DAILY PROGRESS
PROJECT : LV8 HOTEL PROJECT DAY : 1
SUBJECT : AS BUILT DRAWING OF LV8 HOTEL DATE : 19-Sep-16
LOCATION : CANGGU, BALI - INDONESIA

Original Contract Previous Now Total


Code Description
Unit Quantity Weight Progress Weight Progress Weight Progress Weight
1 PRELIMINARIES
1.1 Mobilitation & Demobilitation ls 1 2,11% 0% 0,00% 2% 0,04% 2% 0,04%
1.2 Accomodation ls 1 1,22% 0% 0,00% 2% 0,02% 2% 0,02%
1.3 Administration ls 1 0,81% 0% 0,00% 2% 0,01% 2% 0,01%
1.4 Site management ls 1 12,15% 0% 0,00% 2% 0,20% 2% 0,20%
1.5 Equipment ls 1 0,67% 0% 0,00% 2% 0,01% 2% 0,01%
2 SITE INVESTIGATION, SURVEY & MAPPING
2.1 Benchmark & Boundary line ls 1 2,46% 0% 0,00% 0% 0,00% 0% 0,00%
2.2 Building perimeter ls 1 2,46% 0% 0,00% 0% 0,00% 0% 0,00%
2.3 Building detail ls 1 2,46% 0% 0,00% 0% 0,00% 0% 0,00%
2.4 Landscape & Infrastructure ls 1 2,46% 0% 0,00% 0% 0,00% 0% 0,00%
3 AS BUILT DRAWING
3.1 Structural
3.1.1 Standard Drawing ls 1 1,22% 0% 0,00% 0% 0,00% 0% 0,00%
3.1.2 Basement ls 1 0,70% 0% 0,00% 0% 0,00% 0% 0,00%
3.1.3 1st Zone (Restaurant & Pool) ls 1 2,79% 0% 0,00% 0% 0,00% 0% 0,00%
3.1.4 2nd Zone (Rooms) ls 1 3,14% 0% 0,00% 0% 0,00% 0% 0,00%
3.1.5 3rd Zone (Lobby) ls 1 3,14% 0% 0,00% 0% 0,00% 0% 0,00%
3.1.6 M/E Room ls 1 0,70% 0% 0,00% 0% 0,00% 0% 0,00%
3.1.7 Detail ls 1 3,48% 0% 0,00% 0% 0,00% 0% 0,00%
3.2 Architectural
3.2.1 Standard Drawing ls 1 0,37% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.2 Floor Plan ls 1 0,74% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.3 Elevation & Section ls 1 0,83% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.4 Floor Pattern ls 1 0,74% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.5 Ceiling ls 1 0,74% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.6 Doors & Windows Schedule ls 1 0,83% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.7 Room Detail ls 1 7,48% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.8 Partial Interior ls 1 2,59% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.9 Partial Exterior ls 1 1,94% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.10 Swimming Pool & Pond ls 1 0,46% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.11 Roof ls 1 0,37% 0% 0,00% 0% 0,00% 0% 0,00%
3.2.12 Landscape ls 1 0,37% 0% 0,00% 0% 0,00% 0% 0,00%

PRELIMINARIES1
2.2. DAILY PROGRESS
PROJECT : LV8 HOTEL PROJECT DAY : 1
SUBJECT : AS BUILT DRAWING OF LV8 HOTEL DATE : 19-Sep-16
LOCATION : CANGGU, BALI - INDONESIA

Original Contract Previous Now Total


Code Description
Unit Quantity Weight Progress Weight Progress Weight Progress Weight
3.3 Mechanical, Electrical & Plumbing
3.3.1 Mechanical ls 1 3,22% 0% 0,00% 0% 0,00% 0% 0,00%
Lift
Genset
Heating-Ventilation-Air Conditioning (HVAC)
Pumping & Filtration
3.3.2 Electrical ls 1 6,43% 0% 0,00% 0% 0,00% 0% 0,00%
3.3.3 Plumbing ls 1 4,13% 0% 0,00% 0% 0,00% 0% 0,00%
3.3.4 Fire System ls 1 1,84% 0% 0,00% 0% 0,00% 0% 0,00%
Fire Alarm
Hydrant & Sprinkler
3.3.5 Electronic ls 1 1,84% 0% 0,00% 0% 0,00% 0% 0,00%
CCTV
Telp System
Cable Data
MATV
3.4 Infrastucture
3.4.1 Gate & Fence ls 1 0,92% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
3.4.2 Road Pavement ls 1 2,30% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
3.4.3 Drainage ls 1 0,92% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
3.4.4 Stormwater Drainage ls 1 1,38% 0,00% 0,00% 0,00% 0,00% 0,00% 0,00%
4 TESTING
1.1 Hammer test ls 1 1,73% 0% 0,00% 0% 0,00% 0% 0,00%
1.2 Core drilled ls 1 4,33% 0% 0,00% 0% 0,00% 0% 0,00%
1.3 Test pit ls 1 1,95% 0% 0,00% 0% 0,00% 0% 0,00%
1.4 Repairing ls 1 4,87% 0% 0,00% 0% 0,00% 0% 0,00%
5 FINAL REPORT ls 1 4,76% 0% 0,00% 0% 0,00% 0% 0,00%
TO TOTAL FINAL SUMMARY 100,00% 0,00% 0,28% 0,28%

Canggu, 19 September 2016


CHECKED BY, SUBMITTED BY,
PT. BALI UNICORN PT. SYAPRIL JANIZAR

Name : ___________________________

Position: ___________________________
PRELIMINARIES2