NAME OF PROJECT :-

CONSTRUCTION OF ADMINISTRATION BUILDINGS COMMANDANT OFFICE,COMPANY AND


WIRELESS OFFICE,QUARTER GUARD,MULTIPURPOSE HALL,MTS WORKSHOP BUILDING,READING
ROOM & GYMNASIUM,PRIMARY HEALTH CENTER,SITE OFFICE & 557 RESIDENTIAL QUARTERS OF
TYPE II,III,IV,VI FOR S.R.P.F. GR III AT JALNA

ABSTRACT

SEWAGE TREATMENT PLANT - 550KLD

sr no Item Description Qty Unit Rate Amount


1 Providing, supplying, constructing, installing, testing, 1 SET 15134013 15134013
comisioning and giving satisfactory trials of
modernised Sewage Treatment Plant Of Make -
Green Act consisting of receiving chamber, screen
chamber, grit chamber, measuring flume, distribution
chamber with primary and secondary treatment, etc.
as detailed below, for waste disposal with all civil,
mechanical, & electrical works involved, along with
five years AMC etc. complete (turn key job).

Supply, installation, testing and commissioning of


filter feed pump including all required accessories for
pumps.
Each pump in set shall be equipped with isolation
valves, reducers,
Pump (1 working +1 standby) System flow - 40
m3/hr @ 30 mtrs head

Supply, installation, testing & commissioning of


SLUDGE TRANSFER PUMP non clogging type
pumps capable of handling solids upto 10 mm
having Cast iron casing & CIimpeller complete with
all accessories, motor of required capacity. Delivery
header with isolation valve, pressure gauge on
delivery line with isolation valve, reducer

Pumps shall have following duty:Sludge handling


pump (1Working + 1Standby) System flow
15m3/hr @ 12 mtr. Head

256
Supplying, installing, testing and commissioning of
Pressure sand filter shall be suitable for working
pressure of 6.0 kg/cm and minimum burst pressure
is 10 kg/cm and shall include media, standard
fittings like pressure gauges, sampling cock, rinse
drain, vacuum breaker, with FRONTAL PIPING AND
VALVES with all required accessories.
Pressure sand filter
System flow 35m3/hr
Filtration Velocity : 15-16 M/S
Material of Construction : mild steel

Supplying, installing, testing and commissioning of


Activated Carbon filtershall be suitable for working
pressure of 6.0 kg/cm and minimum burst pressure
is 10 kg/cm and shall include media, standard
fittings like pressure gauges, sampling cock, rinse
drain, vacuum breaker, with frontal piping and valves
with all required accessories. Activated carbon filter
System flow 35m3/hr Filtration Velocity : 15-16 M/S
Material of Construction : mild steel

UV disinfection system, require gasket and steel


tubes (SS316), require bolt and nuts, studs,
operating valves, flanges, etc to complete the
installation. With 1W system

Supply Installation Testing and commissioning of all


interconnection UPVC piping, pipe support, including
all fittings, valves, bypass valves, flanges, union, for
proper operating of plant.
MS ERW class for air piping

Supply, Installation Testing & commissioning of


Sludge dewatering system CENTRIFUGE
ELECTRICALS WORKS
Supply, Installation Testing & Commissioning of
Electricals of Sewage treatment plant
LT PANEL

Supply, installation, Testing & Commissioning of LT


Panel Boards. Complete in all respects as per
technical specifications & approval of Client /
Consultant. Refer Electrical Specification no.

