Creating a Primavera P6 Schedule

Prepared by

Bill Pepoon, Managing Partner


Construction Science, LLC

2013 Construction Science, LLC 1


Overview
Introduction
Creating a new Project
Adding Activities
Activity Types
Calendars

2013 Construction Science, LLC 2


Overview
Activity Codes
Activity Logic
Scheduling
Custom Layouts & Views (Formatting)
Additional Information

2013 Construction Science, LLC 3


2013 Construction Science, LLC 4
Introduction
Data Structures in P6
EPS (Enterprise Project
Structure)

Centralized Management of
multiple projects

Categorizes work in the


Organization: A hierarchy of
projects or a grouping of projects
within departments

Projects represent the lowest


level of the EPS

Every project in the organization


must be included in an EPS

2013 Construction Science, LLC 5


Introduction
Data Structures in P6

OBS (Organization Breakdown Structure)

A Separate global hierarchy reflecting the


management structure

One OBS for the entire organization

Used to control access to projects and


data

An OBS element/person will be


responsible for each node/project within
the EPS

2013 Construction Science, LLC 6


Introduction
Data Structures in P6

Work Breakdown Structure (Company Name) EPS

Acts as a continuation for the Project A Project B Project C


individual projects in the EPS

The WBS is a Project-Specific


Structure. Each project has its own
Project B (WBS Level 1)
WBS that further breaks down the
work in that project. WBS Node 1 WBS Node 2 WBS Node 3

Activity 1
The project is the highest level of
the WBS. Activities are the lowest Activity 2
level of the WBS

2013 Construction Science, LLC 7


2013 Construction Science, LLC 8
Creating a New Project

Creating a New EPS

1. Enterprise Command Menu


Enterprise Project Structure

2. Click Add

3. Specify EPS ID & Name

4. Change the EPS position in the


hierarchy using arrows

5. Modify Display Options

2013 Construction Science, LLC 9


Creating a New Project
To Create a new Project

Select the EPS to


which you want to add
the new project
Click Add OR Right-
Click the EPS Add
Type Project Data
Project ID
Project Name
Planned Start Date
Must Finish By :
Contract Finish Date
Responsible Manager
in the OBS
Rate Type: Price/Unit

2013 Construction Science, LLC 10


Creating a New Project
In the Defaults Tab,
Choose the Auto-
Numbering preferences

Use Smart IDs to


denote activitys
information. E.g.
PH1F2C001 : Phase 1,
Floor 2, Concrete
Works

2013 Construction Science, LLC 11


Creating a New Project
To open the Project:

Select the Project in the


Home Page

Click on the
"Activities" tab in the
Directory Toolbar

OR

Right-Click on the
Project "Open
Project"

2013 Construction Science, LLC 12


2013 Construction Science, LLC 13
Adding Activities
1. Click on the
Activities icon in the
Directory Toolbar
2. Right-Click where you
want to insert the new
activity "Add"
OR
Click the "Add" icon
and follow the Wizard
steps
OR
Click "Insert"

2013 Construction Science, LLC 14


Adding Activities
You can also, Cut, Copy,
Paste and Delete activities
using the Command Bar

2013 Construction Science, LLC 15


2013 Construction Science, LLC 16
Activity Types
In P6, an Activity Type can be either:
Task Dependent
Resource Dependent
Level of Effort
Start Milestone / Finish Milestone
WBS Summary

2013 Construction Science, LLC 17


Activity Types (Task)
Task Dependent Activity

Scheduled only according to the Activity's calendar

When you want to control the Activity's duration yourself

Activitys Resources are scheduled according to the Activity's


Calendar

Use this Activity Type for all construction / physical activities

2013 Construction Science, LLC 18


Activity Types (Resource)
Resource Dependent Activity

Scheduled according to the calendars of assigned resources

Resources are scheduled according to their own calendars

Used when several resources are assigned to the same


activity, but may work separately, or when availability can
affect Activity's duration

2013 Construction Science, LLC 19


Activity Types (Level of Effort)
Level of Effort Activity
Commonly known as Hammocks
Has a duration which is determined by its dependent
activities, from the earliest start of its predecessors to the
latest finish of its successors
Should be linked to its predecessors with a SS, and to its
successors with a FF
Overhead-type activities are typically Level of Effort, e.g. Site
Cleanup
Can be used for monitoring purposes, e.g. "Project Duration"
2013 Construction Science, LLC 20
Activity Types (Level of Effort)
Level of Effort Activity
(Cont'd)

Predecessors: 02 & 03 Predecessors


Successors

Successors: 04 & 05

2013 Construction Science, LLC 21


Activity Types (Milestone)
Start Milestone/Finish Milestone

A zero-duration activity with no resources

Used when an activity is intended to signify the


commencement/completion of a significant stage, rather than
a physical work product

Examples : Notice to Proceed, Substantial Completionetc

2013 Construction Science, LLC 22


Activity Types (WBS Summary)
WBS Summary Activity

Has a duration which is determined by a group of activities


that share a common WBS level.

