You are on page 1of 2

PROJECT: CPF PHASE 1 AT BADRA OIL

FIELDPermanent Camp Phase-II Project ITR No : C-021084 XA


INSPECTION & TEST RECORD-CIVIL
Proj.ITR No:
AREA CIVIL WORK COMPLETION
GB088GB150-2013IE02-
CERTIFICATCONCRETE PRECAST UNITS
0200-QA-IT-20104
INSTALLATION CHECK SHEETE
Rev. : B0
(Space reserved for barcode) Project No: JI-2013IE02
Record No:
TAG RFI No:
SUB-SYSTEM No:
Description:
Drawing No: Rev:
Location:
Specification No: Rev:
Quality Control Procedure No: Rev:

Inspection findings
Item Description of check Remarks
Satisfactory Unsatisfactory
Check and ensure the excavation carried out to the required dimension
1 and bottom of foundation is compacted to required degree of
compaction
Check survey report and compaction test report. Check and ensure the
2 blinding concrete curing period is complete and ensure protective
coating on top surface is complete and is acceptable (if applicable)
Ensure concrete strength test result are satisfactory prior to start
3
installing precast Units

Check and ensure the concrete pre-pour inspection check sheet is


4
acceptable for the precast member
Check and ensure the concrete pouring inspection check sheet and
5 field concrete pouring check sheet are acceptable for the precast
member
Check and ensure the concrete post pour inspection check sheet and
6 field concrete pouring check sheet are acceptable and protective
coating application is complete.
Check cast date and foundation type is legibly marked on the precast
7
member

Check and installed coordinates in plan and elevation for the anchor
8
bolts and top of concrete of installed precast members

Check all anchor bolts exposed threaded portion is covered with a film
9
of degree to avoid corrosion
Check and ensure back filling around installed foundation is carried out
10 in layers as per project specification and compacted to required
degree of compaction (verify compaction test report

Remarks:

Reference:

Record Acceptance Sub Contractor QCI Contractor QCM Employer


Name

Signature

Date
PROJECT: CPF PHASE 1 AT BADRA OIL
FIELDPermanent Camp Phase-II Project ITR No : C-021084 XA
INSPECTION & TEST RECORD-CIVIL
Proj.ITR No:
AREA CIVIL WORK COMPLETION
GB088GB150-2013IE02-
CERTIFICATCONCRETE PRECAST UNITS
0200-QA-IT-20104
INSTALLATION CHECK SHEETE
Rev. : B0
(Space reserved for barcode) Project No: JI-2013IE02
Record No:
TAG RFI No:
SUB-SYSTEM No:
Description:
Drawing No: Rev:
Location:
Specification No: Rev:
Quality Control Procedure No: Rev:

Record Acceptance Sub Contractor QCI Contractor QCM Employer


Name

Signature

Date

You might also like