0 COMPLETION PERIODS:
6.1 Mobilization Period
6.1.1A For Tank Preparatory Services
A Period of 1 day shall be allowed for mobilization.

6.1.1B For Tank Cleaning Works


A period of 1 day per tank will be allowed.
6.1.2 For Tank Repair, Fiberglassing & Painting Works
A period of 3 days per tank will be allowed.
6.2A Calculation of Completion Periods for Tank Preparatory Services:

(a) The following time periods shall be allowed for blinding & shell man-ways
opening.

Tank Dia. No. of Days


Up to 130 ft. 2
Above 130 ft. 3

(b) Following time period shell be allowed for stripping the Tank.

1 Day for stripping 60 M3 of products / water from the Tanks.

(c) The following time period shall be allowed for degassing.

ATK / Naphtha All other


Tank dia.
(Days) (Days)
Up to 130 ft. 4 3
Above 130 ft. 7 5

(d) 1 Day shall be allowed for opening of roof man ways.

6.2B Calculation of Completion Periods for Tank Cleaning Works:


The completion time for all work activities of each tank will be determined individually by
the Company based on the following parameters / activities :
Total completion period shall be the sum of periods calculated per clause # 6.2.1 and 6.2.2.
Additional period will be allowed by the Company depending on tank service, internals,
non-availability of cleanout door, requirement of scaffolding etc., as specified under clause
# 6.2.3 hereof.
6.2.1 Completion Periods based on Type of Sludge
For Heavy Product Sludge: - 1 Day for every 40 M3 of sludge (Crude Oil, Fuel
Oil, Coker Gas Oil, Vacuum Gas Oil and Vacuum Residue Storage Tanks).
For Light Product Sludge: -1 Day for every 60 M3 of sludge (Naphtha,
Kerosene, ATK, Motor Gasoline and Diesel Oil Storage Tanks and any type of
water storage tanks).
6.2.2 Completion Periods for all types of cleaning
works(Washing & wiping)

Tank Dia. Fltg. Roof Tank Fixed Roof Tank

Upto130 ft.. 2 days 3 days

Above 130 ft. 4 days 6 days

6.2.3 Additions/Extensions Allowed over Compellation


Period:

SR. ITEM DESCRIPTION ALLOWED EXTENSION PERIOD


NO. (CALENDAR DAYS)
1. Cleaning of tanks Containing One day extra for every ten days of
products in lead hazardous class completion period
2. Cleaning of tanks having heating One days extra for every ten days of
coils completion period
3. Cleaning of tanks in MEA / One day extra is allowed over
Chemical service with Arsenic completion period
inhibitor.
4. Cleaning of sulfur / Bitumen Two days extra will be allowed for
storage tanks every ten days of completion Period
5. In the event that Scaffolding is One day extra is allowed per 1500
Required cu.m. of scaffolding

6. Cleaning of tanks without One day extra will be allowed for


Cleanout Door every ten days of Completion period.

7. In the event that Sweep/Abrasive One day extra per 300 sq.m. of
blasting is sweep-blasted area.
Required
9. In the event that Floating roof Two days
external washing is Required
10. In the event that Scarp cleaning of One day extra per 50 sq.m.
concrete basins is required

6.2.4 DELAY EXTENSIONS :


a) The Contractor may sometimes be restricted from working due to delays caused
by the Company operational reasons, Inspection of existing tank conditions, any
other reasons/Company requirements or inclement weather and the like.
Superintendent shall be the sole judge as to whether the weather is sufficiently
inclement to have the work stopped.
b) In case of such delay getting rectified within two hours no time extension will be
allowed.
c) If the Contractor is completely prevented from working due to such delays for
more than two continuous hours of the working day then the Contractor has to
notify the Company representative within 24 hours in writing of such delay.
The Contractor will be allowed time extension for equal period.
d) If such a delay exceeds four hours of the working day then an extension of one
working- day will be granted against each working day during which such delay
occurred.
e) In all above cases, all waiting times incurred shall be solely at the cost of the
Contractor and the Company shall not pay any compensation at all for the idling of
his manpower/equipment (except as allowed in Clause No. 4.6 (b) of Part-II,
Exhibit-A).
6.3 COMPLETION PERIODS FOR TANK REPAIR,
FIBREGLASSING & PAINTING WORKS
6.3.1 COMPLETION PERIODS-CALCULATION BASIS FOR EACH TANK
The completion time for each tank will be determined individually, based on the tank
diameter for complete re-bottoming, re-roofing or on the area basis for patch work on
shell, roof and tank bottom, fiberglass lining and painting of tank etc., the higher
figures (only one figure from each group) from each of the following applicable
group will be added together to conclude the total completion period and this shall not
be less than five (5) days besides the mobilization period. Completion period for
Group-V Activities (Miscellaneous) will be independent and will be added to the
completion period calculated for the other Groups.
Completion time includes all inspection, testing, scaffolding and hydrostatic testing as
required by Companys Inspection & Corrosion Division.
Sample Calculation for Completion Period :
Example 1: Fixed roof of 130' dia. needs following repair
work.
Activity
a) Re-bottoming (Complete new Bottom).

