A, AMP AMPERE MAX MAXIMUM MOTOR # INDICATES HORSEPOWER PUSHBUTTON MOMENTARY, 1 NORMALLY OPEN CONTACT
AFF ABOVE FINISHED FLOOR MCB MAIN CIRCUIT BREAKER
APPROX APPROXIMATE MCC MOTOR CONTROL CENTER PUSHBUTTON MOMENTARY, 1 NORMALLY CLOSED
DISCONNECT, SIZE AS INDICATED
AT AMPERE TRIP MCP MOTOR CIRCUIT PROTECTOR
ATS ACCEPTANCE TEST SPECIFICATIONS MDP MAIN DISTRIBUTION PANEL CONTACT PUSHBUTTON MOMENTARY, 1 NORMALLY OPEN
AWG AMERICAN WIRE GAUGE MIN. MINIMUM JUNCTION BOX, SIZE AS REQUIRED BY NEC, UNLESS OTHERWISE AND 1 NORMALLY CLOSED CONTACT
MISC MISCELLANEOUS NOTED ON THE DRAWINGS
BKR BREAKER MTD MOUNTED TIME DELAY STARTING OR CLOSING RELAY
BLDG BUILDING MVA MEGA VOLT AMPERE
HOMERUN WIRING AND CONDUIT TO PANELBOARD. SIZE AND QUANTITY OF SYNCHRONIZING CHECK RELAY
C CONDUIT N.C. NORMALLY CLOSED WIRING AND CONDUIT SHALL BE AS SHOWN ON THE PANELBOARD SCHEDULES
CAB CABINET NEC NATIONAL ELECTRICAL CODE AND/OR POWER ONE-LINE DIAGRAMS, U.O.N. LETTER DENOTES PANELBOARD UNDER VOLTAGE RELAY
CB CIRCUIT BREAKER NEUT NEUTRAL A-1,3 DESIGNATION. NUMBER DENOTES CIRCUIT NUMBER. THE NUMBER OF ARROWS
CKT CIRCUIT N.O. NORMALLY OPEN INDICATE THE NUMBER OF CIRCUITS IN THE SAME CONDUIT. SIZE AND MANUAL SELECTOR SWITCH
CM CIRCULAR MILS NO. NUMBER QUANTITY OF WIRES PER CIRCUIT SHALL BE AS SHOWN ON THE SCHEDULES
COB CORPORATE OFFICE BUILDING NTS NOT TO SCALE AND/OR POWER ONE-LINE DIAGRAMS. PHASE SEQUENCE VOLTAGE RELAY
COTR CONTRACTING OFFICER'S TECHNICAL REPRESENTATIVE NEMA NATIONAL ELECTRICAL MANUFACTURERS
CS CONTROL SWITCH ASSOCIATION TIME OVERCURRENT RELAY WITH INSTANTANEOUS UNIT
CT CURRENT TRANSFORMER NETA INTERNATIONAL ELECTRICAL TESTING 3/4" DIAMETER X 10' LONG COPPER CLAD STEEL GROUND
CU COPPER ASSOCIATION ROD TIME OVERCURRENT GROUND RELAY
P POLE GROUND
DIA DIAMETER RESIDUALLY CONNECTED TIME OVERCURRENT RELAY
PB PULL BOX,
DISC DISCONNECT
PH PUSH BUTTON
DWG DRAWING OVERVOLTAGE RELAY
PLC PHASE
PNL PROGRAMMABLE LOGIC CONTROLLER PANEL DETAIL/SECTION TAG: "DETAIL X/Y"
EA EACH DETAIL/SECTION NUMBER AUTOMATIC SELECTIVE CONTROL OR TRANSFER RELAY
PVC POLYVINYL CHLORIDE
EL, ELEV ELEVATION DRAWING NUMBER WHERE SHOWN
ELEC ELECTRIC LOCKOUT RELAY
RGS RIGID GALVANIZED STEEL
EMH ELECTRIC MANHOLE
EMT ELECTRICAL METALLIC TUBING SWITCH TRIPPING RELAY
SCH SCHEDULE
EQUIP EQUIPMENT SPEC SPECIFICATION
EX, EXIST EXISTING STD STANDARD CIRCUIT BREAKER POWER QUALITY MONITOR, DIGITAL 3P METER
EPS ELECTRONIC POWER SUPPLY SUSP SUSPENDED
ETU ELECTRONIC TRIP UNIT SW POWER MONITOR
SWITCH
SWBD SWITCHBOARD ELECTRICAL OPERATED, DRAWOUT TYPE CIRCUIT
F FUSE, FUSIBLE SWGR BREAKER, FULLY RATED, SIZE AS NOTED CONTROL SWITCH
SWITCHGEAR
FDR FEEDER S/N SOLID NEUTRAL
FLA FULL LOAD AMPERES PLC PROGRAMMABLE LOGIC CONTROLLER
FR FRAME FUSE
FT FEET, FOOT TEMP TEMPORARY UPS UNINTERRUPTIBLE POWER SUPPLY
FVR TERM TERMINAL
FULL VOLTAGE REVERSING
FVNR 3/C THREE CONDUCTOR FUSED SWITCH TVSS TRANSIENT VOLTAGE SURGE SUPPRESSOR
FULL VOLTAGE NON REVERSING
3/P 3 WAY THREE POLE THREE WAY
GFI GROUND FAULT INTERRUPTER THRU THROUGH
GFCI TP TRIP
GROUND FAULT CIRCUIT INTERRUPTER TRANSFORMER
GRD TTB TELEPHONE TERMINAL BOARD
GROUND
TV TELEVISION
HOA HAND-OFF-AUTOMATIC TVSS TRANSIENT VOLTAGE SURGE SUPPRESSOR
HZ TYP. TYPICAL PILOT LIGHT (R=RED, B=BLUE,
HERTZ
G=GREEN, A=AMBER)
INT INTERIOR U/G UNDERGROUND PILOT LIGHT (R=RED, B=BLUE,
IPC INDUSTRIAL PC UON UNLESS OTHERWISE NOTED G=GREEN, A=AMBER), PUSH-TO-TEST
JUNCTION BOX
TYPE
JB V VOLT
THOUSAND AMPERE INTERRUPTING CAPACITY VA VOLT AMPERE POTENTIAL TRANSFORMER (SIZE
KAIC THOUSAND CIRCULAR MIL AS NOTED)
KCMIL KILOVOLT W WATTS
KV KILOVOLT-AMPERE WXD WIDTH X DEPTH CURRENT TRANSFORMER (SIZE
KVA KILOWATT W/ WITH AS NOTED)
KW W/O WITHOUT
LONG TIME, SHORT TIME, INSTANTANEOUS WP WATERPROOF, WEATHERPROOF
LSI LONG TIME, SHORT TIME, INSTANTANEOUS GROUND EQUIPMENT (AS
LSIG FAULT NOTED)
XFMR TRANSFORMER
LOW VOLTAGE
LV HATCH INDICATES
DEMOLITION
1. COORDINATE WITH OTHER CONTRACTORS/TRADES, UTILITIES AND 'COTR' FOR ENTIRE 1. SEE DWG. EL00.003 & EL00.004 FOR PHASING SEQUENCE OF CONSTRUCTION REQUIREMENTS.
