic strength specified below is obtained. Owner may ask the bidder
to get mix design done through any approved reputed institution and bidder shall
arrange the same at his own cost. Nothing extra shall be paid on this account. The
concrete mix to be actually used shall be in accordance with IS 456 and as approved by
the Engineer-in-charge.
Grade Specified

Characteristic
Compressive
strength at 28 days ( N / mm2)

M 10

10 (100 Kg / cm2)

M - 20

20 (200 Kg / cm2)

The minimum consumption of cement irrespective of design mix shall not be less than
that specified in IS:456. i.e Minimum 8 bags (each bag shall be of 50 kg) for M20
(1:1.5:3) Grade of & 5.2 bags for M10 (1:3:6) Grade.
Notwithstanding the above , the following shall be the maximum combined weight of
coarse and fine aggregate as per 50 kg of cement.

Page 8 of 21

Grade of concrete

M 10
M 20

Maximum weight of fine


and coarse aggregate
together per 50 kg of
cement ( for nominal mix
)
450 kg .
250 kg .

The workability of concrete produced shall be adequate, so that the concrete can
be properly placed and compacted. The slump shall be as per IS:456.
Sieve analysis of the aggregates shall be carried out at least once a day by the
contractor without any extra charge and the results shall be recorded.
All tests in support of mix design shall be maintained as a part of records of the
contract. Test cubes for mix design and works tests shall be prepared by the contractor
under his own arrangements and at his costs but under the supervision of the Engineerin-Charge.
3.1.12 Testing of Concrete:
Testing of Concrete, sampling and acceptance criteria shall be in accordance with
IS:456.
A slump test shall be taken at each mixer at least once in every fifty batches mixed.
Any batch for which a slump test is being made shall not be transferred to the place of
laying until the slump test has been completed. Any batch, which gives a slump in
excess of, that described at the time of preliminary tests shall be rejected and removed
from the site.
At least six cubes shall be taken for every 15 cu.m of concrete or part thereof deposited
in the work on any day. Three cubes shall be tested for 7 and 28 days strength.
3.1.13 Protection of the Concrete:
All concrete shall be protected from damage by rain or by workmen, equipment, over
load or any other causes. All edges, corners and projections of concrete members
likely to be damaged, shall be protected by means of wooden cover fillets.
3.1.14 Construction Joints:
Construction joints shall be made only where shown on the drawings or as approved by
the Engineer-in-Charge.
guidance.

Page 9 of 21

The procedure given in IS:456 shall be followed for general

3.1.15 Damp Proof Courses:


Damp proof course shall consist of cement concrete or RCC of specified proportions
and thickness. Surface of brick or stone masonry shall be leveled and prepared before
laying the cement concrete.
Sampling of concrete shall be as stipulated in IS-456.
Samples from fresh concrete shall be taken as per IS:1199 and cubes shall be made,
cured and tested at 7 & 28 days in accordance with IS:516.
3.1.16 Testing of building materials:
The Contractor shall carry out the following tests at his own expense and as directed by
the Engineer-in-charge. Engineer-in-charge reserves their right to ask the Contractor to
carry out any further tests on any material which is being used in the project.
3.1.17 Sands:
Coarse sand conform to grading zones I and II of IS:383. Fine sand shall conform to
grading zones III & IV of IS: 383.
Tests to be conducted are
a.

Particle size Lab.

b.

Silt content - Field.

c.

Bulking of sand Field.

IS code for material IS: 383.


IS code for testing IS: 2386 (Part I) to IS: 2386 (Part VIII).
Periodicity of testing:

Whenever there is a change in source of supply or as

directed by the Engineer-in-charge.


Remarks:
1. Silt content should not exceed 8%.
3.1.18 Coarse Aggregate:
Tests to be conducted
a.

Percentage of soft deleterious Field (Visual).

Periodicity of testing.
Tests to be repeated for every 45 cum or part thereof.
Remarks.

