You are on page 1of 69

Scientific Council:

dr hab. ukasz Baszczak, prof. dr hab. Maria Dragun-Gertner, dr Beata Gessel Kalinowska vel Kalisz,
prof. dr hab. Jadwiga Pazdan, prof. dr hab. Jerzy Poczobut, prof. dr hab. Jerzy Rajski
prof. dr hab. Marek Michalski, prof. dr hab. Andrzej Szumaski

Editorial Board:

Main Editor: prof. dr hab. Jadwiga Pazdan


dr ukasz arnowiec

Editorial Committee:

Przemysaw Krzywosz
ucja Nowak
Jadwiga Pazdan
ukasz arnowiec

Secretary Editor:

Agnieszka Ralska-Kucal, arozalska@pkpplewiatan.pl


Maria Dudziska, mdudzinska@pkpplewiatan.pl

ISSN: 2083-8190

Court of Arbitration at PCPE Lewiatan


ul. Zbyszka Cybulskiego 3
00-727 Warszawa
Phone: (+48 22) 55 99 970
Fax (+48 22) 55 99 910 (with a note dla Sdu)
e-mail: sadarbitrazowy@pkpplewiatan.pl
www.sadarbitrazowy.org.pl
Issue No. 1(8)/2012:

EDITORIAL
Przemysaw Krzywosz, ucja 5
Nowak, Jadwiga Pazdan, ukasz
arnowiec

ANALYSES & OPINIONS

Why arbitrate? Philip L. Bruner 6

Multiple Parties in the Construction Litigation Dominik Gakowski, Kamil 13


and Arbitration Proceedings Comparative Case Zawicki, Olga Horwath
Study

Effectiveness of contractual time-bars in Fidic con- Agnieszka Lizer-Klatka 22


tract under Polish Law

The Period for Giving Notice of Contractors Claims Piotr Bytnerowicz, Magda 29
Set Out in Sub-Clause 20.1 of the FIDIC Conditions Kofluk
in Light of Polish Law

Awarding In-House Counsel costs in arbitration Adam Olszewski, Ewelina 38


Czerniawko

Partnering and Dispute Management an instru- Peter Tr Nielsen 43


ment for Polish construction and Project industry?

Alternative methods of resolution of construction Vlodymyr Yaremko 51


disputes in Ukraine
CASE LAW

The legal nature of a consortium in the con- Compile Agnieszka Ralska- 56


text of creditors joint and several liability Kucal

Limitations period relating to a FIDIC-based Compile Agnieszka Ralska- 58


construction contract in the context of partial
Kucal
delivery of works

A construction contract or a contract for the Compile Agnieszka Ralska- 60


performance of a specific task? Kucal

LEWIATAN ARBITRATION MOOT COURT

Introduction Anna Maria Pukszto 64

Ist Edition of The Competiton Photos Tomasz Szczepek, Robert 66


Gardziski, Compile Maria Du-
dziska
EDITORIAL

Dear Readers,

We have a pleasure to present the new e-Review. This time, we have devoted the whole number
to building industry matters, including, specifically, the FIDIC based contracts.
In the context of the infrastructure development in our country and of the disputes arising out of
the contract performance, we expect that this topic will attract the interest of a broad range of practi-
tioners, and that the Readers will benefit from this form of consolidation of provided material that
has been aimed at enabling them having many interesting viewpoints available to them at one place.
We have made efforts to select the most interesting articles presenting issues that involve doubts in
practice or that give rise to different interpretations. We have also added items dealing with arbitra-
tion and foreign practice developments in belief that they will enable the Readers to get acquainted
with other countries approaches and to apply their experiences in everyday work.
This study suits well the subject matter of and, in our opinion, may be a good supplement to, the
material of the several conferences organized in Poland, which show the interest paid in the region
and in the arbitration aspects involved in the building industry, such as the very successful FIDIC
(KIG) Regional Conference held in April or the workshops organized by SIDIR in May, that discuss
the conditions of changing the terms of FIDIC-based building contracts.
Let us point out that the articles we publish express only their authors opinions and are not the
opinions of the Court or of the editorial board neither may they be put down to them.
The review also contains extracts from selected Arbitration Courts awards we will be trying to
continue this practice in order to disseminate arbitration awards. There is also a part about Lewiatan
Arbitration Moot Court organized by Lewiatan Court of Arbitration and Young Arbitration
Practiotioners in Poland.
This new issue of the e-Review is a good occasion and forum to present its new Scientific Council:
dr hab. ukasz Baszczak, prof. dr hab. Maria Dragun-Gertner, dr Beata Gessel Kalinowska vel Kalisz,
prof. dr hab. Jadwiga Pazdan, prof. dr hab. Jerzy Poczobut, prof. dr hab. Jerzy Rajski, prof. dr hab. Ma-
rek Michalski, prof. dr hab. Andrzej Szumaski.
We wish you having a good reading and invite you to paying interest in the next e-Review in
which we will presenting sports issues.

Editors:

Przemysaw Krzywosz
ucja Nowak
Jadwiga Pazdan
ukasz arnowiec

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 5 |


ANALYSES & OPINIONS

Why Arbitrate?
Philip L. Bruner
Any inquiry into the wisdom of engaging in binding arbitration must begin with consideration
of the celebrated advice of U.S. Supreme Court Chief Justice Warren E. Burger, who in 1985 said this:

The obligation of the legal profession is, or has long been thought to be, to serve as healers of human
conflicts. To fulfill that traditional obligation means that there should be mechanisms that can produce
an acceptable result in the shortest possible time, with the least possible expense and with a minimum
of stress on the participants. That is what justice is all about.
One thing an appellate judge learns very quickly is that a large part of all litigation in the courts is an
exercise in futility and frustration. A large proportion of civil disputes in the courts could be disposed
of more satisfactorily in some other way.

Chief Justice Burger then went on to propose achieve Chief Justice Burgers vision of arbitra-
another way, and said: tion as an ADR method most suitable in com-
My overview of the work of the courts from plex cases for producing acceptable results in
a dozen years on the U.S. Court of Appeals the shortest possible time with the least possi-
[for the District of Columbia] and now six- ble expense and with a minimum of stress on
teen in my present position, added to twenty the participants.
years of private practice, has given me some To set the stage, let me begin by review-
new perspectives on the problems of arbi- ing why it is that disputes and claims, so en-
tration. ( ) My own experience persuades demic to the construction industry, have been
me that in terms of cost, time and human perceived since the late 1800s to be more suit-
wear and tear, arbitration is vastly better able for resolution by arbitration rather than
than conventional litigation for many kinds court litigation. Six points favoring both domes-
of cases (...) I emphasize this because to find tic and international arbitration over litigation
precisely the judge whose talents and expe- stand out:
rience fit a particular case of great complexi- First, construction has been for genera-
ty is a fortuitous circumstance. This can be tions and continues to be the largest segment of
made more likely if two intelligent litigants the production sector of the United States
agree to pick their own private triers of the economy, and quite likely of the world econo-
issues. 1 my. The industry comprises millions of compa-
The objectives of this article are: (1) to nies that employ many millions of people. In-
review binding arbitration as a method for re- dustry size alone will produce sizable numbers
solving complex construction disputes, (2) to of disputes amenable to resolution in a non-
discuss what cures exist for perceived prob- judicial forum.
lems with arbitration, and (3) to propose how A second reason favoring arbitration
best to utilize the binding arbitration process to over litigation is that construction is technolog-
ically complex. Construction comprises a host
1
Warren E. Burger, Using Arbitration to Achieve Justice, 40 Arb. of applied science disciplines, such as architec-
J. 3 (1985). ture, engineering sciences such as civil, soils,

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 6 |


ANALISES & OPINIONS

structural, electrical, mechanical and others, tions reflecting broad factual realities of in-
materials sciences that govern the formulation dustry experience, custom and usage, special-
and manufacture of building materials, and ized language and unique foreseeable risks
principles of construction and construction perceived as invoking the law of the shop ra-
management that address the practical building ther than the law of the courts. Construction
process. Constructions technological complexi- law addresses the complex legal relationships
ty is amplified by the uniqueness of each pro- between and among the multitude of parties
ject, which usually is built to a unique design, involved in a construction project owners,
on a unique site location, by a unique aggrega- architects, engineers, contractors, subcontrac-
tion of companies, operating without econo- tors, material suppliers and manufacturers,
mies of scale in an uncontrolled environment sureties, insurers, code officials, lenders invoke
where productivity is affected by weather, ge- a multitude of legal relationships and concepts
ology, local labor skills and availability, local to address legal rights and remedies arising out
building codes, and site accessibility. of a common dispute. Types of legal relation-
Construction has achieved a legendary ships include: (1) express and implied contrac-
reputation for complexity, which the judiciary tual relationships, (2) tort relationships in the
embellishes. As just one example, a 1999 opin- absence of contractual privity, (3) equitable
ion of the Supreme Court of California said: principles governing surety rights and obliga-
The owners may have hoped to build their tions, (4) statutory rights and obligations cre-
dream house and live happily ever after. ated by statues governing mechanics liens,
But there is a reason that tagline be- claims against surety bonds, sale of goods un-
longs only in fairy tales. Building a house der the Uniform Commercial Code, (5) public
may turn out to be a stress-free project; it duties created by building codes, licensing laws
is much more likely to be the stuff of urban and health and safety laws, and (6) specialized
legends the cause of bankruptcy, marital damage concepts unique to construction, such
dissolution, hypertension and fleeting fanta- as the doctrines of substantial performance,
sies ranging from homicide to suicide. As economic waste, betterment, and other ap-
Justice Yegan noted below: No reasonable proaches to damage measurement that recog-
homeowner can embark on a building pro- nize constructions imperfect world. As one U.
ject with certainty that the project will be S. Federal judge observed in 1974:
completed to perfection. Indeed, errors are Construction contracts are a separate breed
so likely to occur that few if any homeown- of animal, and, even if not completely sui
ers would be justified in resting their peace generis still the law must be stated in princi-
of mind on its timely or correct completion. ples reflecting underlying economic and in-
A third reason arbitration is perceived dustry realities. Therefore, it is not safe to
as better suited for resolution of construction broadly generalize. True, general principles
cases is that, as a consequence of constructions of contract law are applied to construction
increasing technological complexity, law gov- contracts, but they are applied under differ-
erning construction necessarily has become ent operative conditions. Care must be tak-
more complex, and has evolved into what some en, then, not to rely too uncritically on such
in the judiciary describe as a separate breed of cases as those arising from the sale of real or
animal. Construction law today comprises cen- personal property. And even within the larg-
turies-old legal theories fortified by statutory er rubric of construction contracts it is
law and seasoned by contextual legal innova- manifest that the law, if sensitive to the un-

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 7 |


ANALISES & OPINIONS

derlying realities, will carefully discriminate is a principal reason why international parties
between, say a contract to construct a home choose arbitration rather than local courts as
and a contract to construct a fifty-story of- the forum for resolution of their disputes.
fice building this is, generally, what one finds It is no wonder, then, that for genera-
when he reviews the actual development of tions both the courts and the construction in-
the law. dustry have perceived construction disputes to
A fourth reason favoring arbitration be best suited to be settled by arbitrators or
over court litigation is that, because of con- mediators experienced in the construction pro-
structions complexity and uniqueness, legal cess and expert in the law of the shop as well
proof of causation and quantification of damag- as the law of the courts. The U. S. construc-
es necessarily relies heavily upon opinion tes- tion industrys century-old historical prefer-
timony of experts a fact of life that can be ence for arbitration goes back for well over 100
frustrating to judges inexpert in construction years. Beginning with the 1888 Uniform Con-
and mesmerizing to jurors. Illustrative of this tract, which was the first national construction
fact of life is the advice offered by a federal contract negotiated between and co-sponsored
judge to the parties during a pre-trial confer- by the fledgling American Institute of Archi-
ence: tects and the National Association of Builders
Being trained in this field of construction, (predecessor of the Modern Associated General
you are in a far better position to adjust your Contractors of America), the American con-
differences than those untrained in its relat- struction industry mandated that disputes aris-
ed fields. As an illustration, I who have no ing out of the building process should be re-
training whatsoever in engineering, have to solved under legally enforceable non-judicial
determine whether or not the emergency dispute resolution processes employing ex-
generator system proposed to be furnished perts and ADR methods offering fair and rapid
() met the specifications, when experts resolution of disputes. The Industrys early
couldnt agree. This is a strange bit of logic ADR approach placed the design professional
(). The object of litigation is to do substan- as the professional peace keeper between the
tial justice between the parties litigant, but owner and contractor with authority to make
the parties litigant should realize that, in final decisions on disputes between the own-
most situations, they are by their particular er and contractor involving the scope and in-
training better able to accomplish this tent of the plans and specifications, and author-
among themselves. ized either party to refer other disputes to a
A fifth reason favoring arbitration is panel of arbitrators appointed by the parties.
that arbitration is amenable to maintaining This arrangement worked so well that as late as
business and personal relationships, and has 1967 a study of the legal profession in the Unit-
been said to be well-suited to the task of blur- ed States and England concluded that, regard-
ring the distinction between victor and van- ing U.S. construction industry disputes, law-
quished, so that the parties could continue their yers and courts will probably remain relatively
relations within the business community. unimportant to this sphere of conflict resolu-
A sixth reason favoring arbitration is tion.
that local fact finders are known sometimes to Yet 40 years later in 2007, this time-
hold views reflecting local prejudices and bias- honored U. S. construction industry approach
es. Arbitration can place disputes beyond the to ADR was turned on its head. The 2007 edi-
reach of such local biases and prejudices. This tions of the standard industry forms of the

str. 8 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

American Institute of Architects (AIA) and the tor selection procedures, where candidates are
ConcensusDocs jettisoned arbitration as the limited to a small list submitted by a low-level
mandated ADR method, and prescribed court case manager for the ADR provider, and sug-
litigation as the dispute resolution default op- gest that arbitrators too often lack requisite
tion. The AIA Documents also allowed the par- subject-matter and process expertise, fail to
ties to appoint their own initial decision mak- control the process, and end up splitting the
er in lieu of the architect. The apparent pur- baby. Complaints also suggest that arbitration
pose of those changes was to force parties to do disrupts business relationships by encouraging
their own early ADR planning upon pain of end- parties to accumulate disputes until the end of
ing up in court litigation. Thus, now for the first the job for resolution in a single arbitration
time in over a century, the construction indus- proceeding, rather than resolving them
try and its lawyers are obliged to craft and promptly and fairly as they arise.
agree upon ADR methods if they wish to avoid
resolving disputes by court litigation. The fa- Below is a list of eleven key initiatives
vored industry objective now is Rapid Resolu- being used by parties and their counsel to en-
tion - employing the right ADR method for the hance arbitrations efficiency and cost-
particular dispute at an early time. The indus- effectiveness of arbitration.
try has developed a number of non-binding
rapid resolution ADR methods that can be 1. Planning for Conflict Management.
tailored to the needs of each particular project First, parties must expect to plan ahead if they
and dispute, such as structured negotiations, wish to avoid court litigation as the default op-
project neutral, initial decision maker, expert tion. Failure of parties to plan for and apply
determination, dispute review board, media- business management principles to the resolu-
tion, adjudication, and non-binding mini-trial/ tion of business disputes has made arbitration
arbitration. The industry has demanded, and a scapegoat for lack of planning. Systematic
the legal profession is beginning to prescribe management of conflicts requires constant at-
by contract, various ADR methods aimed at tention to specific ADR methods most suitable
utilizing specialized expertise, innovation, effi- to resolution of particular disputes. The mes-
ciency and flexibility to rapidly resolve complex sage of the 2007 amendments to the AIA and
construction disputes. ConcensusDocs general conditions is that one
So what has caused this sea change in size of ADR does not fit all and those parties
construction ADR? Although each party has its need to plan for and include ADR methods suit-
own list of horrible, a major cause of mount- able to specific contracts and particular dis-
ing dissatisfaction with the arbitration process putes. In many jurisdictions, counsel has a pro-
arises out of long-standing tensions between fessional obligation to advise clients about al-
competing demands for economic efficiency ternatives to litigation that may be in the cli-
and for legal due process. Arbitration today is ents best interest. Thus, an affirmative agree-
viewed by many as having become ment to arbitrate, rather than consent by de-
judicialized and as expensive as litigation, due fault, now is the required pre-condition to en-
to over-lawyering, unlimited discovery, exten- gage in binding arbitration in the construction
sive motion practice, liberal hearing due pro- industry.
cess, inefficient arbitration administration,
and post-award disputes over confirmation. 2. Drafting a Good Arbitration Agree-
Complaints also point to unsatisfactory arbitra- ment. A second initiative is to have parties (not

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 9 |


ANALISES & OPINIONS

just their lawyers) focus on business objectives cepts for consideration in crafting an arbitra-
and on comparative balancing of economic effi- tion agreement to assure cost-effective and
ciency and legal due process. It is the parties timely resolution of disputes. JAMS, AAA and
themselves who have the most to say about just CPR all offer rules governing both complex and
how efficiently the arbitration will be conduct- expedited (JAMS $250,000, AAA $75,000, CPR
ed, and how many arbitrators ought to hear the no limit) arbitration, but they each are different
matter. In crafting the arbitration clause and in certain respects.
governing rules, parties need to understand
that the cost-effectiveness of the arbitration 4. Selecting Arbitrators With Requisite
process is not furthered by prescribing discov- Subject-matter and Arbitration Management
ery rules mirroring litigation practice. Expertise and Available Time. This fourth initi-
Drafting and agreeing upon arbitration ative is perhaps the most crucial factor in as-
rules is crucial. This calls for the parties to craft suring satisfaction with the arbitration process,
efficient rules, or at least review and tailor ADR and that is selection of one or three respected
provider rules, that best promote cost-efficient arbitrators with stellar expertise (1) in the sub-
arbitration. For example, such rules can deline- ject-matter of the disputes and (2) in arbitra-
ate the scope of powers granted to the arbitra- tion pre-hearing and hearing management, and
tors to decide issues and award types of relief (3) with time to hear the case without extended
and damages; can impose limits on pre-hearing interruptions. All too often, parties end up with
discovery; can invoke time limits for pre- arbitrators who lack expertise in one or both
hearing activities, for the hearing itself and for areas of expertise or who simply do not have
rendition of the award; and, can limit relief to the time to hear the arbitration without inter-
particular remedies and damages. Effective ruption.
expert arbitrators willing to enforce such Resolution of construction industry
agreed limitations typically will not allow ei- disputes, for example, demand arbitrators with
ther party to impede case progress except for expertise in construction practices and in con-
extraordinary good cause normally concurred struction law critical to the complex factual
with by the other party. and legal issues, such as: (1) whether the own-
Even when both parties have agreed to er or the contractor was the first to materially
extend an established schedule, however, effec- breach the contract, (2) whether the contract
tive expert arbitrators usually seek the concur- was properly terminated, (3) whether encoun-
rence of the parties themselves rather than rely tered soil conditions varied materially from
solely on the requests of counsel for it is the those represented in the contract documents,
parties themselves who will suffer the econom- (4) whether delay to the project critical path
ic consequences of a delayed award. was inexcusable, excusable, or compensable,
and so forth. These examples of disputed issues
3. Selecting the Right Arbitration Rules. of fact and law can best be resolved by arbitra-
A third initiative is to select the most appropri- tors who are expert in the subject matter.
ate arbitration rules. Both complex case and But, subject matter expertise alone is
expedited case rules are available from ADR not enough. Arbitrator expertise in manage-
providers. Although expedited rules are used ment of the arbitration process also is essential,
primarily for disputes involving limited issues because lack of proper control and timely re-
or smaller dollar amounts presented to a single sponsive rulings leads inexorably to significant
arbitrator, they offer good delineation of con- delay and added cost.

str. 10 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

A major arbitrator selection problem is (which may include some electronic docu-
inherent in the practice of some ADR providers ments) relevant to issues in dispute. Unless the
who submit lists of names of little-known arbi- parties have agreed expressly to open-ended
trators and, if parties fail to agree on arbitrator deposition discovery in their arbitration
selection from such lists, administratively ap- agreement, effective expert arbitrators normal-
point the arbitrators themselves. Requisite ex- ly exercise their inherent authority to limit
pertise and appropriate number of arbitrators, deposition discovery to key people and issues.
usually either one or three, is crucial to such
selection decisions. To avoid problems in major 7. Allowing pre-Hearing Dispositive Mo-
cases, parties usually compile their own lists of tions. A seventh initiative is to encourage dis-
arbitrators in disregard of ADR provider lists, positive motions. Effective expert arbitrators
and typically agree either to appoint a single are much more willing than those less expert to
arbitrator or agree each to appoint a neutral consider, when authorized, and grant where
arbitrator, with their two selected arbitrators appropriate, motions dispositive of all or part
appointing the panel chair. In compiling such of the case. All too often, arbitrators are unwill-
lists themselves, parties look for the best arbi- ing to grant dispositive motions out of fear that
trators anywhere in the world without regard courts may vacate an award.
to provider lists.
8. Promoting Joinder of Parties. An
5. Requiring Detailed Statements of eighth initiative is to promote joinder of inter-
Claim. A fifth initiative for promoting arbitra- ested and related parties. One inhibition to use
tion efficiency is requiring parties to present of arbitration has been arbitration clauses that
detailed factual statements of claim rather than limit joinder of relevant parties. Parties in civil
brief notice pleading as allowed in common law litigation have broad joinder rights, and the
courts. This helps the parties prepare their same broad rights are finding their way into
cases, and helps the arbitrators to focus on spe- arbitration by careful arbitration clause draft-
cific issues in dispute and consequent need for ing or by legal concepts of estoppel and vouch-
discovery. Rule 9 of the JAMS expedited con- ing in.
struction rules, for example, provides that the
claim submission shall include the material 9. Controlling the hearing. A ninth initi-
facts to be proved, legal authority relied on, ative calls on the arbitrators themselves to ex-
documents initially relied on, and names of all ercise better control over the hearing. Effective
witnesses and experts likely to testify at the expert arbitrators work with the parties to re-
hearing. Similar specificity of pleading is re- duce significantly the time required for hear-
quired by most international arbitration rules. ings by making effective use of (1) written wit-
ness statements for direct testimony, subject to
6. Limiting Document and Deposition live witness cross-examination; (2) employing
Discovery to the Issues. A sixth initiative is lim- a chess clock to maintain discipline in presen-
iting document and deposition discovery to tation of the case within the confines to time
critical issues and witnesses. Effective expert limits agreed upon; (3) reversal of admissibility
arbitrators know how to control and cut rules by allowing admissibility of offered doc-
through broad, open-ended discovery requests umentary evidence, unless expressly objected
to focus on salient facts. Initially parties usually to; (4) joint examination of expert witnesses;
are required to exchange classes of documents (5) not allowing delay or continuance without