CONSTRUCTION/INSTALLATION WORK TO GUARANTEE SMOOTH COMPLETION OF THE PROJECT. SEE OTHER ELECTRICAL DRAWINGS FOR ADDITIONAL DEMOLITION REQUIREMENTS.
2. FIELD SURVEY AND VERIFY EXACT LOCATION OF EXISTING EQUIPMENT AND CONTROL DEVICES 2. REMOVE ALL DEMOLISHED MATERIAL AND EQUIPMENT FROM SITE AND DISPOSE OF IN A
TO REMAIN. ALL EXISTING EQUIPMENT/SYSTEMS TO REMAIN SHALL BE PROTECTED DURING LAWFUL MANNER.
CONSTRUCTION.
3. SALVAGE EXISTING POWERLOGIC POWER MONITORS ALONG WITH WINDOW DISPLAY UNITS &
3. ALL PENETRATIONS OF WALLS, FLOORS, OR CEILINGS SHALL BE CORE DRILLED. SEAL AROUND ASSOCIATED CABLES IN 34.5KV & 5KV SWITCHGEAR AND TURNOVER TO MWAA.
CORE-DRILL OPENINGS AND RACEWAY/SLEEVES.
4. ALL INSTRUMENTATION, POWER AND CONTROL WIRING ASSOCIATED WITH SWITCHGEAR,
4. SIZE AND QUANTITY OF WIRING AND CONDUIT INDICATED ON THE SWITCHGEAR PANELS, DEVICES, EQUIPMENT, FIXTURES, ETC., INDICATED TO BE REMOVED, SHALL BE
SCHEDULE/POWER CONDUIT SCHEDULE SHALL APPLY TO THE ENTIRE LENGTH OF THE BRANCH REMOVED COMPLETELY UP TO SOURCE (SWITCHGEAR OR CONTROL PANEL) ALONG WITH
CIRCUIT/FEEDER, THROUGH ANY SWITCHES/DISCONNECTS/JUNCTION BOXES OR OTHER ASSOCIATED RACEWAYS. MARK ALL UNUSED CIRCUITS THAT ARE REMOVED FROM
INTERMEDIATE POINTS, ALL THE WAY UP TO FINAL LOAD CONNECTION UON. SWITCHGEAR/PANELBOARD AS SPARE CIRCUITS. IF THE MOUNTING SUPPORTS (METAL
CHANNELS AND OTHER MOUNTING DEVICES) FROM WHICH THE REMOVED EQUIPMENT ARE
5. KEEP ALL CONTROL WIRING IN SEPARATE RACEWAYS FROM OTHER/POWER WIRING. SUPPORTED, NO LONGER SERVE ANY PURPOSE, THEN THESE SUPPORTS SHALL ALSO BE
REMOVED.
6. PROVIDE INDEPENDENT SUPPORTS FOR ALL FREE STANDING SWITCHGEARS/EQUIPMENT AS
PER MANUFACTURER'S REQUIREMENTS. 5. ALL EXISTING EQUIPMENT TO REMAIN SHALL BE PROTECTED DURING CONSTRUCTION.
EXISTING EQUIPMENT DAMAGED DURING CONSTRUCTION SHALL BE REPLACED BY
7. ADJUST EXACT LOCATIONS OF EQUIPMENT AND DEVICES TO SUIT FIELD CONDITIONS. CONTRACTOR AT NO COST TO THE AUTHORITY.
8. DO NOT COMBINE FEEDER WIRING FOR DIFFERENT LOADS IN THE SAME RACEWAY. 6. CONTRACTOR SHALL FIELD VERIFY ALL EXISTING CIRCUITS TO REMAIN AND LABEL THEM
WITH PROPER IDENTIFICATION PER SPECIFICATIONS BEFORE STARTING DEMOLITION.
9. COORDINATE WITH ALL EXISTING FEEDERS ROUTING OVERHEAD/UNDERGROUND WITH NEW
EQUIPMENT FEEDERS CONNECTIONS BEFORE STARTING INSTALLATION OF SWITCHGEARS. 7. KEEP EXISTING ELECTRICAL CIRCUITS CONTINUOUS FOR EXISTING EQUIPMENT TO REMAIN.
CONTRACTOR SHALL COORDINATE ALL UTILITY LOCATING WORK WITH THE COTR AT LEAST 72 TRACE EACH CIRCUIT THAT IS TO BE REMOVED IN ORDER TO VERIFY THAT CIRCUITS
HOURS PRIOR TO COMMENCING WORK. FEEDING EXISTING EQUIPMENT TO REMAIN ARE NOT AFFECTED DURING THE DEMOLITION.
CONTRACTOR IS RESPONSIBLE FOR REPAIRING ANY EXISTING CIRCUIT TO REMAIN THAT IS
10. RONALD REAGAN NATIONAL AIRPORT SHALL REMAIN OPERATIONAL BEFORE, DURING AND DAMAGED OR REMOVED.
AFTER CONSTRUCTION. CONTRACTOR SHALL COORDINATE WITH THE COTR THE POWER
OUTAGE SCHEDULE, MINIMUM 30 DAYS IN ADVANCE, AND SHALL NOT PROCEED WITHOUT 8. ALL EXISTING POWER AND CONTROL WIRING TO BE AFFECTED DURING CONSTRUCTION
WRITTEN PERMISSION FROM THE COTR. CONTRACTOR SHALL BE ENTIRELY RESPONSIBLE FOR SHALL BE LABELED PER SPECIFICATIONS AT EACH TERMINATION OR SPLICE POINT SO AS TO
TEMPORARY CONSTRUCTION POWER. CONTRACTOR SHALL PROVIDE ALL TEMPORARY PERMIT EASE OF RECONNECTION OR EXTENSION OF THE WIRING.