Page 10 of 21

For the percentage of soft deleterious materials usually visual inspection shall be
carried out. If Engineer-in-charge desires , the same may be tested in an approved
laboratory.
The following material will be tested and given to the Contractor if suitable for
construction.
3.1.19 Acceptance criterion for concrete work:
Minimum of six samples cubes shall be taken for all concreting work and three cubes
shall be tested after seven days curing and balance after 28 days curing if found
necessary.
3.1.20 Seven days test:
The average strength of the three specimen shall be accepted as the compressive
strength of the concrete provided that the difference between maximum and minimum
strength of the three cubes does not exceed 15% of average strength. If the difference
exceeds 15% of the average strength, 28 days test shall be carried out.
In case the 7 days strength is not satisfactory all further work structurally interlinked with
the concrete represented by the samples shall be stopped till the remaining three cubes
are tested for 28 days strength and are found satisfactory.
3.1.21- 28 day test:
The tests should generally be carried out on 28th day but in no case should be delayed
beyond 35 days. The strengths of the cubes shall be as specified in table if they are
tested on the 28th day. In case if the cubes are tested after 28 days , the minimum
acceptable compressive strength shall be increased by 1.5 kg/cm2 for each day beyond
28th day.
The acceptance criteria of 28 days shall be as follows:
a)

If the average compressive strength of the three cubes is more than or equal to
the compressive strength shown in the table, the concrete shall be accepted at
full rates.

b)

If the average compressive strength of the three cubes is less than specified, but
not less than 75% of the specified strength, the concrete shall be accepted at
reduced rates at the discretion of Engineer-in-charge. The reduced rate shall be
calculated on proportionate basis, i.e for every percent decrease in the specified
strength the rate shall be reduced by the same percentage.

Page 11 of 21

c)

If the average compressive strength of the three cubes is less than 75% of the
specified strength , Engineer-in-charge shall either reject the defective portion or
get it dismantled along with the structurally connected work as considered
necessary at the risk and cost of the Contractor. Engineer-in-charge may also
desire to carry out additional tests on the defective work and if on the basis of
these additional tests , Engineer-in-charge is satisfied about the structural
adequacy of the concrete , the concrete work may be accepted at the reduced
rate as specified in (b) above except , for the reduced strength below 75 % for
which the reduction shall be 1.5 times for every percent decrease below 75%.

3.1.22 Steel reinforcement


Steel reinforcement shall comprise:
a)

Mild steel bars conforming to IS:432

b)

High yield strength deformed bars conforming to IS:1786

c)

Hard drawn steel wire fabric conforming to IS:1566

d)

Dowel Bars conforming to IS: 432

All joints in reinforcement shall be lapped adequately to develop the full strength of the
reinforcement as per provision of IS: 456 or as per instruction of Engineer-in-charge.
MS round bars shall be hooked at ends as specified. Ribbed Tor steel shall be bent at
right angles at ends as indicated or directed.

!"
%

#
!" &

3.1.23 welding of tor steel reinforcement bars:


Welding of tor steel reinforcement bars shall be taken up only after specific approval by
engineer in charge.
Lap welding with longitudinal beads shall only be adopted.
The thickness of weld bead should be 0.2 x diameter of bar and the length of the
longitudinal bead required shall be 10xdiameter of bar, however the maximum length of
the continuous bead shall be limited to 5 x diameter of the bar with intermediate gap.
When welding is done on both sides bead length shall be 5 x diameter of bar on each
side.
Stirrups at closer spacing shall be provided in the lap welded joints as directed by
Engineer-in-charge.