b) 120 sq.m. patching/repairing/partial replacement on shell course.

c) Full shell external painting.

d) Roof external painting.

e) Hydrostatic testing with 8000 M3 of water, with water hold up for four (4)
days during Inspection check and four (3) days for cleaning tank after
hydrotest.

Now based on Table 6.3.2 of the Specification


Completion time for activity (a) above is 45 days.

Completion time for activity (b) above is 15 days.


Completion time for activity (c),(e) and (d) above is 35 days.

Completion time for activity (e) above is (4+4+3) 11 days.

Computation of Total Completion Period


1. Activity (a) & (b) above is part of Group-I and the longer completion time
between the two is 45 days, hence Group-I activities will be given 45 days.

2. Activity (c) & (d) above is part of Group-IV and the longest completion time
between the two is 40 days, hence Group-IV activities will be given 35 days.

3. Activity (e) is only activity of Group-V, hence the same will be given 11 days.

Therefore, total completion time will be sum of Group-I, IV & V above i.e.
45+ 35 + 11 = 91 days besides mobilization time of 3 days.

Example 2: Floating roof of 180' dia. needs following repair work.

Activity
a) Complete re-roofing including all structural repair work if any.

b) Repair shell & bottom plates 480 sq.m.

c) Replacement of sealing system 150 m. long.

d) Repair of Fiberglass work 480 sq.m. (As per Technical Specification No. 5).

e) Full shell external painting.

f) Roof external painting.

g) Hydrostatic testing with 6000 M3 of water, with water hold up for two (2)
days during Inspection work and three (3) days for cleaning tank after
hydrotest.
Now based on Table 6.3.2 of the Specification
Completion time for activity (a) above is 755 days.

Completion time for activity (b) above is 60 days.

Completion time for activity (c) above is 8 days.

Completion time for activity (d) above is 10 days.

Completion time for activity (e) if above is 35 days.

Completion time for activity (f) above is 25 days.


Completion time for activity (g) above is (3+2+3) = 8 days.

Computation of Total Completion Period


1. Activity (a) & (b) above is part of Group-I and the longest completion time
between the two is 75 days, hence Group-I activities will be given 75 days.
2. Activity (c) above is the only activity of Group-II, hence the same will be given 8
days.
3. Activity (d) is only activity of Group-III, hence the same will be given 10 days.
4. Activity (e) & (f) is part of Group-IV, and completion time between the two is 35
days.
5. Activity (g) is the only activity of Group-V, hence the same will be given 8 days.

Therefore, total completion time will be sum of Group-I to Group V above i.e. 75 +
8 + 10 + 35 + 8 = 136 days besides mobilization time of 7 days.

6.3.2 COMPLETION PERIOD


The following table showing no of maximum days allotted for each activity of work.
The figures in the following tables for Group I, II, III, IV & V activities indicate the
number of days unless specified otherwise.
Group I Activities (Plate Work and As Mentioned Below)

Tank Diameter in Feet

Sr. Activity Upto Over Over Over Over Over Over


No. Description 30 Ft 30 Ft 60 Ft 90 Ft 120 Ft 150 Ft 200 Ft
upto upto upto upto upto
60 Ft 90 Ft 120 Ft 150 Ft 200 Ft
1 Re-bottoming 15 20 25 30 45 55 65
(Complete new bottom
including soil side painting)
2(A) Complete re-roofing 30 35 40 55 60 70 75
(Fixed Roof Tank)
including all structural work
and underside painting of
roof plates.
2 (B) Complete re-roofing 35 40 45 60 65 75 80
(Floating Roof Tank)
including all structural work.
3(A) Patching/partial 8 Sq.M. or part thereof per day
Replacement/Repairing
shell, roof and bottom plate.
3(B) Scattered patching of sizes 5 Sq. M. or part thereof per day.
less than 2.5 Sq.Ft.
Group II Activities (Structural Work and Sealing System)
Tank Diameter in Feet

