Professional Documents
Culture Documents
University of Nottingham, UK
Team Member
Ruijun Zhang
Jiayi Qiu Ruijun Zhang
Undergraduate in BEng (Hons)
Undergraduate in BEng (Hons) Architectural Environment Engineering in BEng (Hons)
Undergraduate
@
Architectural Environment Engineering Architectural Environment Engineering
Xuyang Zhong
layjq3@exmail.nottingham.ac.uk tri.circles@gmail.com
Zhongzhe Wu
Undergraduate in BEng (Hons)
Architectural Environment Engineering
layzw7@exmail.nottingham.ac.uk
Supervisor
Dr. Ed Cooper
Lecturer, Course Director
University of Nottingham, UK
Edward.Cooper@nottingham.ac.uk
1
1. Introduction
2
2. Pre-design Phase
3
2.3. Site Analysis
2.3.1. Site Selection
The site for this building is in south Ningbo, which
is a new business area planned by Ningbo
government. The site was farmland many years ago
but is now planned to be residential area due to the
urbanization. The surrounding area has been
already well developed so this site is complied with
ASHRAE 189.1 5.3.1.1 e : on a greenfield that is
within 800m of not less than 10 basic services. The
surrounding basic services are indicated in the
Figure 3 Services within 800m.
4
generally the daily temperature in Ningbo changes cyclically.
2.4.4. Day-lighting and Natural Ventilation
Day-lighting can improve occupants comfort as well as reduce much energy in terms of artificial lighting. For
this building, it is essential to achieve high level of day-lighting level for residential area because that is where
people live day by day. For commercial area, day-lighting can be compromised to some extent because
occupants in that space will not require high level of visual comfort.
It is hard to design natural ventilation for a high-rise building like this because all spaces are separated by
several residential units. But good natural ventilation can still be achieved by innovation envelope strategies
and careful design of opening positions. For commercial area, natural ventilation is much less important than
residential area.
2.4.5. HVAC System
For ventilation requirement, ASHRAE 62.1 has been used as benchmark for ventilation requirements as well
as predicted maximum occupancy density of each space type.
Table 1 Ventilation Requirements
For terminal system, it should be selected and designed based on thermal requirements, control requirements
and architectural limitations of each space type. Following table summarizes the potential use of different
systems in various areas.
Table 2Potential Use of HVAC Systems
5
Equipment efficiency should meet the minimum level stated by ASHRAE 189.1 7.4.3 to save energy. Other
renewable energies can also be used to achieve this goal. Ningbo is a good place for ground source heat pump
because the soil has high thermal exchange property and is easy to be drilled. Besides, the Ningbo
Government would cover 20% of the GSHP installation cost to encourage its application.
3. Conceptual-design Phase
2) Refining based on Day-lighting: The space and layout design is mainly based on daylighting, so all
rooms must not be too deep. Besides, maximum number of rooms must be designed for each level.
Therefore, layout and space design must be changed. The layout of each floor has been further
6
simplified and treated as a rectangle. Also, the depth of each room will be minimized while the area of
each room must be no smaller than 50 m2. Figure 6 Refined Building Layout and Space Design shows the
refined design. There will be totally 17 levels of such design for residential area.
3.4. Envelope Design
3.4.1. Construction Material
1) Thermal Property
Building envelope thermal requirements of ASHRAE Standard 189.1 for climate zone 3 is illustrated as
below. (The minimum requirements used for this project are underlined)
Opaque Elements Thermal Property Residential Thermal Property Commercial
Roof-Insulation Entirely above Deck U-0.22 U-0.22
Steeled Framed Wall-above grade U-0.43 U-0.31
Below Grade Wall C-6.47 C-6.47
Steel Joint Floor U-0.21 U-0.21
Slab-On-Grade Floor-heated F-1.11 F-1.11
Metal Fr. Curtainwall-Vertical Penestration U-2.84 ,SHGC-0.25 U-2.84, SHGC-0.25
2) Green Roof
Green roof has the benefits of reducing cooling load for
the building. Besides, the water storage ability of soil
and plants will reduce rain-water run-off from roof,
which will help to earn points in LEED. It is also a
recommended strategy to reduce heat island effect by
LEED because plants and soil have very high solar
reflection index (SRI). Figure left shows the benefits of
green roof very clearly.
