Professional Documents
Culture Documents
B. Preliminary Works
1. Hoarding works
2. Preconstruction survey
3. Asbestos survey
4. Cable detection works
5. Environmental Control Programs
a. Vector control program
b. Dust, noise and vibration control program
C. Demolition Works
1. Asbestos removal
2. Stripping / Removal of projecting materials
3. Scaffolding works
4. Propping of slab soffit
5. Lifting plan
6. Physical Demolition works
7. Disposal of demolished materials
1. PROJECT DETAILS
2. LOCATION PLANS
Blk 110
Carpark
Blk 110
Blk 114
Blk 111
HE6 Carpark
1. Hoarding works
2. Preconstruction survey
3. Asbestos demolition survey
4. Cable detection works
5. Envronmental Control Programs
a. Vector control program
b. Dust, noise and vibration control program
B.1. HOARDING WORKS
8
B.1. HOARDING WORKS
Hoarding with covered walkway at
Henderson Road and opposite
hawker center
9
B.1. HOARDING WORKS
10
B.2. PRECONSTRUCTION SURVEY
LHS engaged Inquiro Consulting
Pte. Ltd. to do preconstruction
survey.
Pre-condition photographic
survey report initial report was
released on 07th June 2016
11
B.3. ASBESTOS DEMOLITION SURVEY
LHS engaged Cabo Environmental Pte. Ltd. who conducted
Asbestos demolition survey
12
B.4. CABLE DETECTION WORKS
Detection of under ground services are carried by
HH Tan Technical Services
All services in relation to the building must be
disconnected, prior to any commencement of
demolition works.
All disconnection must be notified and conducted to
the satisfactory of the relevant authorities.
The service detection works shall carried out by a
(LCDW) Licensed Cable Detection Worker and a record
is to be obtained.
Singtel, StarHub, Power Grid, Power Gas, PUB
13
B.5.a VECTOR CONTROL PROGRAM
LHS engaged Carefree Pest Management Pte Ltd. to do
pest control within the worksite.
Pest control strategies:
Weekly mosquito larvaciding by Carefree Pest Management
Weekly check for mosquito breeding and report to LHS for further
action
Bi-weekly mosquito fogging by Carefree Pest Management
Regular rats inspection and apply poison
Daily worksite housekeeping by LHS ECO worker
Daily larvaciding by LHS ECO worker
Regular ECO inspection and action by LHS Site Management Team
14
B.5.a. VECTOR CONTROL PROGRAM
1. Mosquito Control
15
B.5.a. VECTOR CONTROL PROGRAM
Carefree Pest Management Mosquito Control Rodent Control
16
B.5.b. DUST, NOISE & VIBRATION CONTROL
PROGRAM
Vibration monitoring will be done by Geo Scan Pte. Ltd.
Noise Monitoring
LHS to install Real-time
Noise monitoring
B.5.b. DUST, NOISE & VIBRATION CONTROL PROGRAM
DUST CONTROL
Continues water spraying during demolition.
External nets installed at the external scaffold
1. Asbestos removal
2. Stripping / Removal of projecting materials
3. Scaffolding works
4. Propping of slab soffit
5. Lifting plan
6. Physical Demolition works
7. Disposal of demolished materials
20
C.1. ASBESTOS REMOVAL WORKS
LHS will engage Pure Enviro Pte. Ltd. for the removal of Asbestos
Nature of Work
Decontamination & Removal of asbestos containing materials
Asbestos to be removed
Rubbish Hooper Lining - Chrysotile (un-broken) approx. 500 units
( Blocks 110 to 114)
21
Preparation for Asbestos Removal
A. Information shall be convey across the entire building: There shall not
be any unauthorized personnel working or movements near the removal
area during the period of Asbestos removal
B. All stakeholders to be informed of the schedule of work before start
work.
C. Apply permit to work for asbestos removal
D. PPE includes Half-face respirator with P100 filter cartridge, disposable
body suit, rubber gloves, shoe cover, safety goggles, safety helmet,
safety boots.
E. All workers must go through mask fit test before assigning of the correct
size of respirators for individual use.