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 11 |


ANALISES & OPINIONS

extraordinary just cause; and (6) providing to agree to a de novo review of the award, not
convenient break-out space for the parties, and by the courts, but by one or more expert appel-
refreshments and lunches so that parties do not late arbitrators. JAMS rules provide for such an
have to leave the premises. appellate review where the parties have so
agreed.
10. Requiring a Reasoned Award. A In conclusion, arbitration, when
tenth initiative is to require a reasoned award unjudicialized, is still preferred over litigation
in all cases, unless both parties agree other- because of the expertise that competent arbi-
wise. A reasoned award is essential to main- trators can bring to resolution of the dispute
taining confidence of the parties, without re- and to the efficiency of the proceedings. Win-
gard to the result, that the arbitrators have ston Churchills characterization of Democracy
carefully considered and decided all issues as the worst form of government, except for all
submitted. JAMS rules require a reasoned other forms, can also be said of arbitration.
award unless the parties agree otherwise: AAA ADR need not be an acronym for another day
rules are the reverse. To assure that no issue ruined rather than another dispute resolved.
submitted is overlooked, effective expert arbi- As my JAMS colleague Professor Tom
trators usually require the parties to submit at Stipanowich discusses in his article on Arbitra-
the close of the hearing final lists or score- tion The New Litigation, there are numerous
cards of the issues for decision. This cuts down ways that arbitration can be made more infor-
on later arguments that the arbitrators failed to mal and cost-efficient.
decide all submitted issues.
Philip L. Bruner*
11. Appealing the Award, and Scope of
Judicial Review. An eleventh initiative is to al-
leviate concern over the limited scope of judi-
cial review of an arbitration award by provid-
ing for appellate review of the award by a panel
of appellate arbitrators. For example, in the
United States, this initiative addresses the issue
decided by the U.S Supreme Court in Hall
Street Associates v. Mattel (2008), which ruled
that the statutory scope of judicial review un-
der the Federal Arbitration Act may not be al-
tered by agreement of the parties. Under some
state arbitration acts, however, courts follow-
ing the Supreme Court of California precedent * Philip L. Bruner: International Arbitrator and Mediator,
in the Cable Connection v. DirectTV (2008) may Fellow, Chartered Institute of Arbitrators, Director, Glob-
al Engineering & Construction Group, JAMS - The Resolu-
allow the parties to broaden by agreement the tion Experts!, London UK and New York NY,
statutory scope of judicial review to include pbruner@jamsinternational.com
everything from de novo review of errors of law
and findings of fact. Since virtually all major
construction projects involve interstate com-
merce, however, the Federal Act will preempt
contrary state law. The solution is for parties

str. 12 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALYSES & OPINIONS

Multiple Parties in the Construction Litigation and


Arbitration Proceedings Comparative Case Study
Dominik Gakowski, Kamil Zawicki, Olga Horwath

Dispute resolution in the case of construction contracts may prove to be a challenging and complex
process. When an investor enters into a construction contract with a general contractor, there are, as a
rule, several other parties involved in the process, such as: an architectural design studio and sub-
contractors. These parties are, as a rule, bound by several contracts. The existence of multiple parties
and multiple contracts is a key characteristic of the construction process. From the perspective of
disputes that might arise in connection with such contracts it is equally important that technologies
used in many construction projects can be described as a novelty and there are no common
standards for applying them. Also, faults in the buildings construction are often revealed after several
years and also under unusual, often extreme circumstances.

From the procedural perspective, both Fact Pattern


in the case of national courts and in arbitration, In our model case an investor decided to build
the main risk that emerges from such a a hospital ward. Innovative architectural
complexity of arrangements is that multiple solutions were proposed in the new buildings
parties are likely to commence multiple design. The modern design resulted, however,
litigations or arbitrations, which can eventually in the need to use a very advanced construction
lead to the existence of parallel proceedings technology, as the sloping roof was designed to
between the same parties or concerning have a bend into the building. The design was
identical issues and, in consequence, provided by a well-known architectural design
contradictory awards or rulings. studio. Similarly, the construction works were
The existence of multiple parties in a entrusted to a large, renowned, construction
single arbitration or litigation raises both legal company (general contractor). The sub-
and practical questions. In this article we would contractor of the construction company, whose
like to address some of them, from the task was to build the roof, was also a well
perspective of Polish procedural laws as well as known, highly specialized company. After the
from the perspective of arbitration. As it is our construction works were finished and the
intention to address the issues in a practical hospital ward was open to the public, the roof
manner, we would like to discuss an example of started leaking. As a result of heavy rainfall and
such challenging multi-party and multi- the resulting inundation, the hospitals
contract proceedings extracted from our expensive medical equipment was damaged.
practice. Three litigations followed the event,
which concerned: (i) a dispute between the
general contractor and the investor regarding
payment for the construction works, (ii) a dis-

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 13 |


ANALISES & OPINIONS

pute between the investor and the architectural Identification of the Legal Issues
design studio, and (iii) a dispute between the It is apparent from the facts pattern described
main constructor and the sub-contractor. In the above that the parties faced a paradoxical
first of the proceedings, the investor claimed situation, in which court experts opinions were
that the constructor carried out the works in- radically different and neither the parties, nor
correctly- inconsistently with the newest tech- the courts, undertook any steps in order to
nology- which resulted in the leaks and de- consolidate proceedings. The above-mentioned
struction of the equipment. The construction case can provide a good basis for further
company claimed that the investor presented consideration of how a national court in Poland
the company with incorrect documentation and (or the parties) could have acted, as the
also that the newest technology applied for national provisions
building the roof could not have been verified of law generally allow for the consolidation of
by the company, as such a novelty was beyond the proceedings if similar claims are disputed.
standard professional knowledge at the time. The regulations of the Code of Civil Procedure
There were three judgments hin this litigation (CCP) will be the basis of the analysis regarding
(the judgment that was unfavorable to the the ordinary civil proceedings as well as the
construction company was quashed twice). A separate norms concerning commercial
court experts independent opinion indicated disputes. We will briefly relate to the new regu-
that the fault was on the side of the lations of the CCP which will be in force as of e
construction company, but the defects were the 3rd of May 2012. The further part of this
present both in the project and its completion. article concerns the possibilities available to
According to the last decision in these the parties in the arbitration proceedings. The
proceedings, the fault was divided equally practical question of the reasonableness of
between the architectural design studio and the appointing several different experts in
contractor. Eventually, the dispute ended in a proceedings that share a common factual
settlement between the parties. In the second background lies outside the scope of this
litigation, the investor demanded comparison. It is characteristic for construction
compensation from the architectural design disputes involving a great number of
studio. The two independent opinions provided technological and construction issues that they
by court experts indicated that the completion are in fact decided on the basis on court
of the project, but not the design itself, was experts opinions. The fact pattern described
defective. In the third proceedings the sub- above should just serve as a model provided for
contractor demanded payment from the a discussion of a more systematic nature.
general contractor. an andependent expert
opinion was also delivered in this litigation. It Multiple Parties in Litigation before
stated that it was the design of the building that National Courts
was defective and the construction company The Polish legislator introduced several
was ordered to pay the sum indicated in the possibilities for parties to add new participants
contract. All these disputes were conducted in to the proceedings in the capacity of a claimant
the same Regional Court, as it had jurisdiction or respondent in the CCP. The CCP also
over all participants; each of the proceedings, contains mechanisms that allow, at least in
however, was decided separately. theory, for the proceedings that are related to
one another to be harmonized. We will discuss

str. 14 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

them below, in light of the fact pattern either, because in the above-mentioned case,
described above. neither of the participants acted parallel in
different procedural capacities (as a claimant
Joint Participation and Joinder (Citation) or respondent) in different proceedings. A
In Article 72 of the CCP, the Polish legislator further analysis of such a possibility would be
regulated the institution of joint participation, groundless. In the commercial mode, a counter-
when more than one person is joined as claim would not be admissible (Article 47914.3
claimant or respondent (formal joint of the CCP).
participation and substantive joint
participation). However, the courts would not Technical Consolidation of the Proceedings
be able to apply this institution in the above- The consolidation of the proceedings does not
mentioned case, as the premises for joint create a separate case, but is a technical,
participation have not been fulfilled. procedural device used by the courts in order
Consequently, also the regulations regarding a to increase economic efficiency of the trial. The
facultative citation (Art. 194.3 of the CCP) or judgment made by the court in a consolidated
court summons of a third party (Article 195 of case contains decisions regarding each of the
the CCP) would not be applicable, because the joined proceedings separately1. The most
possibility of using the institutions mentioned important advantage of consolidation is that it
above could be, theoretically, considered only allows contradicting judgments and the
in a different setting of participants of the multiplication of the procedural activities of the
litigations; for instance, if the investor acted in same kind (for example testimonies of the same
the capacity of the claimant in all proceedings. witnesses, courts experts opinions) to be
Even in such a configuration, it might be avoided. According to Article 219 of the CCP
difficult to prove that the rights and obligations separate cases can be consolidated if: (i) the
of all parties involved are common or share the cases are related to one another (or could fall
same factual or legal basis (material joint within the scope of one lawsuit), (ii) the cases
participation), or were of the same kind, or belong to the same procedural mode, (iii) the
were based on the same factual or legal cases are decided before the same court. Let us
grounds (formal joint participation). presume that the both latter premises are
In the case of a special procedural mode for fulfilled in order to concentrate on the relation
commercial cases (in which most construction between the cases. According to legal scholars,
disputes would be decided), paradoxically, the such a relation should be understood similarly
situation is even more unfavorable. According to Article 204 of the CCP, which here means
to Article 4794 2 of the CCP, the changes to that the claims have to result from the same
the subjects taking part in the proceeding are legal relationship or have the same factual
inadmissible. It must be noted, however, that basis2. Ascan be seen, the consolidation of cases
the commercial mode was abolished by the is not always a simple matter. The reasoning
legislator and new provisions will be in force as behind the procedural obstacles is to prevent
of 3 May 2012. consolidation from being used as a tool to delay
the proceedings. In the analyzed fact pattern,
Counter-claim according to Article 204 of
the CCP 1 A. Zieliski, Kodeks postpowania cywilnego.
The institution of the counter-claim, regulated Komentarz do artykuw 150514. Tom I, Warszawa
2005, p. 619.
in Article 204 of the CCP, would not be helpful 2 P. Telenga [in:] A. Jakubecki, Kodeks postpowania
cywilnego. Komentarz, Warszawa 2010, p. 293.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 15 |


ANALISES & OPINIONS

such action on the part of the court or the par- the proceedings. In such a case the provisions
ties would be, in our opinion, the most ade- of Article 73 2 of the CCP, which stipulates
quate. The final decision, whether to that the procedural actions of joint participants
consolidate the cases lies within the are valid also for joint participants who chose
prerogatives of the court as such a decision not to take part in the proceedings or not to
cannot be challenged by the parties. undertake this procedural action. Accessory
intervention in both of these forms can and
Main Intervention should be broadly applied in the proceedings in
The main intervention is regulated in Article 75 order to achieve the efficiency of the trial, not
of the CCP as a specific type of a lawsuit. It only as the judgment would have a res iudicata
helps to increase uniformity in a dispute effect to the independent intervener but also
between several parties as it provides a due to the limitation of the intervener to claim
possibility to uniformly decide in one that the procedural actions were faulty in
proceeding to whom a right or a thing belongs regards to the party that joined the proceeding.
(i.e. if it belongs to one of the parties of the (Article 82 of the CCP).
proceedings or to the intervener). There is a question, whether in the
Consolidation of cases commenced by configuration of entities involved in the facts
the interveners suit with the main proceedings pattern, a legal interest exists that would allow
can also be an aditional result of bringing the for accessory intervention or whether it is only
main intervention(Article 219 of the CCP). a factual interest? According to scholars, a legal
Another possibility is that the court will interest exists in the case of an ordinary
suspend the proceedings of the main case until accessory intervener when there is a legal
a binding judgment is issued in the main relationship of such a kind between him and
intervention case (Article 177 1 S.2 of the the party to the proceedings to which he
CCP). accedes that (based on the legal provisions of
It is apparent that this institution - substantive law) the judgment that will be
although useful in practice - would not be made in the proceedings can have
applicable in the case described at the a positive or negative impact on the legal
beginning of this article, as the distribution of sphere of the intervener. However, the legal
claims between the participant does not allow interest of an independent intervener exists
any of them to file a lawsuit based on the when the intervener is a party to the legal
institution of the main intervention. relationship that is the subject-matter of the
proceedings and he remains in such legal
Accessory Intervention relationship with the party to the proceedings
According to Article 76 of the CCP, the subject to which he accedes that the judgment made
who has a legal interest in deciding the case in those proceedings can have a positive or
favor of any of the parties taking part in the negative impact on the legal sphere of the
proceedings can join the proceedings. This intervener.
general clause of the CCP is supplemented by As the above shows, an evaluation and a
Article 81 of the CCP, which regulates decision as to whether the legal interest exists
independent intervention when it is apparent can be complicated.
from the nature of the case or stipulated by law
that the judgment will have a direct result
between the intervener and the other party to

str. 16 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

Third-Party Notice provide a construction allowing for making a


The third-party notice, regulated in Article 84 decision in all of the above-mentioned claims in
of the CCP, is an institution that allows the only one proceeding that would result in one
subject that could be bear regressive liability decision concerning all the participants. This
against one of the party of the proceedings to results from the high degree of formalism in the
be informed about the pending proceedings. civil procedure applied in national courts. Such
The third-party notice allows a time period, in a situation prevents the courts from
which such a person is to join the proceedings unconstrained action only procedural actions
in the capacity of an intervener. It also entails provided for in the CCP are allowed.
the limitation of the possibility of the interven-
er to claim that the party to which he acceded Multiple Parties in Arbitration Proceedings
caused failures in the conduct of the proceed- As a general rule, as far as arbitration is
ings that had a negative impact on the third concerned, the parties are not supposed to call
party (Article 82 of the CCP) . further parties to the proceedings, unless the
arbitration clause specifically binds all of the
Suspension of the Proceedings participants. Arbitration is based on the
Article 177 S.1 point 1 of the CCP also foresees consent of all parties and is characterized by a
the possibility of the facultative suspension of high level of confidentiality3. The prevailing
proceedings ex officio (such a decision may be view is that a multi-party arbitration is not
inspired by a motion of a party) if the adjudica- possible unless all the relevant parties have
tion of the case depends on the result of other consented to arbitration4. Parties may oppose
pending civil proceedings (suspension for pre- an intervention5 or a joinder6 of another party,
judicial considerations). Pursuant to Article because such a solution could expose sensitive
178 of the CCP, the Court can suspend proceed- commercial information. Introducing other
ings at the agreed request of the parties (such a participants to the arbitration proceedings
possibility, which is rather peculiar, does not without the previous consent of the other
regard proceedings in commercial cases - Arti- parties may be judged as an infringement of
cle 4794 3 of the CCP. their individual rights, especially with regard to
to due process7. Another problematic issue
The finding that the case is of a prejudicial na- involves the appointment of arbitrators, in a
ture for another case, resulting in the possibil-
ity of suspension of the latter, is not arbitrary. 3 See also A. Redfern, M. Luther, N. Blackaby, C.
In the legal doctrine, it is accepted that we are Partasides, Law and Practice of International
Arbitration, London 2004, p. 200; Gary B. Born,
dealing with prejudiciality when the subject of International Commercial Arbitration, Kluwer Law
prejudicial proceedings constitutes an element International 2009, p. 2071.
4 B. Hanotiau, Complex Arbitrations, Multiparty,
of the factual bases of the adjudication in the Multicontract, Multi-issue and Class Actions, Kluwer
other of the cases. In other words, when the Law International 2005, p. 165.
Under the intervention the situation should be
adjudication of a given case is not possible understood as a party, which is not a contracting
without prior adjudication of the prejudicial party, may wish to intervene with the proceedings.
6 When a contracting party acting as a respondent
issues, adjudicated in a different case. wishes to join another contracting
party which has not been named as the respondent in
the proceedings.
Conclusion See also: C. Yannaca-Small Consolidation of Claims: A
The Polish Code of Civil Procedure does not Promising Avenue for Investment Arbitration [in:]
International Investment Perspective, p. 237; D. St. J.
provide for a tailored regulation which would Sutton, J. Gill, M. Gearing, Russel on Arbitration,
London 2007, p. 108.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 17 |


ANALISES & OPINIONS

situation where there arew no previously the ICC Arbitration Rules10. The date on which
agreed rules8. If all the parties agreed on an the request is received will count as the date of
arbitration court, it is difficult to commence a commencement of the arbitration against the
multi-party arbitration when there is no additional party. No additional party may join
agreement addressing the consolidation of the after the confirmation or appointment of any
proceedings. On the other hand, the arbitrator, unless all parties, including the
consolidation of the proceedings can be additional party, agree otherwise. The
beneficial with respect to the efficiency of the Secretariat may set a deadline for filing the
arbitration process and may help prevent the Request for Joinder. The additional party to the
risk of having several conflicting arbitration proceedings may submit an answer in
awards9. accordance with the provisions of Articles 5.1.
5.4. If an arbitration has multiple participants,
Can Arbitration Provide Equally or More claims may be made by any party against any
Effective Solutions? other party, but no other claims are made after
The situation is slightly different when parties the Terms of Reference are signed or approved
decide to select institutional arbitration by the Court without the authorization of the
because then the relevant provisions of the arbitral tribunal (Article 8). Claims arising from
arbitration rules of a given institution can or in connection with more than one contract
provide a solution. Various arbitration may be made in a single arbitration,
institutions adopt different approaches to the irrespective of whether such claims are made
problem of intervention and the issuance of a under one or more than one arbitration
joinder. Some of the regulations of arbitration agreement under the ICC Arbitration Rules
courts do not foresee such a possibility at all. (Article 9). The Court has a prerogative to
Therefore, it is essential for the parties drafting consolidate two or more arbitrations pending
a contract to inspect the regulations of the under the ICC Arbitration Rules, into a single
institutions taken into consideration. arbitration proceeding if, alternatively: the
The Rules of the International Court of parties agree to consolidation, or all of the
Arbitration at the International Chamber of claims in the arbitrations are made under the
Commerce (ICC), effective as of 1 January 2012 same arbitration agreement, or the claims in
, determine that a party wishing to join an the arbitration are made under more than one
additional party in an arbitration shall submit arbitration agreement, the arbitrations are
its request for arbitration against the additional between the same parties, the disputes arise in
party (Request for Joinder) to the Secretariat. connection with the same legal relationship,
The specific requirements for the Request of and the Court finds the arbitration agreements
Joinder are stipulated in Article 7.2 and 7.3 of to be compatible. When making the decision on
consolidation, the Arbitration Court can take
into account any circumstances which it finds
relevant (Article 10 of the ICC Arbitration
Rules).
8 Gary B. Born, International Commercial Arbitration,
Kluwer Law International 2009, p. 2071. According to Article 15 of the
9 See also A. Redfern, M. Luther, N. Blackaby, C.
Arbitration Rules of the Vienna International
Partasides, Law and Practice of International
Arbitration, London 2004, p. 200; D. St. J. Sutton, J. Gill,
M. Gearing, Russel on Arbitration, London 2007, p.
108; Gary B. Born, International Commercial 10

Arbitration, Kluwer Law International 2009, p. 2069 http://www.iccwbo.org/uploadedFiles/Court/Arbitra


2070. tion/other/rules_arb_english.pdf.