The native plant is suggested to be planted to reduce
Figure 7Benefits of Green Roof the water consumption of irrigation and maintenance
cost. Some points in LEED WE will also be earned for the use of native plants. Native plants suitable for
the green roof include:
Examples of Native Plants for Green RooF
Pink Reineckea Herb Speiranthagardenii Radix Ophiopogonis
3) Thermal Mass
From climate analysis in section 2.2, thermal mass will reduce heating and cooling load of building.
7
Figure 8 Rendered Concrete Example
Concrete is the most common thermal mass material (commands direct exposure to environment) and
will be used for this project. Nowadays, the availability of rendered concrete makes exposed concrete out
of aesthetical issues. A property "admittance value" can be used to evaluate the thermal mass effect.
4) Sustainable and Regional Material
For this project, traditional aggregates and cement are partly replaced by recycled and secondary material.
Ningbo has one of the largest coal-fired power plants in China. This gives an access to use Pulverised
Fuel Ash (PFA) and Fly Ash Aggregates (bio-product from coal burning) for concrete production. It has
been researched that if 30% of OPC is replaced by PFA, 17% of greenhouse gas emission and 14% of
primary energy can be conserved. This strategy will contribute to points for LEED MR credit 4: recycled
content.
Table 3Reduced Environmental Impact of PFA With the purpose to reduce transportation energy
consumption embodied in material, all the material
selected should be purchased or processed locally if
possible. Ningbo is located in Yangtze River Delta,
which is famous for its developed secondary industry.
So, all construction materials can be bought locally.
Table 4 lists the companies and factories that are
related to the construction materials. This strategies
will contribute to 2 points in LEED NC MR credit 5:
regional material.
Table 4 Local Construction Material Provider
Company Main Products
Baosteel Ltd, Shanghai Providing steel products
Ningbo CONCH Cement Ltd Providing cement and cement alternatives
Ningbo CONCH Profiles and Science Ltd Providing window and door
Ningbo Huamei Insulation Material Ltd Providing insulation materia
NBSolar Ltd Providing PV panels.
Figure 12 DSF Air Flow Pattern in winter Figure 11 Solar Gain Comparison of DSB
The CFD analysis has been conducted for DSF in winter. In sunny days, the simulation result shows
that if the outer glazing is sealed, the solar heat will be trapped within cavity area and then transferred to
occupied space.
The cooling energy falls slightly by 13%, which is due to the reduced solar gain in summer (seen in
Figure 11 Solar Gain Comparison of DSB). However, even the cavity area will be natural ventilated in
summer to avoid overheating, the heat gain to occupied zone through glazing is raised slightly (Figure
10 Annual Heat Transfer Comparison of DSF). Also, it should be noted that double skin facade may have
influence on natural ventilation effectiveness, so passive cooling effect is weaken (Figure 10 Annual
Heat Transfer Comparison of DSF) which is a probable limitation of this kind of facade.
2) Trombe Wall
Trombe wall is another passive solar design
considered in this project. The simulation is
processed by EnergyPlus. In order to evaluate the
feasibility of trombe wall in Ningbo, a simple
rectangular model is built as shown below.
Trombe wall provides advantages in increasing the
solar heat gain in winter, so that the heat energy can
Figure 13 Trombe Wall Model for EnergyPlus be reduced. It is found that trombe wall can cut
down the heating energy consumption by about 64%
due to simulation results. As the outside glazing will trap the heat, cooling load is then increased and
9
cause a big issue in summer. Although the outside glazing will be open to allow the natural ventilation so
that heat can be taken out, the heat gain through partition is still higher than normal walls. Generally, the
cooling energy for building with trombe wall will be increased by 60% in Ningbo.
In conclusion, double skin facade will be implemented in this project for part of south facade of this
building, while trombe will not.
3.4.3. Window and Opening Design
1) Residential Area
a) Window design: A general rule for window design to ensure that total window area is less than 40% of
gross wall area, as required by ASHRAE 189.1 Section 7. Day-lighting is the major consideration for
window design.
