Nominal Productivity Rate Table

Operations Department Earth Works

Labours
Productivity Rate productivity per
Activity Type UNIT Hour Rate
(Unit/Man/Hour) day
(AED/Hour)

Mechanical Excavation (Large Areas ) m 28.5 228 10


Mechanical Excavation (Small Areas ) m 16 128 10
Manual Excavation m 0.3 2.4 10
Excavation for Kerb Stone (Manual) Lm 1 8 10
Excavation for Manholes ( Mechanical ) Nos 3 24 10
Excavation for Trenches (Mechanical ) Lm 15 120 10
Levelling Works (Single Level) m 12.5 100 10
Levelling Works For Multi Levels (Profiling) m 7 56 10
Levelling for Semi Rock Area m 7 56 10
Road Base m 2.5 20 10
Levelling of Black Sand under Inter Lock Tiles m 12.5 100 10
Compaction Works m 100 800 10
PCC Shutter Works ( Raft) m 25 200 10
PCC Shutter Works ( Strip Footing ) m 12.5 100 10
PCC Shutter for Single Footing m 7 56 10
PCC Shutter for Tie Beams ( 400mm - 800mm) m 7 56 10
Backfilling Under Suspended Slab ( No Layers Required) m 13 104 10
Backfilling Under Suspended Slab ( Layers) m 6 48 10
Back Filling Work for Trenches ( With Backhoe ) Lm 10 80 10
Backfilling Works For Manholes Nos 3 24 10
Max. Low.
Company Company
Standard Standard
Remarks
Labour Labour
Rate Rate
(AED/Unit) (AED/Unit)

0.35 0.25
0.63 0.44
33.33 23.33
10.00 7.00
3.33 2.33
0.67 0.47
0.80 0.56
1.43 1.00
1.43 1.00
4.00 2.80
0.80 0.56
0.10 0.07
0.40 0.28
0.80 0.56
1.43 1.00
1.43 1.00
0.77 0.54
1.67 1.17
1.00 0.70
3.33 2.33
Nominal Productivity Rate Table
Water Proofing Work

Max.
Company
Labours
Productivity Rate Standard
Activity Type UNIT Hour Rate
(Unit/Man/Hour) Labour
(AED/Hour)
Rate
(AED/Unit)

Applying Lequid Betumin Water Proofing (Per Coat) m 36 10 0.28


Applying Water Proofing Membrane for Vertical ( Hot Fix) m 7.5 10 1.33

Applying Water Proofing Membrane for Horizontal ( Hot Fix) m 10 10 1.00

Extruded polystreme insulation laid horizontally m 10 10 1.00


Fixing Protection Board for Vertical Surfaces m 5 10 2.00
ANGLE FILLET Lm 10 10 1.00
Foam Concrete m 10 10 1.00
Polystyrene Fixing m 10 10 1.00
Geotextile m 10 10 1.00
ROOF SCREED m 3.5 10 2.86
Low.
Company
Standard
Remarks
Labour
Rate
(AED/Unit)

0.19
0.93

0.70

0.70
1.40
0.70
0.70
0.70
0.70
2.00
Nominal Productivity Rate Table

Kerb Stone and Interlock

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Fixing of Kerb Stone Lm 1 10 10.00 7.00

Fixing Interlock Tiles 1 10 10.00 7.00


Remarks
Nominal Productivity Rate Table
Operations Department Shuttering works
Plywood &
Cup Peri
Paschal Doka
Lock
Productivit Productivit
System Productivi
Activity Type Scope of Work UNIT y Rate y Rate
Productivit ty Rate
(Unit/Man/H (Unit/Man/H
y Rate (Unit/Man
our) our)
(Unit/Man/H /Hour)
our)