str. 18 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

Arbitral Centre (2006)11, the claim will be The Arbitration Rules of the London
considered admissible only if three premises Court of International Arbitration contain a
are jointly fulfilled: (i) the Centre has similar, but less comprehensive provisions12.
jurisdiction over all Respondents, (ii) all Its Article 8 provides that where the
Claimants have nominated the same arbitrator Arbitration Agreement entitles each party
and also (iii) one of the following must howsoever to nominate an arbitrator, the
alternatively occur: (a) the applicable law parties to the dispute number more than two
positively provides that the claim is to be and such parties have not all agreed in writing
directed against several persons, (b) all that the disputant parties represent two
Respondents are, by applicable law, in legal separate sides for the formation of the Arbitral
accord or are bound by the same facts or are Tribunal as Claimant and Respondent
joint and severally bound, (c) the admissibility respectively, LCIA Court will appoint the
or multi-party proceedings have been agreed Arbitral Tribunal without regard to any partys
upon, (d) all Respondents submit to multiparty nomination. The arbitration clause will then be
proceedings and, in the case of proceedings read for all purposes as incorporating a written
before an arbitral tribunal, all Respondents agreement by the parties for the appointment
nominate the same arbitrator, (e) one or more of the Arbitral Tribunal by the LCIA Court.
of the Respondents on whom the claim was The arbitration rules of the Japan
served fails or fail to provide the particulars Commercial Arbitration Association also give
according to Article 10.2.b and c of the VIAC the power to consolidate multiple requests for
Arbitration Rules (Article 15.1.). In the event arbitration, in the event the claims are
the multi-party proceedings are admissible, the essentially and mutually related, to the
Respondents need to agree upon the number tribunal13. The request of the parties must
and the person of the arbitrator; if they fail to result from the same arbitration agreement,
reach agreement, the Secretary General will and not from the consent of the parties
make a decision for them. In the event the claim subsequent to the commencement of the
cannot be served on all Respondents, the proceedings.
Claimant may apply to continue the The UNCITRAL Arbitration Rules14, as
proceedings against those Respondents on revised in 2010, provide for a specification of
which the claim could be served, whereas the the mode of appointing an arbitrator, in the
proceedings against the remaining event there are multiple parties as claimants or
Respondents may be subject to separate respondents (Article 10). Unless the parties
proceedings. In cases other than those agreed on another method, the multiple parties
stipulated in Article 15.1 of the Arbitration acting as the claimant or as a respondent must
Rules, the consolidation of multiple disputes jointly select an arbitrator.
may be admissible only if the same arbitrator Also, the Polish Court of Arbitration at
or arbitrators have been appointed in all these the Polish Confederation of Private Employers
disputes which are to be consolidated and upon
the consent of all parties, as well as the 12 See:
arbitrator(s). http://www.lcia.org/Dispute_Resolution_Services/LCIA_Arbitr
ation_Rules.aspx.
13 See:
http://www.jcaa.or.jp/e/arbitration/docs/e_shouji.pdf.
14 See:
11 See also: http://internationales- http://www.uncitral.org/pdf/english/texts/arbitration/arb-
schiedsgericht.at/images/stories/documents/en/VIA rules-revised/pre-arb-rules-
C_Arbitration_Rules_2006_1.pdf. revised.pdf.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 19 |


ANALISES & OPINIONS

Lewiatan15 embraces respective regulations. In From the perspective of the issue of


its newest Arbitration Rules provisions multiple contracts, it is crucial to ensure that
concerning multiple parties were added16. the same arbitration clause is incorporated into
According to Article 7 of the Arbitration Rules, all project-related contracts. The consent of all
if multiple parties act as Claimant or parties is the key element of a joinder or
Respondent and the issue is litigated before intervention or consolidation in arbitration
three arbitrators, these multiple parties have to proceedings. It is also crucial that the
agree on the person of the arbitrator (if not, the arbitration clause provides for the same
Nomination Committee will make the approach to the place of arbitration, language,
appointment). In the case of one arbitrator, all substantive law, the jurisdiction of the
parties must agree on such person, failing appointed tribunal, as well as the person of the
which the Nomination Committee will appoint arbitrator or the arbitration institution. The
the arbitrator, according to Article 6.4 of the parties may also address the question of
Arbitration Rules. consolidation, as a preventive measure, if
parallel proceedingsoccur.
Conclusion As far as multiple parties are concerned,
The approach presented in the arbitration is the clause should at least contain an agreement
more flexible. Therefore, in complicated on: (i) the arbitration clause that refers to any
construction disputes this mode of dispute dispute arising from the construction contract
resolution should be preferrable, especially and related contracts, (ii) a joinder as an
when certain measures at the contract drafting additional party to any proceedings
stage are undertaken (see below). commenced in connection to the arbitration
clause, (iii) allow for the intervention of
Recommendations another party to the arbitration commenced
There are several methods for preventing under the arbitration clause.
parallel proceedings arising from the contracts One can also consider a general clause
concluded in connection with the construction which binds the parties to undertake pro-
process. As long as there is consent between arbitration steps, in the event of conflicting
the parties, even after the dispute arises, a positions or doubts.
range of solutions is at hand (such as the Additionally, the clause should include
appointment of the same arbitrator or a the method for the selection of an arbitrator by
consensual intervention, joinder or multiple parties, unless the parties decided to
consolidation of the proceedings). However, chose an institution and surrender to its
the most effective method for preventing the regulations, in which specific rules are
risks of multiple proceedings is to draft an provided. Also, the parties should specify that a
arbitration clause (or a stand-alone dispute notice of any proceedings commenced under
resolution protocol) that would address the the clause would be given to each contracting
problem of multiple parties, as well as multiple
contracts17. The recommendations for drafting arbitration clauses
for the multi-party arbitration as well as the
multi-contract arbitration can be found in the IBA
15 See: Guidelines for Drafting International Arbitration
http://www.sadarbitrazowy.org.pl/en/homepage. which also provide the wording of an arbitration
16 The Regulation is available at: clause. Compare respectively paragraphs 97105 and
http://www.sadarbitrazowy.org.pl/upload/Regulami 106113 at:
n1marca2012.pdf. http://www.ibanet.org/Publications/publications_IB
17 See D. St. J. Sutton, J. Gill, M. Gearing, Russel on A_guides_and_free_materials.aspx#drafting.
Arbitration, London 2007, p. 108109.

str. 20 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

party regardless of whether it is named as


respondent or not (the time limit for applying
for intervention following receipt of a notice of
arbitration should be specified, as well as the
prohibition on the appointment of an arbitrator
before the lapse thereof).

Dominik Gakowski*
Kamil Zawicki
Olga Horwath

*
Dominik Gakowski: attorney at law, KKG Partner
Kamil Zawicki: attorney at law, KKG Partner
Olga Horwath: LLM, associate

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 21 |


ANALYSES & OPINIONS

Effectiveness of contractual time-bars in Fidic contract


under Polish Law

Agnieszka Lizer-Klatka, PhD

The FIDIC Conditions of Contract (1999 edition) both for Plant and Design-Build (the so-called Yellow
Book) as well as for Construction (the so-called Red Book) include several provisions imposing an
obligation, both on the Contractor and on the Employer, to notify diverse circumstances or claims re-
garding the performed and contracted Works. Simultaneously, consequences of infringement of the
notification obligations have been regulated diversely, depending on the entity obliged to make
a notification and depending on the type of a given obligation.

In the FIDIC Conditions of Contract, the not later than 28 days after the Contractor be-
obligations of the Employer regarding the pe- came aware, or should have become aware, of
riod within which he is obliged to raise claims the event or circumstances. Should the Contrac-
have been defined relatively simply. In pursu- tor fail to give notice of a claim within the said
ance of the Sub-clause 2.5 of both said versions 28-day period, he would lose his entitlement to
of the Conditions of Contract if the Employer a given claim, and simultaneously, the Em-
considers himself to be entitled to any payment ployer would be discharged from all liability in
under any clause of the Contract or otherwise connection with the claim. As regards other
in connection with the Contract, as a rule, he time-limits for claims and notices provided in
should notify the Contractor about his claims as the FIDIC Conditions of Contract, the FIDIC
soon as practicable after the Employer became Conditions of Contract do not stipulate any
aware of the event or circumstances giving rise sanctions for failure to meet various specified
to the claim. Infringement of this obligation time limits for notification in the form of loss of
does not entail any sanction in the FIDIC Condi- a given claim.
tions of Contract . The sanction in the form of a loss of right
A different regulation is stipulated for to assert a claim is also provided for in Sub-
the claims raised by the Contractor. In line with clause 14.14 of both versions of FIDIC Condi-
the Sub-clause 20.1 of both versions of the tions of Contract. In compliance with this Sub-
FIDIC Conditions of Contract as regards clause, the Contractor loses its right to raise
claims for the so-called extension of time for any financial claims from the Employer under
completion and claims for any additional pay- or in connection with the Contract or execution
ment, under any Clause of the Conditions of of the Works, if the claim is not disclosed in the
Contract or otherwise in connection with the so-called Statement of Completion (in line with
Contract, the Contractor shall give notice to the the Sub-clause 14.10) and in the Final State-
Engineer, describing the event or circumstance ment (in line with Sub-clause 14.12), unless the
giving rise to the claim as soon as practicable, Employer committed a fraud, is in deliberate

str. 22 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

default as regards any contractual obligation or (1978)2, the effectiveness of setting the condi-
in case of the Employers reckless misconduct. tion of making claims by one of the parties to
the contract depends on two premises:
Special regulation regarding the time-
a contractual clause must specify precisely the
bars for raising claims of any kind both by the
time limit for notification, and moreover, it
Employer and by the Contractor is to be found
should make an express reservation that after
in Sub-clause 20.4 of both versions of the FIDIC
the time limit a given right expires. Such an in-
Conditions of Contract. The provision refers to
terpretation of Sub-clause 20.1 of the FIDIC
the possibility of appealing against decisions
Conditions of Contract, that a condition prece-
awarded by the Dispute Board and introduces
dent is set which extinguishes the Contractors
a 28-day time limit, which starts on the day
claims if the notification obligation is not met
when such a decision is received, for giving
has been also assumed by the authors of the
a Notice of Dissatisfaction by any of the Parties
FIDIC Conditions of Contract in the 1999 ver-
dissatisfied with the contents of the settlement.
sion3.
After the lapse of the time limit, the dissatisfied
Party forfeits the right to bring the claim for a Although, initially the admissibility and
settlement by an arbitration court in line with effectiveness of the solution adopted in Sub-
the Sub-clause 20.6, and the DBs decision be- clause 20.1 regarding the Contractors claims
comes final and binding on the Parties. gave rise to doubts in English law, at present
this issue is not so disputable. The possibility of
In accordance with the above stipula-
contractual stipulation of time bars to notify
tions of the FIDIC Conditions of Contract, fail-
the claims upon pain of losing them has been
ure to meet certain time limits for exercising
finally confirmed in the ruling given in Multi-
specified activities results in the expiration of
plex Construction v Honeywell Control Systems
a given right. Such a contractual legal construc-
[2007]4 and in the ruling in Streia Ltd v Sigma
tion that conditions existence of a given claim
Wireless Communications Ltd [2008]5. At pre-
on exercising certain acts of due care (lodging
sent, only the problem of executing the condi-
a notification, filing a claim within the time
tion precedent in specific circumstances of the
limit) may be differently classified under legal
case is disputable, especially the problem of
norms of the law applicable to the Contract.
loss of the Contractors claims due to reasons
In the Anglo-Saxon legal system, the so- attributable to the Employer, or resulting from
lution adopted in Sub-clause 20.1 of the FIDIC faulty action or negligence attributable to the
Conditions of Contract whose essence is to Employer. Some authors allow in these specific
condition the possibility of asserting certain circumstances the possibility of challenging the
claims by the Contractor on its fulfilling the effectiveness of contractual stipulations being
obligation to notify circumstances or events in the nature of a condition precedent6.
resulting in a claim for extension of time or any
additional payment is treated as setting
a condition precedent1. In line with the formula
assumed in the case Bremer Handelsgesell- 2 2 Lloyds Rep. 113, O(HL) per Lord Salon
schaft mbH v Vanden Avenne Izegem nv 3 Seppala: Contractors claims under the FIDIC Contracts for
Major Works, p. 17; see also: H. Lal: The rise and rise of time-
bar clauses, Management, Procurement and Law, z. 160, p. 26.
1 J. Glover, S. Hughes: Understanding the new FIDIC red book, A 4 EWHC 447 (TTC); quotation of J. Glover: FIDIC an overview,

clause-by-clause commentary, London 2006, p. 378; J. Glover: p. 98 s. 16;


FIDIC an overview: the latest developments, comparisons, 5 CILL 2544 per HHJ Davies QC; quotation of J. Glover: FIDIC an

claims and a look into the future, www.fenwickelliott.co.uk, overview, p. 100, s. 16;
2008, p. 14; N. Gould: Making claims for time and money, 6 H. Lal: The rise and rise of time-bar clauses s. 28; por. te J.

www.fenwickelliott.co.uk, s.17, p. 3. Glover: FIDIC an overview, p. 110-112, s. 18;

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 23 |


ANALISES & OPINIONS

Under Polish law, classification of con- which depends entirely on his will (the so-
tractual clauses setting time limits for the exe- called inadmissible protestative condition)8.
cution of specified acts of due care upon pain of Undoubtedly, the notification by the Contractor
losing a given right or claim by the entitled is an event that depends entirely on its will.
party may give rise to doubts. Most notably, Without embarking on a polemic about the
classifying the contractual constructions of that stand assumed, in principle, in jurisprudence,
type as setting a condition precedent seems though its correctness gives rise to doctrinal
groundless. disputes and is also an object of divergent
judgements of the Supreme Court9, it may be
In the Polish academic literature, A.
assumed for the present that both the admissi-
Wolter advocates the admissibility of introduc-
bility and assessment of the effectiveness of
ing contractual time-bars for the execution of
contractual clauses introducing time-bars for
specified acts of due care (notifica-
performing acts of due care which make the
tions)upon pain of losing a given right. He is of
retention of the right conditional should not
the opinion that introduction of the time-bars
be assessed under the regulations of the Civil
for complaints (that is the time-bars for notifi-
Code regarding the condition.
cation about a claim) does not denote the set-
ting of a preclusive time limit for making The Polish academic literature also ex-
claims, but it conditions the retention of the pressed the quite superficial opinion that the
right on the performance of a specified act. He contractual time-bars for complaints provided
claims that the parties that are permitted by for in the Sub-clause 20.1 are de facto contrac-
the statute to make the consequences of the tual time limits to sue similar in their construc-
entire legal transaction conditional, may set tion to the statute of limitations. In the opinion
a contractual condition for the occurrence or of some authors, preventing the Contractor
termination of certain rights resulting from the from making claims under the Contract due to
legal relationship under the contract7. So far, the lapse of time limits for notification is
this is the only opinion in the Polish academic equivalent in its function to the regulations on
literature that enables contractual clauses of the statute of limitations. Based thereon, the
that type being classified as a condition prece- opinion was expressed that setting a time limit
dent. of that type is either expressly contrary to the
contents of Article 119 of the Civil Code which
It seems that at present classifying the
forbids the shortening of the limitations period,
clauses that introduce contractual time-bars for
or is aimed at evading the regulations regard-
complaints upon pain of losing the entitlement
ing the statute of limitations, and as such is
or claims as setting the condition precedent is
groundless. In line with the dominant opinion
8 See, for instance, the ruling of the Supreme Court of
in the jurisprudence of the Supreme Court, in 5 June 2002, II CKN 701/00, OSP 2003, no. 10, item 124; the
pursuance of Article 89 of the Civil Code, ruling of the Supreme Court of 11 October 2002, I CKN
1044/00, Lex no. 75270; the ruling of the Supreme Court of
a condition cannot constitute an event, covered 24 April 2005, V CK 799/04, Lex no. 152457; the judgement of
with the debtors obligation, the fulfilment of the Supreme Court of 23 February 2011, V CSK 277/10, Lex no.
786398.
9 See, for instance, the ruling of the Supreme Court of

27 June 1995, I CR 7/95, OSNC 1995/12/183; the ruling of the


7 A. Wolter: Glosa do wyroku Sdu Najwyszego z dnia Supreme Court of 8 March 2002, III CKN 748/00, OSNC
1.07.1958 r. I CR 683/57/Gloss to the decision of the Supreme 2003/3/33; the ruling of the Supreme Court of 29 April 2009, II
Court from 1 July 1958 ref. no. I CR 683/57/, OSPIKA 1960, item CSK 614/08, OSNC 2010/2/32 and the ruling of the Supreme
187, p. 420; cf. also J. Ignatowicz [in:] System prawa cywilnego Court of 31 March 2005, V CK 490/04, Lex no. 277115; cf. also
Tom I, Cz oglna pod red. S. Grzybowskiego /Civil law sys- Z. Radwaski [in:] System prawa prywatnego. Tom 2, Prawo
tem, volume I, General Part, ed. by S. Grzybowski, 1985, p. 847, cywilne cz oglna, Warszawa 2002 /Private law system.
footnote 224. Volume 2, Civil law general part, Warsaw 2002/, p. 276;

str. 24 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

subject to the sanction of invalidity based on limit for the statute of limitations and from the
Article 58(1) of the Civil Code10. judicial time bars for making claims and, as
a rule, no solutions of relevance to the time
Statutory time limits for the perform-
limit for the statute of limitations are applied
ance of acts of due care, inclusive of notifica-
even by analogy to the regulations regarding
tions in order to retain the right, are not con-
complaint related proceedings. The above in-
sidered under Polish law the time-bars for the
cludes, but is not limited to, the regulations
statute of limitations. In principle, the legal na-
regarding suspension or discontinuance of the
ture of the so-called statutory time-bars for
running of the limitations period. Thus, there
complaints gives rise to no doubt. It is com-
are no grounds to compare the stipulations of
monly assumed that the time limits for com-
Sub-clause 20.1 of the FIDIC Conditions of Con-
plaints, including but not limited to, the ones
tract directly to the regulations of the Civil
resulting from Article 563(1) of the Civil Code,
Code governing the institution of the statute of
are a kind of non-judicial time bars and thus
limitations. Such a broadly understood analogy
they do not constitute time limits for asserting
is groundless as the time bars for notification
claims11. Some authors draw attention to the
stipulated by the FIDIC Conditions of Contract
fact that the time-bars for complaints are pre-
do not refer to the actions to be taken before
liminary towards actions for which the statute
the court.
provides for the judicial time bars or the time
limit for the statute of limitations12. Time bars It seems that the time bars provided for
of that type differ significantly from the time in Sub-clause 20.1 of the FIDIC Conditions of
Contract most resemble, as regards their con-
10 J. Kosiski: FIDIC a polskie prawo /FIDIC and Polish law/, struction, the statutory time bars for com-
Biuletyn Informacyjny Konsultant 2009, no. 14, p. 9; cf. also T.
Latawiec: FIDIC a polskie regulacje prawne. Czy stosowanie plaints one of the statutory time bars. The
warunkw kontraktowych FIDIC przeszkadza w sprawnej Ineffective lapse of the time limit for a specific
realizacji kontraktw /FIDIC and Polish legal regulations. Does
the application of the FIDIC Conditions of Contract hinders the notification results in the loss of entitlement.
efficient execution of contracts?/, Biuletyn Informacyjny Kon- The contractual clauses that stipulate the con-
sultant no. 12/2009, p. 10. such a standpoint may be substan-
tiated taking into account the judgement of the Supreme Court sequence of the loss of entitlement should one
dated 18 February 2011, I CSK 358/10, Bulletin of the Supreme of the parties fail to fulfil its obligation within
Court from 2011, np. 6, item 10 in line with which contractual
stipulations forbidding, also indirectly, waiving the charge of the time limit provided for in the contract may
the statute of limitations are not legally admissible as being be classified as the so-called contractual time
contrary to Article 117 (2) of the Civil Code.
11 B. Kordasiewicz [in:] System prawa prywatnego. Prawo cy- bar, or the so-called purely contractual time
wilne cz oglna, t.2, Warszawa 2002/Private law system.
Civil law general part, volume 2, Warsaw 2002/, p. 628; J.
bars. Article 353(1) of the Civil Code might be
Ignatowicz [in:] System prawa cywilnego /Civil law system /, the only normative basis for the admissibility of
p. 841; S. Rudnicki [in:] Komentarz do kodeksu cywilnego.
Ksiga pierwsza. Czc oglna, Warszawa 2009 /Commentary
the clauses of that type. 13
to the civil code. The first book. General part, Warsaw 2009/, p.
495; S. Wjcik: Z problematyki przedawnienia i terminw zawi- The concept of the so-called contractual
tych w prawie cywilnym /Selected problems related to statute of time bars is not completely new in the Polish
limitations and final dates in civil law/ [in:] Studia z prawa
cywilnego i gospodarczego. Ksiga pamitkowa dedykowana academic literature. The classification of con-
profesor Czesawie uawskiej, Krakw 2000 /Studies in civil tractual clauses of that type and an appraisal of
and business law. Commemorative book dedicated to Prof.
Czesawa uawska, Krakow 2000/, p. 59; T. Zieliski:
Przedawnienie i terminy zawite na tle ustawy z dnia 17 lutego 13 B. Kordasiewicz: System prawa prywatnego /Private law
1961 r. o spdzielniach i ich zwizkach, Studia Cywilistyczne, t. system/, p. 650-652; A.Stangret-Smoczyska: Umowne termi-
XIX, Warszawa-Krakw 1971 /Statute of limitations and final ny zawite /Contractual final dates/, Przegld Sadowy 2011
dates based on the Act of 17 February 1961 pertaining to co- /Court Review 2011/, no. 1, p. 57; see also M. Jamka, A. Bar-
operatives and their associations, Civil law studies, volume XIX, czewski: Arbitra w sprawach budowlanych wybrane pro-
Warsaw-Krakow 1971/, p. 37; see also a resolution of the Su- blemy praktyczne /Arbitration in building cases selected prac-
preme Court 7s dated 19 May 1969, III CZP 5/68. tical problems/ [in:] Arbitra w Polsce, Warszawa 2011
12 B. Kordasiewicz: System prawa prywatnego, s. 631; /Arbitration in Poland, Warsaw 2011/ p. 47;