The Activity's duration will equal the overall duration of


activities assigned to the same WBS level.

Resources that drive activity dates cannot be assigned to WBS


summary activities.

2013 Construction Science, LLC 23


Activity Types
To change the Activity Type:

1. Select the activity & show


activity details

2. Click the "General" tab

3. Choose the appropriate


activity type from the drop
down menu

2013 Construction Science, LLC 24


2013 Construction Science, LLC 25
Creating Calendars [Enterprise Calendars]

1. Enterprise Command Menu


Calendars

2. Choose Global

3. Click Add to create a new calendar


or Modify to edit an existing one

4. Choose the Calendar that you want


to use as a template for new Projects

5. Modify the Work Week

6. Double-click to add work/non-work


days

7. Check in the Default Box to make


this the default Calendar for all
future projects
2013 Construction Science, LLC 26
Creating Calendars [Enterprise Calendars]

8. In the main Calendars window,


choose Project

9. Add the Global Calendar that was


created in Step 3 above

10. Holidays will be inherited


automatically

11. Go back to the Home Page, Right-


Click on the new project
Project Details

12. In the Defaults Tab, choose the


new Calendar from the drop down
menu

2013 Construction Science, LLC 27


Creating Calendars
To Assign a Calendar

1. Select the Activity.

2. From the General


tab, select the
appropriate
Calendar.

2013 Construction Science, LLC 28


2013 Construction Science, LLC 29
Activity Coding Structures

In addition to the WBS, you can group, filter,


summarize and sort activities using Activity Codes
You can use Activity Codes in lieu of, or in
combination with the WBS
E.g.: Phase, Area, Work type, Specification Division,
Subcontractoretc

2013 Construction Science, LLC 30


Activity Coding Structures [Enterprise Activity Codes]

Create the Activity Coding


structure:

Enterprise Command Menu


"Activity Codes"

P6 provides 3 types of Activity


Codes:
Global: can be assigned to
activities in all projects
EPS: can be assigned to
projects within the EPS
Project: can only be assigned to
activities in the opened project

2013 Construction Science, LLC 31


Activity Coding Structures [Enterprise Activity Codes]

Create the Activity Coding


structure (Contd):

Note the difference between the


Activity Code and Activity Code
Values

2013 Construction Science, LLC 32


Activity Coding Structures [Enterprise Activity Codes]

Create the Activity Coding


structure (Contd):

1. In the main Activity Codes


Window select "EPS"
2. Click "Modify"
3. A new window will appear, add
the new code & new codes name
4. Close the window
5. Select the new code from the drop-
down menu
6. Add new values to the code

2013 Construction Science, LLC 33


Assigning Activity Codes

1. Show the Project details by


clicking on the "Show/Hide
Bottom Layout" in the
"Layout Options" toolbar

2. Click the "Codes" tab

3. Click "Assign"

2013 Construction Science, LLC 34


Assigning Activity Codes
5. From the top bar, choose
the coding level from
which you want to assign
codes, whether Global,
EPS or Project
Note: To assign from the
Global codes, make sure
the display Filter is set to
All values

6. Select the code you want


to assign

2013 Construction Science, LLC 35


Assigning Activity Codes
To add/change the Code
Assignment of multiple
activities:

Highlight activities that


you want to add/change
their code assignments

Click on "Activity
Codes" icon on the
"Command Bar

Select the appropriate


code

2013 Construction Science, LLC 36


2013 Construction Science, LLC 37
Adding Logic Relationships

1. Show the Project details by


clicking on the "Show/Hide
Bottom Layout" in the
"Layout Options" toolbar

2. Click the "Relationships"


tab

3. Click "Assign" to add


Predecessors / Successors

4. Select the Predecessor /


Successor from the list

2013 Construction Science, LLC 38


Adding Logic Relationships
New logic relationships are
Finish-to-Start by default.
To change the relationship
type, double click in the
"Relationship Type" field
then choose the appropriate
type from the drop-down
menu.

You can only input the


Relationship Type & Lag.
Other fields are
automatically calculated by
the software.