Shutter Fabricating, Fixing,


Single Footing Shutter m 0.63 0.90
Applying of Oil Shutter

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Strip Footing Shutter m 0.63 0.91
Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Raft Footing Shutter m 0.63 0.90
Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Plinth Walls from .8m to 1.5m Applying of Oil Shutter,
m 0.63 0.90 1.25
Height Scaffolding is Erected by
others for casting
Nominal Productivity Rate Table
Operations Department Shuttering works
Plywood &
Cup Peri
Paschal Doka
Lock
Productivit Productivit
System Productivi
Activity Type Scope of Work UNIT y Rate y Rate
Productivit ty Rate
(Unit/Man/H (Unit/Man/H
y Rate (Unit/Man
our) our)
(Unit/Man/H /Hour)
our)

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Tie Beams up to .8m Height m 0.35 0.50 0.70
Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (Less Than Applying of Oil Shutter,
m 0.25 0.36
40X40) from 0.2m to 1m Height Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (More Than Applying of Oil Shutter,
m 0.35 0.50
40X40) from 0.2m to 1m Height Scaffolding is Erected by
others for casting
Nominal Productivity Rate Table
Operations Department Shuttering works
Plywood &
Cup Peri
Paschal Doka
Lock
Productivit Productivit
System Productivi
Activity Type Scope of Work UNIT y Rate y Rate
Productivit ty Rate
(Unit/Man/H (Unit/Man/H
y Rate (Unit/Man
our) our)
(Unit/Man/H /Hour)
our)

Shutter Fabricating, Fixing,


Column Necks (Less Than Applying of Oil Shutter,
m 0.25 0.36
40X40) from 1m to 2m Height Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (More Than Applying of Oil Shutter,
m 0.35 0.50
40X40) from 1m to 2m Height Scaffolding is Erected by
others for casting

Shutter Fabricating, Fixing,


Column Necks (Less Than Applying of Oil Shutter,
m 0.45 0.65
40X40) from 2m to 3m Height Scaffolding is Erected by
others for casting
Nominal Productivity Rate Table
Operations Department Shuttering works
Plywood &
Cup Peri
Paschal Doka
Lock
Productivit Productivit
System Productivi
Activity Type Scope of Work UNIT y Rate y Rate
Productivit ty Rate
(Unit/Man/H (Unit/Man/H
y Rate (Unit/Man
our) our)
(Unit/Man/H /Hour)
our)

Shutter Fabricating, Fixing,


Column Necks (More Than Applying of Oil Shutter,
m 0.45 0.65
40X40) from 2m to 3m Height Scaffolding is Erected by
others for casting
Miva
Aluma
Productivi
Productivi
ty Rate
ty Rate
(Unit/Man
(Unit/Man
/Hour)
/Hour)
Miva
Aluma
Productivi
Productivi
ty Rate
ty Rate
(Unit/Man
(Unit/Man
/Hour)
/Hour)
Miva
Aluma
Productivi
Productivi
ty Rate
ty Rate
(Unit/Man
(Unit/Man
/Hour)
/Hour)
Miva
Aluma
Productivi
Productivi
ty Rate
ty Rate
(Unit/Man
(Unit/Man
/Hour)
/Hour)
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Paschal
Doka Peri
Lock
Productivit Productivit
System Productivit
Activity Type Scope of Work UNIT y Rate y Rate
Productivit y Rate
(Unit/Man/ (Unit/Man/
y Rate (Unit/Man/
Hour) Hour)
(Unit/Man/ Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Grouns slab Shutter Shutter, Scaffolding is m 0.35 0.50
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Steps Shutter Shutter, Scaffolding is m 0.35 0.50
Erected by others for
casting
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Paschal
Doka Peri
Lock
Productivit Productivit
System Productivit
Activity Type Scope of Work UNIT y Rate y Rate
Productivit y Rate
(Unit/Man/ (Unit/Man/
y Rate (Unit/Man/
Hour) Hour)
(Unit/Man/ Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Normal Stair Case Shutter Shutter, Scaffolding is m 0.63 0.90
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Decorative Stair Case Shutter, Scaffolding is m 0.35 0.50
Erected by others for
casting
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Paschal
Doka Peri
Lock
Productivit Productivit
System Productivit
Activity Type Scope of Work UNIT y Rate y Rate
Productivit y Rate
(Unit/Man/ (Unit/Man/
y Rate (Unit/Man/
Hour) Hour)
(Unit/Man/ Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Retaining Walls Shutter (Single Side) up
Shutter, Scaffolding is m 0.63 0.90
to 3.5m Height
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Retaining Walls Shutter (Single Erected by others for
m 0.63 0.90
Side)More Than 3.5 3m Height casting, plat forms
used to work at
heigher Level is
produced by Others
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Paschal
Doka Peri
Lock
Productivit Productivit
System Productivit
Activity Type Scope of Work UNIT y Rate y Rate
Productivit y Rate
(Unit/Man/ (Unit/Man/
y Rate (Unit/Man/
Hour) Hour)
(Unit/Man/ Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Retaining Walls Shutter (Double Side)
Shutter, Scaffolding is m 0.63 0.90
up to 3.5m Height
Erected by others for
casting