Sr. Activity Upto Over Over Over Over Over Over


No. Description 30 Ft 30 Ft 60 Ft 90 Ft 120Ft 150Ft 200Ft
upto upto upto upto upto
60 Ft 90 Ft 120Ft 150Ft 200Ft

5 Repair/Replacement 1/4 Ton or part thereof per day.


to fixed roof
Tank structure only

6 Repair/Replacement 1/4 Ton or part thereof per day.


to floating
roof tank structure
Only

7 Replacement of 20 Meters or part thereof per day.


sealing system on
floating roof.

Group III Activities (Fibre-glassing)


Tank Diameter in Feet
Sl No. Activity Upto Over Over Over Over Over Over
Description 30ft 30ft 60ft 90ft 120ft 150ft 200ft
upto upto upto upto upto
60ft 90ft 120ft 150ft 200ft
8.1 Application of
Fiberglass lining 10 10 15 15 20 25 30
(Tank bottom & lower
shell course) as per
Tech. Spec. No.4
8.2 Application of
Fiberglass lining 15 20 25 30 35 40 45
(Tank bottom & lower
shell course) as per
Tech. Spec. No. 10
9.1 Repair of Fiberglass As per Technical Specification No. 5.2.1
50 sq. M. or part thereof per day
9.2 Repair of Fiberglass As per Technical Specification No. 5.2.2
25 sq. M. or part thereof per day

NOTE :
i) Final curing time of fibreglass work is not included in the completion
time.
ii) For item no. 9.1 - For repair of Fiberglassing areas less than 200 sq. M, 5 days will be
allotted.

iii) For item no. 9.2 - For repair of Fiberglassing areas less than 100 sq. M, 5 days will be
allotted.

iv) Where it is required to repair fiberglass only under the roof legs the time duration for
repair of one group 20% of legs shall be 3 days. The total time duration for repair of
fiberglass under legs shall be calculated based on the number of groups of legs to be
repaired at 3 days per group. The number of groups of legs shall be decided by the
Superintendent's Representative. This time shall be allowed over and above the time
required for repair of fiberglass at other areas other than that under legs.

v) Time allotted for removal of lining shall be at the rate of 200 sq.m/day.

Group IV Activities (Painting)

Tank Diameter in Feet

Sr. Activity Upto Over Over Over Over Over Over


No. Description 30 Ft 30 Ft 60 Ft 90 Ft 120 150 200
upto upto upto Ft Ft Ft
60 Ft 90 Ft 120 upto upto
Ft 150 200
Ft Ft

10 Tank bottom Inside 5 8 10 12 14 16 18


(Complete)

11(A) Full shell External 10 12 14 18 20 25 30

11(B) Full Shell external and 15 20 25 30 35 40 45


Roof external.
12 Upto 3 feet shell
internal/external 3 4 6 7 8 10 12
(Lower or Upper shell)

13(A) Roof Internally 6 8 10 14 15 18 20


Floating Roof

13(B) Column Supported Roof 8 10 14 16 18 20 25

13(C) Truss Supported Roof 10 12 16 20 25 30 35

14(A) Roof Externally: 7 8 10 14 15 18 20


Cone Roof

14(B) Floating Roof 8 10 12 17 18 20 25


Tank Diameter in Feet

Sr. Activity Upto Over Over Over Over Over Over


No. Description 30 Ft 30 Ft 60 Ft 90 120 150 200
upto upto Ft Ft Ft Ft
60 Ft 90 Ft upto upto upto
120 150 200
Ft Ft Ft

15 Full shell 5 10 15 20 25 30 35
Internal

16(A) Roof internally 10 15 20 25 30 35 40


& bottom/Plate/Shell partial
Foating Roof

16(B) Column supported Roof 15 20 30 40 45 50 55


internal/Bottom plate/Shell
top and bottom(3 feet)

16(C) Truss supported 20 25 35 45 50 55 60


Roof internal/bottom
plate/Shell top and bottom
( 3 feet)

