ID Task Name Duration Start Finish

2017
Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17
3006132027041118250108152229051219260310172431071421280512192602091623300613202706132027031017240108152229051219260310172431071421280411182502091623300613202704
1 KANDY CITY WASTEWATER MANAGEMENT PROJECT 1840 days 21/11/2014 04/12/2019
16 CONTRACT 1370 days 03/03/2015 01/12/2018
17 PRELIMINARIES, DESIGN, SUPPLY, CONSTRUCTION, DOCUMENTATION & COMMISSIONING 1370 days 03/03/2015 01/12/2018
1614 CONSTRUCTION 717 days 01/01/2016 07/06/2018
1615 WASTEWATER TREATMENT PLANT (WWTP) 717 days 01/01/2016 07/06/2018
1616 CONSTRUCTION INCLUDING SUPPLY OF ALL MATERIALS REQUIRED FOR COMPLETE 717 days 01/01/2016 07/06/2018
INSTALLATION OF EQUIPMENT AND SYSTEMS
1630 REINFORCED CONCRETE FOR PROCESS STRUCTURES AND BUILDINGS. INCLUDES 483 days 29/06/2016 13/02/2018
EXCAVATION, FOUNDATION, BACKFILLING AND TESTING OF LIQUID RETAINING
STRUCTURES INCLUDING BASEMENT STRUCTURES.
1631 OXIDATION DITCHES 437 days 29/06/2016 16/12/2017
1632 Start of Oxidation Ditch 0 days 29/06/2016 29/06/2016 29/06
1633 OXIDATION DITCH 3 & 4 315 days 29/06/2016 21/07/2017
1634 Start of Oxidation Ditch 3 & 4 0 days 29/06/2016 29/06/2016 29/06
1635 EARTH WORK (See Appendix_01) 62 days 30/06/2016 12/09/2016
1636 EXCAVATION 52 days 30/06/2016 31/08/2016
1637 Setting Out for Excavation 1 day 30/06/2016 30/06/2016
1638 station + 61.2 to + 73.909 6 days 01/07/2016 07/07/2016
1639 station + 73.909 to + 89.909 8 days 08/07/2016 16/07/2016
1640 station + 89.909 to + 105.909 9 days 18/07/2016 28/07/2016
1641 station + 105.909 to + 121.909 10 days 29/07/2016 09/08/2016
1642 station + 121.909 to + 137.909 11 days 10/08/2016 23/08/2016
1643 station + 137.909 to + 146.514 7 days 24/08/2016 31/08/2016
1644 FOUNDATION FILL & COMPACTION 47 days 18/07/2016 12/09/2016
1645 station + 61.2 to + 89.909 10 days 18/07/2016 29/07/2016
1646 station + 89.909 to + 121.909 10 days 10/08/2016 22/08/2016
1647 station + 121.909 to + 146.514 10 days 01/09/2016 12/09/2016
1954 OXIDATION DITCH 1 & 2 296 days 19/12/2016 16/12/2017
1955 Start of Oxidation Ditch 1 & 2 0 days 19/12/2016 19/12/2016 19/12
1956 EARTH WORK (See Appendix_01) 47 days 20/12/2016 15/02/2017
1957 EXCAVATION 47 days 20/12/2016 15/02/2017
1958 Setting Out for Excavation 1 day 20/12/2016 20/12/2016
1959 station + 61.2 to + 73.909 7 days 21/12/2016 28/12/2016
1960 station + 73.909 to + 89.909 7 days 29/12/2016 05/01/2017
1961 station + 89.909 to + 105.909 8 days 06/01/2017 16/01/2017
1962 station + 105.909 to + 121.909 9 days 17/01/2017 26/01/2017
1963 station + 121.909 to + 146.514 15 days 27/01/2017 15/02/2017
2271 SEDIMENTATION TANKS 349 days 12/09/2016 15/11/2017
2272 Start of Sedimentation Tank 0 days 12/09/2016 12/09/2016 12/09
2273 SEDIMENTATION TANK - 04 170 days 12/09/2016 07/04/2017
2274 Start of Civil Work of Sedimentation Tank - 04 0 days 12/09/2016 12/09/2016 12/09
2275 EARTH WORK (See Appendix_01) 33 days 13/09/2016 22/10/2016
2276 EXCAVATION 16 days 13/09/2016 01/10/2016
2277 Setting Out for Excavation 1 day 13/09/2016 13/09/2016
2278 station + 0 to + 15.85 8 days 14/09/2016 23/09/2016
2279 station + 15.85 to + 30.6 7 days 24/09/2016 01/10/2016
2280 FOUNDATION FILL & COMPACTION 17 days 03/10/2016 22/10/2016
2281 station + 0 to + 30.6 17 days 03/10/2016 22/10/2016
2352 SEDIMENTATION TANK - 03 176 days 22/10/2016 30/05/2017
2353 Start of Civil Work of Sedimentation Tank - 03 0 days 22/10/2016 22/10/2016 22/10
2354 EARTH WORK (See Appendix_01) 46 days 24/10/2016 19/12/2016
2355 EXCAVATION 18 days 24/10/2016 12/11/2016
2356 Setting Out for Excavation 1 day 24/10/2016 24/10/2016
2357 station + 30.6 to + 45.35 8 days 25/10/2016 02/11/2016
2358 station + 45.35 to + 61.2 9 days 03/11/2016 12/11/2016

Task Summary Group By Summary Manual Task Manual Summary Critical Split
Date: 08/06/2016
Milestone Project Summary External Milestone Manual Milestone Critical Progress

