MEG PROJECT

DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
1 Excavation Hand tools: 1. Injury due to defective tools 1. All hand tools shall be kept in good Safety Supervisor
shovels, picks 2. Injury due to incompetence of worker condition. They must be kept clean Site Supervisor
3. Injury due to wrong use of tool and stored properly. Handles shall be
Power handtools: 4. Injury due to collapse of excavation inspected frequently for damages and
Jack hammer or cave-in. shall remain tightly secured. Defective
air compressor 5. Injury due to fall of personnel into tools shall be removed from service and
excavation. repaired or disposed.
Mechanical excavator 6. Injury due to scattered materials 2. Train the personnel on how to handle
Backhoe, Payloader 7. Breakdown of equipment. and operate the equipments or tools
Dump truck/s 8. Injury due to fall of dump truck and . properly.
Dewatering pump other heavy equipments into excavation 3. Provide adequate shoring and
9. Injury due to accidental hit by bracing system to protect the wall from
back-tracking equipment collapsing.Wall shall be sloped when
10. Injury due to incompetence of excavating in an open area.
driver, operator. 4.Provide hard barricades around the
11.Injury to personnel and damage to excavation site and bar any unwanted
vehicle due to traffic confusion personnel, provide ladder for access
12. Injury due to inhalation of fumes in and out of the excavation. Ladder
from air compressor. shall be extended min.1m. above ground
13. Injury due to ignorance of level.Provide handrail at least on one
personnel in operating the air side of the ladder.
compressor and jack hammer. 5. Daily house keeping shall be done.
6. Conduct regular check of equipments
to maintain good operating condition
and avoid breakdown during operation.
7. Barricades the excavation site.
Assign one trained person to lookout
and give signal to operator/driver.
8. Backhoe, dump truck/s payloader,
shall be provided with

Submitted by : Nasser S.Al-Hajri Corp. Page 1 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
back tracking alarm or signal
to alert personnel on site.
9. Only licenced and certified driver/
operator shall be allowed to handle
and operate or drive.
10.Assign one personnel wearing an
orange reflectorized vest to direct traffic
among equipments and other vehicles.
11. Conduct regular check up and
maintain good working condition
of the air compressor. Use proper PPE
by all personnel at the location.
12. Personnel must be trained about the
proper usage and handling of tools.

2 Operation of Diesel powered 1. injury due to fire. 1. Check the engine for fuel leaks. Safety Supervisor
Dewatering system dewatering pump 2. Injury due to inhalation of fumes Repair and keep good maintenance. Site Supervisor
and noise pollution. 2. Use dust mask and ear plugs when
working close to the pump.

3 Scaffolding work scaffolding materials : 1. Injury due to collapse of scaffolding 1. Scaffolds shall be designed by a quali- Safety Supervisor
pipes due to everloading fied person and shall be constructed Site Supervisor
clamps 2. Injury due to sway and fall of scaffolding and loaded in accordance with that design. Scaffold foreman
wooden planks 3. Injury due to fall of personnel 2. Scaffold and component shall be capa-
spanners 4. Injury due to fall of any material from ble of supporting, without failure, its
the top of the scaffolding over personnel own weight and at least 4 times the
on the ground. maximum intended load applied or
5. Injury due to unsafe scaffolds. transmitted to it.
3. Guys, ties, and braces shall be ins-
talled at the closest horiontal member
to the 4:1 height and be repeated ver-
tically at locations of horizontal mem-
bers every 26 ft. or less thereafter.
4. The top guy, tie or brace of completed
scaffolds shall be placed no further than
the 4:1 from the top. Such guy, tie and

Submitted by : Nasser S.Al-Hajri Corp. Page 2 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
bracessall be installed at each end of
of the scaffold and at horizontal intervals
not to exceed 30 ft.
5. Fall protection shall be provided for em-
ployees erecting or dismantling scaffolds.
6. A safe means of acces shall be provi-
ded, such as properly fixed ladders,
shall be provided for employees erecting
or dismantling scaffolds.
7. 100% fall protection to be used when
working 6 ft. or more from an unpro-
tected elevtion.
8. Full body harness with two 6 ft. shock
absorbing lanyards shall be provided for
employees working on top of scaffoldings.
9. Document monthly inspections on fall
protection equipment and system. Con-
duct visual inspection prior touse. En-
sure that the equipments are in good
condition at all times.
10.Make sure that lanyard anchorage shall
be capable of supporting 5000 lbs.
11.Horizontal lifelines shall be designed,
installed and used under the supervision
of a qualified person.
12.Each platform on all working levels of
scaffold shallbe fully planked or decked
between the the uprights and the guard
supports.
13. Barricade shall be provided around the
area where scaffolding work is going on
or where people are working on elevated
platform at any level of the scaffolding.
14. Warning signs shall be posted to cau-
tion unwary personnel from entering the
barricaded area.
15. Scaffolds shall be erected, moved,
dismantled or altered only under the su-

Submitted by : Nasser S.Al-Hajri Corp. Page 3 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
pervision and direction of a competent
person qualified inscaffold erection, mo-
ving, dismantling or alteration. Such ac-
tivities shallbe performed only by expe-
rienced and trained personnel.
16. Footings shall be levelled, sound, ri-
gid and capable of supporting the loaded
scaffold without setting or displacement.
17. Scaffold and its component shall be
pected for visible defects by a competent
person before each work shift, and after
any occurrence which could affect a
scaffold's structural integrity.
released to proper personnel for use.

