STANDARD PRODUCTIVITY RATES

(based on 10 hrs per day)

A. For Roads and Drainal:e

1.0 Site Clearance


2
1.1 Grader (14 G) =3150 M /Day
(20 ems thick layer)
3
1.2 Wheel Loader (966) to load (Stock pile within 20M) =1260M /Day
(7 minuter per truck)
1.3 Haulage by Dump Trucks (25tonnes) =110M3/Day
(One way 25 kms) 7 trips
or
1.4 Haulage by Trailer (60 tonnes) =220M3/Day
1.5 Bull Dozer (D8) =893M3/Day
or
1.6 Bull Dozer (D6) =630M3/Day

2.0 Borrow Pi t Excayation (Material Collection)


I

~x Go~:glc -~~--~~~~~~~~~- .;; '*


.'J Search -I- ~ shar.1 More Sign In "

2.0 Borrow Pit Excavation (Material Collection)


~
2.1 Bull Dozer (D8) =893M3!Day
2.2 Wheel Loader (966) =893M3!Day

F 3.0 Borrow Excavation (Haulage & Compaction) (Considering Loose materials)


3.1 Dump Truck (25 tones) =IIOM3!Day
(A verage haul 25 km one way
3.2 Grader (14 g) =630M3!Day
3.3 Water Tanker (4000 GIns) =8400 Glns!Day
2
3.4 Vibratory Roller (25 tones) =2100 M !Day
Average depth (150 mm)
4.0 Sub-Base and Road Base (CoIn.paction) (Considering Loose materials)
4.1 Grader 14 G (150 mm thick layer) =630M3/Day
4.2 Water Tanker (4000 GIns) =8400 GIns/Day
2
4.3 Vibratory Roller (25 tones) =4200M IDay
4.4 PTR Roller (25 tonnes)

5.0 Bituminous Paving (Laying and Compaction)


(based on 42 tonnes/Hr. average production)
.----- ~, 1
~
~ ~ 1l!I1g).
m
_ 1m ~ ~ - - -- _ ----2:25PM--

:!' ~ IIiiI 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
I

~x Go~:glc .'J Search -I- ~ Share I More


-~~------------- .;; '*
Sign In "

5.0 Bituminous Paving (Laying and Comilaction)


(based on 42 tonneslHr. average production)
5.1 Dump Truck =2 hrs/42 tonnes
5.2 Finisher =1/2 hrs/42 tonnes
E
5.3 Water Tanker =1 hr 1 42 tonnes
5.4 Vibratory Roller =2 hrs/42 tonnes
5.5 PTR =2 hrs 142 tonnes

6.0 Prime Coat


2
6.1 Bitumen Tanker (600 GIns) =2625 M /Day

7.0 Interlocking Tiles

,
,;. ~ .
'"- ~ ~ ~ - - - -- - ----2:26PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
~
. .. __
,
h~!,tt
x Go gle Search -I- Si Share I Mor.
. ~t Sign In "

STANDARD PRODUCTIVITY RATES


(based on .10 hrs per day)
7.1 Compactor (INo.) =210 M2/Day E
7.2 Mason (4 Nos.) =10S M2/Day or
7.3 Helper (6 Nos.) =IO.SO M2/Man Day

8.0 Kerb Stones (excluding concrete)


8.1 Mason (2 Nos.) =95 M/Day or
8.2 Helpers (4 Nos.) = 16M/Man Day

9.0 Trench Excavation


3
9.1 Excavator 22S =IS8 M IDay
(Trench width 1.8M and avarage SM depth)
9.2 JCB =74 M3/Day
(Trench width I.OM and average 3M depth)
9.3 Shovel (Loading) =893 M3IDay
9.4 Trench Sheeting after boxing (using excavator) =210 Nos. Day
9.S Boxing for Sheeting (3 to SM depth) =3 Nos.! Day
(With I Welder and 2 Helpers)
Q h "Rark"_Pl-'_Llna ,
III
I

~x Go~:glc .'J Search -I- ~ shar.1 More


-~~------------- .;; '*
Sign In "

(wnn I Welder and '1 Helpers)


9.6 Back Filling
9.6.1 Baby Roller (1 No.) =53M3!Day
9.6.2 Plate Compactor (1 No.)
9.6.3 Water Tanker (4000 Glns) = 0.25 No
E
10.0 Structural Excavation (Open Area)
10.1 Excavator 225 =263M31Day
Dozer D8 =893M3lDay
Shovel 966 =893M31Day
Dump Truck (25 tonnes) =105M3lDay
(25 km Haul)

11.0 Manhole Construction


11.1 Concrete.Pouring =6.50M3lDay
(without pump)
Mason =1 No
Labour =4 Nos.
Vibrator =1 No.

11.2 Formwork
,
,;. ~ .
'"- ~ ~ ~ - - - -- - ----2:27PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
I

~x Go~:glc .'J Search -I- ~ shar.1 More


-~~------------- .;; '*
Sign In "
Y lUJ. 'ILVl 1. .I ~V.

