Status as of: 28-Apr-17 SELECT WEEKLY DATE FROM DROP DOWN

ROM DROP DOWN


Reporting Year 2016 2017 2018
Reporting Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Weeks In Reporting Period 4 4 5 4 4 5 4 4 5 4 4 5 4 4 5 4 1 2 3 4 5 4 4 5 4 4 5 4 4 5 4 4 5 4 4 5 4 5 5
Start of Reporting Period 16-Jan-16 13-Feb-16 19-Mar-16 16-Apr-16 14-May-16 18-Jun-16 16-Jul-16 13-Aug-16 17-Sep-16 15-Oct-16 12-Nov-16 17-Dec-16 14-Jan-17 11-Feb-17 18-Mar-17 15-Apr-17 22-Apr-17 29-Apr-17 6-May-17 13-May-17 17-Jun-17 15-Jul-17 12-Aug-17 16-Sep-17 14-Oct-17 11-Nov-17 16-Dec-17 13-Jan-18 10-Feb-18 17-Mar-18 14-Apr-18 12-May-18 16-Jun-18 14-Jul-18 11-Aug-18 15-Sep-18 13-Oct-18 17-Nov-18 22-Dec-18
End of Reporting Period 22-Jan-16 19-Feb-16 25-Mar-16 22-Apr-16 20-May-16 24-Jun-16 22-Jul-16 19-Aug-16 23-Sep-16 21-Oct-16 18-Nov-16 23-Dec-16 20-Jan-17 17-Feb-17 24-Mar-17 21-Apr-17 28-Apr-17 5-May-17 12-May-17 19-May-17 23-Jun-17 21-Jul-17 18-Aug-17 22-Sep-17 20-Oct-17 17-Nov-17 22-Dec-17 19-Jan-18 16-Feb-18 23-Mar-18 20-Apr-18 18-May-18 22-Jun-18 20-Jul-18 17-Aug-18 21-Sep-18 19-Oct-18 23-Nov-18 28-Dec-18