F. All workers must go through medical checkup (X-ray) to determine if
they are fit for work. The X-ray test is to be conducted on a 2 year basis.
22
Enclosure of the entire work area with Hygiene facility & Air
Extraction Unit
A. All movable objects will be removed from site and all immovable
items will be covered completely with Polyethylene sheets.
B. The polyethylene sheets must be at least 0.2mm in thickness
and a double layer is recommended for enclosure at all openings
such as doors, windows, air vents etc.
C. Polyethylene sheets will be used to isolate all entrance & exits to
the working area and secured with strong adhesive tapes. The
existing building structures such as windows, wall, doors shall be
used as part of the enclosure set up.
D. There will be 2 hygiene units provided during demolition
E. Warning signs as per below will be displayed at all approaches to
the asbestos site:
23
Full barricade & Enclosure of the entire work site with Hygiene
facility & Air Extraction Unit
A. All movable objects will be removed from site and all immovable items will be
covered completely with Polyethylene sheets.
B. The polyethylene sheets must be at least 0.2mm in thickness and a double layer is
recommended for enclosure at all openings such as doors, windows, air vents etc.
C. Polyethylene sheets will be used to isolate all entrance & exits to the working area
and secured with strong adhesive tapes. The existing building structures such as
windows, wall, doors shall be used as part of the enclosure set up.
D. There will be 2 hygiene unit; 1 at the entrance to the kitchen area, another at the
entrance to each rubbish chute column at ground floor.
E. The toilet inside the kitchen will be sealed off completely
F. Smoke test will be conducted to detect any leakage and to take corrective actions at
areas where enclosure is not done properly.
G. Warning signs will be displayed at all approaches to the asbestos site:
ASBESTOS WORKING AREA
AUTHORISED PERSONNEL ONLY
DO NOT INHALE DUST
A. Installation of Air Extraction Unit: Not applicable for this job since the removal
involves breaking of concrete surrounding the asbestos lining. 24
Actual Photographs of Preparation Works
27
C.3. SCAFFOLDING WORKS
External scaffolding works will
be erected prior to demolition
works by Approved Scaffold
Contractor. The scaffolding will
serves as: REPLACE WITH ACTUAL PROJECT
PHOTO
1. Edge protection to prevent
falling from heights and
falling debris
2. To help to control dust thru
scaffold netting
28
C.3. SCAFFOLDING WORKS
Typical scaffolding
plan for Blocks
110,111 and 112
29
C.3. SCAFFOLDING
WORKS
31
C.4. PROPPING AND STRUCTURE SUPPORTS
35
C.5. LIFTING
PLAN
SH-200 Technical
Specifications
36
C.5. LIFTING
PLAN
SH-200 Technical
Specifications
37
C.6.
PHYSICAL
DEMOLITION
WORKS
38
C.6. PHYSICAL DEMOLITION WORKS
39
C.6. PHYSICAL DEMOLITION WORKS
Clearances letters / Emails From Service Providers
SP Telecom
Singtel
40
C.6. PHYSICAL DEMOLITION WORKS
Clearances letters / Emails From Service Providers
SP Power Gas
Starhub SCV
41
C.6. PHYSICAL DEMOLITION WORKS
Clearances letters / Emails From Service Providers
PUB-Drainage
LTA Relocation
of Lamp posts
42
C.6. PHYSICAL DEMOLITION WORKS
Clearances letters / Emails From Service Providers
SP Services- Cable
installation and Energise
Singtel
Payphone
43
C.6. PHYSICAL DEMOLITION WORKS
PUB- Abandonment of existing manhole
Netlink Trust-
Services
Decommissioning
46
C.6. PHYSICAL DEMOLITION WORKS
Step 3. Step 4.
Demolition of slab and beams walls, The crusher moves to next floor by steel ramp
columns
47
C.6. PHYSICAL DEMOLITION WORKS
Ramp Details
48
C.6. PHYSICAL
DEMOLITION
WORKS
Ramp Details
49
C.6. PHYSICAL DEMOLITION WORKS
Step 5. Step 6.