Page 12 of 21

3.1.24 Formwork:
The shuttering or form work shall conform to the shape, lines and dimensions as shown
in the drawings and shall be so constructed as to remain sufficiently rigid during placing
and compacting of the concrete and shall be sufficiently tight to, prevent loss of liquid
from the concrete. The surface that becomes exposed on the removal of forms shall be
examined by Engineer-in-Charge or his authorized representative before any defects
are made good. Work that has sagged or bulged out, or contains honey combing, shall
be rejected. All shuttering shall be plywood or steel.
The contractor shall be responsible for sufficiency and adequacy of all formwork.
Centering and formwork shall be approved by the Engineer-in-Charge, before placing of
reinforcement and concreting.
3.1.25 Stripping time:
Forms shall not be struck until the concrete has reached a strength at least twice and
stress to which the concrete may be subjected at the time of removal of formwork. The
strength referred to shall be that of concrete using the same cement and aggregates,
with the same proportions and cured under conditions of temperature and moisture
similar to those existing on the work. Where possible, the formwork shall be left longer
as it would assist the curing.
Note 1: In normal circumstances and where ordinary Portland cement is used, forms
may generally be removed as stipulated in IS-456.
4. UNCOURSED RUBBLE (UCR) MASONRY:
UCR Masonry shall be carried out for foundation, plinth & superstructure (wall above
ground level) Rubble stone for un-coursed masonry work shall be carried out using
approved trap / basalt / granite and shall be hard, tough, sound, durable, dense, clean,
of close texture and free from unsound material, cracks, decay and weathering. Water
absorption when tested as per IS standards shall not be more than 5%.
Size of Stone:
Normally stone used should be small enough to be lifted and placed in position by hand. The
length of stone shall not exceed three times the height, and the breadth on base shall not be
greater than of the thickness of wall, but not less than 15 cm. The height of stone may be up
to 30 cms.
Dressing :
Stone shall be hammer dressed on faces, the sides and the beds, to enable it to come into close
proximity with the neighboring stone. The bushing in the face shall not project more than 40
mm on exposed faces and 10 mm on a face to be plastered.

Page 13 of 21

4.1 MORTAR:
The Rubble Masonry shall be carried out in Cement Mortar 1:6. The Mortar for rubble Masonry
shall be prepared as per IS: 2250. Guage boxes for the sand shall be of such dimensions that
one complete bag of cement containing 50 kgs of cement forms one unit. The sand used shall
be free from clay, shale, loam, alkali and organic matter and shall be of sound, hard,
clean and durable particles. Sand shall be approved by Engineer. It shall be thoroughly
washed until it is free from any contamination.
For preparing cement mortar, the ingredients shall first be mixed thoroughly in dry condition.
Water shall then be added and mixing continued to give a uniform mix of required consistency.
The mixed mortar shall be used within 25 minutes of mixing Mortar left unused beyond
25 minutes shall be not be used & rejected.
The Contractor shall arrange for test on mortar sample, if so directed by the ENGINEER. Retempering of the mortar will not be permitted.
4.2 WORKMANSHIP:
Workmanship shall confirm to I.S. 1597 (Part 1): 1992
4.2.1 Laying:
All stone shall be wetted before use. The base or bed shall be prepared before commencing
masonry. The cement mortar of specified mix shall be spread over the base of minimum
thickness 20mm. Every stone shall be carefully fitted to the adjacent stone so as to form neat
and close joints. The bushing more than 40mm for random masonry may be knocked off. The
hearting or interior filling of wall shall consist of rubble stones which may be of any shape but
shall not pass through a circular ring of 150mm inner diameter. The thickness of these stones in
any direction shall not be less than 100mm. This stone shall be carefully laid, hammered down
with wooden mallet, into position and solidly bedded in mortar, chips and spalls of stone being
used, wherever necessary to avoid thick mortar beds or joints. The header stone shall be
provided and paint marked H on exposed face. The wall shall be constructed in true plumb and
shall be roughly brought to the same level all along the construction of wall and where
permitted, stepping shall not exceed one metre height at an angle of 450.
4.2.2 Bond Stones :
Bond or through stones shall be laid right through the thickness of walls. At least one bond
stone or a set of bond stones shall be provided for every 0.50 m2 of the wall surface. All bond
stones in stone masonry shall be marked suitably as directed by the Engineer-in-Charge. In
case the wall thickness is less than or equal to 60 cm., single through stone shall be provided. In
case the wall thickness exceeds 60 cm., a set of two or more through stones overlapping each
other by at least 15 cm. shall be provided in a line from face to back. Where bond stone of
suitable length is not available, cement concrete block of 1:3:6 (nominal mix) shall be used at no
extra cost.
4.2.3 Quoins:
The quoins shall be of selected stones neatly dressed with the hammer or chisel to form the
required angle, and laid header and stretcher alternately.
4.2.4 Joints :
Stones shall be so laid that all joints are fully packed with mortar and chips. The face joints shall
not be more than 20 mm thick. Where plastering or pointing is not required, the joints shall be
struck flush and finished at the time of laying only. Otherwise the joints shall be raked to

