You are on page 1of 18

Type MBCI Relay: Translay S Differential Feeder

and Transformer Feeder Protection

Features Optional Extras MCTH Transformer inrush


current detector
MBCI Pilot wire differential MRTP Supervision relay for ac Allows MBCI to be applied to
protection relay pilot circuits transformer feeders
Blocks operation of the MBCI relay
High stability for through faults Alarm and indication of pilot failure
during transformer inrush conditions
High speed operation for in-zone faults and supervision supply failure
Blocking does not occur for zero,
Simultaneous tripping of relays Suitable for pilot circuits insulated for
normal load, or genuine fault current
at each line end 5kV or 15kV with pilot isolation
transformers
Low current transformer requirements
Application
Low earth fault settings
MVTW Destabilising and The Translay S differential schemes have
Designed for the unit protection of
overhead and underground feeders intertripping relay been designed for the unit protection of
For use with pilot wire relays overhead and underground feeders and
Suitable for pilots up to 1k or 2.5k with
pilot isolation transformers transformer feeders.
Destabilises the feeder protection so
Four electrically separate contacts that tripping occurs
Can be used as definite time overcurrent Intertripping: injects ac voltage into Plain Feeders
relay in the event of pilot failure the pilot circuit so that tripping occurs

Differential protection
Models Available MCRI Instantaneous
Differential feeder protection requires a
overcurrent and start/check
MBCI 01 comparison of the currents entering and
relay
MBCI 02 leaving the protected zone. For faults
High speed operation occurring within the protected feeder it is
Not slowed by dc transients desirable to trip the circuit breakers at each
Wide setting range end to isolate the fault. Two MBCI relays are
Two phase and earth fault relay therefore required, one for each end of the
feeder. A pair of pilot wires is used to
transmit information between the two
relays so that each may be able to
compare the current flowing at its
respective end with the current at the
other.

The relays at both line ends operate


simultaneously, providing rapid fault
clearance irrespective of whether the
fault current is fed from both line ends or
only one line end.

When applying this protection to


overhead lines the limiting factor is
generally the length of the pilot circuits:
MBCI

for cable feeders the limiting factors are


more likely to be the level of line
charging current and the method of
system earthing.

240
Pilot supervision Destabilising/intertripping When the starting feature is used the
overall operation time of the scheme is
Correct interchange of information over When the protected line is connected to
increased by 35ms. However, there is no
the pilot circuit is essential for the proper a busbar system, a fault on the busbars
increase in the overall operation time when
functioning of any differential feeder will in general be cleared by the busbar
the overcurrent protection performs a check
protection. Pilots may be exposed to protection by opening some or all of the
function only.
hazards and some risk of damage and local circuit breakers. Although such
failure always exists. The most common faults will usually appear to the feeder When overcurrent relays are used the
pilot failure is to the open circuit state, protection as through faults, with protection cannot be intertripped by ac
caused by the accidental excavation of resultant stability of the feeder injection into the pilots, and destabilising
buried pilots or storm damage to protection, it may be desirable to open the protection will result in tripping only if
overhead pilots. With the pilots open the remote line circuit breaker also, to an overcurrent condition exists
circuited the differential protection will be clear the line completely. The remote unit simultaneously.
unstable and will trip the feeder if of the differential feeder protection can
sufficient through current is flowing. be caused to operate, provided sufficient
Emergency use for overcurrent
line current is flowing, by open circuiting
For this reason the circulating current protection
the pilots. If line current is not flowing,
system is often preferred as such schemes
the remote unit can be operated In the event of a pilot failure which
will fail safe and trip so that attention is
(intertripped) by injecting a current into cannot quickly be rectified, the Translay
immediately drawn to the fault.
the pilots. S scheme may be adapted for use as a
The addition of pilot supervision will not definite time overcurrent relay as follows:
prevent tripping for pilot faults but will
Overcurrent check/starting
indicate the cause. It will also detect
short circuit and cross-connected pilot
If overcurrent relay is fitted
Although the supervision scheme provides
conditions which would not otherwise be indication of pilot failure it does not disconnect pilot wires and leave
detected. Indication is also provided for prevent the protection operating if primary terminals open circuited
loss of the supervision supply. current above setting is flowing. Where
set Kt to 3(300ms)
this hazard is unacceptable it is necessary
to add an overcurrent check feature. check that overcurrent elements are on
the required setting above maximum
The current transformer requirements are
anticipated load current.
not modified by the addition of
overcurrent elements since they present a
very low burden. If overcurrent relay is not
fitted
disconnect pilot wires and connect a
1k resistor across pilot terminals of
relay

set padding resistors Rpp to maximum


A (600)
B set Kt to 3 (300ms)
C
set Ks to required open circuit setting:
Ks = 1 gives three phase equal to
Trip Trip
Rpp Rpp rated load In.
T2 T2
T1 Tr Tr T1 Note: Other fault settings will depend
Rs Tt c c Rs upon the summation ratio.
To To
Pilot wires

Ts RVD Ro Ro RVD
V V
MBCI

T1 - Summation transformer To - Operating winding Rpp - Pilots padding resistor Figure 1:


T2 - Auxiliary transformer Tr - Restraining winding c - Phase comparator
Basic circuit arrangement
RVD - Non linear resistor Tr - Tertiary winding
Ts - Secondary winding Ro - Linear resistor