For south facade, DSF will be implemented as discussed before. To increase day-lighting at deep end of
the room, two windows are added on upper left and upper right side of DSF. For north side, two identical
windows with height of 2m and width of 2.5m are installed for each room.
10
Figure 16 Opening Design and CFD Results (age of air)
In Figure 16 Opening Design and CFD Results (age of air) it can be seen that the maximum age of air is
1102.86s, which is generally equivalent to ACH of 1.62.
North window
For north facing room there are two identical windows with each has the area of 5 m2. The simulation
time point is at 12:00 in 2nd Jun. It is found that the best scheme occurs when there is opening at both top
and bottom of each window.
Figure 17 Opening Design for North Window and CFD Results (Velocity Vector)
It can be seen from above figure that cold air enters from bottom window and hot air leaves from top
windows. The maximum age of air is 710.6 s which is generally equivalent to ACH 2.53.
East Room
The east room has windows on two different walls, which makes the natural ventilation much more
effective. After tests of several strategies, following figure shows the best design of opening.
The simulation time point is 12:00 1st Jun. It can be seen that at noon on 1st Jun, the air goes into the
building from east windows and comes out through north window. The maximum age of air is only
238.58s, which is equivalent to ACH 7.54. It can be seen that the ventilation effectiveness is much more
better than previous rooms.
Figure 18 Opening Design for East Rooms and CFD Results (Velocity Vector)
11
2) Commercial Area
a) Retail space: From previous calculation it has been designed that retail space will be moved to
underground, but 2 strategies will be implemented on window (and door) design to increase day-lighting
performance.
Firstly, entrance to retail level will be all glass
doors on north side of the building, to provide
day-lighting and avoid large solar heat gain in
summer. Besides, a line of windows will be
equipped on top of walls of B1 to increase
light penetrating into room. Figure below
shows these two strategies.
b) Restaurant
Floor-to-ceiling window is designed to
Figure 20 Temperature Profile in Winter Design Days heating. Besides, a terminal reheat coil will be as well
added to meet the heating load when necessary.
2) Residential Area
Based on the analysis in pre-design, the chilled ceiling and fan coil unit may be appropriate for residential area.
Even though generally speaking chilled ceiling is much more energy efficient than FCU, it must be noted that
Ningbo has very humid summer so there will be the danger of condensation and high RH if the chilled ceiling
is used. Simulation results show that during simulation period from 1 Jul to 7 Jul (summer design week for
Ningbo) indoor RH is always above 90% and indoor air temperature will be above 24.5 sometime. This means
chilled ceiling is not suitable for Ningbo.
12
Figure 21Temperature and RH in Summer Design Week for Chilled Ceiling System
13
Figure 23VAV with Reheat System for Commercial Area
Fan coil systems can satisfy the individual heating and cooling requirements of multiple zone buildings and
enable good building flexibility. Each room in residential area is served by one fan coil unit. Fresh air is
centrally supplied to each room after being treated by Pre-treatment Air Handling Units (PAU) which are
located on the top of building. Underfloor heating is used for winter heating.
Simple illustration for system is described in Figure 24 Fan Coil Unit+Floorheatng for Residential Area.
14
Control Type Differential Temperature
Upper and Lower Temperature Limit No limit
Operation Schedule On for whole year
The annual simulation results are shown in Figure 25 Energy Consumption after 3 Strategies. It can be found
that the total HVAC energy consumption has been decreased by 6.65%.
Heat recovery
Heat recovery is used to recover the heat form extract air so the incoming air can be preheated or precooled.
In this case, the heat recovery is needed not to recover the heat in winter but recover the "heat" from cool air
in summer. This is because the effect of heat recovery will counteract the effect of economizer. Generally,
heat recovery will be bypassed when economizer is operating.
In the simulation the rotational heat recovery device with sensible heat recovery 75% and latent heat
recovery 70% is used (Nowadays technology allows higher efficiency than that). The operation schedule is
on for the whole year.
From the Figure 25 Energy Consumption after 3 Strategies. it can be seen that both cooling and heating
energy has been reduced by heat recovery. The total HVAC energy consumption is about 13.5%.
