NOMENCLATURE AND A/R OF MODIFIED DSR ITEMS

6.28 Brick work with common burnt clay machine moulded modular bricks of class designation 12.5 in
exposed brick work including making horizontal and vertical grooves 10 mm wide 12 mm deep complete
in cement mortar 1:4 (1 cement : 4 coarse sand).

6.28.1 From ground level upto plinth level

Code No Description Unit Quantity Rate ` Amount `


Details of cost for 1 cum.
1986 Common burnt clay modular bricks class 1000 487.000 5500.00 2678.50
designation 12.5 Nos
2201 Carriage of bricks 1000 487.000 283.96 138.29
Nos
Cement mortar 1:4(1 cement: 4 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.220 4172.05 917.85
9999 Sundries including steel / wooden strips for L.S. 16.380 1.78 29.16
making grooves
LABOUR:
0123 Mason (brick layer) 1 st class day 0.330 435.00 143.55
0124 Mason (brick layer) 2nd class day 0.330 399.00 131.67
0115 Coolie day 1.000 329.00 329.00
0101 Bhisti day 0.180 363.00 65.34
TOTAL 4433.36
Add Water Charges @ 1% 44.33
TOTAL 4477.69
Add CPOH @ 15% 671.65
Cost of 1 cum 5149.34
Say 5149.35

6.28.2 Above plinth level and upto floor V level

Code No Description Unit Quantity Rate ` Amount `


Details of cost for 1 cum.
1986 Common burnt clay modular bricks class 1000 487.000 5500.00 2678.50
designation 12.5 Nos
2201 Carriage of bricks 1000 487.000 283.96 138.29
Nos
Cement mortar 1:4(1 cement: 4 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.220 4172.05 917.85
9999 Sundries including steel / wooden strips for L.S. 16.380 1.78 29.16
making grooves
LABOUR:
0123 Mason (brick layer) 1 st class day 0.440 435.00 191.40
0124 Mason (brick layer) 2nd class day 0.440 399.00 175.56
0115 Coolie day 1.430 329.00 470.47
0101 Bhisti day 0.180 363.00 65.34
Extra labour element required for lifting of
material (above floor two level upto floor five
level)
0115 Coolie day 1.130 329.00 371.77
9999 Sundries L.S. 22.360 1.78 39.80
TOTAL 5078.14
Add Water Charges @ 1% 50.78
TOTAL 5128.92
Add CPOH @ 15% 769.34
Cost of 1 cum 5898.25
Say 5898.25