REF: SB012/BLDK3D2/HYGC/WR05

CONSTRUCTION PROGRESS REPORT

PROJECT TITLE : CONSTRUCTION AND COMPLETION OF 1 UNIT OF WATCH TOWER AT K3D2, SIBU
CLIENT : BINTULU LUMBER DEVELOPMENT SDN BHD
CONTRACTOR : HY GENERAL CONTRACTOR
CONTRACT PERIOD : 16.02.2017 - 15.07.2017

WEEKLY REPORT
% Complete
NO SCOPE OF WORKS
Last Week 20/03-24/03/17
1 PILING 100% 100%
2 PILE CAP/FOOTING 100% 100%
3 GROUND BEAM 100% 100%
4 GROUND SLAB 100% 100%
5 FENCING + GATE 0% 0%
6 TRUSSES/BRACING 40% 40%
7 LADDER 0% 0%
8 ROOFING WORK 0% 0%
9 BOLT & NUT/PAINTING/WELDING WORK 10% 15%
10 LIGHTNING ARRESTER 0% 0%
OVERALL COMPLETION 45.0% 45.5%

PREPARED BY,

(WILLIAM TING)
PROJECT ENGINEER, KTS PD3 SIBU

Page 1 of 3
REF: SB012/BLDK3D2/HYGC/WR05

10 inches in between the welds. 10 inches in between the welds.

9 inches weld length. 9 inches in between the welds.

300mm weld length. 300mm weld length.

Page 2 of 3
REF: SB012/BLDK3D2/HYGC/WR05

Site Diary

1. Currently, HY contractor finished 1 side welding on the trusses. 15 sides yet to weld.

2. Contractor explained slow progress is due to weather. Welding process is prohibited during
raining.

3. Contractor will submit weather report and verify by PD3.

4. Contractor has followed the welding specification.

Page 3 of 3