4 Rebar work manual handtool: 1. Injury due to defective tools 1. All hand tools shall be kept in good Safety Supervisor
Lifting knipper / wire cutter 2. Injury due to incompetence of worker condition. They must be kept clean Site Supervisor
bar cutter 3. Injury due to wrong use of tool and stored properly. Handles shall be Rebar Foreman
4. Injury due to fall of personnel working inspected frequently for damages and Rigger
power supplied equipment: above 1 meter height shall remain tightly secured. Defective
bar bending machine 5. Injury due to tripping over rebar tools shall be removed from service and
bar cuting machine 6. Injury due to protruding rebar ends. repaired or destroyed.
7. Injury due to mechnical failure. 2. Personnel must be trained about the
equipment: 8. Injury due to overloading. proper usage and handling of tools.
crane ( if necessary ) 9. Injury due to crane tripping. 3. All hand tools must be used only for the
10. Injury due to confusion of signal to intended purpose.
operator. 4. Provide scaffolding for every work above
11. Injury due to fall of suspended loads. 1 meter in height. Scaffolding shall pass
SSA safety inspection prior to its use.
5. Personal protection equipment shall be
issued and used properly by personel.
6. Use ladder in ascending and
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
7. Arrange and pile rebar in order in a
manner that would give free access of
personnel in the worksite. Access shall

Submitted by : Nasser S.Al-Hajri Corp. Page 4 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
not be obstructed.
8. All protruding rebar ends shall be
protected. Bent bars should be arranged
where the ends are pointed to the ground
9. Crane must be inspected by client prior
to use.
10. Confirm load weights and crane
configuration.
11. Out riggers are to be fully extended, Safety Supervisor
in the down position and on pads when Site Supervisor
on unstable ground. Level crane. Rebar Foreman
12.Qualified rigger to signal crane operator Rigger
using standard hand signals.
13. No one is permitted under loads
14. Tag lines( rope) are to be used to
control loads from swinging.
15. Maintain housekeeping for both
Site and Fabrication shop.

5 Formworks Manual hand tools: 1. Injury due to defective tools 1. All hand tools shall be kept in good Safety Supervisor
Form removal hammer 2. Injury due to loose electical cable condition. They must be kept clean Site Supervisor
handsaw 3. Injury due to exposed wirings and stored properly. Handles shall be Carpenter Foreman
Power handtools: 4. Injury due to incompetence of worker inspected frequently for damages and
Jigsaw 5. Injury due to wrong use of tool shall remain tightly secured. Defective
hand drill 6. Injury due to fall of personnel working tools shall be removed from service and
above 1 meter height repaired or destroyed.
7. Injury due to fall of form 2. All power equipment and their extension
8. Tripping hazard cords shall be inspected prior to use
9. Injury due to scattered materials and color-coded monthly.
3. Cords shall be protected from damage.
Any exposed wiring shall be taped and
insulated adequately.
4. All guards, mechanical and protective devices
shall remain
devices shall remain attached and in
proper working condition.
5. Personnel must be trained about the
proper usage and handling of tools.

Submitted by : Nasser S.Al-Hajri Corp. Page 5 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
6. All hand tools must be used only for the
intended purpose.
7. Provide scaffolding for every work above
1 meter in height. Scaffolding shall pass
SSA safety inspection prior to its use.
Use fall protection when above 6 ft. high.
8. Personal protection equipment shall be
issued and used properly by personel.
9. Forms shall be inspected to ensure a-
dequate support and bracing is provided.
10. Use ladder in ascending and
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
11. Arrange forms in order in a manner
that would give free access of personnel
in the worksite. Access shall not be
obstructed. Keep all materials in order.
12. Housekeeping shall be done.

6 Concrete pouring Concrete mixer truck 1.Injury due to fall of concrete truck and 1. Provide barricades around the exca- Safety Supervisor
concrete pump truck pump truck into the excavation vation site. Assign one personnel to Site Supervisor
concrete vibrator engine 4. Injury due to accidental hit by look out and give signal to operator/ Mason Foreman
back-tracking equipment driver of the edge of an excavation.
5. Injury due to incompetence of driver, 2. Concrete and pump trucks shall be
operator provided with back tracking alarm or
6. Injury to personnel and damage to signal to alert personnel on site.
vehicle due to traffic confusion 3. Only licensed and certified operator
7. Breakdown of equipment and driver shall be allowed to han-
8. Injury due to negligence of driver dle and operate or drive.
9. Injury due to fall of personnel working 4. Assign one personnel wearing an
above 1 meter height orange reflectorized vest for visibility
10.Injury due to inhalation of fumes from to direct traffic among equipments
concrete vibrator and other vehicle at excavation site.
11. Injury due to ignorance of personnel 5. Conduct regular check of equipment
in operating the vibrator engine to maintain good operating condition
and avoid breakdown during operation.
6. Concrete trucks should not be permit-

