GAMMON INDIA LTD.

C/o Bhavnagar Energy Company Limited


2x250 MW LIGNITE BASED TPP AT PADVA, BHAVNAGAR
Daily Progress Report
Progress Date: 2/21/2017 Reporting Date: 2/22/2017
Fot the mnt Feb'17
Manpower Report

Upto Previous
Sr. No. Work Description Scope (Approx.) UOM Month Total Cumm. Remarks Remarks
Today Previous Total Cumm. (31-01-17)
Sr.No. Designation

1 Staircase Erection 90 MT 0 2.500 2.500 87.500 90.000 Completed STAFF

2 Handrail Fixation 8550 Rms 0 1850.000 1850.000 6460.000 8310.000 Welding work is in progress. 1 1
Site Incharge/Project Manager

3 Grade Slab Ouside 25 Cum 0 0.000 0.000 17.500 17.500 2 1


Engineers

4 Chimney shell paint out side 13000 Sqm 0 0.000 0.000 13000.000 13000.000 2 0

QA/QC Engineer

5 AWL Fixation 20 Nos 0 0.000 0.000 20.000 20.000 3 2


Adm./Accountant

Staircase Lighting work is in


6 HPSV Lamp Fiaxtion. 116 Nos 0 26.000 26.000 8.000 34.000 4 1
progress. Store Keeper

7 Lightening Arrester 8 Nos 0 0.000 0.000 0.000 0.000 5 Safety 0

Earthing Pit Work is in progress


8 Drain Water Pipe Laying 210 Mts 0 0.000 0.000 210.000 210.000 6 Forman 2

Others 2
7
TOTAL 9

MANPOWER AT SITE (DAY SHIFT)

Mech

1 Supervisor 1

2 Fitter 0

3 rolling operator 0

4 Welder 1

5 Gas Cutter 0

6 Grinder 1

7 Helper 1

8 Rigger 1

9 T. Welder 0

SUB TOTAL 5

Civil

12 Skilled 0
13 Semi Skilled 0
SUB TOTAL 0
electrical

12 Skilled 4

13 Semi Skilled 1

SUB TOTAL 5

Grand Total 10