241
Protected Zone Protected Zone
P1 P2 P2 P1
A
S1 S2 S2 S1
B
C

12
See
RS Note 5 RS
MBCI 13 + MBCI
Power
23 Supply VX
Circuits 14
IA
See
Note 4
24
25
& Enable 11
See
23
24 IA
Squarer Kt 1
IB
RL1
2 Note 2 25
RL11 3
26
5 26 IB
27 Enable
A 27
IC 2
Level RL2 28 IC
IN 28 2 RL12 4
C B Detector 6 IN
Phase OP
Trip/
&
RL3
Rotation 1 Alarm
KS RES 7
RO Outputs
RL21 9
Squarer
Case Earth
See Note 3 8
Case earth
RL22
1 2
3 4
10
RPP 17
5 6
7 8
9 10 18 Pilot
11 12
Wires
13 14 19
15 16
17 18
Notes
19 20
1. (a) C.T. shorting links make before (b) & (c) disconnect. 3. Earthing connections are typical only.
21 22 Module
23 24 terminal block (b) Short terminals break before (c) 4. C.T. connections are typical only.
25 26
viewed from (c) Long terminal. 5. For overcurrent start schemes, terminal 12 must be
rear connected directly to D.C. +VE to provide a supply for
27 28
2. Link terminals 11 and 13 except when used with overcurrent the L.E.D. and reset circuits.
check replay type MCRI.

Figure 2 Application diagram: differential feeder protection relay type MBCI

17 17

MBCI Pilots MBCI

18 18
17 18 17 18
19

Case 20
Earth MRTP02

20
RL2 OP RL7
2 1 Supply
19 Reset
Fail
A.C. 27 OP
A.C. RL1 RL3 RL6 1
Auxiliary 2 2 1 Pilot
28 Power Reset RL41 3
Supply Supply S/C Output
13 OP RL8
5 Contacts
D.C. Reset 1 Pilot 2 Change
Case earth Vx 14 Power O/C RL42 4 state for
Supply
1 2 RL4 6 pilot fail
3 4 2
7
5 6
RL51 9 Output
7 8
9 10 11
Contacts
11 12
MRTP01 Change
8
13 14 +VE
RL5 state for
2 RL52 10
supply
15 16
RL1 RL2 RL3 RL1 RL2 RL3 12
17 18 Case fail
1 1 1 Start 2 2 2
19 20
Earth t
21 22
23 24
MBCI

25 26 Module terminal block Note 1.


27 28
viewed from rear (a) C.T. shorting links make before (b) & (c) disconnect.
(b) Short terminals break before (c).
(c) Long terminal.

Figure 3 Application diagram: pilot supervision relay and injection filter type MRTP 01

242
Pilot isolation Pilot isolation
transformer transformer
P6 S2 S1 P1
17 17
P5
P4 X2 X1
P3
P2
MBCI Pilots MBCI
P2
X2 P3
X1 P4
P1 S1 S2 P5
18 18
P6
S1 S2 Supervision
isolation
P1 P2 transformer

20 OP
RL2 RL7
2 1 Supply
19 Reset See
Fail
A.C. 27 OP Note 7
A.C. RL1 RL3 RL6 1
Auxiliary 2 2 1 Pilot
28 Power Reset RL41 3
Supply Supply S/C Output
13 OP RL8
5 Contacts
D.C. Reset 1 Pilot 2 Change
Vx 14 Power O/C RL42 4 state for
Case earth Supply
RL4 6 pilot fail
1 2 2
3 4
7
RL51 9
Output
5 6
Contacts
7 8 11
9 10 MRTP 03 Change
8
11 12 +VE
RL5 state for
13 14
2 RL52 10
supply
16
RL1 RL2 RL3 RL1 RL2 RL3 12 fail
15 Case 1 1 1 Start 2 2 2
17 18
Earth t
19 20
21 22
23 24 Note 1.
25 26
(a) C.T. shorting links make before (b) & (c) disconnect.
27 28
Module terminal block (b) Short terminals break before (c).
viewed from rear (c) Long terminal.

Figure 4 Application diagram: pilot supervision relay 15kV isolation type MRTP 03

P1 P2
A A
S1 S2
B
C C B +
D.C. _
See Phase
Note 4 Rs Rotation
See Note 2(B)

13 See Note
Power 23 11
2(A)
supply 24
14 13
23 circuits 25
IS (A) 26 14
27
Case earth 24 28
1 2
25
3 4 IS ( ) RL1
5 6 2 5
26 RL11 1 MBCI
7 8
27 3
9 10
IS (C)
11 12 6
13 14 RL12 2
28
15 16 Case earth MCRI 4
17 18 See Note 3
19 20
Case earth
21 22
See Note 3
23 24 Notes
MBCI

25 26
1. (a) C.T. shorting links make before (b) & (c) disconnect. 2. (A) Connection for overcurrent start
27 28
Module terminal block (b) Short terminals break before (c). (B) Connection for overcurrent check
viewed from rear (c) Long terminals. 3. Earthing connections are typical only
4. C.T. connections are typical only

Figure 5 Application diagram: overcurrent relay type MCRI 01

243
Transformer Feeders (use Scheme Pilot Supervision O/C
of transformer inrush Insulation Start/Check Arrangement of Equipment
Level (kV) (Viewed from front)
current detector)
In the case of transformer feeders where A 5kV 1 1

there is no circuit breaker separating the


B 15kV 1 1
transformer from the feeder, the
phenomenon of transformer magnetising
C 5kV 2 1 3 1
inrush must be considered. This is a
transient condition which may occur at 4 1 1
D 15kV
the instant of transformer energisation, or
immediately following a system voltage E 5kV 1 5 1 5
drop due to a nearby heavy fault
condition. Magnetising inrush current is F 15kV 1 5 1 5

not a fault condition and therefore does


G 5kV 2 1 5 3 1 5
not necessitate the operation of
protection equipment which, on the
H 15kV 4 1 5 1 5
contrary, must remain stable during the
inrush transient. The inclusion of a type
Table 1. Typical scheme arragements for plain feeders. See key below.
MCTH relay, designed to provide a
blocking signal in the presence of
Scheme Pilot Supervision Transformer
transformer inrush currents, enables a Insulation Arrangement Arrangement of Equipment
pilot wire differential protection scheme Level (kV) (Viewed from front)
to be applied to a transformer feeder. Pilots
I 5kV
Where line and therefore transformer 1 8 9 7 1 8

energisation can occur at one end only


J 15kV 1 8 9 7 1 8
of the transformer feeder, then a MCTH
unit would be required on that side only. K 5kV 1 8 2 9 7 1 8 3