11.2 Formwork

2
11.2.1 Preparation and Forming =13M /Day
Carpenter =2 No
Helper =lNo

Average = (13/6) = 2.10 M2/Man Day


P.S. For circular man holes difficulty factor for preparation and forming to be considered as 0.45

,
~ ~ 1l!I1g)'
'"- ~~~ - - -- - ----2:28PM--
:!' ~ IIiiI 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
(based on 10 hrs per day)
12.0 Laying PipeworkiDuctwork

Pipe Fitters = 2 Nos.


Helpers = 4 Nos.
PIPE SIZE QTY IGANGDA Y
100 mm UPVCIAC Pipes 101 Meters
150 mm UPVCIAC Pipes 95 Meters
200 mm UPVCI AC Pipes 88 Meters
250 lllin UPVCIAC Pipes 82 Meters
300 rnm UPVCI AC Pipes 76 Meters
400 mm AC/GRP Pipes 69 Meters
450 mrn AC/GRP Pipes 63 Meters
500 lllin AC/GRP Pipes 57 Meters
550 rnm AC/GRP Pipes 50 Meters
600 mm AC/GRP Pipes 44 Meters Use of
700 mm AC/GRP Pipes 38 Meters Mobile
800 rnm AC/GRP Pipes 32 Meters Crane
850 rnm AC/GRP Pipes 32 Meters allowed.
I
~ ~: h;*
.'J Search -I- ~
x Go glc
_.
. .., ..................... -_-- '"'_" -- -"r-._,
shar.1 More
~~ _._ . ,.._. .... -.._-- ..... __ ._.... __ .... - lim Sign In "
A

800 mm AC/GRP Pipes 32 Meters Crane


850 mm AC/GRP Pipes 32 Meters allowed.
900 mm AC/GRP Pipes 25 Meters
1000 mm AC/GRP Pipes 19 Meters
1200 rnm AC/GRP Pipes 13 Meters
90,100 mm PVC Ducts 189 Meters
150 mm PVC Ducts 158 Meters 5
B. BUILDINGS

1.0 Excavation and Get Out (ManuaJ).


3
1.1 upto 1.50 M deep =3.70 M IDay/Labour
1.2 upto 2.0 M deep =2.90 M3/Day/Labour
1.3 upto 3.0 M deep =2.10 M3/Day/Labour

2.0 Hand Backfilling and compaction


Plate Compactor =1 No
Labour =3 Nos
21 M3/Day

, I ~ _ _1 _1 1

~ ~ 1l!I1g)' _ 1M ~ ~ - - -- _ ----2:29PM--
:!' ~ IIiiI 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
.J.V IVldl"JJlllC; C;Al"aVaUVll UJ\AUUUJ~ Ul:')VV~i:U

Shovel =1 No.
Trucks =2 Nos.
Labour =6 Nos.
210 M3/Day

4.0 Cutting of Pile Heads


Compressor unit with Jack Hammer =0.5 No.
Labour =3 Nos.

STANDARD PRODUCTIVITY RATES


(based on 10 hrs per day)
3 ..... > 2.50 piles/day
I

~x Go~:glc -~~------------- .;; '*


't Search -I- ~ shar.1 More Sign In "
.).u Concrete Works

5.1 Blinding Concrete (Mixing by us)

Plant =1 No
Mixer machine (14/10) =1 No
Dumper

Labour for Mixing


Mixer Operator =1 No
Labour for Aggregates =2 Nos
Labour for Sand =2 Nos
Labour for Cement =1 No.

Labour for Placing


Labour for Dumper to Trolley =1 No
Labour on Wheel Barrow =3 Nos
Helper for mason =1 No
Mason =2 Nos
Production =16 M3/Day

,
,;. ~ .
'"- ~ ~ ~ - - - --- - ----2:30PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
I

~x Go~:glc ,'J Search -I- ~ shar.1 More


-~~------------- .;; '*
Sign In "

5,2 Blinding Concrete (unsing Ready Mixed Concrete)

Labour for shifting and pouring =6 Nos


Mason =2 Nos
Dumper =1 No.
Production =16 M3/Day

5.3 Concrete for Columns. Walls & Parapet (using Pump)

Labour =3 Nos
Mason =2 Nos
Carpenter =1No
Pump =1 No
Vibrator =1 No
Production =17 M3/Day

5.4 Concrete for columns: Walls & Parapet (without Pump)

Labour for shifting and pouring =6 Nos


Mason =2 Nos
Carpenter =1 No
,
,;. ~ .
'"- ~ ~ ~ - - - -- - ----2:30PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
~t
Search>
Li:lUUUl lUl e
;:'lHllHlt=, i:lllU pUUllll =U l'11U;:'

Mason =2 Nos
Carpenter =1 No
Vibrator =1 No
Dumper =1 No
Production 13 M3IDay

STANDARD PRODUCTIVITY RATES


(based on 10 hrs per day)

5.5 Concrete for beams. slabs and big sections (using prnnp)
I

~x Go~:glc .'J Search -I- ~ shar.1 More


-~~------------- .;; '*
Sign In "