Supply air temperature reset
VAV has the most obvious drawbacks in winter
heating, especially when the heating and cooling
load happens simultaneously at different zones. If
AHU supply air setpoint can be reset based on the
heating load, the heating energy may be reduced
because repeated heating may be avoided. After
EnergyPlus testing, the best reset strategy is
resetting supply air temperature based on the
average zone heating load. But it must be noted
that the supply air temperature cannot be too high,
because cooling is needed for inner zones, even
in winter. In this case, the upper supply air
temperature limit is 14 C. From Figure 25 Energy
Consumption after 3 Strategies it can be seen that
Figure 25 Energy Consumption after 3 Strategies the heating energy is reduced obviously. The total
energy consumption is reduced by 14.6% (compared with baseline case)
2) FCU+ Fresh Air-Residential Area
To minimize the energy consumption of the system, heat
recovery on fresh air supply and different FCU capacity
control methods are tested.
Heat Recovery
For residential rooms, separate fresh air supply is needed.
Therefore, heat recovery is essential for this system to
reduce heating energy. For EnergyPlus simulation, sensible
heat recovery effectiveness is 75% and latent heat recovery
effectiveness is 70%.
It can be seen that heat recovery could effectively reduce
heating energy, as well as cooling and fan energy. The total
Figure 26 Energy Consumption after Heat Recovery
15
HVAC energy consumption can be reduced by 23.8%.
FCU Capacity Control Method
Three capacity methods are tested including 1) 3 speed air flow; 2) variable air flow variable water flow; 3)
variable air flow and constant water flow.
The results show that all three control methods have similar energy performance, but the first two control
methods the energy consumption is slightly better..
To conclude, VAV with terminal reheat system is used in commercial area. Heat recovery, economizer and
supply air temperature reset technologies are recommended and the total HVAC energy consumption will be
reduced by about 14.6%. For residential area, FCU + separate fresh air supply+heated floor is selected. Heat
recovery can reduce energy consumption to about 23.8%. The FCU is recommended to control by 3-speed-air
or variable air flow & variable water flow.
3.5.4. Ground Source Heat Pump
A ground source heat pump (GSHP) is a central heating and cooling system that
transmits heat to or from the ground or groundwater. Ningbo is a suitable place
to practice GSHP as discussed in pre-design section, and Ningbo government
declared that there is a 20% subsidy of installed cost in GSHPs in 2005.
GSHP is a well integrated unit, which means one unit can be used to provide
refrigeration, heating as well as domestic hot water service. GHSP also has very
low maintenance costs and quite long lifespan. Above ground equipments have
25-year lifespan and the ground circulation system has lifespan of over 50 years.
1) Energy Analysis
At least two GSHP units will be equipped for this building in which one for
residential area and one for commercial area, because residential and
commercial area has different thermal requirement of operation schedule. As
comparison, one water-cooled chiller from and boiler system from local
companies in China has been selected. The normal chiller has EER of 3.3 and
Figure 27 GSHP for EnergyPlus boiler has efficiency of 0.89.
Figure 27 GSHP for EnergyPlus shows the comparison of energy consumption between GSHP and normal
chiller+boiler system for commercial and residential area.
As shown in Figure 28 GSHP Energy Consumption Comparison Simulation shows that much energy is
reduced for heating and cooling for both residential and commercial area, the total HVAC energy consumption
will be reduced by nearly 40%.
16
2) Cost Analysis
Compared with the normal chiller +
boiler system, the GSHP system has a
higher initial cost for installation in the
building. However, the yearly
expenditures of GSHP is only
334944.27(CNY), which is about 40%
lower than normal chiller + boiler
system. Therefore, it could only use no
more than 5 years to reach the break
even. Therefore GSHP is financially
feasible for this building project.
Figure 29 Life Cost of GSHP
17
should have separate control. Thus the lighting level attains compensation by balancing the daylight and
artificial lighting.
For the exterior lighting, this method is also applied but combined with the timer control.
c) Timer control
This method is applied in the supermarket at B1&B2 and exterior lighting of large area for centralized control.
According to the each particular schedule, lights would be switched on/off automatically.
3.7. PV System
Ningbo is a suitable place for PV application because strong solar irradiation in summer and sufficient supply of
products (Ningbo is one of the manufacturing center of PV in China). For this project, PV will be designed to be
integrated into building.