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Retaining Walls Shutter (Double)More Erected by others for
m 0.63 0.90
Than 3.5 3m Height casting, plat forms
used to work at
heigher Level is
produced by Others
Nominal Productivity Rate Table
Operations Department Shuttering Works

Plywood &
Cup Paschal
Doka Peri
Lock
Productivit Productivit
System Productivit
Activity Type Scope of Work UNIT y Rate y Rate
Productivit y Rate
(Unit/Man/ (Unit/Man/
y Rate (Unit/Man/
Hour) Hour)
(Unit/Man/ Hour)
Hour)

Shutter Fabricating,
Fixing, Applying of Oil
Shutter, Scaffolding is
Columns Shutter (Less Than 40X40) up Erected by others for
m 0.63 0.90
to 3.5m Height casting, plat forms
used to work at
heigher Level is
produced by Others
Aluma Miva
Productivit Productivi
y Rate ty Rate
(Unit/Man/ (Unit/Man/
Hour) Hour)
Aluma Miva
Productivit Productivi
y Rate ty Rate
(Unit/Man/ (Unit/Man/
Hour) Hour)
Aluma Miva
Productivit Productivi
y Rate ty Rate
(Unit/Man/ (Unit/Man/
Hour) Hour)
Aluma Miva
Productivit Productivi
y Rate ty Rate
(Unit/Man/ (Unit/Man/
Hour) Hour)
Aluma Miva
Productivit Productivi
y Rate ty Rate
(Unit/Man/ (Unit/Man/
Hour) Hour)
Nominal Productivity Rate Table

Operations Department Shuttering Works

Plywood & Cup


Paschal Doka Peri
Lock System
Activity Type Scope of Work UNIT Productivity Rate Productivity Rate Productivity Rate
Productivity Rate
(Unit/Man/Hour) (Unit/Man/Hour) (Unit/Man/Hour)
(Unit/Man/Hour)

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Columns Shutter (More Than 40X40) up to 3.5m Scaffolding is Erected by others for m 0.63 0.90
Height casting, plat forms used to work at
heigher Level is produced by Others
Shutter Fabricating, Fixing,
Applying of Oil Shutter,
Columns Shutter (Less Than 40X40) More Than 3.5m Scaffolding is Erected by others for
m 0.63 0.90
Height casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Columns Shutter (More Than 40X40) More Than 3.5m Scaffolding is Erected by others for
m 0.63 0.90
Height casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Walls Shutter up to 3.5m Height Scaffolding is Erected by others for m 0.63 0.90
casting

