1 Name of SubStation 2 Adress 3 SubStation Incharge 4 Sub Division 5 Sub Divisional Incharge 6 Sub Station Operating Staff (nos.) 7 Single Line Diagram Available yes/no : 8 Incomming 33 KV Lines Originating from 9 Tapping Substation on 33 KV Lines 10 Power Transformer Details: PTR I PTR II PTR III PTR IV a) Make: b) Capacity(MVA) c) Date of Commission : d) sr.no. e) Ampere rating 11 Station Transformer Details : Transformer I Transformer II a) Make: b) Capacity (KVA): c) Date of Commission : d) sr.no. e) Ampere rating 12 33 KV Potential Transformer Details: a) Make: b) Capacity (KVA): c) Date of Commission : d) sr.no. e) Voltage rating 13 33 KV Current Transformer Details : Incommer CT o/G 33 KV CT PTR I CT PTR II CT a) Make: b) sr.no. c) Ratio Available d) Ratio Connected e) Date of Commission : 14 11 KV Potential Transformer Details: a) Make: b) Capacity (KVA): c) Date of Commission : d) sr.no. e) Voltage rating 15 11 KV Current Transformer Details : PTR I Inc . CT PTR II Inc . CT PTR III Inc . CT a) Make: b) sr.no. c) Ratio Available d) Ratio Connected e) Date of Commission : 16 11 KV Current Transformer Details : 11 KV Feeder I CT 11 KV Feeder 2 CT 11 KV Feeder 3 CT etc. a) Make: b) sr.no. c) Ratio Available d) Ratio Connected e) Date of Commission : 17 33 KV Vaccum Circuit Breaker : a) Make: b) sr.no. c) Capacity Making: d) Capacity Braking e) Date of Commission : 18 11 KV Vaccum Circuit Breaker : a) Make: b) sr.no. c) Capacity Making: d) Capacity Braking e) Date of Commission : 19 Register Available at SubStation : a) Permit book: b) Login Rgister : c) Tripping Register : d) Max. Min Load register : e) Max. Min Voltage register : f) History Register : g) Shift Duty Chart : h) Earth Pit Measurement Register : 20 Safety Equipement : a) Hand gloves b) Rubbermat c) Fire Extinguishers: d) Fire sand Buckets: e) Earthing Rods f) Torch g) Tool kit h) First aid kit : 21 Equipements: a) Megger b) Earth Tester c) Hydrometer d) Tester e) Multimeter 22 Baterry Set Details : a) No. Of cells: b) Make : c) Voltage : d) Amp Hour Cap: 23 Baterry Charger : a) Make : b) Capacity c) Float setting: d) Boost setting : 24 Baterry Cell Record Register: 25 Switch Yard: a) Metal Spreading b) Grass cutting c) Yard lighting d) Cable Trench cover e) Compound wall f) Water Arrangement 26 Control room : a) Control Panel b) Announciations : c) Semaphore : 27 Protections: a) 33 KV RELAYS (Make & settings) Line Relay O/C E/F relay b) 11 KV Relays (Make & settings) Line Relay O/C E/F relay 28 Capacitor Bank Details if available: No. Of Cells : Total Capacity : 29 Eart Pits: Nos: Water Tap Arrangement :