Mechanical Miro Planning

Scope of
Sr.no DRAWING no Qty UOM
Work
1 PIPING of Auxilarry

2" 602.75
1.1 1046-k72-04-ISO-041 ID
1.2 1046-k72-04-ISO-042 2" ID 608.75
1.3 1046-k72-04-ISO-043 2" ID 595.81
1.4 1046-k72-04-ISO-044 2" ID 608.75
1.5 1046-k72-04-ISO-045 2" ID 586.85
1.6 1046-K72-04-ISO-006 6" ID 35
1.7 1046-K72-04-ISO-007 6" ID 48.25
1.8 1046-K72-04-ISO-008 6" ID 56.25
1.9 1046-K72-04-ISO-010 6" ID 28.25
1.1 1046-K72-04-ISO-012 10" ID 292.25
1.12 1046-K72-04-ISO-013 12"/10" ID 120
1.13 1046-K72-04-ISO-014 6" ID 156
1.14 1046-K72-04-ISO-015 6" ID 42
1.15 1046-K72-04-ISO-021 4" ID 64
1.16 1046-K72-04-ISO-022 4" ID 24
1.17 1046-K72-04-ISO-023 2" ID
1.18 1046-K72-04-ISO-024 2" ID
1.19 1046-K72-04-ISO-025 10" ID
1.2 1046-K72-04-ISO-026 6" ID
1.21 1046-K72-04-ISO-027 10" ID
1.22 1046-K72-04-ISO-028 10" ID
1.23 1046-K72-04-ISO-029 4" ID
1.24 1046-K72-04-ISO-030 2" ID
1.25 1046-K72-04-ISO-031 10" ID
1.26 1046-K72-04-ISO-032 4" ID
1.27 1046-K72-04-ISO-033 6" ID
1.28 1046-K72-04-ISO-034 2" ID
1.29 1046-K72-04-ISO-035 2" ID
1.3 1046-K72-04-ISO-036 2" ID
1.31 1046-K72-04-ISO-017 4" ID
1.32 1046-K72-04-ISO-018 1" ID
1.33 1046-K72-04-ISO-019 1" ID
1.34 1046-K72-04-ISO-020 2" ID
1.35 1046-K72-04-ISO-009 3" ID
1.36 1046-K72-04-ISO-011 2" ID
1.37 1046-K72-04-ISO-016 1" ID
1.38 1046-K72-04-ISO-001 18" ID
1.39 1046-K72-04-ISO-002 18" ID
1.4 1046-K72-04-ISO-003 2" ID
1.41 1046-K72-04-ISO-004 2" ID
1.42 1046-K72-04-ISO-005 3" ID
2 Firewater Line Rerouting
2.1 14" ID 142

2.2 12" ID 286

3 Underground Drain OWS line


3.1 1046-K72-04-UG-001 3" ID 111
4 HOT TAPPING to SUCTION KOD INPUT

4.1 18" ID 504

5 INSULATION
Insulation
Pipe Description
Type
5.1 A1A 2" SQ.M IH
5.2 12/10-A02-CS150-S80 12"/10" SQ.M IH
5.3 A1A 6" SQ.M IS

5.4 10" IH
10-A4-CS150-S80 SQ.M
5.5 A1A 10" SQ.M IS
5.6 A1M 4" SQ.M IS
5.7 A1M 2" SQ.M IS
5.8 A1M 4" SQ.M IS
5.9 A1M 4" SQ.M IS
5.1 A1M 1" SQ.M IS
6 EQUIPEMENT ERECTION
6.1 COMPRESSOR 1 Nos
6.2 MOTOR 1 Nos
6.3 SEPARATOR SKID 1 Nos
6.4 COOLER 1 Nos
6.5 SUCTION KOD 1 Nos
6.6 DISCHARGE KOD 1 Nos
7 HOT TAPPING of 36" Flare input line
7.1 SCAFFOLDING
7.2 SPLIT TEE FITTUP
7.3 MACHINE ALIGNMENT for Hot Tapping
8 HOT TAPPING of 10" Discharge line
8.1 EXCAVATION
8.2 SPLIT TEE FITTUP
8.3 MACHINE ALIGNMENT for Hot Tapping
9 MOTOR Activity
9.1 Shaft coupling 1
9.2 Motor Alignment 1
10 COMPRESSOR ACTIVITY
10.1 Compressor Alignment 1
10.2 Compressor Grouting 1
11 SEPARATOR ACTIVITY
11.1 Separator Skid Alignment 1
11.2 Separator Skid Grouting 1
13 HYDROTEST

13.1 Hydrotest will be done on spool bases

14 Radiography Test
Radiography Test Will be Done on
14.1
spool bases
15 CHEMICAL CLEANING

15.1
Flushing with water to remove dirt etc.
15.2 Degreasing
15.3 Inhibited acid circulation

15.4 Neutralisation with soda ash / caustic


soda.
15.5 Rinsing
15.6 Passivation
15.7 Drying
16 PIPE SUPPORT CONSTRUCTION
16.1 Support Material required
16.2 Febrication
16.3 Sandblasting
16.4 Primer
16.5 MIO
16.6 Final Painting
Progress REMARK

awaiting
approved drg

Isometric Drawing
Pending
142
at the end of the
project

PIPE Doubling
72
done as per GAD

Drawing not
made

Material not
receipt at site

contractor not
assigned

contractor not
assigned
Pipe Spool
drawing Pending

Pipe Spool
drawing Pending

Pipe Spool
drawing Pending

Drawing Pending