Shutter Fabricating, Fixing,


Walls Shutter More Than 3.5m Height Applying of Oil Shutter, m 0.63 0.90
Scaffolding is Erected by others for
Shutter Fabricating, Fixing,
casting
Drop Beams Shutter up to 3.5m Height Applying of Oil Shutter, m 0.63 0.90
Scaffolding is Erected by others for
casting
Shutter Fabricating, Fixing,
Drop Beams Shutter More Than 3.5m Height Applying of Oil Shutter, m 0.63 0.90
Scaffolding is Erected by others for
casting Fabricating, Fixing,
Shutter
Applying of Oil Shutter,
Slab shutter up to 3.5m Height ( up to 0.4m Slab Scaffolding is Erected by others for m 0.63 0.90
Thickness) casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Slab shutter up to 3.5m Height (More Than 0.4m Slab Scaffolding is Erected by others for
m 0.31 0.45
Thickness) casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Slab shutter More Than 3.5m Height ( up to 0.4m Slab Scaffolding is Erected by others for
m 0.35 0.50
Thickness) casting
Aluma Miva
Productivity Rate Productivity Rate
(Unit/Man/Hour) (Unit/Man/Hour)
Nominal Productivity Rate Table

Operations Department Shuttering Works

Plywood & Cup


Paschal Doka Peri
Lock System
Activity Type Scope of Work UNIT Productivity Rate Productivity Rate Productivity Rate
Productivity Rate
(Unit/Man/Hour) (Unit/Man/Hour) (Unit/Man/Hour)
(Unit/Man/Hour)

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Slab shutter More Than 3.5m Height (More Than 0.4m Slab Scaffolding is Erected by others
m 0.16 0.23
Thickness) for casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Slab Side Shutter Scaffolding is Erected by others m 0.63 0.90
for casting

Shutter Fabricating, Fixing,


Applying of Oil Shutter,
Deshuttering Works Scaffolding is Erected by others m 3.50 5.04
for casting
Aluma Miva
Productivity Rate Productivity Rate
(Unit/Man/Hour) (Unit/Man/Hour)
Nominal Productivity Rate Table

Operations Department Concrete Works

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Concrete Pouring for PCC 50 mm (Raft and Strip m 0.75 10 13.33 9.33
Footing)
Concrete Pouring for PCC 100 mm (Raft and Strip
m 1 10 10.00 7.00
Footing)
Concrete Pouring for PCC 50 mm (With Shaping) m 0.5 10 20.00 14.00
Concrete Pouring for PCC 100 mm (With Shaping) m 0.65 10 15.38 10.77
Concrete Pouring for PCC 50 mm For Single Footing m 0.6 10 16.67 11.67
Concrete Pouring for PCC 100 mm For Single Footing m 0.9 10 11.11 7.78
Concrete Pouring for PCC 50 mm For Tie Beams m 0.4 10 25.00 17.50
Concrete Pouring for PCC 100 mm For Tie Beams m 0.6 10 16.67 11.67
Concrete Pouring for Single Footing m 2.5 10 4.00 2.80
Concrete Pouring For Strip Footing m 3 10 3.33 2.33
Concrete Pouring For Raft Footing m 4 10 2.50 1.75
Concrete Pouring For Walls m 1.5 10 6.67 4.67
Concrete Pouring For Columns m 1.5 10 6.67 4.67
Concrete Pouring For Slabs m 3 10 3.33 2.33

Cleaning for Slab or Footing Before Casting m 50 10 0.20 0.14


Curing For Walls and Columns (Per Once Per Day) m 100 10 0.10 0.07
Curing for Slabs (Per Once Per Day) m 100 10 0.10 0.07
Laying and Removing of Hessian Cloth m 50 10 0.20 0.14

Concrete Logistics m 20 10 0.50 0.35


Remarks
Nominal Productivity Rate Table
Operations Department Steel Fixing Works

Productivity Rate
Activity Type UNIT
(Unit/Man/Hour)

Steel Fixing for 8mm Kgs 18


Fixing of Rings 8mm Kgs 12
Steel Fixing for 10mm Kgs 20
Fixing of Rings 10mm Kgs 13
Steel Fixing for 12mm Kgs 25
Fixing of Rings 12mm Kgs 17
Steel Fixing for 14mm Kgs 30
Fixing of Rings 14mm Kgs 20
Steel Fixing for 16mm Kgs 35
Fixing of Rings 16mm Kgs 24
Steel Fixing for 20mm Kgs 40
Steel Fixing for 25mm Kgs 60
Steel Fixing for 32mm Kgs 70
Steel Fixing for 40mm Kgs 80

