You are on page 1of 2

Activity

1. Draw a network from activity list for the Reliable Construction Co. project
2. Determine the path and path lengths
3. Determine the critical path

Immediate
Activity Activity Description Estimated Duration
Predecessors

Excavate
A - 2 weeks
Lay the foundation
B A 4 weeks
Put up the rough wall
C B 10 weeks
Put up the roof
D C 6 weeks
Install the exterior
E C 4 weeks
plumbing
F E 5 weeks
Install the interior plumbing
G D 7 weeks
Put up the exterior siding
H E,G 9 weeks
Do the exterior painting
I C 7 weeks
Do the electrical work
J F,I 8 weeks
Put up the wallboard
K J 4 weeks
Install the flooring
L J 5 weeks
Do the interior painting
M H 2 weeks
Install exterior fixtures
N K,L 6 weeks
Install the interior fixtures

Activity

1. Draw a network from activity list for the Reliable Construction Co. project
2. Determine the path and path lengths
3. Determine the critical path

Immediate
Activity Activity Description Estimated Duration
Predecessors

A -
B Excavate A 2 weeks
C Lay the foundation B 4 weeks
D Put up the rough wall C 10 weeks
E Put up the roof C 6 weeks
F Install the exterior E 4 weeks
G plumbing D 5 weeks
H Install the interior plumbing E,G 7 weeks
I Put up the exterior siding C 9 weeks
J Do the exterior painting F,I 7 weeks
K Do the electrical work J 8 weeks
L Put up the wallboard J 4 weeks
M Install the flooring H 5 weeks
Do the interior painting
2 weeks
Install exterior fixtures
N K,L 6 weeks
Install the interior fixtures