Piling
Engineering Plan Cumulative - - 225 562 1,163 1,679 2,240 3,165 3,959 4,639 4,823 4,900 4,950 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 ###
Engineering Plan Incremental - - 57 85 151 104 141 232 160 170 46 15 12 6 - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative 110 128 951 1,018 2,400 3,385 3,614 3,781 4,289 4,555 4,825 4,825 4,825 4,895 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938 4,938
Engineering Actual Incremental - - 41 5 206 13 346 246 46 42 127 53 68 - - - 43 - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative - - - 49 347 671 996 1,890 2,215 2,688 3,101 3,486 4,390 4,802 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 4,975 ###
Construction Plan Incremental - - - 21 74 65 81 224 65 118 103 77 226 103 35 - - - - - - - - - - - - - - - - - - - - - - - -
Construction Actual Cumulative 40 305 491 724 1,761 2,845 3,352 3,442 3,731 4,464 4,630 4,824 4,859 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870 4,870
Construction Actual Incremental - - - 15 66 37 58 259 217 127 23 58 183 42 44 11 11 - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 1% 6% 10% 15% 35% 57% 67% 69% 75% 90% 93% 97% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98% 98%
Concrete (Cast in Situ)
Engineering Plan Cumulative 63 522 830 991 4,420 7,169 9,605 11,479 13,752 15,752 17,379 20,447 25,942 27,518 29,094 30,670 32,246 34,624 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 ###
Engineering Plan Incremental - - - 43 115 62 40 857 550 609 469 455 500 407 614 1,374 1,576 1,576 1,576 1,576 476 205 - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative 30 200 450 9,000 13,730 16,728 16,978 16,978 19,513 26,288 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480 27,480
Engineering Actual Incremental - - - - - - 10 43 50 2,138 1,183 600 63 - 507 - 1,192 - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative - - - - 62 168 617 3,226 3,798 5,832 9,397 13,186 16,494 17,684 18,873 20,063 21,253 27,176 30,442 32,660 33,713 34,138 34,538 34,891 35,222 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 35,442 ###
Construction Plan Incremental - - - - - - - 16 21 112 652 114 508 891 758 827 1,190 1,190 1,190 1,190 1,185 816 555 211 106 100 71 83 55 - - - - - - - - - -
Construction Actual Cumulative 154 360 630 2,225 6,606 8,555 10,306 12,710 14,982 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253 15,253
Construction Actual Incremental - - - - - - - 39 41 68 399 876 487 438 481 914 271 - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 1% 2% 6% 19% 24% 29% 36% 42% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43% 43%
Concrete (Pre-Cast Drain & Pipe Sleeper)
Engineering Plan Cumulative
Engineering Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 678 2,576 6,588 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 12,204 ###
Construction Plan Incremental - - - - - - - - - - 170 380 1,003 1,404 - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Actual Cumulative 123 1,532 2,570 4,253 9,675 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238 11,238
Construction Actual Incremental - - - - - - - - - - 63 282 260 421 1,084 - - - - - - - - - - - - - - - - - - - - - - - -
Actual Pre-Cast Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 1% 13% 21% 35% 79% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92% 92%
Concrete (Paving)
Engineering Plan Cumulative
Engineering Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 12,776 28,122 42,213 50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 50,000 ###
Construction Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - 2,555 3,836 3,523 1,557 - - - - - - - - -
Construction Actual Cumulative
Construction Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Shelter & Pipe Rack - Fabrication
Engineering Plan Cumulative - - - - - ### - - - ### - - - 121 511 891 969 1,046 1,124 1,201 1,484 1,571 1,663 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 ###
Engineering Plan Incremental - - - - - - - - - - - - - 41 78 95 78 78 78 78 57 22 23 - - - - - - - - - - - - - - - -
Engineering Actual Cumulative - - - - - ### - - - ### - - - - 329 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717 717
Engineering Actual Incremental - - - - - - - - - - - - - - 80 - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 2 14 17 20 23 26 102 272 486 924 1,265 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 ###
Construction Plan Incremental - - - - - - - - - - - - - - 0 3 3 3 3 3 15 43 53 88 85 100 - - - - - - - - - - - - -
Construction Actual Cumulative 54 86 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179 179
Construction Actual Incremental - - - - - - - - - - - - - - 30 4 93 - - - - - - - - - - - - - - - - - - - - - -
Actual Fabricated Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 3% 5% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11% 11%
Shelter & Pipe Rack - Erection
Engineering Plan Cumulative
Engineering Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 41 107 381 764 1,250 1,647 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 1,667 ###
Construction Plan Incremental - - - - - - - - - - - - - - - - - - - - - 10 17 55 96 122 79 - - - - - - - - - - - -