Steel Cut and Bend 8mm Kgs 150


Steel Cut and Bend 10mm Kgs 175
Steel Cut and Bend 12mm Kgs 200
Steel Cut and Bend 14mm Kgs 225
Steel Cut and Bend 16mm Kgs 250
Steel Cut and Bend 20mm Kgs 300
Steel Cut and Bend 25mm Kgs 350
Rings Steel Fabrication 8mm Kgs 50
Rings Steel Fabrication 10mm Kgs 80
Rings Steel Fabrication 12mm Kgs 115
Rings Steel Fabrication 14mm Kgs 155
Rings Steel Fabrication 16mm Kgs 200

Steel Works Logistics Kgs 350


Productivity Rate Table
l Fixing Works

Max. Company Standard Low. Company Standard


Labours Hour Rate
Labour Rate Labour Rate Remarks
(AED/Hour)
(AED/Unit) (AED/Unit)

10 0.56 0.39
10 0.83 0.58
10 0.50 0.35
10 0.77 0.54
10 0.40 0.28
10 0.59 0.41
10 0.33 0.23
10 0.50 0.35
10 0.29 0.20
10 0.42 0.29
10 0.25 0.18
10 0.17 0.12
10 0.14 0.10
10 0.13 0.09

10 0.07 0.05
10 0.06 0.04
10 0.05 0.04
10 0.04 0.03
10 0.04 0.03
10 0.03 0.02
10 0.03 0.02
10 0.20 0.14
10 0.13 0.09
10 0.09 0.06
10 0.06 0.05
10 0.05 0.04

10 0.03 0.02
Nominal Productivity Rate Table
Operations Department Tiling Works

Max. Company
Productivity Rate Labours Hour Rate Standard Labour
Activity Type UNIT productivivty per day
(Unit/Man/Hour) (AED/Hour) Rate
(AED/Unit)

Floor Tiling (Normal)


20X20 m 0.7 5.6 10 14.29
Any Size (Areas Less Than 5 m2) m 0.35 2.8 10 28.57
25X25 m 0.75 6 10 13.33
30X30 m 0.8 6.4 10 12.50
40X40 m 0.85 6.8 10 11.76
50X50 m 0.9 7.2 10 11.11
60X60 m 0.95 7.6 10 10.53
Floor Tiling (45 Degree) 0
20X20 m 0.55 4.4 10 18.18
Any Size (Areas Less Than 5 m2) m 0.3 2.4 10 33.33
25X25 m 0.6 4.8 10 16.67
30X30 m 0.65 5.2 10 15.38
40X40 m 0.7 5.6 10 14.29
50X50 m 0.75 6 10 13.33
60X60 m 0.8 6.4 10 12.50
Wall Tiling 0
20X20 m 0.6 4.8 10 16.67
Any Size (Areas Less Than 10 m2) m 0.3 2.4 10 33.33
25X40 m 0.65 5.2 10 15.38
30X45 m 0.7 5.6 10 14.29
20X50 m 0.75 6 10 13.33
30X60 m 0.8 6.4 10 12.50
Wall Tiling (45 Degree) 0
20X20 m 0.5 4 10 20.00
Any Size (Areas Less Than 10 m2) m 0.25 2 10 40.00
25X40 m 0.55 4.4 10 18.18
30X45 m 0.6 4.8 10 16.67
20X50 m 0.65 5.2 10 15.38
30X60 m 0.65 5.2 10 15.38
Low. Company
Standard Labour
Remarks
Rate
(AED/Unit)

10.00 14.28571
20.00
9.33
8.75
8.24
7.78
7.37

12.73
23.33
11.67
10.77
10.00
9.33
8.75

11.67
23.33
10.77
10.00
9.33
8.75

14.00
28.00
12.73
11.67
10.77
10.77
Trojan Holding Nominal Productivity Rate Table
Operations Department Tiling Works