Page 14 of 21

minimum depth of 20 mm by raking tools, during the progress of work, when the mortar is still
green.
4.2.5 Scaffolding:
For rubble masonry, single scaffolding shall be permitted. If required, additional one set of
vertical support may be allowed. The support shall be sound and strong, tied together by
horizontal pieces, over which the scaffolding plank shall be fixed. The inner end of horizontal
scaffolding member may rest in holes provided in the masonry. However, no holes shall be
allowed in piller under one metre in width or near skew back of arches. The holes left in
masonry work for supporting scaffolding shall be filled and made good with cement concrete
1:3:6 (nominal mix).
4.2.6 Curing:
Masonry work shall be kept constantly moist on all faces for a minimum period of seven days.
4.2.7 Measurement:
The length, height and thickness shall be measured correct to cm. The thickness of wall shall be
measured at joints, excluding the bushings. Only specified dimension shall be allowed and paid,
anything extra shall be ignored. The quantity shall be calculated in cubic metre nearest to two
places of decimal. However, no deduction shall be made nor extra payment shall be made for
opening up to 0.1 sq.m. in area, water pipe holes, drain holes, or weep holes, gas pipe holes,
cable entry holes.
4.2.8 Rate:
The rate shall include the cost of materials, wastage, labour involved in all operations described
above, including transportation, overheads, profits, curing, tools and equipment, necessary
scaffolding, raking out joints, etc. including dressing stone, bond stone, or cement bond stones,
weep holes of required dia. As specified in items.
5.0 CEMENT POINTING:
The Joints of masonry shall be raked at least 12 mm deep. The dust shall then be brushed out
of the joints and the wall washed with water. The mortar shall consist of cement mortar in
proportion 1:3. This mortar shall be filled into joints and well pressed with special steel trowels.
The joints shall not be touched again after it has once begun to set.
The joints of the pointed work shall be neat. The lines shall be regular and uniform in breadth
and joints shall be flat as directed. No false joints shall be allowed.
The work shall be kept wet for seven days after pointing is complete.

6.0 Supply & Installation of Barb Razor Concertina Coil:


Job includes1) Supply and fixing of RAZOR WIRE BARBED TAPE type Concertina coil having diameter 600
mm, 50 spirals, barbed width 19 mm clipped with SS 304 Clips
2) Supply and fixing of 3 line Medium Barb Razor wire.
The schematic diagram is attached for your reference.
Job includes SUPPLY, FABRICATION & FIXING of 50 mm x 50 mm x 6 mm size MS FENCE
POST. The height of the fence post shall be 5 feet. The Fence Post shall be painted with 2 coat
of red oxide and two coats of Aluminium Paint
6.1. SCRAPPER BARB RAZOR HELICAL WIRE COIL
a. Description:

Page 15 of 21

Razor wire barbed tape concertina coil is a wire spiral of 50 turn having core wire of high carbon
spring steel of high tensile strength and a carbon steel strip of 21mm width , 0.5mm thick having
razor sharp barbs punched along the length on both sides of strip at regular intervals. The
punched tape and core wire are hot dip galvanized to prevent corrosion in outdoor exposure.
The punched tape is cold clenched to more then 230 deg over the core wire then formed into
coils. At various parts on the circumference of the coil the spirals of the coil are connected to
each other with STAINLESS STEEL SS304 clips to form the concertina coil so that it can be
opened up like an accordion. Two handles are provided on both sides to ensure ease of
handling. The length of the obstacle when opened up is 6 meters.
The Razor wire barbed tape concertina coil consists of various components like:
1) Punched Tape
2) Spring steel core wire
3) Clip
Scrapper Barb - specification
Barb Length 26mm
Barb width 19mm
Flange on each side 1.5mm (min.)
Each coil is wound in plastised jute packing to provide protective packing
The tolerance for the dimensions is as follows:
TOLERANCE
Sr No