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 25 |


ANALISES & OPINIONS

their admissibility under Polish law was also that the standpoint prevailing in the Polish
the subject of a few incoherent rulings of the academic literature is such that the issue of a
Supreme Court14. However, the problem of time lapse, namely the statue of limitations and
functioning of purely contractual time bars in time bars constitutes a domain reserved exclu-
the transactions has been dealt with in only sively to statutory regulations16. There is
few publications and there are no available in- a general rule in Polish law that property
depth considerations thereon. The authors who claims are subject to the statute of limitations,
deal with the admissibility and appraisal of unless the regulations of the statute provide
contractual time bars usually conclude that otherwise (Article 117 (1) of the Civil Code).
under Article 353 (1) it is possible15 (or impos- However, there is no such rule pertaining to the
sible) to introduce the contractual time bars rights and entitlements other than claims. The
conditioning the retention or the occurrence of majority of authors are of the opinion that the
the entitlement on meeting the time limits consequence of the above is that the claims and
specified in the Contract. However, there are no other rights are subject to the operation of the
express statements in the doctrine regarding time bars only in the cases provided for in the
the possibility for introducing into the contract statute and only after the lapse of time limits
contractual time bars for complaints upon pain specified in specific regulations.17In particular,
of expiration of that right. Most notably, aca- S. Wjcik states his standpoint categorically. In
demic literature does not tackle the issue of the his statements, he underlines many times that
effectiveness of contractual time bars for mak- time limitation through time bars applies only
ing claims pertaining to the non-performance to those civil law rights which are expressly
or improper performance of the contract by the provided for as such by statute18.
other party to the civil law relationship. To justify his standpoint he stated that
The lack of relevant considerations re- the regulations providing for the time bars be-
garding the potential scope of admissibility of long - due to the general purposes which they
time bars is connected most of all with the fact serve, even to a greater extent than the ones
governing the statute of limitations to the
14 For instance the judgement of the Supreme Court of
30 June 1980, I CR 206/80, OSNC 1981, no. 4, item 63 in which
iuris cogentis norms. This means, for instance,
the Supreme Court adjudicated that failure to collect the award that the parties cannot set any preclusive time
within the time limit specified in the Regulations may lead to
the expiration of the claim; the judgement of the Supreme Court
limits for making claims or other rights before
of 20 September 2007, II CSK 241/07, Lex no. 487506 in which
the Supreme Court opted for the possibility of including
a clause linked with the time limit in the contract; the judge-
ment of the Supreme Court of 3 February 2011, I CSK 282/10,
Lex no. 7983229 in which the Supreme Court adjudicated that
it is admissible, under the freedom of contract principle, to 16 T. Padyna: Przedawnienie /Statute of limitations/, p. 94;
introduce the time limit into the preliminary contract after 17 J. Ignatowicz [w:] System prawa cywilnego /Civil law sys-
which the obligation to conclude the preliminary contract shall tem/,p. 845).
expire; see also the judgement of the Court of Appeal in Biay- 18 S. Wjcik: O potrzebie i sposobie uregulowania cywilno-

stok of 19 February 2003, I ACa 14/03, OSA 2003, no. 8, item prawnych terminw zawitych /About the need and method of
36 in which the court ruled that making a reservation in the regulating the civil law final dates/ [in:] Prace cywilistyczne.
general terms and conditions of the contract regarding the Ksiga pamitkowa dla uczczenia pracy naukowej profesora
termination of the contract in case of failure to pay a premium Jana Winiarza, Warszawa 1990 /Civil law works. Commemora-
within the time limit goes beyond the limits of the freedom tive book devoted to the scientific work of Prof. Jan Winiarz,
given to the Parties under Article 3531 of the Civil Code; Warsaw 1990/, p. 390; the same author: Z problematyki
15 In the Polish academic literature, the possibility of establish- /Selection of problems /, p. 61; the same author: W sprawie
ing contractual final dates was supported, among others, by B. metody oglnego uregulowania terminw zawitych /Regarding
Kordasiewicz: System prawa prywatnego /Private law sys- the method of general regulation of final dates/ [in:] Studia z
tem/, p. 632; A.Stangret-Smoczyska: Umowne terminy prawa prywatnego gospodarczego. Ksiga pamitkowa ku czci
zawite /Contractual final dates/,p. 58; cf. also T. Padyna: Profesora Ireneusza Weissa /Studies in private business law.
Przedawnienie w polskim prawie cywilnym, Warszawa 2010 Commemorative book devoted to Prof. Ireneusz Weiss/, Zakamy-
/Statute of limitations in Polish civil law, Warsaw 2010/, p. 98; cze 2003, p. 439.

str. 26 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

the body established for that purpose19. It is tion. However, in the opinion of the court it
also considered that the parties are not allowed does not mean that such a condition was totally
to agree on the length of the time bar stipulated ineffective in legal terms. In particular, failure
by statute, or on the moment the said time limit to make a complaint may constitute the basis
starts. The ban is derived from the rule in- for demanding compensation for the damage
cluded in Article 119 of the Civil Code: as it is which the defendant could suffer due to failure
not permissible to agree on moderating the to comply with the stipulations of that contrac-
time limits for the statute of limitations, and the tual condition21.
preclusive time limits are to be a more strict While analysing the admissibility of es-
method of affecting the execution of the right in tablishing the contractual time bars it shall be
question, all the more so they should not be kept in mind that the opinions, expressed both
changed by the will of the parties. In the opin- in the jurisprudence as well as in the academic
ion of some representatives of the doctrine, the literature, objecting to any autonomy of the
ban on contractual modifications does not refer Parties will as regards setting time bars mostly
fully to non-judicial preclusion20. date from the period before the change of the
An analysis of the admissibility of the political system in Poland and before the intro-
contractual time bars for complaints was also duction of Article 3531 into the Civil Code. At
the subject of a 1958 ruling of the Supreme present, the standpoint objecting to the func-
Court. Although the said ruling refers to regula- tioning in legal transactions of contractual time
tions that are no longer in force, the considera- bars limiting in time the existence of contrac-
tions of a general nature that are presented in tual entitlements seems to be unnecessarily
the reasons for the ruling may be useful also for rigorous. In professional transactions, reserv-
an appraisal of current civil law relationships. ing contractual time limits for the execution of
In the opinion of the Supreme Court, to settle contractual entitlements seems to be justified,
whether the contractual clauses establishing and in this scope the will of the Parties ex-
the time limits for making complaint claims pressed in this way should be respected.
should be deemed effective and if so - to what However, it seems debatable to allow
extent, it is important that acknowledging the
the possibility of setting the time limits for
full effectiveness of similar contractual clauses making claims or for notification upon pain of
would make it possible to make the expiration forfeiting the claim in a situation when they
of the rights or claims to which the parties are are based on the charge of non-performance or
entitled subject to the will of the parties. How- improper performance of the contract. The es-
ever, such dependence could not be reconciled sence of the contractual obligation of notifica-
with the principle that establishing the condi- tion of the claims attributable to the other
tions whose occurrence entails the statute of Party to the contract or to the circumstances
limitations as regards the claim or deprivation for which the other Party is liable limits the
of the right to enforce it in court (let alone the
possibility of such claims being asserted by the
conditions whose occurrence causes its expira- authorised Party before the court. There is also
tion) may be introduced only as a legal regula- no axiological justification for stipulations of
that kind, as the Party infringing the Contract
19 J. Ignatowicz [in:] System prawa cywilnego /Civil law sys-
tem/, p. 846; B. Kordasiewicz: System prawa prywatnego should have the same knowledge regarding
/Private law system/, p. 632. circumstances leading to liability, without be-
20 J. Ignatowicz [in:] System prawa cywilnego /Civil law sys-

tem/, p. 846; cf. also B. Kordasiewicz [in:] System prawa pry-


watnego /Private law system/, p. 632, footnote 3 and p. 21The judgement of the Superior Court dated 1 July 1958, I CR
634). 683/57, OSPIKA 1960, item 187.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 27 |


ANALISES & OPINIONS

ing separately informed about by the aggrieved


party. Thus such stipulations may be deemed
contrary to the nature of the legal relationship
and, as such, may be invalid.
The formula of making claims by the
Contractor described in Sub-clause 20.1 of
FIDIC covers both contractual entitlements (for
instance, to extend the time for performance)
as well as any financial claims, inclusive of
claims for indemnity under breach of Contract
by the Employer. Thus, it is not possible to give
explicit information whether the time limits
provided for notification by the Contractor
should be respected with all the consequences
stipulated by the contract. In my opinion, there
is no reason why one should not fully take into
account a sanction in the form of expiry of the
claim in the part regarding the Contractors
entitlement provided for in the contract, and
which does not result from the circumstances
related to the non-performance or improper
performance of the Contract by the Employer.
However, the Contractors failure to fulfil the
notification obligation should not result in the
expiration of the Contractors claims for in-
demnity from the Employer due to breach of
Contract. Failure to comply with the time limits
for notification also should not provide the ba-
sis for ignoring the Contractors charges against
the Employers claims.

Agnieszka Lizer-Klatka*

*Agnieszka Lizer-Klatka: PhD, legal advisor, ADP


Popioek Adwokaci i Doradcy Partner, Lewiatan Court of
Arbtration Arbitrator

str. 28 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALYSES & OPINIONS

The Period for Giving Notice of Contractors Claims Set


Out in Sub-Clause 20.1 of the FIDIC Conditions in Light of
Polish Law
Piotr Bytnerowicz, Magda Kofluk

1. The Period of 28 Days for Giving Notice of Contractors Claim Pros and Cons
Sub-Clause 20.1 of the FIDIC Conditions1 provides for a period of 28 days for the contractor to give
notice to the engineer about the circumstances giving rise to a claim for extension of the time for com-
pletion of works or any additional payment. This period is counted from the moment the contractor
became aware or should have become aware of the circumstances giving rise to the claim. Pursuant to
the second paragraph of Sub-Clause 20.1, if the contractor fails to give notice of a claim within the 28-
day period, the time for completion shall not be extended, the contractor shall not be entitled to addi-
tional payment, and the employer shall be discharged from all liability in connection with such a de-
layed contractors claim.

Both in Polish and international practice similar to the shortening of the period of limita-
the sanction for a contractors failure to give tion (termin przedawnienia) of a claim. Pursu-
notice of a claim within the period of 28 days ant to Article 119 of the Polish Civil Code, the
gives rise to controversy. Some commentators periods of limitation cannot be shortened by
recommend that the parties modify the FIDIC the parties. In view of the above, the provisions
Conditions by removing the wording which of the FIDIC Conditions providing for the forfei-
provides for such a sanction.1 This is because it ture of a contractors claims in the event of a
is questionable whether a stipulation of such a failure to give notice of such claims within 28
severe sanction as the forfeiture of a claim can days are invalid. Consequently, the intended
be effective. In some jurisdictions, this possibil- effect (the Contractors forfeiture of its claims)
ity does not cause serious concern, while in does not occur.3
others it is admissible only on certain condi- Another view is that Sub-Clause 20.1 of
tions, and in still others it is legally excluded.2 the FIDIC Conditions does not modify the pe-
In the Polish literature, there are two riod of limitation of claims, but provides for a
opposing views. According to the first view, the contractual prescription period (termin zawity)
effects of the stipulation of a sanction for the for asserting them. In the opinion of the propo-
failure to comply with the time limit in the form
of the forfeiture (expiration) of a claim are 3 See: T. Ciaowicz, Zgodno warunkw kontraktowych FIDIC z
przepisami polskiego prawa [The Consistency of the FIDIC Con-
1 B. Totterdill, FIDIC users guide. A practical guide to the 1999 ditions of Contract with the Provisions of Polish Law]
red and yellow books, 2006, p. 291. (http://www.taxfin.pl/artykul,724,Zgodnosc_warunkow_kontr
2 Cf., e.g., E. Baker, B. Mellors, S. Chalmers, A. Lavers, FIDIC aktowych_FIDIC_z_przepisami_polskiego_praw
Contracts: Law and Practice, London 2009, pp. 320-321; T.
Latawiec, FIDIC a polskie regulacje prawne [FIDIC and the a.html); T. Latawiec, FIDIC a polskie regulacje prawne [FIDIC
Polish Legal Regulations], Inynieria Bezwykopowa, July - Au- and the Polish Legal Regulations], Inynieria Bezwykopowa,
gust 2009, p. 77. July - August 2009, p. 77.

str. 29 | e-Przegld Arbitraowy nr1(8) 2012 r.


ANALISES & OPINIONS

nents of that view, this is admissible under Pol- of social coexistence6. According to this princi-
ish law. Therefore, the provisions of Sub-Clause ple, Polish civil law permits the construction of
20.1 excluding the possibility of a contractor contractual prescription periods.
asserting its claims after the expiration of the On the basis on the above assumptions, A. Ol-
period of 28 days are fully effective.4 szewski has expressed the view that the period
So far, this issue has not been clearly of 28 days for a contractor to give notice of a
settled in Polish case law or extensively ana- claim is a contractual prescription period ad-
lysed in the literature. This article is an attempt missible in light of Polish law under the princi-
to summarize and evaluate the arguments pre- ple of freedom of contract.7 That author is of
sented to support both opposing views and to the opinion that such a period must not be
point out the ones which, in the authors opin- identified with the period of limitation of
ion, are prevalent.5 First, we discuss the argu- claims. This is because the expiration of the
ments presented to support the thesis on Sub- period of limitation does not result in the expi-
Clause 20.1s effective stipulation of the con- ration of the claim, but only its transformation
tractual prescription period for asserting into a natural obligation which cannot be effec-
claims. Next, we present the arguments in fa- tively pursued before a court when the other
vour of concluding that the period of 28 days party raises the defence of limitation, but in
for giving notice of a claim, with the claim oth- some situations may set-off. On the other hand,
erwise being forfeited, cannot be effectively the consequence of failing to give notice of a
stipulated. claim within the period provided for under
Sub-Clause 20.1 is not the transformation of a
2. The Period for Giving Notice of a claim into a natural obligation, but its expira-
Claim as a Prescription Period tion. Thus, the formal and legal effects of failing
2.1 General Comments to meet such notice periods are different.
The view on the effectiveness of the stipulation Because of such different effects pro-
of the period of 28 days for a contractor to give duced by the expiration of the period of limita-
notice of a claim or otherwise forfeiting it, as tion and the failure to comply with the notice
provided for in Sub-Clause 20.1, and its consis- period under Sub-Clause 20.1, A. Olszewski
tency with Polish law is derived from the prin- concludes that the period under Sub-Clause
ciple of freedom of contract. Pursuant to Article 20.1 is not a period of limitation, but a contrac-
3531 of the Polish Civil Code, the parties may tual prescription period. For this reason, the
arrange their legal relationship at their discre- introduction of a period for giving notice of a
tion, provided its content or purpose is not in claim under Sub-Clause 20.1 is not in contradic-
contradiction to its nature, the law or the rules tion to Article 119 of the Polish Civil Code,
which does not permit the shortening or ex-

4 See: A. Olszewski, Kontraktowe procedury rozwizywania 6 The rules of social coexistence is a Polish law concept. For the
sporw w umowach o roboty budowlane opartych na wzorach purposes of this article, it can be assumed that these rules are,
umownych FIDIC w wietle prawa polskiego [Contract Proce- more or less, an equivalent of good customs.
dures of Settlement of Disputes in Contracts for Construction 7 A. Olszewski, Kontraktowe procedury rozwizywania sporw w

Works Based on The FIDIC Contract Forms in Light of Polish umowach o roboty budowlane opartych na wzorach umownych
Law], Monitor Prawniczy 21/2010, Radca Prawny 2/2010. FIDIC w wietle prawa polskiego [Contract Procedures for
5 The views expressed in this article are the private views of its Settlement of Disputes in Contracts for Construction Works
authors (and not of White & Case which the authors cooperate Based on the FIDIC Contract Forms In Light of Polish Law],
with) and do not constitute legal advice. Monitor Prawniczy 21/2010, Radca Prawny 2/2010.

str. 30 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

tending of periods of limitation by way of par- and out-of-court preclusion. Contractual pre-
ties consent. scription periods are divided into contractual
The consequence of adopting these arguments prescription periods sensu largo (in the
is the conclusion that the limitation of the con- broader sense) and contractual prescription
tractors right to assert its claims to the period periods sensu stricto (in the strict sense).
of 28 days as a contractual prescription period Contractual prescription periods sensu
under Sub-Clause 20.1 is admissible and legally largo are the periods whose application, effects
effective. Such a view seems to be difficult to and usually length are provided for in the Pol-
accept, first of all because of the nature and ish Civil Code, with a certain area being left to
rules governing prescription periods which, the parties discretion. This area, however, is
therefore, need to be briefly discussed. very limited and the non-interference of the
parties is of no relevance for the existence of
2.2 Characteristics of Prescription Periods the period itself and its effects. This is because
The notion of prescription periods is usually statutory provisions are applicable, unless oth-
associated by the doctrine with the periods erwise agreed by the parties. Such periods are
indicating the time limits for performing spe- also sometimes called dispositive. They in-
cific acts. Prescription periods are considerably clude, for example, the period for pursuing
rigorous, since failure to meet a deadline often claims under warranty or the period for exer-
results in the expiration of a right or entitle- cising the right of pre-emption. The group of
ment.8 Upon the expiration of such a period, the contractual prescription periods sensu largo
possibility of evoking a right limited by a pre- also includes periods whose length is not speci-
scription period or any other use of that right fied by statute, which leaves this issue to the
expires. Furthermore, it is impossible to set-off will of the parties (mixed contractual peri-
a claim after the expiration of its prescription ods). In the case of such periods, the source of
period and, in principle, it is inadmissible to entitlement to stipulate the period, the princi-
acknowledge a prescribed debt.9 In view of the ples of its course and effects of its expiration
foregoing, in accordance with the long- arise from statutory law. The length of the pe-
established view, prescription periods, in prin- riod and the fact of it being stipulated result
ciple, except for the exceptions discussed be- from the will of the parties. The period for ac-
low, are not left to the parties discretion.10 cepting an offer may serve as an example in this
Prescription periods may be either respect (Article 66, 2 of the Polish Civil Code).
statutory or contractual. Statutory prescrip- Contractual prescription periods sensu
tion periods are those for which a statutory stricto in turn are the periods for which the
provision is the source of existence of the pe- will of the parties is the only basis of their exis-
riod itself, its length and the effects of its expi- tence and determination of the effects of their
ration.11 Statutory prescription periods are di- expiration. They are also defined as pure
vided into two main groups: periods of court contractual prescription periods (and this is
the term that we will be using hereinafter).
8 A. Stangret-Smoczyska, Umowne terminy zawite [Contractual Their creation is accepted under the freedom of
Prescription Periods], Przegld Sdowy 1/2011, pp. 52-53.
9 Ibidem, p. 53. contract principle.12
10 B. Kordasiewicz [in:] System Prawa Prywatnego [The Private

Law System]. Vol. 2. Prawo cywilne cz oglna [The Civil


Law - A General Part], ed. Z. Radwaski, Warsaw 2008, Legalis.
11 A. Stangret-Smoczyska, Umowne terminy zawite [Contractu-

al Prescription Periods], Przegld Sdowy 1/2011, p. 52. 12 Ibidem, pp. 52-57.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 31 |


ANALISES & OPINIONS

If we assume that the period for giving prescription periods appointed on the basis of
notice of a contractors claim, as set out in Sub- statutory provisions (by the identification of the
Clause 20.1, is a prescription period, then that possible situations and entities authorised to
period should be classified as a pure contrac- stipulate the period) [i.e., contractual prescrip-
tual prescription period since it has no statu- tion periods the authors note], there are no
tory source. The will of the parties (consisting periods for asserting claims or any other enti-
of incorporating a FIDIC form into the content tlements before a court or any other authority.
of their legal relationship) is the only basis of This matter is regulated by the periods of court
its existence. In order to decide if a pure con- preclusion derived exclusively from the stat-
tractual prescription period, with the effects as ute.15 Thus, the parties to contract obligations
specified in Sub-Clause 20.1 (expiration of clearly have not been given any statutory right
claims), may be effectively stipulated, it is nec- of having an impact on the periods for asserting
essary to thoroughly analyse the principles ap- rights and claims before the competent authori-
plicable to such periods. ties. The more so, there are no grounds to ac-
In principle, it is admissible to introduce cept the possibility of introducing such periods
pure contractual prescription periods (i.e., ones by the will of the parties alone.
having no specific statutory basis). However, it For these reasons, treating the period of
is also pointed out that contractual periods 28 days under Sub-Clause 20.1 as a contractual
which limit pursuing claims, directly or indi- prescription period does not mean that the
rectly, before a court or any other authority ap- above Sub-Clause is consistent with Polish law
pointed to this end, should be considered inad- with respect to the effects of exceeding the pe-
missible. This matter is reserved for statutory riod for giving notice of a claim set out in that
regulations, including primarily the institution of Sub-Clause. As can be seen from the above
the statute of limitations [], which is not of a comments, there are strong arguments in fa-
dispositive nature due to the wording of Article vour of concluding that the effects of exceeding
119 of the Polish Civil Code.13 Thus, in accor- the period of 28 days for giving notice of a
dance with a well-established view in the doc- claim set out in Sub-Clause 20.1 in the form of
trine [] the parties must not establish preclu- expiration of the claim cannot be effectively
sive periods for pursuing claims or any other stipulated if a contract is governed by Polish
forms of subjective rights before competent au- law.
thorities [].14 Furthermore, even if one assumes that
This view should be accepted. It is a the introduction of a contractual prescription
logical consequence of the principles governing period for giving notice of claims under Sub-
prescription periods. It is a rule that the pre- Clause 20.1 is, in principle, consistent with Pol-
scription periods which limit the possibility of ish law, it would not automatically mean that
pursuing claims before a court or any other the effects of a failure to comply with that no-
competent authority are derived from statutes tice period could be effectively evoked in every
(they are statutory prescription periods). On case. The effectiveness of the stipulation of the
the other hand, [] in the group of contractual effects of failing to comply with the notice pe-
riod and the possibility of evoking them would
then have to be evaluated on the grounds of the
13Ibidem, p. 59.
14B. Kordasiewicz [in:] System Prawa Prywatnego [The Private
Law System]. Vol. 2. Prawo cywilne cz oglna [The Civil 15A. Stangret-Smoczyska, Umowne terminy zawite [Contractual
Law - A General Part], ed. Z. Radwaski, Warsaw 2008, Legalis. Prescription Periods], Przegld Sdowy 1/2011, p. 54.

str. 32 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

circumstances of each individual case. This is it is necessary to take into account, among
because pure contractual prescription periods other things, the purpose of the introduction of
and, in particular, their effects, are subject to the period of 28 days for giving notice of con-
evaluation in terms of the mandatory provi- tractor claims into the FIDIC contractual forms.
sions of law, the nature of a given contract obli- This purpose was specified by the authors of
gation and the rules of social coexistence (good the FIDIC forms as follows:
customs).16 After much reflection, the conclusion of
the FIDIC drafting committee was that
2.3 Contractual Prescription Periods and the there must be a notice of claim within 28
Defence of Abuse of Rights days [] so that all involved are aware
Moreover, if we were to conclude after such that there is an event or circumstance
evaluation that the period for giving notice of a where extra payment or time may be due
claim under Sub-Clause 20.1 was effectively to the contractor.21
stipulated, we should consider the possibility of Additionally, commentators emphasise
the contractor raising a defence of abuse of that the purpose of mutual notice of claims
rights. given by the parties to the contract is to make it
There is controversy in the doctrine and case possible to settle disputes, if possible, during
law as to the possibility of applying the defence the term of the contract.22 This means that the
of abuse of rights with respect to prescription introduction of the period for giving notice of a
periods.17 The doubts in this respect, however, contractors claim was aimed at, among other
pertain chiefly to statutory prescription peri- things, improving communication between the
ods, and not to contractual ones.18 In particular, parties and preventing a situation where the
the possibility of raising the defence of abuse of employer is taken by surprise by the contrac-
rights should not cause doubts with respect to tors claims after the completion of the con-
pure contractual prescription periods. Intro- tract. A question arises, however, if the un-
duction of a prescription period into a contract doubtedly right and justified interest of the
by the will of the parties only, its effects and employer in avoiding unexpected claims upon
principles of its course should be evaluated on the completion of the contract is sufficient to
the same principles as any other element of the deprive the contractor of its claims if the con-
contract.19 Consequently, raising of a defence of tractor fails to give notice of them within 28
abuse of rights could allow either for a denial to days from the date when the contractor became
take into account the expiration of the prescrip- aware or should have become aware of the
tion period at all or modifying the effects of its event or circumstance giving rise to its claim. In
expiration.20 particular, it is doubtful whether such interest
In order to evaluate the grounds for of the employer prevails over the interest of the
making an effective defence of abuse of rights, contractor in receiving payment for the addi-
tional costs caused by circumstances beyond
16 Ibidem, p. 58.
the contractors control or obtaining an exten-
17 A. Stpie-Smorek, F. Smorek, Przedawnienie i terminy zawite
[The Statute of Limitations and Prescription Periods], Lex
Polonica, Chapter 4.2. 21 C. Seppala, Contractors Claims under the FIDIC Contracts for
18 A. Stangret-Smoczyska, Umowne terminy zawite [Contractu- Major Works, (2005) 21(4) Construction Law Journal, p. 287,
al Prescription Periods], Przegld Sdowy 1/2011, p. 59. quote after: E. Baker, B. Mellors, S. Chalmers, A. Lavers, FIDIC
19 Ibidem, p. 59. Contracts: Law and Practice, London 2009, p. 311.
20 B. Kordasiewicz, [in:] System Prawa Prywatnego [The Private 22 J. Glover, S. Hughes, Understanding the New FIDIC Red Book.