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Skirting Works
20CM Lm 2 10 5.00 3.50
30CM Lm 2.5 10 4.00 2.80
40CM Lm 3 10 3.33 2.33
50CM Lm 3.5 10 2.86 2.00
60CM Lm 4 10 2.50 1.75

Grouting Works m 5 10 2.00 1.40


Cleaning and Protection Works m 20 10 0.50 0.35
Logistics Works m 10 10 1.00 0.70
Remarks
Nominal Productivity Rate Table
Operations Department Painting Works

Max. Company
Productivity Rate Labours Hour Rate Standard Labour
Activity Type UNIT productivity per day
(Unit/Man/Hour) (AED/Hour) Rate
(AED/Unit)

Ceiling
Primar Application ( Normal Ceiling) m 20 160 10 0.50
Grooves Preperation in the Ceiling Lm 5 40 10 2.00
Grooves Stucoo every coat Lm 5 40 10 2.00
Putty Application ( Single Coat) m 10 80 10 1.00
Putty Application ( Two Coat) m 5 40 10 2.00
Sanding for Second Coat Only m 10 80 10 1.00
Painting First Coat m 20 160 10 0.50
Touchup Beefore Final Coat m 25 200 10 0.40
Painting Final Coat m 16 128 10 0.63
Internal Walls 0
Primar Application m 25 200 10 0.40
Putty Application ( Single Coat) m 12 96 10 0.83
Putty Application ( Two Coat) m 6 48 10 1.67
Sanding for Second Coat Only m 12 96 10 0.83
Touch up Before Final Coat m 30 240 10 0.33
Painting First Coat m 25 200 10 0.40
Painting Final Coat m 20 160 10 0.50
0
External Paint 0
Primar Application m 40 320 10 0.25
GRC and Decorative Items (in each coat) Lm 10 80 10 1.00
Texture Coating (Spray) m 12.5 100 10 0.80
Weather Proof Paint Application Per Coat m 25 200 10 0.40
0
Scaffolding Works m 4 32 10 2.50
Logistics Works m 10 80 10 1.00
Low. Company Standard
Labour Rate Remarks
(AED/Unit)

0.35
1.40
1.40
0.70
1.40
0.70
0.35
0.28
0.44

0.28
0.58
1.17
0.58
0.23
0.28
0.35

0.18
0.70
0.56
0.28
0.4 0.32
1.75
0.70
Nominal Productivity Rate Table
Operations Department Block Works

Max. Company Low. Company


Productivity Rate Labours Hour Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) Rate (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Solid Block 4",6", 8" (Up to 1.5m Height) m 0.6 10 16.67 11.67
Solid Block 4",6", 8" (From 1.5m to 3m Height) m 0.4 10 25.00 17.50
Hollow Block 4",6", 8" (Up to 1.5m Height) m 0.7 10 14.29 10.00
Hollow Block 4",6", 8" (From 1.5m to 3m Height) m 0.5 10 20.00 14.00
Light Weight Block with Glue m 1 10 10.00 7.00

Logistics for Solid Block Works m 2 10 5.00 3.50


Logistics for Hollow Block m 4 10 2.50 1.75
Logistics for Light Weight Blocks m 6 10 1.67 1.17

Block Works Layout with Damp Proof Coarse Lm 2 10 5.00 3.50


Curing for Block Works (Per once Per Day) m 100 10 0.10 0.07
Remarks
Nominal Productivity Rate Table
Operations Department Plaster Works

Max. Company Low. Company


Productivity Rate Labours Hour Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) Rate (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Fixing of Mesh Lm 40 10 0.25 0.18


Fixing of Angles Lm 3 10 3.33 2.33

Making of Plastering Points ( Up to 3m Height) m 10 10 1.00 0.70


Making of Plastering Points ( Above 3m Height) m 6 10 1.67 1.17

Rush Coat ( Up to 3m Height) m 15 10 0.67 0.47


Rush Coat ( Above 3m Height) m 10 10 1.00 0.70

Plaster Filling Continuous ( Up to 3m Height) m 1 10 10.00 7.00


Plaster Filling Continuous ( Above 3m Height) m 0.7 10 14.29 10.00
Plaster Filling with Control Joints ( Up to 3m Height) m 0.75 10 13.33 9.33
Plaster Filling with Control Joints ( Above 3m Height) m 0.5 10 20.00 14.00
Plaster Filling for External Walls ( Up to 3m Height) m 0.75 10 13.33 9.33
Plaster Filling for External Walls ( Above 3m Height) m 0.5 10 20.00 14.00