Description

Diameter

01

Coil Diameter when


Packed

600 mm

Plus
50 mm

Tolerance

Minus
0 mm

MATERIAL COMPONENTS :
i) Cold rolled carbon steel punched tape :
The punched tape is fabricated out of cold rolled carbon steel strips obtained from cold rolled
carbon steel sheets conforming to IS: 513.
The chemical composition of the steel strip shall be as follows as per IS: 228:
Carbon
(C)
0.10% max.
Manganese (Mn)
0.45% max.
Sulphur
(S)
0.035% max.
Phosporous (P) 0.035% max.
The test piece when bent cols 180 deg. Its thickness shall not show any cracks on the outer
surface and also satisfy the requirement of strain age em-brittlement test. The steel strips shall
be hot dip galvanized or electroplated to FeZn12. The width of the steel strip shall be 21mm (+/1) prior to cold clenching.
ii) Spring Steel Core Wire :

Page 16 of 21

The core wire shall be cold dawn steel wire as per grade 2 of IS: 4454 (Part I).
Core wire chemical analysis shall be as follows as per IS: 228
Carbon
(C)
Manganese (Mn)
Sulphur
(S)
Phosporous (P)

0.60-85%
0.8%
0.040%
0.040%

max.
max.
max.
max.

The diameter of the steel core wire shall be 2.6mm (+/- 0.1)
The tensile strength shall be 1500-1650 Mpa
The steel core wire shall be galvanized as per IS4826 & IS2629 to 230 gms/m2
iii). Steel for Clips
The material shall be STAINLESS STEEL SS304
and shall meet chemical properties as follows :
Chemical composition (weight %)
C

Si

Mn

Cr

Mo Ni

max.0.07 max.1.00 max.2.00 18.25 -

V W Others

9.25 - -

Corrosion preventive coating


A thin coating of corrosion preventive coating shall be applied by dip process over the complete
concertina coil to give it high corrosion resistance.
The coating shall conform to IS: 1153
Packing material
Plastised jute cloth shall be used for packing of the finished coil , to ensure no injury to any
person while handling and in transit.
6.2. SINGLE LINE MEDIUM BARBED RAZOR WIRE:
The specifications and material composition shall be same as that of SCRAPPER BARB
RAZOR HELICAL WIRE COIL with following deviations:
a. Barb Length : 20 mm &
b. Barb Width : 14 mm
6.3. TEST CERTIFICATES:
Vendor shall submit all relevant Test Certificates of the material used like Razor barbed tape
Concertina Coil, Medium barb clip mesh; medium barbed razor wire from Original Manufacturer
as well as Government approved Testing House prior to dispatch of the material. Test
Certificate shall include material composition, dimensions of the material and their tensile
strength in addition to other parameters.
6.4. GUARANTEE AGAINST CORROSION:
Against Satisfactory Completion of warranty period of 12 month after fixing oc concertina coil,
the Bank Guarantee will be released , however Vendor shall give Minimum 5 years

Page 17 of 21

GUARANTEE for all the material supplied against CORROSION on a Judicial Stamp Paper
prior to dispatch of material.
7.0 SUPPLY, FABRICATION & PAINTING OF MS GATES (03 Nos):
Job includes supply, fabricate and fixing Main Gate (03 Nos) as per drawing using MS pipes,
Plates, bars etc including cuttig, welding, fixing with hinges, rollers, locking arrangement,
aligning, balancing for smooth operation, grouting the hinges in the RCC column, etc complete.
The gate shall be finished with two coats of enamel paint / Aluminium Paint over two coats of
Zinc Chromate primer after due cleaning, grinding to get the smooth surface after welding etc.
complete. The drawing attached is only for the reference purpose. The contractor shall prepare
the detailed drawing based on the site conditions; reference drawings attached and submit the
same to HPCL for approval prior to fabrication of the same.
The rate quoted shall inclusive of preparation of detailed drawing, supply, fabrication & painting
of MS Gates.