Law System], Vol. II, C. H. Beck 2008, p. 697. A clause-by-clause commentary, 2009, p. 378.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 33 |


ANALISES & OPINIONS

sion of time for the completion of works when tractor other than by a formal notice of a claim
the works are delayed as a result of such cir- made pursuant to Sub-Clause 20.1. These situa-
cumstances. tions may include, for instance, cases in which
Furthermore, it will be necessary to con- the contractor must stop working because of
sider, on a case-by-case basis, whether the failure to the actions of the employer itself or the occur-
give notice of a claim actually resulted in the fact rence of unforeseeable circumstances a risk
that the employer was not aware of the circum- attributable to the employer. Examples include:
stances or events which could give rise to a claim
a) work delays caused by the au-
for additional payment or an extension of time. In
thorities;
other words, if, in spite of the absence of a notice,
the purpose which that notice is intended to serve
b) engineers instruction to suspend
has not been nevertheless achieved in full or in part. works, e.g., because of the neces-
In contracts carried out under the FIDIC forms, the sity to carry out archaeological
employer has its representative the engineer (a works;
member of the employers personnel Sub-Clause c) unforeseeable operation of the
1.1.2.6), who is regularly present on site and has forces of nature, such as floods;
up-to-date knowledge of the progress of the works d) the employers failure to give the
and related issues. The engineer should, therefore, right of access to the construc-
in many cases be aware of the circumstances which tion site to the contractor.
may give rise to a claim regardless of the fact
Naturally, in such cases the employer
whether the contractor gives notice of such circum-
may argue that, even though it was aware of
stances or not. This is because the engineer partici-
pates in construction councils, is in permanent di-
the given circumstances, it did not associate
rect contact with the contractor and conducts regu- them with the possibility of contractor claims
lar correspondence with the contractor (which does being raised or, in the absence of a notice, con-
not always take the form of formal notices of a cluded that the contractor was not going to
claim under Sub-Clause 20.1). The engineer also pursue its claims on this account. Such issues as
often appoints resident engineers (contract engi- whether the employer had sufficient knowl-
neers assistant Sub-Clause 3.2) who should have edge of the circumstances giving rise to a claim
the latest news from the construction site. For these and if the employer should have associated
reasons, the employer will be often aware of the them with the emergence of a contractors
events or circumstances which may give rise to a
claims or could have assumed that such claims
claim because it will obtain such knowledge from
would not arise or the contractor would not
the engineer. In such a case, the employers reliance
on the absence of timely notice of a claim, in a situa-
intend to pursue them require an independent
tion where the engineer was fully aware of the cir- evaluation on a case-by-case basis.
cumstances giving rise to the claim, could be con- One can also speak of an abuse of rights if the
sidered an abuse of rights (especially in a situation contractors claim originates from the non-
where the contractors notice is only slightly de- performance or improper performance of a
layed). contractual obligation by the employer or a
person for whom the employer is liable.23 In
A similar situation may occur when the
such cases, it would be particularly difficult to
knowledge of the circumstances giving rise to a
accept the possibility of the employer relying
claim is in the public domain or is otherwise
known to the employer, or when the employer
23See: A. Sandberg, A Contractors View on FIDIC Conditions of
was notified of such circumstances by the con- Contract for EPC Turnkey Projects, International Construction
Law Review, 1999, p. 47

str. 34 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

on the expiration of the claim as a result of the tions imposed on the contractor and the em-
contractors failure to give notice on time. Such ployer.26
activities could not be reconciled with the prin- For these reasons, the view whereby the
ciples of fairness (social coexistence / good stipulation of the period of 28 days for giving
customs) under which no one can benefit from notice of a contractors claim under Sub-Clause
its own misconduct. 20.1, with the claim otherwise expiring, is in
It is also pointed out in the literature fact the appointment of a contractual prescrip-
that the very introduction of the period, as well tion period does not provide sufficient grounds
as its length or excessively grave effects of a for concluding that the solution adopted in Sub-
failure to comply with it could constitute an Clause 20.1 is effective and consistent with Pol-
abuse of rights. The period of 28 days set out in ish law.
Sub-Clause 20.1, taking into account that it ap-
plies to construction works, often of a complex 3. The Period of Giving Notice of a Claim
nature and on a large scale, is relatively short. and Periods of Limitation of Claims
Furthermore, in Polish practice, it is sometimes In accordance with the Polish Civil Code, pecu-
additionally shortened (e.g., the General Direc- niary claims are barred by the statute of limita-
torate of National Roads and Motorways24 of- tions in the periods specified by law. The pe-
ten shortens it to 14 days in the Particular Con- riod of limitation for claims under construction
ditions). Also, the effects of failure to comply contracts connected with the business activity
with that period are extremely grave the con- of an authorised party is three years.27 Article
tractor forfeits its claim. Certainly, in many 119 of the Polish Civil Code stipulates that pe-
cases there would be strong arguments in fa- riods of limitation cannot be shortened or ex-
vour of concluding that depriving a contractor tended by the parties. The statute of limitations
of its claims because it exceeded the deadline is mandatory, which takes the question of limi-
for giving notice of them is an abuse of rights tation of claims, in principle, totally out of the
(especially when the delay is only minor). All hands of the parties.28
the more so, since it is pointed out in the doc- Some argue that Sub-Clause 20.1 intro-
trine that limiting the claims of only one party duces a 28-day period of limitation of claims
to a contract by a prescription period (which is under contracts for construction works, which
the case, e.g., in the FIDIC Red Book) can consti- is contrary to the mandatory provisions of the
tute an abuse of rights25. The employer, pursu- civil law (Article 118 in connection with Article
ant to Sub-Clause 2.5, should give notice of a 119 of the Polish Civil Code). Therefore, the
claim as soon as practicable. However, no stipulation of the effects of a failure to comply
sanction is provided for the failure to comply with the period of 28 days for giving notice of a
with this imprecise deadline. The European
International Contractors (EIC) have concluded
that it is a manifestation of unequal treatment
of the parties and unfair distribution of obliga-
26 EIC Contractors Guide to the FIDIC Conditions of Contract
for Construction, 2002, p. 20, quote after: E. Baker, B. Mellors, S.
Chalmers, A. Lavers, FIDIC Contracts: Law and Practice, London
2009, p. 311.
27 Cf. the Ruling of the Supreme Court of July 11, 2001, file No. V
24 Generalna Dyrekcja Drg Krajowych i Autostrad. CKN 357/00, LEX No. 52487.
25 A. Stangret-Smoczyska, Umowne terminy zawite [Contractu- 28 B. Kordasiewicz, [in:] System Prawa Prywatnego [The Private

al Prescription Periods], Przegld Sdowy 1/2011, p. 59. Law System], Vol. II, C. H. Beck 2008, p. 579.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 35 |


ANALISES & OPINIONS

claim made in Sub-Clause 20.1 should not be one is not allowed to do more than little (ar-
legally effective.29 gumentum a minori ad maius). It is not allowed
The above view seems only partly cor- to shorten the periods of limitation, while the
rect. One should agree with A. Olszewski that, effect of their expiration is weaker than the
strictly speaking, the period under Sub-Clause expiration of a claim. Therefore, it is all the
20.1 is not a period of limitation. This is due to more difficult to admit a possibility of the par-
the fact that the effects connected with the ex- ties voluntarily introducing pure contractual
piration of the period set out in Sub-Clause 20.1 prescription periods, shorter than the applica-
are different from the effects of limitation of a ble limitation periods, the expiration of which
claim.30 However, this does not change the fact results in the further-reaching effect of expira-
that Sub-Clause 20.1 stands in contradiction to tion of the claim. Therefore, there are strong
Article 118 in connection with Article 119 of arguments for holding that the introduction
the Polish Civil Code. into a contract of a period shorter than the pe-
The effect of the expiration of the period riod of limitation for a given type of claims,
of limitation is not the expiration of a claim, but which limits, directly or indirectly, the pursuing
only its transformation into a natural obliga- of claims before a court or any other authority,
tion. Thus, the claim continues to exist, but a is contrary to the provisions of substantive law
debtor may raise the defence of limitation specifying the period of limitation of a given
which releases the debtor from the duty to per- claim in connection with Article 119 of the Pol-
form. Therefore, the expiration of the period of ish Civil Code.
limitation does not deprive the creditor of its In accordance with Article 58 1 of the
claim, but only creates the debtors entitlement Polish Civil Code, a legal act contrary to the law
to raise the defence of limitation and thus re- is invalid, unless the applicable statutory provi-
lease itself from the obligation to perform. The sion provides for a different effect, especially
expiration of the period set out in Sub-Clause that the invalid provisions of a legal act are re-
20.1, in accordance with its literal wording, is placed by the relevant statutory provisions.
to result in the expiration of a claim. Thus, the However, when only part of a legal act is inva-
expiration of the period for giving notice of a lid, in principle, the remaining part remains in
claim set out in Sub-Clause 20.1 has a farther- force. An entire act will only be invalid when
reaching effect than the expiration of the period the circumstances indicate that the act would
of limitation. not have been performed at all without the in-
In line with the rules of legal inference, if valid provisions (Article 58, 3 of the Polish
one is not allowed to do little, all the more so Civil Code).
The provisions of Sub-Clause 20.1 con-
29See: T. Ciaowicz, Zgodno warunkw kontraktowych FIDIC z cerning the period for giving notice of claims
przepisami polskiego prawa [The Consistency of the FIDIC Con- and the effects of exceeding this period are not
ditions of Contract with the Provisions of the Polish Law]
of a type making it possible to claim that in
(http://www.taxfin.pl/artykul,724,Zgodnosc_warunkow_kontr
aktowych_FIDIC_z_przepisami_polskiego_praw their absence the parties would not have con-
cluded the contract at all. This is especially be-
a.html).
30 A. Olszewski, Kontraktowe procedury rozwizywania sporw cause the FIDIC Conditions constitute a con-
w umowach o roboty budowlane opartych na wzorach tract form, and the parties, in principle, do not
umownych FIDIC w wietle prawa polskiego [Contract Proce-
dures of Settlement of Disputes in Contracts for Construction incorporate them into the content of their legal
Works Based on The FIDIC Contract Forms In Light of Polish
Law], Monitor Prawniczy 21/2010, Radca Prawny 2/2010.

str. 36 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

relationship due to the wording of individual tions and the effects of their non-performance.
clauses of the FIDIC Conditions. These effects will depend of the circumstances
It would also be too far-reaching to de- of a given case.
clare the whole Sub-Clause 20.1 invalid because
the entire Sub-Clause is not contrary to the law. Piotr Bytnerowicz*
Only the provision of Sub-Clause 20.1 which Magda Kofluk
provides that the contractors claim expires if it
is not notified within 28 days may be deemed
invalid.

4. Final Comments
In view of all the above comments, it seems that
the arguments in favour of acknowledging the
invalidity of the stipulation of the sanction of
expiration of a claim in the case of a failure to
comply with the time limit for giving notice of
the claim, as set out in Sub-Clause 20.1, are
stronger than those in favour of the admissibil-
ity of stipulating such a sanction under the rule
of freedom of contract. This matter, however,
has not been explicitly settled by case law and
there is little Polish legal writing on this issue.
In view of the absence of established domestic
case law and divergent views expressed by
commentators, we suggest that the provisions
of Sub-Clause 20.1 should not be ignored. To
the contrary, it is by all means advisable to
comply with the period for giving notice of a
claim whenever possible. It should be remem-
bered that only the effect of failure to meet the
deadline for giving notice of a claim (i.e., expira-
tion of the claim) may be deemed invalid, but
not the very fact of stipulation of such deadline.
Therefore, irrespective of the possible invalid-
ity of the sanction stipulated in Sub-Clause
20.1, when a contractor gives notice of a claim
after the expiration of the period of 28 days * Piotr Bytnerowicz is an attorney at law (adwokat) at the
Department of Litigation and Arbitration of the Warsaw
without reasonable cause, it is in breach of Sub-
office of White & Case. He is a member of the Chartered
Clause 20.1. The effects of such a breach of the Institute of Arbitrators (ACIArb).
procedure specified in the contract for giving Magda Kofluk is a trainee legal advisor (aplikantka
notice of claims should be evaluated on the radcowska) at the Department of Litigation and Arbitra-
grounds of the provisions of the Polish Civil tion of the Warsaw office of White & Case. She is a mem-
ber of the Chartered Institute of Arbitrators (ACIArb).
Code concerning the performance of obliga-

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 37 |


ANALYSES & OPINIONS

Awarding In-House Counsel costs in arbitration

Adam Olszewski, Ewelina Czerniawko

It is usual in commercial proceedings, when parties are legally represented, for costs to be awarded
against an unsuccessful party. Both practice and principle are clear about when an external lawyer is
retained. But what about the costs borne by a company for the involvement of an in-house counsel in
proceedings; is he entitled to claim legal costs? If the answer is affirmative, how should these costs be
substantiated, considering that salaried employees usually take advantage of comprehensive legal as-
sistance or there is a permanent legal service provided with a lump sum without involvement in a spe-
cific matter?

This article addresses several key fac- tion proceedings are conducted by external
tors that attorneys and their clients should lawyers or the costs of in-house legal staff are
consider when seeking to recover legal costs not claimed in arbitration proceedings.
for an in-house counsels arbitration work. This Most of the literature and the judicature
issue is especially important in construction that we analyzed concern the International
arbitration disputes where in-house lawyers, Court of Arbitration of the International Cham-
including state lawyers, are often involved. ber of Commerce in Paris (hereinafter ICC
As far as proceedings before Polish Court). Prokuratoria Generalna Skarbu
courts are concerned, a full-time legal advisor Pastwa (hereinafter Prokuratoria
may count on legal representation costs being Generalna)2 is conducting several cases before
a multiple of the minimum remuneration pro- the ICC Court, therefore we are interested in
vided for in the Order of the Ministry of Jus- the practice of this Court also as to the costs of
tice1. These rules, however, will not be applica- the proceedings. Prokuratoria Generalna also
ble to arbitration proceedings because the reg- has experience as regards Polish arbitration
ulation concerns merely proceedings before courts, such as The Court of Arbitration at The
the state court. Institutional arbitration courts Polish Chamber of Commerce in Warsaw
do not have such detailed schedules of legal (hereinafter also as KIG) or The Court of Ar-
representation costs of their own. bitration at The Polish Confederation of Private
An examination of the practice of Employers Lewiatan (hereinafter also as
awarding costs, including the costs of in-house Lewiatan) as well asthe ad hoc arbitration
legal staff, is quite difficult since there are few courts.
published awards (or their excerpts covering
this aspect). The reason might be that arbitra-

1 Order of the Ministry of Justice dated of 28 September 2002 2 The Polish State Treasury Solicitors Office which is an institu-
(O.J. 2002 No. 163, item 1349 with amendments.) on legal advi- tional attorney ad litem of the State Treasury, representing it in
sors fees or Order of the Ministry of Justice dated of 28 Sep- court and arbitration proceedings, founded by the Act dated 8
tember 2002 (O.J. No. 163, item 1348 with amendments) on July 2005 on Prokuratoria Generalna Skarbu Pastwa (O.J. No.
attorneys fees. 169, item 1417 with amendments).

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 38 |


ANALISES & OPINIONS

The approach to the costs of in-house claims. Assuming, however, that Claimant
legal staff borne as arbitration costs of the par- had proven that it was entitled to damages
ties has evolved during the last decades. as a result of the breaches complained in
Still, in the 1990s, it was not generally this arbitration. I do not consider that the
accepted that the costs of in-house legal staff twenty-three man-days claimed for its four
could be awarded as part of the parties arbi- employees involved in preparation of the
tration costs. case should be compensated. The per diem
In ICC Case No. 50293 the Arbitral Tri- sum claimed for each employee whether for
bunal arrived at the conclusion that legal costs salary alone or salary plus overhead, does
did not include any allowance for the time not represent a special cost incurred by it
spent on the arbitration by the party itself or for purposes of the arbitration but is part of
its directors, employees, representatives, and its normal operating expenses. It is for the
agents. same reason that such amounts cannot, in
Arbitration inevitably takes up time of the my opinion, form part of its legal costs.
parties themselves and their staff, but, in the As to in-house lawyers it is said that a
Arbitral Tribunals opinion, the cost of such company will employ in-house lawyers wheth-
time is not a part of the legal costs of the er they conduct proceedings or not. This argu-
proceedings. Normal legal costs do not in- ment is wrong since in-house lawyers are em-
clude any allowance for the time spent by ployed to conduct proceedings, arbitration or
the Defendants executives and other staff litigation. Should a company have no in-house
on this arbitration. The same ruling applies lawyers, it would engage an external lawyer.
to the time spent by the Defendants agents, There was a turning point in ICC Case
including ABC, the Defendants engineer for No. 6564 of 1993.5 The Arbitral Tribunal de-
this project. cided that the costs were admissible in princi-
Similarly, in-house counsels costs were ple and also gave some directions as to the
fully rejected by the Arbitral Tribunal in ICC principle and discussed certain directions, but
Case No. 62934, although as it flows from the refused to grant them on the following
published excerpts it was duly substantiated, grounds:
on the following grounds,: In the Arbitral Tribunal view in-house legal
Claimant has claimed compensation for costs form part of partys normal legal cost
time of its personnel involved in preparation incurred in the conduct of case. It is for each
of its case. This claim does not in my view party to decide whether it wishes to retain
form part of the costs of arbitration in the outside counsel or prepare and argue the
sense of being part of Claimants normal case by its own staff. There is no justification
legal costs, contemplated in Article 20(2) of to privilege a party in terms of costs for the
the ICC Rules. It is really a separate head of sole reason that it retained outside counsel.
damages claimed by the Claimant and must So, the Tribunal expressly said that the costs of
be rejected together with its other damage in-house lawyers may be awarded.
A claim for a partys internal costs is admis-
3 ICC Case No. 5029 (1991), ICC International Court od Arbitra-
tion. Bulletin , Vol. 4 (1993), p. 32. sible in principle also in those cases where
4 ICC Case 6293 (1990), ICC International Court od Arbitration.