Plaster Filling For Ceilings ( Up to 3m Height) m 0.625 10 16.00 11.20


Plaster Filling For Ceilings ( Above 3m Height) m 0.45 10 22.22 15.56

Plastering of Decorative Items Lm 1 10 10.00 7.00

Logistics Works Related to Plaster m 10 10 1.00 0.70

Curing for Plaster Works (Per once Per Day) m 100 10 0.10 0.07
Remarks
Nominal Productivity Rate Table
Operations Department Survey Works

Max. Company Low. Company


Productivity Rate Labours Hour Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) Rate (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Level Points Pts 15 27.5 1.83 1.28


Total Station Points Pts 8 27.5 3.44 2.41
GPS Points Pts 20 27.5 1.38 0.96

Stoppage time and Site Requirement PCT -35%


Remarks
Nominal Productivity Rate Table

Operations Department Safety and Scaffolding Works

Max. Company Low. Company


Productivity Rate Labours Hour Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) Rate (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Scaffolding Erection Works m 4 10 2.50 1.75


Scaffolding dismantalling Works m 8 10 1.25 0.88
Edge Protection Lm 4 10 2.50 1.75
Remarks

Including shifting of materials


Nominal Productivity Rate Table
Operations Department Other Works

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Ceiling Joints Between Hollow Core Lm 10 11 1.10 0.77


Walls Joints Between Panels Lm 15 11 0.73 0.51
Cutting for MEP Works in Block Works Lm 5 11 2.20 1.54
Repairing works in Block Works Lm 10 11 1.10 0.77
Coring Works Nos 3 11 3.67 2.57
Angle Fillet in Roof and Wet Aeas Lm 10 11 1.10 0.77
Fixing of Manholes Cover (Any Size) Nos 0.2 11 55.00 38.50
Remarks
Nominal Productivity Rate Table
Operations Department Electrical Works

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Fixing of Sleeves in Walls Nos 3 14 4.67 3.27


Under Ground Conduiting Pts 3 14 4.67 3.27
Conduiting in Slabs Pts 3 14 4.67 3.27
Electrical First Fix in Walls (Block Works) Pts 3 14 4.67 3.27
Electrical First Fix in Walls ( Precast) Pts 2 14 7.00 4.90
Coring works Pts 3 14 4.67 3.27
Conduiting in Slabs ( Topping Works) Pts 2 14 7.00 4.90
DB First Fix Box 0.25 14 56.00 39.20
DB First Fix ( Precast) Box 0.25 14 56.00 39.20
Conduiting works in Corridors ( up to 10 Lm to DB ) Room 1 14 14.00 9.80
Conduiting works in Corridors (more than 10 Lm to DB ) Room 0.5 14 28.00 19.60
Wiring for Lighting Circuit Pts 0.5 14 28.00 19.60
Wiring for Power Circuit Pts 0.5 14 28.00 19.60
Wiring for Data Circuit Pts 0.5 14 28.00 19.60
Wiring from Rooms to DB in corridors (up to 10 Lm to DB ) Room 0.5 14 28.00 19.60
Wiring from Rooms to DB in corridors (More Than 10 Lm to DB ) Room 0.5 14 28.00 19.60
Fixing of Lighting Fixtures Nos 2 14 7.00 4.90
Fixing of Face Plates (switches, Sockets,..etc) Nos 3 14 4.67 3.27
Fixing of Lighting Fixtures with threaded rods Nos 1 14 14.00 9.80
Fixing of Spot Lights Nos 2 14 7.00 4.90
Fixing of Cable Trays Lm 3 14 4.67 3.27
DB Dressing and Termination (16 Circuit Breaker DB) CB 2 14 7.00 4.90
ONU Cable Termination Nos 0.25 14 56.00 39.20
Cables Pulling from external to DB and Between DB`s DB 0.15 14 93.33 65.33
Fixing of Exhaust Fans Nos 0.5 14 28.00 19.60
SMDB Cable Glanding CB 0.25 14 56.00 39.20
Remarks
Nominal Productivity Rate Table
Operations Department Drainage Works