When the feeder transformer is


1 8 4 9 7 1 8
energised any resulting inrush current L 15kV
will be detected by the MCTH relay, the
M 5kV 1 8 1 8
output blocking unit of which will pick-up
causing the pilot wires of the Translay S
N 15kV 1 8 1 8
to be short-circuited. This will stabilise
the differential relay and prevent it from O 5kV 1 8 2 1 8 3
responding to what would otherwise
appear to be an in-zone fault. The P 15kV 1 8 4 1 8

immunity to operation due to inrush


current is coupled with fast fault Table 2. Typical scheme arragements for transformer feeders. See key below.
clearance times and the built-in
No. Type of relay
overcurrent detectors of the MCTH relay
ensure that the blocking feature is 1 MBCI 01/02 Differential
overridden if a fault is detected in one 2 MRTP 01 Pilot supervision and injection filter
phase whilst inrush is present in another. 3 MRTP 02 Injection filter
4 MRTP 03 Pilot supervision
5 MCRI 01 Overcurrent start/check
Symbols: 6 MVTW 01 Destabilising
7 MVTW 03 Destabilising and Intertripping
Schemes A to D can be fitted with relay types 6 or 7.
15kV Isolating transformer Schemes E to H can be fitted with type 6 which will provide
destabilising if the overcurrent start/check relays (MCRI 01) have
operated. Schemes I to L must use type 7 or 8.
8 MCTH 01 Transformer inrush current detector
MBCI

15kV Isolating transformer


9 MFAC 14 High impedance earth fault relay
with injection filter
10 MMLG Test plug/block
It is advisable on all schemes to include the test unit to facilitate
commissioning and routine testing. The unit will be situated on the
righthand side of the scheme.

244
Description The phase comparator has angular limits Figure 4 shows the similar arrangement
of 90 giving a circular bias for pilot circuits insulated for 15kV (Type
characteristic in the complex plane. If the MRTP 03).
Differential protection pilots are open circuited, current input will
The injection filters are then assembled
The differential feeder protection circuit tend to operate the relay. Conversely,
as part of the isolation transformer and
is derived from the well known Merz- short-circuited pilots will cause the relay to
have to be isolated from the supervision
Price circulating current system but restrain, holding its contacts open.
relay. The supervision isolation
employs phase comparators as the Transformers T1 and T2 also provide the transformer provides the necessary 15kV
measuring elements. This novel
necessary insulation barriers for static isolation barrier. For further technical
combination provides high stability
circuitry. The input circuits of the phase information see Publication R6026.
performance for external faults with the
comparator are tuned to the power
minimum of bias (restraint) quantity
frequency so that the threshold of
thereby ensuring that the low earth fault
operation increases with frequency. This Destabilise and Intertrip
settings are effectively retained even
when load current is flowing. Figure 1 de-sensitises the relay to the transient Facilities
shows the basic circuit arrangement. A high frequency charging current that
summation current transformer T1 at flows into the line when it is energised.
each line end produces a single phase A further advantage provided by the MVTW01
current proportional to the summated tuned input is that the waveform of the
Refer to Figure 6.
three phase currents in the protected derived signal, which may be severely
line. The neutral section of the distorted by current transformer Operation of the destabilising relay (UN)
summation winding is tapped to provide saturation, is improved, ensuring high results in the summation current
alternative sensitivities for earth faults. speed operation under adverse transformer in the differential relay
conditions. In order to maintain the bias being short circuited and the local relay
The secondary winding supplies current
characteristic at the designed value it is prevented from tripping. The remote
to the relay and the pilot circuit in
necessary to pad the pilot loop relay then sees a single end feed
parallel with a non-linear resistor (RVD).
The non-linear resistor can be resistance to 1k. condition and trips, provided the through
considered to be nonconducting at load current exceeds the no-load fault setting
A padding resistor Rpp is provided in
current levels. Under heavy fault of the protection (see Table 5 page 18).
the relay for this purpose.
conditions it conducts an increasing Typical operating times are shown in
current and thereby limits the maximum Figure 7.
secondary voltage. At normal current Pilot isolation transformers Terminals 17 and 20 should normally be
levels the secondary current flows
When pilot isolation transformers are linked together on the destabilising relay.
through the operating winding To on
used, the range of primary taps enables However, the operating level of the
transformer T2 and then divides into two
pilots of loop resistance up to 2.5k to remote equipment can be reduced to
separate paths, one through Ro and the
be matched to the relay. The pilot one half of the normal fault setting
other through the restraint winding Tr of
T2, the pilot circuit and resistor Ro of the insulation level is also raised to 15kV by (under destabilising operation only) if
remote relay. these transformers. this link is omitted.