Continue demolition, follow sequence. Remove the external columns and beams
- Walls (non-structural) Then the process repeated down the floors
- Slabs
- Secondary beams
- Main beams
- Columns and structural walls
50
C.6. PHYSICAL DEMOLITION WORKS
Blocks 113
and 114
51
C.6. PHYSICAL DEMOLITION WORKS
52
C.6. PHYSICAL DEMOLITION WORKS
Blocks
110, 111
and 112
53
C.6. PHYSICAL DEMOLITION WORKS
Blocks 110,
111 and
112
54
C.6. PHYSICAL DEMOLITION WORKS
55
C.6. PHYSICAL DEMOLITION WORKS
56
C.6. PHYSICAL DEMOLITION WORKS
Debris disposal point to Blocks 110,111 and 112
Steel plates in the form of U-
Debris Disposal point shape (3.0m) will be installed
will be using the together with safety nets at
existing rubbish chute level 1
Rubbish bin
57
C.6. PHYSICAL DEMOLITION WORKS
Fall protection to all floor openings during demolition
Lift shaft and staircase wall will not be
demolished on the same demolition floor. The
existing wall will maintain to serve as fall
protection. Lift door area will be installed by G.I.
pipes (refer to section A-A)
A A
58
C.6. PHYSICAL DEMOLITION WORKS
SECTION A-A DETAILS OF FALL PROTECTION ON DEMOLITION FLOOR
Barricade to install at rubbish Excavator with crusher, SH-200
chute or any fall protection
Demolition floor
Staircase
Lift shaft
not be demolished on the same
demolition floor. The existing
wall will maintain to serve as fall
External
protection.
scaffold
External
scaffold
Lift door area will be installed by
G.I. pipes
Rubbish
Chute
59
C.6. PHYSICAL DEMOLITION WORKS
Traffic Management Plan and Control
60
C.6. PHYSICAL DEMOLITION WORKS
Traffic Management Plan and Control
Pedestrian strips with
warning of incoming
vehicles form the
worksite
Warning signages
Warning to slow
down by all
drivers due to
pedestrian Pedestrian strips
crossing in the
entrance of the
worksite
61
C.6. PHYSICAL DEMOLITION WORKS
Traffic Management Plan and Control
Entrance to STAGE 2
Entrance to STAGE 1
62
C.6. PHYSICAL DEMOLITION WORKS
STAGE 1 and 2 Traffic Management Plan and Control
Security
Post
Warning to
pedestrians on
moving vehicles
Warning to drivers to slow down
in and out
due to pedestrian crossing
Public Road
Warning to
pedestrians on
moving vehicles
in and out
63
PHYSICAL DEMOLITION PHOTOGRAPHS
Demolition of low rise building/ structure ( Block 113- 114)
65
DEMOLITION OF SUPER STRUCTURE
66
C.7. WASTE MANAGEMENT PLAN & DISPOSAL
67
C.7. WASTE MANAGEMENT PLAN & DISPOSAL
68
LEGEND: Estimat Actual Qty (ton)
Type of Propose
No ed Qty
A HARDCORE/BRICKS Waste
(ton) from to d Usage
Concrete
B STEEL 1 Debris RCA
(hardcore)
Site
Masonry
C TIMBER/PVC PLASTIC 2
(bricks)
hard
standing
Metal
D REFUSE 3 (reinforced
Recycle
Steel
steel)
Timber/Alu Disposal
RC RECYCLING CONCRETE 4
minium etc. (NEA)
A
AGGREGATE
TOTAL
WASTE
MANAGEMENT
PLAN
C.7. WASTE MANAGEMENT PLAN & DISPOSAL
DEBRIS AND WASTE HANDLING
71
D. BACKFILLING, GROUND LEVELLING & TURFING
WORKS
72
Surveying and pegging of pile points Excavation, Backfilling of soil leveling
Turfing works 73
E.
SAFETY, HEALTH AND
ENVIRONMENTAL
CONSIDERATIONS
74
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
75
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
Safety Target
Our Safety Target for the Proposed Project is ZERO ACCIDENT.