Max. Company Low. Company


Productivity Rate Labours Hour Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) Rate (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Fixing of Sleeves Nos 2 14 7.00 4.90


Installation of Drainage First Fix Under Ground ( In Sand) Pts 1.25 14 11.20 7.84
Installation of Drainage First Fix in Rafts (Inside Concrete) Pts 1 14 14.00 9.80
Installation of Risers in Walls and Shafts Nos 0.5 14 28.00 19.60
Installation of Drainage Second Fix in Wet Areas ( With Connection to
Pts 0.75 14 18.67 13.07
Risers)
Testing of Pipes Pts 1 14 14.00 9.80
Fixing of Sanitary Wares Nos 0.75 14 18.67 13.07
Fixing of Horizontal Piping under Slab ( With Suspension) Pts 0.5 14 28.00 19.60
Fixing of Pumps Nos 0.1 14 140.00 98.00
Fixing of Roof Cowel Nos 3 14 4.67 3.27
Remarks
Nominal Productivity Rate Table
Operations Department Water supply Works

Max. Company
Productivity Rate Labours Hour Rate Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate
(AED/Unit)

Fixing of Sleeves and Main Inlet Nos 3 14 4.67


UnderGround Inlets ( First Fix) Pts 1 14 14.00
PPR Piping Works Hot and Cols Pts 1 14 14.00
Insulation Works For Pipes ( For Hot Water Supply) Pts 2 14 7.00
Fixing of Horizontal Piping to Main Connection (With Suspension
Pts 0.25 14 56.00
Works)
Fixing of Angle Valves Nos 3 14 4.67
Fixing of Gate Valves with Final Connection Nos 1 14 14.00
Fixing of Shower, Mixer , ...etc. Pts 1 14 14.00
Testing of Network Pts 1 14 14.00
Fixing of Electrical Water Heater Nos 0.25 14 56.00
Fixing of Solar Heating System System 0.02 14 700.00
Fixing of Water Tank with Main Connection Nos 0.1 14 140.00
Low. Company
Standard Labour
Remarks
Rate
(AED/Unit)

3.27
9.80
9.80
4.90
39.20
3.27
9.80
9.80
9.80
39.20
490.00
98.00
Nominal Productivity Rate Table
Operations Department AC Works

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Coring in Walls for Main Connection Nos 3 14 4.67 3.27


Fixing of Indoor Units With Copper Pipes Connection Nos 0.5 14 28.00 19.60
Fixing the Copper Pipes Supply and Return Lm 4 14 3.50 2.45
Insulation works for Copper Pipes Lm 4 14 3.50 2.45
Suspension Works For Copper Pipes Lm 4 14 3.50 2.45
Installation of Out Door Unit ( up to 2Tons Unit) Nos 0.5 14 28.00 19.60
Installation of Out Door Unit ( Package up to 20 Tons) Nos 0.03 14 466.67 326.67
Pipes Tray and Protection for on Roof Copper Pipes Lm 1 14 14.00 9.80
Remarks
Nominal Productivity Rate Table
External MEP Works

Operations Department

Max. Company Low. Company


Productivity Rate Labours Hour Rate Standard Labour Standard Labour
Activity Type UNIT
(Unit/Man/Hour) (AED/Hour) Rate Rate
(AED/Unit) (AED/Unit)

Pipes Laying Between Manholes (UPVC) Lm 3 14 4.67 3.27


Cables Laying in Ground Lm 0.25 14 56.00 39.20
Cables Pulling in Manholes Lm 0.1 14 140.00 98.00
Remarks