ELECTRICAL CONNECTIONS AND EQUIPMENT. CONTRACTOR SHALL PROVIDE TEMPORARY
GENERATORS, PANELS & LIGHTING AS REQUIRED FOR CONSTRUCTION. 9. SEAL ANY OPENINGS IN CONDUIT BODIES, JUNCTION/PULL BOXES, ENCLOSURES, WALLS OR
CEILINGS CAUSED BY THE REMOVAL OF EXISTING RACEWAY AND/OR EQUIPMENT. PATCH
11. ALL 34.5KV, 5KV AND 480V REPLACED SWITCHGEAR CUBICLE SECTIONS MUST MEET EXISTING OPENINGS TO MATCH EXISTING CONDUIT BODIES, JUNCTION/PULL BOXES, ENCLOSURES,
SWITCHGEAR SECTIONS FOOT PRINT. WALLS OR CEILINGS. PAINT SURFACES TO MATCH EXISTING.
12. THE PHASING SEQUENCES FOR 34.5KV, 5KV AND 480V SWITCHGEAR ARE SCHEMATIC IN NATURE, 10. COORDINATE ELECTRICAL DEMOLITION WORK WITH THE COTR PER THE CONTRACT
CONTRACTOR SHALL PROVIDE FINAL PHASING SEQUENCE FOR EACH SWITCHGEAR FOR DOCUMENTS. FIELD VERIFY ALL EXISTING CONDITIONS PRIOR TO STARTING DEMOLITION
APPROVAL BY MWAA BEFORE STARTING THE WORK. WORK.
13. STAGING AREA SHALL BE COORDINATED WITH THE COTR PRIOR TO CONSTRUCTION. STAGING 11. PROVIDE TEMPORARY POWER, WIRING, CONDUIT, ETC. FOR CONTRACTOR'S CONSTRUCTION
AREA IS SUBJECT TO CHANGE PER DIRECTION FROM THE COTR AND/ORAS DETERMINED BY THE REQUIREMENTS.
AIRPORT'S REQUIREMENTS.
14. CONTRACTOR SHALL SUPPLY ALL HIGH VOLTAGE TESTING EQUIPMENT AND SAFETY EQUIPMENT
INCLUDING ITEMS REQUIRED FOR LOCK OUT/TAG OUT PROCEDURE.
PHASE 1:
PHASE 2:
1. THIS PHASE OF THE CONSTRUCTION WILL REQUIRE A TOTAL SHUTDOWN OF 480 VOLT SWITCHGEAR FP FOR A
PERIOD REQUIRED TO DISCONNECT AND ISOLATE THE BUSES IN THE SWITCHGEAR TO ENABLE REPLACEMENT OF 1. AT THE BEGINNING OF THIS PHASE BOTH FEEDERS FROM TRANSFORMERS T-3 AND T-4 ARE ACTIVE, AND THE
ONE MAIN, THREE FEEDER BREAKERS AND THE TIE BREAKER. PREVIOUS PHASE SWITCHGEAR IS OPTIONAL, THE NEW TIE BREAKER IS PRESENT AND TESTED, BUT NOT
OPERATIONAL OR CONNECTED TO THE EXISTING BUSES. ONLY A MOMENTARY OUTAGE SHOULD BE REQUIRED TO
2. BECAUSE TWO OF THE LOADS FED FROM THE SIDE TO BE REPLACED IN THIS PHASE HAVE NO OTHER SOURCE OF TRANSFER ALL LOAD TO THE NEW SWITCHGEAR.
POWER, TEMPORARY POWER SHALL BE PROVIDED TO THOSE LOADS FROM THE SIDE REMAINING ACTIVE DURING
THIS PHASE. PROVIDE TEMPORARY POWER AS SHOWN ON SHEET EL02.006 BEFORE REQUESTING THE OUTAGE. 2. PROVIDE TEMPORARY CONNECTIONS TO LOADS SERVED FROM BREAKERS 4B AND 4C TO NEW AVAILABLE SPARE
BREAKERS 1C AND 2B, RESPECTIVELY, ADJUST BREAKER SETTINGS TO MATCH EXISTING.
3. COORDINATING WITH COTR FOR INTENDED POWER OUTAGE DATE AND TIME. OUTAGE WILL BE PERMITTED ONLY
BETWEEN 12:00 MIDNIGHT AND 4:00 AM. WORK REQUIRING OUTAGES, SUCH AS SWITCHING FEEDERS, EQUIPMENT 3. COORDINATE WITH COTR TO ARRANGE FOR THE TRANSFER ALL LOADS TO THE TRANSFORMER T-3 (NEW) SIDE OF
REMOVAL, DE-ENERGIZING PORTIONS OF SWITCHGEAR, SHALL OCCUR WITHIN THE ALLOWED TIME PERIOD. THE 480 VOLT SWITCHGEAR FP, WHICH WILL REMAIN IN SERVICE DURING THIS PHASE.
CONTRACTOR SHOULD BE AWARE THAT THERE MAY BE OCCASIONS, DUE TO AIRPORT AND AIRLINE OPERATIONAL
REQUIREMENTS, SECURITY AND/OR EMERGENCIES WHEN THE SCHEDULED OUTAGE MAY HAVE TO BE CANCELED. IN 4. POWER OUTAGE FOR INCOMING 480 VOLT LINES FROM TRANSFORMER T-4 WILL OCCUR IN THE TRANSFORMER YARD
SUCH AN EVENT, RESCHEDULING OF WORK WILL BE NECESSARY AND SHOULD BE COORDINATED WITH THE COTR. OUTSIDE OF THE NORTH SUBSTATION AT THE AIRPORT'S PAD MOUNTED SWITCHES. SWITCHES WILL BE OPERATED
BY AIRPORT AUTHORITY.
4. POWER OUTAGE FOR INCOMING 480 VOLT LINES FROM TRANSFORMERS T-3 AND T-4 WILL OCCUR IN THE
TRANSFORMER YARD OUTSIDE OF THE NORTH SUBSTATION AT THE AIRPORT'S PAD MOUNTED SWITCHES. 5. REQUEST THAT MWAA OPEN SWITCH FOR TRANSFORMER T-4.
SWITCHES WILL BE OPERATED BY AIRPORT AUTHORITY.