Project: Kandy City Wastewater Management Project - Package 01 Page 1 of 2 JFEEC-CDQ-Detail Design & Construction Schedule Rv.01-160608-0800
ID Task Name Duration Start Finish
2017
Jun '16 Jul '16 Aug '16 Sep '16 Oct '16 Nov '16 Dec '16 Jan '17 Feb '17 Mar '17 Apr '17 May '17 Jun '17 Jul '17 Aug '17 Sep '17 Oct '17 Nov '17
3006132027041118250108152229051219260310172431071421280512192602091623300613202706132027031017240108152229051219260310172431071421280411182502091623300613202704
2359 FOUNDATION FILL & COMPACTION 28 days 15/11/2016 19/12/2016
2360 station + 30.6 to + 61.2 28 days 15/11/2016 19/12/2016
2431 SEDIMENTATION TANK - 01 180 days 15/02/2017 23/09/2017
2432 Start of Civil Work of Sedimentation Tank - 01 0 days 15/02/2017 15/02/2017 15/02
2433 EARTH WORK (See Appendix_01) 43 days 16/02/2017 06/04/2017
2434 EXCAVATION (SEDIMENTATION TANK 01 & DISINFECTION BUILDING) 28 days 16/02/2017 20/03/2017
2435 Setting Out for Excavation 1 day 16/02/2017 16/02/2017
2436 station + 0 to + 15.85 13 days 17/02/2017 03/03/2017
2437 station + 15.85 to + 30.6 14 days 04/03/2017 20/03/2017
2438 FOUNDATION FILL & COMPACTION 15 days 21/03/2017 06/04/2017
2439 station + 0 to + 30.6 15 days 21/03/2017 06/04/2017
2510 SEDIMENTATION TANK - 02 180 days 06/04/2017 15/11/2017
2511 Start of Civil Work of Sedimentation Tank - 02 0 days 06/04/2017 06/04/2017 06/04
2512 EARTH WORK (See Appendix_01) 43 days 07/04/2017 02/06/2017
2513 EXCAVATION (SEDIMENTAION TANK 02 & SLUDGE PUMP BUILDING) 28 days 07/04/2017 16/05/2017
2514 Setting Out for Excavation 1 day 07/04/2017 07/04/2017
2515 station + 0 to + 15.85 14 days 08/04/2017 27/04/2017
2516 station + 15.85 to + 30.6 13 days 28/04/2017 16/05/2017
2517 FOUNDATION FILL & COMPACTION 15 days 17/05/2017 02/06/2017
2518 station + 0 to + 30.6 15 days 17/05/2017 02/06/2017
2590 PRELIMINARY PROCESS BUILDING INCLUDING FLOWMETER 159 days 02/06/2017 12/12/2017
2591 Start of Civil Work of Preliminary Process Building 0 days 02/06/2017 02/06/2017 02/06
2592 EARTH WORK (See Appendix_01) 11 days 03/06/2017 16/06/2017
2593 Setting Out for Excavation 1 day 03/06/2017 03/06/2017
2594 Excavation 9 days 05/06/2017 15/06/2017
2595 Preparation of Floor for Lean Concrete 1 day 16/06/2017 16/06/2017
2865 SLUDGE TREATMENT BUILDING 199 days 15/06/2017 13/02/2018
2866 Start of Civil Works of Sludge Treatment Builidng 0 days 15/06/2017 15/06/2017 15/06
2867 SITE WORKS 30 days 16/06/2017 20/07/2017
2868 EARTHWORK (See Appendix_01) 28 days 16/06/2017 18/07/2017
2869 Setting out for Excavation 1 day 16/06/2017 16/06/2017
2870 Excavation 27 days 17/06/2017 18/07/2017
3067 RETAINING WALL STRUCTURE 120 days 12/09/2016 07/02/2017
3068 Start of Civil Work of Retaining Wall 0 days 12/09/2016 12/09/2016 12/09
3069 EARTH WORK (See Appendix_01) 21 days 13/09/2016 07/10/2016
3070 Setting out for Excavation 1 day 13/09/2016 13/09/2016
3071 Excavation 20 days 14/09/2016 07/10/2016
3126 ADMINISTRATION BUILDING INCLUDING CAR PARK 115 days 18/07/2017 05/12/2017
3127 Start of Civil Work of Administration Building 0 days 18/07/2017 18/07/2017 18/07
3128 EARTH WORK 6 days 19/07/2017 25/07/2017
3129 Setting out for Excavation 1 day 19/07/2017 19/07/2017
3130 Excavation 5 days 20/07/2017 25/07/2017
3242 WORK SHOP AND GARAGES 105 days 25/07/2017 29/11/2017
3243 Start of Civil Work of Workshop and Garage 0 days 25/07/2017 25/07/2017 25/07
3244 EARTH WORKS 8 days 26/07/2017 03/08/2017
3245 Setting out for Excavation 1 day 26/07/2017 26/07/2017
3246 Excavation 7 days 27/07/2017 03/08/2017
3322 GUARD HOUSE 50 days 20/11/2017 20/01/2018
3323 Start of Civil Work of Guard Hous 0 days 20/11/2017 20/11/2017 20/11
3324 EARTH WORKS 2 days 20/11/2017 21/11/2017
3325 Setting out for Excavation 1 day 20/11/2017 20/11/2017
3326 Excavation 1 day 21/11/2017 21/11/2017

Task Summary Group By Summary Manual Task Manual Summary Critical Split
Date: 08/06/2016
Milestone Project Summary External Milestone Manual Milestone Critical Progress

Project: Kandy City Wastewater Management Project - Package 01 Page 2 of 2 JFEEC-CDQ-Detail Design & Construction Schedule Rv.01-160608-0800