Construction Actual Cumulative 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35 35
Construction Actual Incremental - - - - - - - - - - - - - - - - 35 - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2% 2%
Tank - Fabrication
Engineering Plan Cumulative 343 1,072 1,965 1,971 1,977 1,982 1,988 2,018 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 ###
Engineering Plan Incremental - - - - - - - - - - - - - 86 146 223 6 6 6 6 6 3 - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative 1,050 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206 1,206
Engineering Actual Incremental - - - - - - - - - - - - - - 210 - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 130 420 508 597 685 773 1,200 1,676 1,894 2,019 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 ###
Construction Plan Incremental - - - - - - - - - - - - - - 55 73 88 88 88 88 85 119 55 25 - - - - - - - - - - - - - - -
Construction Actual Cumulative 281 971 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980 980
Construction Actual Incremental - - - - - - - - - - - - - - 81 119 9 - - - - - - - - - - - - - - - - - - - - - -
Actual Fabricated Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 14% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48% 48%
Tank - Erection
Engineering Plan Cumulative
Engineering Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 30 78 127 175 223 435 768 1,129 1,425 1,741 1,995 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 2,039 ###
Construction Plan Incremental - - - - - - - - - - - - - - - 10 48 48 48 48 42 83 90 59 79 64 6 - - - - - - - - - - - -
Construction Actual Cumulative 78 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93 93
Construction Actual Incremental - - - - - - - - - - - - - - - 43 15 - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 4% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Underground Piping - Fabrication & Erection
Engineering Plan Cumulative 7,849 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 ###
Engineering Plan Incremental - - - - - - - - - - - - - - 1,570 561 - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative 4,500 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034 10,034
Engineering Actual Incremental - - - - - - - - - - - - - - 4,500 - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 757 1,322 1,887 2,452 3,017 5,698 7,835 9,765 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 10,091 ###
Construction Plan Incremental - - - - - - - - - - - - - - - 189 565 565 565 565 536 534 482 65 - - - - - - - - - - - - - - -
Construction Actual Cumulative 418 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460 460
Construction Actual Incremental - - - - - - - - - - - - - - - 288 42 - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 4% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5% 5%
Aboveground Piping - Fabrication
Engineering Plan Cumulative - - - - - ### - - - ### - - - - 1,203 12,650 16,108 19,565 23,022 26,479 40,308 54,835 69,337 83,178 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 ###
Engineering Plan Incremental - - - - - - - - - - - - - - 241 2,862 3,457 3,457 3,457 3,457 2,766 3,632 3,626 2,768 2,919 - - - - - - - - - - - - - -
Engineering Actual Cumulative - - - - - ### - - - ### - - - - - 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000 25,000
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative - - - - - ### - - - ### - - - - - - - - - - - 1,476 12,268 28,739 53,714 77,021 89,428 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 94,855 ###
Construction Plan Incremental - - - - - - - - - - - - - - - - - - - - - 369 2,698 3,294 6,244 5,827 2,481 1,357 - - - - - - - - - - -
Construction Actual Cumulative - - - - - - - - - - - - - - - - - - - - - - - -
Construction Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Actual Fabricated Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Aboveground Piping - Erection
Engineering Plan Cumulative 1,850 19,462 24,781 30,100 35,419 40,738 62,013 84,361 106,672 127,966 145,930 145,930 145,930 145,930 145,930 145,930 145,930 145,930 145,930 145,930 145,930 145,930 145,930 ### 145,930
Engineering Plan Incremental - - - - - - - - - - - - - - 370
E A C m
E A m
Con u on P C m
C P m
Reporting Year 2016 2017 2018
Reporting Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Weeks In Reporting Period 4 4 5 4 4 5 4 4 5 4 4 5 4 4 5 4 1 2 3 4 5 4 4 5 4 4 5 4 4 5 4 4 5 4 4 5 4 5 5
Start of Reporting Period 16-Jan-16 13-Feb-16 19-Mar-16 16-Apr-16 14-May-16 18-Jun-16 16-Jul-16 13-Aug-16 17-Sep-16 15-Oct-16 12-Nov-16 17-Dec-16 14-Jan-17 11-Feb-17 18-Mar-17 15-Apr-17 22-Apr-17 29-Apr-17 6-May-17 13-May-17 17-Jun-17 15-Jul-17 12-Aug-17 16-Sep-17 14-Oct-17 11-Nov-17 16-Dec-17 13-Jan-18 10-Feb-18 17-Mar-18 14-Apr-18 12-May-18 16-Jun-18 14-Jul-18 11-Aug-18 15-Sep-18 13-Oct-18 17-Nov-18 22-Dec-18
End of Reporting Period 22-Jan-16 19-Feb-16 25-Mar-16 22-Apr-16 20-May-16 24-Jun-16 22-Jul-16 19-Aug-16 23-Sep-16 21-Oct-16 18-Nov-16 23-Dec-16 20-Jan-17 17-Feb-17 24-Mar-17 21-Apr-17 28-Apr-17 5-May-17 12-May-17 19-May-17 23-Jun-17 21-Jul-17 18-Aug-17 22-Sep-17 20-Oct-17 17-Nov-17 22-Dec-17 19-Jan-18 16-Feb-18 23-Mar-18 20-Apr-18 18-May-18 22-Jun-18 20-Jul-18 17-Aug-18 21-Sep-18 19-Oct-18 23-Nov-18 28-Dec-18

