You are on page 1of 7

ASSESSING THE RELATIONSHIPS BETWEEN PROJECT SUCCESS,

AND SYSTEM ENGINEERING PROCESSES


Paul J . Componation, The Univer sity of Alabama in Huntsville
Alisha D. Youngblood, The Univer sity of Alabama in Huntsville
Dawn R. Utley, The Univer sity of Alabama in Huntsville
Phillip A. Far r ington, The Univer sity of Alabama in Huntsville

Abstract in this paper is part of a larger study in which an


NASAs Procedural Requirements for systems assessment of historical and current MSFC projects
engineering - NPR 7123.1A NASA Systems will be made to determine the correlation between the
Engineering Processes and Requirements was released extent of the formal SE&I process and organizational
to provide the agency with a standard system implementation with programmatic and technical
engineering model to support the continued success. Specifically the researchers were interested in
development of manned and unmanned space flight evaluating the Systems Engineering Approach and
systems. The NPR draws on both industry best Teaming Effectiveness as related to project success.
practices and NASA experience to identify a core set of An SE&I Skill Board was established to provide
system engineering processes. The NPR is overarching guidance and to identify and rate
comprehensive, however, managers are still faced with successful MSFC projects. Seven projects were
the competing demands of balancing cost, schedule and identified to begin the study. Results from the data
technical requirements on ever more complex system collection and analysis efforts will be used to develop
development projects. Additional guidance on tailoring approaches to standard SE&I processes. The
effective tailoring of system engineering to meet ultimate goal is to apply lessons learned to on-going
individual project needs may be of help. This paper MSFC projects, namely the Constellation project
reports on an initial study into the relationship between (travel to Mars).
the system engineering processes identified in NPR This paper is a summary of the key findings
7123.1 and the technical, schedule and budget success reports the Beta project used to assess the methodology
of past and currently NASA space flight hardware and test the analysis and resulting conclusions for
projects. The results do show correlations; however appropriateness. The project used for the Beta test was
not all the processes identified had the same effects on the International Space Welding Experiment (ISWE)
success. The unique characteristics of individual project whose mission was to incorporate Russian
projects do influence which system engineering technology of welding in space in the space station.
processes should be focused on. While this project never flew, it was considered
extremely successful in overcoming obstacles and
Keywor ds: Project Success, System engineering, working toward a viable plan to safely weld in space.
Project Management
Literature Review
Introduction Systems Engineering Approach.
NASAs Marshall Space Flight Center (MSFC) has NASA defines systems engineering as a robust
been a primary benefactor of the systems engineering approach to the design, creation, and operation of
approach. They have been part of such complex and systems. In simple terms, the approach consists of
overarching projects as the Apollo program, the space identification and quantification of system goals,
shuttle, and more recently have become involved with creation of alternative system design concepts,
the redirected mission to return to the Moon in performance of design trades, selection and
anticipation to go beyond to Mars (ref). While some of implementation of the best design, verification that the
these complex projects have been very successful using design is properly built and integrated, and post-
the systems engineering (SE) approach, others have implementation assessment of how well the system
become unduly constrained and overburdened with the meets (or met) the goals. (NASA SP-610S, 1995) This
full detailed use of the SE approach, and still others definition, while developed and used to specifically
have been successful with only a limited application of support NASA systems, does reflect similar
the formal SE approach. As part of SE Skill Lead components as other definitions from the International
responsibility an effort has been initiated to address Council on Systems Engineering (INCOSE) and
personnel training specific to systems engineering and researchers in the field. This definition is further
integration (SE&I), and develop effective ways to developed and put into practice with the publication of
tailor standard SE&I processes. The research reported NASA NPR 7123.1 Systems Engineering