5.5 Concrete for beams. slabs and big sections (using pump)

Labour for signalling =1 No


Labour for pump chute =? Nos
Labour for vibra tors =5 Nos
Labour for concrete spreading =5 Nos
Masons (4+:1) =5 Nos
Carpenters =2 Nos
Steel Fixer =1 No
Scaffolder =1 No
Vibrators =2 Nos
Production 105 M3/4 Hrs

5.6 Form work

6.1 For Foundations and Tie Beams


2
6.1.1 Preparations and Forming 26 M /Day

Carpenter =2 Nos
,
,;. ~ . '"_ 1m ~ ~ - -- --- _ ----2:31PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
I

~x Go~:glc .'J Search -I- ~ shar.1 More


-~~------------- .;; '*
Sign In "

Carpenter =2 Nos
Helper =1 No

2
6.1.2 Fixing. stripping and cleaning 26 M IDay

Carpenter =2 Nos
Helper =1 No

P .S. Average Production Rate of complete operation shall be 4.40 M2/Man Day

6.2 For Columns and Walls


2
6.2.1 Preparation and FOfIning 21 M IDay

Carpenter =2 Nos
Helper =1 No

6.2.2 Fixing, stripping and cleaning 21 M2/Day


r"1,... __ _
,!
,;. ~ . '"_ 1m ~ ~ - -- --- _ ----2:31PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
http://www.scribd.com/doc/48476892fStandard-Productivity-of-pCX

Helper =1 No

P.S. Average Production Rate of complete operation shall be 3.40 M2/Day

STANDARD PRODUCTIVITY RATES


(based on 10 hrs per day)

6.3 For Beams and Slabs


I
~ ~: _~~_____________ h;*
x Go glc .'J Search -I- ~ shar.1 More Sign In "

6.3 For Beams and Slabs

(Based on area 2 x 4 x 4 M2: total forms area 54 M2

6.3.1 Preparation and Forming 57 M2/Day

Carpenter =4 Nos.
Helper =2 Nos.

6.3.2 Fixing. stri12ping and cleaning

Carpenter =4 Nos
Helper =2 Nos

6.3.3 Scaffolding Erection


3
(2 x 4 x 4 x 3.40 M) =107M

Considering Average Production =2.83M3 11.60 Hrs.


,
,;. ~ .
'"- ~ ~ ~ - - - -- - ----2:32PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
I

~ ~: -~~------------- ;;~*
x Go glc .'J Search -I- ~ shar.1 More Sign In "

Scaffolders =5 Nos
Helpers =3 Nos

P.S. A verage Production Rate of complete operation shall be 2.90 M2/Man Day

7.0 Steel Reinforcement


Steel Fixers =3 Nos
Helpers =3 Nos

P.S.
1) A verage production rate for complete operation including
cutting, bending, handling, placing and tying =147 kg/ Man Day

2) Average production rate for handling placing and tying =263 kg/Man Day

8.0 Masonry
Mason =1 No
Helper =1.5 No
2
A verage Production =5.3 M /Man Day
,
,;. ~ .
'"- ~ ~ ~ - - - --- - ----2:32PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
http://www.scribd.com/doc/48476892fStandard-Productivity-of-pCX

9.0 Plaster Works

STANDARD PRODUCTIVITY RATES


~
{based on 10 hrs l2er daYl
9.1 Internal Plaster
Mason =1 No
Helper =2 Nos.
Average Production =6.3 M2/Man Day
9.2 External Plaster
Mason =1 No
Helper =2 No
r. , ,of ,.., ... .-"'" I r-..
'"
I

~x Go~:glc .'J Search -I- ~ shar.1 More


-~~------------- .;; '*
Sign In "
J-\. VCI (1~C r 1VUUl:UVU

")0.0 Screening (Trowel Finish)


Mason =1 No
Helper =2Nos
Production =25 M2/Man Day
= 8.4 M2/Man Day
11.0 Ceramic Tiles
Mason =1 No
Helper =1 No
Production for big size tiles =6.3 M2/Man Day or
3.2 M2/Man Day

Production for small size tiles =4.7 M2IMan Day or


2.4 M2/Man Day

12.0 Terrazo Tiles


Mason =1 No
Helper =1 No
Production =13 M2/Man Day
,
,;. ~ .
'"- ~ ~ ~ - - - --- - ----2:33PM--
:!' ~ 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012
I

~ ~: -~~------------- ;;~*
x Go glc "J Search -I- ~ shar.1 More Sign In "

b,j M./Nlanuay

13.0 vinyl Tiles


Mason =1 No
Helper =1 No
Production =18 M2/Man Day
7.4 M2IMan Day

14.0 Skirtings
Mason =1 No
Helper =1 No
Production =19 M/Day or
9.S M/Man Day

,
~ ~ 1l!I1g)'
'"- ~~~ - - -- - ----2:34PM--
:!' ~ IIiiI 4!!A ~ "" ~ I ~ ..
'II~" 10114/2012