Construction Actual Cumulative - - - - - - - - - - - - - - - - - - - - - - - -


Construction Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Electrical Cable
Engineering Plan Cumulative
Engineering Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 20 80 100 120 140 160 240 320 35,391 102,993 180,901 258,881 315,901 358,133 358,133 358,133 358,133 358,133 358,133 358,133 358,133 358,133 358,133 ### 358,133
Construction Plan Incremental - - - - - - - - - - - - - - 20 15 20 20 20 20 16 20 8,768 13,520 19,477 19,495 11,404 10,558 - - - - - - - - - - -
Construction Actual Cumulative - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Instruments Cable
Engineering Plan Cumulative
Engineering Plan Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Engineering Actual Cumulative
Engineering Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Construction Plan Cumulative 10,570 25,467 45,570 68,467 93,957 110,115 118,120 118,120 118,120 118,120 118,120 118,120 118,120 118,120 118,120 118,120 ###
Construction Plan Incremental - - - - - - - - - - - - - - - - - - - - - - 2,643 2,979 5,026 5,724 5,098 4,039 2,001 - - - - - - - - - -
Construction Actual Cumulative - - - - - - - - - - - - - - - - - - - - - - - -
Construction Actual Incremental - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Actual Installed Progress % 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0% 0%
Concrete Breakdown

Type (RCC) Volume (m3) Area (m2) Length (m)


Thickness (mm)

Cast in- situ 35,442.00 n/a n/a

Precast Drain +
6,060.00 n/a 12,204.00 n/a
Pipe Sleeper
Paving 7,500.00 50,000.00 n/a 150.00

Total 49,002.00 n/a n/a n/a


PETRONAS RAPID PROJECT
PACKAGE 16 A

Piling
2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


1,600 6,000
Piling Statistics Engineering - Plan Incremental
Estimated Total Quantity: 4,975 nos Engineering - Actual
Incremental
1,400
Engineering Releases Construction - Plan
5,000
Plan Cumulative : 4,975 nos Incremental
Plan Incremental : - nos Construction - Actual
Actual Cumulative : 4,938 nos 1,200 Incremental
Actual Incremental : 43 nos Engineering - Plan Cumulative
Construction Engineering - Actual 4,000
Plan Cumulative : 4,975 nos 1,000 Cumulative
Plan Incremental : - nos Construction - Plan Cumulative
Actual Cumulative : 4,870 nos
Actual Incremental : 11 nos
800 3,000

600

2,000

400

1,000
200

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
1,163

1,679

2,240

3,165

3,959

4,639

4,823

4,900

4,950

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975
225

562

Engineering Plan Cumulative


0

225

337

601

516

561

925

794

680

184

Engineering Plan Incremental


77

50

25
0

0
1,018

2,400

3,385

3,614

3,781

4,289

4,555

4,825

4,825

4,825

4,895

4,938
128

951
110

Engineering Actual Cumulative


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,382
823

985

229

167

508

266

270
110

Engineering Actual Incremental


18

67

70

43
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,890

2,215

2,688

3,101

3,486

4,390

4,802

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975

4,975
347

671

996

Construction Plan Cumulative


49
0

298

325

325

895

325

473

413

385

904

412

173

Construction Plan Incremental


49
0

0
1,761

2,845

3,352

3,442

3,731

4,464

4,630

4,824

4,859

4,870
305

491

724

Construction Actual Cumulative


40
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,037

1,084
265

186

233

507

289

733

166

194

Construction Actual Incremental


40

90

35

11
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Piling Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Concrete (Cast in Situ)


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


9,000 40,000
Engineering - Plan Incremental
Concrete (Cast in Situ) Statistics
Estimated Total Quantity: 35,442 m Engineering - Actual
8,000 Incremental
35,000
Engineering Releases Construction - Plan
Plan Cumulative : 27,518 m Incremental
Plan Incremental : 1,576 m 7,000 Construction - Actual
Actual Cumulative : 27,480 m Incremental 30,000
Actual Incremental : 1,192 m Engineering - Plan Cumulative
Construction 6,000 Engineering - Actual
Plan Cumulative : 17,684 m Cumulative 25,000
Plan Incremental : 1,190 m Construction - Plan Cumulative
Actual Cumulative : 15,253 m 5,000
Actual Incremental : 271 m
20,000