8.0 PAINTING OF COMPOUND WALL:


The job includes external painting of Compound wall (from inside as well as outside) in white
WATERPROOF cement paint.
The specifications and method of application is as follows:
8.1. Material:
8.1.1. Cement Paint:
Cement Paint shall comply with IS: 5410-1992 and shall be of approved brand like Snowcem
India Ltd.only. The shade shall be approved by the Engineer before its application.
8.2.Application:
8.2.1. General:
Wherever scaffolding is required / necessary, it shall be erected on double support tied together
by horizontal pieces, over which the scaffolding planks shall be fixed. No part of it shall rest on
or touch the surface which is being washed /painted. Where ladders are used , pieces of old
gunny bags shall be tied on their tops to avaoid damage or scratches to walls. The surface on
which wash is to be applied shall be thoroughly brushed free from mortar droppings and foreign
matter.
8.2.2. Cement Primer Coat:
The surface shall be thoroughly cleaned of dust, mortar, droppings etc. and shall be allowed to
dry for at least 48 hours. It shall then be rubbed thoroughly by sand paper to give a smooth and
even surface. Any unevenness shall be made good by applying putty, made of POP (Plaster of
Paris) mixed with water on the entire surface including filling up the undulation and then sand
papering the same after it is dry. The cement primer shall preferably be applied by brushing and
not by spraying. Horizontal strokes shall be given first and vertical strokes shall be applied
immediately, afterwards. This entire operation will constitute one coat. The surface shall be
finished as smooth as possible, leaving no brush marks.
8.2.3. Water proof Cement Paint:
The prepared surface shall be thoroughly wetted with cleaned water before waterproof cement
is applied. The paint shall be prepared strictly as per manufactures specifications, in the
absence of which it shall be mixed in two stages. The first stage shall comprise of 2 parts of
water- proof cement paint and one part of water stirred thoroughly and allowed to stand for 5

Page 18 of 21

minutes. Care shall be taken to add the paint gradually to the water and not vice-versa. The
second stage shall comprise of adding further one part of water to the mix and stirring
thoroughly to obtain a liquid of workable and uniform consistency. The paint shall be mixed in
such quantities as can be used up within an hour of its mixing.
The paint shall be applied with brushes or spraying machine. The solution can be kept well
stirred during the period of application. It shall be applied as far as possible on the surface,
which is on the shady side of the building so that direct heat of the sun on the surface is
avoided. Painted surface shall be sprinkled with water 2 or 3 times a day. This shall be done
between coats and for at least 2 days following the final coat. The curing shall be started as
soon as paint has hardened so as not to damage by sprinkling of water say about 12 hours after
the application. A uniform shade should be obtained after application of paint. Cement paint
shall not be applied on surfaces already treated with white wash, color wash, distemper, varnish
paint etc. and on gypsum, wood and metal surfaces.
8.3 COLOR CODING:
1. Compound wall: Compound wall shall be painted white with grey color patta on top / columns.
9.0 DRAWINGS ATTACHED:
9.1 South Side Section & Plan View
9.2 North Side Section & Plan View
9.3 Plan of UCR Wall & MS Gate
9.4 Schematic view of Concertina Barbed wire fencing
9.5 Schematic view of MS Gate
9.0

TESTING OF BUILDING MATERIALS

The contractor shall carry out the following tests, unless otherwise mentioned and as directed by
the engineer in charge at his own expense. The Engineer in charge reserves the right to ask
the contractor to carry out any further tests on the materials which is being used in the project.
For particle size test, it is recommended that the set of sieves and weighing machines be
arranged by the contractor at site. Necessary manpower for carrying the tests shall be arranged
by the contractor.
For crushing strength of concrete, it is recommended that the contractor arrange the
compression testing machine at the site along with the calibration certificate for gauge.
In case, if any of the machine comes to repairs and tests could not be carried out at the site,
contractor shall arrange to transport the material to an approved laboratory to carry out the
tests. All transports and labour costs also are to borne by contractor.
Sl.
No.
1