257
LT Panel Boards made of 14 SWG powder coated
sheet steel of appropriate Degree of Protection for
Indoor type (as per IS: 13947 Part-I) with C
channels for support with single front openable
doors with duly gasketed with Neoprene gaskets for
all switch gears and Aluminium bus bar with heat
shrinkable colored PVC Sleeves including control
wiring with ferrule & duly riveted anodized aluminium
labels for identification of switch gears all complete.
The Switchboards shall be provided with removable
gland plates for entry of cables from the bottom.
Schematic diagram shall be displayed at the LT
Panel Boards front with glowing fonts. Etc complete

PUMP PANEL
a. Busbar: 100A, TPN (35KA) Aluminium bus bars
with colour coded heat shrinkable insulating sleeves.

b. Incomer: 100A, TPN MCCB, 35kA - 1 Nos.


protection and measurement as per specification
and with following accessories:

c. Metering :

One Set of Phase indicating lights protected by 4


amp fuses, 1 No. 96 x 96 mm 0-100 Amp digital
ammeter with Selector switch and 3 nos. suitable
CTs, 1 No. 96 x 96 mm 0-500 Volt digital voltmeter
with selector switch and 1 No. 96 x 96 mm KWH
Meter, cts shall be protected by 4 amp fuses.

d. Outgoings :

16A, 3 Pole MCB, 10kA - 10 Nos.


Including,

Require wires/cables with necessary cable tray,


supports and Termination with all required
accessories.

Eartning materials for connection from pumps and


panel to nearest earth grid.

Contractor shall provide three extra breaker for


lighting, and ventilation system.
Contractor to consider internal earthing and earthing
strip required as per design.

Note:
All pumps shall be equipped with the control panel
for operating based on level indicator.

258
contractor should consider Hi, Low and dry run
controls and indicators for protecting pump from dry
run and start and stop pump based on water level.

all internal piping require valves, strainers, pressure


gauge , piping from raw water tank, within the
system to treated water tanks shall be consider in
contractors scope. Pipes shall be GI B class /
contractor to specify the same.

Contractor shall include all foundation work require


for the mounting of filters, pumps and other
equipment in his scope.
Contactor shall submit all the GA drawings, P & I/D
diagram and data sheet calculation prior to
installation.
Contract can quote for different types of STP,
however he has to confirm the fixing of the same in
given drawing.
Contractor shall keep provision in STP electrical
panel for Ventilation and Lighting breaker. This can
be paid extra as negotiated
Providing, Suppling, installing, testing &
commissioning of water transfer pumping system
including all required accessories for pumps etc
complete.
Each pump in set shall be equipped with
isolation valves, reducers, flexible bellows on
both discharge and suction side, non return valve
and pressure gauge on discharge side, y strainer ( if
required ) on suction side, etc. (depending upon
submersible /non submersible pumps requirement)
including foundation and supports

Including Electrical control panel with require


rating MCCBs and starters, protections, isolators,
and require cabling and all accessories as per
system requirement.

Including Electrical connection to pumps from


panel using suitable conductors and earthing of
equipment.
Including Hi and low level indication and control
system to on and off the pump system based on
water level and avoid dry run of pumps

All interconnection piping as required for


system.
Including all the structural supports, cable trays,
conduits, stainless steel pump skid, fasteners, bolts
and nuts with all accessories for completion of work.

Note:

259
Pump motor shall be EFF-1 as per green building
standard requirement
Filter feed pumps (1W+1S)
System flow - 40 m3/hr & head 30 mtrs

ANNUAL MAINTAINNACE CONTRACT


Providing working staff for the STP for AMC period
of five years maintaining and running the plant
continuously including all gaurunttee, warranty for
five years including all spares,Manpower (3
Operators+1 Supervisor cum reliever), with
chemicals consumables and spares etc.etc
complete.
Annual Maintenance contract for first year, With
working staff in three shift

Annual Maintenance contract for second year, With


Annual Maintenance contract for third year, With
working staff in three shift
Annual Maintenance contract for fourth year, With
working staff in three shift
Annual Maintenance contract for fifth year, With
working staff in three shift