4,000

15,000
3,000

10,000
2,000

1,000
5,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

13,752

15,752

17,379

20,447

25,942

32,246

34,624

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442
11,479
4,420

7,169

9,605
522

830

991

Engineering Plan Cumulative


63
0

3,429

2,749

2,436

1,874

2,273

2,000

1,627

3,068

5,495

6,304

2,378
459

308

161

818
Engineering Plan Incremental
63
0

0
13,730

16,728

16,978

16,978

19,513

26,288

27,480
9,000
200

450

Engineering Actual Cumulative


30
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
8,550

4,730

2,998

2,535

6,775

1,192
170

250

250

Engineering Actual Incremental


30
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
13,186

16,494

21,253

27,176

30,442

32,660

33,713

34,138

34,538

34,891

35,222

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442

35,442
3,226

3,798

5,832

9,397
168

617

Construction Plan Cumulative


62
0

2,609

2,034

3,565

3,789

3,308

4,759

5,924

3,265

2,218

1,053
106

450

572

426

400

353

331

220
Construction Plan Incremental
62
0

0
10,306

12,710

14,982

15,253
2,225

6,606

8,555
154

360

630

Construction Actual Cumulative


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,595

4,381

1,949

1,751

2,404

2,272
154

206

270

271

Construction Actual Incremental


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Concrete (Cast in Situ) Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Concrete (Pre-Cast Drain & Pipe Sleeper)


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


6,000 14,000
Concrete (Pre-Cast Drain & Pipe Sleeper) Statistics
Construction - Plan
Estimated Total Quantity: 12,204 m
Incremental
12,000
Construction 5,000 Construction - Actual
Plan Cumulative : 12,204 m Incremental
Plan Incremental : - m
Actual Cumulative : 11,238 m Construction - Plan Cumulative
Actual Incremental : - m
10,000
4,000 Construction - Actual
Cumulative

8,000

3,000

6,000

2,000

4,000

1,000
2,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204

12,204
2,576

6,588
678

Construction Plan Cumulative


0

1,898

4,012

5,616
678

Construction Plan Incremental


0

0
11,238

11,238
1,532

2,570

4,253

9,675
123

Construction Actual Cumulative


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,409

1,038

1,683

5,422

1,563
123

Construction Actual Incremental


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Concrete (Pre-Cast Drain & Pipe Sleeper) Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Concrete (Paving)
2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


18,000 60,000
Concrete (Paving) Statistics
Construction - Plan
Estimated Total Quantity: 50,000 m
16,000 Incremental

Construction Construction - Actual 50,000


Plan Cumulative : - m Incremental
Plan Incremental : - m 14,000

Actual Cumulative : - m Construction - Plan Cumulative


Actual Incremental : - m
12,000 Construction - Actual 40,000
Cumulative

10,000

30,000
8,000

6,000 20,000

4,000

10,000

2,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

12,776

28,122

42,213

50,000

50,000

50,000

50,000

50,000

50,000

50,000

50,000

50,000

50,000
Construction Plan Cumulative
0

12,776

15,346

14,091

7,787
Construction Plan Incremental
0

0
Construction Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Concrete (Paving) Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Shelter & Pipe Rack - Fabrication


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


500 1,800
Engineering - Plan Incremental
Shelter & Pipe Rack - Fabrication Statistics
Estimated Total Quantity: 1,667 MT Engineering - Actual
450
Incremental 1,600
Engineering Releases Construction - Plan
Plan Cumulative : 969 MT Incremental
400
Plan Incremental : 78 MT Construction - Actual 1,400
Actual Cumulative : 717 MT Incremental
Actual Incremental : - MT 350 Engineering - Plan Cumulative
Construction Engineering - Actual 1,200
Plan Cumulative : 17 MT Cumulative
Plan Incremental : 3 MT 300 Construction - Plan Cumulative
Actual Cumulative : 179 MT 1,000
Actual Incremental : 93 MT
250

800
200

600
150

400
100

50
200

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

1,201

1,484

1,571

1,663

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667
121

891
511
Engineering Plan Cumulative
0

121

390

380

310

283
Engineering Plan Incremental

87

92
0

0
329

717

717
Engineering Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
329

388
Engineering Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,265

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667
102

272

486

924
Construction Plan Cumulative 14

26
0

170

214

438

341

402
Construction Plan Incremental
12

12

76
0

0
179

Construction Actual Cumulative


54

86
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
54

32

93
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Shelter & Pipe Rack - Fabrication Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Shelter & Pipe Rack - Erection


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


600 1,800
Shelter & Pipe Rack - Erection Statistics
Construction - Plan
Estimated Total Quantity: 1,667 MT
Incremental 1,600
Construction 500 Construction - Actual
Plan Cumulative : - MT Incremental
Plan Incremental : - MT 1,400
Actual Cumulative : 35 MT Construction - Plan Cumulative
Actual Incremental : 35 MT
400 Construction - Actual 1,200
Cumulative