Bulletin, Vol. 4 (1993), p. 43., See also: HANOTIAU Bernard, The


parties costs of arbitration, Dossier of the ICC Institute of World 5ICC Case 6564 (1993), ICC International Court od Arbitration.
Business Law: Evaluation of Damages in International Arbitra- Bulletin , Vol. 4 (1993), p. 46., See also: HANOTIAU Bernard,
tion, 2006, p. 3 op.cit., p. 3.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 39 |


ANALISES & OPINIONS

outside counsel has been retained. A party costs for in-house counsels, apparently as a
must be free in allocating the work between matter of course. As commentators say, legal
its outside counsel and its own services. A representation costs were awarded without
party which decides to perform most of the any particular justification. It does not stem
preparatory work for the case by its own le- from the published excerpt of the award what
gal and technical departments should not be the grounds for such ruling were.
placed at disadvantage compared to ona Thus, there is still no clear pattern as to how
which confers all work to outside counsel and the costs of in-house legal staff should be justi-
experts fied in order to be awarded by the Arbitral Tri-
So, the Arbitral Tribunal agreed that the bunal.
costs of in-house lawyers may be taken into The costs of in-house lawyers can be
consideration also when legal services were claimed for work carried out by them on the
provided in cooperation with in-house law- same basis as costs claimed for work carried
yers. out by external lawyers - according to proper
However, at the end of the day, the Arbi- time records. In the foreign legal realm, the so
tral Tribunal spoiled the whole barrel with one called lodestar method refers to the method
bad apple: of computing attorney's costs whereby the
There is, however, an important difference number of hours reasonably spent by a trial
between the costs for outside counsel and counsel is multiplied by a reasonable market
those incurred in-house: the former are ex- hourly rate. But, as far as this method is con-
penditures and can be clearly identified and cerned, the problem is what the appropriate
evidenced; in the case of the latter this is not market rate for work of an in-house lawyer
always the case. In view of this difference it should be. One may refer to the rates of exter-
appears justified to require some more sub- nal lawyers; however, diversification of exter-
stantiation inter alia with respect to the na- nal lawyers rates in Poland is huge. What is
ture of cost, the personnel involved and the more, in Poland, except for large law firms, the
type of work performed. In the present case, standard is that the remuneration of external
neitherthe party satisfied there requirements. lawyers is in line with the amount in dispute.
Their claims are too general to permit an as- Prokuratoria Generalnas experience
sessment of the justification and reasonable- shows that legal representation costs in cases
ness of the costs claimed. Therefore, no al- conducted by Prokuratoria Generalna may be
lowance will be made for internal costs of the awarded. Prokuratoria Generalna is formally a
Parties. kind of an in-house lawyer since it is an agency
Unfortunately, since the costs were not of the Polish State Treasury to the state entities
evidenced properly or the Arbitral Tribunals it represents.
requirements were not met, the costs were not In proceedings before Polish permanent
awarded. arbitration courts, such as KIG or Lewiatan or
There is only one award (ICC Case No. 8786 of ad hoc arbitration, when the Arbitral Tribunal
19976) in which the Arbitral Tribunal allowed consists of Polish arbitrators only,
Prokuratoria Generalna refers by analogy to
6 ICC Case 8786 (1997), 20 ASA Bulletin 1 (2002), p. 68. See
also: DERAINS Yves, SCHWARTZ Eric. A., A Guide to the New
the regulations of the Order of the Minister of
ICC Rules of Arbitration Kluwer Law International 2005, p. Justice mentioned above. Surely, the provisions
366.
of the Order of the Minister of Justice do not

str. 40 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

apply directly as the regulation concerns mere- the work of one solicitor. This cost, except for
ly proceedings before state courts; however, the salary, contains the respective proportion
local tariffs on attorneys costs are applied as a of other costs intertwined with the functioning
yardstick for the reasonableness of the claimed of the office, such as the costs of assistance,
costs. Such tariff costs are deemed as low or secretaries and paralegal service, copying,
reasonable. So far there has been no case postal services, phone and fax costs. Next, we
where such justification for awarding costs apply a percentage representing the propor-
with reference to the Order of the Minister of tion of time spent for representation in arbitra-
Justice would not be taken into account. Usual- tion case to the annual cost per solicitor in or-
ly, in justification of the award one may find an der to determine the cost of representation in
explanation that the Arbitral Tribunal consid- said arbitration case per solicitor in a particu-
ers such an amount as justified; sometimes the lar year.
Arbitral Tribunal refers to an analogous appli- Naturally, this cost is an approximate
cation of the Order of Minister of Justice. estimation; however, this method is transpar-
Such practice is an important signal for ent and based on data that can be verified. The
in-house lawyers, who consider including an budget of Prokuratoria Generalna as well as
arbitration clause in a contract. As far as Polish the number of solicitors employed at
permanent arbitration courts are concerned, Prokuratoria Generalna is public information.
there should not be a problem to get the costs Engagement of one solicitor is also an estima-
awarded if a party, represented by an in-house tion but it can be easily verified by arbitrators
lawyer, is not able to evidence precisely its whether the percentage is correct. If a solicitor
costs of in-house lawyers. Anyway, it should points out that (s)he contributed 10 per cent of
reconsider whether to include in the rules of the time to a particular case, one has to answer
permanent arbitration courts that, upon a par- the question whether ten similar cases in a giv-
tys request, the Tribunal may consider award- en year constitutes lawyers normal workload.
ing legal representation costs in accordance This method was accepted by the Arbitral Tri-
with the said order of the Minister of Justice. bunal in ICC case No. 15282 conducted by
In proceedings before arbitration Prokuratoria Generalna. In the justification, the
courts, when the Arbitral Tribunal is interna- Arbitral Tribunal said:
tional, and probably is not familiar with The fees and expenses of lawyers are calcu-
thepractice of awarding legal representation lated with regard to the budget of
costs by the state courts in Poland, the other Prokuratoria Generalna in the respective
practice of awarding legal costs is used. That is years and reduced to reflect the percentage of
the case as far as costs born by Prokuratoria time worked on this case. According to docu-
Generalna is concerned. Below we show the mentation provided by the Respondent on 15
methodology used. March 2010, the Arbitral Tribunal has no
Legal representation costs are calculat- reason to conclude that this amount is exces-
ed with regard to the budget of Prokuratoria sive or unreasonable.
Generalna. The methodology is as follows. We This method may be applicable also in
divide the annual costs of the Solicitors Office companies that take advantage of comprehen-
by the number of solicitors employed by the sive legal assistance provided on the basis of
State Treasury Solicitors Office in a given year an employment contract if, in the structure of
and we receive an approximate annual cost of the organization, there is a singled out financial

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 41 |


ANALISES & OPINIONS

unit that deals with legal services. This is a


well-known method of so-called cost centers,
where each cost centre in this case the inter-
nal legal department has its own budget (ex-
penses limit) and such budget, may be the ba-
sis for evidencing the costs incurred.
It is important in this method to take in-
to account the budget of the unit, whose sole
task is to provide legal services, while the cost
structure of the unit that deals with production
or other aspects of functioning of the company
may differ significantly per employee.

Adam Olszewski*
Ewelina Czerniawko

*Adam Olszewski: Director of the Arbitration Depart-


ment in the State Treasury Solicitors Office
Ewelina Czerniawko: LL.M. solicitor of the State Treasury
Solicitors Office

str. 42 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALYSES & OPINIONS

Partnering and Dispute Management an instrument for


Polish construction and Project industry?

Peter Tr Nielsen

The author was a pioneer in his native country, Denmark, in developing partnering and dispute man-
agement programs. Based on a concrete case story developed by himself the expansion of Billund
Airport in Western Denmark he analyzes if these tools and systems could be beneficial in Poland.

Back in the late 90s the management of numerous big and expensive court and arbitra-
Billund Airport faced a big challenge. The air- tion cases and even a grim competition/public
port the second largest in Denmark after Co- procurement case.
penhagen, organized as a publicly owned joint How to satisfy the ambitions as to size
stock company and situated next to world- and quality of the planned facilities within the
famous Legoland was to move completely and limits of the budget? How to at the same time
expand the terminal, platforms and taxiways. treat the contractors in a commercial but still
The only airport component that was given ethically decent way? How to avoid the costs,
only a facelift was the runway itself. All the rest frustrations and burdens of disputes during or
was to be abandoned and replaced with com- after the project? How to avoid cartels (mean-
pletely new facilities on the opposite side of the ing higher costs), which were obviously present
runway. in certain trades at that time?
This was a project for DKK 1 billion
(PLN 600 million) which was to take place on The project
an airport in operation, a factor limiting the Basically the most complicated and main part
flexibility. On the other hand the circumstances of the project the terminal - was organized
increased the flexibility as the old terminal was with approx. 21 trades of independent contrac-
still there as a reserve so that the airport suf- tors. In addition there were another approx. 20
fered only limited exposure to the risk and con- so-called black boxes, meaning supply and de-
sequence of delays. livery of technical equipment to be fitted into
The management could find alarming in- the building, such as escalators, air condition-
formation and experience in the then just com- ing, baggage handling system, communication
pleted expansion of Copenhagen Airport, ter- system etc. So with some 45 independent con-
minal 3, which ended with substantial excesses tractors with the terminal under the leadership
of the budget and prices per sq. meter and oth- of the airport and its engineers and architects,
er unit prices far above what the Billund man- there was some potential for conflicts.
agement could afford within their budget. Also Danish weather is tough. So the first
they could look at the recently completed move of the management was to merge the first
Storeblt Western Bridge, which also had sub- 5 trades/contracts into one. This meant that all
stantial excesses of the budget and ended with of the underground work, structural work,

str. 43 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

walls, roof etc. was performed by one contrac- Also misunderstandings and rocks on
tor securing the others better working condi- the road were clarified and removed during
tions and thereby less risk as could result from such discussions, so the end result for the win-
the a.m. bad weather. ner was that the scope of services and works
This left 16 contracts (plus all the black was very precisely defined together with the
boxes) to be administered by the airport pro- airport and that the price was sharp and com-
ject management. petitive.
Such a contract-organization gave the Negotiating this way requires that the
airport as owner a very high degree of control bidders act in a different way than usual. If they
over matters like quality, materials, design etc. are not open and constructive (but they should
It basically also meant lower prices as the pric- not be nave, of course) they are simply unable
ing is more transparent when taken trade by to be competitive and are usually the losers of
trade and there are less intermediaries. the race.
Those days in Denmark all competitive This procedure could expose the owner
bidding in the building sector was regulated by to cartel style agreements or concerted practic-
national law according to which it was not al- es to a higher extent than in normal bidding
lowed to negotiate with the bidders at all, ex- procedures, as, although forbidden by law, car-
cept for to accept or refuse the bids. The airport tels and similar arrangements were present in
as a public utility had a duty also to obey the certain trades.
then Utilities directive of the EU, according to In the tendering materials the airport
which the negotiated procedure was allowed therefore included a comprehensive statement
in addition to public or restricted tendering. to be signed by the contractor, assuring that the
The rules of the directive are normally contractor was not neither participant in nor
created to prevent nepotism or favoring of cer- knowledgeable of any cartels or similar re-
tain bidders in the process and as the negotiat- striction of competition that would affect the
ed procedure is seen as possessing the highest bidding procedure in question. Also, the con-
risk for such phenomena the use of this proce- tractor acknowledged that if now or later it was
dure is restricted. revealed that some cartel or the like was pre-
The airport used the negotiated proce- sent then this would be regarded as a gross
dure (thereby violating Danish law, but refer- breach of contract with those usual conse-
ring to the superiority of the EU law) in order quences that has according to law, rescission of
to increase competition and efficiency, by nego- contract and damages included.
tiating and clarifying with all bidders in a man- By demanding the signatures of the bid-
ner transparent for everybody, then gradually ders ultimate (or parent company) senior
in stages - excluding the least competitive bid- management on this statement cartels or other
ders until the winner was found. restrictions of competition were to the best
In the beginning the bidders were of knowledge of the airport excluded.
course suspicious, but they found out that they The bottom line was a saving of 20 % on
could optimize with all what they learned the terminal building as compared to the (al-
through the negotiations themselves and ready tight) budget and a bit less saved on the
through the information about their competi- other works around the terminal. In one quite
tors and their work that they gained via trans- big trade (where the unit prices were quite
parency.

str. 44 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

easy to calculate) the final bid was almost 50 % The contractors also on top got a further bo-
below the budget. nus of approx. 3 % of their respective contract
Some of this money was used for sav- prices. (see below).
ings, some for improvements of the elements of
the project that were removed in the planning The partnering and dispute management
phase for financial reasons. The rest was used program
for a bonus to the contractors (see further be- Inspiration to the program was first of all found
low) in the publications of the US Army Materiel
For the entire project as such the rela- Command. The army buys for billions literally
tive price level (e.g. per m2 of the terminal etc.) every type of goods and services and has also
was a bit less than 50 % of the equivalent pro- long standing and development aimed contrac-
ject in Copenhagen Airport, terminal 3. tual relationships with its contractors.
So it seemed that there was more than The disputes are therefore not only a
enough money to satisfy the visions and ambi- question of time and money but also a threat to
tions of the owners and management of the the continued cooperation and relationship,
airport. both on personal and institutional level. For
As it appears the pricings of the contrac- this reason in the 90s the army started devel-
tors were quite sharp. oping the partnering concept. Its main publica-
This of course makes it necessary that tion Partnering for Success now in the se-
the construction process runs smoothly and cond edition can be found on
efficiently and that all disputes, from the small- http://www.amc.army.mil/pa/PartneringForS
est on the site to the biggest at the top-level uccess.pdf or
negotiation table, are avoided or strongly lim- http://www.daytonaero.com/Files/resource/7
ited. Otherwise the contractors would be forced 8.pdf
to present claims against the airport or each Back in Denmark the team of top man-
other (=trouble and cost) in order not to lose agers who ran the Storeblt Bridge project did
money. not want to see a repetition of all the disputes
Therefore the airport decided to initiate arising from this project. The almost same team
the first Danish partnering and dispute man- took over a new project, the Danish Swedish
agement program valid throughout the con- resund Bridge project and they developed the
struction time. very first Scandinavian partnering program and
carried through successfully the entire project
At the inauguration of the new airport several avoiding the disputes. They opened for the air-
years later the spokespersons for the contractors port the access to look into their know how and
(i.e. the top directors) expressed their satisfac- experiences.
tion with the project, the economical aspects and The result of the inspiration collected
the partnering and dispute management pro- was the first Danish partnering project, Billund
gram included. It was recognized, that although Airport.
prices were low the contractors got a normal Already during the tender and negotia-
profit out of it, thanks to the way the process had tions the contractors were getting used to a
run. different atmosphere as described above.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 45 |


ANALISES & OPINIONS

Partnering Agreement
A partnering agreement was entered into with After that the participants were put in
each and every of the successful bidders. groups in order to discuss how they could
The main contents was: commit and contribute to a smooth and dis-
pute-free performance of the whole project.
a general commitment to partner and to The groups were rotated so that people met
solve all problems in the partnering and discussed with as many as possible.
spirit After the groups went back to the plena-
an obligation to participate with per- ry meeting, all elements developed by each and
sonnel from the site and from the man- every group were highlighted and discussed
agement in one or more partnering sem- and boiled down to some bullet points that eve-
inars where: ryone could agree to in the partnering spirit.
o the basic partnering concept and These points were then signed by all the per-
spirit was defined sons present in the form of the Partnering
o a Rocks on the road procedure Charter.
was discussed and agreed This showed later to have an enormous
o a Conflict Escalation Procedure effect, as when someone forgot the partnering
was discussed and agreed spirit it was easy to remind the relevant per-
o alternative dispute resolution sons of their personal obligations to partner.
procedure (ADR) was discussed It is important to point out that the obli-
and agreed (without prejudice to gation to partner did not mean that the con-
the standard Danish building ar- tractor just had to say yes to whatever the
bitration clause in the construc- airport asked. It just meant that the parties had
tion contracts) to work for solutions and find them at the low-
o a Success Bonus was agreed est level possible and as fast as possible.
Provisions binding the parties to certain The rule was that any big problem you
rules in connection with the above men- face was a small problem once upon a time
tioned, including that disputes must meaning that the earlier it was solved the more
NOT delay or disturb the project and smoothly and cheaper it could be solved.
progress.
Rocks on the Road
The airport itself together with its advisers Also the continuous activities within the Rocks
took the role of facilitators and coordinators of on the Road program were promoted to en-
the partnering project. courage relevant parties and persons to work
together in order to have any problems (legal,
Partnering seminar technical, financial) or challenges in the project
The successful contractors were called to a highlighted and discussed/solved as early as
partnering seminar where the above men- possible.
tioned elements were highlighted by the air- The idea was that if people directly in-
port together with advisers and external, neu- volved could not solve the problem then the
tral experts. It was carefully checked that the Conflict Escalation Procedure entered into
contractors (and the airport itself of course) force and the directly involved people were
were represented by appropriate people.

str. 46 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

thus excluded from dealing any more with the Dispute Resolution Board (DRB)
specific problem. The airport in its capacity as the owner and
The rule was that in a discussion or ne- facilitator constituted in due course a Dispute
gotiation of a topic one party declares that here Resolution Board comprising of two neutral
is a dispute not solved, there is a problem. The senior persons with commercial and technical
discussion was then moved away from the per- expertise (a consultant engineer and a CEO of a
sons involved and they did not participate any construction company - not involved in the pro-
more in the discussion/solving of the dispute. ject) as members and an external lawyer with
The persons directly involved were thus given expertise in ADR as the chairman.
the time to look after the project and the pro- The DRB met at regular intervals not-
gress and they instead of thinking further about withstanding whether there were disputes up-
the dispute. coming or not - in order to be updated at all
times with the project and so that the parties in
The Conflict Escalation Procedure (the Conflict doubt also could consult informally with the
Staircase) board.
If one of the discussion/negotiation partners In no event the construction process
gave up and declared that here is a dispute then could have been delayed by a dispute.
the dispute passes to the next level e.g. the site If a dispute could not be solved with all
management of both parties or the project the previous steps the DRB held a very fast
management back in the headquarters of the procedure with the parties (with lawyers or
parties or first the one then the other if two other experts as they might desire) to find and
steps are wanted. recommend a solution of the dispute which
Again, if one party declares that agree- could at the end of the day be accepted by both
ment cannot be reached the conflict moves to parties.
the next level and the persons in the previous If this within the tight deadlines -
level are excluded. could not be reached, the parties were obliged
The ultimate step on the staircase could to follow the directions given in the construc-
be the CEOs of the parties. tion project and by the DRB as such, and then
All the representatives of the parties on the parties would have to subsequently have
the different levels are mentioned by name in the financial outstanding solved by traditional
the agreement and it is up to the parties to look arbitration in accordance with the construction
after formalities, if the identity of such person contract.
changes e.g. due to job rotation. In the airport project the DRB had a few
The idea is that the persons involved are informal consultations and one formal proce-
motivated to find a solution as they are risking dure which ended with an amicable settlement.
losing control and/or prestige when/if the dis- It should be strongly emphasized that
pute goes to the next level. They are of course any partys right to refer to arbitration is not
also obliged to act and negotiate in the partner- waived. However before arbitration the parties
ing spirit. involved are obliged to complete the previous
Before reaching the end of the Conflict steps described above in an attempt to reach an
Escalation Procedure more than 99 % of dis- amicable settlement.
putes were solved amicably.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 47 |


ANALISES & OPINIONS

Partnering Success Bonus The bottom line was that all 16 contractors got
It is obvious that from the owners point of their bonus and praised the airport and the
view the partnering-project generates substan- project. The airport got what it wanted within
tial advantages by dramatically increasing the the time and (lowered) budget. And no parties
chances of having the project delivered on time had to suffer afterwards from the headaches of
and free of defects. Also, as pointed out above, court or arbitration disputes.
the owner gets some direct savings and, if suc-
cessful, avoids the costs and frustration of hav- Partnering something for Poland?
ing arbitration cases. Seen from the point of view of a foreign con-
The advantages from the point of view the struction lawyer in Poland, programs, and not
contractors are less clear and obvious. the least partnering/dispute management pro-
Therefore the airport decided, and included grams like the Billund Airport program, in
in the agreements, that a bonus of approx. 3 % principle would be very beneficial as far too
of the contract sums (including approved extra many projects are delayed or disrupted by dis-
works etc.) would be payable at the end of the putes and similar trouble.
project on the following conditions:
Authorities
o the project would be delivered (by all of In Poland, however, it is also common that pro-
the contractors respectively) in time and jects are delayed or disrupted by decisions (or
free of substantial defects as to quality lack of decisions) from the relevant authorities
and craftsmanship, This happens to an extent which for a Scandi-
o within a short time after the final deliv- navian professional is extreme.
ery all relevant parties should declare I guess there is a reason why Polish au-
formally that they had no further claims thorities put a sign on the site of infrastructure
towards the owner or each other than projects saying closed as from . and avoid-
those already settled (defects punch list ing the more relevant closed until ...
and warranty obviously excluded). Ac- The contracting authorities and other
cording to the Danish construction law it (private included) employers must be willing to
is already so, that there is a tight dead- take the risk to committing to something. How
line for the final presentation of claims, else could they seriously demand some proper
so it was easy to adapt this to the rou- fulfillment from their contracting partners?
tines. Balancing between fulfilling some for-
o no outstanding claims or arbitration mal conditions (in 100 %) and preventing the
cases existed as of the closing dates be- usage of e.g. an important infrastructure, has to
tween the owner and the contractors or be changed dramatically in Poland.
between the relevant contractors inter- Disregarding all other legal or political
nally. This did not include subcontrac- arguments Poland simply cannot afford such
tors. use/waste of resources for which nothing
o the above should be fulfilled by all con- beneficial to the society or the employer is ob-
tractors. If one failed then the bonus for tained in return.
everyone would be annulled. A joint As long as the authorities and the au-
and several right and risk. thorities handling of matters remain this way,
whether justified or not, it can block the whole

str. 48 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

project due to the lack of fulfillment of a small makes up his mind and changes to a REAL
detail in some approval or specification, it partnering spirit and imposes it on his employ-
makes no or less sense for the contracting par- ees and consultants also by a.o. education etc.
ties to initiate a partnering program from a tra- If the employer cannot manage this, the
ditional point of view. partnering project is doomed to fail as contrac-
So in my opinion the government and tors and other parties will see it as just a uni-
the authorities would have to improve the leg- lateral optimization measure, only in the inter-
islation, the procedures and the interpreta- est of the employer and his budget.
tion/administration of the law dramatically in In Poland many public and even private
order to avoid or limit the many senseless situ- employers show a fight to the very end atti-
ations and paralysis and senseless waste of re- tude which is hard to combine with partnering.
sources occurring in projects of all kinds. If the attitude of the employer, as it is often in
There must be a willingness and ability Poland, is so aggressive that (s)he would (have
by the public hand to balance the interests so to) go so far as to contest even an arbitration
that e.g. a few deficient windows in a building award after having lost, (s)he should forget
do not prevent the use of the building for long about partnering.
periods. Even before starting the employer has to
But this takes time. What to do in the hold up the mirror in front of himself asking
meantime in order to avoid further waste of whether (s)he is able to carry through in a de-
resources? cent partnering spirit being fair, balanced and
decent even in situations where (s)he would
The contracting parties attitudes have to take the burden of some problems.
The experience from Denmark shows that the But on the other hand if you study the
partnering projects, which are the most suc- extent of savings and avoidance of delays and
cessful are those initiated and controlled by the trouble triggered by partnering projects like
owner/employer part (such as the resund resund and Billund (and those of the Ameri-
Bridge and Billund Airport). Programs initiated can Army) any authority or government re-
by contractors or consultant engineers etc. sponsible for projects or private companies
normally are not able to survive the process of ought to be VERY interested and motivated.
construction, mainly due to the reason that
they are regarded as unbalanced and beneficial Partnering/dispute managing programs for
to one party only. handling of authority interference?
Furthermore, if a partnering project is to As mentioned above some trouble, paralyzing
be beneficial as compared to the resources of the project included, are triggered by some
spent on it, experience shows that the project authority withholding or denying a permit or
has to have a certain size and complexity. approval, or imposing something on the con-
Under the right circumstances it is how- tracting parties, sometimes justified, some-
ever possible to benefit from a reduced part- times not.
nering project even in smaller projects simply Very small things will then trigger
by using relevant components of what is de- enormous negative consequences and this is
scribed above. most likely to be far too expensive when bal-
It is however a very important pre- anced with the benefit. In such situations it is
condition that the employer himself upfront commonly seen that all parties lean back and

