Professional Documents
Culture Documents
PPA Contracting
Regional Meeting on Economics of Nuclear Power, Funding
of Nuclear Power Programmes and Risk Allocation in Nuclear
Power Projects
Nairobi, 10-13 April 2017
3
1. RISK ALLOCATION
4
Power Purchase Agreement (PPA)
5
Key messages
6
Risk allocation via agreement
Commercial
banks
LDs for poor fuel
performance?
Fuel supplier
Loan
Lending in domestic currency?
agreement
Fuel supply
agreement
PPA
Take or pay?
Electricity
Utility
7
Contracting: efficient risk allocation
8
Controllable vs uncontrollable
risks
Regulatory Equipment
delay failure during
SWU price Design
operation
escalation performance
not achieved
Exchange
convertibility
risk Interest rate
Construction
volatility
cost overrun Inadequate Connection
demand risk
Schedule
delay
Change in
Temperature taxation
Exchange of tertiary regime Project Fuel supply
rate volatility intake water becomes interruption
uneconomic
Escalation in
price of
Design
U3O8 price materials
capacity not
escalation
achieved
Controllable Uncontrollable
9
Allocating uncontrollable risks
10
2. POWER PURCHASE
AGREEMENTS
11
Power Purchase Agreement
(PPA)
Contrast investor/lender assurance from
a PPA with that from a direct loan
guarantee
Direct loan guarantees are about reassuring
lenders about the prospect of the project
becoming uneconomic before loans are
repaid
1. Construction cost overruns
2. Post commissioning economics
12
Power Purchase Agreement
(PPA)
Host government guaranteed Power
Purchase Agreement (PPA) is typically
about host assuming market demand risk
Inadequate demand, low prices
Guaranteeing a price (per MWh), quantity, or
both
2. Post commissioning economics
13
Redpoint Energy Study
14
Host Government Backed PPA
15
Financial modelling
Assumptions
Financial modelling is essential to
any NPP procurement process
A financial model consists of a
set of technical and financial
relationships typically a set of
equations in an Excel
spreadsheet Financial
Model
Model takes a set of assumptions
Deterministic or stochastic; typically
includes a price or tariff profile
Produces a set of outputs
Outputs are typically figures
of merit for valuing a project
Outputs
(e.g., IRR on equity)
16
Identifying a strike price
Strike price
Financial modelling is key to
identifying the strike price to
be included in a PPA
Identification of a strike price
(more generally a tariff
structure) is effectively - an
exercise in reverse Financial
engineering Model
1. Specify an IRR that is
appropriate for investors
2. Solve for the price (tariff
or strike price) which
delivers that IRR
IRR
17
A well designed PPA>
Is politically credibleN
Compare strike price to existing wholesale prices
Avoids windfallsN
Gain sharing mechanisms
Is flexibleN
Reopeners
18
A well designed PPA>
19
Takeaways
20
Thank you!