Type of Panels
There are two main types of PV panels for this building: one is roof mounted PV and the other one is
installed on top of south windows to act as shading devices.
1) PV as shading devices
For south windows of residential area, horizontal shading
needs to be provided for double skin facade. The design
criteria is to block direct sun light in summer days
(June, July, August).Therefore, shading device need
the dimension of 1.15m*2m (width*length).
For south windows on ground floor, huge ceiling-to
floor windows are installed. The design criteria is to
Figure 32 PV Shading for South Window forblock windows above 1.5 m from direct sunlight in
Residential Area summer days because the window is too high.
Therefore, the horizontal shading above windows will be width of 1.15m.
2) Roof-mounted PV panels
Arrays of PV panels will be installed on flat roof of this project. Conceptually half of the roof area
will be occupied by PVs and the other half is for plants of building services. This design will help to
meet the requirement of SS credit 7.2 in LEED 2009 NC.
Type of installation
There are two main installation types for PV panels, including grid-interactive and off-grid using
battery. For high rise building in city on-grid PV is better because the cost of batteries is relative high
large space is needed to storage batteries. All PV panels needed to be connected in series in order to
rise its voltage to be easily integrated into grid. A typical example of grid-interactive PV panels is
shown below.
18
3.8.1. Building Automation System (BAS)
Building automation system (BAS) provides the centralized monitoring and remote control to manage and
optimize the use of all the mechanical and electrical equipments in the whole building, including central
air-conditioning system, power supply and distribution system, lighting system, fire & security system and
elevator system. The most complicated part in this case building is the control of HVAC system coupled with
floor heating and GSHP system, which involves the data collection from each air & water temperature sensor
and the corresponding controllers. Other systems such as lighting and fire system also have their exclusive
sensors and are controlled in independent means, whereas all of them need to monitor and report the operation
conditions to BMS. This process is realized by computer software, which collecting RT digital signals from
each system, then make a diagnosis of these issues and responding to the aberrant part. Its also beneficial to
reduce equipment failure rate and minimize maintenance and operating costs.
3.8.2. Energy Management System
The EMS system is designed to reduce energy consumption and save operation cost, which also has the data
exchange with BAS. Generally, the EMS is achieved by the Real-time monitoring, collecting and analysis on
energy management software to realize these effects:
1. Improve the overall management level by monitoring the energy consumption condition of equipments
during operation.
2. Find the aberrant energy consumption or Low efficiency of equipment operation timely.
3. Reduce the peak power consumption
4. Preliminary-design Phase
19
Figure 35Entrance Slop
2) Wall
20
Table 7 Wall Construction
Wall type External wall Internal wall
For the wall below grade wall, water proofing (Sealants) is needed to be added.
3) Floor:
21
4) Window:
Level Ground B1 B2
Max Supply AFR 5588 l/s 5626 l/s 5168 l/s
Supply Air DB 12C 12C 12C
Supply Air Moisture Content 0.0076kg/kg 0.0082 kg/kg 0.008kg/kg
Ventilation Rate 1450l/s 2340l/s 2340l/s
Coil Cooling Power 154 kw 232 kw 226 kw
N.B. AFR = Air Flow Rate. For all AHUs, the design coil inlet temperature is 6C and design outlet
temperature is 11C.
Every terminal unit consists of reheat coil and following table summarizes the basic information of
this coil.
22
Max Supply AFR 2951 l/s
Supply air DB 23C in Summer, 21C in winter
Summer Supply Air RH* 50%
Coil Cooling Power 171 kw
Coil Heating Power 9.53 kw
*In winter, the supply air will be humidified to meet the RH requirement of indoor air.
FCU
FCU is used to eliminate sensible and latent heat gain of each room. The following table summarizes
the basic parameters of each FCU.
FCU in Each Residential Room
Max Supply AFR 250l/s
Control Type 3-level supply air flow rate, constant supply air temperature
FCU in Each Corridor
Max Supply AFR 225l/s
Control Type 3-level supply air flow rate, constant supply air temperature
In summer the design coil inlet temperature is 7 C, design outlet coil temperature is 12 C.