6. PROVIDE SAFETY GROUNDS ON ALL DEACTIVATED BUSES AND CABLES.
5. AT LEAST 24 HOURS PRIOR TO THE 480 VOLT SHUTDOWN FOR PHASE 1, ARRANGE FOR THE TRANSFER OF ALL
LOADS TO THE SIDE OF THE 480 VOLT SWITCHGEAR THAT WILL REMAIN IN SERVICE DURING PHASE 1. THIS INCLUDES 7. DISCONNECT FEEDER CABLES FROM TRANSFORMER T-4 TO FP GEAR. PROVIDE INSULATED END CAPS SO
THE TEMPORARY FEED FOR LOADS ON BREAKERS 2C AND 2D. THE COB SWITCHBOARD ALSO NEEDS TO BE TRANSFORMER T-4 CAN BE RE-ENERGIZED TO PROVIDE POWER TO BOTH SIDES OF COB SWITCHBOARD DURING THE
TRANSFERRED TO TRANSFORMER T-4, PRIOR TO THE OUTAGE. REQUEST THAT MWAA OPEN AND LOCK-OUT THE REST OF THIS PHASE.
INCOMING 480 VOLT FROM BREAKER 2A TO THE COB UPS.
8. PROCEED WITH REMOVAL OF EXISTING AND INSTALLATION AND TESTING OF NEW EQUIPMENT AND 480 VOLT
6. REQUEST THAT MWAA OPEN SWITCH FOR TRANSFORMER T-3 FEEDERS, CONNECTORS AND SPLICES.
7. PROCEDURE AFTER ALL 480 VOLT POWER IS SHUT DOWN BY MWAA: 9. CONNECT NEW BUSES TO LOCKED OUT TIE BREAKER PROVIDED IN THE PREVIOUS PHASE.
a. OPEN INCOMING 480 VOLT MAIN CIRCUIT BREAKERS A AND B AND THE TIE BREAKER IN THE SWITCHGEAR. 10. RECONNECT FEEDER CABLES FROM TRANSFORMER T-4 TO FP GEAR. REPLACEMENT OF 480 VOLT FEEDER FROM
TRANSFORMER T-4 WILL BE DONE AFTER THIS PHASE, SEE SHEET EL06.007.
b. PROVIDE SAFETY GROUNDS ON ALL DEACTIVATED BUSES AND CABLES.
11. PROCEED TO ENERGIZE NEW EQUIPMENT WITHOUT LOAD TO TEST ALL OPERATIONS, THEN PROCEED TO TEST
c. CUT MAIN 480 VOLT BUS TO ISOLATE SIDE OF SWITCHGEAR CONTAINING MAIN CIRCUIT BREAKER A, TIE BREAKER SYSTEM IN STAGES TO MINIMIZE IMPACTS OR POSSIBLE OUTAGES.
AND FEEDER BREAKERS FED FROM MAIN A.
12. REMOVE TEMPORARY FEEDS FROM 'A' SIDE OF SWITCHGEAR AND PROVIDE NEW FEEDS TO SPLICE BOX TO
d. REMOVE 480 VOLT TIE BREAKER AND OTHER EQUIPMENT NECESSARY TO ISOLATE ALL EQUIPMENT TO BE CONNECT TO LOADS, PER SHEET EL02.007.
REPLACED IN THIS PHASE.
e. PROVIDE NEW INSULATED CAPS AND PHYSICAL BARRIER / PROTECTION FOR ENDS OF BUSES IN THE SIDE OF
THE 480 VOLT SWITCHGEAR THAT WILL RETURN TO LIVE STATUS DURING THIS PHASE.
f. PERFORM INSULATION RESISTANCE AND DIELECTRIC WITHSTAND VOLTAGE TESTS ON REMAINING 480 VOLT
BUSES PER NETA SPECIFICATIONS.
g. REQUEST THAT MWAA RESTORE POWER TO T-4 TO PROVIDE 480 VOLT FEEDER TO MAIN B FEEDERS IN FP AND
COB SWITCHBOARD. VERIFY THAT ALL EQUIPMENT IS FUNCTIONAL.
8. DISCONNECT FEEDER CABLES FROM TRANSFORMER T-3 TO FP GEAR. PROVIDE INSULATED END CAPS SO
TRANSFORMER T-3 CAN BE RE-ENERGIZED TO PROVIDE POWER TO BOTH SIDES OF COB SWITCHBOARD DURING THE
REST OF THIS PHASE.
9. PROCEED WITH REMOVAL OF EXISTING AND INSTALLATION AND TESTING OF NEW EQUIPMENT, INCLUDING NEW TIE
BREAKER AND 480 VOLT FEEDERS, CONNECTORS AND SPLICES.
10. ENERGIZE NEW EQUIPMENT WITHOUT LOAD TO TEST ALL OPERATIONS, THEN PROCEED TO TEST SYSTEM IN STAGES
TO MINIMIZE IMPACTS OR POSSIBLE OUTAGES.
11. RECONNECT FEEDER CABLES FROM FROM TRANSFORMER T-3 TO FP GEAR. REPLACEMENT OF 480 VOLT FEEDER
FROM TRANSFORMER T-3 WILL BE DONE AFTER THE NEXT PHASE, SEE SHEET EL06.007.
12. REMOVE TEMPORARY FEEDS FROM B SIDE OF SWITCHGEAR AND PROVIDE NEW FEEDS TO SPLICE BOX TO CONNECT
TO LOADS ON BREAKERS 2C AND 2D, PER SHEET EL02.007.
13. NEW BREAKERS IN COMPARTMENTS 1C AND 2B WILL BE USED IN THE NEXT PHASE TO PROVIDE TEMPORARY FEEDS
TO HANGAR 12 (BREAKER 4B) AND THE ATS (BREAKER 4C).
14. WHEN ALL EQUIPMENT HAS BEEN ACTIVATED AND ACCEPTED PROCEED TO NEXT PHASE.
PHASE 3: PHASE 5:
1. THIS CONSTRUCTION PHASE WILL REQUIRE A TOTAL SHUTDOWN OF THE NORTH SUBSTATION FOR THE PERIOD REQUIRED TO DISCONNECT AND ISOLATE THE SOLIDLY 1. THIS CONSTRUCTION WILL REQUIRE A TOTAL SHUTDOWN OF THE 5 KV SWITCHGEAR FOR THE PERIOD REQUIRED TO DISCONNECT AND ISOLATE THE BUSES IN
CONNECTED BUSES IN THE 34.5 KV SWITCHGEAR TO ENABLE REPLACEMENT OF ONE MAIN, TWO FEEDER AND THE TIE BREAKER. THE 5 KV SWITCHGEAR TO ENABLE REPLACEMENT OF ONE MAIN, TWO FEEDER AND THE TIE BREAKER.