The resultant of the currents flowing in Tr It should be noted that, with this link
and To is delivered by the third winding omitted, if the destabilising relay UN is
Telephone type pilots
on T2 to the phase comparator and is operated for longer than the supervision
compared with the voltage across Tt of When the pilots to be used are of the time delay (6-10 seconds) an indication
Transformer T1. The emf developed telephone type, an alternative limiter of pilot failure will be given. This does
across Tt is in phase with that across the based on a zener diode is available to not apply if pilot isolating transformers
secondary winding Ts which is in turn ensure that the maximum voltage which are used.
substantially the voltage across Ro. can appear on the pilot system is within
When overcurrent elements are used to
prescribed limits. Pilot isolating
Taking into account the relative values of provide a starting or check function there
transformers can be used in this
winding ratios and circuit resistance is no advantage in removing this link
arrangement also, both to provide
values, it can be shown that the since, for operation, the through current
quantities delivered for comparison in insulation to 15kV and also indirectly to
must exceed the overcurrent setting.
phase are: enable pilots of relatively high resistance
to be used.
(IX + 2IY) and (2IX + IY)
MVTW 03
where IX and IY are the currents fed into
Pilot supervision A circuit diagram for the MVTW 03 type
the line at each end (for through faults
relay which depicts the destabilising,
IX=IY). The expressions are of opposite Figure 3 shows the arrangement for pilot
intertrip and inverter function is shown in
MBCI

sign for values of IY which are negative supervision in a pilot circuit insulated for
relative to IX and are between 0.5IX and Figure 8. On energising the relay, a
5kV. In this instance the injection filters
2IX in value. The system is stable with this green LED illuminates and the normally
and the supervision unit are assembled
relative polarity and operates for all closed contacts of RL1 open to indicate
with the relay case. (Types MRTP
values of IY outside the limits. the supply is healthy and the inverter is
01/02).
operating.

245
The MVTW 03 incorporates a full bridge A typical scheme for a deltastar power A high impedance differential relay
inverter, which receives complementary transformer is shown in Figure 9. The (type MFAC 14) is included in the
square wave signals from the oscillator line current transformers are connected neutral lead of the star-connected line
circuit at a frequency of 80Hz. This in star on the delta side of the transformers to give lower earth fault
frequency was chosen because it lies transformer. Appropriate choice of CT settings on the delta side of the power
sufficiently far from the pilot frequency of ratios ensures that for normal load and transformer. The MFAC 14 high
50 or 60Hz and cancellation of the through fault conditions, equal currents impedance differential relay may be
intertripping signal will not be caused by flow into the differential tripping units used to initiate an intertrip unit
the beat frequency that may be produced. (MBCI) at each end. (type MVTW 02).
The inverter is continually energised and
supplies a transformer which isolates the
pilots to 5kV from the input circuits. The
transformer supplies the intertripping Pilot isolation transformer P6
17 S2
current and the power supply for the
output relay (RL2). Pilots
P1 S1
Intertripping is initiated by applying a
MBCI
trip signal to terminal 11 which
energises the output relay. 17 UN-1

The signal is isolated from the pilots to 18


5kV by the opto isolator. When the 18 UN-2
19
output relay (RL2) is operated, the local 19
UN-3
MBCI is made stable by shorting
20
terminal 18 to terminal 19. This action Case earth
destabilises the remote MBCI. If the load 1 2
11 UN
current level is greater than the 3 4 Vx(1)+ 3
5 6 12
Vx(2)+
differential current setting the remote 7 8 13
Vx(3)+
MBCI trips; however if the current level is 9 10 14
11 12
lower than the setting the remote MBCI 13 14
does not trip. To ensure intertripping 15 16 MVTW 01
17 18
occurs the output relay (RL2) injects a
Notes
20mA intertrip current into the pilots; the 19 20
Case earth
21 22 CT shorting links make
remote MBCI sees the intertrip current as 1. (a)
23 24 See note 2
before (b) & (c) disconnect
a differential current which causes it to 25 26
(b) Short terminals break before (c)
27 28
trip. Module terminal block (c) Long terminals
viewed from rear
For further technical information see 2. Earthing connections are typical only
Publication R6027.

Figure 6 Application diagram: destabilising relay type MVTW 01


Transformer Inrush Current
Blocking

Transformer inrush current


detector feature
200
Refer to Figure 9.
The principle of operation of the
transformer inrush current detector 160
(MCTH) is based upon a unique feature
of substantially zero for significant
periods in each cycle. During load or 120.
Milliseconds

fault conditions, the current waveform


remains at zero for negligible periods in Kt = 6
80
each cycle. The relay detects these zero Kt = 14
periods in the inrush waveform and
Kt = 20
initiates a blocking relay, which causes 40 Kt = 40
the pilot wires of the Translay S relay to
be short-circuited, preventing tripping for
MBCI

transformer inrush current. 0


1 2 3 4 5 6 7 8 9 10 20 30 40 50 80
Current - Multiple of setting

Figure 7 Time characteristic for destabilised operation

246
Figure 8 Destabilising and intertripping relay type MVTW 03

Pilot isolation transformer P6 S2


17
Pilots
P1 S1
MBCI
17

18
18
19
19
11+VE
Trip send
Case earth RL2
2
1 2 RL2-2
3 4
5 6
7 8
9 10 RL2-1
11 12 13+VE
13 14 RL1-1 1
Power
15 16 Vx RL1
2 Supply fail
14VE supply 1
17 18 MVTW 03
19 20
Supply
21 22
23 Case earth See note 2 healthy
24
25 26
27 28 Notes
1. (a) CT shorting links make 2. Earthing connections as shown is typical only
before (b) & (c) disconnect
Module terminal block
(b) Short terminals break before (c)
viewed from rear
(c) Long terminals

Figure 9 Typical application diagram: overall protection of transformer feeders

P2 P2 P1
A I i A
S1 S2 S2 S1
B II ii B

C III iii C
yn

N.E.R.

23 MCTH MCTH 23
24 24
17 17
25 25
26 26
19 19
27 27
28 28

23 MBCI 17 17 MBCI 23
24 24
25 Pilots 25
26 26
27 18 18 17 18 27
28 19 19 28
MVTW03

MFAC14 1
27
MBCI

RVD3 3
28 11

Note1: It is essential that the current transformer connections are earthed at one point only.