Underfloor Heating
The residence room will be heated
3) GSHP Parameters
Geological conditions
The vertical distribution (0-70m) of ground soil in the east of Zhejiang can be divided into four layers,
which are clay layer, sludge layer, silty clay and silty sand layer. Referring to the Quality Monitoring
Document of GSHP Installation in the National Tax Bureau of Ningbo, the thermal parameter of soil
(0-70m) in Ningbo can be displayed as following:
Ground thermal conductivity =0.5 Btu/h ft F
Ground thermal diffusivity =0.020 ft2/h
Function Classification
Based on the demands of user, this system should providing refrigeration, floor heating and domestic hot
water services.
This building consists of two different functionalized areas which are residential area and commercial area.
Thus, considering the different requirements of operation and control, at least two GSHP units must be
installed. Additionally, due to the total cooling load of the 17 levels residential area is too high
approaching 998.9kw, it is designed that there are two units providing heating and cooling for entire
23
residential area to minimize the impact on the whole building if one unit occurs breakdown; one is for
F1-9 and the other one is for F10-17.
No. Load area HVAC load Thus in this design, the Unit-1
Cooling load 612 kw is supplying for retail &
Unit 1 Commercial level (B2, B1, F0)
Heating load 96.7 kw
restaurant, and Unit-2&3 work
Cooling load 528.8kw
Unit 2 Residential level (F1-F9) for residential zone. Table left
Heating load 185.4kw
shows HVAC load required for
Cooling load 470.1kw
Unit 3 Residential level (F10-F17) each unit.
Heating load 164.8kw
24
4) System Schematic Diagram
25
Figure 40 FCU and Heated Floor for Residential Area (L1-17)
For L0 Restaurant:
The 2000lm 40w energy-saving lighting down lamp is
applied.
LPD in restaurant design can be computed as 3.61w/m2,
which is also far less than 12.6 w/m2of LPD allowance in
ASHRAE Standard 189.1
For L0 Entrance hall and corridor, the selection is the same.
26
For L1-L7 elevator hall and corridor:
The 1100lm 10w LED Downlight is selected.
The actual LPD in elevator hall can be determined as
5.82w/m2, which is also far less than 13.3 w/m2of LPD
allowance in ASHRAE standard 189.1.
4.2.3. PV System
Predicted Energy Production
1) PV devices on shading: Based on the dimension of 1.15m (width) * 2m (length) for the south shading
device determined in the conceptual design, a suitable product has been chosen from local PV
manufacturer Ningbo Solar Co. Ltd., which is listed below.
For shadings on residential area (L1-L17), each double-skin facade will have one panel, so total active
area of PV is A=1.640.992=1.62688 m2 (active area of one panel) multiplied by 174 panels, which
equals 110.628 m2. Total solar radiation on horizontal level per year in Ningbo is R=1269.05 KWH/m2
and the efficiency of panel works is =16%. So total electricity generated by panels in residential area is
W = A R = 22468KWH /year.
For panels on ground floor, same type of PV will be used. The total active area of 35.79 m2 is determined
by 1.62688m2 22 windows, so annual energy generation is W = A R = 7270KWH /year
2) Roof mounted PV panels: Known from Ningbo Solar Co. Ltd, PV panels with angle of 24will get the
highest solar radiation, and the total solar radiation at 24per year in Ningbo is 1508.9 KWH/m2. The
product from Ningbo Solar Co. Ltd. has been selected, which is listed below.
Type Peak power Efficiency Size Weight Price
SGP-220 220 Wp 16% 1640*992*45mm 20 kg 3.98/Wp
If the panels are too closed to each other, some PV panels would be shaded by other panels.
The minimum space between two panels is determined by using the formula:
D=Lcos+Lsin(0.707tan+0.4388)/(0.707-0.4388tan)
Where L is the length of panel=1.64m; is
the angle=24and is the latitude in Ningbo
which is about 29N. Thus, D is obtained as
2.68m. The reason for choosing 1.64m as
length is that more PV panels can be installed
than using 0.992m as length. All PV panels
will be installed on the north part of the roof
in order to minimize its influence on green
roof. The layout of roof PV panels is shown in
Figure 42 PV Layouts on Roof Figure 42 PV Layouts on Roof.