Submitted by : Nasser S.Al-Hajri Corp. Page 6 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
ted to travel with chute gates attached.
7. Provide scaffolding for every work above
1 meter in height. Scaffolding shall pass
SSA safety inspection prior to its use.
8. Personal protection equipment shall be
issued and used properly by personel.
9. Use ladder in ascending and
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
10. Conduct regular chech up and maintain
good working condition of the concrete
vibrator engine.
11. Use personal protection equipment
such as dust/gas mask, helmet, gloves,
goggles,safety harness, earmuffs , etc.
12. Train the personnel on how to handle
and operate the equipment properly.

7 Application of con- Paintbrush 1. Health risk due to mishandling of coat- 1. Only skilled and properly trained per- Safety Supervisor
crete protection Polyurethane coating mat'l. ing material sonnel shall be allowed to do the appli- Site Supervisor
cation of the material. Mason Foreman
2. Materials shall be stored properly and
released to proper personnel for use.
3.The Material Safety Data Sheet shall be
displayed and available to the site where
the application is going on.
4. Proper cleaning and disposal of waste
and residue shall be followed as recom-
mended by the manufacturer.
5.Application of material shall be as
manufacturer's recommendation.
6.Use proper personal protection equip-
ment when using the material such as
gloves, dust/gas mask, goggles, etc.
8 Backfilling work Payloader 1. Injury due to incompetence of driver, 1. Only licensed and certified operator Safety Supervisor

Submitted by : Nasser S.Al-Hajri Corp. Page 7 of 10


MEG PROJECT
DETAIL RESPONSIBLE
SN EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE
ACTIVITY PERSON
Excavator operator and driver shall be allowed to han- Site Supervisor
Dump truck 2. Injury to personnel and damage to dle and operate or drive. Earthwork Foreman
Bobcat equipment due to traffic confusion 2. Assign one personnel wearing an
plate compactor 3. Breakdown of equipment orange reflectorized vest for visibility
Water Tanker 4. Injury due to accidental hit by to direct traffic among equipments
back-tracking equipment and other vehicle at excavation site.
5. Injury due to incompetence of compac-3. Conduct regular check of equipment
tor operator. to maintain good operating condition
6. Injury due to fall of compactor when and avoid breakdown during operation.
bringing down and up the excavation. 4. Train the personnel on how to handle
and operate the equipment properly.
5. Use personal protection equipment
such as dust/gas mask, helmet, gloves,
goggles,safety harness, earmuffs , etc.
6. Small compacting equipment shall be
lifted in and out of excavations by means
of approved rigging techniques.

Submitted by : Nasser S.Al-Hajri Corp. Page 8 of 10


MEG PROJECT
RESPONSIBLE
SN DETAIL ACTIVITY EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE PERSON
1 Building FinishesManual hand tools: 1. Injury due to defective tools 1. All hand tools shall be kept in good Safety Supervisor
2 Scaffoldings Hammer 2. Injury due to loose electical cable condition. They must be kept clean Site Supervisor
Handsaw 3. Injury due to exposed wirings and stored properly. Handles shall be
Power handtools: 4. Injury due to incompetence of inspected frequently for damages and
Tile Cutter worker
5. Injury due to wrong use of tool shall remain tightly secured. Defective
Hand Drill 6. Injury due to fall of personnel tools shall be removed from service and
Block Cutter working
above 1 meter height repaired or destroyed.
Riveter 7. Injury due to fall of form 2. All power equipment and their extension
8. Tripping hazard cords shall be inspected prior to use
9. Injury due to scattered materials and color-coded monthly.
3. Cords shall be protected from
damage.
Any exposed wiring shall be taped
and
insulated adequately.
4. All guards, mechanical and
protective devices
devices shall shallattached
remain remain and in
proper working condition.
5. Personnel must be trained about the
proper usage and handling of tools.
6. All hand tools must be used only for
theintended purpose.
7. Provide scaffolding for every work
above
1 meter in height. Scaffolding shall pass
safety inspection
Use fall prior
protection to its
when use. 6 ft.
above
high.
8. Personal protection equipment shall
be issued and used properly by
personel.
9. Forms shall be inspected to ensure a-
dequate support and bracing is provided.
10. Use ladder in ascending and

Page 9 of 10
MEG PROJECT
RESPONSIBLE
SN DETAIL ACTIVITY EQUIPMENT / TOOLS RISK INVOLVE PREVENTIVE MEASURE PERSON
descending the scaffolding platform.
Ladders shall be extended 3 ft. and be
secured.
11. Arrange forms in order in a manner
that would give free access of personnel
in the worksite. Access shall not be
obstructed. Keep all materials in order.
12. Housekeeping shall be done.

Page 10 of 10