1,000

300

800

200 600

400

100

200

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

1,250

1,647

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667

1,667
107

381

764
Construction Plan Cumulative

41
0

274

383

486

397
Construction Plan Incremental

41

66

20
0

0
Construction Actual Cumulative

35
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
35
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Shelter & Pipe Rack - Erection Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Tank - Fabrication
2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


1,200 2,500
Engineering - Plan Incremental
Tank - Fabrication Statistics
Estimated Total Quantity: 2,039 MT Engineering - Actual
Incremental
Engineering Releases Construction - Plan
1,000
Plan Cumulative : 1,971 MT Incremental
2,000
Plan Incremental : 6 MT Construction - Actual
Actual Cumulative : 1,206 MT Incremental
Actual Incremental : - MT Engineering - Plan Cumulative
Construction 800 Engineering - Actual
Plan Cumulative : 508 MT Cumulative
Plan Incremental : 88 MT Construction - Plan Cumulative 1,500
Actual Cumulative : 980 MT
Actual Incremental : 9 MT
600

1,000

400

500
200

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

1,072

1,965

1,988

2,018

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039
343
Engineering Plan Cumulative
0

343

729

893
Engineering Plan Incremental

23

30

21
0

0
1,050

1,206

1,206
Engineering Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,050

156
Engineering Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
1,200

1,676

1,894

2,019

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039
130

420

773
Construction Plan Cumulative
0

130

290

353

427

476

218

125
Construction Plan Incremental

20
0

0
281

971

980

Construction Actual Cumulative


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
281

690

Construction Actual Incremental


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Tank - Fabrication Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Tank - Erection
2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


400 2,500
Tank - Erection Statistics
Construction - Plan
Estimated Total Quantity: 2,039 MT
Incremental
350
Construction Construction - Actual
Plan Cumulative : 78 MT Incremental 2,000
Plan Incremental : 48 MT
300
Actual Cumulative : 93 MT Construction - Plan Cumulative
Actual Incremental : 15 MT
Construction - Actual
250 Cumulative
1,500

200

1,000
150

100

500

50

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

1,129

1,425

1,741

1,995

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039

2,039
223

435

768
Construction Plan Cumulative

30
0

193

212

333

361

296

316

254
Construction Plan Incremental

30

44
0

0
Construction Actual Cumulative 78

93
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
78

15
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Tank - Erection Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Underground Piping - Fabrication & Erection


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


9,000 12,000
Engineering - Plan Incremental
Underground Piping - Fabrication & Erection Statistics
Estimated Total Quantity: 10,091 m Engineering - Actual
8,000 Incremental
Engineering Releases Construction - Plan
10,000
Plan Cumulative : 10,091 m Incremental
Plan Incremental : - m 7,000 Construction - Actual
Actual Cumulative : 10,034 m Incremental
Actual Incremental : - m Engineering - Plan Cumulative
Construction 6,000 Engineering - Actual 8,000
Plan Cumulative : 1,322 m Cumulative
Plan Incremental : 565 m Construction - Plan Cumulative
Actual Cumulative : 460 m 5,000
Actual Incremental : 42 m
6,000

4,000

3,000 4,000

2,000

2,000

1,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091
7,849
Engineering Plan Cumulative
0

7,849

2,242
Engineering Plan Incremental
0

0
10,034

10,034
4,500
Engineering Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
4,500

5,534
Engineering Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091

10,091
3,017

5,698

7,835

9,765
Construction Plan Cumulative 757
0

2,260

2,681

2,137

1,930
757

326
Construction Plan Incremental
0

0
418

460

Construction Actual Cumulative


0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
418

Construction Actual Incremental


42
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Underground Piping - Fabrication & Erection Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Aboveground Piping - Fabrication


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


30,000 100,000
Engineering - Plan Incremental
Aboveground Piping - Fabrication Statistics
Estimated Total Quantity: 94,855 dia.-inch Engineering - Actual
Incremental 90,000