2. COORDINATE WITH THE COTR FOR INTENDED POWER OUTAGE DATE AND TIME. OUTAGE WILL BE PERMITTED ONLY BETWEEN 12:00PM (MIDNIGHT) AND 4:00AM. WORK 2. COORDINATE WITH THE COTR FOR INTENDED POWER OUTAGE DATE AND TIME. OUTAGE WILL BE PERMITTED ONLY BETWEEN 12:00PM MIDNIGHT AND 4:00AM.
REQUIRING OUTAGES SUCH AS, SWITCHING FEEDERS, EQUIPMENT REMOVAL, DE-ENERGIZING PORTIONS OF SWITCHGEAR, SHALL OCCUR WITHIN THE ALLOWED TIME WORK REQUIRING OUTAGES SUCH AS, SWITCHING FEEDERS, EQUIPMENT REMOVAL, DE-ENERGIZING PORTIONS OF SWITCHGEAR, SHALL OCCUR WITHIN THE
PERIOD. CONTRACTOR SHOULD BE AWARE THAT THERE MAY BE OCCASIONS, DUE TO AIRPORT AND AIRLINE OPERATIONAL REQUIREMENTS, SECURITY AND/OR ALLOWED TIME PERIOD. CONTRACTOR SHOULD BE AWARE THAT THERE MAY BE OCCASIONS, DUE TO AIRPORT AND AIRLINE OPERATIONAL REQUIREMENTS,
EMERGENCIES WHEN THE SCHEDULED OUTAGE MAY HAVE TO BE CANCELED. IN SUCH AN EVENT, RESCHEDULING OF WORK WILL BE NECESSARY AND SHOULD BE SECURITY AND/OR EMERGENCIES WHEN THE SCHEDULED OUTAGE MAY HAVE TO BE CANCELED. IN SUCH AN EVENT, RESCHEDULING OF WORK WILL BE
COORDINATED WITH THE COTR. NECESSARY AND SHOULD BE COORDINATED WITH THE COTR.
3. TOTAL POWER OUTAGE FOR INCOMING LINES OF VIRGINIA POWER CIRCUITS 697 AND 698 WILL OCCUR AT THE AIRPORT'S PAD MOUNTED SWITCHES LOCATED NEAR THE 3. POWER OUTAGE FOR INCOMING 5 KV LINES FROM TRANSFORMER T-1 AND T-2 WILL OCCUR IN THE TRANSFORMER YARD OUTSIDE OF THE NORTH SUBSTATION AT
SHOPS BUILDING. SWITCHES SHALL BE OPERATED BY AIRPORT AUTHORITY. THE AIRPORT'S PAD MOUNTED SWITCHES. SWITCHES SHALL BE OPERATED BY AIRPORT AUTHORITY.
4. AT LEAST 24 HOURS PRIOR TO TOTAL SHUTDOWN FOR THIS PHASE, ARRANGE FOR THE TRANSFER OF ALL LOADS TO FEEDER 698 AND THE SIDE OF THE 34.5 KV 4. AT LEAST 24 HOURS PRIOR TO THE 5 KV SHUTDOWN FOR PHASE 3, ARRANGE FOR THE TRANSFER ALL LOADS TO THE SIDE OF THE 5 KV SWITCHGEAR THAT WILL
SWITCHGEAR THAT WILL REMAIN IN SERVICE DURING THIS PHASE. REQUEST THAT MWAA OPEN AND LOCK-OUT THE INCOMING 34.5 KV EQUIPMENT IN EACH LOAD SERVED REMAIN IN SERVICE DURING PHASE 3. REQUEST THAT MWAA OPEN AND LOCK-OUT THE INCOMING 5 KV EQUIPMENT IN EACH LOAD SERVED BY THE PHASE 3 SIDE
BY FEEDER 697. OF THE SWITCHGEAR.
5. TEST FEEDERS #697 & 3507 PER DWG EL02.002. 5. TEST FEEDERS #0404 & 0406 PER DWG EL02.004.
6. ARRANGE FOR TEMPORARY POWER FOR WORKING DURING TOTAL POWER OUTAGE PERIOD. 6. REQUEST THAT MWAA OPEN SWITCHES TO TRANSFORMER T-1 AND T-2.
7. REQUEST THAT MWAA OPEN INCOMING POWER SWITCHES FROM VIRGINIA POWER CIRCUITS 697 AND 698. 7. PROCEDURE AFTER ALL NORTH SUBSTATION 5 KV POWER IS SHUT DOWN BY MWAA:
8. PROCEDURE AFTER ALL POWER IS SHUT DOWN BY MWAA: a. OPEN INCOMING 5 KV MAIN CIRCUIT BREAKERS 0402, 0404, 0406 AND THE TIE BREAKER IN THE SWITCHGEAR.
a. OPEN INCOMING 34.5 KV MAIN CIRCUIT BREAKERS 3501, 3502 AND THE TIE BREAKER IN THE NORTH SUBSTATION. b. PROVIDE SAFETY GROUNDS ON ALL DEACTIVATED BUSES AND CABLES.
b. PROVIDE SAFETY GROUNDS ON ALL DEACTIVATED BUSES AND CABLES. c. CUT MAIN 5 KV BUS TO ISOLATE THE SIDE OF THE SWITCHGEAR CONTAINING MAIN CIRCUIT BREAKERS 0402, AND FEEDER BREAKERS 0406 AND 0406.
c. CUT MAIN 34.5 KV BUS TO ISOLATE SIDE OF SWITCHGEAR CONTAINING MAIN CIRCUIT BREAKER 3501, AND FEEDER BREAKERS 3505 AND 3507. d. REMOVE 5 KV TIE BREAKER AND OTHER EQUIPMENT NECESSARY TO ISOLATE ALL EQUIPMENT TO BE REPLACED IN THIS PHASE.
d. REMOVE 34.5 KV TIE BREAKER AND OTHER EQUIPMENT NECESSARY TO ISOLATE ALL EQUIPMENT TO REPLACED IN THIS PHASE. e. PROVIDE NEW INSULATED CAPS AND PHYSICAL BARRIER/PROTECTION FOR ENDS OF BUSES IN THE SIDE OF THE 5 KV SWITCHGEAR THAT WILL RETURN TO LIVE
STATUS DURING THIS PHASE.