Grand Total Rs 15134013

260
NAME OF PROJECT :-

CONSTRUCTION OF ADMINISTRATION BUILDINGS COMMANDANT OFFICE,COMPANY AND


WIRELESS OFFICE,QUARTER GUARD,MULTIPURPOSE HALL,MTS WORKSHOP BUILDING,READING
ROOM & GYMNASIUM,PRIMARY HEALTH CENTER,SITE OFFICE & 557 RESIDENTIAL QUARTERS OF
TYPE II,III,IV,VI FOR S.R.P.F. GR III AT JALNA

ABSTRACT
(ESTIMATE BASED ON DSR OF PWD AURANGABAD & JALNA DIVISION YEAR 15-16)

SOLAR WATER HEATING SYSTEM

Item No Short Description Unit QTY Rate Amount


(1) (2) (3)
4.1 Solar Hot Water System(ESD-SHWS)
4-1-2 Supplying & Installing, Testing & Commissioning of Each 60 49643 2978580
Solar water heating system without heat exchanger
type of 250 LPD capacity as per specification No. ESD-
SHWS
4-1-3 Supplying & Installing, Testing & Commissioning of Each 62 100057 6203534
Solar water heating system without heat exchanger
type of 500 LPD capacity as per specification No. ESD-
SHWS

4.2 Pipes for Solar Hot Water System (ESD-HWP)

4-2-1 Supplying and erecting G.I pipe 15 mm dia B class with m 200 404 80800
resin bonded flap rock wool/glass wool insulation,
with necessary material as per specification No. (ESD-
HWP/TGP)
4-2-2 Supplying and erecting G.I pipe 20 mm dia B class with m 100 526 52600
resin bonded flap rock wool/glass wool insulation,
with necessary material as per specification No. (ESD-
HWP/TGP)
4-2-3 Supplying and erecting G.I pipe 25 mm dia B class with m 100 638 63800
resin bonded flap rock wool/glass wool insulation,
with necessary material as per specification No. (ESD-
HWP/TGP)

GRAND TOTAL 9379314

276
NAME OF PROJECT :-

CONSTRUCTION OF ADMINISTRATION BUILDINGS COMMANDANT OFFICE,COMPANY AND


WIRELESS OFFICE,QUARTER GUARD,MULTIPURPOSE HALL,MTS WORKSHOP
BUILDING,READING ROOM & GYMNASIUM,PRIMARY HEALTH CENTER,SITE OFFICE & 557
RESIDENTIAL QUARTERS OF TYPE II,III,IV,VI FOR S.R.P.F. GR III AT JALNA

MEASUREMENT SHEET

SOLAR WATER HEATING SYSTEM

Item No Short Description Unit QTY


(1) (2) (3)
4.1 Solar Hot Water System(ESD-SHWS)
4-1-2 Supplying & Installing, Testing & Commissioning of Solar water Each 60
heating system without heat exchanger type of 250 LPD capacity as
per specification No. ESD-SHWS
Type II
250ltr x 2 system x 30 bld = 60 system

4-1-3 Supplying & Installing, Testing & Commissioning of Solar water Each 62
heating system without heat exchanger type of 500 LPD capacity as
per specification No. ESD-SHWS
Type II
500ltr x 2 system x 30 bld = 60 system

Type III
500ltr x 2 system x 1 bld = 2 system

4.2 Pipes for Solar Hot Water System (ESD-HWP)


4-2-1 Supplying and erecting G.I pipe 15 mm dia B class with resin m 200
bonded flap rock wool/glass wool insulation, with necessary
material as per specification No. (ESD-HWP/TGP)
as per Tender Drawing & Computer calculation

4-2-2 Supplying and erecting G.I pipe 20 mm dia B class with resin m 100
bonded flap rock wool/glass wool insulation, with necessary
material as per specification No. (ESD-HWP/TGP)
as per Tender Drawing & Computer calculation

4-2-3 Supplying and erecting G.I pipe 25 mm dia B class with resin m 100
bonded flap rock wool/glass wool insulation, with necessary
material as per specification No. (ESD-HWP/TGP)
as per Tender Drawing & Computer calculation

277