B. To assist in the further development of the remaining REP Parcels, REP plans to
construct and install a road on and through portions of the REP Parcels (the Roadway),
together with a retention pond serving the Roadway and possibly adjacent areas (the Retention
Pond) and certain other improvements and associated appurtenances (collectively, the
Project). The Roadway will be located on the south side of E. Michigan Avenue directly
across from Harrison Street.
C. The City believes that the development of the REP Parcels and surrounding area
will enhance property values and result in a demonstrable economic benefits for the City. In light
of the Citys desire for continued development and rehabilitation of the surrounding area, the
Parties agreed that the Roadway should meet the City standards for a public street. Accordingly,
the City agrees to reimburse REP for the Project Costs (as defined below).
1. Recitals. The above recitals are acknowledged as true and correct, and are
incorporated by reference into this paragraph.
23427890.3
Improvements) in the approximate locations as depicted on the Site Plan. REP shall at its
expense provide the City with 2 boundary surveys, one for the Roadway and one for the
Retention Pond. REP agrees to perform such work in accordance with the Citys relevant
construction standards and specifications for those Project Improvements; and under applicable
Federal, State or local laws, ordinances or regulations. Appropriate City employees will be
actively engaged with REP and its consultants during all phases of the Project Improvements.
a. The City has included in its 2017 City Budget, as amended, the funds
necessary to reimburse REP the Project Costs; those funds to be held in escrow by a title
company agreeable to the Parties under a separate escrow agreement the Parties will sign
within 20 days following the Parties execution of this Memorandum.
b. The Parties acknowledge that unforeseen costs and conditions may arise
during the construction of the Project Improvements that may result in costs beyond those
outlined in Exhibit C. The City will reimburse REP for those added costs to the extent
that the total Project Costs do not exceed $ 425,000.
c. Upon the dedication of the Retention Pond to the City, the City will grant
an easement to REP for drainage, to the extent drainage is required from REPs
development of land adjacent to the Retention Pond.
23427890.3
d. Considering a portion of the REP Parcels were within the original plat for
the Town (now City) of Kalamazoo, the Parties agree to cooperate in good faith to
complete any land division or boundary line adjustment as may be required under MCL
560.263.
5. Street Lighting. The Parties acknowledge and agree that REP shall not be
responsible for the construction or installation of any street lighting and related utility lines and
systems within the Proposed ROW. The City will contract directly with Consumers for the
construction and installation of such street lighting and utility lines and systems.
6. Parking. As part of the Foundry Project, the City will allow REP to utilize the
western portion of the Proposed ROW for parallel parking for the occupants, tenants and
customers of the businesses located in the Foundry Project in satisfaction of the parking space
requirements under the Citys Zoning Code. Therefore, those spaces will not have parking
meters, but the City may impose limits on length of time a vehicle may park in one of those
spaces. The parking of motor vehicles under this paragraph remains subject to the No Parking
requirement between 2:00 a.m. and 6:00 a.m. on any public street under 36-170 of the
Kalamazoo Code of Ordinances.
23427890.3
EXHIBIT A
Site Plan
23427890.3
EXHIBIT B
23427890.3
EXHIBIT C
Proposed Budget