e. PROVIDE NEW INSULATED CAPS AND PHYSICAL BARRIER/PROTECTION FOR ENDS OF BUSES IN THE SIDE OF THE 34.5 KV SWITCHGEAR THAT WILL RETURN TO LIVE
STATUS DURING THIS PHASE. f. PERFORM INSULATION RESISTANCE AND DIELECTRIC WITHSTAND VOLTAGE TESTS ON REMAINING 5 KV BUSES PER NETA SPECIFICATIONS.
f. PERFORM INSULATION RESISTANCE AND DIELECTRIC WITHSTAND VOLTAGE TESTS ON REMAINING 34.5 KV BUSES PER NETA SPECIFICATIONS. g. REQUEST THAT MWAA RESTORE POWER TO 5 KV FEEDER 0401 AND VERIFY THAT ALL EQUIPMENT IS FUNCTIONAL.
g. REQUEST THAT MWAA RESTORE POWER TO NORTH SUBSTATION FEEDER 698 AND VERIFY THAT ALL EQUIPMENT IS FUNCTIONAL. 8. PROCEED WITH REMOVAL OF EXISTING AND INSTALLATION AND TESTING OF NEW EQUIPMENT INCLUDING NEW TIE BREAKER AND 5 KV FEEDERS AND
CONNECTORS/SPLICES.
9. PROCEED WITH REMOVAL OF EXISTING AND INSTALLATION AND TESTING OF NEW EQUIPMENT INCLUDING NEW TIE BREAKER AND 34.5 KV FEEDERS AND
CONNECTORS/SPLICES. 9. PROCEED TO ENERGIZE NEW EQUIPMENT WITHOUT LOAD TO TEST ALL OPERATIONS, THEN PROCEED TO TEST SYSTEM IN STAGES TO MINIMIZE IMPACTS OR
POSSIBLE OUTAGES.
10. REPLACEMENT OF EXISTING ELECTRICAL ALARM ANNUNCIATOR WITH NEW HMI SYSTEM CAN PROCEED DURING THIS PHASE OR PRIOR SINCE NO AUTOMATIC CONTROLS
NEED TO BE IN PLACE TO OPERATE THE SYSTEM. 10. WHEN ALL EQUIPMENT HAS BEEN ACTIVATED AND ACCEPTED, PROCEED TO NEXT PHASE.
11. PROCEED TO ENERGIZE NEW EQUIPMENT WITHOUT LOAD TO TEST ALL OPERATIONS, THEN PROCEED TO TEST SYSTEM IN STAGES TO MINIMIZE IMPACTS OR POSSIBLE
OUTAGES.
PHASE 6:
12. WHEN ALL EQUIPMENT HAS BEEN ACTIVATED AND ACCEPTED PROCEED TO THE NEXT PHASE.
1. AT THE BEGINNING OF THIS PHASE BOTH FEEDERS FROM TRANSFORMER 1 AND 2 ARE ACTIVE, AND THE NEW 5KV SWITCHGEAR IS OPERATIONAL, THE NEW TIE
BREAKER IS PRESENT AND TESTED, BUT NOT OPERATIONAL OR CONNECTED TO THE EXISTING BUSES. ONLY A MOMENTARY OUTAGE SHOULD BE REQUIRED TO
TRANSFER ALL LOAD TO THE NEW SWITCHGEAR.
PHASE 4:
2. COORDINATE WITH THE COTR TO ARRANGE FOR THE TRANSFER ALL LOADS TO THE NEW SIDE OF THE 5 KV SWITCHGEAR, WHICH WILL REMAIN IN SERVICE DURING
1. AT THE BEGINNING OF THIS PHASE BOTH FEEDERS 697 AND 698 ARE ACTIVE, AND THE NEW 34.5KV SWITCHGEAR IS OPERATIONAL, THE NEW TIE BREAKER IS PRESENT AND THIS PHASE.
TESTED, BUT NOT OPERATIONAL OR CONNECTED TO THE EXISTING BUSES. ONLY A MOMENTARY OUTAGE SHOULD BE REQUIRED TO TRANSFER ALL LOAD TO THE NEW
SWITCHGEAR. 3. REQUEST THAT MWAA OPEN AND LOCK-OUT THE EQUIPMENT SERVED BY FEEDERS 0405, 0407 AND 0409.
2. AT LEAST 24 HOURS PRIOR TO SHUTDOWN FOR THIS PHASE, COORDINATE WITH THE COTR TO ARRANGE FOR THE TRANSFER ALL LOADS TO FEEDER 697 AND THE NEW 4. TEST FEEDERS #0405 & 0409 PER DWG EL02.005.
SIDE OF THE 34.5 KV SWITCHGEAR THAT WILL REMAIN IN SERVICE DURING PHASE 2.
5. PROCEED WITH REMOVAL OF EXISTING AND INSTALLATION AND TESTING OF NEW EQUIPMENT AND 5 KV FEEDERS AND CONNECTORS/SPLICES.
3. REQUEST THAT MWAA OPEN AND LOCK-OUT THE INCOMING 34.5 KV EQUIPMENT IN EACH LOAD SERVED BY FEEDER 698.
6. CONNECT NEW BUSES TO LOCKED OUT TIE BREAKER PROVIDED IN THE PREVIOUS PHASE.
4. TEST FEEDERS #698 & 3506 PER DWG EL02.003
7. PROCEED TO ENERGIZE NEW EQUIPMENT WITHOUT LOAD TO TEST ALL OPERATIONS, THEN PROCEED TO TEST SYSTEM IN STAGES TO MINIMIZE IMPACTS OR
5. PROCEED WITH REMOVAL OF EXISTING AND INSTALLATION AND TESTING OF NEW PHASE 2 EQUIPMENT AND 34.5 KV FEEDERS AND CONNECTORS/SPLICES. POSSIBLE OUTAGES.
7. PROCEED TO ENERGIZE NEW EQUIPMENT WITHOUT LOAD TO TEST ALL OPERATIONS, THEN PROCEED TO TEST SYSTEM IN STAGES TO MINIMIZE IMPACTS OR POSSIBLE
OUTAGES.
MAIN-A FEEDER FEEDER BUS-A TIE MAIN-B BUS-B FEEDER FEEDER 7 EXISTING GROUNDING CONNECTION FOR SWITCHGEAR SECTIONS TO
BKR 3501 BKR 3505 BKR 3507 RELAYS BKR 3503 BKR 3502 RELAYS BKR 3504 BKR 3506 REMAIN, SHALL BE MAINTAINED AS IT IS IN PHASE-1.
