Project start Date 1/Dec/2014 31/May/2016 1/Dec/2014 23/Apr/2017

As per approved L3 Program Actual work

Description Start Date Finish Date Start Date Finish Date


Dec-14 Jan-15 Feb-15 Mar-15 Apr-15 May-15 Jun-15
19/Jan/2016 2/May/2016
Ceramics procurement 18/Feb/2015 2/Jun/2015
MATERIAL

9/Apr/2016 7/Jul/2016
Paint Procurement 14/Feb/2015 28/May/2016
Externl Cladding 9/Apr/2016 7/Jul/2016
procurement
ZONE-1
Block work 14/Apr/2015 6/Sep/2015 Block work as pe L3
Block work as per site
11/May/2015
Block work 8/Sep/2015
Plaster 20/May/2015 8/Sep/2015 Plaster as per L3
ZONE-1

Plaster May/15 3/Dec/2015 Plaster as per site


Ceramics 19/Jul/2015 7/Oct/2015 Ceramic as per L3
Ceramics 4/Jan/2016 30/Jun/2016
Paint 16/Jul/2015 25/Aug/2015 Paint as per L3
Paint 16/Apr/2016 10/Aug/2016
wood Door 6/Sep/2015 24/Oct/2016 Wooden door installation as per
wood Door 30/Jul/2016 15/Oct/2016
Mep final Fixing 13/Aug/2015 21/Oct/2015 MEP final Fix as per L3
Mep final Fixing 15/Aug/2015 31/Oct/2016
External Cladding 8/Jul/2016 30/Aug/2016

ZONE-2
Block work 27/Jun/2015 7/Oct/2015 Block work Aas per L3
Block work 13/Jun/2015 31/Jan/2016 Block work As per site
Plaster 14/Jul/2015 10/Oct/2015 Plaster as per L3
Plaster 5/Dec/2015 20/Mar/2016
Ceramics 18/Aug/2015 9/Nov/2015 Ceramic As per L3
ZONE-2

Ceramics 27/Apr/2016 30/Jul/2016


Paint 24/Aug/2015 3/Nov/2015
Paint 8/Jul/2016 10/Oct/2016
wood Door 7/Oct/2015 26/Nov/2015
wood Door 8/Jun/2016 30/Aug/2016

MEP Final Fixing 14/Jul/2015 5/Oct/2015

MEP Final Fixing 15/Sep/2016 16/Nov/2016

External Cladding 25/Jul/2016 25/Sep/2016

ZONE-3
Block work 14/Sep/2015 29/Dec/2015
Block work 8/Nov/2015 15/Jun/2016
Plaster 4/Oct/2015 31/Dec/2015
Plaster 7/Feb/2016 30/Jun/2016
Ceramics 13/Oct/2015 30/Jan/2016
ZONE-3

Ceramics 15/Jul/2016 31/Oct/2016


Paint 14/Nov/2015 25/Jan/2016
Paint 23/Jul/2016 3/Sep/2016
wood Door 29/Dec/2015 11/Feb/2016
wood Door 8/Sep/2016 23/Oct/2016

MEP Final Fixing 10/Dec/2015 11/Feb/2006


MEP Final Fixing 6/Oct/2016 20/Dec/2016

External Cladding 11/Aug/2016 10/Sep/2016

ZONE-3
Block work 23/Nov/2015 16/Mar/2016
Block work 9/Nov/2015 13/Mar/2016
Plaster 16/Dec/2015 19/Mar/2016
Plaster 7/Feb/2016 20/Jun/2016
Ceramics 20/Jan/2016 17/Apr/2016
Ceramics 24/Apr/2016 25/Jul/2016
Paint 26/Jan/2016 12/Apr/2016
Paint 10/Jul/2016 10/Oct/2016
Wood Door 12/Mar/2016 24/Apr/2016
ZONE-4

Wood Door 20/Jul/2016 5/Sep/2016


MEP Final Fixing 2/14/2015 4/25/2016
MEP Final Fixing 10/Nov/2016 10/Jan/2017
External Cladding 10/Sep/2016 15/Oct/2016
Additional time for roof
water Tank 11/Jan/2017 13/Feb/2017

Additionaltime for
Infrastructure work 11/Jan/2017 20/Mar/2017

Snagging & Rectification 21/Mar/2017 22/Apr/2017


Handovering 23/Apr/2017
AS PER APPROVED L3 PROGRAMM

ACTUAL WORK ON SITE

DELAY DUE TO MODIFICATIONS / Mater


PROJECT DELAY SCHEDULE

Jul-15 Aug-15 Sep-15 Oct-15 Nov-15 Dec-15 Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17
Ceramic procurement

Paint procurement

external cladding procurement


M1 M2
NO CONFIRMATION TO
PROCEED FOR OTHER VILLAS V03

* M1 * M2 * Modification work blockwork Zone-1

Modificcation work plaster Zone-1


Ceramic Installation as per Approval
Ceramics Installation Zone-1
nt as per L3
Paint as per material on site Zone-1
ooden door installation as per L3
wooden door installation Zone-1
al Fix as per L3
MEP final Fixing Zone-1

External Cladding Zone-1

Modification Block work Zone-2


Modification plaster Zone-2

Plaster as per Site


Ceramic As per L3
Ceramic Installation for Zone-2

Paint as per L3
Paint for Zone-2
Wood work as per L3

Wood work as per Site Zone-2

MEP final Fix as pe L3

MEP final Fixing Zone-2

External Cladding Zone-2

Block work as per L3

Block work as per site Modification work Zone-3


Plaster as per L3

Plaster as per site Modification Plaster Zone-3

Ceramics installation as per L3

Ceramic as per site Zone-3

Paint as per L3

Paint as per site Zone-3

Wooden Door Installation L3


Wooden door installation Zone-3

MEP final Fixing L3 MEP final Fixing Zone-3

External Cladding Zone-3

Block Work as per L3


Plaster Work L3 Modification Work

Modification Work Plaster

Cermic installation as per L3


Ceramic s per Site Zone-4

Paint A PER l3
Paint as per Site Zone-4
Wooden door installation as per L3
Wooden Door Installation Zone-4
MEP final Fixing MEP final Fixing Zone-4
External Cladding Zone-4

ADDITIONAL WORK FOR ROO

Snagging And rectific

ROVED L3 PROGRAMM

RK ON SITE MODIFICATION RECEIVING

TO MODIFICATIONS / Material
Feb-17 Mar-17 Apr-17
ONAL WORK FOR ROOF WATER Tank

Snagging And rectification


*
Handovering