247
200 Metrosil
Figure 11 Limiter
Pilot voltage characteristics
160

Pilot Voltage (V Peak)


120

Zener
80
Limiter

40

0 1 0 20 30
A-N fault current (x In)

Figure 10: Current circuit burden

N = 6 AN 2.0
15 3

1.8
Voltage across summation current transformer primary volts 1A relay

N = 6 CN
Factor by which setting is increased

Without 15 kV pilot isolating trans.


With 15 kV pilot isolating trans. (Ks = 1.0 or 2.0)
Voltage across summation current transformer primary volts

N = 3 AN With 15 kV pilot isolating trans. (Ks = 0.5)


(Note: Pilot isolating transformer ratio = 1:1)
1.6
10 2

1.4

N = 3 BN 1.2
5 1

AC
1.0
0 1 2 3 4 5
Pilot intercore capacitance -mF
AB

Figure 12 Effect of pilot capacitance and pilot isolating transformers on setting


1 2 1A relay
0
5 10 5A relay
Current in summation current transformer primary Amps

%In %In A-N


Earth Fault Setting 70 Earth Fault Setting
Ks = 2.0 Ks = 1.0
N=3 N=6 N=3 N=6
60
C-N
A-N B-N
100 50
A-N
C-N
80 40
B-N
A-N B-N
60 30
C-N C-N
B-N
40 20
MBCI

20 10

Figure 13
0 0.5 1.0 1.5 2.0 0 0.5 1.0 1.5 2.0
Minimum earth fault current for Through Load (xIn) Through Load (xIn)
operation with through load

248
240

200

CTs

Operation time (Milliseconds)


CTs 160

120

RL RL RL
80 Kt = 6
Kt = 14
40 Kt = 20
Kt = 40

CTs 0
1 2 3 4 5 6 10 20 30 40 50 60 80 100
Current (multiples of setting)

Figure 15 Time characteristics for internal faults


End A End B
Pilots
Relay Relay

Figure 14 Mesh type switchgear arrangements

60
Induced pilot loop voltage to operate

40
Figure 16
Response to spurious
induced loop voltage in pilots
20

0
0.5 1.0 1.5 2.0
Setting multiplier Ks

Transformer (Dy 11)

Feeder Figure 17

Overall protection of transformer feeders


showing connections to MBCI relay

Delta Star
23 25 27 17 17 23 25 27
MFAC N.E.R.
MCTH MCTH
inrush A B C REF inrush A B C
detector detector
24 26 28 19 19 24 26 28

MBCI MBCI

23 23
MBCI

25 1.25 17 17 1.25 25
27 1 1 27

24 6 6 24
18 Pilots 18
26 26
28 28

249
Technical Data Durability AC ripple on dc supply
(MBCI Relay) Loaded contact IEC 60255-11: 1979
10,000 operations minimum The unit will withstand 12% ac ripple on
the dc supply.
Current rating (In) Unloaded contact
100,000 operations minimum High frequency disturbance
1A, 2A or 5A
IEC 60255-22-1: 1988 Class III
Reset time 2.5kV peak between independent
Frequency rating
circuits and case.
Less than 100ms
50Hz or 60Hz
1.0kV peak across terminals of the same
circuit.
Indication
Current withstand ratings
Fast transient disturbance
A non-volatile LED trip indicator is used.
Duration (s) Differential
If the auxiliary supply is lost the LED will IEC 60255-22-4: 1992 Class IV
Continuous 2In
return to the same state when the supply 4.0kV, 2.5kHz applied directly to
3 45In
is restored. auxiliary supply.
2 55In
1 80In IEC 60801-4: 1988 Level 4 4.0kV,
0.5 100In Stability level 2.5kHz applied to all inputs.
Table 2
The stability of the protection for through Surge immunity
faults is greater than 50In
IEC 61000-4-5: 1995 Level 3
Current circuit burden
2.0kV peak, 1.2/50ms between all
Highest phase burden High voltage withstand groups and case earth.
(with three phase rated current)
Dielectric withstand 2.0kV peak, 1.2/5-ms between
6VA N=6
terminals of each group.
3.5VA N = 3 IEC 60255-5: 1977
At setting current 0.5VA 2.0kV rms for 1 minute between all EMC compliance
terminals and case earth. 89/336/EEC
Auxiliary supply 2.0kV rms for 1 minute between all Compliance to the European
terminals of independent circuits, with Commission Directive on EMC is claimed
Rated Operative Current drain (mA)
terminals on each independent circuit via the Technical Construction File route.
voltage (Vx) range (V) Quiescent Operated
connected together. EN 50082-2: 1994
24/27 19.232.4 30 17.5
30/34 2437.5 15 175 5.0kV rms for 1 minute between pilot EN 50082-2: 1995
48/54 37.672 15 175 terminals and all other terminals and Generic Standards were used to
110/125 87.5150 15 90 case earth. establish conformity.