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 49 |


ANALISES & OPINIONS

defend their own interests instead of the inter-


ests of the common goal and the project.
The result is substantial expendi-
ture/waste of resources/delays for which no
benefits are generated. Meaning too expensive
for the employer or the general society.
Could the contracting parties develop a
methodology to handle such situations in
common and in the common interest of the
project? Or in other words to stand shoulder to
shoulder in handling the authority causing the
problem thereby creating a better opportunity
for fast and cheap solutions?
I could propose a procedure like the
Conflict Escalation Procedure (Conflict Stair-
case) for handling the problem between the
parties and showing the necessary strength vis-
-vis the relevant authority. In bigger projects
the Dispute Resolution Board too could play a
role, maybe even vis--vis the authority in
question.
A partnering success bonus (joint and
several as described above) to the contractor
parties involved, which is lost in case of delays,
deficiencies and disputes, could be the motivat-
ing factor for the contractors forcing them to
regard the problem as a common one and forc-
ing them to work (together) for a solution ben-
eficial for the project instead of just optimizing,
each of them for themselves.
The benefit for the employer is obvious:
savings in time and money. So that motivation
should be enough for the employer.

Peter Tr Nielsen*

*Peter Tr Nielsen: MCIArb, Founder and Senior Part-


ner, Peter Nielsen Partners Law Office, Warszawa

str. 50 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALYSES & OPINIONS

Alternative methods of resolution of construction dis-


putes in Ukraine
Volodymyr Yaremko

Spory budowlane na Ukrainie s zazwyczaj rozwizywane na drodze sdowej. Jednoczenie, arbitra


staje si powszechn metod efektywnego rozwizywania midzynarodowych sporw handlowych.
Coraz wiksza ilo duych projektw budowlanych, realizowana na Ukrainie z udziaem zagranicz-
nych wykonawcw. Wzorce umowne oraz sposoby rozwizywania sporw, do ktrych s przyzwycza-
jone ukraiskie spki, nie mog w takiej sytuacji dominowa. Coraz waniejsze staje si pytanie, czy
uznawane midzynarodowe standardy i najlepsze praktyki przemysu budowlanego sprawdz si na
Ukrainie, biorc pod uwag nadchodzce Mistrzostwa Europy w Pice Nonej EURO 2012, ktre przy-
cigny na Ukrain znaczn ilo projektw infrastrukturalnych. Jednym z kluczowych postanowie
w umowach budowlanych jest efektywna klauzula dotyczca rozwizywania sporw.

In this article, the readiness of Ukraine for the published by the International Federation of
settlement of construction disputes by interna- Consulting Engineers (FIDIC).
tionally recognized mechanisms, namely those FIDIC contracts are not popular in
introduced in FIDIC forms of contract, is dis- Ukraine and are typically used only in large-
cussed. scale projects involving foreign funding. Local,
and quite often foreign, contractors still prefer
I. International construction pro- to use the established schemes and are not will-
jects in Ukraine and international ing to resort to sophisticated legal instruments,
forms of contract (FIDIC) such as FIDIC forms of contracts. The specific
features of Ukrainian regulations sometimes
The Ukrainian construction market was badly require significant amendments to FIDIC
hit by the global financial crisis. Starting from standard forms for adaptation and use in
2008 there was a decline in that sector. The Ukraine.
construction market finally recovered in 2011. At the same time, Ukrainian law does
The sectors recent upturn is mostly driven by not prohibit the use of foreign forms of contract
infrastructure development thanks largely to and there are even certain signs that such use is
the preparations for the Euro 2012 Football becoming increasingly popular. For instance, in
Championship which have entered the decisive order to ensure the good quality of road repair
phase. Major infrastructure projects are often and construction works, the State Motorways
financed by international institutions, such as Agency is considering setting up and develop-
the World Bank and the European Bank for Re- ing a system for controlling and ensuring the
construction and Development (EBRD), which good quality of motorways, including by applica-
apply internationally recognized standard
forms of construction contracts. The most pop-
ular standard forms are those developed and

str. 51 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

tion of the FIDIC conditions of contract1. The ly all large-scale construction projects in
Ukrainian Cabinet of Ministers notes that the Ukraine now include the so-called foreign el-
institutional changes and the development of ement in the form of a foreign contractor, in-
legal principles for the road industry shall be vestor etc. This undoubtedly leads to increased
aimed at the construction of, repairs and rede- use of internationally recognized standard
velopment of roads by tender procedures using forms of construction contract. For instance,
the international standards for concluding civil the contract between Boryspil International
engineering works contracts (FIDIC)2. Besides, Airport State Enterprise and the Turkish joint
the actions aimed at ensuring the good quality venture Dou inaat ve Tic. A.. - Alsim Alarko
of works on motorways planned by the Ukrain- Sanayi Tesisleri ve Ticaret A.. - YDA naat ve
ian State Motorway Agency include: drafting Sanayi Ticaret A.., concluded on 26 September
and adopting new legal instruments and amend- 2008 for the construction of a new Terminal D
ing those remaining in force with regard to at Kyiv-Boryspil Airport, as part of the prepara-
payments between the Employer and the Con- tions for the EURO 2012 Football Champion-
tractor and the acceptance of works performed ship, was based on the FIDIC standard form4.
pursuant to the FIDIC (International Federation Another example includes the Illichivsk
of Consulting Engineers) during construction of Sea Commercial Port Infrastructure Develop-
motorways in order to hire independent groups ment Project, which is financed by the EBRD.
of engineering experts (whether Ukrainian or The procurement documentation for the recon-
foreign) for work quality control purposes3. struction of existing berths nos. 7, 8 and 9 pro-
The above cited legal instruments at vides for the execution of a FIDIC-based con-
least show the will of the Ukrainian authorities, tract with the general contractor.
in particular in the motor roads industry, to The Ukrainian local requirements for
implement the FIDIC standards, i.e. best prac- construction projects are set out primarily in
tices, in Ukraine. This is a good sign, if one con- 3 Part 61 Construction Works of the Civil
siders the conservative stand of practitioners in Code of Ukraine, dated 16 January 2003, Part
this area, who, as mentioned above, prefer con- 33 Capital Construction of the Commercial
tracting in accordance with the established Code of Ukraine, dated 16 January 2003 and the
construction contracts. General Conditions for the Conclusion and Per-
The Ukrainian state authorities and con- formance of Contracts in Capital Construction,
tractors should understand that they cannot adopted by the Ministry of Regional Develop-
play only by their rules in the present-day ment and Construction of Ukraine on 1 August
globalized world, i.e. in accordance with 2005 (General Conditions). Besides, there is a
Ukrainian law and Ukrainian forms of contract, local model construction contract approved by
especially if foreign financing is involved. Near- the Ukrainian Ministry for Construction, Archi-
tecture and Facilities on 27 October 2005, the
1 Order of the State Agency of Motor Roads no. 37 dated 09
use of which during contraction works is not
February 2006 On adopting a plan for a scientific and technical obligatory. However, it should be taken into
policy in the Ukrainian road industry for 2006-2010.
2 Decree of the Ukrainian Cabinet of Ministers no. 710 dated 03

August 2005 On adopting a State program for the develop-


ment of motorways for 2007-2011. 4 See e.g. para. 3 of the Order of the Ukrainian Cabinet of Minis-
3 Order of the State Motorways Agency no. 513, dated 29 De- ters no. 1219-p, dated 21 November 2011, On certain issues
cember 2010, On adopting an action plan for improving the regarding the construction of Terminal D at the State-Owned
quality of motorway works. Enterprise Boryspil International Airport State.

str. 52 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

account when negotiating a construction II. The FIDIC disputes resolution


agreement involving state authorities. method in Ukrainian reality

Article 323 of the Commercial Code of Ukraine is a party to all major international
Ukraine stipulates that large-scale construction instruments in the area of international com-
contracts involving a foreign party, should be mercial arbitration, including the New York
concluded and performed in the manner stipu- Convention on the Recognition and Enforce-
lated therein , in international agreements and ment of Foreign Arbitral Awards of 1958 and
in the General Conditions. Thus, the same re- the European Convention on International
quirements of Ukrainian law apply to local and Commercial Arbitration of 1961. The Law of
foreign companies. Ukraine On International Commercial Arbitra-
Moreover, the General Conditions in Ar- tion was adopted in 1994 on the basis of the
ticles 119-126 contain the Specific terms and UNCITRAL Model Law 1985. That said, Ukraine
conditions for concluding and performing con- is still considered an arbitration-unfriendly
struction contracts involving foreign compa- jurisdiction, and often with good reason. The
nies. In particular, Articles 120 and 122 pro- lack of efficient cooperation between arbitral
vide as follows: tribunals and state courts constitutes one of
While concluding international construction the main problems restraining the develop-
contracts, the parties have the right to apply ment of arbitration in Ukraine . Moreover, state
international customs and recommendations of court judges are often unfriendly toward arbi-
international organizations. tration or simply do not recognize arbitration
The terms and conditions of an international and its fundamental principles. This results in
construction contract may be based on model or the lack of their practical experience with
standard templates for international construc- granting interim measures in support of arbi-
tion contracts, previously concluded contracts, tration, in parallel court and arbitral proceed-
etc., ings, interim measures blocking arbitrations
Article 120 of the General Conditions and frequent decisions to annul or to refuse to
emphasizes that an international contract for enforce awards in Ukraine.
works may be declared invalid by a court, if it Nevertheless, despite the wide-spread
was concluded in breach of the national legisla- criticism of the Ukrainian judiciary, arbitration
tion or the applicable international agreements. remains the best way of resolving international
As can be seen, Ukrainian law enables commercial disputes concerning or otherwise
the use of FIDIC forms of contracts for con- related to Ukraine. This is also true of interna-
struction projects in Ukraine. Construction tional construction disputes.
works performed on the basis of FIDIC con- FIDIC contracts provide for a multi-tier
tracts are becoming increasingly common in mode of dispute resolution , unusual in
Ukraine. Having said that, adapting FIDIC con- Ukraine, requiring that the dispute should be
tracts to Ukrainian realities and Ukrainian law submitted to the Disputes Adjudication Boards
requires significant legal expertise in order for (DAB) before it is referred to arbitration.
numerous local mandatory regulations to be Ukrainian law is silent on DABs and includes
observed. no regulations concerning their operation, the
enforcement of their decisions etc. Local com-
panies are not used to this type of dispute reso-

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 53 |


ANALISES & OPINIONS

lution mechanism, either. Ukrainian courts then the decision shall become final and binding
would most probably not acknowledge a DABs upon both Parties.
decision as final and binding. Moreover, courts Due to the fact that that practically no arbitral
usually apply a very formalistic approach to the award in Ukraine is enforced on a voluntary
interpretation of arbitration agreements and basis, the possibility of the DABs decision be-
may find an arbitration clause inoperative if it ing enforced is next to nil, especially as it has
contains a minor mistake. In International Port much lower legal force than an arbitral award.
Services Ltd. v. Odessa Maritime Commercial In such circumstances, sub-Clause 20.7 applies,
Port, the Ukrainian Supreme Court annulled the which stipulates that:
arbitral award on the grounds that the parties In the event that:
had failed to meet a simple negotiation re- (a) Neither Party has given notice of dissatis-
quirement before the matter was referred to faction within the period stated in Sub-
arbitration5. Clause 20.4 [Obtaining Dispute Adjudica-
The formalistic approach of Ukrainian tion Boards Decision]
courts also leads to the strict interpretation of (b) the DABs related decision (if any) has be-
pre-arbitration requirements agreed by the come final and binding, and
parties. The pre-arbitration procedure on (c) a Party fails to comply with this decision
which the parties usually agree is recognized then the other Party may, without prejudice to
by Ukrainian courts. Consequently, it is only an any other rights it may have, refer the failure
arbitral award issued under the procedure set itself to arbitration under Sub-Clause 20.6 [Arbi-
forth in the arbitration clause, which may be tration]. Sub-Clause 20.4 [Obtaining Disputes
effectively enforced in Ukraine. Adjudication Boards Decision] and Sub-Clause
Such an attitude of Ukrainian courts has 20.5 [Amicable Settlement] shall not apply to
a positive effect on the implementation in this reference.
Ukraine of the dispute resolution mechanism Given the Ukrainian legal culture, namely the
prescribed in FIDIC contracts. Under FIDIC lack of a tradition of amicable dispute resolu-
standard forms of contract, a dispute should be tion or voluntary execution of decisions, one
considered by the DAB before it is referred to may assume that almost every dispute under
arbitration. Subsequently, the disputants may FIDIC contracts, which involves a Ukrainian
appeal the DABs decision, which is not yet final party - particularly as the respondent - would
and binding, under the Rules of Arbitration of lead to arbitration.
the International Chamber of Commerce. Oth- On the face of it, the DABs decisions might
erwise, Sub-Clause 20.4 of the FIDIC 1999 Red seem useless, as they would always be ap-
Book, the 1999 Yellow Book and the 1999 Sil- pealed by the losing party or by the winning
ver Book, provides: party due to the losing partys failure to comply
If the DAB has given its decision as to a matter with the decision. However, that is not the case
in dispute to both Parties, and no notice of dis- due to the following reasons:
satisfaction has been given by either Party with-
in 28 days after it received the DABs decision, (i) due to the strict time-frames envis-
aged in FIDIC contracts, the DABs are
undoubtedly faster (and often much
5International Port Services Ltd. v. Odessa Maritime Commercial cheaper) than arbitration;
Port, Decision of the Ukrainian Supreme Court, dated 21 Octo-
ber 2009, in case no. 6-1863407.

str. 54 | e-Przegld Arbitraowy nr 1(8) 2012 r.


ANALISES & OPINIONS

(ii) in time, Ukrainian companies should successfully implemented in practice for the
become accustomed to DABs, and purposes of efficient settlement of construction
the number of the DABs decisions disputes.
performed on a voluntary basis
should increase; Volodymyr Yaremko*
(iii) the DABs are undoubtedly more effi-
cient in resolving small and medium-
sized disputes arising during con-
tract implementation;
(iv) if a party has appealed the DABs de-
cision, the decision will become a
good starting-point for the arbitral
tribunal, as some of the work will
have already been performed by the
DAB;
(v) if a party fails to comply with the
DABs decision, the arbitral tribunal
will not have to decide the dispute
on the merits; rather, it will only re-
solve the failure to execute the
award saving time and reducing the
costs of arbitration.
The dispute resolution mechanism introduced
into FIDIC contracts is undoubtedly unusual for
Ukrainian companies which prefer to resolve
construction disputes by litigation or one-tier
arbitration. However, given its advantages and
due to the fact that foreign construction project
participants insist on using it, Ukrainian com-
panies should apply such best practices to their
construction projects and duly observe this
type of dispute resolution procedure.

III. Conclusion

Arbitration is the right way of resolving inter-


national construction disputes in Ukraine.
FIDIC forms of contracts are not very popular
in Ukraine, but they are used with increasing
frequency and will be even more common in
the future. The multi-tier dispute resolution
mechanism introduced into FIDIC contracts is *Volodymyr Yaremko: Associate and Attorney-at-Law at
not often used in Ukraine. However, it may be the Lviv office of Arzinger law firm (Ukraine)

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 55 |


CASE LAW

The legal nature of a consortium in the context of credi-


tors joint and several liability
Acting as the Claimant in the present case was a consortium composed of several companies which
jointly brought a claim for payment. The Arbitral Tribunal had to determine the nature of the consor-
tium under Polish law and to establish whether the companies composing it might assert their claim
for payment on the basis of creditors joint and several liability.

Award published in: 2009 umowa spki, Art. 860 et seq. of the Code of
Award rendered in: Warsaw Civil Procedure) should be applied to the Con-
Object of dispute: Claims under additional tract. Such a conclusion may be drawn from,
works on a construction project among others, the description of the mutual
economic objective, i.e. construction of the
From the reasons: structure defined in the Contract, the detailed
(...) To begin with, one should determine the description of the mode of cooperation, a de-
legal relationship by which the Claimants, re- scription of the partners shares in profit, as
ferred to collectively as the Contractors in the well as the use of the term partner with refer-
Contract, were bound. The relationship in ques- ence to the parties to the agreement, which
tion arose from the Contract concluded by the corresponds to the notion of partnership ac-
Parties. A legal assessment of the Contract cepted in Polish law. Accordingly, one should
should be made on the basis of Polish law. In determine the nature of a debtors obligation
the Contract, the Contractors are also referred toward partners in a civil partnership (Polish:
to as a consortium. In principle, consortium spka cywilna).
does not function as a legal concept in Polish Under Art. 369 of the Civil Code, an obli-
law (S. Wodyka [in:] S. Wodyka (ed.), System gation is referred to as joint and several if it
prawa handlowego [The system of commercial results from statutory law or from a legal act.
law], Volume 5, p. 806; J. Hilla, Prawne Joint and several liability is an exception to the
problemy funkcjonowania konsorcjum [Legal rule that an obligation is divided into parts if
problems with the operation of a consortium], the object of an obligation is divisible and in-
Radca Prawny no. 5 of 2005, p. 35 and the writ- volves multiple entities. The provisions on the
ings cited therein). No in-depth analysis of the civil partnership provide only for the joint and
Contract was required for the purposes of the several liability of partners for obligations of
present arbitration in order to determine the partnership, but not for the liability of third
whether the Contract contained the features of parties. There is no other statutory basis for
a consortium agreement identified by legal assuming that the Claimants bear joint and sev-
commentators. It sufficed to state, at least with- eral liability as creditors. Nor does such liability
in the scope under consideration, i.e. from the result from the legal act, as there is no such
viewpoint of an assessment of the legal rela- provision in the Contract.
tionships between the Parties, that the provi- The above discussion and findings seem
sions on the partnership agreement (Polish: to lead to the conclusion that, if the Claimants

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 56 |


CASE LAW

are entitled to claims for payment against the Grzybowski (ed.), System Prawa Cywilnego.
Respondent in the present case, the said claims Prawo Zobowiza. Cz szczegowa [System
were divided into two parts by operation of of Civil Law. The Law of Obligations. Detailed
law, in accordance with Art. 3791 of the Civil Part], Volume III, part 2, Wrocaw 1976, p.
Code. In the absence of any circumstances to 814): A claim is treated as if only one creditor
the contrary, the two parts are equal (Art. existed, i.e. the partnership, not all partners.
3791 of the Civil Code, 2nd sentence). Such Such an interpretation entails far-reaching con-
division of the obligation is also confirmed by sequences. A partner may not demand that the
the stipulation in the contract of the Parties partnerships debtor pay any portion of the debt
about equal shares in the partnership. to it. Consequently, only all partners are enti-
However, adoption of such ex lege divi- tled to demand payment from the partnerships
sion of an obligation, whereby partners in a debtor, provided that such payment should be
civil partnership as understood by Art. 860 et made in a manner which is most suited to the
seq. of the Civil Code constitute one of the specific nature of the partnership originating,
parties, raises serious doubts. In accordance in particular, from the joint co-ownership of the
with a commonly held view, the joint property partners with respect to the partnerships as-
of partners during the life of a civil partnership sets, including claims.
is in the nature of joint co-ownership whereby In the judgment of January 17, 1997, I
the shares of partners are not specified and the CKN 42/96, the Supreme Court held that [t]he
co-owners may not dispose of them at their provision of a consideration to one of the part-
discretion. Unlike the articles of associations of ners of a civil partnership constitutes due per-
companies limited by shares, the civil partner- formance of the obligation, unless the civil
ship agreement does not give rise to a separate partnership agreement, known to the debtor,
legal entity. In principle, it only triggers conse- stipulates that shareholders determined the
quences inter partes. This is the reason why the manner of managing the partnerships affairs
contractual clause about equal shares is irrele- and of its representation other than provided
vant from the viewpoint of any possible deter- for in Art. 865 and 866 of the Civil Code. The
mination of shares in a claim. Such a clause is Arbitral Tribunal concurs with this legal view.
only binding upon the parties to the agreement The Parties are jointly seeking payment in the
concerned. statement of claim, acting as the partners of a
Legal commentators note that a sui gen- partnership in this regard. This justifies the
eris joint claim arises in relation to claims conclusion that the awarded sum may be paid
constituting the object of the joint co- to any one of them. Due to the specific nature of
ownership of partners in a civil partnership (M. the claim, a statement about the consequences
Litwiska, Skuteczno umowy spki cywilnej of a payment to one of the creditors had to be
wzgldem osb trzecich [Effectiveness of a civil made in the dispositive section of the award.
partnership in relation to third parties],
Przegld Prawa Handlowego no. 9 of 1997, p.
38). This should lead to the conclusion that if
the debtor remits payment to one of the part-
ners, the obligation is discharged with respect
to all other partners. This view is also con-
firmed by S. Grzybowski, among others (S.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 57 |


CASE LAW

Limitations period relating to a FIDIC-based construction


contract in the context of partial delivery of works

A plea of limitation concerning payments for works performed and delivered in stages was raised dur-
ing the consideration of a dispute over additional construction works. The Arbitral Tribunal had to
decide whether the plea was justified.