1
Processes and Requirements in 2006. This new Exhibit 1. Project Success Assessment Questionnaire
Procedural Requirement refines and operationalizes
NASAs approach to deploying system engineering in How would you rate the technical success of
agency programs and projects. It is this approach that this project relative to the initial set of system
is used as a basis for analyzing system engineering requirements?
processes in past and current projects. How would you rate the technical success of
this project relative to other similar projects?
Methodology How well did the project stay on schedule in
This research into the relationship between project relation to the original project plan?
success and system engineering processes was
How well did the project stay on schedule in
conducted in four phases: Phase I was the identification
relation to other similar projects?
and assessment of a sample of aerospace flight
projects; Phase II was the collection of data on the use How well did the project stay within budget in
of system engineering processes; Phase III was to relation to the original project plan?
conduct interviews with project personal to verify data; How well did the project stay within budget in
and, Phase IV was to assess relationships between relation to other similar projects?
project success and system engineering processes. The What is your level of satisfaction with the
artifacts used to evaluate the relationship between process by which the project was managed?
success and system engineering processes were NASA What is your overall assessment of the project
space flight hardware projects. Characteristics on the success?
individual projects selected for study were also
collected. This research was conducted from June, The assessment of the projects was done by the
2006 through December 2007. Skill Board members. The members were asked to
A SE&I Skill Board was established to provide only assess those projects with which they had closely
oversight and guidance for the research effort. The worked; therefore, not all projects were assessed by all
SE&I Skill Board members for this project were all members. The research team elected to use a 5-point
senior managers at NASAs Marshall Space Fight scale (Exhibit 2) for the assessment. A short
Center (MSFC) and included: discussion was held with the Skill Board members and
Deputy Director, Constellation Systems they confirmed that they were comfortable with this
Engineering & Integration Office scoring system. A comparison between each
Deputy Director, Exploration Launch Office individual Skill Board member project scores was done
Deputy Manager, Shuttle Propulsion Office as a validation for this approach
Chief, Systems Engineering Division
Exhibit 2. Project Success Assessment Scoring Key
Phase I: Identification and Assessment of Sample
Aerospace Flight Projects Key
The first phase of the research effort included two 5 Excellent
activities. First was the identification of an appropriate
4 Very Good
method to assess the success of the projects and second
was the .selection of a sample set of aerospace flight 3 Good
hardware projects. 2 Fair
The modified list of project success assessment 1 Poor
questions looked at the three common measures of
project success, technical performance, schedule The second activity was to select a sample of the
performance, and budget performance. The research aerospace flight projects that had been managed by
team tried to account for the unique culture and MSFC. The selection of projects was limited to this
operating environment at MSFC by asking for success site to help improve access to project team personnel
to be assessed based on both the initial project planning and materials.
documents for each project, and success to be assessed
based on the projects performance compared to similar The projects identified for the research effort included:
projects. The project success assessment also looked at Space Shuttle Main Engines (SSME)
the overall satisfaction with the project management X-37 Experimental unpiloted vehicle
project and asked for an overall assessment of project Chandra - Orbiting observatory
success. The final success assessment questionnaire
EXPRESS Rack - provides interfaces for payloads
totaled eight questions (Exhibit 1).
on the shuttle

2
Gravity Probe B - is the relativity gyroscope Procedural Requirements (NPR) for systems
experiment engineering - NPR 7123.1A NASA Systems
International Space Welding Experiment (ISWE) Engineering Processes and Requirements (Exhibit 3).
Gravity Probe B (GP-B) This NPR "establishes a core set of common Agency-
ECLSS level technical processes and requirements needed to
Shuttle External Tank define, develop, realize, and integrate the quality of the
SME Advanced Health Monitoring System system products created and acquired by or for
AXAF NASA." The processes described in the NPR are
intended to "clearly delineate a successful model to
Saturn Booster
complete comprehensive technical work, reduce
IML
program and technical risk, and improve mission
success." (NASA, 2007).
Phase II: Collection of Data on the use of System
NPR 7123 identifies 17 common technical
Engineering Processes
processes fall into three groups: systems design
The second phase of this research included three
processes (4 each), product realization processes (5
activities. First was to identify the system engineering
each), and technical management processes (8 each).
model that were to be used as the basis for comparison
Within the NPR, each technical process is described by
in the research, second was to identify a scoring
giving its purpose, inputs and sources, outputs and
scheme to quantify the level of the processes planned
destinations, typical activities, and a process flow
on each project, and third was to conduct the individual
diagram.
project assessments.
This research was focused primarily on NASA, so
the systems engineering model selected was the NASA