3
34.5KV
3503
1200A
1200A
50 50N 50 50N 50 50N 50 50N DRAWING NOTES
51 51N 51 51N 51 51N 51 51N
1200A 1200A 1200A 1200A
1 EXISTING FEEDER-698 FROM S&C SERVICE DISCONNECT SWITCH
3507 3505 3504 3506 (INCOMING UTILITY POWER, LOCATED IN YARD, NEAR SHOPS
BUILDING) TO 34.5KV SWITCHGEAR. AFTER OPENING YARD
SWITCHES, PERFORM INSULATION RESISTANCE TEST PER NETA
ATS OF CABLES FROM YARD TO NORTH SUBSTATION. AFTER
RECORDING AND REPORTING TEST RESULTS TO COTR, REMOVE
PART OF THIS MAIN FEEDER-698 FROM MANHOLE ED-105 TO
2 8 34.5KV SWITCHGEAR. SEE DWG EL06.001 FOR NEW FEEDER
REQUIREMENT & EL04.005 FOR LOCATION.
5 5 TO 34.5 KV TO MANHOLE 2 REMOVE EXISTING 34.5KV FEEDER TO SWITCH. SEE DWG. EL06.001
SWITCH SW-2 ED-105 FOR NEW FEEDER REQUIREMENT & EL04.005 FOR LOCATION.
4160V 1
0403
1200A 50 50N 50 50N 50 50N 50 50N 50 50N 50 50N
51 51N 51 51N 1200A 51 51N 51 51N 51 51N 51 51N
1200A 1200A 1200A 1200A 1200A 1200A DRAWING NOTES
0406 0404 0407 0405 0409 0411
1 REMOVE EXISTING 5KV SWITCHGEAR ALONG WITH
ASSOCIATED BREAKERS, RELAYS, & CONTROLS AS SHOWN.
MAIN BUS AUTO TIE CONTROL NO LABEL CPT MAIN BUS DRAWING NOTES
SPACE CPT CONTROLS 1600AT FUSES RECEPT.
METERING 800AT SPACE GFP 300AT GFP 1200AT AND 800AT 800AT GFP 300AT 1200AT GFP 800AT METERING
1600AF 1 EXISTING 480V FEEDER TO BE REMOVED AND REPLACED AS
800AF 800AF 1600AF POWER 800AF 800AF 800AF 1600AF 1600AF
PART OF DOUBLE TAP CORRECTION AFTER PHASE 2.
CONNECTOR 4
2 EXISTING BRANCH FEEDER TO REMAIN.
MAIN-A 2-4" CONDUIT EACH WITH MAIN-B 4 ADJUST & TEST EXISTING 1200AT/1600AF BREAKER TRIP
3-500 KCMIL & #1/0 GROUND SETTING TO 800AT, FOR TEMPORARY FEED.
6
221" CONDUIT WITH TEMPORARY FEEDER
3#1/0 & #1/0 GROUND 5 TRANSFER LOADS FED FROM EXISTING FEEDERS SECTION-2C
6 6 & SECTION-2D TO TEMPORARY CIRCUIT BREAKERS, AS PER
9 2 2 2
PHASING SEQUENCE. REFER TO DWG EL00.003 FOR PHASING
300A 600A SEQUENCE.
COB COB HANGER 12 ATS
UPS EXIST. UPS USAIR 400HZ 150A
JUNCTION 6 PROVIDE TEMPORARY WIRE TROUGH (SIZE AS REQUIRED PER
BOX NEC) & ENCLOSED CIRCUIT BREAKERS, 300AMP 480V, 3P 3W,
30KAIC BREAKER TO FEED PANELS (SECTION-2C) & 600AMP
5 5 480V, 3P 3W, 30KAIC BREAKER TO FEED TV-6A (SECTION-2D), AS
TV-6A PER PHASE-1 PHASING SEQUENCE. SPLICE TEMPORARY
PANELS - PHALS, SWITCHGEAR FEEDERS FROM SECTION 4D WITH 2 SETS OF (3-500KCM & 1/0
PHARS, LIGHT CONTROL
G) FOR 600A BREAKER & ONE SET OF 3-500KCM & 1/0 G FOR
PANEL
300A BREAKER IN TEMP. WIRE TROUGH. REFER TO DWG
EL00.003 FOR PHASING SEQUENCE DETAILS.
1 480V SWITCHGEAR - SINGLE LINE DIAGRAM - DEMOLITION
EL02.006 7 VERIFY AND DISCONNECT EXISTING GROUND CONNECTION TO
PHASE-1 EXISTING SUBSTATION GROUND SYSTEM CAREFULLY.
EXISTING GROUNDING TO BE RE-USED.
DRAWING NOTES
1 PROVIDE 34.5KV SWITCHGEAR AS SHOWN. PREFER TO
SPECIFICATIONS FOR DETAILS.
1 34.5KV MEDIUM VOLTAGE SWITCHGEAR - PLAN
EL04.002
2 ELEVATION
EL04.003
DRAWING NOTES
1 PROVIDE 480V SWITCHGEAR AS SHOWN.
7 7 7
3 4 5 6
5KV/120V CPT 120V/5KV CPT 2 NEW 5KV FEEDER FROM TRANSFORMER T1 TO 5KV BREAKER
PQM PQM 0402 WITH 3- #4/0 & 4/0 G IN EXISTING 4" RACEWAY.
8 8 8
SPARE
4 FROM TRANSFORMER FROM TRANSFORMER REFER TO DWG EL00.003 FOR 480V CONSTRUCTION PHASING
T-3 T-4 SEQUENCE.
FROM GENERATOR SEE DWG. NO. EL06.004 SEE DWG. NO. EL06.004
FUTURE CONNECTION MAIN BREAKERS & TIE BREAKER SHALL HAVE 'EUT776'
ELECTRONIC TRIP UNIT AND BRANCH BREAKERS SHALL HAVE
'EUT745' ELECTRONIC TRIP UNIT.
1
NORTH SUBSTATION 480V SWITCHGEAR
83 DRAWING NOTES
CPT-G CPT-A CPT-B
480V/120V 480V/120V 480V/120V
1 PROVIDE 480V SWITCHGEAR AS SHOWN.
600A:5A
UPS UPS
(TYP.) 2 FEEDER REPLACED AS PART OF DOUBLE TAP CORRECTION.
PT SIEMENS SIEMENS SIEMENS SEE DWG EL06.007 FOR DETAILS.
PLC
480V/120V 25 25 25
27 59 2 27 59 2 PLC 27 59 2 3 NEW FEED TO COB. SEE DWG EL06.007 FOR DETAILS.