There are 332=96 pieces of PV panels. Actual area is A=961.640.992=156.18048m2, total solar
radiation per year at 24is R=1508.9 KWH/m2 and the PV efficiency is 16%. So annual energy
27
production is W = A R = 37705KWH.
Totally, power generation by PV panels per year is 67443KWH.
Cost Analysis
According to the PV panels
electricity generation, the
figure of PV life cycle cost
left shows that it could pay
for itself in 8-9 years.
28
With regard to the power supply & distribution system, the power consumption of each room and
commercial property would be recorded individually in this system, which is convenient for the charge of
electricity. Additionally, the electricity generated from the PV panels would also be logged then connected
to the grid.
Thus, the total annual cost of electricity in this designed building is 729924.648CNY. For the HVAC system,
energy cost is shown below.
29
4.3.2. Investment costs
Construction materials
Item Quantity Unit Unit cost(CNY) Total Cost(CNY)
PV panel 1 17 No 200*3.98 13532
PV panel 2 96 individual 220*3.98 84057.6
Interior wall 1 3468 Sq. Meter 980 3398640
Interior wall 2 578 Sq. Meter 980 566440
Floor 1 11343.6 Sq. Meter 165 1871694
FLOOR 2 200181176 Sq. Meter 165 330298.941
Windows 1755.124 Sq. Meter 289 507230.836
Exterior wall 3741.848 Sq. Meter 1118.5 4185256.99
Common roof 561 Sq. Meter 800 448800
Green roof 561 Sq. Meter 2000 1122000
Building systems
Item Quantity Unit Unit cost(CNY) Total Cost(CNY)
GSHP host unit 1(730kw) 1 No 360000 360000
GSHP host unit 2&3(470kw) 2 No 280000 560000
Ground heat exchanger
67200 m 7.5 504000
system-buried pipe
AHU 3 No 15555 46665
VAV terminal unit 60 No 5000 300000
Supply diffuser 60 No 300 18000
Return terminal 30 No 180 5400
fan 8 No 12300 98400
Temperature sensor 60 No 75 4500
Electrical systems
Item Quantity Unit Unit cost(CNY) Total Cost(CNY)
Room lights (average) 816 No 60 48960
Passageways LED lights 260 No 135 35100
Supermarket fluorescent lamp 350 No 73 25550
Restaurant energy-saving light 70 No 13 910
Entrance hall LED light 160 No 135 21600
Green roof systems
Item Quantity Unit Unit cost(CNY) Total Cost(CNY)
Roof Lower 1 491.98 Sq. Meter 1000
245990
Roof Lower 2 245.99 Sq. Meter 1000
Roof upper 1 630.02 Sq. Meter 1000
315010
Roof upper 2 315.01 Sq. Meter 1000
The total investment cost of materials in this case is equals to 15118035.37 (CNY)
5. LEED Evaluation
In order to certify the design of this building reach the healthful, durable, affordable and environmental aim,
LEED2009 Green Building Rating System has been chosen to evaluate that. Prerequisites and credits in the
30
LEED 2009 are including 7 topics that sustainable sites (SS), water efficiency (WE), energy and atmosphere
(EA), materials and resources (ME), indoor environmental quality (IEQ), innovation design (ID) and regional
priority (RP).
The LEED check list of this project is fully shown in the table below. The final score of this project in LEED
rating is 71, which can be qualified as Gold level (60-79 points).
31
2) Water Efficiency (WE)
Rain water harvest system (as described in 4.1.1) and local plants will be used to help achieve this
requirement.
Water-efficient fixture, which is better than baseline of WE credit three, will be used to earn points.
3) Energy and atmosphere (EA)
A baseline building described in ASHRAE 90.1 Appendix G has been built and annual energy
consumption was simulated using EnergyPlus v7.2. Following table summarizes the basic information of
baseline building and design case.