To customize the displayed


columns, Right-Click
anywhere in the Predecessor
or Successor area.
2013 Construction Science, LLC 39
Adding Logic Relationships
To Add a Predecessor /
Successor to Multiple
Activities

1. Highlight all activities to


which you want to add the
predecessor / successor

2. Click on the "Predecessors"


or "Successors" icon on the
"Command Bar", as may be
appropriate

3. Select the common


predecessor / successor that
you want to add to the
highlighted activities
2013 Construction Science, LLC 40
Adding Logic Relationships
To link a Series of Activities

1. Ctrl-Click the activities in


the order you want them in

2. Right-Click "Link
Activities"

3. They are now linked in the


order they were selected

2013 Construction Science, LLC 41


2013 Construction Science, LLC 42
Scheduling

Now its time to calculate the Schedule


Click Tools Schedule
OR click F9

Select the Data date

Schedule the project after


each logic change for it to
take effect

2013 Construction Science, LLC 43


2013 Construction Science, LLC 44
Grouping & Sorting

Click on the "Group & Sort"


icon in the Layout Options
Toolbar

Double-click in the "Group


by" field to select the
grouping data item.

Double-Click on the Font &


Color field to modify the
format of the grouping bands

2013 Construction Science, LLC 45


Grouping & Sorting
Mark "Show Group Totals"
to display the totals per data
item in the grouping bands
(e.g. total budgeted cost per
Area)

2013 Construction Science, LLC 46


Grouping & Sorting

Click "Sort" to specify the


order of activities within each
group

When done, click "Apply" for


changes to take effect

2013 Construction Science, LLC 47


Filters
1. Click on the "Filters"
icon

2. Click:
"New" to create a
new filter,
"Modify" to edit an
existing one, or
Copy/paste a global
filter under the "User
Defined" category to
modify it

2013 Construction Science, LLC 48


Filters
3. Enter the Filter criteria; could
be any activity attribute: Code,
WBS or Resource assignment,
a Date, % completeetc.

4. Choose the Filter Parameter,


whether you want to filter to
show activities complying
with ALL or ANY of the
criteria.

2013 Construction Science, LLC 49


Filters
5. Mark against the
filter(s) that you want
to apply

6. Select "All Selected


Filters" or "Any
Selected Filter" to
display activities that
meet ALL or ANY
criteria specified in the
selected filters

7. To revert to displaying
all activities, mark the
"All Activities"
checkbox

2013 Construction Science, LLC 50


Customizing the Bar Chart
To Customize the Timescale

View Menu Timescale


OR
Click on the "Timescale icon in
the Layout Options toolbar

Enter the Timescale start

Enter the Timescale Interval

Use Timescale Type :Calendar

2013 Construction Science, LLC 51


Customizing the Bar Chart
To customize the Bars:

View Menu Bars


OR
Click on the "Bars" icon in
the Layout Options toolbar

Mark the checkbox next to


bars you want to show

Modify the shape and color


of the selected Bar from the
Bar Style tab.

2013 Construction Science, LLC 52


Customizing the Bar Chart
Under the Bar Labels Tab,
Click "Add" to select a Bar
Label, e.g. Activity Name,
Start & Finish Datesetc

2013 Construction Science, LLC 53


Customizing the Bar Chart
You can add a new bar
style for a certain group of
activities, e.g.:
all activities with a certain
Activity code
1. Click "Add" or copy
another Bar
2. Enter the new Bars
style and criteria
3. Enter a Filter to
associate a group of
activities with the Bars
style

2013 Construction Science, LLC 54


Customizing the Bar Chart
Click on the "logic lines"
icon to show logic
relationships in the Bar
Chart

2013 Construction Science, LLC 55


Print Setup [File Menu Page Setup]

File Menu Page Setup

In the "Page" tab, make sure to


"Fit Timescale" to 1 page wide

2013 Construction Science, LLC 56


Print Setup [File Menu Page Setup]

In the "Footer" tab specify


Number of sections into
which the footer to be
divided
Which pages to show the
footer on
Data to be included in
each section

To enter Data into the footer Sections, select the section,


Select Data Item form the drop down menu click Add

2013 Construction Science, LLC 57


Print Setup [File Menu Page Setup]

In the "Options" tab


Specify:

Timescale Start

Timescale Finish

Data Items to be printed

2013 Construction Science, LLC 58


Layouts [View Menu Layout]

To open or save layouts:


Click the View Menu Layout

To Create a new layout

1. Open an existing layout that


most closely resembles the
format of the new layout you
want to create

2. Choose View, Layout, Save As

3. Type a name for the new layout

4. In the Available To field, select


a user category, then click Save

2013 Construction Science, LLC 59


Additional Information

For additional information and training please visit our


Primavera P6 training site:
www.primaverascheduling.com

Please contact lead instructor Bill Pepoon with any


comments or questions:
bpepoon@constructionscience.com
(916) 779-4145

2013 Construction Science, LLC 60