76
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
The Management & Staff of Leong Hin Seng Civil Engineering Pte Ltd is
committed to provide Total Customer Satisfaction, Safe and Healthful
workplace through the following corporate policies:
Compliance to regulatory and statutory requirements which the
company subscribes
Excellent quality services and products
OHS hazards and all possible accidents related to project works are
identified and controlled
Use processes that do not adversely affect the environment to
minimize waste, prevent air, water and other pollution, minimize health
and safety risks and dispose of waste safely and responsibly
Continual improvement by seeking new training for employees and
subcontractors.
77
TAN LIAN GUAN
9623 3055
Managing Director
ABDUL KADER
9729 6770
Site Supervisor
SAFETY MANAGEMENT
TEAM
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
79
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
Safety, Health and Environmental Training and Programs
80
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
81
E. SAFETY, HEALTH AND
ENVIRONMENTAL
CONSIDERATIONS
Incident Investigation
and Reporting
82
E. SAFETY, HEALTH AND
ENVIRONMENTAL
CONSIDERATIONS
Project Emergency Response
Plan was formulated on 30th
May 2016
83
Relevant Authorities Emergency
E. SAFETY, HEALTH AND Contact Numbers
ENVIRONMENTAL
CONSIDERATIONS
84
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
85
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
In-House Safety Rules & Regulations
LHS to strictly implement their own In-House Safety Rules &
Regulations
Will be highlighted during SIC
86
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
Maintenance Regimes
All machineries and equipment's on site will be regularly check
and maintain to ensure it is safe working condition
Maintenance checklist forms will be filled-up and submit to LHS
safety department
87
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
Control & Movement of Hazardous Materials
All chemicals that will bring to worksite will be controlled
All must submit SDS to LHS.
Training for safe handling and SDS of chemical must be done.
Emergency Preparedness
Emergency Response Plan (ERP) will be formulated and
prepared for the worksite.
Emergency drill will be conducted to ensure the effectiveness of
ERP.
During SIC, ERP will be highlighted to all participants
88
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
89
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
90
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
91
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
Legal Requirements
WSH (General Provisions) Regulations
WSH (Construction) Regulations
WSH (Risk Management) Regulations
WSH (Noise) Regulations 2011
WSH (Scaffold) Regulations 2011
WSH (Asbestos) Regulations 2014
Code of practice SS 557: 2010 and CP 11:2002
Others
HDB Standard Specifications for Demolition Works (2016 Edition)
HDB- Supplementary Specification for Demolition Works at Block 110 to 114
Bukit Merah View
92
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
Worksite Supervision
a) An experienced and competent Site Supervisors shall be appointed to
oversee all daily operations.
b. All Safety, Health and Environmental issues raised during demolition
works shall be carried out under the supervision of the experienced
WSH Site Supervisor and WSH Officer
93
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
a) The Professional Engineer (PE) shall carry out a site check for any
defects which may have weakened the structures. He / she shall
propose ways to support them if he/ she finds any weakened
structures
b) The Professional Engineer (PE) shall apply all necessary drawings
from the relevant authorities for the calculation/ design and
proposed demolition method to be submitted to BCA.
c) Regular inspection shall be carried out during demolition to ensure
that immediate rectification is performed on any weakened
structures
d) To issue COS upon after inspection of structures or any temporary
structures (e.g. scaffolding, proppings, hoarding, etc.) with PE
design
94
.
Covered walkway are provided if the building with clear space between
building line and lot boundary
95
.
96
.
DUST CONTROL
LHS to take measures to control dust emission from affecting the areas
outside the demolition work area. Such measures may include enclosing
the demolition work area by dust screens/netting installed within the
external scaffold. Use of water spray during demolition to reduce dust
emission.
97
.
98
.
99
D. BACKFILLING, GROUND LEVELLING & TURFING
WORKS
100
TAN LIAN GUAN
9623 3055
Managing Director
BIJU KN
9737 7350
Assistant Project Manager
ABDUL KADER
9729 6770
Site Supervisor
SAFETY MANAGEMENT
TEAM
Relevant Authorities Emergency
E. SAFETY, HEALTH AND Contact Numbers
ENVIRONMENTAL
CONSIDERATIONS
102
E. SAFETY, HEALTH AND ENVIRONMENTAL CONSIDERATIONS
103
THANK YOU