47 PT 47 47 PT 480V/120V
7SJ80 7SJ80 7SJ80 4 GENERATOR BREAKER FOR FUTURE EMERGENCY POWER, SEE
480V/120V 480V/120V
SPECIFICATIONS FOR DETAILS.
PT(TYP.)
1B 1A 1C 1D 2B 2A 2C 2D 3A 3B 3C 3D 4A 4B 4C 4D 5A 5B 5C 5D 6D 6C 6A 6B
AUTO CONTROL CONTROLS MAIN BUS-B
GENERATOR SPACE CPT-G MAIN BUS-A CPT-A TIE CPT-B
CONTROLS FUSES RECEPT. METERING
POWER METERING
METERING 1200AT 800AT 800AT 300AT 600AT 1600AT & POWER 800AT 800AT 150AT 800AT 1200AT
1600AF 800AF 800AF 800AF 800AF 1600AF CONNECTOR 800AF 800AF 800AF 800AF 1600AF
LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG LSIG
3 3
SPARE SPARE
MAIN-A MAIN-B
TO BE USED COB UPS PANELS TV-6A COB UPS HANGAR 12 ATS 150A TO BE USED FOR
FOR COB SEE PHALS SWITCHGEAR USAIR TO FEED COB SEE DWG.
DWG. NO. EL06.007 PHARS 400HZ PANEL EPHA NO. EL06.007
LIGHTING
CONTROL
PANEL
27 27
47 47
59 59
51N 51 51 51N
1200A 1200A
86 3501 3502 86
35KV
3503
1200A
REFER TO DWG.
EL06.006 FOR
CONTINUATION
L T R R T L
1600AT TIE
1600AF 3200AT
REFER TO DWG. REFER TO DWG. 3200AF
FP GEAR
EL06.005 FOR MAIN B MAIN A EL06.005 FOR
CONTINUATION CONTINUATION PARKING STRUCTURE B/C
A1600AT 1600AT
TO 5KV SWITCHGEAR 1600AF TIE 1600AF TO 5KV SWITCHGEAR
MAIN-A MAIN-B
1600AT
0401 1600AF 0402
COB SWITCHBOARD
NORTH SUBSTATION
4160V SWITCHGEAR
27 27
47 47
59 59
51N 51 51 51N
1200A 1200A
86 0402 0401 86
4160V
0403
1200A 50 50N 50 50N 50 50N 50 50N 50 50N 50 50N
51 51N 51 51N 1200A 51 51N 51 51N 51 51N 51 51N
1200A 1200A 1200A 1200A 1200A 1200A
EXIST.
PULL
BOX
ED-105 ED-105
ED-106 ED-106
ED-107 ED-107
ED-108 ED-108
ED-109 ED-109
100E 35E
34.5KV 5KV
SWITCHGEAR 120V AC SWITCHGEAR 120V AC 120V AC
480V SWITCHGEAR
RELAY FEEDER BKR RELAY FEEDER BKR RELAY 3. ALL PLCS AND ALL INTELLIGENT RELAYS AND ALL BREAKERS IN EACH OF THREE SWITCHGEARS (34.5KV,
MAIN BKR B
PQM 5KV, 480V SHALL ) SHALL RESIDE ON SAME COMMUNICATION NETWORK.
RELAY FEEDER BKR RELAY FEEDER BKR 4. A SEPARATE ENCLOSURE IN THE SUBSTATION SHALL CONTAIN HUMAN MACHINE INTERFACE (HMI)
ETU FEEDER BKR PANEL, PLC, NETWORK SWITCH AND DUAL INPUT POWER SUPPLY THAT POWERS TO ALL EQUIPMENT IN
THE ENCLOSURE. INPUT POWER TO ENCLOSURE SHALL BE 120 VAC, PROVIDED BY EXISTING PANEL
RELAY FEEDER BKR RELAY FEEDER BKR 'EPA' IN THE SUBSTATION, A DUAL INPUT (120VAC & UPS) PROVIDES 120V AC POWER FOR ALL
ETU FEEDER BKR EQUIPMENT IN THE PANEL. HMI AND PLC IN THIS PANEL SHALL BE ON SAME NETWORK AS THE PLCS
AND BREAKERS AND RELAYS IN THE SWITCHGEARS. THE NETWORK SWITCH IN THIS ENCLOSURE SHALL
ALSO PROVIDE FIBER OPTIC CONNECTION POINT FOR FUTURE SITE-WIDE SCADA SYSTEM, (SCADA =
RELAY FEEDER BKR RELAY FEEDER BKR
ETU FEEDER BKR SUPERVISORY CONTROL AND DATA ACQUISITION). EXISTING TRANSFORMERS LOCATED OUTSIDE THE
SUBSTATION ARE EQUIPPED WITH SENSORS TO MONITOR TRANSFORMER OIL SYSTEMS. THESE
EXISTING SIGNALS ARE CONNECTED AS INPUTS AND OUTPUTS (I/O) TO THE PLC IN THE HMI
RELAY FEEDER BKR ENCLOSURE. EXISTING INCOMING SENSOR-SIGNAL WIRES SHALL REMAIN DURING DEMOLITION & BE
ETU FEEDER BKR
PROTECTIVE RECONNECTED TO NEW HMI PANEL.
RELAY
(TYP.) RELAY FEEDER BKR
ETU FEEDER BKR 5. PROVIDE SHOP DRAWING FOR COMPLETE HMI SYSTEM FOR REVIEW AND APPROVAL PRIOR TO
ASSEMBLY/FABRICATION. SHOP DRAWING SHALL INCLUDE BILL OF MATERIAL, WIRING DIAGRAMS,
EQUIPMENT LAYOUT DRAWINGS, CATALOG CUT SHEETS FOR ALL EQUIPMENT IN THE HMI PANEL. REFER
FIBER OPTIC ETU FEEDER BKR SPECIFICATIONS FOR DETAILS.
(MODBUS/PROFIBUS/IEC 61850)
OR COPPER (TYP.)
HMI ETU FEEDER BKR
PANEL
PLC
ETU FEEDER BKR
SWITCH
ETU FEEDER BKR
HMI
120V AC
POWER SUPPLY
EXISTING INCOMING SIGNALS EXISTING INCOMING SIGNALS
ETHERNET TO UPS
BUSINESS
T1 TRANSFORMER T4 TRANSFORMER
COMPUTER
TEMP. LEVEL, PRESSURE TEMP. LEVEL, PRESSURE
ION NETWORK