Exhibit 3. NPR 7123.1A System Engineering Processes

3
The second task was project scoring. The difficulties with data interpretation were also
presence or absence of these system engineering addressed. The project team members included in the
processes was scored by reviewing the data archives interviews included the project manager, the chief
for each project. The data reviewed was limited to engineer, and a representative of the functional leads.
approved planning documents. The level of The majority of the interviews included two
documentation on individual projects was variable, but researchers and one project team member. A limited
all projects included in this research included at a number of interviews included multiple team members.
minimum the project plan, the systems engineering It is should be noted again that this research effort,
management plan, the risk management plan, the assessing the relationships between project success,
systems engineering requirements document, and and system engineering process, was part of larger
design review planning documents. The research team effort that also looked at project success and team
did work to keep the data reviewed for all the projects organization. The interviews collected data for both
the same. efforts. For the purposes of this research the data
The third task, assessment of the data, was done assessment verification was the primary focus of the
by reviewing the project documentation and noting the interviews.
presence or absence of references to the system
engineering processes identified in NPR 7123. The Phase IV: Assessing the Relationships between Project
research team elected to use a 4-point scale (Exhibit 4) Success and System Engineering Processes.
for the assessment that was modeled on previous The final phase of this research was to assess the
research done at MSFC to assess system engineering relationship between the project success and system
processes in relation to CMMi. engineering processes. This assessment was done both
qualitatively and quantitatively. The quantitative
Exhibit 4. Project System Engineering Processes assessment was done first and was limited to a
Assessment Scoring Key correlation analysis due to the limited size of the data
set. A preliminary review of the data was done to
Key identify correlations of .5. The qualitative assessment
0 None: No direct references located for this was then conducted using the correlations found in the
system engineering process initial analysis as a starting point. The qualitative
1 Low: Direct reference to this system reviews looked at specific data to further explore the
engineering process is evident in the document. relationships that may exist between the unique
The reference is in standard form and could be characteristics of the individual projects, system
viewed as a boiler-plate reference. engineering processes along with level of technical,
2 Medium: Direct reference to this system schedule, budget and overall managerial success.
engineering process is evident in the
documentation. The reference shows evidence Results
that the process has been cross-referenced and is The research methodology was initially tested on the
tailored to meet the needs of the project. International Space Welding Experiment (ISWE). Two
changes were made to the methodology based on this
3 High: Direct references to this systems
beta test. First, the interviews with project team
engineering process is evident in multiple
members were initially planned for one researcher and
documents. The documents show evidence that
one team member. Since the interviews on the beta test
the process has been cross-referenced, is tailored
took much longer than planned, 60 minutes on average
to the specific project, and there are monitoring
rather than an initial plan of 30 minutes, two
and control procedures identified.
researchers were used for each interview. This helped
with note taking during the interviews. Second, the
The assessment of project data was done document reviews for each project were found to take
independently by two research team members. approximately 20 hours for this relatively small
Variances between the two assessments were then project. To reduce the labor hours required a system
resolved. A cross-section of the total project team was engineering process check sheet was developed. Two
asked to participate in the study. reviewers also looked at each document for
consistency. The document review process was still
Phase III: Project Team Member Interviews to Verify the most resource intensive task in the research effort.
Data These modifications were made before the remaining
The third phase of this research effort was to interview projects were reviewed.
project team members to verify the data that was The first analysis concerned the data collected
collected and assessed. Missing documents and from the SE&I Skill Board members associated with