Engineering Releases Construction - Plan


25,000
Plan Cumulative : 16,108 dia.-inch Incremental
80,000
Plan Incremental : 3,457 dia.-inch Construction - Actual
Actual Cumulative : 25,000 dia.-inch Incremental
Actual Incremental : - dia.-inch Engineering - Plan Cumulative 70,000
Construction 20,000 Engineering - Actual
Plan Cumulative : - dia.-inch Cumulative
Plan Incremental : - dia.-inch Construction - Plan Cumulative 60,000
Actual Cumulative : - dia.-inch
Actual Incremental : - dia.-inch
15,000 50,000

40,000

10,000
30,000

20,000
5,000

10,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

12,650

26,479

40,308

54,835

69,337

83,178

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855
1,203
Engineering Plan Cumulative
0

13,829

13,829

14,526

14,502

13,841
11,448

11,676
1,203
Engineering Plan Incremental
0

0
25,000

25,000
Engineering Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
25,000
Engineering Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
12,268

28,739

53,714

77,021

89,428

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855

94,855
1,476
Construction Plan Cumulative
0

10,792

16,471

24,975

23,307

12,407
1,476

5,426
Construction Plan Incremental
0

0
Construction Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Aboveground Piping - Fabrication Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Aboveground Piping - Erection


2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


45,000 160,000
Aboveground Piping - Erection Statistics
Construction - Plan
Estimated Total Quantity: 145,930 dia.-inch
40,000 Incremental
140,000
Construction Construction - Actual
Plan Cumulative : - dia.-inch Incremental
Plan Incremental : - 35,000
dia.-inch
Actual Cumulative : - dia.-inch
120,000
Construction - Plan Cumulative
Actual Incremental : - dia.-inch
30,000 Construction - Actual
Cumulative 100,000

25,000

80,000
20,000

60,000
15,000

40,000
10,000

5,000
20,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

121,402

141,536

145,930

145,930

145,930

145,930

145,930

145,930

145,930

145,930

145,930

145,930

145,930
21,183

48,598

89,151
4,402
Construction Plan Cumulative
0

16,781

27,415

40,553

32,251

20,134
4,402

4,394
Construction Plan Incremental
0

0
Construction Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Aboveground Piping - Erection Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Electrical Cable
2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


90,000 400,000
Electrical Cable Statistics
Construction - Plan
Estimated Total Quantity: 358,133 m
80,000 Incremental
350,000
Construction Construction - Actual
Plan Cumulative : 100 m Incremental
Plan Incremental : 20 m 70,000

Actual Cumulative : - m
300,000
Construction - Plan Cumulative
Actual Incremental : - m
60,000 Construction - Actual
Cumulative 250,000

50,000

200,000

40,000

150,000
30,000

100,000
20,000

10,000
50,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

102,993

180,901

258,881

315,901

358,133

358,133

358,133

358,133

358,133

358,133

358,133

358,133

358,133

358,133

358,133

358,133
35,391
160

240

320
Construction Plan Cumulative

20

80
0

35,071

67,601

77,908

77,980

57,020

42,231
Construction Plan Incremental
20

60

80

80

80
0

0
Construction Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Electrical Cable Commodity Curve
PETRONAS RAPID PROJECT
PACKAGE 16 A

Instruments Cable
2016 2017 2018
DESCRIPTION
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Status as of: 28-Apr-17


30,000 140,000
Instruments Cable Statistics
Construction - Plan
Estimated Total Quantity: 118,120 m
Incremental
120,000
Construction 25,000 Construction - Actual
Plan Cumulative : - m Incremental
Plan Incremental : - m
Actual Cumulative : - m Construction - Plan Cumulative
Actual Incremental : - m
100,000
20,000 Construction - Actual
Cumulative

80,000

15,000

60,000

10,000

40,000

5,000
20,000

0 0

2016 2017 2018


Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

118,120

118,120

118,120

118,120

118,120

118,120

118,120

118,120

118,120

118,120

118,120
110,115
10,570

25,467

45,570

68,467

93,957
Construction Plan Cumulative
0

10,570

14,897

20,103

22,897

25,490

16,158

8,005
Construction Plan Incremental
0

0
Construction Actual Cumulative
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Construction Actual Incremental
0

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A

#N/A
Remarks / Comments PETRONAS RAPID PROJECT REVISIONS
PACKAGE 16 A Date Revision Generated Checked Approved
29/Aug/16 A
Instruments Cable Commodity Curve

You might also like