Award published in: 2009 ceptance thereof by the investor (see also the
Award rendered in: Warsaw judgments of the Supreme Court, dated January
Object of dispute: Claims for payment for ad- 23, 2007, III CSK 275/06, and September 4,
ditional construction works 2002, I CK 1/02). The above is the result of the
indivisible nature of the consideration prom-
From the reasons: ised in the construction contract. The said na-
(...) In order to determine whether a plea of ture is not altered by the admissibility of partial
limitation is justified, it is crucial to establish deliveries specified in detail in the Contract,
when the limitations period began to run. Oth- which was stipulated in Art. 654 of the Civil
erwise, it is beyond dispute that, in accordance Code.
with Art. 118 in fine of the Civil Code, the limi- Interim Payment Certificates do not
tations period lasts 3 years. change the maturity date of the Claimants
In principle, the limitations period begins to claims because they are not definitive in nature
run once the claim has become due (Art. 1201 and may be modified by the Contract Engineer
in principio of the Civil Code). As regards a con- in accordance with Sub-clause 60.4. Under
struction contract, unless the parties do not Sub-clause 60.6 of the Conditions of Contract,
agree otherwise, the contractors claims be- the sums recognized as due to the contractor
come due upon the delivery of works (judg- are definitively determined only in the Final
ment of the Court of Appeal in Katowice, dated Statement, so that the contractor may not fore-
January 16, 1991, I ACr 118/90, OSA see which of its claims will not be acknowl-
1992/1/10). Moreover, it is worthwhile to cite edged and should be asserted in arbitration
the view expressed by the Supreme Court in its proceedings.
judgment of April 16, 2007, III CSK 366/06, It follows from the above that a contrac-
with which the Arbitral Tribunal fully concurs: tual stipulation of payment for partial deliver-
partial delivery and payment of a portion of re- ies does not determine the maturity date of a
muneration merely signifies the confirmation by claim. Therefore, the question one should ask
the investor, for remuneration payment purpos- is: Did the Parties agree a different maturity
es, that a certain portion of works has been per- date for a claim? In answering this question,
formed. Such a manner of settlement does not one must conclude that the Respondent was to
prevent the parties from settling their accounts make payments to the Claimants on the basis of
definitively and in full after the delivery of the the Final Payment Certificate (as provided for
entire facility by the contractor and the ac- in clause 60.8 of the Conditions of Contract)

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 58 |


CASE LAW

which the Contract Engineer should have is-


sued within 20 business days following receipt
of the Final Certificate and of the Written
Statement. Under Sub-clause 60.10, payments
should be made within 45 business days fol-
lowing delivery of the Final Payment Certificate
to the Ordering Party. The maturity date there-
fore falls on the day following that period.

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 59 |


CASE LAW

A construction contract or a contract for the perfor-


mance of a specific task?
A plea of limitation was raised in a case relating to a claim for payment for construction works involv-
ing the delivery, installation, launch and arrangement for delivery by the competent authority of an
escalator and lifts as well as free-of-charge cooperation on a transparent lift shaft design in an infra-
structure project. In order to decide if the plea was justified in light of various limitations periods, the
Arbitral Tribunal had to determine whether the works in question were actually conducted under a
construction contract (Polish: umowa a roboty budowlane) or a contract for the performance of a
specific task (Polish: umowa a dzieo).

Award published in: 2011 in accordance with the general principles laid
Award rendered in: Warsaw down in Art. 118 of the Civil Code, i.e. after
Object of dispute: Claim for payment for con- three years (as stated in the judgment of the
struction works on an infrastructure project Supreme Court of January 11, 2002, III CZP
63/01).
From the reasons:
Legal classification of the Contracts with X. Contracts with X as result-based agree-
In order to assess the claims under Invoices ments. While a service provision contract rep-
Nos. 1 and 2, in the context of the effectiveness resents a due diligence agreement, a contract
of the related set-off, it was crucial to establish for the performance of a specific task, like a
whether the Contracts with X constituted con- construction contract, constitutes a result-
tracts for the provision of services, as referred based agreement. An analysis of the Contracts
to in Art. 750 of the Civil Code; contracts for the with X leads to the conclusion that X committed
performance of a specific task, as provided for itself to the delivery, as well as the full installa-
in Art. 627 et seq. of the Civil Code; or construc- tion, launch and arrangement for delivery by
tion contracts, as defined in Art. 647 et seq. of the competent authority of escalators and lifts
the Civil Code. Determining the legal nature of within the Structure as well as to free-of-charge
these contracts was important in that, under cooperation on a transparent lift shaft design in
Art. 751 Point 1 of the Civil Code, claims for the scope of issuing guidelines and checking the
payment of the remuneration for services of a design. This means that the main obligation of
business entity become time-barred after two X was result-oriented (in the scope of the deliv-
years. The two-year limitations period, starting ery of escalators and lifts, including the installa-
from the day the work is delivered, is also ap- tion, launch and arrangement for such deliv-
plicable to claims under a contract for the per- ery), with the auxiliary part of the main obliga-
formance of a specific task (Art. 646 of the Civil tion being a due diligence commitment (in the
Code); while, due to the lack of lex specialis, scope of cooperation on a lift shaft design). Ac-
construction works claims become time-barred cordingly, we shall deal with the legal classifi-

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 60 |


CASE LAW

cation of the Contracts with X as result-based struction works, as the specified result of con-
agreements exclusively in the context of a con- struction works which constitutes an autono-
tract for the performance of a specific task and mous whole in the design documentation and
a construction contract. which can be separated at least in the technical
or technological sense. It should be inferred
The contracts with X in light of Art. 647 of from the above that the delivery, installation,
the Civil Code. The Arbitral Tribunal held the launch and the arrangement for delivery of lifts
view that the construction works specified in and escalators may not be classified as the im-
the Building Law might be performed under a plementation of a large-size project. Undoubt-
construction contract or a contract for the per- edly, it is the construction of the entire struc-
formance of a specific task. This statement is ture the Structure under discussion which
consistent with the view expressed by the Su- constitutes such a project, not the delivery, in-
preme Court in the judgment of September 16, stallation and launch of some of the facilities
2009 (II CSK 104/09). That being said, one within the Structure. As regards exercising the
should agree with the Claimant that, under institutional supervision referred to in the Su-
Art. 65 2 of the Civil Code, an assessment of preme Courts rulings, construction supervision
the nature of a contract depends on the actual tasks are performed, in accordance with the
content thereof, as well as the purpose and the Building Law (Art. 80 et seq.), by construction
mutual intention of the parties, not on the con- supervision authorities viz. the district, re-
tracts name. Under Art. 647 of the Civil Code, gional or chief construction supervision inspec-
in concluding a construction contract, the con- tor. Under the Contracts with X, the works per-
tractor commits itself to delivering the con- formed thereunder were to be supervised by
tracted-for structure, to be built in accordance the Office of Technical Inspection (UDT), an
with the design and the rules for building ex- authority tasked with technical inspection, not
pertise, and the investor undertakes to perform building supervision.
the tasks required by the applicable regulations
in order for the works to be prepared or, more b. the construction works are to be
specifically, to hand over the construction site performed by the contractor in accordance
and deliver the design, to take delivery of the with the design, with the proviso that the appli-
structure and to pay the remuneration agreed. cable clause subsequently provides that the
The following elements of the above definition investor is obliged to deliver the said design.
merit particular attention: Pursuant to the Supreme Courts judgment, a
construction contract which is not accompa-
a. the contractor undertakes to deliv- nied by the delivery of a design by the investor
er a structure, i.e. a large-size project pos- constitutes a contract for the performance of a
sessing individual features, both physical and specific task, to which the provisions on con-
functional, associated with designing and insti- struction works do not apply (judgment of the
tutional supervision (cf. judgments of the Su- Supreme Court of October 6, 2004, I CK 71/04).
preme Court of May 18, 200, I CSK 51/07 and In this regard, it should be noted that some le-
of January 11, 2002, III CZP 63/01). In the gal commentators are of the view that, even if it
judgment of July 22, 2004 (II CK 477/03), the is the contractor which is obliged to deliver a
Supreme Court also referred to a structure, as building design under the contract, the said
understood by the provisions governing con- contract does not cease to be a construction

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 61 |


CASE LAW

contract (such a view was expressed by Janusz which construction works are carried out, in-
A. Strzpka, Ewa A. Zieliska, Glosa aprobujca cluding the area occupied by backup facilities
do wyroku Sdu Najwyszego z dnia 11 stycznia (Art. 3 Section 10 of the Building Law). The
2002 r. [Approving gloss to the judgment of the term work front is not confined to the con-
Supreme Court of January 1, 2002], III CZP duct of construction works and it denotes the
63/01, OSP 2002/10/125). In the present case, creation of appropriate conditions in order for
the works under the contracts with X were not the given activities to be conducted.
performed on the basis of any design, and Xs
commitment under Art. 1 to free-of-charge co- Other issues related to the legal classifica-
operation on a transparent lift shaft design or, tion of the Contracts with X
more specifically, on issuing a set of guidelines (...) In this scope, the Arbitral Tribunal stated
and on checking the design, by no means con- that, in order to determine that the facilities
stitutes any obligation to deliver a design or Xs constitute part of the structure, as a construct
obligation to perform the works contemplated which came into existence under a construction
by the contracts with X in accordance with a contract as understood by Art. 647 of the Civil
design. That being said, it should be added that Code, it is necessary to determine that they
the very undertaking to install lifts and an esca- represent a component thereof i.e. a tangible
lator, i.e. to adapt them to the existing infra- object connected with another tangible object,
structure, does not mean that the works were operating as the superior (main) object (this
performed on the basis of the Claimants de- view was expressed by M. Bednarek, [in:] M.
sign. Quite the contrary, Xs obligation was per- Bednarek, Mienie. Komentarz do art. 44-55(3)
formed in accordance with the contractors de- Kodeksu cywilnego [Property. Commentary to
sign and technology. Art. 44-55(3) of the Civil Code], Zakamycze,
1997). The result of the finding that a given
c. as part of the tasks related to the facility constitutes a component of the main
preparation of works, the investor is obliged to object (the structure) is that in accordance
hand over the construction site in addition to with Art. 47 of the Civil Code the facility in
being obliged, as mentioned above, to deliver a question may not constitute a separate object
design. In this regard, the Arbitral Tribunal re- of ownership (property) from the structure.
fused to accept the position expressed by the Under the Contracts with X, the facilities con-
Respondent, that the timely commencement templated in those Contracts were not to be-
and conclusion of the installation of the par- come the property of the Claimant until it had
ticular facilities depend on the timely prepara- performed its payment obligations. The stipula-
tion of the work front (pursuant to the Con- tion that ownership was not to be obtained un-
tracts with X), in support of its contention that til the price had been paid suggests that the
the Contracts with X were essentially construc- facilities in question may not constitute a com-
tion contracts. The term construction site ponent of the Structure, and thus may not con-
(Polish: teren budowy), as used in Art. 647 of stitute a structure within the meaning of Art.
the Civil Code, is not identical to work front 647 of the Civil Code.
(Polish: front robt), a concept which has a dif- As regards the issue of a building permit,
ferent meaning, not necessarily connected with the Building Law (Art. 28 Section 1) provides
a construction site. In fact, construction site is that construction works are performed on the
defined by the Building Law as the area in basis of a final building permit. In this case, the

str. 62 | e-Przegld Arbitraowy nr 1(8) 2012 r.


CASE LAW

Arbitral Tribunal did not agree with the Re- contract for the performance of a specific task.
spondent that the works were performed by X Which is exactly how the Arbitral Tribunal clas-
on the basis of a decision concerning a building sified the Contracts with X.
permit and approving the building design. In Incidentally, the Arbitral Tribunal
point of fact, the works under the Contracts wishes to add that it is irrelevant for the finding
with X were carried out on the basis of the that the Contracts with X constitute contracts
Conditions for commencing the installation, for the performance of a specific task that, in
for conducting works and for taking delivery of accordance with the definition of construction
lifts in accordance with the Lifts Directive (LD) works provided in Art. 3 Section 7 of the Build-
95/16/EC. The fact that a building permit for ing Law, the works in question may involve,
the Structure in M. was issued does not yet among others, installation and that the struc-
mean that the works were performed by X on ture may also include technical facilities under
the basis of a final decision concerning a build- Art. 3 Section 1 of the Building Law. Likewise,
ing permit. In fact, the building permit present- one should disregard, as irrelevant to the case
ed by the Respondent does not refer to the at hand, the fact that the site manager is a con-
conditions for performing works involving the struction process participant under Art. 17 of
installation of lifts or an escalator. the Building Law, even though it was the site
The Contracts with X may not be classi- manager who signed the Material Inspection
fied as construction contracts concluded with Certificate on behalf of the Claimant, which
the contractor under Art. 6471 1 and 2 of the constitutes proof that X has taken delivery of
Civil Code. The above Article provides that a the works. As noted above, the fact that specific
contract with a subcontractor constitutes an works are classified as construction works
element of a greater whole, i.e. of a construc- within the meaning of the Building Law does
tion contract entered into with the general con- not yet mean that they were performed under a
tractor and, in order to be valid, it requires the construction contract, as defined by Art. 647 of
investors consent and the delivery of the de- the Civil Code. It should be noted that, other
sign documentation concerning the given part than the site manager, the Contracts with X do
of the structure. These elements are nowhere not mention any other participants typical of
to be found in the Contracts with X. The above the construction process, such as the inspector,
arguments prove that the Contracts with X may investor supervision inspector or designer. In
not be classified as construction contracts. The accordance with the judgment of the Supreme
works performed by X should be regarded as Court of May 25, 1998 (II CKN 653/97), an as-
furnishing works (Polish: prace o charakterze sessment of how the investment project was
wyposaeniowym) (see the judgment of the Su- implemented under the Building Law require-
preme Court of March 25, 1998 , II CKN ments serves as the main criterion for differen-
653/97). At this point, it is necessary to cite the tiating between a contract for the performance
view expressed by the Supreme Court in its of a specific work and construction contract.
judgments of November 6, 2002 , III CKN
997/00 and of May 18, 2007, I CSK 51/07 that,
if a party fails to demonstrate that a given con-
tract contains features which enable it to be
classified as a construction contract, it is cor-
rect to infer that the parties were bound by a

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 63 |


LEWIATAN ARBITRATION MOOT COURT

The opening edition of the Lewiatan Arbitration Moot Court, Polands first moot
court competition for bar trainees, organized by the Lewiatan Court of Arbitra-
tion and Young Arbitration Practitioners in Poland at the Lewiatan Court of Arbi-
tration (YAPP) finished on May 31, 2012.

The competition consisted of two parts: written panel of arbitrators. Professional arbitrators
and oral. In the written part, competing teams stressed that all participants were well pre-
drafted a statement of claim and a statement of pared, that the briefs they drafted and the
defense, whereas in the oral part, they acted as pleadings they made were of very good quality
counsel and took part in a moot arbitral hear- and generally praised them for outstanding
ing before a panel consisting of three arbitra- elocution skills.
tors. The moot case concerned a construction
dispute in connection with the construction of a Organizing such a large competition was
football stadium for the EURO 2012 champion- a real challenge. The scale of the project was
ship, to be resolved under the new Rules of the unprecedented, as was shown by the impres-
Lewiatan Court of Arbitration, effective as of sive number of teams and participants as well
March 1, 2012. A selection of photographs as other indicators. For example, the partici-
from the oral part of the competition are in- pants briefs and pleadings were assessed by
cluded below. approximately 150 arbitrators, and over 70
hearings took place in the oral phase. Organiz-
When we organized the competition, we ers obtained invaluable help from sponsors and
did not expect such immense interest from jun- the authorities of the Polish bar associations
ior lawyers, as over 100 teams and 250 bar (legal counsel and advocate bars). Major con-
trainees from all across Poland took part in the tributors to the project include the Polish Arbi-
competition. The response to the Lewiatan tration Association (the competitions main
Arbitration Moot Court will imbue all profes- supporting partner), Polish and international
sional arbitrators with a hefty dose of opti- law firms, as well as Regional Chambers of Le-
mism, as it confirms a growing interest in arbi- gal Counsel and Regional Chambers of Advo-
tration among the younger generation of law- cates from across the country. The competition
yers, and demonstrates their genuine interest was held under the honorary patronage of the
in enhancing their professional skills. The par- President of the National Board of Legal Coun-
ticipants highly rated the educational dimen- sel, Maciej Bobrowicz and President of the Na-
sion of the competition and appreciated being tional Board of Advocates, Advocate Andrzej
able to receive advice and comments from re- Zwara, as well as the Chartered Institute of Ar-
nowned arbitrators. For many of them, the bitration (CIArb) in London.
competition was their first opportunity to try
their hand at arbitration and to appear before a

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 64 |


Not only was the competition an oppor-
tunity to promote arbitration as a dispute reso-
lution method, but also it served to integrate
the Polish arbitration community and bar
trainees from different regions of the country.
The Lewiatan Arbitration Moot Court stands a
fair chance of becoming the Polish equivalent of
international competitions, including the fa-
mous Willem C. Vis International Commercial
Arbitration Moot, thus becoming a permanent
fixture in the annual calendar of arbitration
events.

Once again we would like to extend our


heartfelt thanks to everybody who contributed
to the wonderful success of this project and to
encourage them to take part in the same com-
petition again next year.

Anna Maria Pukszto

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 65 |


LEWIATAN ARBITRATION MOOT COURT

Ist Edition
of the Lewiatan Court Competition for young lawyers
On May 30-31, 2012, the Lewiatan Arbitration Competition finale and the formal announcement of its
results were held. The competition was the first arbitration moot court competition in Poland ad-
dressed to trainee advocates or trainee attorneys all over Poland. Such a competition takes the form of
common moot court or arbitration moot court proceedings. The competition has received much inter-
est (100 teams, over 250 lawyers, have responded to it). This shows great interest in and much need
for advancing knowledge in the area of alternative ways of dispute resolution. The subject matter of
the competition case was dispute resolution of disputes involved in the process of carrying out a
building investment.

The Finale took place at the Warsaw University Library. In the Arbitral Tribunal were Mec. Jolanta
Nowakowska-Zimoch, Profesor dr hab. Stanisaw Sotysiski i Profesor dr hab. Jerzy Rajski. An-
nouncement of the results was held at the Arbitration Picnic in the Gardens of the Warsaw University
Library. The winners are: Alicja Zieliska i Pawe Kwiatkowski (team: KAL129).

The Information Point for Teams (Warsaw Towers)

The Information Point for


teams was situated in Warsaw
Towers.

Announcement of results of
the Eliminations.

Photo:. Tomasz Szczepek

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 66 |


Photo: Robert Gardziski
The Welcoming: Mec. Anna Pukszto Vicepresident of Lewiatan Court of Arbitration and Mec.
Agnieszka Wojciechowska President of Young Arbitration Practitioners In Poland

The Arbitral Tribunal: (after


exlusion of herself dr Beata
Gessel Kalinowska vel Kalisz):
Mec. Jolanta Nowakowska-
Zimoch, Profesor dr hab. Stani-
saw Sotysiski and Profesor dr Photo: Robert Gardziski
hab. Jerzy Rajski

Photo: Robert Gardziski


Team KAL3: ukasz Lasek and Jeremiasz Ku- Team KAL129: Alicja Zieliska and Pawe
mierz Kwiatkowski

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 67 |


Photo: Robert Gardziski

The Arbitration Picnic

The Best Statement of Claim The Best Speaker (Mec. Maciej


(Mec. Wodziemirz Chrcik The Best Reply to The Statement Bobrowicz handing the prize to
handing the prize to Aleksandra of Claim (Mec. Anna Pukszto Jeremiasz Kumierz)
Jankowska from the KAL9 Team) handing the prize to the KAL89
Team: Elbeta Bogucka, Patrycja
Bolimowska, Andrzej Gsior)

Photo: Robert Gardziski


The announcement of results: (from left) P. Kwiatkowski, A. Zieliska, dr B. Gessel Kalinowska
vel Kalisz, prof. S. Sotysiski, mec. J. Nowakowska-Zimoch, prof. J. Rajski, . Lasek, J. Kumierz

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 68 |


Konkurs Arbitraowy Lewiatan

Handing of prizes Photo: Robert Gardziski

Photo: Robert Gardziski

The Arbitration Picnic Photo: Robert Gardziski

e-Przegld Arbitraowy nr 1(8) 2012 r. str. 69 |

You might also like