17(A) Full roof, shell & bottom 20 25 30 35 40 45 50


internally Floating Roof

17(B) Column supported Roof 25 30 40 50 55 60 65

17(C) Truss supported 30 35 45 55 60 65 70


Roof
COMPLETION PERIOD : (Cont'd)

Group V Activities (Miscellaneous)

Tank Diameter in Feet

Sr. Activity Upto Over Over Over Over Over Over


No. Description 30 Ft 30 Ft 60 Ft 90 120 150 200
upto upto Ft Ft Ft Ft
60 Ft 90 Ft upto upto upto
120 160 200
Ft Ft Ft
18 Hydrostatic testing. 2500 Cubic M or part thereof per day plus actual time of
Actual volume of water hold up during Inspection(Minimum 24Hrs), plus (3)
water required for days for cleaning after drainage of water
Hydrostatic testing.
19(A) Skirting repair work 50 Sq. Meter per day.

19B) Tank farm dyke repair 15 Cubic Meter per day.


work
20(A) Floating Roof 3 Calendar days per tank.
drain line repair.

20(B) Floating Roof drain 8 Calendar days per tank.


line replacement

21 Fiber Glassing 150 Sq. meter per calendar day.


removal.
22(A) Calibration of Tanks 1 Calendar days.
upto 150 feet in
diameter.
22(B) Calibration of Tanks 1 Calendar day.
above 150 feet in
diameter.
23 Boxing up of shell, 1 Calendar day.
roof & Clean out man
ways
24 Deblind process utility 2 Calendar days.
lines
6.4 NOTES ON COMPLETION PERIOD:

1) Item # 19 includes filling, draining and cleaning of tank after draining.

2) Day(s) definition means calendar day(s) which include all week ends and National
holidays.

3) Item 13(B & C), 15A, 17(B & C) and 18(B & C) includes roof internal and all roof
internal structure.

4) For items 2A & 3 for re-roofing, in the event of Dome roof tank, an additional of 20%
duration shall be allotted.

5) Duration for sweep blasting shall be accounted as 300 Sq.M. per day.

6) In case any specific type or item of work without duration is stipulated in contract,
Supdt., may allot reasonable duration which shall be at his sole discretion.

7) For Group-1 item-1, works per Technical specification 1A of Appendix-B; an additional


20% duration shall be allotted.

8) For Hydrostatic testing of tank, the height of water shall be as recommended by


Inspection & Corrosion section/Operation.

9) Full or partial activities from different groups which could be executed in parallel, shall
be executed accordingly. Such evaluation and decision shall be at the sole discretion of
the Superintendent.

10) Duration of coupons removal, abrasive blasting of Soil Side, welding of coupons &
testing of coupons regardless of tank diameter shall be 5 days. Data sheet shall be
submitted within a week from completion of field work.

11) Completion period for Skirt repair activity including supplying laying, compaction of
Gatch and bitumen mix laying shall be considered 5 days, even if the area to be repaired
is more than 175 sq.m. If area to be repaired is less than 175 sq.m. then completion
period shall be calculated as per item no. 20(A) .

12) Duration for surface preparation, priming and painting including removal and refixing of
floating roof seal steel sheet shall be accounted as 10M2 per day.

13) Duration for removal, surface preparation, priming, painting and refixing of floating roof
support legs shall be accounted as 3 Nos. per day. However, this clause will be applicable
only when legs are removed from position and painted outside the tanks.

14. Duration for Impervious Lining of tank bund wall area shall be 500 Sq.meter/day.
Impervious lining shall be carried out as per KNPC DEP 34.11,DEP 34.11.00.21
(APPENDIX K)
15) Following time period shall be considered for the under mentioned activities.

(A) Number & Emblem painting -2 days.


(B) Piping painting -40M2/day.
(C) Approval of Drawings -7 days.

16) Duration for excavation, auguring & back-filling works for C.P. system shall be fourteen
(14) Calendar days for each tank.

17) Time duration for following activities shall be considered.

Dia. Less Dia. More


Sl. No. Activity Description than 130 ft. than 130ft.
(Days) (Days)
Hydrotesting sample point lines
1 3 3
Remove roof legs, galvanize, repair &
2 fix back. 50 60
Service & Hydrotesting foam and
3 sprinkler lines. 15 15

18) The duration for activities under note # 17 shall be placed in parallel to Tank repair work and
shall not be added to the completion period allowed for other groups.