4
the project success criteria questionnaire. To check for On average, and in each individual project, the
validity in the approach a comparison was made technical success scores were consistently higher than
between the rankings of individual members. The two the success scores for other factors. This observation
key observations of the questionnaire results were was raised during interviews with project team
noted. First was the observation that the rank ordering members. Team members who commented on the data
of the projects by the Skill Board members very noted that the results do support NASAs emphasis on
consistent (Exhibit 5). The only exception was the technical performance over programmatic
ordering of SRB/RSRM and SSME by three of the requirements. Also, the scores for technical, schedule
members. Upon closer examination of the raw data, and budget success compared to other similar projects
there did not seem to be a strong difference between was consistently higher than the scores for technical,
the individuals scores for these projects, so the schedule and budget success in relation to other similar
discrepancy is not considered to be problematic. projects. This observation does support the emphasis
on selecting projects that had successfully flown during
Exhibit 5. Rank Order of Pilot Study Projects this initial phase of the research effort.
The third analysis concerned the comparison of
Rater Rater Rater Rater the project success assessments with the project system
Average Rank engineering processes assessment scoring. A
1 2 3 4
Chandra 1 1 - - correlation was done to determine if there were
relationships between the success metrics and the
SRB/RSRM 3 - 1 1
system engineering processes. The analysis looked for
EXPRESS Rack - 2 - - both positive and negative correlations.
SSME 2 3 2 2 An initial assumption going into the research was
X-37 4 - 3 - that the primary purpose of system engineering was to
GP-B 5 - - - assist in meeting technical requirements for system
development; therefore we would assume that system
engineering processes would have a positive
Second was the observation that the comparison
correlation with the technical success measures for a
between technical, schedule, and budget success
project. This was not always the case. A look at
(Exhibit 6).
positive correlations between project success measures
and system engineering processes (exhibit 7) showed
Exhibit 6. Breakout by Project of Average Response
that product verification, product integration, product
for Criteria
implementation, configuration management, and
technical risk management were correlated with the
Criteria Average per Project Average Average technical success measures. These processes, along
with technical assessment were also correlated with the
Technical success relative to overall project success measure. Technical
4.19
initial requirements requirements definition and technical planning were
4.32
Technical success relative to correlated with relative schedule success. Stakeholder
4.44 expectation definition, technical requirements
similar projects
definition, technical planning, and technical assessment
On schedule relative to
2.21 were all positively correlated with relative budget
original project plan
2.62 success. Of interest is the observation that system
On schedule relative to similar engineering processes that positively correlated with
3.03
projects technical success relative to initial requirements also
On budget relative to original correlated with technical success relative to similar
2.51 projects. However, the system engineering processes
project plan
2.89 that positively correlated with schedule and budget
On budget relative to similar relative to similar projects did not positively correlate
3.26
projects with schedule and budget relative to original project
Satisfaction with project plan. Also of note is that several of the system
3.50
management process engineering processes, such as logical decomposition
and design solution, did not show any positive
Overall project success 4.22
correlation with any success measures.

5
Exhibit 7. Positive Correlations between Project Success Assessments and System Engineering Processes

Project Success and System

1. Stakeholder Expectations Definition

2. Technical Requirements Definition

3. Logical Decomposition

4. Design Solution

5. Product Implementation

6. Product Integration

7. Product Verification

8. Product Validation

9. Product Transition

10. Technical Planning

11. Requirements Management

12. Interface Management

13. Technical Risk Management

14. Configuration Management

15. Technical Data Management

16. Technical Assessment

17. Decision Analysis


Engineering Processes

Observed Data

Technical success relative to initial req.


Technical success relative to similar proj
Schedule relative to original project plan
Schedule relative to similar projects
Budget relative to original project plan
Budget relative to similar projects
Satisfaction with project management
Overall project success

Exhibit 8. Negative Correlations between Project Success Assessments and System Engineering Processes

Project Success and System


1. Stakeholder Expectations Definition

2. Technical Requirements Definition

3. Logical Decomposition

4. Design Solution

5. Product Implementation

6. Product Integration

7. Product Verification

8. Product Validation

9. Product Transition

10. Technical Planning

11. Requirements Management

12. Interface Management

13. Technical Risk Management

14. Configuration Management

15. Technical Data Management

16. Technical Assessment

17. Decision Analysis


Engineering Processes

Observed Data

Technical success relative to initial req.