Table 9 Baseline and Design Case for Energy Consumption Comparison
Baseline Design Case
Construction
Residential-U-0.365 Residential&Commercial U-0.245
External Wall
Commercial-U-0.479
Flat Roof Residential&Commercial-U-0.273 Residential&Commercial-U-0.177
Residential&Commercial-U3.41 Residential&Commercial-U-2.258
External Window
SHGC-0.25 SHGC-0.212
Ground Floor Residential&Commercial-U-0.169 Residential&Commercial-U-0.169
Internal Floor Residential&Commercial-U0.296 Residential&Commercial-U-0.430
Lighting
2
Residential Rooms (1-17) 12W/m , no automatic control 4 W/m2, no automatic control
Retail & Supermarket (B1 &B2) 18 W/m2, no automatic control 9 W/m2, automatic control-500lux
Restaurant (Ground) 13W/m2, no automatic control 4 W/m2, automatic control-200lux
Architectural Devices
PV shading device for every No shading
Shading Device
south-facing external window
All Others Baseline is the same as design case
HVAC system
Residential: ASHRAE system Residential: FCU+ separate fresh
1-PTAC air+ underground heating, GSHP
System Description
Commercial: ASHRAE system Commercial: VAV with reheat.
5-Packaged VAV with Reheat GSHP
32
Figure 46 Annual Energy Consumption Comparison
It can be seen in above figure that about 35% of total energy has been reduced compared with ASHRAE 90.1
baseline building. Therefore, 12 points can be earned.
Percentage of renewable energy
The PV system and GSHP are two sources of on-site renewable energy.
1) PV system
It has been predicted in section 4.2.4 that 67000 KWH of electricity can be generated by PV panels. The
electricity price of Ningbo is 0.7195 CNY/KWH. Therefore, annual electricity cost can be reduced by
48206.5 CNY.
2) GSHP
According to section 4.3.1 and Figure 46, 334944 CNY can be reduced by GSHP.
In conclusion, on-site renewable energy system in this project could reduce 383150 (CNY) of total energy
consumption cost, which is about 33% reduction. Therefore, full points (4 points) can be earned.
4) Material and Resources
The bio-products (Pulverised Fuel Ash (PFA) and Fly Ash Aggregates) as described in section 3.4.1. from
local coal fired plants will be used in concrete, which is contribute to points in this section. Besides, all
material used for this building will be from local manufacturers, as listed in Table 4.
5) Indoor Environmental Quality
Daylight design for residential area has been proven by simulation results from RADIANCE that it complies
with requirements of LEED.
33
All ventilation design has exceeded requirements in ASHRAE 90.1-2007.
Thermal comfort of this building complies with the requirements of ASHRAE 55-2004 section 6.1.1.
7. Reference
1. ANSI/ASHRAE/USGBC/IES Standard 189.1-2011
2. ANSI/ASHRAE Standard 55-2004
3. ANSI/ASHRAE Standard 62.1-2007
4. ANSI/ASHRAE/IESNA Standard 90.1-2007
5. ASHRAE (2008) HVAC Systems and Equipment in Air Handling and Distribution 2008, ASHRAE.
6. Building Water Supply and Drainage Design Specification GB50015-2003
7. Center, M.T.C. (2010) Thermal Performance: Part L1A. .
8. Eric E. R. (2007) Requirements for Lighting Levels referring IESNA 9th Edition Handbook
9. Endecon Engineering & Regional Economic Research, Inc. (2001) A GUIDE TO PHOTOVOLTAIC (PV)
SYSTEM DESIGN AND INSTALLATION CONSULTANT REPORT Prepared for: California Energy
Commission
10. Green Seal, I., (2011) Green Seal Standard For Paints and Coatings, Connecticut Ave, NW, Ste 872.
Washington, DC USA.
11. LEED 2009 for New Construction and Major Renovations Rating System
12. LV Yue, MO Ra, ZHOU Mo, DENG Haiyan (2006) China GSHP Technology Application Development
Report(20052006) Construction & Design for Project Publisher
13. Program, E.E. (2009) Washington State Energy Code: Builder's Field Guide.
14. Wen B. W., Dong H. L (2012) Quality Monitoring Document of GSHP Installation in the National Tax
Bureau of Ningbo Gong Zheng Construction Supervision Co. Ltd in ZheJiang, China.
15. Zheng, X.,Wolff, H., (2008). Measures to Administrate the Particular Fund to Develop Energy-Saving and
Clean Production Geothermal Source Heat Pump in China. In: Proc. 9th Annual IEA Heat Pump Conference
2008.
34