1.0kV rms for 1 minute across normally Product safety


Contacts open contacts. 73/23/EEC
Contact arrangements High voltage impulse Compliance with the European
2 make and 2 change-over Commission Low Voltage Directive.
IEC 60255-5: 1977
(See Figure 2) EN 61010-1: 1993/A2: 1995
Three positive and three negative
impulses of 5.0kV peak, 1.2/50s, 0.5J EN 60950: 1992/A11: 1997
Contact ratings between all terminals and all terminals Compliance is demonstrated by
and case earth. reference to generic safety standards.
Make and carry for 0.2s 7500VA
subject to maxima of 30A and 300V
ac or dc Electrical environment Atmospheric environment

Carry continuously DC supply interruption Temperature


5A ac or dc IEC 60255-6: 1988
IEC 60255-11: 1979
MBCI

Break The unit will withstand a 10ms Storage and transit 25C to +70C
ac 1250VA interruption in the auxiliary supply, Operating
dc 50W resistive under normal operating conditions, 25C to +55C
25W inductive without de-energising. IEC 60068-2-1: 1990 Cold
L/R = 0.045s
subject to maxima of 5A and 300V IEC 60068-2-2: 1974 Dry heat

250
Humidity Pilot voltage Line charging current
IEC 60068-2-3: 1969 The voltage applied across the pilots In applications pertaining to cables, with
56 days at 93% RH and 40C varies with fault current as shown in or without in zone shunt reactors, and
Figure 12. For normal through load overhead lines, it is necessary for the
Enclosure protection
conditions the peak pilot voltage will be most sensitive fault setting to be
IEC 60529: 1989 in the order of 50V rising to a maximum increased to:
IP50 (dust protected) of: 200V for MBCI 01, 80V for MBCI 02
1.1 times the steady state line
Mechanical environment under fault conditions.
charging current for solidly earthed
Vibration When pilot isolation transformers are systems
IEC 60255-21-1: 1988 used this value of voltage is multiplied by
3.2 times the steady state line
Response Class 1 KM .
charging current for resistance earthed
Note: Types MBCI 01 and 02 are not systems
compatible. Relays should be of
Pilots 1.9 times the steady state line
the same type at either end.
charging current for resistance earthed
systems with one relay per phase
Pilots isolation
Pilot current
In all cases, allowance should be made
Pilot isolation transformers are required
The pilot current is typically 30mA for for some system overvoltage.
when any longitudinally induced voltage
normal through load conditions and This requirement ensures stability during
in the pilot circuit is likely to exceed 5kV:
rises to a maximum of 300mA under external ground faults which will cause
in effect this means when protecting
through fault conditions. the three phase capacitance currents to
feeders operating at voltages in excess
be unequal, resulting in an increased
of 33kV, unless these are short in length.
output from the summation transformer.
The use of pilot isolation transformers
The high frequency line in-rush currents
also extends the acceptable range of
can be neglected because the setting of
pilots. This is achieved by the matching
the relay automatically increases at high
ratios available as shown in Table 4.
frequencies by a factor:
Inrush frequency
Pilots Rated system frequency

KM 0.8 1.0 1.2 1.5 2.5 Matching ratio

Loop resistance 800 1000 1200 1500 2500


Capacitance 6.25 5 4.2 3.3 2 F
Terminals P1-P6 P1-P5 P1-P4 P1-P3 P1-P2

Table 4

Where KM = (turns ratio)2 for respective tap of pilot isolation transformers.

When pilot isolation transformers are not used KM = 1.

The optimum value for KM is the nearest value Rp/1000 in Table 4, where Rp is the
measured pilot loop resistance.

There are two types of pilot isolation transformers: ZC0244-002 for schemes without
pilot supervision: HN0068-001 for schemes with pilot supervision. The latter includes
the injection filter for the pilot supervision circuit.

The pilot padding resistor (Rpp) at each end should be set to:

1/2(1000 Rp/KM)
MBCI

251
Overcurrent starter/check Unit Protection of Plain Minimum operation for earth
element settings Feeders faults with through load
The maximum resetting value of the Bias being a direct function of through
overcurrent elements is not less than 90% Fault settings for plain feeders current, increases minimum operating
of the operating value. Thus, to ensure current with through load. Figure 14
that they will reset when the current is The input transformer has a summation shows the minimum earth fault current
restored to the full load level, the setting ratio of 1.25:1:N where N = 3 for required for various levels of through
should be at least 1.2 times the normal use. N = 6 is used where low load.
maximum anticipated through load earth fault settings are needed. The
minimum operating current will therefore The curves shown are for the first relay to
current.
be dependent on the phase or phases trip. The second relay will trip sequentially
The setting of the earth fault elements involved in the fault. The minimum earth provided the resulting in-feed at that end
should be at least 1.2 times any fault current (If) should be greater than is above the setting value. To ensure that
standing zero sequence current and not twice the least sensitive earth fault setting simultaneous tripping will occur the
higher than 80% of the minimum earth to ensure rapid fault clearance. minimum fault current should be greater
fault current. than twice the minimum operating current
The range setting of fault settings is given in Figure 14.
The value chosen as an assessment of shown in Table 5.
minimum earth fault current must be
conservative, due allowance being made Line current transformer
for all aspects of minimum system requirements for plain feeders
operating conditions and fault
Class X BS 3938
impedance; alternatively, a larger
tolerance below the nominal minimum VK 0.5N Kt In (RCT + XRL)
fault current value is advisable.
Where

Differential Fault Settings VK = knee point voltage of current


(Summation ratio = 1.25/1/N) N=3 N=6 transformers for through fault
stability
Ks is a setting multiplier AN 0.19Ks.In 0.12Ks.In
and may be varied BN 0.25Ks.In 0.14Ks.In RCT = resistance of current transformer
from 0.5-2.0 CN 0.33Ks.In 0.17Ks.In secondary circuit ()
In is the rated relay current AB 0.8Ks.In RL = lead resistance of single lead
BC 1.0Ks.In from relay to current
CA 0.44Ks.In transformers ()
ABC 0.5Ks.In
X = 1 for 4 wire connections
between the main current
Table 5
transformers and the relay: 2
for 6 wire connections
The minimum operating current of the N = relative neutral turns on
relay will be increased by any shunt summation transformer winding
impedance connected across the pilot (3 or 6, as shown under
wires, for example, pilot capacitance heading Current Settings)
and the magnetising path of the pilot
isolation transformers. The effect of the Kt = the selected time-dependent
pilot capacitance is shown in Figure 12. constant (40, 20, 14, 6 or 3)

Values of Ks from 0.5 to 1.0 are *Note; For all applications at or above
provided to achieve effective fault 220kV where X/R ratios are
setting equal to the nominal value large use:
indicated in Table 5. This is achieved by VK N Kt In (RCT + XRL)
single end injection tests during
commissioning. Values of Ks from 1.0 to
MBCI

2.0 are used to increase the setting


when the application demands. Refer to
section: Line charging current.