Material

Tests

Water

Cement

a)
b)
c)
d)
e)
f)
g)
h)
i)
a)

Page 19 of 21

PH value
Limits of Acidity
Limits of Alkalinity
Percentage of solids
Chlorides
Suspended matter
Sulphates
Inorganic solids
Organic solids
Fineness

Test
procedure
I.S. 3025

Acceptanc
e criteria
I.S. 456

Periodicity
From the
source at the
beginning of
work / change
of source.

Sand
For
concreting

4.

Coarse
aggregate
For
concreting

Reinforcem
ent steel

Cement
concrete
(For RCC)

Sand for
filling

Stones

Page 20 of 21

b) Soundness
c) Setting time ( Initial &
Final )
d) Compressive strength
e) Consistency

I.S. 4031

I.S. 8112 /
12269

a)
b)
c)
d)
e)
f)

IS 2386

IS 383

a) Percentage of soft /
deleterious material
b) Particle Size distribution
c) Organic impurities
d) Sp. Gravity
e) Bulk density
f) Aggregate crushing
strength
g) Aggregate impact value
h) Alkali Reactivity
i) Flakiness index

I.S. 2386

I.S. 383

a) Physical properties
b) Chemical test
c) Bend & rebend test
d) Elongation test
e) 0.2% Proof stress
f) Tensile strength
a) Slump test
Cube test ( three cubes for 7
days strength and 3 cubes
for 28 days strength for
every sample )

I.S. 1608

I.S. 516

I.S. 456

6 cubes per
every 15 cum
or part there of

a) Particle size distribution


b) Organic content
c) Silt content
d) Uniformity coefficient
(D60/D10)
e) Max. Dry density
f) Optimum Moisture
content

I.S. 2386

Max.
organic
content 3%
by wt.
Silt content
10% by
weight
Particle size
max. 5mm
Uniformity
coefficient
2.0 to 8.0

One lab test for


each source.

Particle Size distribution


Sp. Gravity
Deleterious substance
Organic impurities
Water absorption
Fineness modulus

a) Compressive strength
b) Water absorption
c) Efflorescence

Manufacturers
test certificate
and Lab test for
each batch
brought to site.
at the beginning
of work /
change of
source or for
every 100 Cu.m
of concreting.
One test for
each source
Every 100 cum
concreting or
part thereof

I.S. 1786

Each lot from


each source for
each dia.
Min. Qty 10 MT.

I.S. 2720

Compaction
as per PO
specs.

Field
compaction
test:
1 test for 500
M2 area of
each layer.
There shall be
min. 10 density
measurements
for each test.
1 no. per lot of
2000 nos
5 nos. per lot of

2001-10000
10nos per lot of
10001- 35000
15nos per lot of
35001- 50000
8.0 LIST OF APPROVED BRANDS OF MATERIALS
(Only approved brand of materials as mentioned below shall be used in the work.
Equivalent brands are applicable only in the case non-availability of the approved
brands.)
1.

Portland Cement

: BIRLA / ACC / Ultra Tech/Ambuja/


ZUARI / COROMANADEL / RAJASHREE

2.

Tor / Mild Steel

: SAIL / RINL/TISCO or any equivalent brand


With prior approval of Engineer-in-charge.

3.

Structural steel

: SAIL / TISCO or equivalent brand with


prior approval of Engineer-in-charge

4.

Paint

Water proof Cement Paint

: SNOWCEM / SUPERCEM or equivalent brand


with prior approval from Engineer-in-charge

Synthetic Enamel Paint

: ICI / ASIAN / NEROLAC

Red Oxide

: SHALIMAR or equivalent brand with prior


approval of engineer-in-charge

Note: All Bidders are requested to visit & check the site conditions before submission of
tender enquiry. No representation of any nature will be entertained once Offer has been
submitted & PO is placed on the successful bidder.

Page 21 of 21

You might also like