Technical success relative to similar proj
Schedule relative to original project plan
Schedule relative to similar projects
Budget relative to original project plan
Budget relative to similar projects
Satisfaction with project management
Overall project success

6
Conclusions
This study was designed to explore the About the Authors
relationship between project success and system Paul J. Componation, Ph.D. is an Associate professor
engineering processes and was driven by the in the Industrial and Systems Engineering and
introduction of the new NASA NPR 7123.1 Systems Engineering Management Department at The
Engineering Processes and Requirements. If this new University of Alabama in Huntsville. He holds a
NPR would indeed improve project success then there doctorate and bachelor degree in industrial engineering
should be a relationship between the system from West Virginia University, and a masters degree
engineering processes identified in the NPR and in management from Troy State University. His
common measures of project success. research interests are in the development and
The research did show some correlations, however management of complex systems. Dr. Componation is
the correlations were not all to project technical an active member of the American Society for
success. Some correlations were found to be with Engineering Management (ASEM), the International
project schedule and budget success, as well as some Council on Systems Engineering (INCOSE), and a
correlations with overall project success. In addition, senior member of the Institute of Industrial Engineers
some system engineering measures did not show a (IIE).
positive, but rather a negative correlation with some
success measures implying that while there presence Alisha D. Youngblood, Ph.D. is an Assistant Professor
did not help support project success their absence in the Industrial and Systems Engineering and
would support failure in some success measures. Engineering Management Department at The
There were two limitations on this work which University of Alabama in Huntsville. She earned her
should be noted. The first was the relatively limited B.S., M.S, and Ph.D. in Industrial Engineering from the
number of projects that were reviewed. The thirteen University of Arkansas. Her research interests include
projects selected do present a reasonable sample of engineering management, performance measurement,
NASA projects, but more projects would be needed to economic decision analysis, and logistics. She is an
determine if the observations from this work were of active member of the American Society for
statistical significance. The second was the selection Engineering Management (ASEM) and the Institute of
process for the projects in the study. Since the Industrial Engineers (IIE) and.
objective of this work was to determine if the system
engineering processes noted in NASA NPR 7123.1 Dawn R. Utley, Ph.D., P.E., is an Associate Professor
were present in successful projects, only relatively in the Industrial and Systems Engineering and
successful projects were selected. If would be of Engineering Management Department at The
benefit to see if the processes were present or absent University of Alabama in Huntsville. Her research
in relatively unsuccessful projects. interests include the engineering management, the
This study has several ramifications for the motivation of the technical workforce, organization
engineering manager. First, the success of the project structure and team building, and organizational
was found to be influenced by the use of system metrics. She is an active member of the Institute of
engineering processes. The influences of those Industrial Engineers (IIE) and the American Society for
processes on success are varied and does not influence Engineering Management (ASEM).
all type of project success the same. Second, not all
system engineering processes have the same influence Phillip A. Farrington, Ph.D. is an Associate Professor
on project success, so tailoring of the processes should in the Department of Industrial and Systems
be considered based on the individual characteristics of Engineering and Engineering Management at The
the project being undertaken. University of Alabama in Huntsville. His research
interests are collaborative systems engineering,
References integrated product development, quality engineering,
NASA NPR 7123.1A NASA Procedural Requirements, and rapid simulation model development. He is an
NASA Systems Engineering Processes and active member of American Society of Engineering
Requirements, (2007). Management (ASEM), American Society of Quality
Control (ASQC), and the Institute of Industrial
NASA Systems Engineering Handbook. SP-610S
Engineers (IIE).
(1995).

You might also like