252
It is not necessary for the line current The operation time varies with fault Small in-zone teed loads
transformers at the two ends of the current as shown in Figure 16. Stability
Small three phase loads may be
protected system to have the same knee is maintained with smaller current
connected to the feeder within the
point voltage. Differences of up to 4:1 transformers if the value of Kt is reduced.
protected zone; normally these will be
can be tolerated provided both are
This will of course result in the operation supplied by a delta/star transformer
above the minimum value. However, the
time increasing, typical operation times connected to the line through HRC fuses.
three line current transformers at any
being: Substantial faults on this circuit will cause
one end should have similar magnetising
the fuses to blow very quickly before the
characteristics. Kt 40 20 14 6 3
differential relay can operate.
Time at
Magnetising current:
5x setting 30 50 65 90 300 (ms) The limiting condition is a value of fault
In order that the minimum effective current which will just produce an AC
Kt= 20 will suit most current
operating current of the relay remains phase setting current in the relay: this
transformers on distribution systems
low, it is necessary to apply a limit to the current must cause the fuse to operate
Kt = 40 is the preferred setting for EHV
value of the magnetising current quickly enough to discriminate. Most
systems where high speed operation is
demanded by the line current fusing time curves show pre-arcing time
required
transformers: and some allowance must be made for the
It should be noted that the knee point arcing period.
IM 0.05 In at 10 V
In requirement increases with the nominal
To accommodate the largest teed load, use
current rating In. Advantage is therefore
may be made of the Ks (setting multiplier)
Mesh type switchgear arrangements obtained by using a low value of rated
adjustment, and/or selection of a value of
current eg. 1A or even 0.5A.
The relay may be fed by parallel Kt corresponding to a lower operating
connected current transformers as shown Wires may be connected in parallel to speed.
in Figure 15. It is essential to balance reduce the lead resistant (RL) and hence
The particulars tabulated below for teed
the lead resistance in the circulating the current transformer requirements.
loads connected to a fused 11kV feeder
secondary current path to ensure
If the relay is fed from delta connected may be helpful as a general example.
stability for a through busbar fault.
line current transformer then N = 1.
Connecting the current transformers as Feeder 11kV 300A rating
shown in Figure 15 will result in the If one relay is used per phase then
Tee Transformer Fuse Ks Kt
required balance being obtained. It is assume N = 1
rating(kVA) rating (A)
essential that the current transformers at
300 20 1 40
the same end should have similar
Stabilising resistance 400 25 1.7 40
magnetising characteristics. The value of
V 400 25 1.5 6
RCT to be used in calculations should be Rs = K but not greater than 122
40In In 500 30 1.75 3
the resistance of one current transformer
plus the resistance of one lead between Table 6
the two parallel connected current Note: This resistor is not required for
The table above refers to individual teed
transformers. The value of RL should be single phase protection or when
loads. When smaller loads are connected
the resistance of a single lead from the Translay S is fed from delta
at separate locations, on the basis that
common connection of the current connected current transformers.
only one will be subject to a fault at any
transformers to the relay.
instant, the aggregate load may be
Methods of reducing the current Additional requirements: greater. For example twelve 100kVA
transformer requirements: transformers each protected by 10A fuses
It is a stability requirement that the
could be connected to the above line, with
In general the larger the current relays at both ends have the same value
main protection settings Ks = 1 and Kt =
transformer the better the overall of N & Kt selected.
40. Similarly for ten 300kVA transformers
performance. However, when current
It is preferred, although not absolutely each protected by 20A fuses, relay
transformer size is critical the following
essential, that the equipment at the two settings Ks = 2.0 and Kt = 20 would be
notes should prove helpful.
line ends have the same rated current In. suitable. In general the aggregate tee-off
load should not exceed 0.25Ks x current
transformer rating.
MBCI

253
Maximum induced pilot loop Line Current Transformer
voltage Requirements for Transformer
Vs = If ( 3In+ RCT + RL)
2

Ideally the pilot cores should be wormed Feeders:


Where
(twisted together) so that the induced Operating times less than 80ms will be
loop voltage is kept to a minimum. The achieved and through fault stability Vs = setting of MFAC (V)
required level of this voltage to cause assured provided the following CT If = maximum through fault current
operation varies with the setting requirements are satisfied (Kt = 14): referred to CT secondary for
multiplier Ks as shown in Figure 17. which stability is required (A-
For star connected CTs
rms)
(
Vk 50 In 2.2 2+ RCT + RL
I n
) In = rated currency of relay (A) RCT
= resistance of secondary
Unit Protection of For delta connected CTs
winding ()
Transformer feeders
3 (
Vk > 50In 9.72 + RCT + RL
In ) RL = resistance of a single lead from
If longer operating times can be tolerated the CTs to the relay ()
Fault Setting
CT requirements to the following formulae The effective primary operating circuit
The relay internal summation is identical will give operating times less than 160ms (Iop) of the MFAC 14 is given by:
to that used for plain feeders but the and assured through fault stability (Kt =
turns ratio used is 2.25:6. This is 14):
Iop = n(IR + NIIu)
connected as shown in Figure 18 and Where
For star connected CTs
will result in secondary settings as given
( )
IR = relay operating current and
in the table below: Vk 35 In 2.2 2+ RCT + RL
I n metrosil current at setting
Relay setting in amps = Ks x In constant voltage (see MFAC publication)
For delta connected CTs
in table below
Iu
( )
= current transformer magnetising
A to N 0.44 Vk > 35In 9.72 + RCT + RL
B to N 3 I n current at setting voltage (A)
C to N 0.17 Where Nl = number of connected current
A to B 0.44 Vk = kneepoint voltage (V) transformers
B to C 0.17 In = rated current of relay (A)
n = current transformer turns ratio
C to A 0.12
RCT = resistance of CT secondary
3 Phase 0.14 The following notes on this application
winding ()
are also important:
Table 7
RL = resistance of a single lead from
A setting of 14 is recommended for Kt
Where the CTs to the relay ()
to ensure sufficient time for inrush
Ks = setting multiplier which may be
Note 1: Operating times are quoted at 5x blocking. Tripping for internal faults will
adjusted between 0.5 and 2.0
rated current. then occur (typically) within 60 80 ms.
In = relay rated current.
Note 2: The above equations for through fault The N = 6 setting on the MBCI relay
NB. The Figures quoted in this table are stability are applicable for up to 20% must be used to achieve increased
those to be expected under CT mismatch. sensitivity.
conditions of secondary injection
Note 3: In normal applications, to ensure the Where the CT lead resistance is a
testing
fast operation of the MFAC, the knee predominant part of the CT burden at
Note 1: As shown in Figure 18 there is a point voltage Vk must be greater than one, or both, line ends then the use of
restricted earth fault relay in the twice the voltage setting Vs of the 1A line CTs is recommended. The
neutral of the star connected CTs on MFAC relay. However, when used selected rating of current transformers
the delta side of the power with the MBCI/MCTH relay must be the same as the relays (MBCI
transformer. This provides protection combination, lower knee point and MCTH) which they supply.
against earth faults on the delta side voltage, down to Vs, may be used
of the power transformer when the provided operating times up to the
infeed is into the delta. It will provide scheme operating time of 80ms are
MBCI

settings lower than any of the phase accepted.


to neutral settings given above.

Note 2: The MBCI relay, when used in the


transformer feed application, does
not require a stabilising resistor.

254
Additional conductors may be Auxiliary Equipment Information Required with
connected in parallel in order to reduce
For outline drawings of pilot isolation Order
the lead resistance (RL) and, hence, the
transformers, and stabilising resistor, see Basic scheme reference
current transformer requirements.
Figures 20, 21, 22 and 23. (refer to Table 1)
The pilot resistance should not exceed
700. Type(s) of relay
Associated Publications
With 15kV pilots, the MCTH output Type of pilots (private or telephone)
contacts should be connected on the R6001 Midos system
Pilot loop resistance and intercore
relay side of the isolating transformer to R6026 MRTP supervision for ac pilot capacitance values.(This information is
terminate numbers 17 and 18 of the circuits required to determine whether pilot
MBCI relay. isolating transformers are required for
R6027 MVTW destabilising and
The MCTH overcurrent settings for matching purposes.)
intertripping relay
each phase, set by 3 front-mounted Pilot insulation level (5kV or 15kV). Is pilot
potentiometers (one per phase), should R6028 MCRI instantaneous overcurrent
supervision equipment required?
be set at least 50% above the maximum relay
possible load current. Is the overcurrent relay required?
R6004 MMLG/B test block
The steady state magnetising current Is the destabilising facility or
R6006 MSTZ power supply
must not exceed the three phase fault destabilising/intertrip facility required?
R6007 MFAC high impedance
setting of the MCBI relay. For a Ks = 1 Pilot voltage: Metrosil (MBCI 01) or Zener
differential relay
setting, the three phase fault setting is limiting (MBCI 02).
14% of rated current. If the transformer R6066 MCTH transformer inrush current See Figure 11.
is likely to be subjected to overfluxing, detector relay
with the corresponding increase in Current rating
steady state magnetising current, then Frequency rating
the three phase setting must be
Auxiliary dc supply rating
permanently set above this higher
magnetising current by increasing Ks. Auxiliary ac supervision supply rating

AC intertrip supply rating


Cases
Relay type MBCI is provided in case size
6 as shown in Figure 18.

103.6
149
4 holes 4.4 24

168 159
Figure 18
Case outline size 6

Push button 151


projection 10 max
Panel cut-out:
Flush mounting fixing details

32 212 25 min.

177 157 max.


MBCI

Reset

155 Flush mounting 11


All dimensions in mm

255
P1 2.5 1.5
1.2 1.0 0.9 S1 S2

Injections 172 mm
Inputs

X1 X2

340 mm

6 fixing holes, M6 clearance

64.5 mm

154 mm

30 mm 116 mm 9 mm
176 mm

Figure 19 Pilot isolation transformer with filter.With insulation for 15kV

244 mm
176 mm 190 mm
45 mm

171.5 mm

8-M6 Terminals

9 mm
4 Fixing holes, M6 clearance

Figure 20
64.5 mm
Pilot isolation transformer without filter.
MBCI

With insulation for 15kV

30 mm 116 mm

256
19 mm 134 mm 19 mm 69 mm

S2

98 mm

S2

2 off M5 studs
2 off M5 studs

2 off fixing holes M5

52 mm 69 mm

8.5 mm 50 mm 52 mm

Figure 21 Pilot supervision isolation transformer.With insulation for 15kV

2BA connection
screws

354 mm

48 mm

2 holes
6.5 mm 310 mm 48
mm
342 mm

Figure 22 Stabilising resistor


MBCI

257

You might also like